SECTION 02 41 13.13 PAVING DEMOLITION TRINITY METRO RE-BRANDING PROJECT MARCH 18, 2019 02 41 13.13 PAVING DEMOLITION - 1 PART 1 - GENERAL 1.1 DESCRIPTION A. This Section includes specifications for demolition, removal and disposal of surface and subsurface structures and facilities, including backfilling of excavations and depressions to restore site to final grade. B. The work shall include the abandonment of utilities to be left in place and removal of pavement, sidewalks, curbs, posts, pole foundations, structural steel and c oncrete, c oncrete foundations, fences, walls, utilities, utility structures and other facilities designated to be removed or the removal of which is necessary for the a ccom plishm ent of the project as show n on the Contract Drawings and as specified herein. 1.2 DEFINITIONS A. Demolition: Complete removal and disposal of existing facilities from areas to be cleared and grubbed and from other areas as shown. B. Existing facilities: Includes buildings, portions of buildings, sheds, foundations, pavements, sidewalks, curbs and gutters, signs, posts, fences, bridges, abutments, piers, and other structures which may interfere with construction. Also includes utility facilities such as drainage, sewerage, manholes, inlets, and other utility facilities including underground and overhead utility appurtenanc es. C. Salvage: Refer to Article entitled ‘‘Definitions’’ in Section 02072, ‘‘Removal and Restoration of Miscella neous Existing Facilities’’. D. Selective Demolition: Removal and disposal of portions of existing buildings. 1.3 SUBMITTALS A. Submit Demolition Plan including procedures and operational sequence, methods and equipment for demolition, removal and disposal of structures and facilities, including salvage if require, for review and approval by the Contracting Officer. Demolition Plan shall include procedures for backfilling and shoring and underpinning, as applicable. 1. Submit demolition permit from the jurisdictional agency or ow ner. 2. Submit traffic permit from the jurisdictional agency for transport of debris. 3. Submit permit for disposal of debris. 4. Submit written releases from each owner of property where demolition debris will be deposited absolving the Authority of responsibility in connection with such disposal. Submit releases at least 15 days prior to disposal. Releases shall be signed by owners of property on which material will be deposited. 1.4 REGULATORY REQUIREMENTS AND PERMITS A. Comply with c odes and regulations of jurisdictional authorities. 1. The Contractor shall obtain special permits and licenses and give notices required for performance and completion of the demolition and removal work, hauling, and disposal of debris. 1.5 JOB CONDITIONS A. The Authority assumes no responsibility for the condition of the existing structures to be demolished. B. Utilities: Arrange with the app ropriate utility ow ner for the remo val, rerouting, or c apping of utility and c omply with its regulations. C. Maintenance and Control of Traffic 1. Inc orporate arrangem ents for maintenance and control of traffic as required for demolition work including road closures and hauling of debris in Traffic Control Plan as specified in Section 01570, "Maintenance and Control of Traffic’’. Execute Traffic Control Plan and perform other measures as required to maintain and control traffic. 2. Keep traffic areas free from debris and spillage of materials. D. Protection and Restoration:
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
SECTION 02 41 13.13 PAVING DEMOLITION
TRINITY METRO RE-BRANDING PROJECT MARCH 18, 2019 02 41 13.13 PAVING DEMOLITION - 1
PART 1 - GENERAL
1.1 DESCRIPTION
A. This Section includes specifications for demolition,
removal and disposal of surface and subsurface
structures and facilities, including backfilling of
excavations and depressions to restore site to final
grade.
B. The work shall include the abandonment of utilities
to be left in place and removal of pavement,
sidewalks, curbs, posts, pole foundations, structural
steel and c oncrete, c oncrete foundations, fences,
walls, utilities, utility structures and other facilities
designated to be removed or the removal of
which is necessary for the a ccom plishm ent of the
project as show n on the Contract Drawings and as
specified herein.
1.2 DEFINITIONS
A. Demolition: Complete removal and disposal of
existing facilities from areas to be cleared and
grubbed and from other areas as shown.
B. Existing facilities: Includes buildings, portions of
buildings, sheds, foundations, pavements,
sidewalks, curbs and gutters, signs, posts, fences,
bridges, abutments, piers, and other structures
which may interfere with construction. Also
includes utility facilities such as drainage,
sewerage, manholes, inlets, and other utility
facilities including underground and overhead
utility appurtenanc es.
C. Salvage: Refer to Article entitled ‘‘Definitions’’ in
Section 02072, ‘‘Removal and Restoration of
Miscella neous Existing Facilities’’.
D. Selective Demolition: Removal and disposal of
portions of existing buildings.
1.3 SUBMITTALS
A. Submit Demolition Plan including procedures and
operational sequence, methods and equipment
for demolition, removal and disposal of structures
and facilities, including salvage if require, for
review and approval by the Contracting Officer.
Demolition Plan shall include procedures for
backfilling and shoring and underpinning, as
applicable.
1. Submit demolition permit from the
jurisdictional agency or ow ner.
2. Submit traffic permit from the jurisdictional
agency for transport of debris.
3. Submit permit for disposal of debris.
4. Submit written releases from each owner of
property where demolition debris will be
deposited absolving the Authority of
responsibility in connection with such
disposal. Submit releases at least 15 days
prior to disposal. Releases shall be signed
by owners of property on which material will
be deposited.
1.4 REGULATORY REQUIREMENTS AND PERMITS
A. Comply with c odes and regulations of jurisdictional
authorities.
1. The Contractor shall obtain special permits
and licenses and give notices required for
performance and completion of the
demolition and removal work, hauling, and
disposal of debris.
1.5 JOB CONDITIONS
A. The Authority assumes no responsibility for the
condition of the existing structures to be
demolished.
B. Utilities: Arrange with the app ropriate utility ow ner
for the remo val, rerouting, or c apping of utility and
c omply with its regulations.
C. Maintenance and Control of Traffic
1. Inc orporate arrangem ents for maintenance
and control of traffic as required for
demolition work including road closures and
hauling of debris in Traffic Control Plan as
specified in Section 01570, "Maintenance
and Control of Traffic’’. Execute Traffic
Control Plan and perform other measures as
required to maintain and control traffic.
2. Keep traffic areas free from debris and
spillage of materials.
D. Protection and Restoration:
SECTION 02 41 13.13 PAVING DEMOLITION
TRINITY METRO RE-BRANDING PROJECT MARCH 18, 2019 02 41 13.13 PAVING DEMOLITION - 2
1. Prevent damage to above and below
ground pipes, conduits, wires, cables, and
structures which are not designated for
removal. Repair or replace damaged items.
2. Provide protective devices as specified in
Section 01500, ‘‘Temporary Facilities and
Servic es’’.
3. Provide safe passageways for the public
around the demolition area and conduct
operations to prevent injury to the public
and damage to adjacent buildings,
structures, and other facilities.
4. Protect sidewalks, utilities, streets, and
facilities adjacent to the work from damage
caused by settlement, lateral movement,
undermining, washout, and other hazards
created by demolition operations. Do not
leave sidewalks, utilities, streets, and facilities
adjacent to the work in a dangerous
condition as a result of the demolition
operation.
5. Maintain, support and restore utilities in
accordance with Section 02 76 00,
"Maintenance, Support, and Restoration of
Existing Utility Fa cilities".
6. Existing utilities and drainage systems below
grade are located from existing documents
and from surface facilities such as
manholes, valve boxes, area drains and
other such surface fixtures. It is the
responsibility of the Contractor to verify
existing utilities prior to demolition.
7. If existing active services encountered are not
indicated or otherwise made known to the
Contractor and interfere with the permanent
facilities under construction, immediately notify
the Contracting Officer in writing, requesting
instructions on their disposition. Take
immediate steps to ensure the services
provided are not interrupted, at no additional
cost to the Authority and do not proceed with
the work until instructions are received from the
Contracting Officer.
8. Thicknesses of existing pavements are from
previous construction documents, and do not
imply the actual depth or thickness of the total
pavement or base material, where it occurs.
Remove pavement of whatever thickness as
required, at no additional cost to the Authority.
E. Environental Protection: In accordance with
Section 01560, "Environmental Protection’’.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Materials used for backfill shall conform to the
requirements of Section 02 22 00, ‘‘Grading,
Excavating and Backfilling’’.
PART 3 - EXECUTION
3.1 GENERAL
A. Backfill depressions caused by excavations,
demolition and removal with materials placed and
compacted in accordance with Section 02 20 00,
‘‘Grading, Exc avating and Backfilling’”.
1. Furnish additional materials required for
backfilling at no cost to the Authority.
3.2 REMOVAL OF PAVEMENTS, SIDEWALK, CURBS, AND
GUTTERS
A. Demolish pavement, sidewalks, curbs, and gutters
within demolition area shown to underside of
pavement and dispose of resulting debris.
B. Fill resulting excavations, holes, and depressions to
existing grade or alternative as shown using fill
material conforming to requirements of Section
02220, "Gra ding, Exc avating, and Ba ckfillin g".
C. Adequately drain resulting surfa c es.
D. Saw cut neat lines in c oncrete between demolition
and existing to remain.
3.3 SELECTIVE DEMOLITION
A. Perform Selective Demolition in accordance with
Section 01 73 10, ‘‘Cutting and Patching’, and
requirements specified herein.
B. Steel Structures:
1. Steel structures or steel portions of structures
shall be dismantled in sections of such
weight and dimensions which will permit
convenient handling and hauling.
SECTION 02 41 13.13 PAVING DEMOLITION
TRINITY METRO RE-BRANDING PROJECT MARCH 18, 2019 02 41 13.13 PAVING DEMOLITION - 3
2. Steel may be dismantled by flame cutting
or other methods approved by the
Contracting Offic er.
If existing steel structures scheduled to be
demolished are determined to be
contaminated with lead-based paint or
other hazardous materials, structures shall
be disposed of as scrap metal pursuant to
hazardous waste regulations including
40CFR, Part 260 through 263, (Subchapter
I).
3.4 DISPOSAL OF REMOVED MATERIALS AND DEBRIS
A. Remove debris resulting from demolition work and
dispose of it in accordance with applicable laws
and ordinances and as prescribed by authorities
having jurisdic tion.
B. Disposing by burying or burning of trash and
debris on the site will not be permitted.
C. Remove debris resulting from demolition work
from the site at frequent intervals so that its
presence will not delay the progress of the work
or cause hazardous conditions for workers and
the public.
D. Removed debris shall become the property of the
Contractor and shall be removed from the
Authority’s property and disposed of in a legal
manner with written permission of property owner
where such material is to be deposited. Loc
ation of disposal site and length of haul shall be
the Contractor's responsibility.
E. Provide copies of permits or licenses showing
compliance to state and local requirements for
disposing.
PART 4 - PAYMENT
4.1 GENERAL
A. The work described in this section will not be
measured but will be paid for at the lump sum
price for ‘‘Demolition’’.
END OF SECTION 02 41 13
SECTION 03 45 13 PRE-CAST ARCHITECTURAL CONCRETE
TRINTY METRO RE-BRANDING PROJECT MARCH 18, 2019 03 45 13 PRECAST ARCHITECTURAL CONCRETE - 1
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the fabrication and
installation of precast architectural concrete for
building walls, sound barriers, wall panels, and
other precast concrete building elements
designated as Precast Architectural Concrete.
1.2 REFERENCE STANDARDS
A. American Concrete Institute (ACI):
1. ACI SP-66 - ACI Detailing Manual
2. ACI 308.1 - Standard Specification for Curing
Concrete
3. ACI 318/318R - Building Code
Requirements for Structural Concrete (ACI
318) and Commentary (ACI 318R)
B. American Welding Society (AWS):
1. AWS D1.1/ D1.1M - Structural Welding Code -
Steel
2. AWS D1.4 - Structural Welding Code -
Reinforcing Steel
C. ASTM International (Formerly know n as American
Society for Testing and Materials) (ASTM):
1. ASTM A36/ A36M - Standard Specification for
Carbon Structural Steel.
2. ASTM A108 - Standard Specification for Steel
Bars, Carbon and Alloy, Cold-Finished.
3. ASTM A153/ A153M - Standard Specification
for Zinc Coating (Hot-Dip) on Iron and Steel
Hardware.
4. ASTM A167 - Standard Specification for
Stainless and Heat-Resisting Chromium-
Nickel Steel Plate, Sheet, and Strip
5. ASTM A193/ A193M - Standard Specification
for Alloy-Steel and Stainless Steel Bolting
Materials for High-Temperature Service
6. ASTM A307 - Standard Specification for
Carbon Steel Bolts and Studs, 60,000 PSI
Tensile Strength.
7. ASTM A666 - Standard Specification for
Annealed or Cold-Worked Austenitic
Stainless Steel Sheet, Strip, Plate, and Flat Bar
8. ASTM A884/ A884M - Standard Specification
for Epoxy-Coated Steel Wire and Welded
Wire Fabric for Reinforcement
9. ASTM C33 - Standard Specification for
Concrete Aggregates
10. ASTM C94 - Standard Specification for Read
y-Mixed Concrete
11. ASTM C260 - Standard Specification for Air-
Entraining Admixtures for Concrete
12. ASTM C494/C494M - Standard Specification for
Chemical Admixtures for Concrete
13. ASTM C618 - Standard Specification for Coal
Fly Ash and Raw or Calcined Natural Pozzolan for Use in Concrete
14. ASTM C979 - Standard Specification for
Pigments for Integrally Colored Concrete
D. Concrete Reinforcing Steel Institute (CRSI):
1. CRSI DA4 - Manual of Standard Practice
E. Precast/Prestressed Concrete Institute (PCI):
1. PCI/ CONCRT MNL-116 - Manual for Quality
Control for Plants and Production of Precast
and Prestressed Concrete Products
2. PCI/ CONCRT MNL-117 - Manual for Quality
Control for Plants and Production of
Architectural PreCast Concrete Products
3. PCI/ CONCRT MNL-119 - Drafting Handbook -
Precast and Prestressed Concrete
4. PCI/ CONCRT MNL-122 - Architectural
Precast Concrete
1.3 SUBMITTALS
A. Shop Drawings:
1. Prepare drawings in accordance with PCI/
CONCRETE MNL-119, ACI SP66 and CRSI
DA4. Take and include field verified
SECTION 03 45 13 PRE-CAST ARCHITECTURAL CONCRETE
TRINTY METRO RE-BRANDING PROJECT MARCH 18, 2019 03 45 13 PRECAST ARCHITECTURAL CONCRETE - 2
dimensions, details of form fabrication,
profiles, joints, reinforcing steel, clips,
anchors, inserts, reglets, lifting devices,
openings, electrical and structural
embedded items, connection to other work
and placement, and erection sequence.
Shop drawings shall be prepared, sealed
and signed by a Professional Engineer
licensed in the state of Texas.
2. Prior to installation of units, submit schedule
indicating sequence of installation, joints,
support and bracing systems, and anchoring
system.
3. Design Calculations: Submit complete
calculations for the design of precast units
and precast connections 60 days prior to start
of precast fabrication. Do not proceed with
fabrication of units until notified in writing that
the Contracting Officer has completed review
of calculations and approved the submittal.
4. Design mix: Submit concrete mix to comply
with product requirement of this section: Part
2 - PRODUCTS.
A. Product Data: Submit manufacturer’s product
data and specifications, with application and
installation instructions for manufactured materials
and products. Include concrete mix reports,
material certificates and laboratory test reports as
specified in Section 03300, "Cast-In-Place
Concrete".
B. Samples:
1. Panels representing color, texture and
general finish of test units and production
panels, each 12 inches square by 1-1/2
inches thick: Submit two samples prior to
fabrication.
2. Gasket and flashing materials proposed for
use: Submit two, each 12 inches long.
C. Job Mock-Up: After acceptance of material
samples, construct full-size sample of each
required architectural precast concrete unit for
Contracting Officer’s inspection at production
plant or on site prior to start of installation work.
Include representative items encountered in work,
per Contracting Officer’s directive. Cast, finish,
cure, and erect job mock-up panel in same
manner as will be employed in work. Acceptable
full-size samples may be incorporated in job
installation.
1.4 QUALITY ASSURANCE
A. Qualifications:
1. Fabricator Qualifications: Firms which have a
minimum of 5 years successful experience in the
fabrication of Architectural Precast Concrete
units, similar to units required for this project, will
be acceptable. Fabricator must have sufficient
production capacity to produce, transport, and
deliver required units without causing delay in
the work.
2. Qualifications of Erector: Firms which have a
minimum of 2 years successful experience in
the erection of Architectural Precast Concrete
units, similar to units required for this project,
will be acceptable.
B. Certifications:
1. Fire-Resistance Rated Precast Units: Where
precast concrete units are shown or scheduled
as requiring fire-resistance classification,
provide units tested and listed by UL in "Fire
Resistance Directory", or with each unit bearing
UL label and marking.
2. Certificate of Conformance: Provide written
certification that all material, shipped or used
and shown on invoices for this project,
including chemical test results for mills, meets
the contract requirements.
3. Concrete Testing: Requirements for testing
laboratories, and sampling and testing to
demonstrate compliance with specified
properties, are as specified in Section 03300,
"Cast-In-Place Concrete", and Section 01450,
"Quality Control".
4. Precast Unit Design: The precast units have
been proportioned to resist in-place service
loading conditions only. Using the services of a
Professional Engineer, licensed in the State of
Texas and experienced in providing
engineering services that resulted in
successful installation of precast concrete units
similar in material, design and extent as
required by this Project, analyze the units for
stresses resulting from fabrication, handling,
shipping, storage, erection, connection to the
supporting structure and temperature
changes, and select concrete strength,
reinforcement, and lifting devices and
SECTION 03 45 13 ARCHITECTURAL PRE-CAST CONCRETE
TRINTY METRO RE-BRANDING PROJECT MARCH 18, 2019 03 45 13 PRECAST ARCHITECTURAL CONCRETE - 3
procedures necessary to provide precast units
conforming to requirements shown and
specified. Maintain general design concept
shown without increasing or decreasing sizes
of members or altering profiles and
alignment shown. Provide complete design
calculations and drawings prepared, sealed
and signed by the Professional Engineer.
5. Precast Connections: Design Modifications to
connection configurations shown may be
made only as necessary to meet field
conditions and to ensure proper fitting of the
work, and only as acceptable to Contracting
Officer. Precast connections have been
shown on the drawings indicate general types
acceptable and locations of dimensions,
details of form fabrication, profiles, joints,
reinforcing steel, clips, anchors, inserts,
reglets, lifting devices, openings, electrical
and structural embedded items, connection
to other work and placement, and erection
sequence. Shop drawings shall be prepared,
sealed and signed by a Professional Engineer
licensed in the state of Texas.
6. Prior to installation of units, submit schedule
indicating sequence of installation, joints, support
and bracing systems, and anchoring system.
7. Design Calculations: Submit complete
calculations for the design of precast units and
precast connections 60 days prior to start of
precast fabrication. Do not proceed with
fabrication of units until notified in writing that the
Contracting Officer has completed review of
calculations and approved the submittal.
8. Design mix: Submit concrete mix to comply with
product requirement of this section: Part 2 -
PRODUCTS.
D. Product Data: Submit manufacturer’s product data
and specifications, with application and installation
instructions for manufactured materials and
products. Include concrete mix reports, material
certificates and laboratory test reports as specified
in Section 03300, "Cast-In-Place Concrete".
E. Samples:
1. Panels representing color, texture and general
finish of test units and production panels, each
12 inches square by 1-1/2 inches thick:
Submit two samples prior to fabrication.
2. Gasket and flashing materials proposed for use:
Submit two, each 12 inches long.
F. Job Mock-Up: After acceptance of material
samples, construct full-size sample of each required
architectural precast concrete unit for Contracting
Officer’s inspection at production plant or on site