Page 1: SEM 6th final 1

1

GUJARAT TECHNOLOGICAL UNIVERSITY

Chandkheda, Ahmedabad

Affiliated

Noble Group of institution

A Project Report On

Automatic railway crossing system (ARC)

Under subject of DESIGN ENGINEERING – 2B

B. E.III, Semester – VI

(Electrical & Mechanical Branch)

Submitted by: -ARC makers

Page 2: SEM 6th final 1

2

Group: ARC makers

Sr. Name of Student Enrollment No.

1. Kacha Naimish 130350109513

2. Raval Sagar 130350109523

3. Odedara Subhash 140353109008

4. Nandania Yagnik 130350119084

Prof. K. K. Chouhan

Prof. Pankaj C. Jadav

Prof. Rakesh Akbari

(Head of the Department)

Academic year

(2015-2016)

Page 3: SEM 6th final 1

3

Certificate

This is to certify Mr. Naimish Kacha Enrollment no. 130350109513

of B.E 6th semester of Electrical Engineering Branch has satisfactory

completed the laboratory work in Design Engineering 2B subject

within the four walls of laboratory.

Date of submission: /04/2016

_____________ ________________

Mentor signature Head of Department

Page 4: SEM 6th final 1

4

Certificate

This is to certify Mr. Sagar Raval Enrollment no. 130350109523

of B.E 6th semester of Electrical Engineering Branch has satisfactory

completed the laboratory work in Design Engineering 2B subject

within the four walls of laboratory.

Date of submission: /04/2016

_____________ ________________

Mentor signature Head of Department

Page 5: SEM 6th final 1

5

Certificate

This is to certify Mr. Subhash Odedara Enrollment no. 140353109008

of B.E 6th semester of Electrical Engineering Branch has satisfactory

completed the laboratory work in Design Engineering 2B subject

within the four walls of laboratory.

Date of submission: /04/2016

_____________ _________________

Mentor signature Head of Department

Page 6: SEM 6th final 1

6

Certificate

This is to certify Mr. Yagnik Nandania Enrollment no. 130350119084

of B.E 6th semester of Mechanical Engineering Branch has satisfactory

completed the laboratory work in Design Engineering 2B subject

within the four walls of laboratory.

Date of submission: /04/2016

_____________ ________________

Mentor signature Head of Department

Page 7: SEM 6th final 1

7

Index

Points & Questions

Page no.

Introduction

8

Modelling and Analysis using Software

9

Engineering Economics of design

15

Design for Use, Reuse and Sustainability

16

Prototyping

17

Measuring instruments/technique- knowledge and use

manufacturing/fabrication process, electronic circuit, boar,

open source tool

18

Comparison of existing materials, methods, tools and

equipment for your project and justify your selection of

materials, methods, tools and equipment etc.

19

Conclusion

20

Future scope

21

Page 8: SEM 6th final 1

8

introduction:

Definition that shows that an automated railway crossing is based on operate railway gates.

Which are specifically stands for better handling and security purpose. As we have kept this

project since 3rd semester we had implemented too many new things for better performance for

ARC.

As in 3rd semester a definition has been fixed i.e. using simple structure how to make secure

crossing gates. With minimal knowledge and lack of concept we had introduce a simple system

for crossing that having laser sensors, ultrasonic sensor, and a DC shunt motor for simple

designing. That whole structure was being control with micro controller and switch

mechanism.

After realizing the remedies of sensor and fault of concept we have implemented a better secure

ARC in 4th semester where we had replaced laser sensor with weight sensor as laser sensor is

low secure and easily decoded by anyone the security being lost by the one single fault.

As we concern our fault and making solution within PLC SCADA we had solve many problems

like wise controlling delay and better operation facility and so on in 5th semester where we

learn programming and basic of PLC SCADA.

Now in this 6th semester we made PLC Circuit board with required circuits and malfunction,

we made whole PLC Program for working of ARC and we have tested this circuit and program

too. We install this program to our PLC DELTA DVP-14SS2. we got great results. As far we

concern and as per our developing speed we will manage to complete our controlling of this

Automaton of railway gate soon.

Page 9: SEM 6th final 1

9

Modeling and Analysis using Software:

WPLsoft 2.38

WPLsoft version 2.38 is basically programming software for Delta PLCs which has elaborated

facility as per required to the programmer, here as we program whole program we have face

some causality for logic control and much more, we need to practice harder for making whole

program through WPLsoft 2.38.

In our project we made programming through ladder diagram which is extra ordinary

feature of WPLsoft where after some logic programming becomes easy to be attempt and can

easily be understood as well. We have rights that received through consumer.

Page 10: SEM 6th final 1

10

Here is snapshot of our program:

Snapshot – 1

Snapshot - 2

Page 11: SEM 6th final 1

11

Snapshot - 3

Snapshot - 4

Page 12: SEM 6th final 1

12

Snapshot - 5

Snapshot - 6

Page 13: SEM 6th final 1

13

Snapshot - 7

Page 14: SEM 6th final 1

14

Math work MATLAB R2015a

For simulation toward circuit and testing we arrange MATLAB circuit by using version 2015.

For testing and resulting MATLAB is one of the important software for simulation.

Simulink PLC Coder

Generate IEC 61131-3 Structured Text for PLCs and PACs

InTouch 10.1

This software is basically for SCADA operation only; this software is being learn in process

we do not have much idea about InTouch 10.1 version but we do know how to arrange all the

function in this software.

Page 15: SEM 6th final 1

15

Engineering Economics of design:

Cost Estimation:

(Project)

Material Cost

DVL Delta 8500

Relay 5V X4 272

Relay 24V X3 300

SMPS (jigo) 950

Connectors box 120

PLC Board 100

Wire 300

IR sensor X3 300

Total 10,842

Material Cost in project Cost in real

Poles 50 1000

Gear 0 200

Total 50 1200

Labor, material and overhead cost:

This system only required maintaining like PLC checkup and circuit checking only like

monthly routine or schedule checking that depends upon system priority. For that an engineer

has to be appointed

Time for value:

As we know time is money this project needs only 1-week time if blue print is available. This

project need less labor and less time too for building up. Set up needs 1 day at location and

moreover total time is 8 days.

Page 16: SEM 6th final 1

16

Design for Use, Reuse and Sustainability: Design for use – how long this system will work?

This system has mainly working on DVL Delta PLC which has life of 25 years perfectly and

it depends on system and atmosphere to increase and decrease of life

Fixing whole circuit so easily that if one component got damage the whole circuit does not

get damage with it. And replacing of that damaged part is also easy.

Maintainability:

This system required maintenance as per routine like monthly and if we put some better

material maintenance.

Page 17: SEM 6th final 1

17

Prototyping:

Versions of prototypes with all possible modification and iterations to

further refine the solutions: -

In ARC project versions there are many modifications and solutions are solved in each semester

working in 4th, 5th and in 6th semester is the final product solution of ARC but steal there is

some hardware software combination problems are occurring because of the small scale

prototype working but it all are solved in real implementation.

In 4th semester Basically idea is there are two weight sensors helps to make sence for upward

and downward of the crossing poles.At some distance from the crossing place we need to apply

a weight sensing sensor for sence incoming trains, as that sensor sence incoming train it gives

that information to those two DC Shunt motors. Armature of motor rotates in clockwise

direction and this is how crossing poles get closed. After that while train left the crossing,

another weight sensor get sence and again that makes sence to DC Shunt motor, after that motor

reverse its rotations and rotates armature in anti-clockwise direaction, this is how corssing poles

moves upward. So, It’s work on this simple principle or process and We also add some security

feateres & high technology features in it.

For security purpose we have included ultrasonic sensor which situated in between network

of crossing poles to make safer transportation while crossing faces traffic. Another hand there

is CCTV 24*7 observed camera for suggestion for critical situation.

But still operation of ARC is not so accurate in sem 4th because of the controller limitations.so

that The operation and controlling is implemented in semester 5th prototype which are

controlled by PLC SCADA controllers.

And final solution and prototype is coming in semester 6th which is as per using Delta PLC

controller and some other changes related to power supply is mainly top of line solutions in

semester 6th

.

Page 18: SEM 6th final 1

18

Measuring instruments/technique- knowledge and use

manufacturing/fabrication process, electronic circuit,

boar, open source tool.

As we started working onto this project here we got first came to face is circuit board. This

circuit board is basically a plywood base have channels implied on it, these channels are stand

for give mechanical support to wire and for better appearance.

We set supply 230v to 24v SMPS for convert 230volt to 24volt DC, This SMPS has +ve 24

and –ve 24 supply output which has to connect respective reply for giving motors or sensor

supply and also for PLC supply.

We are using PLC of DELTA which name is DVL DELTA DVP14SS2 which need 24 DC

input to run and gives 7 outputs respect to 7 inputs

Snapshot of PLC DELTA DVC14SS2

We have using relays to switch voltage level for respective withstand capacity of overall

sensors and motors. We have using 2 Relay channels.

1) 24v relay board

2) 5v replay board

Page 19: SEM 6th final 1

19

Comparison of existing materials, methods, tools and

equipment for your project and justify your selection

of materials, methods, tools and equipment etc.

In this project of ARC, now using PLC-SCADA there are huge difference between earlier

thinking and recently applied improvements and implementations because of in the

introduction of this project is that the main programmer or controller circuit is PLC.

so that is totally different and industrial thinking of upgradation of ARC by preferring this

manual and according to this design thinking and making of arc when we compare the project

materials technique or other factors that shows the sequential progress we have seen many

difference that is given below.

Firstly the main thing is about the PLC which is shows the level of the ARC because of the

microcontroller is common thing in small level projects but when we talking about the

industrial use of controller only one thing is coming that is PLC because of the scale, reliability,

and decision making since of PLC is higher because in ARC which is use for security purpose

or it is more difficult when it is center of traffic or biggest ability to change and replicate the

operation or process while collecting and communicating vital information another advantage

of PLC system is that it is modular. That is, you can mix and match the types of input and

output devices to best suit your application. so, it is very big advantage using PLC.

Second one is the supervisory software SCADA (supervisory control and Data Acquisition) it

is the revolutionary change in Railway improvements in India because of the in rail way control

room in India is the very trafficking zone because of the use of old technologies accept for

communication or also accept for the automation purpose thing SCADA is the best supervisory

software which allows the such kind of good reliability time to think some time auto decision

making is very reliable.

Think about the other equipment like sensors, motor in the market they are many sensors are

available for requirement for the ARC Prototype like the Ultrasonic wave sensors, Proxy

sensor, Load cell but including some reason for security purposes we going to use IR sensor

for selecting this the main thing is for IR sensor IR detectors are little microchips with a

photocell that are tuned to listen to infrared light. They are almost always used for remote

control detection - every TV and DVD player has one of these in the front to listen for the IR

signal from the clicker. Inside the remote control is a matching IR LED, which emits IR pulses

to tell the TV to turn on, off or change channels. IR light is not visible to the human eye, which

means it takes a little more work to test a setup.

In other things like motor there is lots of motor is available in the market which gives different

specifications but in arc we use the DC motor because of the necessary is in the prototype is

small scale use (only in PROTOTYPE) so in smaller size it is very essentially good for better

working and reliability of external DC supply.

Page 20: SEM 6th final 1

20

Conclusion:

By performing this project and taking implementation onto this project from 2 years we had reach to

such an extreme stage where we have a better security like controlling through PLC using proximate

accuracy sensor that measure its sensitivity through mm and other sensor like IR sensor. With using

PLC Delta and SCADA.

All that implemented from last 2 years we provide security and better performance as well in minimal

cost.

Page 21: SEM 6th final 1

21

Future scope:

For future scope we will show efforts for power supply with renewable source like solar energy.

With this source we can show efforts for environment and with solar we can use this project in

remote areas where supply could not be possible, this one step is for ecofriendly contribution

for nature.

Moreover, we will use rare PLC which have number of input with number of output i.e. 50000

systems can be handle with single PLC. So costing can be minimal and single operator required.

Also for more mechanical efforts for redial gates situated in single direction we can use

conveyer and gear mechanism that is how single motor operates multiple gates.

Page 22: SEM 6th final 1

22

References

http://www.scribd.com/doc/7370623/Automatic-Railway-gate-

Control-System

http://engineersprojects.blogspot.in/Automatic Railway gate Control

System

http://engineersebooks-papers.blogspot.in/2012/03/automatic-railway-

gate-control-system.html

http://electronicswork.blogspot.in/2011/11/automatic-railway-gate-

control-system.html

www.atmel.com/dyn/resources/prod_documents/doc2503.pdf

sensor based automatic railway gates (IJARCAT) (ISSN: 2278 –

1323) by: Karthikng Krishnamurthi, Monica Bobby, Vidya V,

Edwin Baby

automated railway controlling (AIEEE) (ISSN (Print): 2320 – 3765

ISSN Online:22788875)

Acy M. Kottalil, Abhijith S, Ajmal M M, Abhilash L J, Ajith Babu PLC controlled gate working (AIEEE) (ISSN: 2044 –

2654) By Mahesh bhattachariya