What’s so Progressive about Progressive Design-Build? Mark Alpert, PE, DBIA CH2MHill & Peter Tunnicliffe, PE, DBIA CDM
22

What’s so Progressive about Progressive Design-Build?

Jan 24, 2022

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: What’s so Progressive about Progressive Design-Build?

What’s so Progressive about

Progressive Design-Build?

Mark Alpert, PE, DBIA

CH2MHill &

Peter Tunnicliffe, PE, DBIA

CDM

Page 2: What’s so Progressive about Progressive Design-Build?

Progressive design-build:

A better way?

Discussion topics:– What is progressive design-build? How does it work?

– Investment in projects, not procurements

– Schedule advantages

– Managing project risk as a team

– Owner Questions to Facilitate Choice of alternate delivery

– Top ten success strategies for owners

Page 3: What’s so Progressive about Progressive Design-Build?

Project delivery options

Design-Bid-Build

(DBB)

Construction

Management at Risk

(CMAR)

Lump-Sum

Design-Build

(LS)

“Progressive”

Design-Build

(GMP)

Design-Build-

Operate/

Finance, etc.

Traditional

DeliveryAlternative Delivery

Page 4: What’s so Progressive about Progressive Design-Build?

Distinguishing design-build

delivery optionsLump-sum

design-build

(LS)

“Progressive”

design-build

(GMP)True single contract design-build models

offer owners a wide variety of evaluation

options, ranging from qualifications-

focused to “best value” with a lump-sum

price

Progressive design-build:

Maximum flexibility for owners

Lump-sum design-build:

“Performance-based”

or

“Prescriptive”

Page 5: What’s so Progressive about Progressive Design-Build?

Design-build nomenclature

Quasi Design-Build:

Multiple Entities

• Design plus CMAR

(different engineer

and CMAR firm)

• Design plus Early

Contractor Action

• Design plus GCCM

• Integrated Delivery

Design-Build:

One Entity

• Progressive DB

• EPCM (Engineer,

Procure,Construction)

• Design-CMAR (same

firm)

• Lump Sum Design Build

Page 6: What’s so Progressive about Progressive Design-Build?

Progressive design-build:

A better way?

“Progressive”

Design-Build

(GMP)Key Advantages

• Investment in projects, not procurements

• Schedule

• Progressive estimates address owners’ challenges

• Better opportunities for local subcontracting

• Capital budget management

Page 7: What’s so Progressive about Progressive Design-Build?

Pros and cons of

progressive design-build

• Construction cost is not known at

the time of initial contract signing

• Cost determined through

negotiated and competitive

processes

• May need public education

campaign

• Simple, inexpensive, quick

procurement process

• Potential for increased participation

• Flexibility to complete work based

on funding

• Owner can reject lump sum or

GMP without significant project

delays

• Better chance of designing to

budget

Advantages to Owner Disadvantages to Owner

Page 8: What’s so Progressive about Progressive Design-Build?

“Progressive” design-build

procurement model• “Progressive” model complies with most state design-build statutes as long as some

form of “price/cost-related” criteria is included in selection

• Offers owners maximum flexibility/opportunity to collaborate on permitting/ design

• Owners have an “off-ramp” in case of permitting issues or if GMP can’t be negotiated

• Very successful evolving model

Construction, Startup

(Verify) O&M

Warranty

Verify DB Performance

Inspection

Complete Design

Permits/Design Input

Verify GMP

Design/Develop GMP

Agree on GMP - based on

collaborative scope and

design; pricing may be

verified by third party

Quals

Define Performance Criteria

Plan Project

RFQ – defines qualifications

criteria; short lists qualified

firms

RFQ

Tech Support

Select from qualified firms

- selection based on

qualifications; may include “rates”

or “conceptual/ target price” in

evaluation

RFP

Propose Concept

LC

Page 9: What’s so Progressive about Progressive Design-Build?

Progressive DB can reduce

project complexity and cost . . . • Owner’s staff time and additional technical support for procurement

• Stipends for multiple unsuccessful proposers

• Industry investment in design for proposal

• Additional risk included in ultimate project cost (more unknowns = higher contingency)

Verify Design

Complete Deign, Construction, Startup

O&M

Warranty

Verify DB Performance

InspectionPerformance Criteria/Permits/Technical Support

Quals

Plan Project RFQ RFP

Design/Price for Proposal

Lump Sum DB (LS)

Construction, Startup

O&M

Warranty

Verify DB Performance

Inspection

Complete Design

Permits/Design Input

Verify GMP

Design/Develop GMPQuals

Define Performance Criteria

Plan Project RFQ

Tech Support

RFP

Propose Concept

Progressive DB (GMP)

$$

LC

$$$$$$+$$$$$$+

Page 10: What’s so Progressive about Progressive Design-Build?

. . . And shorten the

procurement schedule• Timing: Can procurement process start before all basis of permits are certain?

• Duration: Does proposal period need to allow time for design/detailed pricing?

• Potential for delay: How many issues/technical questions might arise?

Verify Design

Complete Deign, Construction, Startup

O&M

Warranty

Verify DB Performance

InspectionPerformance Criteria/Permits/Technical Support

Quals

Plan Project RFQ RFP

Design/Price for Proposal

Lump-Sum DB (LS)

Construction, Startup

O&M

Warranty

Verify DB Performance

Inspection

Complete Design

Permits/Design Input

Verify GMP

Design/Develop GMPQuals

Define Performance Criteria

Plan Project RFQ

Tech Support

RFP

Propose Concept

Progressive DB (GMP)

MonthsMonths

LC

Years+Years+

Page 11: What’s so Progressive about Progressive Design-Build?

Schedule comparison:

Typical vs. fast-tracked procurement

RFQ Response Period Evaluate Qualifications RFP Response Period Evaluate Proposals Contract

Issue RFQ SOQs Submitted Issue Shortlist Submit Proposals Award NTP

RFQ: 30 days Shortlist: 30 days RFP: 60 days Evaluate: 30 days Contract: 30+ days

3-4

RFQ Response Evaluate RFP Response Evaluate Contract

Issue RFQ SOQs Submitted Issue Shortlist Submit Proposals Award NTP

RFQ: 15 daysShortlist: 15 days

RFP: 30 daysEvaluate: 15 days

Contract: 30+ days

Typical Progressive Design-Build Procurement

Fast-Tracked Progressive Design-Build Procurement

3-4months

6 months

Page 12: What’s so Progressive about Progressive Design-Build?

Lump-sum procurements can drag out

Project Definition and Planning

Conceptual or Preliminary Design

RFQ Response Period

Environmental Process

Evaluate Qualifications

Prepare RFP Documents

RFP Response Period

Answer Questions/Issue Amendments

Issue RFQ SOQs Submitted Issue Shortlist Proposals Submitted

Prepare RFQ

Pre-proposal Conference

RFQ: 30-60 days Shortlist: 60 days RFP: 60-90 days

Evaluate Proposals BAFO Response Period Evaluate Final Proposals Contract Negotiations/Conformance

Request Clarifications/Responses

Notice of Award NTP

Evaluation: 60-90 days Interview: 30 days

Selection: 30 days Contract: 30-60 days

Final Submittal

Lump Sum Design-Build Procurements1+ years

Page 13: What’s so Progressive about Progressive Design-Build?

“Progressive” estimates keep owners informed and support-informed scope adjustment decisions

Guaranteed maximum price established at the right time: Risk and contingency reduced, schedule needs met

Progressive estimates

address owners’ challenges

0% 100%30%15%

Construction estimating can start very early in design, allowing comparison of specific technical solutions

First fully detailed estimate can be used to establish a scope baseline. Estimating process is “open book”

60%

Owners can use third-parties to verify cost . . . . . . and go to the hard bid market if needed (the “off

Owners can use third-parties to verify cost . . . . . . and go to the hard-bid market if needed (the “off-ramp”)

Level of Design Completion

Page 14: What’s so Progressive about Progressive Design-Build?

Progressive design-build supports regional firms

• Selection methodology focuses on traditional evaluation criteria

– Primarily qualifications based

– Can be tailored to support local expertise/capabilities

• Proposal preparation significantly less costly

– Limited design effort to be performed “on spec”

– Regional firms can support larger teams with minimal proposal investment

• More flexibility to use regional subs after design-builder selection

– Owner can provide input on preferred specialty firms

– Design packages can be developed after the procurement

• Does not require as much at-risk capability

– Subs can participate without taking an at-risk position

Page 15: What’s so Progressive about Progressive Design-Build?

Risks managed

• Permitting

• Land Acquisition and Easements

• Geotechnical & Utility risk

• Materials and Equipment escalation

• Capital Cost Availability

Page 16: What’s so Progressive about Progressive Design-Build?

Owner interaction benefits

• Work with one designer – do it once, right

• Allows direct input from Owner

Departments

• Cost analysis of options available as

project progresses

• Land acquisition challenges tackled as a

team

• Scope adjustments resulting from capital

constraints

Page 17: What’s so Progressive about Progressive Design-Build?

Owner questions to facilitate

choice of alternate delivery• Is capital availability uncertain?

• Do staff desire to participate in scope

advancement?

• Does project schedule have limited time

(less than 9 months) to develop the

procurement and enter into contract?

• Will permitting requirements likely impact

the scope of the project?

Page 18: What’s so Progressive about Progressive Design-Build?

Owner questions to facilitate

choice of alternate delivery (cont’d)

• Will land acquisition likely impact the

alignment or orientation of project?

• Does schedule dictate initiation of key

project activities before all capital funding

available?

• Do state statutes allow use of alternate

delivery?

Page 19: What’s so Progressive about Progressive Design-Build?

Top ten success strategies for owners1. Choose the qualified people you want to work with

2. Consider the approach presented by the potential design-

builder

3. Establish a decision-making process for the project to

promote rapid decision-making

4. Involve key stakeholders early in design process (e.g.:

operations staff)

5. Senior Management (designer-builder and owner)to meet

regularly to review project status and issues

Page 20: What’s so Progressive about Progressive Design-Build?

Top ten success strategies for owners

6. Jointly address permitting issues, track them, and press

agencies for action

7. Manage land acquisition as early as possible, including

in particular construction easements

8. Communicate capital availability and constraints so they

can be integrated into execution plan

9. Incent the project results you wish to accomplish

10.Celebrate interim success milestones

Page 21: What’s so Progressive about Progressive Design-Build?

Help is available to owners!

www.waterdesignbuild.org

Page 22: What’s so Progressive about Progressive Design-Build?

What’s so progressive about

Progressive Design Build?

Mark Alpert, PE, DBIA

&

Peter Tunnicliffe, PE, DBIA