Background
Previous Studies:
forwardDallas! Comprehensive Plan
DART 2030 Transit System Plan D2 Downtown Dallas Transit Study
8/14/2019 Streetcar Briefing for June 8
3/16
JOINT: City of Dallas and DART work together to
secure funding from various local, regional, stateand national sources
Organizational Roles
8/14/2019 Streetcar Briefing for June 8
4/16
City of Dallas : Owns and maintains right-of-way
Provides funding for infrastructure, vehicles andoperations (Potential Source: City bond funds and TIF
revenues.)
Provides oversight
Organizational Roles
8/14/2019 Streetcar Briefing for June 8
5/16
DART (by agreement with and funding from City): Coordination of system planning and design. (Potential
Source: City bond and RTR funds.)
Procures the vehicles. (Potential Source: City bond funds.)
Contracts for construction. (Potential Source: City bond fundsand TIF revenues.) Operates the streetcar. (Potential Source: Partial funding
through DARTs Site-Specific Shuttle Operating Policy and PIDs.)
Maintains the streetcar system. (Potential Source: Partialfunding through DARTs Site-Specific Shuttle Operating Policy andCity Parking fees.)
Organizational Roles
8/14/2019 Streetcar Briefing for June 8
6/16
Private Sector (Developers, landowners, etc)
Support the operation through public funding. (PotentialFunding Source: TIFs, PIDs)
Support the operation through private funding. (PotentialFunding Source: sponsorships, naming rights)
Organizational Roles
8/14/2019 Streetcar Briefing for June 8
7/16
7
Initial Streetcar
Alignment
Options
* Dashed blue lines: D2 LRT Alignment Options
8/14/2019 Streetcar Briefing for June 8
8/16
8
Initial Streetcar
Alignment
Options
Olive / St. PaulCorridor
* Dashed blue lines: D2 LRT Alignment Options
8/14/2019 Streetcar Briefing for June 8
9/16
9
Initial Streetcar
Alignment
Options
Olive / St. PaulCorridor
Elm / Main /Commerce Corridor
* Dashed blue lines: D2 LRT Alignment Options
8/14/2019 Streetcar Briefing for June 8
10/16
10
Initial Streetcar
Alignment
Options
Olive / St. PaulCorridor
Elm / Main /Commerce Corridor
Lamar Street Corridor
* Dashed blue lines: D2 LRT Alignment Options
8/14/2019 Streetcar Briefing for June 8
11/16
11
Initial Streetcar
Alignment
Options
Olive / St. PaulCorridor
Elm / Main /Commerce Corridor
Lamar Street Corridor
Possible Extensions Oak Cliff / West Dallas
Deep Ellum
Farmers Market
Others
* Dashed blue lines: D2 LRT Alignment Options
8/14/2019 Streetcar Briefing for June 8
12/16
Business Plan Project
Comprehensive description of therecommended project
An Implementation Plan
Kick-off: June 9, 2009
8/14/2019 Streetcar Briefing for June 8
13/16
Deliverables
Preferred Initial Alignment and Operating Plan
Technology Requirements and Recommendations
Facilities Requirements
Staffing Plan and Business ProcessesRecommendations
Base Information and Redevelopment Projections
Funding Requirements, Options and Recommendations
Organizational and Governance Recommendations Outreach and Communications Plan Recommendations
Implementation Plan
8/14/2019 Streetcar Briefing for June 8
14/16
Timeline
Bring study recommendations to City Council /DART Board in early fall 2009
Council action to implement recommendations
8/14/2019 Streetcar Briefing for June 8
15/16
Key Decision Points
Funding Source(s) and Magnitude
Definition of Initial Project Limits
Federal / Non Federal Project Vehicle Specifications