Mr. Nitin Kumar Rohilla AGM (IT – SAP) NDPL 23rd July 2009 SAP Implementation & Functioning – NDPL Experience
42

Track 3 6 Nitin Rohilla NDPL

Apr 13, 2015

Download

Documents

srilu12
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Track 3 6 Nitin Rohilla NDPL

Mr. Nitin Kumar RohillaAGM (IT – SAP)NDPL

23rd July 2009

SAP Implementation & Functioning –NDPL Experience

Page 2: Track 3 6 Nitin Rohilla NDPL

Group Chairman’s Quote…

Page 3: Track 3 6 Nitin Rohilla NDPL

Company Profile

North Delhi Power Limited (NDPL), the power distribution arm of Tata Power serves a populaceof 50 lakh inhabiting North and North West Delhi.

It is a joint venture between Tata Power Company and the Government of NCT of Delhi with themajority stake being held by the Tata Group.

The company started operations on July 1, 2002 post the unbundling of erstwhile Delhi VidyutBoard. With a registered consumer base of around 9 lakh and a peak load of around 1100 MW,the company's operations span across an area of 510 sq kms.

NDPL has been the frontrunner in implementing power distribution reforms in the capital cityand is acknowledged for its consumer friendly practices. Since privatization, the AT&C losses inNDPL areas have shown a record decline. On the power supply front too, NDPL areas haveshown remarkable improvement.

NDPL has to its credit several firsts in Delhi: SCADA controlled Grid Stations, Automatic MeterReading, GSM based Street Lighting system, SMS based Fault Management System. To ensurecomplete transparency, the company has provided online information on billing and payment toall consumers. This happened in the first year of operations itself.

NDPL believes in providing more value than just electricity and is even rewarding its consumersfor timely payment.

NDPL is the youngest company and the first power utility in India to receive the prestigious CIIEXIM Award for 'Strong Commitment to Excel'.

It is also the only distribution utility to receive the ISO 9001, ISO 14001 and OHSAS 18001certification.

NDPL has been recommended for ISO 27001 certification.

Page 4: Track 3 6 Nitin Rohilla NDPL

4

Generation

Power Sourcing

Transmission

TRANSCO – 220/66 kV GridStation (G/Stn.)

XpresssConsumer

NDPL –66/11 kV G/Stn.

NDPL –11kV/ 220V DT

CGHS(HCB Consumers)

NDPL –66/11 kV G/Stn.66/33 kV G/Stn.

HRB / HCBConsumers

NDPL –11kV/ 220 V11kV/ 440 V

DT

KCGConsumer

NDPL –11kV / 440V DT

HVDS Network11 kV / 440 / 220

V

NDPL –33/11 kV G/Stn.

NDPL – 11kV/ 220 VDistribution Transformer

JJ Clusters -LT ABC Network

Distribution

HRB / HCBConsumers

OUR BUSINESS: Carriage & ContentPower To The People…

24 X 7 Service Delivery

Politically Sensitive

Theft Prone

Privatization acting as a barrier to the “Free Lunch”

Page 5: Track 3 6 Nitin Rohilla NDPL

Geographic Description

BSESRajdhani MES

NDMC

BSESYamuna

NDPL

Page 6: Track 3 6 Nitin Rohilla NDPL

Power Distribution

Page 7: Track 3 6 Nitin Rohilla NDPL

Govt. loan of Rs 552 Crores prepaid 9 years ahead of schedule

Dividends being paid from FY 05-06: 10% (in FY 05-06), 16% (in FY 06-07), 18% in 07-08; Bonus in 07-08In 2002, Power Theft / AT&C Loss was about Rs 4 Crores per day in NDPL area- Now it is about 1 Cr./day

Increase in NDPL paying capacity reduced Transco’s dependence on Govt. to NILDomestic Tariff continues to be same since July 2004

CumulativeSavings intune of Rs.4187 Cr.

Reduction in AT&C Losses

Page 8: Track 3 6 Nitin Rohilla NDPL

Power Distribution – Key Functional Areas

Page 9: Track 3 6 Nitin Rohilla NDPL

IT’ s role in Distribution

Page 10: Track 3 6 Nitin Rohilla NDPL

Why ERP

Complete integration of systems across the departments in a Company aswell as across the Enterprise as a whole

Only solution for better Project Management

Better customer service

Automatic introduction of latest technologies

Expertise database

Page 11: Track 3 6 Nitin Rohilla NDPL

Problems tackled by ERP Systems

Systematic look into your systems & procedures

Optimizing the processes

Enables you to adapt yourself to new technologies & makes availabletimely information

Discipline across the functions

Page 12: Track 3 6 Nitin Rohilla NDPL

Why SAP?

Lack of functionalities in existing software & High lead times & Cost forcustomization

Need to adapt best practices

More standardized solution with 3-tier architecture, more robust and withfaster response times with large number of users (users increasedphenomenally)

New initiatives requiring automation & integration e.g., BSC, SCADA, GIS etc.

Need for an application for managing Planned/ un-planned maintenance andbreakdowns

Need for improved application / control for Asset Management

Projects capitalization was a major challenge

Need for an integrated mechanism for reporting purpose

Need for effective and efficient mechanism for traceability & tracking oftransactions

Need for Employee Self Service Facility

Page 13: Track 3 6 Nitin Rohilla NDPL

Implementation mandate at NDPL

“To adopt the SAP Best Practices with least

developments”

Page 14: Track 3 6 Nitin Rohilla NDPL

Definition – Phase I

SAP Implementation Project -

The project name signifies,

“INTEGRATION OF END TO END WORK FLOW IN BUSINESS PROCESSES”

The objective of SAP implementation in NDPL was to assimilate keysupport processes such as Human Resources, Finance & Controlling, PlantMaintenance, Project System, Procurement and Inventory Management etc.

Page 15: Track 3 6 Nitin Rohilla NDPL

Implementation Team

SAP Implementation Project -No. of SAP Users – 500Core Team Members – 40 ( Full Time )SAP Consulting Team – 20 (Peak)Applications replaced by SAP

Energise : Finance , Procurement , Stores , Projects & PayrollSuyojana ( Custom Developed ) : Project MonitoringMTS ( Custom Developed ) : Material Tracking System

Page 16: Track 3 6 Nitin Rohilla NDPL

Implementation Timelines

Kick Off – 3rd June 2005Business Blueprint Signoff – 27th July 2005Realization Phase signoff – 30th Sept 2005GO LIVE – 1st Dec 2005End of PGLS – 31st Jan 2006

ProjectPreparation

BusinessBlueprint

RealizationFinalPreparation Go Live &

Support

Page 17: Track 3 6 Nitin Rohilla NDPL

Critical Success Factors

Senior Management Commitment & InvolvementReadiness to ChangeTrainingAble Implementation PartnerBest People Full TimeProject ManagementEnd User EmpowermentSound MethodologyScope ManagementProject review & AuditInfrastructure AvailabilityCommunication

Training of more than 500 end-users by NDPL core team.

Full time off-site and on-site support of SAP Team

Page 18: Track 3 6 Nitin Rohilla NDPL

Implementation Scope – Functional

Finance &Controlling

Logistic Human CapitalManagement

BW & SEM

General Ledger MM - Purchasing PersonnelAdministration

BW Reports

Accounts Payable MM – InventoryManagement

OrganizationalManagement

SEM – Balance ScoreCard

Accounts Receivables PS – Project Planning Recruitment

Asset Management PS – Project Execution PerformanceAppraisal

Funds Management PS – Project Monitoring Training & EventManagement

InvestmentManagement

PS – ProjectCapitalization

Time Management

Cost Center Accounting PM – ManagingTechnical Objectives

Payroll

Profit CenterAccounting

PM – PreventiveMaintenance

PM – Break DownMaintenance

PM - Refurbishment

SD – Sales (scrap salesonly)

Page 19: Track 3 6 Nitin Rohilla NDPL

Broad Implementation Benefits

Tangible BenefitsReduction in cycle timeImprovement in qualityDecrease in expenses

Non-tangible BenefitsEmployee satisfactionImproved employee efficiencyAdaptation to new technologyManagement by facts

Page 20: Track 3 6 Nitin Rohilla NDPL

Reduction in Lead Time

Automatic Creation of Preventive Maintenance orders based onpredefined scheduling parameters – eliminated the manual schedulecreation job

Automatic receipt of Material Reservation at stores (online) which wasearlier manual taking around 24 hours

Stock overview at different storage locations while creating themaintenance order

The functionality of Retroactive effect in Payroll process has reduced thearrear processing time

Down payment request provision is made available to ensure fastresponse and proper monitoring of Vendor advance payment

Automated the Project capitalization process

Average time taken for issuing the material from the stores reduced from12 minutes to 4 minutes

Page 21: Track 3 6 Nitin Rohilla NDPL

Improvement in Quality

Creation of preventive maintenance schedule for various type of equipment

Creation of scheduled notification for intimating of vehicle insurance/ Fitnessdue date

Prompt and timely internal reporting for dependable decision support system

Capturing of Positive time attendance

Cheque Printing is now made online using continuous stationery

Facility to simulate the various accounting scenario before saving thetransactions

Serialization of Transformers

Page 22: Track 3 6 Nitin Rohilla NDPL

Speedy Decision Making & Reduction inexpenses

Operational, tactical and strategic reports available catering to all levels ofmanagement

Profit & loss analysis done at Business unit / Zonal level

Exercise availability control at the time of booking actual expenses in orderto control the budgets

Page 23: Track 3 6 Nitin Rohilla NDPL

Non-Tangible Benefits

Automatic Reservation receipt at StoreEliminating duplicity of material issuing work

Real-Time Cost Calculation at the time of Order Creation & Reduction inapproval time

Eliminating manual cost calculation, document flow & approval

Cost ControlStructured approach to the organization from a cost accounting perspective.Ability to achieve a flexible and detailed analysis of Cost Centre & the groupas a whole.

Page 24: Track 3 6 Nitin Rohilla NDPL

Non-Tangible Benefits

Budget Controlling

Regular monitoring and reporting of actual expenses vis-à-vis budgetssupported by online control.

Vendor AccountingImmediate accounting of transactionsOn line availability of details of cleared and outstanding liabilities of suppliers’accounts

Project AutomationAutomation of the entire process of Project System encompassing ProjectPreparation, Cost estimation, Scheduling, Tracking, Completion andCapitalization.

Page 25: Track 3 6 Nitin Rohilla NDPL

Non-Tangible Benefits

Implemented “Employee Self Services” portal, which enables users forfollowing activities :

To apply their leave online,View the status and take printouts of Salary slipView the status and take printouts of Form -16 etc.Submitting Tax Saving particularsEmployee SearchUpdate Personal InformationBooking against Training Calendar

Beside this, there are following features which will be used :Performance appraisal systemTravel planning, approval & claim settlement.Reimbursement of all type of expenses.

Page 26: Track 3 6 Nitin Rohilla NDPL

Integration with Operational Systems

NDPL has successfully achieved the SAP-GIS integration for project preparation,creation, movement & retiring of assets

Page 27: Track 3 6 Nitin Rohilla NDPL

Integration with Operational Systems

SAP-BW as Strategic Reporting Tool

Integration with Sambandh (Billing Software) to capture daily cash inflow infinancial books of account

NDPL is using Enterprise Portal as the default portal for MIS for allapplications. MIS of various IT applications in NDPL, namely, Sambandh,BIRD besides SAP standard reports

Page 28: Track 3 6 Nitin Rohilla NDPL

28

Integration of Applications – ReportingPlatform

Page 29: Track 3 6 Nitin Rohilla NDPL

Innovation

Mapping of Balance Score Card in SAP-SEM

Use of all functionalities of ESS

Integration of SAP with other applications like GIS, SCADA, Sambandh(Billing/CRM), Bird

Bar Coding

MRP

Page 30: Track 3 6 Nitin Rohilla NDPL

New SAP functionalities implemented in2009

Travel & Reimbursement module

PPDS - People Potential Development System

Page 31: Track 3 6 Nitin Rohilla NDPL

New functionalities – Projects Aspire –Phase II

Upgrade to ECC 6.0

IS –U Implementation

GRC

SRM

BO

Page 32: Track 3 6 Nitin Rohilla NDPL

IS – U Implementation

Standardized “Best of Breed” Business Process in Billing & Customer ServicesSeamless Integration with other SAP Modules and External ApplicationsEnhanced Decision Support- for both Regulatory & Statutory CompliancesBetter technology support of business processUse of Standard SAP Processes for Power IndustryA stronger and more unified view of the EnterpriseAlign IT strategy to dynamic business requirementsStrengthened Data integrityStrengthened Business Continuity Capabilities

Project Update:

Page 33: Track 3 6 Nitin Rohilla NDPL

IS – U Implementation

Customer CareConnection ManagementMeter ManagementMeter ReadingRevenue BillingRevenue RecoveryRevenue DisciplineRevenue CollectionEnergy Auditing

Process Scope:

Page 34: Track 3 6 Nitin Rohilla NDPL

IS – U Implementation

SAP IS – U Project TimelinesProject Phases Time Periods

Project Preparation 30th Apr 09 – 24th May 09

Project Kick off 22nd May 09

Business Blue Print 25th May 09 – 31st Aug 09

Realization 01st Sep 09 – 31st Dec 09

Final Preprations (HT) 01st Jan 10 – 31st Jan 10

GO LIVE (HT) 01st Feb 10

Final Preprations (LT) 01st Jan 10 – 31st Mar 10

Post Go Live Support (HT) 01st Feb 10 – 28th Feb 10

GO LIVE (LT) 1st Apr 10

Post Go Live Support (LT) 1st Apr 10 – 08th Jun 10

25th May 09 – 31st Aug 09

Page 35: Track 3 6 Nitin Rohilla NDPL

GRC, SRM & BO Implementation

Process ScopeGRC - Governance, Risk & Compliance

Configuration of SAP - GRC Access Control comprising of all 4 components:

- Enterprise Role Management (ERM)

- Risk Analysis and Remediation (RAR)

- Super User Privilege Management (SPM)

- Compliant User Provisioning (CUP)

SRM – Live Auction Cockpit

BO – Business Objects

Configuration of SAP - GRC Access Control comprising of all 4 components:

Page 36: Track 3 6 Nitin Rohilla NDPL

GRC Implementation

SAP GRC Project Timelines

Project Phases Time Periods

Project Preparation 01st Sep 09 – 07th Sep 09

Project Kick off 01st Sep 09

Business Blue Print 08th Sep 09 – 21st Sep 09

Realization 22nd Sep 09 – 14th Oct 09

Final Preprations 15th Oct 09 – 18th Oct 09

GO LIVE 19th Oct 09

Post Go Live Support 19th Oct 09 – 25th Oct 09

Page 37: Track 3 6 Nitin Rohilla NDPL

37

Awards & Recognitions… to name a few

Acknowledgements for persistent efforts……

Page 38: Track 3 6 Nitin Rohilla NDPL

Awards & Recognitions.. to name a few

Winner of SAP ACE Award 2008

Page 39: Track 3 6 Nitin Rohilla NDPL

Year Award

2003-2004

2004-2005

Transparencyin Billing

IntelligentEnterprise

Public LokAdalat Award

Award For BestBilling Solutions

Recognitions

Corporate SocialResponsibility

Page 40: Track 3 6 Nitin Rohilla NDPL

Awards 2008-09

NDPL 40

Asian Power AwardIndia Power AwardsEnertia Award

Edison AwardBalance Scorecard- Hall

of FameAmity Leadership Award

SAP ACE AwardGITA AwardICWAI Award

Page 41: Track 3 6 Nitin Rohilla NDPL

© SAP 2008 / Page 41

Thank you!

Page 42: Track 3 6 Nitin Rohilla NDPL

Copyright 2009 SAP AGAll Rights Reserved

No part of this publication may be reproduced or transmitted in any form or for any purpose without the express permission of SAP AG. The informationcontained herein may be changed without prior notice.

Some software products marketed by SAP AG and its distributors contain proprietary software components of other software vendors.

Microsoft, Windows, Excel, Outlook, and PowerPoint are registered trademarks of Microsoft Corporation.

IBM, DB2, DB2 Universal Database, System i, System i5, System p, System p5, System x, System z, System z10, System z9, z10, z9, iSeries, pSeries,xSeries, zSeries, eServer, z/VM, z/OS, i5/OS, S/390, OS/390, OS/400, AS/400, S/390 Parallel Enterprise Server, PowerVM, Power Architecture,POWER6+, POWER6, POWER5+, POWER5, POWER, OpenPower, PowerPC, BatchPipes, BladeCenter, System Storage, GPFS, HACMP,RETAIN, DB2 Connect, RACF, Redbooks, OS/2, Parallel Sysplex, MVS/ESA, AIX, Intelligent Miner, WebSphere, Netfinity, Tivoli and Informix aretrademarks or registered trademarks of IBM Corporation.

Linux is the registered trademark of Linus Torvalds in the U.S. and other countries.

Adobe, the Adobe logo, Acrobat, PostScript, and Reader are either trademarks or registered trademarks of Adobe Systems Incorporated in the UnitedStates and/or other countries.

Oracle is a registered trademark of Oracle Corporation.

UNIX, X/Open, OSF/1, and Motif are registered trademarks of the Open Group.

Citrix, ICA, Program Neighborhood, MetaFrame, WinFrame, VideoFrame, and MultiWin are trademarks or registered trademarks of Citrix Systems, Inc.

HTML, XML, XHTML and W3C are trademarks or registered trademarks of W3C®, World Wide Web Consortium, Massachusetts Institute of Technology.

Java is a registered trademark of Sun Microsystems, Inc.

JavaScript is a registered trademark of Sun Microsystems, Inc., used under license for technology invented and implemented by Netscape.

SAP, R/3, SAP NetWeaver, Duet, PartnerEdge, ByDesign, SAP Business ByDesign, and other SAP products and services mentioned herein as well as theirrespective logos are trademarks or registered trademarks of SAP AG in Germany and other countries.

Business Objects and the Business Objects logo, BusinessObjects, Crystal Reports, Crystal Decisions, Web Intelligence, Xcelsius, and other BusinessObjects products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of Business Objects S.A. inthe United States and in other countries. Business Objects is an SAP company.

All other product and service names mentioned are the trademarks of their respective companies. Data contained in this document serves informationalpurposes only. National product specifications may vary.

These materials are subject to change without notice. These materials are provided by SAP AG and its affiliated companies ("SAP Group") for informationalpurposes only, without representation or warranty of any kind, and SAP Group shall not be liable for errors or omissions with respect to the materials.The only warranties for SAP Group products and services are those that are set forth in the express warranty statements accompanying such productsand services, if any. Nothing herein should be construed as constituting an additional warrant.