THORNE GROUP Earthworks : Recycling : Reclamation : Demolition : Dismantling GASCOIGNE WOOD COLLIERY RECLAMATION & DEMOLITION Demolition of 30m high rapid loading bunker over live railway lines
8

THORNE GROUP Earthworks : Recycling : Reclamation : Demolition : Dismantling GASCOIGNE WOOD COLLIERY RECLAMATION & DEMOLITION Demolition of 30m high rapid.

Jan 03, 2016

Download

Documents

Sharon Todd
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: THORNE GROUP Earthworks : Recycling : Reclamation : Demolition : Dismantling GASCOIGNE WOOD COLLIERY RECLAMATION & DEMOLITION Demolition of 30m high rapid.

THORNEGROUP

Earthworks : Recycling : Reclamation : Demolition : Dismantling

GASCOIGNE WOOD COLLIERY

RECLAMATION & DEMOLITION

Demolition of 30m high rapid loading bunker over live railway lines

Page 2: THORNE GROUP Earthworks : Recycling : Reclamation : Demolition : Dismantling GASCOIGNE WOOD COLLIERY RECLAMATION & DEMOLITION Demolition of 30m high rapid.

THORNEGROUP

Earthworks : Recycling : Reclamation : Demolition : Dismantling

View of the 30m High Rapid Loading Bunker at Gascoigne Wood Colliery. The control tower located in the centre of the structure was required to remain undisturbed.

Page 3: THORNE GROUP Earthworks : Recycling : Reclamation : Demolition : Dismantling GASCOIGNE WOOD COLLIERY RECLAMATION & DEMOLITION Demolition of 30m high rapid.

THORNEGROUP

Earthworks : Recycling : Reclamation : Demolition : Dismantling

View of the conveyers which required removal and some of the railway lines which would remain in use during the demolition of the structure

Page 4: THORNE GROUP Earthworks : Recycling : Reclamation : Demolition : Dismantling GASCOIGNE WOOD COLLIERY RECLAMATION & DEMOLITION Demolition of 30m high rapid.

THORNEGROUP

Earthworks : Recycling : Reclamation : Demolition : Dismantling

View from the top of the structure, showing the extent of the railway infrastructure. All lines except those running under the main structure remained live during demolition.

Page 5: THORNE GROUP Earthworks : Recycling : Reclamation : Demolition : Dismantling GASCOIGNE WOOD COLLIERY RECLAMATION & DEMOLITION Demolition of 30m high rapid.

THORNEGROUP

Earthworks : Recycling : Reclamation : Demolition : Dismantling

Following isolation of the working area, the cladding sheets were removed utilising a all-terrain crane and cherry picker. Note the temporary works erected to protect the control tower from

damage

Page 6: THORNE GROUP Earthworks : Recycling : Reclamation : Demolition : Dismantling GASCOIGNE WOOD COLLIERY RECLAMATION & DEMOLITION Demolition of 30m high rapid.

THORNEGROUP

Earthworks : Recycling : Reclamation : Demolition : Dismantling

Upper sections of the structure were removed 1st, following removal of the

cladding sheets

This was completed systematically by our specialist demolition plant

Page 7: THORNE GROUP Earthworks : Recycling : Reclamation : Demolition : Dismantling GASCOIGNE WOOD COLLIERY RECLAMATION & DEMOLITION Demolition of 30m high rapid.

THORNEGROUP

Earthworks : Recycling : Reclamation : Demolition : Dismantling

Following removal of the upper steel structure, the concrete and brick

elements were removed and processed on site to produce

secondary aggregates

Once the remaining steelwork structure was clean, it was

dismantled using our long reach excavator fitted with a shear

attachment

Page 8: THORNE GROUP Earthworks : Recycling : Reclamation : Demolition : Dismantling GASCOIGNE WOOD COLLIERY RECLAMATION & DEMOLITION Demolition of 30m high rapid.

THORNEGROUP

Earthworks : Recycling : Reclamation : Demolition : Dismantling

Here is a ‘before and after’ view of the control tower

The works were completed without complication and the control tower and live railway lines continued to operate

throughout the demolition