Top Banner
© Copyright 2011 Teys Lawyers www.teyslawyers.com.au Who’s Responsible for These Defects and How Do I Get Them to Pay? Webinar, 1 September 2011
14

Whos responsible for these defects and how do i get them to pay 1 september 2011

Dec 07, 2014

Download

Economy & Finance

TEYS Lawyers

 
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Who’s  Responsible  for  These  Defects  and  How  Do  I  Get  Them  to  Pay?  

Webinar,  1  September  2011  

Page 2: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Seven  Things  You  Need  to  Know  About  Building  Defects  

1  • Do  you  have  home  warranty  insurance?  

2  • When  did  the  defect  become  apparent?  

3  • Defects  liability  periods  

4  • O  H  S  issues  

5  • Lot  v  common  property  

6  • Maintenance  

7  • When  should  you  get  an  expert?  

Page 3: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Sources  of  Defects  

Workmanship  (Builder  /  Subcontractor)  •  Either  not  building  according  to  the  design  or  good  building  prac]ce  (BCA,  Australian  Standards  or  other  industry  standards)    

Design  (Engineer  /  Architect)  • Has  designer  exercised  reasonable  skill,  care  and  diligence  

Combina]on  of  Workmanship  &  

Design  

Page 4: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Causes  of  Ac]on  for  OCs  

1.  Negligence  •  Possible  defendants  

–  Builder  /  subcontractor  –  Designer  (architect,  engineer  etc)  –  Developer  (in  limited  

circumstances)  –  Principal  cer]fying  authority  (PCA)  –  Strata  manager  –  Building  materials  supplier  

2.  Statutory  warran]es  •  Possible  defendants  

–  Builder  –  Developer  

3.  Other  

Page 5: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Relevant  Limita]on  Periods  

Negligence  6  years  from  the  date  the  cause  of  

ac]on  accrues  (s.14  Limita]on  Act)  

Statutory  Warran]es  

7  years  a_er  the  comple]on  of  the  work  (s.18E(1)  HB  

Act)  

Building  Ac]on  

10  years  a_er  date  on  which  the  final  

occupa]on  cer]ficate  is  issued  (s.109ZK(1)  EPA  Act)  

Page 6: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Jurisdic]on  

1.  Consumer  Trader  and  Tenancy  Tribunal  (Home  Building  Division)  

–  Applica]ons  up  to  $500k  

–  Applica]ons  about  insurance  claims  must  be  lodged  within  10  years  of  comple]on  

–  Must  fall  within  defini]on  of  ‘building  claim’  in  s.48A  of  Home  Building  Act  

–  Mandatory  jurisdic]on  for  building  claims  

2.  Supreme,  District  and  Local  Courts  

Page 7: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Case  Study  1  

OC  of  over  200  units  

Significant  water  penetra]on  issues  

OC  independently  retained  expert  who  described  defect  but  not  cause  

Builder  rejected  content  of  report  ci]ng  ‘wind-­‐driven’  rain  as  cause  

OC  wasted  a  year  in  the  process  

OC  approached  TEYS  Lawyers  for  leier  of  demand  

TEYS  Lawyers  advised  need  to  determine  defect  (not  describe  it)  

Consultant  engaged  and  invited  builder  to  observe  tes]ng.  Rec]fica]on  work  iden]fied  and  es]mated  at  >$5m  

Builder  conceded  responsibility  and  agreed  to  rec]fy  

Outcome  achieved  in  6  months  –  less  than  $10k  in  legal  fees  billed  to  date  

Background   Outcome  

Page 8: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Case  Study  2  

OC  of  over  100  units  

Significant  defects  affec]ng  many  units  (cost  es]mate  circa  $10m)  

Legal  proceedings  commenced  by  another  law  firm  –  claimed  against  HOW  policy  

Builder  aiempted  rec]fica]on,  was  unable  and  engaged  lawyer  to  defend  claim  

OC  spent  a  year  in  the  process  

OC  approached  TEYS  Lawyers  

Consultant  engaged  and  invited  builder  to  observe  tes]ng.  Rec]fica]on  categorised  as  type  and  cause  

Prototypes  for  rec]fica]on  devised  and  agreed  with  builder  

TEYS  Lawyers  discon]nued  unnecessary  proceedings.    Deeds  of  seilement  agreed  with  builder  for  rec]fica]on  at  his  cost  

On-­‐going  legal  spend  on  li]ga]on  reduced  to  $nil  

Background   Outcome  

Page 9: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Home  Warranty  Insurance  

HWI   Mark  1   1  May  1997  –  30  June  2002  

HWI   Mark  2   1  July  2002  –  30  December  2003  

HWI   Mark  3   31  December  2003  –  Present  

Page 10: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Managing  Legal  Risk  

Very    Contractor  /  Builder  

Friendly  

Very    Owner  /  Principal    

 Friendly  

Master  Builders  Assoc  Deacon  2  1998/2005  

Australian  Standards  AS4905  2002  

Royal  Australian  Ins]tute  of  Architects  

CIC  1  1997  

Australian  Standards                        

AS  2124  -­‐  1981  

Australian  Standards                  AS  4300  –  1995  

[D&C]  

Australian  Standards                  

AS  2124  -­‐  1986  

Australian  Standards  AS400  

1997  

Australian  Standards    

AS  2124  -­‐  1992  

Australian  Standards  AS  4902  [D&C]  

Master  Builders  Assoc  GCC  3  Circa  

1980  

ABIC  MW-­‐1  2003  

Property  Council  PC1  

1998  

Page 11: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Access  Issues  

•  Access  to  Neighbouring  Land  Act  2000  

•  Conveyancing  Act  1919  (s.88K  and  s.177)  

•  Deeds  (indemni]es,  security,  insurance,  OHS,  etc)  

Page 12: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Issue a Payment Claim whenever a contractual entitlement to make a

progress claim arises, otherwise on the last day of the month

Failure  to  Issue  a  Payment  Schedule  within  10  days  of  Payment  Claim    (or  less  if  contractually  required)  

2  days  no]ce  of  inten]on  to  suspend  

works  before  suspending  

Payment  Schedule  Issued  indica]ng  Scheduled  Amount  which  is  approved  for  payment  and  providing  reasons  as  to  why  

Scheduled  Amount  may  be  less  than  the  Claimed  Amount  must  be  issued  within  10  days  of  

Payment  Claim  (or  less  if  contractually  required)  

Recover  as  a  debt  due  in  Court  

NoMce  of  IntenMon  to  Apply  For  AdjudicaMon  

giving  further  5  days  (2nd  chance)  to  issue    a  Payment  Schedule  to  be  given  within  

 20  days  of  expiry  of  due  date  for  payment  

Failure  to  Issue    a  Payment  Schedule  within  5  days  of  No]ce  

AdjudicaMon  ApplicaMon  made  within  10  days  of  

expiry  of  5  day  2nd  chance  

Payment  Schedule  Issued  within  5  days  of  No]ce  

Schedule  Amount  

If  less  than  Claimed  Amount  

For  approved  part  of  Claimed  

Amount  

AdjudicaMon  ApplicaMon  made  to  determine  en]tlement  to  balance,  within  10  days  of  receiving  

Payment  Schedule  

Failure  to  Pay  Scheduled  Amount  by  the  due  date  for  payment  under    

the  contract  

2  days  no]ce  of  inten]on  to  suspend  

works  before  suspending  

AdjudicaMon  ApplicaMon  made  within  20  days  of  expiry  

of  due  date  for  payment  

Recover  as  a  debt  due  in  Court  

Adjudicator  Accepts  Appointment  within  4  Days  of  AdjudicaMon  ApplicaMon  Being  Made  (or  failing  acceptance,  a  new  Adjudica]on  Applica]on  can  be  made  within  5  days  of  expiry  of  the  4  day  period  for  accep]ng  first  applica]on)  

AdjudicaMon  Response  within  5  days  a_er  receiving  Adjudica]on  Applica]on,  or  2  days  a_er    

receiving  no]ce  of  Adjudicator’s  acceptance,  whichever  ]me  expires  later  

Adjudica]on  Response  not  permiied  

Adjudicator  Determines  Adjudicated  Amount,  due  date  for  payment  and  applicable  rate  of    interest  within  10  days  of  accep]ng  appointment  to  act  as  Adjudicator,  unless  the  par]es  agree  to  extend  the  ]me  for  determina]on  

Failure  to  pay  Adjudicated  Amount                    

Request  Adjudica]on  Cer]ficate  and  give  2  days  no]ce  of  inten]on  to  suspend  works  

File  Adjudica]on  Cer]ficate  as  judgment  for  unpaid  amount  in  Court  

Or  

Or  

Or  

Or  

PAYMEN

T                  PAYMEN

T                PAYMEN

T                PAYMEN

T            PAYMEN

T            PAYMEN

T            Full  payment  is  made  prior  to  expiry  of  period  in  which  a  Payment  Schedule  can  be  issued  

Payment  within  5  days  of  determina]on  unless  later  ]me  determined  by  Adjudicator  

Debt  recovery  process  (including  process  set    out  in  the  Contractors  Debts  Act)  

Claimant’s  steps  Respondent’s  steps   Adjudicator’s  steps  

References  to  days  in  this  flowchart  are  references  to  business  days.    This  flowchart  demonstrates  the  payment  mechanism  set  down  by  the  Act  and  should  not  be  construed  as  legal  advice.  

Building  and  Construc]on  Industry  Security  of  Payment  Act  1999  (NSW)  

Scheduled  amount  must  be  paid  by  the  contractual  due  date  for  payment  otherwise  ,  within  10  business  days  of  the  Payment  Claim  

Page 13: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

Join  our  next  webinar  

Join  us  for  our  next  webinar  at  4.00pm  on  6  October  2011  

‘How  To  Prevent  Building  Defect  Li7ga7on  Tearing  Your  OC  Apart’  

Reserve  your  seat  now  at:  hips://www3.gotomee]ng.com/register/772441334  

Page 14: Whos responsible for these defects and how do i get them to pay 1 september 2011

©  Copyright  2011  Teys  Lawyers                  www.teyslawyers.com.au  

About  The  Presenter  

TEYS   Lawyers   prac]ce   na]onally   in   strata   ]tle   law   represen]ng   owners   corpora]ons,  bodies   corporate   and   apartment  owners.     The  firm’s  prac]ce   groups   include  building  defects,  management  rights,  strata  community  disputes,  by-­‐laws  and  rules  and  levy  and  fee  collec]on.  

Subscribe   for   their   free   e-­‐newsleier   StrataSpace   and   find   out   more   about   them   at  www.teyslawyers.com.au  

Chris   worked   for   many   years   in   leading   commercial   construc]on  law  prac]ces  ac]ng  for  government,  developers  and  contractors  in  disputes   in   the   building,   transport   infrastructure   and   resources  sectors.   He   has   been   involved   in   all   forms   of   dispute   resolu]on  including  li]ga]on,  arbitra]on  and  alterna]ve  dispute  resolu]on  in  a   range   of   jurisdic]ons   in   Australia.   In   the   last   few   years,   he   has  brought  his  specialist  construc]on  industry  knowledge  to  the  strata  sector   and   now   only   acts   for   owners   corpora]ons   in   a   range   of  disputes  in  various  jurisdic]ons.