Engineer Mohamed Esmat Abdelrazek PMP Project Management professional
Aug 23, 2014
EngineerMohamed Esmat Abdelrazek
PMP
Project Management professional
Organizational Influences on Project Management
The organizational culture, style, and structure influence how projects are performed .
An organization’s degree of project management maturity and its project management systems can also influence the project
Organizational StructureOrganizational structure is an enterprise environmental factor which can affect the availability of resources and influence how projects are conducted
Functional organization
Functional manager
staff
staff
Functional manager
staff
staff
Functional manager
staff
staff
Functional manager
staff
staff
C.E.O
Weak Matrix organization
Functional manager
staff
staff
Functional manager
staff
staff
Functional manager
staff
staff
Functional manager
staff
staff
C.E.O
Expeditor orcoordinator
Balanced Matrix organization
Functional manager
staff
Project manager
Functional manager
staff
staff
Functional manager
staff
staff
Functional manager
staff
staff
C.E.O
Strong Matrix organization
Manager of project managers
Project manager
Project manager
Functional manager
staff
staff
Functional manager
staff
staff
Functional manager
staff
staff
C.E.O
Projectized organization
Project manager
Staff
Staff
Project manager
Staff
Staff
Project manager
Staff
Staff
Project manager
Staff
Staff
C.E.O
Organizational influences on Projects
Functional
Matrix
ProjectizedWeak matrix Balanced
matrixStrong matrix
PM Authority Little or None Limited Low to
ModerateModerate To
HighHigh To
almost total
Resource Availability
Little or None Limited Low to
ModerateModerate To
HighHigh To
almost total
Who Controls The Project
Budget
Functional Manager
Functional Manager Mixed Project
managerProject
manager
Let us start .……Question:
how to formally authorize the project?
Answer :Develop
project charter
المشروع قبل ما خطواتخاص- 1 مستشفى لبناء مناقصة لدخول بالشركة االتصال تمللمشروع- 2 جدوى دراسة عمل Business Caseتمالشركة- 3 في للمشروع تصور عمل Project Statement ofتم
Work
المستشفى- 4 مالك مع عقد توقيع Contractتم
المشروع بدايةللمشروع- 1 مدير وتعيين التأسيسية الوثيقة Devolp projectعمل
charter
initiating•Develop Project charter
• The process of developing a document that formally authorizes a project or a phase
•Inputs
• Project statement of work
• Business case• Contract• Enterprise environmental
factors• Organizational process
assets
Tools & Techniques
1. Expert judgment
Outputs
1. Project charter
• Statement of Work• narrative description of products or services to
be delivered by the project contain• Business need• Product scope description • Strategic plan
Business Case• Provide the necessary information from business
standpoint to determine whether or not the project is worth the required investment.
Enterprise Environmental Factors
Organizational culture and structure , Government or industry standards
product standards, quality standards, and workmanship standards),
Infrastructure (e.g., existing facilities and capital equipment),
Existing human resources (e.g., skills, disciplines, and knowledge, such as design,
development, law, contracting, and purchasing), Personnel administration (e.g., hiring and firing
guidelines, employee performance reviews, and training records),
Company work authorization systems, Marketplace conditions,/
Organizational process assets
-Organizational policies as they pertain to scope planning andmanagement
-Organizational procedures related to scope planning and management
-Historical information about previous projects, lesson learned project archives
Project charter contents-Project purpose & justification.
-Objectives and their success criteria-High level requirements that satisfy
stakeholder needs, wants, and expectation. -Business need, high level product
description, or product requirements.-Assigned project manager and authority
level.-Summary milestone schedule.
-Summary budget -Name of sponsor or those authorizing the
project -Functional organizations and their
participation.-Organizational, environmental & external
assumptions.
خاص مستشفى انشاء لمشروع التأسيسية الوثيقةبمدينة : التخصصات جميع خاص مستشفى انشاء المشروع من الهدف
االسماعيليةاالرضي : الطابق طوابق اربع من المستشفى مبنى يتكون المشروع وصف
عدد على ويحتوى و 9للطوارئ للمرضى 37غرف االول والطابق سريرعلى ويحتوي القصيرة واالقامة و 12االطفال الثاني 35غرفة والطابق سرير
على ويحتوى الرجال من البالغين و 12للمرضى الثالث 35غرفة والطابق سريرعلى ويحتوى النساء من البالغين و 12للمرضى سرير 35غرفة
من المشروع مصري 15:12تكلفة جنيه مليونالرئيسيين المصلحة اصحاب
المستشفى مالك محمد احمد الحاجالمستشفى عام مدير على حسام الدكتور
االستشاري المكتب رئيس سليمان محمد المهندسالمشروع : واالجهزة 5زمن للتجهيزات وشهرين للمباني شهور
الطبية : , االجهزة بعض ندرة الشراء عند الحديد سعر ارتفاع المحتملة المخاطرالموردين وتأخير
بمصر : للجودة القياس لمعايير طبقا القبول يتم القبول معاييرالمرضى : لنقل مصعد ووجود غرفة بكل شباك وجود الرئيسية المتطلبات
المستشفى تحت االطباء لسيارات جراج ووجودالمشروع ادارة سلطات وله االرض باستالم المشروع مدير يختص
الجدول على يؤثر تغيير وجود عند الشركة الدارة الرجوع المشروع مدير علىالتكلفة او الزمني
المختلفة العقود كتابة عند المشتريات مدير مشاركة المشروع مدير على
الممول المشروع مدير / مصطفى/ خالد د فاروق علي م
Question: What is the next
step? Answer :
Identify Stakeholder
Identify Stakeholder
• The process of identifying all people or organizations impacted by the project, and documenting relevant information regarding their interest, involvement, and impact on project success.
Inputs
1. Project charter2. Procurement
documents3. Enterprise
environmental factors4. Organizational process
assets
Tools & Techniques
1. Stakeholder analysis2. Expert judgment
Outputs
1. Stakeholder register2. Stakeholder
management strategy
Stakeholder Analysis
• A technique of systematically gathering and analyzing quantitative & qualitative information to determine whose interests should be taken into account throughout the project.
Output of Identify Stakeholder
• Stakeholder Register
Stakeholder Stakeholder interest(s) in the project
Assessment of impact Potential strategies for gaining support or reducing obstacles
Name Contact Information
Role in Project Department/
Supervisor Company Impact Influence Main expectations Attitude about the project Major requirement
• Stakeholder Management Strategy- Defines an approach to increase the support and minimize negative impacts of
stakeholder.- The information could be too sensitive to be shared.- A common way of representing is by using a stakeholder analysis matrix.
االسم
االتصال الدور في
المشروع
القسم
الشركة
التأثير
االهتمام
التوقعات الموقمن ف
المشروع
اهم االحتيا
جات
حسي. دن
01222536 مفتش التفتيش
وزارة الصح
ة
كبير كبير تأخر المشروع
سلبي االهتمام بزيادة
مساحة الغرف لصحة المرض
ىم . احمد
01423563 مهندس تخطيط
المتحدة
متوسط
كبير المشروع الوقت في
المحدد
ايجابي زيادة الموارد البشرية بالموقع
النجاز المشرو
في عالوقت المحدد
اصحاب سجلالمصلحة
المتاحة الخططاالستفادة لزيادة
من التقليل اوالضرر
التأثير االهتمام االسم
مديره الى اللجوء يتمخالفات وجود حالة في
كبير كبير حسين. د
بمدى الحوافز ربط يتمالخطة دقة
متوسط كبير احمد. م
اصحاب ادارة خطةالمصلحة
QUESTIONS?
1-Which of the following is not a project?
a. Running an election campaign for a political candidate.
b. Building a bridge over a river.
c. Pilot aircraft for a United flight. d. Writing a book on Project Management
2 .Which of these is not one of the triple constraint of a project ?
A-Scope
b. Resources
c. Time
d. Cost
3-Which of the following is NOT a characteristic of a project?
A- Constrained by limited resources
B- Planned, executed, and controlled
C- Creates a unique product or service
D- Ongoing and repetitive
4-You are managing the release of a new drug in the market. Your role is that of a:
A- Functional Manager, because you have good functional knowledge of the pharmaceutical industry
B- Project Manager, because you are creating a unique product within specific time schedules
C- Operations Manager, because you have to do several repetitive tasks
D- Program Manager, because you have to manage several projects to do your job effectively
5-What is the purpose of a project charter?
A-To formally authorize a project or a phase and document initial requirements which satisfy the stakeholder’s needs and expectations .
B-To document how the project will be planned, executed ,monitored/controlled, and closed .
C-To link the project, which is going to be planned, executed, and monitored/controlled to the ongoing work of the organization .
D-To describe the process of performing the work defined in the project management plan in order to achieve the project’s objectives .
6-During a planning meeting, a discussion takes place on which resource will be assigned to perform an activity that will be fast-tracked. As the project manager, you decide to assign Fred to the activity.
What type of organizational structure is this?A. Functional organization
B. Projectized organization
C. Matrix organization
D. Balanced Matrix organization
7 -Who should be responsible for defining project objective?
A- Project manager
B- sponsor
C-Project management team
D-Stakeholders
8 -a difference between the requirements is best resolved in favor for the:
A- project manager
B- stakeholders
C- sponsor
D- customer
9 -which of the following is not example of a Project?
A- Issuing monthly invoices
B- Implementation of a new Software Program
C-Design of a new department store
D- Construction of a bridge
10 -in a projectized organization the project Team
A- reportes to many bosses
B- has no loyalty to project
C- reports to functional manager
D- has no loyalty to organization
Thank you