© Copyright 2011 Teys Lawyers www.teyslawyers.com.au Who’s Responsible for These Defects and How Do I Get Them to Pay? Webinar, 1 September 2011
Dec 07, 2014
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Who’s Responsible for These Defects and How Do I Get Them to Pay?
Webinar, 1 September 2011
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Seven Things You Need to Know About Building Defects
1 • Do you have home warranty insurance?
2 • When did the defect become apparent?
3 • Defects liability periods
4 • O H S issues
5 • Lot v common property
6 • Maintenance
7 • When should you get an expert?
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Sources of Defects
Workmanship (Builder / Subcontractor) • Either not building according to the design or good building prac]ce (BCA, Australian Standards or other industry standards)
Design (Engineer / Architect) • Has designer exercised reasonable skill, care and diligence
Combina]on of Workmanship &
Design
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Causes of Ac]on for OCs
1. Negligence • Possible defendants
– Builder / subcontractor – Designer (architect, engineer etc) – Developer (in limited
circumstances) – Principal cer]fying authority (PCA) – Strata manager – Building materials supplier
2. Statutory warran]es • Possible defendants
– Builder – Developer
3. Other
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Relevant Limita]on Periods
Negligence 6 years from the date the cause of
ac]on accrues (s.14 Limita]on Act)
Statutory Warran]es
7 years a_er the comple]on of the work (s.18E(1) HB
Act)
Building Ac]on
10 years a_er date on which the final
occupa]on cer]ficate is issued (s.109ZK(1) EPA Act)
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Jurisdic]on
1. Consumer Trader and Tenancy Tribunal (Home Building Division)
– Applica]ons up to $500k
– Applica]ons about insurance claims must be lodged within 10 years of comple]on
– Must fall within defini]on of ‘building claim’ in s.48A of Home Building Act
– Mandatory jurisdic]on for building claims
2. Supreme, District and Local Courts
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Case Study 1
OC of over 200 units
Significant water penetra]on issues
OC independently retained expert who described defect but not cause
Builder rejected content of report ci]ng ‘wind-‐driven’ rain as cause
OC wasted a year in the process
OC approached TEYS Lawyers for leier of demand
TEYS Lawyers advised need to determine defect (not describe it)
Consultant engaged and invited builder to observe tes]ng. Rec]fica]on work iden]fied and es]mated at >$5m
Builder conceded responsibility and agreed to rec]fy
Outcome achieved in 6 months – less than $10k in legal fees billed to date
Background Outcome
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Case Study 2
OC of over 100 units
Significant defects affec]ng many units (cost es]mate circa $10m)
Legal proceedings commenced by another law firm – claimed against HOW policy
Builder aiempted rec]fica]on, was unable and engaged lawyer to defend claim
OC spent a year in the process
OC approached TEYS Lawyers
Consultant engaged and invited builder to observe tes]ng. Rec]fica]on categorised as type and cause
Prototypes for rec]fica]on devised and agreed with builder
TEYS Lawyers discon]nued unnecessary proceedings. Deeds of seilement agreed with builder for rec]fica]on at his cost
On-‐going legal spend on li]ga]on reduced to $nil
Background Outcome
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Home Warranty Insurance
HWI Mark 1 1 May 1997 – 30 June 2002
HWI Mark 2 1 July 2002 – 30 December 2003
HWI Mark 3 31 December 2003 – Present
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Managing Legal Risk
Very Contractor / Builder
Friendly
Very Owner / Principal
Friendly
Master Builders Assoc Deacon 2 1998/2005
Australian Standards AS4905 2002
Royal Australian Ins]tute of Architects
CIC 1 1997
Australian Standards
AS 2124 -‐ 1981
Australian Standards AS 4300 – 1995
[D&C]
Australian Standards
AS 2124 -‐ 1986
Australian Standards AS400
1997
Australian Standards
AS 2124 -‐ 1992
Australian Standards AS 4902 [D&C]
Master Builders Assoc GCC 3 Circa
1980
ABIC MW-‐1 2003
Property Council PC1
1998
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Access Issues
• Access to Neighbouring Land Act 2000
• Conveyancing Act 1919 (s.88K and s.177)
• Deeds (indemni]es, security, insurance, OHS, etc)
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Issue a Payment Claim whenever a contractual entitlement to make a
progress claim arises, otherwise on the last day of the month
Failure to Issue a Payment Schedule within 10 days of Payment Claim (or less if contractually required)
2 days no]ce of inten]on to suspend
works before suspending
Payment Schedule Issued indica]ng Scheduled Amount which is approved for payment and providing reasons as to why
Scheduled Amount may be less than the Claimed Amount must be issued within 10 days of
Payment Claim (or less if contractually required)
Recover as a debt due in Court
NoMce of IntenMon to Apply For AdjudicaMon
giving further 5 days (2nd chance) to issue a Payment Schedule to be given within
20 days of expiry of due date for payment
Failure to Issue a Payment Schedule within 5 days of No]ce
AdjudicaMon ApplicaMon made within 10 days of
expiry of 5 day 2nd chance
Payment Schedule Issued within 5 days of No]ce
Schedule Amount
If less than Claimed Amount
For approved part of Claimed
Amount
AdjudicaMon ApplicaMon made to determine en]tlement to balance, within 10 days of receiving
Payment Schedule
Failure to Pay Scheduled Amount by the due date for payment under
the contract
2 days no]ce of inten]on to suspend
works before suspending
AdjudicaMon ApplicaMon made within 20 days of expiry
of due date for payment
Recover as a debt due in Court
Adjudicator Accepts Appointment within 4 Days of AdjudicaMon ApplicaMon Being Made (or failing acceptance, a new Adjudica]on Applica]on can be made within 5 days of expiry of the 4 day period for accep]ng first applica]on)
AdjudicaMon Response within 5 days a_er receiving Adjudica]on Applica]on, or 2 days a_er
receiving no]ce of Adjudicator’s acceptance, whichever ]me expires later
Adjudica]on Response not permiied
Adjudicator Determines Adjudicated Amount, due date for payment and applicable rate of interest within 10 days of accep]ng appointment to act as Adjudicator, unless the par]es agree to extend the ]me for determina]on
Failure to pay Adjudicated Amount
Request Adjudica]on Cer]ficate and give 2 days no]ce of inten]on to suspend works
File Adjudica]on Cer]ficate as judgment for unpaid amount in Court
Or
Or
Or
Or
PAYMEN
T PAYMEN
T PAYMEN
T PAYMEN
T PAYMEN
T PAYMEN
T Full payment is made prior to expiry of period in which a Payment Schedule can be issued
Payment within 5 days of determina]on unless later ]me determined by Adjudicator
Debt recovery process (including process set out in the Contractors Debts Act)
Claimant’s steps Respondent’s steps Adjudicator’s steps
References to days in this flowchart are references to business days. This flowchart demonstrates the payment mechanism set down by the Act and should not be construed as legal advice.
Building and Construc]on Industry Security of Payment Act 1999 (NSW)
Scheduled amount must be paid by the contractual due date for payment otherwise , within 10 business days of the Payment Claim
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
Join our next webinar
Join us for our next webinar at 4.00pm on 6 October 2011
‘How To Prevent Building Defect Li7ga7on Tearing Your OC Apart’
Reserve your seat now at: hips://www3.gotomee]ng.com/register/772441334
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au
About The Presenter
TEYS Lawyers prac]ce na]onally in strata ]tle law represen]ng owners corpora]ons, bodies corporate and apartment owners. The firm’s prac]ce groups include building defects, management rights, strata community disputes, by-‐laws and rules and levy and fee collec]on.
Subscribe for their free e-‐newsleier StrataSpace and find out more about them at www.teyslawyers.com.au
Chris worked for many years in leading commercial construc]on law prac]ces ac]ng for government, developers and contractors in disputes in the building, transport infrastructure and resources sectors. He has been involved in all forms of dispute resolu]on including li]ga]on, arbitra]on and alterna]ve dispute resolu]on in a range of jurisdic]ons in Australia. In the last few years, he has brought his specialist construc]on industry knowledge to the strata sector and now only acts for owners corpora]ons in a range of disputes in various jurisdic]ons.