training report on construction of multi-storeyed residential flats in presentation submitted by • Raj Vaibhav Singh • Roll no 1236300084 • (CE 4 th year) • Ambalika institute of management technology
Summer training report on construction of multi-storeyed residential flats in
presentation submitted by• Raj Vaibhav Singh• Roll no 1236300084• (CE 4th year)• Ambalika institute of management technology
Project highlightSite location
About marg group• incorporated in 1994, MARG Group today successfully operates the fully
functional ‘MARG Karaikal Port’ having a current capacity of 21 MMTPA. In addition, the Group has developed 1.2 Mil sqft of residential space, delivered 1200 homes and has a customer base of over 4000. The Group is executing 21 major projects worth more than Rs 3800 crores in varied domains through its EPC division. Major developments include a 1.85 million sq.ft. integrated development – 'MARG Junction Mall' and a unique 23 million sq. ft. integrated industrial and services township, 'MARG Swarnabhoomi'.
• MARG Group is one of India's fastest growing infrastructure organizations and is listed by Dun & Bradstreet as among "India's Top 500 Companies 2011".
Project synopsis
• Name of project• Location of the project
• Client
• Contractor• Construction area• Built up area• No. of towers
Himalya enclaveLucknow Uttar pradesh
Up housing and developing boardMarg ltd6352 sqm32500 sqm3
featuresTower name
NO’S SUPERBUILT UP AREA(sqm)
configuration
D3 52 627.843 3 BHK+S,S+13
C3 52 576.033 3BHK,S+13
B5 104 785.223 2BHK,S+13
Site layout
PLAN OF BUILDING
CONTRACT DETAIL
• Date of start• Date of completion• Built up area• Cost of project• Earnest money• Completion time• Performance bank
guarantee• Security deposit
19/09/201310/12/20153250069 crores75 lacks27 months5% of contract value for a period of 3 yr. 6 month5%of contract amount shall be deducted in running bills
NAME OF WORK
• E,P & C of multi storeyed residential finished houses including basement based on rcc monolithic shear wall concept using aluminium framework in Himalaya enclave in sec 17 vrindavan yojana, lucknow including soil testing, structural design and all site internal development complete in all respect ready to move in for living condition.
Construction sequence• Survey and soil test• Excavation test pile • Piling• Retaining wall• Pile cap beam & stilt• Basement shear wall & stilt• Base roof slab & stilt• Mock up• Floors• Mep &fire fighting • finishing
Quality management system
Quality management
system
Quality control
Quality assurance
Field quality plan• This plan is document which is submitted by contractor in tender document• Some important test are given below
tests frequency
Cube test (concrete) 6 m3 of concrete (6 nos. cubes)
Slump test Every lot
Temperature Every lot
Sieve analysis (aggregate) Daily
Moisture content(aggregate) Daily
Flakiness index Weekly once
Specific gravity Once in 3 months
Elongation index Weekly once
Silt content Daily
Water absorption Once in 3months
Bulk density Change of source
Cement testing Every lot
Silt content daily
Quality control labA q.c. lab with well equipped apparatus is present where previous test are carried
1.slump cone testA slump test is a method used to determine consistency of concrete. The consistency, or stiffness, indicate how much water has been used in mix. For pile , slump should be 165 mm
Cube testing• This test is done to check the compressive strength of casted
concrete or mixed in respective proportions and poured in cube mould. The cubes are then oven dried the cubes are then cured for 28 days. The cubes strength for 3 days,7 days, 28 days curing are recorded. The cubes are tested in compression testing machine or universal testing machine. The test result corresponding to 28 days curing gives the grade of concrete
Impact test
• This test done to determine the aggregate impact value of coarse aggregates as per is:2386 (part 4)-1963. the apparatus used for determining aggregate impact value of coarse aggregate is impact testing machine conforming to is:2386(part4)-1963, is sieve sizes -12.5mm, 10mm, and 2.36mm, A cylindrical metal measure of 75mm dia and 50mm depth, a tamping rod of 10mm circular cross section and 230mm length, rounded at one end and oven.
ImpactApparatus
Sieve shaker
temping rod cylindrical metals
Project execution• SurveySurvey is the first step done in any construction site so as to get the required level of the surface. Survey in the site is carried out by two instruments.
Auto level Total stationAuto levelAuto level is optical instrument used toEstablish or check point in the same horizontalPlane. It is used in surveying and building toTransfer, measure, or set horizontal levels.in theSite, it used for excavation works and levelling.Least count of auto level is 5mm.
Total stationTotal station is an electronic theodolite (transit) integrated with an electronic distance meter(EDM) to read slope distances from the instrument to a particular point. points for the piling are given by the total station. In this site, 5 benchmarks are established.While giving the point for pile, we take back sight reading after setting the total station. Then we start giving points for pile. The least count of total station is +2
PILING• Piling is the type of deep foundation. bored cast-in-situ
R.C.C. pile was caste for the construction purpose.• specification
Length of pile below C.O.L. 30 meter
Diameter of pile 600,750 mm
Type of pile Cast-in-situ(installation)End bearing pile(function)Concrete pile (material)
Grade of concrete M-30
Design safe load(compression) 180 MT
tower 750mm dia pile 600mm dia pile NO. of piles
D3 99 14 113
C3 106 - 106
B5 140 - 140
TOTAL PILE 359
PILE DRIVEN MACHINES Truck mounted rotary machine Rig machine
Rotary machine
Rig machine
Process in piling
boring
Washing and cleaning
reinforcement
concreting
boring• After marking the point from total station, the first
process is to bore the hole up to 3 meter and after 3 meter, the boring will take place with the help of water jet fitted on the top of the machine which convey the water from the bore pipe.
as per soil condition sodium bentonite used to avoid collapsing of the soilGenerally 5-6 bags of bentonite bags are used for boring 31.20 meters.Why sodium bentonite?
Excellent collidel properties Self-sealing Low permeability carrier
Cleaning of bore holes
When the bore has been completed then cleaning of bore hole is done with the help of water jet fitted over the top of the TMR/DMC rod . Washing is done till the soil suspended particles has been removed from the water.
reinforcementAfter washing, reinforcement has been placed. The reinforcement has been break up in to 4 parts 12,8,7,6.6 meter.800 mm is lapping between the two section of reinforcement.
Description of reinforcement
name Diameter of bar
No’s spacing
Vertical bars 16 16 108 mm
Master bars 12 32 1000 mm
Helical ring 8 209 150 mm
Cover : 75 mm
concreting
Concreting for bored pile is done by tremie method Site data:
Length of tremie pipe: 3 m, 1.5m Diameter of tremie pipe: 220mm, as per IS2911
(part1/sec2), the dia of the tremie pipe should not less than 200mm
slump: 165mm Cement content: 415 kg/m3 Grade of concrete : M30
Time & costactivity Time taken (in hrs)
boring 4.0 (depend on soil condition)
washing 1.0
reinforcement 2.0
Tremie pipe (fixing) 1.0
casting 1.0
The above data is of tmr machine. The main difference as compared with ring machine with respect to time is it take 8 hrs. for boring while TMR machine takes 4hrs depends on soil condition
Project drilling time
• Project drilling time (pdt) = N* TDT days 60 WHWhere,N= no. of pilesTDT= total drilling timeWH= working hoursTaking data of D3 tower,N= 113 pilesTDT= 4 hrs/hole = 240 min/holeWH= 7hrs/day
Project drilling time (pdt)= 113*240 days = 64.5 days 60*7So, the project drilling time of D3 tower in this site is 64.5 days.
cost
• Calculation of cost of one pile
activity Cost(R s.)
Bore (1000/meter) 31000
Reinforcement (rs.47/kg) 49068
M-30 concrete 81000
total Rs. 161068/pile
Retaining wall• In this site, cantilever retaining wall is constructed. Cantilever
retaining walls are constructed of reinforced concrete. They consist of a relatively thin stem and a base slab. The base is also divided in to two parts, the heel and toe. The heel is the parts of the base under the backfill. The toe is the other part of base.
• North direction: 71.25 meter• West direction: 102.69 meter• South direction: 41.13 meter• East direction: 40.66 meter• Grade of concrete: M-25 • Expansion joint 50mm every 40 meter.
Concrete Forms Construction of Reinforced Concrete Walls.mp4
Let take a look on video
Construction equipment planning
s.no. equipment Peak requirement
Immediate requirement
Available
1 Concrete batching plant
1 1 1(30 cum/hr)
2 Transit mixture 4 6 4
3 D.G sets 1 1 2
4 Dewatering & curing pump
4 4 4
5 Concrete pump 2 2 2
6 trailers 2 1 2
Marg equipment’s1.Transit mixture2.Concrete pumps3.Concrete batching plant4. Vehicle5. jcb
function of equipment
1.concrete pump They are used to pump concrete to various places (above and below ground level) he capacity of the pumps used to depends on height to which concrete is to be pumped. The capacity of the pump also depend on the mix design. The concrete used should be pump able concrete i.e. concrete having slump value 140mm or more.2.Transit mixtureIt transport the ready mix concrete from the batching plant to the site. The capacity of transit mixer is 6m3, but only 5 m3 of concrete is filled to prevent overloading
Batching plant
A batching plant has been set up 4km from the site in order to meet the concrete requirement for the site. Batching plant helps in reducing the cost of concrete as compared to procuring it from an outside source. It also give the freedom to design the mix at will.The ideal production capacity of the batching plant is 30m3 of concrete in one hour, but practically it produce 25-26m3 of concrete in one hour. The fine and coarse aggregates are transferred using conveyor belts. The opening to the skip bucket are controlled by hydraulic jacks. As the required quantity of fine and coarse aggregates fall into the skip bucket, the opening close and the bucket is taken up, and the concrete are emptied into the mixer drum. The capacity of the mixer drum is 0.5m3.OPC cement, aggregate and fly ash are stored in three different silos. The required amount of cement and fly ash are mixed along with the correct proportion of plasticizer (epex adplax GFH), Water and aggregate fore30 seconds and fresh concrete get poured in to transit mixer which transports the concrete to the site.
Site views
Present condition of building
Any query please…………..
Thank you