PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Best Practice Proceduresin the transition fromin the transition from
Construction to Commissioning
Deniz Metin KayaDirector of Construction OperationsFoster Wheler Italiana
Why transition from Construction to Commissioning is soWhy transition from Construction to Commissioning is so important?
• Safety environment is complex and difficult to manage
• Tight schedule: margins are usually eaten up by upstream project phases and little float to cope with unexpected events
• Major over-laps between various activities
• Number of participants are quite high compared to other project phases
• Stakeholders’ priorities sometimes conflict with each others
• Require very skilled and experienced personnel
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
What is Mechanical Completion ?What is Mechanical Completion ?
• Construction is completed in accordance with drawings, specifications, vendor instructions, applicable codes and regulations and authority requirements
• All inspection, checking and testing works are completed
• System(s) and/or facilities are ready for pre commissioning and commissioning• System(s) and/or facilities are ready for pre-commissioning and commissioning
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
What is Pre-Commissioning andWhat is Pre Commissioning and Commissioning?
• Non-operating adjustment adjustments and cold alignment checks (such as cleaning, drying and testing without introducing process and auxiliary fluids prior to equipment energization )
• Pre-startup, check-out, system adjustment, equipment and system activation activities to prepare system(s) and/or facilities for operation (by introducing auxiliary fluids and with equipment energization)
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Completion & Turnover Map
Project Completion Data Base
Completion & Turnover Map
j p
E Area Driven Construction
System Completion
System Completion
Group of Systems Completion
ReaSE
ngineering
Construction
System Completion
System Completion Group of Systems
ady for PlaStart-up
g
Area Driven ConstructionSystem Completion
yCompletion
ant
f i i d Perform (pre)Preparation
& Data Validation
Measure construction progress Perform inspection and
test requirement
Measure progress.
Perform (pre) commissioning
inspection and test.
Measure progress.
Punch-Out &
Acceptance
Punch-Out &Acceptance
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Road Map for MC by Systems and
Pre-Commissioning
Road Map for MC by Systems and Handover to Commissioning
Test Punch i TOD
MC
ConstructionPre Commissioning Commissioning
TOS Initial Final
Walkdown Check-out Pack List TODList Walkdown Punch List Testing
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Construction Completion MilestonesConstruction Completion Milestones• TOS Self-contained portion of a facility/system for hand over
(Turn Over System)
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Construction Completion MilestonesConstruction Completion Milestones• TOS Self-contained portion of a facility/system for hand over
• Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Construction Completion MilestonesConstruction Completion Milestones• TOS Self-contained portion of a facility/system for hand over
• Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes
• Punch List Formal inspection and identification of remaining outstanding works
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Construction Completion MilestonesConstruction Completion Milestones• TOS Self-contained portion of a facility/system for hand over
• Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes
• Punch List Formal inspection and identification of remaining outstanding works
• Initial Walkdown Identification and closure of all category “A” punch items
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Construction Completion MilestonesConstruction Completion Milestones• TOS Self-contained portion of a facility/system for hand over
• Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes
• Punch List Formal inspection and identification of remaining outstanding works
• Initial Walkdown Identification and closure of all category “A” punch items
• Final Walkdown Demonstration and acceptance of a pre-checked system for hand over & Punch List
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Construction Completion MilestonesConstruction Completion Milestones• TOS Self-contained portion of a facility/system for hand over
• Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes
P h Li t F l i ti d id tifi ti f i i t t di k• Punch List Formal inspection and identification of remaining outstanding works
• Initial Walkdown Identification and closure of all category “A” punch items
• Final Walkdown Demonstration and acceptance of a pre-checked system for hand over & Punch List
• TOD Final dossier including all applicable as-built engineering documents and (Turn Over Dossier) construction certificates as per Inspection & Test Plan attesting the
Construction Completion MilestonesConstruction Completion Milestones• TOS Self-contained portion of a facility/system for hand over
• Test Package Set of documentation demonstrating the MC of a system or its subsystems or sections that can be isolated for test purposes
• Punch List Formal inspection and identification of remaining outstanding works
• Initial Walkdown Identification and closure of all category “A” punch items
• Final Walkdown Demonstration and acceptance of a pre-checked system for hand over & Punch List
• TOD Final dossier including all applicable as-built engineering documents and construction certificates as per ITP attesting the readiness for turn over
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Breakdown of Systems
System
Breakdown of Systems
y
Process
Systems
Standard
SystemsSystems Systems
Sub-Systems Sub-Systems
Disciplines Disciplines
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Typical TOS List
BLACK UTILITIES TOS LISTSYSTEM SYSTEM NUMBER
RUNNING DESCTRIPTION TOS SUBSYSTEM TOS DESCRIPTION AREA
05.41‐BS10/8/3 010 BLACK STEAM
TOS‐05.41‐BS10‐001 BLACK STEAM 10 BAR BASEMENT BASEMENT
TOS‐05.41‐BS8‐001 BLACK STEAM 8 BAR DISTR. BASEMENT BASEMENT
TOS‐05.41‐BS3‐001 BLACK STEAM 3 BAR DISTR. BASEMENT BASEMENT
TOS‐05.41‐BS3‐002 BLACK STEAM 3 BAR DISTR. BULK 1 BULK 1
TOS‐05.41‐BS3‐003 BLACK STEAM 3 BAR DISTR. BULK 2 BULK 2
TOS‐05.41‐BS3‐004 BLACK STEAM 3 BAR DISTR. STERILE FILTRATION STERILE FILTRATION
TOS‐05.41‐BS3‐005 BLACK STEAM 3 BAR DISTR. CASA CASA
05.41-BSC10/8/3 011 CONDENSATE
TOS‐05.41‐BSC10‐001 CONDENSATE 10 BAR BASEMENT BASEMENT
TOS‐05.41‐BSC8‐001 CONDENSATE 8 BAR BASEMENT BASEMENT
TOS‐05.41‐BSC3‐001 CONDENSATE 3 BAR BASEMENT BASEMENT
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Turnover Vision
SystemSystem Acceptance C tifi t
Turnover Vision
S b
Certificate
Sub System
Data BaseINPUT OUTPUT System Ready for Pre-Commissioning
Disciplines
TAGsMechanical Completion Certificate
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Data Flow & InterfacesData Flow & Interfaces
Data Base
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Engineering TAG ListCommissioning Systems Construction Areas
OverviewEngineering TAG List
Unit
Group of Systems
G f S t
Plant Area
Constr Area
Commissioning Systems Construction Areas
Group of Systems
System
System
Constr Area
Select Quality Pack Type Select Quality Steps
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 201228
Select Quality Pack Type Select Quality Steps
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION
Recommendations
• All stakeholders must be continuously kept up-to-date with the safety requirements of changing site conditions
Recommendations
site conditions
• Phased system-wise completion and turnover scheme requires very efficient planning and schedulingscheduling
• The achievement of highest coordination standards between construction and commissioning teams is essential
• Construction contracts need to be structured with focus and incentives on system turn over and completion p
• The administration of voluminous turnover documentation necessitate the implementation of a structured and tag oriented approach and application of software tools
THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUMMilan. Italy, Ooctober 12, 2012