This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
1. Whos Responsible for These Defects and How Do I Get Them to
Pay? Webinar, 1 September 2011 Copyright 2011 Teys Lawyers
www.teyslawyers.com.au
2. Seven Things You Need to Know About Building Defects 1 2 3
Do you have home When did the defect Defects liability warranty
insurance? become apparent? periods 4 5 6 O H S issues Lot v common
Maintenance property 7 When should you get an expert? Copyright
2011 Teys Lawyers www.teyslawyers.com.au
3. Sources of Defects Workmanship Design (Engineer / (Builder /
Architect) Subcontractor) Has designer exercised Either not
building reasonable skill, care Combina]on of according to the
design and diligence Workmanship & or good building Design
prac]ce (BCA, Australian Standards or other industry standards)
Copyright 2011 Teys Lawyers www.teyslawyers.com.au
4. Causes of Ac]on for OCs 1. Negligence Possible defendants
Builder / subcontractor Designer (architect, engineer etc)
Developer (in limited circumstances) Principal cer]fying authority
(PCA) Strata manager Building materials supplier 2. Statutory
warran]es Possible defendants Builder Developer 3. Other Copyright
2011 Teys Lawyers www.teyslawyers.com.au
5. Relevant Limita]on Periods 6 years from the Negligence date
the cause of ac]on accrues (s.14 Limita]on Act) Statutory 7 years
a_er the comple]on of the Warran]es work (s.18E(1) HB Act) 10 years
a_er date Building on which the nal occupa]on Ac]on cer]cate is
issued (s.109ZK(1) EPA Act) Copyright 2011 Teys Lawyers
www.teyslawyers.com.au
6. Jurisdic]on 1. Consumer Trader and Tenancy Tribunal (Home
Building Division) Applica]ons up to $500k Applica]ons about
insurance claims must be lodged within 10 years of comple]on Must
fall within deni]on of building claim in s.48A of Home Building Act
Mandatory jurisdic]on for building claims 2. Supreme, District and
Local Courts Copyright 2011 Teys Lawyers
www.teyslawyers.com.au
7. Case Study 1 Background Outcome OC approached TEYS Lawyers
for OC of over 200 units leier of demand TEYS Lawyers advised need
to Signicant water penetra]on issues determine defect (not describe
it) Consultant engaged and invited OC independently retained expert
builder to observe tes]ng. who described defect but not cause
Rec]ca]on work iden]ed and es]mated at >$5m Builder rejected
content of report Builder conceded responsibility and ci]ng
wind-driven rain as cause agreed to rec]fy Outcome achieved in 6
months less OC wasted a year in the process than $10k in legal fees
billed to date Copyright 2011 Teys Lawyers
www.teyslawyers.com.au
8. Case Study 2 Background Outcome OC of over 100 units OC
approached TEYS Lawyers Consultant engaged and invited Signicant
defects aec]ng many builder to observe tes]ng. units (cost es]mate
circa $10m) Rec]ca]on categorised as type and cause Legal
proceedings commenced by Prototypes for rec]ca]on devised another
law rm claimed against and agreed with builder HOW policy TEYS
Lawyers discon]nued Builder aiempted rec]ca]on, unnecessary
proceedings. Deeds of was unable and engaged lawyer to seilement
agreed with builder for defend claim rec]ca]on at his cost On-going
legal spend on li]ga]on OC spent a year in the process reduced to
$nil Copyright 2011 Teys Lawyers www.teyslawyers.com.au
9. Home Warranty Insurance HWI Mark 1 1 May 1997 30 June 2002
HWI Mark 2 1 July 2002 30 December 2003 HWI Mark 3 31 December 2003
Present Copyright 2011 Teys Lawyers www.teyslawyers.com.au
10. Managing Legal Risk Master Builders Royal Australian Assoc
GCC 3 Circa Ins]tute of Architects 1980 CIC 1 1997 Master Builders
Australian Australian Standards Australian Property Assoc Deacon 2
Australian Standards Standards AS AS 4300 1995 Standards Council
PC1 1998/2005 AS4905 2002 4902 [D&C] [D&C] AS 2124 - 1981
1998 Very Very Contractor / Builder Owner / Principal Friendly
Friendly Australian Australian Australian ABIC MW-1 Standards AS400
Standards Standards 2003 1997 AS 2124 - 1992 AS 2124 - 1986
Copyright 2011 Teys Lawyers www.teyslawyers.com.au
11. Access Issues Access to Neighbouring Land Act 2000
Conveyancing Act 1919 (s.88K and s.177) Deeds (indemni]es,
security, insurance, OHS, etc) Copyright 2011 Teys Lawyers
www.teyslawyers.com.au
12. Building and Construc]on Industry Security of Payment Act
1999 (NSW) Issue a Payment Claim Full payment is made prior to
expiry of period in which a Payment Schedule can be issued whenever
a contractual entitlement to make a progress claim arises,
otherwise on the last day of the month PAYMENT PAYMENT PAYMENT
PAYMENT PAYMENT PAYMENT 2 days no]ce of Failure to Issue a Payment
Schedule Payment Schedule Issued Respondents steps Claimants steps
Adjudicators steps inten]on to suspend within 10 days of Payment
Claim indica]ng Scheduled Amount which is approved works before
suspending (or less if contractually required) Or for payment and
providing reasons as to why References to days in this owchart are
references to business days. Scheduled Amount may be less than the
Claimed This owchart demonstrates the payment mechanism set down by
the Act Amount must be issued within 10 days of and should not be
construed as legal advice. Payment Claim (or less if contractually
required) NoMce of IntenMon to Apply Recover as a debt For
AdjudicaMon due in Court Or giving further 5 days (2nd chance) to
issue a Payment Schedule to be given within 20 days of expiry of
due date for payment Scheduled amount must be paid by the
contractual due date for payment otherwise , within 10 business
days of the Payment Claim Schedule Amount Failure to Issue Payment
Schedule Issued Failure to Pay Scheduled Amount 2 days no]ce of
within 5 days of No]ce If less than For approved inten]on to
suspend a Payment Schedule Or by the due date for payment under
Claimed Amount part of Claimed within 5 days of No]ce the contract
works before suspending Amount AdjudicaMon ApplicaMon AdjudicaMon
ApplicaMon made within 10 days of made to determine en]tlement to
AdjudicaMon ApplicaMon Recover as a debt expiry of 5 day 2nd chance
balance, within 10 days of receiving made within 20 days of expiry
due in Court Payment Schedule of due date for payment Or
Adjudicator Accepts Appointment within 4 Days of AdjudicaMon
ApplicaMon Being Made (or failing acceptance, a new Adjudica]on
Applica]on can be made within 5 days of expiry of the 4 day period
for accep]ng rst applica]on) Adjudica]on Response AdjudicaMon
Response not permiied within 5 days a_er receiving Adjudica]on
Applica]on, or 2 days a_er receiving no]ce of Adjudicators
acceptance, whichever ]me expires later Payment within 5 days of
determina]on unless later ]me determined by Adjudicator Adjudicator
Determines Adjudicated Amount, due date for payment and applicable
rate of interest within 10 days of accep]ng appointment to act as
Adjudicator, unless the par]es agree to extend the ]me for
determina]on Failure to pay Adjudicated Amount Debt recovery
process (including process set File Adjudica]on Cer]cate as out in
the Contractors Debts Act) Request Adjudica]on Cer]cate and give 2
days no]ce of inten]on to suspend works judgment for unpaid amount
in Court Copyright 2011 Teys Lawyers www.teyslawyers.com.au
13. Join our next webinar Join us for our next webinar at
4.00pm on 6 October 2011 How To Prevent Building Defect Li7ga7on
Tearing Your OC Apart Reserve your seat now at:
hips://www3.gotomee]ng.com/register/772441334 Copyright 2011 Teys
Lawyers www.teyslawyers.com.au
14. About The Presenter Chris worked for many years in leading
commercial construc]on law prac]ces ac]ng for government,
developers and contractors in disputes in the building, transport
infrastructure and resources sectors. He has been involved in all
forms of dispute resolu]on including li]ga]on, arbitra]on and
alterna]ve dispute resolu]on in a range of jurisdic]ons in
Australia. In the last few years, he has brought his specialist
construc]on industry knowledge to the strata sector and now only
acts for owners corpora]ons in a range of disputes in various
jurisdic]ons. TEYS Lawyers prac]ce na]onally in strata ]tle law
represen]ng owners corpora]ons, bodies corporate and apartment
owners. The rms prac]ce groups include building defects, management
rights, strata community disputes, by-laws and rules and levy and
fee collec]on. Subscribe for their free e-newsleier StrataSpace and
nd out more about them at www.teyslawyers.com.au Copyright 2011
Teys Lawyers www.teyslawyers.com.au