SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED Under Ground Excavation in progress @ Twin Tunnel Nathdwara end
Feb 24, 2016
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
Under Ground Excavation in progress @ Twin Tunnel Nathdwara end
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
Under Ground Excavation in progress @ Twin Tunnel Nathdwara end
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
Tunnel face of Nathdwara end
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
DBM completed @ Ch. 255 + 200 LHSDBM completed Service Road with drain @ Ch. 232+650 LHS
5
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
Girder Erection work in progress at Khari River Bridge @ Ch. 214+507
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
DBM Completed @ Ch. 191+340
WMM work in progress at Major Junction @ Ch. 183+800 LHS
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
8
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
Girder Erection work in progress at Rajsamand Flyover @ Ch. 204+653
9
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
Foundation work in progress at Minor Bridge @ Ch. 240+725
Reinforcement Steel fixing for Raft of Box Culvert @ Ch. 240+900
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
Girder Erection work in progress at Rajsamand Flyover @ Ch. 204+653
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
Arrangement of 2nd pile load test by Kentledge Method @ Khari River Bridge @ Ch. 241+507
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
Hard barricading provided at Nathdwara Elevated Flyover
Hard barricading provided at Rajsamand Flyover
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
Fixing of flexi Road Signages at various prominent locations
SHREENATHJI UDAIPUR TOLLWAY PRIVATE LIMITED
Road safety Awareness programme conducted at various locations