Activity ID Activity Name Original Duration % Complete Remaining Duration Start Finish Total Float SCIENCE / ENGINEERING & TECHNOLOGY Milestones M-01042.0 Notice To Proceed 0 100% 0 09-Aug-18 A M-01043.0 Site Preconstruction Meeting 0 100% 0 09-Aug-18 A M-45980.0 Contract Substantial Completion (605 Cal Days) 0 0% 0 16-Apr-20* -9 M-45990.0 Contract Completion (695 Cal Days) 0 0% 0 15-Jul-20* -8 Impacts & Delays SP-31290 Lynnwood Plan Review for Mech Yard Ftg Changes 5 100% 0 16-Nov-01 A 21-Nov-18 A SP-31270 SWPPP / Public Works Pre-con 40 100% 0 09-Aug-18 A 17-Sep-18 A SP-31280 RFI 53 - Unforeseen Utilities in Bildg Footprint 10 100% 0 26-Oct-18 A 07-Nov-18 A SP-31300 FA 18-PUD Delay & EdCC Coordinaton for SQL power 17 100% 0 14-Dec-18 A 29-Dec-18 A SP-31310 FA 16 - Revised Relocation of Generator/LP Tank 19 100% 0 17-Dec-18 A 03-Jan-19 A SP-31320 FA 14 - Revised Waterproofing at Utility Tunnel 7 100% 0 19-Dec-18 A 10-Jan-19 A SP-31340 PSE Delay to Deactivate Existing Gas Service Line 20 100% 0 21-Dec-18 A 07-Jan-19 A SP-31330 FA 10 - Kiln Yard Gas Service 7 100% 0 28-Dec-18 A 02-Jan-19 A SP-31350 FA 20 - Add SS MH #1A 5 100% 0 14-Jan-19 A 21-Jan-19 A SP-31360 FA 21 - Unforeseen Concrete under BF 7 1 100% 0 15-Jan-19 A 15-Jan-19 A SP-31370 Unusually Severe Weather Delay 14 100% 0 04-Feb-19 A 17-Feb-19 A SP-31380 ASI 30 - Updates to ECR 6 100% 0 22-Mar-19 A 27-Mar-19 A SP-31390 FA 35 - AS 30.1 Updates to ECR 6 100% 0 27-Mar-19 A 01-Apr-19 A Permits EL-26000.P Electrical Permit 20 100% 0 09-Aug-18 A 27-Aug-18 A MC-23000.P Mechanical Permit 20 100% 0 09-Aug-18 A 27-Aug-18 A PL-22000.P Plumbing Permit 20 100% 0 09-Aug-18 A 27-Aug-18 A DE-02411.P Bridge Demolition Permit 50 100% 0 13-Aug-18 A 28-Sep-18 A FT-01100.P Fuel Tank Permit 40 100% 0 30-Aug-18 A 15-Oct-18 A GN-26335.P Elec Generator Permit 20 100% 0 04-Oct-18 A 15-Feb-19 A Procurement Prepare & Submit 03202.A SUBMIT - Reinforcing Steel - SET 45 100% 0 09-Aug-18 A 18-Sep-18 A 03201.A SUBMIT - Reinforcing Steel - UT 10 100% 0 09-Aug-18 A 27-Aug-18 A 04211.A SUBMIT - Brick 45 100% 0 04-Sep-18 A 21-Sep-18 A 08111.A SUBMIT - Hollow Metal 50 100% 0 06-Sep-18 A 05-Nov-18 A 08140.A SUBMIT - Wood Doors 60 100% 0 06-Sep-18 A 05-Nov-18 A 03300.A SUBMIT - Concrete Mix Designs 10 100% 0 10-Sep-18 A 17-Sep-18 A 22050.A SUBMIT - Plumbing Piping 15 100% 0 10-Sep-18 A 21-Sep-18 A 23311.A SUBMIT - HVAC Ductwork 25 100% 0 10-Sep-18 A 16-Oct-18 A 05120.A SUBMIT - Structural Steel 35 100% 0 17-Sep-18 A 12-Nov-18 A 33051.A SUBMIT - Storm Drainage 40 100% 0 17-Sep-18 A 05-Oct-18 A 08710.A SUBMIT - Finish Hardware 55 100% 0 18-Sep-18 A 05-Nov-18 A 07111.A SUBMIT - Bituminous Dampproofing 50 100% 0 01-Oct-18 A 21-Nov-18 A Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep r 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020 15-Jul-20, S 15-Jul-20, M Notice To Proceed Site Preconstruction Meeting Contract Substantial Comp Contract Co 01-Apr-19 A, Impacts & Delays Lynnwood Plan Review for Mech Yard Ftg Changes SWPPP / Public Works Pre-con RFI 53 - Unforeseen Utilities in Bildg Footprint FA 18-PUD Delay & EdCC Coordinaton for SQL power FA 16 - Revised Relocation of Generator/LP Tank FA 14 - Revised Waterproofing at Utility Tunnel PSE Delay to Deactivate Existing Gas Service Line FA 10 - Kiln Yard Gas Service FA 20 - Add SS MH #1A FA 21 - Unforeseen Concrete under BF 7 Unusually Severe Weather Delay ASI 30 - Updates to ECR FA 35 - AS 30.1 Updates to ECR 15-Feb-19 A, Permits Electrical Permit Mechanical Permit Plumbing Permit Bridge Demolition Permit Fuel Tank Permit Elec Generator Permit 24-Feb-20, Procurement 19-Jul-19, Prepare & Submit SUBMIT - Reinforcing Steel - SET SUBMIT - Reinforcing Steel - UT SUBMIT - Brick SUBMIT - Hollow Metal SUBMIT - Wood Doors SUBMIT - Concrete Mix Designs SUBMIT - Plumbing Piping SUBMIT - HVAC Ductwork SUBMIT - Structural Steel SUBMIT - Storm Drainage SUBMIT - Finish Hardware SUBMIT - Bituminous Dampproofing SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19 Actual Wor k Remaining Work Critical Remaining Work Milestone Summary June 2019 Update 1
25

SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Jul 20, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SCIENCE / ESCIENCE / ENGINEERING & TECHNOLOGYSCIENCE / ENGINEERING & TECHNOLOGYSCIENCE / ENGINEERING & TECHNOLOGYSCIENCE / ENGINEERING & TECHNOLOGYSCIENCE / ENGINEERING & TECHNOLOGYSCIENCE / ENGINEERING & TECHNOLOGYSCIENCE / ENGINEERING & TECHNOLOGYMilestonesMilestonesMilestonesMilestonesMilestonesMilestonesMilestonesMilestonesM-01042.0 Notice To Proceed 0 100% 0 09-Aug-18 AM-01043.0 Site Preconstruction Meeting 0 100% 0 09-Aug-18 AM-45980.0 Contract Substantial Completion (605 Cal Days) 0 0% 0 16-Apr-20* -9M-45990.0 Contract Completion (695 Cal Days) 0 0% 0 15-Jul-20* -8

Impacts & DeImpacts & DelaysImpacts & DelaysImpacts & DelaysImpacts & DelaysImpacts & DelaysImpacts & DelaysImpacts & DelaysSP-31290 Lynnwood Plan Review for Mech Yard Ftg Changes 5 100% 0 16-Nov-01 A 21-Nov-18 ASP-31270 SWPPP / Public Works Pre-con 40 100% 0 09-Aug-18 A 17-Sep-18 ASP-31280 RFI 53 - Unforeseen Utilities in Bildg Footprint 10 100% 0 26-Oct-18 A 07-Nov-18 ASP-31300 FA 18-PUD Delay & EdCC Coordinaton for SQL power 17 100% 0 14-Dec-18 A 29-Dec-18 ASP-31310 FA 16 - Revised Relocation of Generator/LP Tank 19 100% 0 17-Dec-18 A 03-Jan-19 ASP-31320 FA 14 - Revised Waterproofing at Utility Tunnel 7 100% 0 19-Dec-18 A 10-Jan-19 ASP-31340 PSE Delay to Deactivate Existing Gas Service Line 20 100% 0 21-Dec-18 A 07-Jan-19 ASP-31330 FA 10 - Kiln Yard Gas Service 7 100% 0 28-Dec-18 A 02-Jan-19 ASP-31350 FA 20 - Add SS MH #1A 5 100% 0 14-Jan-19 A 21-Jan-19 ASP-31360 FA 21 - Unforeseen Concrete under BF 7 1 100% 0 15-Jan-19 A 15-Jan-19 ASP-31370 Unusually Severe Weather Delay 14 100% 0 04-Feb-19 A 17-Feb-19 ASP-31380 ASI 30 - Updates to ECR 6 100% 0 22-Mar-19 A 27-Mar-19 ASP-31390 FA 35 - AS 30.1 Updates to ECR 6 100% 0 27-Mar-19 A 01-Apr-19 A

PermitsPermitsPermitsPermitsPermitsPermitsPermitsPermitsEL-26000.P Electrical Permit 20 100% 0 09-Aug-18 A 27-Aug-18 AMC-23000.P Mechanical Permit 20 100% 0 09-Aug-18 A 27-Aug-18 APL-22000.P Plumbing Permit 20 100% 0 09-Aug-18 A 27-Aug-18 ADE-02411.P Bridge Demolition Permit 50 100% 0 13-Aug-18 A 28-Sep-18 AFT-01100.P Fuel Tank Permit 40 100% 0 30-Aug-18 A 15-Oct-18 AGN-26335.P Elec Generator Permit 20 100% 0 04-Oct-18 A 15-Feb-19 A

ProcuremeProcurementProcurementProcurementProcurementProcurementProcurementProcurementPrepare & SuPrepare & SubmitPrepare & SubmitPrepare & SubmitPrepare & SubmitPrepare & SubmitPrepare & SubmitPrepare & Submit03202.A SUBMIT - Reinforcing Steel - SET 45 100% 0 09-Aug-18 A 18-Sep-18 A03201.A SUBMIT - Reinforcing Steel - UT 10 100% 0 09-Aug-18 A 27-Aug-18 A04211.A SUBMIT - Brick 45 100% 0 04-Sep-18 A 21-Sep-18 A08111.A SUBMIT - Hollow Metal 50 100% 0 06-Sep-18 A 05-Nov-18 A08140.A SUBMIT - Wood Doors 60 100% 0 06-Sep-18 A 05-Nov-18 A03300.A SUBMIT - Concrete Mix Designs 10 100% 0 10-Sep-18 A 17-Sep-18 A22050.A SUBMIT - Plumbing Piping 15 100% 0 10-Sep-18 A 21-Sep-18 A23311.A SUBMIT - HVAC Ductwork 25 100% 0 10-Sep-18 A 16-Oct-18 A05120.A SUBMIT - Structural Steel 35 100% 0 17-Sep-18 A 12-Nov-18 A33051.A SUBMIT - Storm Drainage 40 100% 0 17-Sep-18 A 05-Oct-18 A08710.A SUBMIT - Finish Hardware 55 100% 0 18-Sep-18 A 05-Nov-18 A07111.A SUBMIT - Bituminous Dampproofing 50 100% 0 01-Oct-18 A 21-Nov-18 A

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

15-Jul-20, S

15-Jul-20, M

Notice To ProceedSite Preconstruction Meeting

Contract Substantial CompContract Co

01-Apr-19 A, Impacts & Delays

Lynnwood Plan Review for Mech Yard Ftg ChangesSWPPP / Public Works Pre-con

RFI 53 - Unforeseen Utilities in Bildg FootprintFA 18-PUD Delay & EdCC Coordinaton for SQL powerFA 16 - Revised Relocation of Generator/LP Tank

FA 14 - Revised Waterproofing at Utility TunnelPSE Delay to Deactivate Existing Gas Service Line

FA 10 - Kiln Yard Gas ServiceFA 20 - Add SS MH #1A

FA 21 - Unforeseen Concrete under BF 7Unusually Severe Weather Delay

ASI 30 - Updates to ECRFA 35 - AS 30.1 Updates to ECR

15-Feb-19 A, Permits

Electrical PermitMechanical PermitPlumbing Permit

Bridge Demolition PermitFuel Tank Permit

Elec Generator Permit24-Feb-20, Procurement

19-Jul-19, Prepare & Submit

SUBMIT - Reinforcing Steel - SETSUBMIT - Reinforcing Steel - UT

SUBMIT - BrickSUBMIT - Hollow MetalSUBMIT - Wood Doors

SUBMIT - Concrete Mix DesignsSUBMIT - Plumbing Piping

SUBMIT - HVAC DuctworkSUBMIT - Structural Steel

SUBMIT - Storm DrainageSUBMIT - Finish Hardware

SUBMIT - Bituminous Dampproofing

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 1

Page 2: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

21100.A SUBMIT - Fire Protection 15 100% 0 01-Oct-18 A 13-May-19 A22330.A SUBMIT - Water Heaters 45 100% 0 01-Oct-18 A 16-Oct-18 A22400.A SUBMIT - Plumbing Fixtures 60 100% 0 01-Oct-18 A 16-Oct-18 A23371.A SUBMIT - HVAC Grills & Diffusers 45 100% 0 01-Oct-18 A 16-Oct-18 A23732.A SUBMIT - AHU Hvac Equipment 45 100% 0 01-Oct-18 A 18-Jan-19 A26241.A SUBMIT - Elec Panelboards 10 100% 0 01-Oct-18 A 06-Nov-18 A26500.A SUBMIT - Elec Lighting Fixtures 50 100% 0 01-Oct-18 A 16-Oct-18 A27010.A SUBMIT - Comminications Mat'l 30 100% 0 01-Oct-18 A 16-Nov-18 A23211.A SUBMIT - Hydronic Piping 20 100% 0 01-Oct-18 A 16-Oct-18 A26100.A SUBMIT - Elec Mat'l 15 100% 0 08-Oct-18 A 05-Nov-18 A23655.A SUBMIT - Coordination Drawings 20 100% 0 08-Oct-18 A 26-Apr-19 A05510.A SUBMIT - Steel Stairs 35 100% 0 30-Oct-18 A 05-Nov-18 A05310.A SUBMIT - Metal Deck 5 100% 0 30-Oct-18 A 12-Nov-18 A14212.A SUBMIT - Elevator Equipment 40 100% 0 01-Nov-18 A 07-Jan-19 A03450.A SUBMIT - Precast Architectural Conc 45 100% 0 02-Jan-19 A 14-Jan-19 A07421.A SUBMIT - Metal Wall Panels 40 100% 0 02-Jan-19 A 28-Jan-19 A08321.A SUBMIT - Alum Framed Glass Doors 35 100% 0 02-Jan-19 A 25-Jan-19 A11530.A SUBMIT - Laboratory Equipment 50 100% 0 02-Jan-19 A 14-Jan-19 A11532.A SUBMIT - Lab Fume Hoods 40 100% 0 02-Jan-19 A 14-Jan-19 A08411.A SUBMIT - Aluminum Windows & Storefront 45 100% 0 07-Jan-19 A 25-Jan-19 A07812.A SUBMIT - Intumescent Fire Proofing 40 100% 0 10-Jan-19 A 16-Apr-19 A07271.A SUBMIT - Water & Air Barriers 45 100% 0 14-Jan-19 A 12-Apr-19 A05520.A SUBMIT - Steel Handrails 50 100% 0 28-Jan-19 A 02-May-19 A06411.A SUBMIT - Architectural Casework 55 100% 0 28-Jan-19 A 07-Feb-19 A09510.A SUBMIT - Acoustical Clg 60 100% 0 28-Jan-19 A 18-Jun-19 A09650.A SUBMIT - Resilient Tile 50 100% 0 28-Jan-19 A 11-Jun-19 A28310.A SUBMIT - Fire Alarm Mat'l 40 100% 0 28-Jan-19 A 29-May-19 A07181.A SUBMIT - Pedestrian Traffic Coating 55 100% 0 01-Mar-19 A 03-May-19 A08611.A SUBMIT - Overhead Sloped Glazing 45 100% 0 01-Mar-19 A 03-May-19 A09681.A SUBMIT - Carpet Tile 55 100% 0 01-Mar-19 A 11-Jun-19 A10110.A SUBMIT - Visual Display Surfaces 50 100% 0 01-Mar-19 A 03-May-19 A26560.A SUBMIT - Site Lighting 45 100% 0 01-Mar-19 A 02-May-19 A09211.A SUBMIT - Gypsum Drywall 50 100% 0 04-Mar-19 A 12-Apr-19 A09301.A SUBMIT - Ceramic Tile 45 100% 0 04-Mar-19 A 11-Jun-19 A09910.A SUBMIT - Painting 55 100% 0 04-Mar-19 A 03-May-19 A07540.A SUBMIT - Thermoplastic Roofing 50 100% 0 11-Mar-19 A 06-May-19 A10211.A SUBMIT - Toliet Partitions 60 100% 0 11-Mar-19 A 03-May-19 A10281.A SUBMIT - Toliet Accessoies 50 100% 0 22-Mar-19 A 03-May-19 A11123.A SUBMIT - Lift Arm Parking Gates 55 72.73% 15 08-Apr-19 A 19-Jul-19 2

Review & AppReview & ApproveReview & ApproveReview & ApproveReview & ApproveReview & ApproveReview & ApproveReview & Approve03201.B APPROVE - Reinforcing Steel - UT 10 100% 0 08-Sep-18 A 14-Sep-18 A03202.B APPROVE - Reinforcing Steel - SET 10 100% 0 18-Sep-18 A 01-Nov-18 A03300.B APPROVE - Concrete Mix Designs 10 100% 0 18-Sep-18 A 24-Sep-18 A22050.B APPROVE - Plumbing Piping 10 100% 0 21-Sep-18 A 01-Oct-18 A

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

SUBMIT - Fire ProtectionSUBMIT - Water HeatersSUBMIT - Plumbing FixturesSUBMIT - HVAC Grills & Diffusers

SUBMIT - AHU Hvac EquipmentSUBMIT - Elec Panelboards

SUBMIT - Elec Lighting FixturesSUBMIT - Comminications Mat'l

SUBMIT - Hydronic PipingSUBMIT - Elec Mat'l

SUBMIT - Coordination DrawingsSUBMIT - Steel StairsSUBMIT - Metal Deck

SUBMIT - Elevator EquipmentSUBMIT - Precast Architectural Conc

SUBMIT - Metal Wall PanelsSUBMIT - Alum Framed Glass Doors

SUBMIT - Laboratory EquipmentSUBMIT - Lab Fume Hoods

SUBMIT - Aluminum Windows & StorefrontSUBMIT - Intumescent Fire ProofingSUBMIT - Water & Air Barriers

SUBMIT - Steel HandrailsSUBMIT - Architectural Casework

SUBMIT - Acoustical ClgSUBMIT - Resilient Tile

SUBMIT - Fire Alarm Mat'lSUBMIT - Pedestrian Traffic CoatingSUBMIT - Overhead Sloped Glazing

SUBMIT - Carpet TileSUBMIT - Visual Display SurfacesSUBMIT - Site Lighting

SUBMIT - Gypsum DrywallSUBMIT - Ceramic Tile

SUBMIT - PaintingSUBMIT - Thermoplastic RoofingSUBMIT - Toliet PartitionsSUBMIT - Toliet Accessoies

SUBMIT - Lift Arm Parking Gates09-Dec-19, Review & Approve

APPROVE - Reinforcing Steel - UTAPPROVE - Reinforcing Steel - SET

APPROVE - Concrete Mix DesignsAPPROVE - Plumbing Piping

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 2

Page 3: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

04211.B APPROVE - Brick 10 100% 0 24-Sep-18 A 27-Sep-18 A33051.B APPROVE - Storm Drainage 10 100% 0 05-Oct-18 A 19-Oct-18 A22330.B APPROVE - Water Heaters 10 100% 0 17-Oct-18 A 26-Nov-18 A22400.B APPROVE - Plumbing Fixtures 10 100% 0 17-Oct-18 A 26-Nov-18 A23311.B APPROVE - HVAC Ductwork 10 100% 0 17-Oct-18 A 19-Nov-18 A23371.B APPROVE - HVAC Grills & Diffusers 10 100% 0 17-Oct-18 A 19-Nov-18 A26500.B APPROVE - Lighting Fixtures 10 100% 0 17-Oct-18 A 20-Dec-18 A23211.B APPROVE - Hydronic Piping 15 100% 0 17-Oct-18 A 30-Oct-18 A05510.B APPROVE - Steel Stairs 10 100% 0 06-Nov-18 A 14-Jan-19 A08111.B APPROVE - Hollow Metal 10 100% 0 06-Nov-18 A 13-Nov-18 A08140.B APPROVE - Wood Doors 10 100% 0 06-Nov-18 A 13-Nov-18 A08710.B APPROVE - Finish Hardware 10 100% 0 06-Nov-18 A 06-May-19 A26100.B APPROVE - Elec Mat'l 10 100% 0 06-Nov-18 A 13-Nov-18 A26241.B APPROVE - ELEC Panelboards 10 100% 0 07-Nov-18 A 16-Jan-19 A05120.B APPROVE - Structural Steel 10 100% 0 13-Nov-18 A 21-Dec-18 A05310.B APPROVE - Metal Deck 10 100% 0 13-Nov-18 A 21-Dec-18 A27010.B APPROVE - Communication Mat'l 10 100% 0 19-Nov-18 A 12-Dec-18 A07111.B APPROVE - Bituminous Dampproofing 10 100% 0 21-Nov-18 A 21-Nov-18 A14212.B APPROVE - Elevator Equipment 10 100% 0 08-Jan-19 A 11-Feb-19 A03450.B APPROVE - Precast Architectural Conc 10 100% 0 15-Jan-19 A 28-Feb-19 A11530.B APPROVE - Laboratory Equipment 10 100% 0 15-Jan-19 A 01-Feb-19 A11532.B APPROVE - Lab Fume Hoods 10 100% 0 15-Jan-19 A 04-Feb-19 A23732.B APPROVE - AHU Hvac Equipment 10 100% 0 18-Jan-19 A 30-Jan-19 A08321.B APPROVE - Alum Framed Glass Doors 10 100% 0 28-Jan-19 A 17-Apr-19 A08411.B APPROVE - Aluminum Windows 10 100% 0 28-Jan-19 A 17-Apr-19 A07421.B APPROVE - Metal Wall Panels 10 100% 0 29-Jan-19 A 01-Feb-19 A06411.B APPROVE - Architectural Casework 10 100% 0 08-Feb-19 A 21-Feb-19 A07760.B APPROVE - Water & Air Barriers 10 100% 0 15-Apr-19 A 26-Apr-19 A09211.B APPROVE - Gypsum Drywall 10 100% 0 15-Apr-19 A 16-Apr-19 A07812.B APPROVE - Intumescent Fire Proofing 10 100% 0 17-Apr-19 A 24-Apr-19 A05520.B APPROVE - Steel Handrails 10 100% 0 03-May-19 A 04-Jun-19 A07181.B APPROVE - Pedestrian Traffic Coating 10 100% 0 03-May-19 A 06-May-19 A26560.B APPROVE - Site Lighting 10 100% 0 03-May-19 A 30-May-19 A07535.B APPROVE - Thermoplastic Roofing 10 100% 0 06-May-19 A 17-May-19 A08611.B APPROVE - Overhead Sloped Glazing 10 90% 1 06-May-19 A 01-Jul-19 -109900.B APPROVE - Painting 10 100% 0 06-May-19 A 27-Jun-19 A10110.B APPROVE - Visual Display Surfaces 10 90% 1 06-May-19 A 01-Jul-19 7510211.B APPROVE - Toliet Partitions 10 100% 0 06-May-19 A 09-May-19 A10281.B APPROVE - Toliet Accessoies 10 100% 0 06-May-19 A 09-May-19 A21100.B APPROVE - Fire Protection 10 100% 0 14-May-19 A 27-Jun-19 A23655.B APPROVE - Coordination Drawings 10 100% 0 14-May-19 A 17-Jun-19 A28310.B APPROVE - Fire Alarm Mat'l 10 100% 0 30-May-19 A 05-Jun-19 A09301.B APPROVE - Ceramic Tile 10 90% 1 12-Jun-19 A 01-Jul-19 4109650.B APPROVE - Resilient Tile 10 90% 1 12-Jun-19 A 01-Jul-19 43

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

APPROVE - BrickAPPROVE - Storm Drainage

APPROVE - Water HeatersAPPROVE - Plumbing Fixtures

APPROVE - HVAC DuctworkAPPROVE - HVAC Grills & Diffusers

APPROVE - Lighting FixturesAPPROVE - Hydronic Piping

APPROVE - Steel StairsAPPROVE - Hollow MetalAPPROVE - Wood Doors

APPROVE - Finish HardwareAPPROVE - Elec Mat'l

APPROVE - ELEC PanelboardsAPPROVE - Structural SteelAPPROVE - Metal Deck

APPROVE - Communication Mat'lAPPROVE - Bituminous Dampproofing

APPROVE - Elevator EquipmentAPPROVE - Precast Architectural Conc

APPROVE - Laboratory EquipmentAPPROVE - Lab Fume Hoods

APPROVE - AHU Hvac EquipmentAPPROVE - Alum Framed Glass DoorsAPPROVE - Aluminum Windows

APPROVE - Metal Wall PanelsAPPROVE - Architectural Casework

APPROVE - Water & Air BarriersAPPROVE - Gypsum Drywall

APPROVE - Intumescent Fire ProofingAPPROVE - Steel Handrails

APPROVE - Pedestrian Traffic CoatingAPPROVE - Site Lighting

APPROVE - Thermoplastic RoofingAPPROVE - Overhead Sloped Glazing

APPROVE - PaintingAPPROVE - Visual Display Surfaces

APPROVE - Toliet PartitionsAPPROVE - Toliet Accessoies

APPROVE - Fire ProtectionAPPROVE - Coordination Drawings

APPROVE - Fire Alarm Mat'lAPPROVE - Ceramic TileAPPROVE - Resilient Tile

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 3

Page 4: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

09681.B APPROVE - Carpet Tile 10 90% 1 12-Jun-19 A 01-Jul-19 7209510.B APPROVE - Acoustical Clg 10 100% 0 19-Jun-19 A 27-Jun-19 A11123.B APPROVE - Lift Arm Parking Gates 10 0% 10 26-Nov-19 09-Dec-19 2

Fab & DeliverFab & DeliverFab & DeliverFab & DeliverFab & DeliverFab & DeliverFab & DeliverFab & Deliver03201.D FAB & DELIVER - Reinforcing Steel - UT 8 100% 0 17-Sep-18 A 09-Oct-18 A33051.D FAB & DELIVER - Storm Drainage 20 100% 0 22-Oct-18 A 19-Nov-18 A03202.D FAB & DELIVER - Reinforcing Steel - SET 40 100% 0 01-Nov-18 A 20-Dec-18 A23211.D FAB & DELIVER - Hydronic Piping 20 100% 0 01-Nov-18 A 09-Nov-18 A22050.D FAB & DELIVER - Plumbing Piping 15 100% 0 05-Nov-18 A 09-Nov-18 A26100.D FAB & DELIVER - Elec Mat'l 15 100% 0 14-Nov-18 A 30-Nov-18 A07111.D FAB & DELIVER - Bituminous Dampproofing 15 100% 0 26-Nov-18 A 14-Dec-18 A27010.D FAB & DELIVER - Communication Mat'l 8 100% 0 10-Dec-18 A 14-Dec-18 A05120.D FAB & DELIVER - Structural Steel 45 100% 0 24-Dec-18 A 01-Apr-19 A05310.D FAB & DELIVER - Metal Deck 40 100% 0 24-Dec-18 A 01-Apr-19 A05510.D FAB & DELIVER - Steel Stairs 60 100% 0 15-Jan-19 A 01-Apr-19 A23732.D FAB & DELIVER - AHU HVAC Equipment 60 98.33% 1 22-Mar-19 A 01-Jul-19 408110.D FAB & DELIVER - Hollow Metal Frames - 1st Flr 40 100% 0 08-Apr-19 A 24-May-19 A26241.D FAB & DELIVER - ELEC Panelboards 35 85.71% 5 15-Apr-19 A 05-Jul-19 15004211.D FAB & DELIVER - Brick 30 96.67% 1 17-Apr-19 A 01-Jul-19 108411.D FAB & DELIVER - Aluminum Windows & Storefront 45 73.33% 12 18-Apr-19 A 16-Jul-19 007812.D FAB & DELIVER - Intumescent Fire Proofing 10 100% 0 01-May-19 A 14-May-19 A08110.D10 FAB & DELIVER - Hollow Metal Frames - 2nd Flr 40 100% 0 01-May-19 A 19-Jun-19 A07760.D FAB & DELIVER - Water & Air Barrier 20 100% 0 13-May-19 A 07-Jun-19 A23311.D FAB & DELIVER - HVAC Ductwork 35 85.71% 5 13-May-19 A 05-Jul-19 814212.D FAB & DELIVER - Elevator Equipment 80 41.25% 47 20-May-19 A 03-Oct-19 -809211.D FAB & DELIVER - Gypsum Drywall 10 100% 0 27-May-19 A 03-Jun-19 A21100.D FAB & DELIVER - Fire Protection 25 100% 0 03-Jun-19 A 21-Jun-19 A07421.D FAB & DELIVER - Metal Wall Panels 30 50% 15 03-Jun-19 A 19-Jul-19 1007535.D FAB & DELIVER - Thermoplastic Roof 20 75% 5 03-Jun-19 A 05-Jul-19 1821102.D FAB & DELIVER - Fire Protection Mains 20 100% 0 03-Jun-19 A 24-Jun-19 A08110.D20 FAB & DELIVER - Hollow Metal Frames - 3rd Flr 40 75% 10 03-Jun-19 A 12-Jul-19 4928310.D FAB & DELIVER - Fire Alarm Mat'l 45 44.44% 25 06-Jun-19 A 02-Aug-19 022330.D FAB & DELIVER - Water Heaters 25 40% 15 14-Jun-19 A 19-Jul-19 903450.D FAB & DELIVER - Precast Architectural Conc 45 0% 45 01-Jul-19 30-Aug-19 7205520.D FAB & DELIVER - Steel Handrails 45 0% 45 01-Jul-19 30-Aug-19 4407181.D FAB & DELIVER - Pedestrian Traffic Coating 20 0% 20 01-Jul-19 26-Jul-19 16009910.D FAB & DELIVER - Paint 15 0% 15 01-Jul-19 19-Jul-19 5723371.D FAB & DELIVER - HVAC Grills & Diffusers 40 0% 40 01-Jul-19 23-Aug-19 4926500.D FAB & DELIVER - ELEC Lighting Fixtures 60 0% 60 01-Jul-19 23-Sep-19 2909301.D FAB & DELIVER - Ceramic Tile 40 0% 40 02-Jul-19 26-Aug-19 4109650.D FAB & DELIVER - Reslient Tile 55 0% 55 02-Jul-19 17-Sep-19 4308111.D FAB & DELIVER - Hollow Metal Doors - 1st Flr 40 0% 40 15-Jul-19 09-Sep-19 4208710.D FAB & DELIVER - Finish Hardware 80 0% 80 29-Jul-19 18-Nov-19 3608111.D10 FAB & DELIVER - Hollow Metal Doors - 2nd Flr 40 0% 40 29-Jul-19 20-Sep-19 43

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

APPROVE - Carpet TileAPPROVE - Acoustical Clg

APPROVE - Lift Arm Parking Gates24-Feb-20, Fab & Deliver

FAB & DELIVER - Reinforcing Steel - UTFAB & DELIVER - Storm Drainage

FAB & DELIVER - Reinforcing Steel - SETFAB & DELIVER - Hydronic PipingFAB & DELIVER - Plumbing Piping

FAB & DELIVER - Elec Mat'lFAB & DELIVER - Bituminous DampproofingFAB & DELIVER - Communication Mat'l

FAB & DELIVER - Structural SteelFAB & DELIVER - Metal DeckFAB & DELIVER - Steel Stairs

FAB & DELIVER - AHU HVAC EquipmentFAB & DELIVER - Hollow Metal Frames - 1st Flr

FAB & DELIVER - ELEC PanelboardsFAB & DELIVER - Brick

FAB & DELIVER - Aluminum Windows & StorefrontFAB & DELIVER - Intumescent Fire Proofing

FAB & DELIVER - Hollow Metal Frames - 2nd FlrFAB & DELIVER - Water & Air Barrier

FAB & DELIVER - HVAC DuctworkFAB & DELIVER - Elevator Equipment

FAB & DELIVER - Gypsum DrywallFAB & DELIVER - Fire Protection

FAB & DELIVER - Metal Wall PanelsFAB & DELIVER - Thermoplastic Roof

FAB & DELIVER - Fire Protection MainsFAB & DELIVER - Hollow Metal Frames - 3rd Flr

FAB & DELIVER - Fire Alarm Mat'lFAB & DELIVER - Water Heaters

FAB & DELIVER - Precast Architectural ConcFAB & DELIVER - Steel Handrails

FAB & DELIVER - Pedestrian Traffic CoatingFAB & DELIVER - Paint

FAB & DELIVER - HVAC Grills & DiffusersFAB & DELIVER - ELEC Lighting Fixtures

FAB & DELIVER - Ceramic TileFAB & DELIVER - Reslient Tile

FAB & DELIVER - Hollow Metal Doors - 1st FlrFAB & DELIVER - Finish Hardware

FAB & DELIVER - Hollow Metal Doors - 2nd Flr

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 4

Page 5: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

26560.D FAB & DELIVER - Site Lighting 50 2% 49 31-Jul-19 A 06-Sep-19 10608611.D FAB & DELIVER - Overhead Sloped Glazing 30 0% 30 06-Aug-19 17-Sep-19 -109681.D FAB & DELIVER - Carpet Tile 50 0% 50 06-Aug-19 15-Oct-19 7209510.D FAB & DELIVER - Acoustical Clg 60 0% 60 09-Aug-19 01-Nov-19 -508111.D20 FAB & DELIVER - Hollow Metal Doors - 3rd Flr 40 0% 40 12-Aug-19 04-Oct-19 4310110.D FAB & DELIVER - Visual Display Surfaces 45 0% 45 13-Aug-19 15-Oct-19 7508321.D FAB & DELIVER - Alum Framed Glass Doors 35 0% 35 22-Aug-19 10-Oct-19 3108140.D FAB & DELIVER - Wood Doors - 1st Flr 60 0% 60 26-Aug-19 18-Nov-19 -808140.D10 FAB & DELIVER - Wood Doors - 2nd Flr 60 0% 60 29-Aug-19 20-Nov-19 008140.D20 FAB & DELIVER - Wood Doors - 3rd Flr 60 0% 60 29-Aug-19 21-Nov-19 1022404.D FAB & DELIVER - Plumbing Fixtures 50 0% 50 24-Sep-19 02-Dec-19 1111532.D FAB & DELIVER - Lab Fume Hoods 30 0% 30 08-Oct-19 18-Nov-19 106411.D FAB & DELIVER - Architectural Casework 40 0% 40 15-Oct-19 09-Dec-19 -610281.D FAB & DELIVER - Toilet Accessories 45 0% 45 12-Nov-19 13-Jan-20 210211.D FAB & DELIVER - Toilet Partitions 40 0% 40 13-Nov-19 07-Jan-20 211530.D FAB & DELIVER - Laboratory Equipment 60 0% 60 03-Dec-19 24-Feb-20 -311123.D FAB & DELIVER - Lift Arm Parking Gates 40 0% 40 10-Dec-19 03-Feb-20 2

MobilizationMobilization & Site PreparationMobilization & Site PreparationMobilization & Site PreparationMobilization & Site PreparationMobilization & Site PreparationMobilization & Site PreparationMobilization & Site PreparationSP-01000 Mobilization 20 100% 0 13-Aug-18 A 07-Sep-18 ASP-01020 Temporary Facilities / Lay Down Areas 10 100% 0 22-Aug-18 A 07-Sep-18 ASP-01010 Site Layout / Locate Existing Utilties 5 100% 0 04-Sep-18 A 10-Sep-18 ASP-31250 Erosion Control / Silt Fence 10 100% 0 18-Sep-18 A 26-Sep-18 ASP-31251 Clearing / Site Demolition 10 100% 0 20-Sep-18 A 19-Oct-18 A

Hazmat RemHazmat RemovalHazmat RemovalHazmat RemovalHazmat RemovalHazmat RemovalHazmat RemovalHazmat RemovalAsbestos RemAsbestos RemovalAsbestos RemovalAsbestos RemovalAsbestos RemovalAsbestos RemovalAsbestos RemovalAsbestos RemovalA02411.0 Selective Demolition for Abatement 10 100% 0 04-Oct-18 A 12-Oct-18 AA02823.0 Asbestos Abatement - Insulation @ UT 3 100% 0 05-Nov-18 A 06-Nov-18 AA02820.0 Asbestos Abatement - CT-1 2 100% 0 31-Dec-18 A 02-Jan-19 AA02821.0 Asbestos Abatement - CT-2 2 100% 0 31-Dec-18 A 02-Jan-19 AA23007.0 HVAC Replace Hot Water Insulation @ UT Abatement 3 100% 0 24-Jan-19 A 20-Feb-19 AA02822.0 Asbestos Abatement @ Boilers 5 0% 5 15-Aug-19 21-Aug-19 64

Lead Paint ReLead Paint Removal @ CUPLead Paint Removal @ CUPLead Paint Removal @ CUPLead Paint Removal @ CUPLead Paint Removal @ CUPLead Paint Removal @ CUPLead Paint Removal @ CUPA28300.0 Lead Paint Removal @ CUP 20 100% 0 26-Dec-18 A 04-Jan-19 A

Fuel Tank RemFuel Tank RemovalFuel Tank RemovalFuel Tank RemovalFuel Tank RemovalFuel Tank RemovalFuel Tank RemovalFuel Tank RemovalSP-02410 Decommision 5000 Gal UST 4 100% 0 29-Oct-18 A 01-Nov-18 ASP-02411 Remove 5000 Gal UST 5 100% 0 12-Nov-18 A 13-Nov-18 ASP-31240 Remove Contaminated Soil 20 100% 0 13-Nov-18 A 13-Nov-18 ASP-31260 Replacement Fill 10 100% 0 12-Dec-18 A 12-Dec-18 A

Utility RelocUtility Relocation & Utility TunnelsUtility Relocation & Utility TunnelsUtility Relocation & Utility TunnelsUtility Relocation & Utility TunnelsUtility Relocation & Utility TunnelsUtility Relocation & Utility TunnelsUtility Relocation & Utility TunnelsGenerator & PGenerator & Power RelocationGenerator & Power RelocationGenerator & Power RelocationGenerator & Power RelocationGenerator & Power RelocationGenerator & Power RelocationGenerator & Power RelocationUT03305.0 Retaining Walls at Relocated Generator 12 100% 0 07-Nov-18 A 29-Nov-18 A

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

FAB & DELIVER - Site LightingFAB & DELIVER - Overhead Sloped Glazing

FAB & DELIVER - Carpet TileFAB & DELIVER - Acoustical Clg

FAB & DELIVER - Hollow Metal Doors - 3rd FlrFAB & DELIVER - Visual Display Surfaces

FAB & DELIVER - Alum Framed Glass DoorsFAB & DELIVER - Wood Doors - 1st FlrFAB & DELIVER - Wood Doors - 2nd FlrFAB & DELIVER - Wood Doors - 3rd Flr

FAB & DELIVER - Plumbing FixturesFAB & DELIVER - Lab Fume Hoods

FAB & DELIVER - Architectural CaseworkFAB & DELIVER - Toilet Accessories

FAB & DELIVER - Toilet PartitionsFAB & DELIVER - Laboratory Equip

FAB & DELIVER - Lift Arm Parking Gate19-Oct-18 A, Mobilization & Site Preparation

MobilizationTemporary Facilities / Lay Down AreasSite Layout / Locate Existing Utilties

Erosion Control / Silt FenceClearing / Site Demolition

21-Aug-19, Hazmat Removal

21-Aug-19, Asbestos Removal

Selective Demolition for AbatementAsbestos Abatement - Insulation @ UT

Asbestos Abatement - CT-1Asbestos Abatement - CT-2

HVAC Replace Hot Water Insulation @ UT AbatementAsbestos Abatement @ Boilers

04-Jan-19 A, Lead Paint Removal @ CUP

Lead Paint Removal @ CUP12-Dec-18 A, Fuel Tank Removal

Decommision 5000 Gal USTRemove 5000 Gal USTRemove Contaminated Soil

Replacement Fill08-Jul-19, Utility Relocation & Utility Tunnels

29-Dec-18 A, Generator & Power Relocation

Retaining Walls at Relocated Generator

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 5

Page 6: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

UT260541.13 14 Day Notice -SQL Shutdown for PUD switchover 1 100% 0 29-Nov-18 A 29-Nov-18 AUT260541.1 Relocate Generator & LP Tank 7 100% 0 10-Dec-18 A 18-Dec-18 AUT260541.2 Relocate PUD Primary to SQL 3 100% 0 10-Dec-18 A 12-Dec-18 AUT260541.3 SQL Shutdown for PUD switchover 1 100% 0 29-Dec-18 A 29-Dec-18 A

Water ServiceWater Service RelocationWater Service RelocationWater Service RelocationWater Service RelocationWater Service RelocationWater Service RelocationWater Service RelocationUT33100.1 Relocate Water to New Vault and CUP 7 100% 0 08-Nov-18 A 28-Nov-18 AUT33100.31 14 Day Notice -Water Service Shutdown - CUP 1 100% 0 08-Nov-18 A 09-Nov-18 AUT33100.3 Install 8" Water South of New Bldg Pad 5 100% 0 29-Nov-18 A 05-Dec-18 AUT33100.21 Set 6" Water Meter 3 100% 0 29-Nov-18 A 29-Nov-18 AUT33100.11 Water Service Shutdown - CUP 1 100% 0 02-Dec-18 A 02-Dec-18 AUT33100.2 Demo Ex. Waterline in New Bldg Pad 4 100% 0 10-Dec-18 A 11-Dec-18 AUT33100.12 Complete Water Loop 5 100% 0 11-Jan-19 A 15-Mar-19 A

New Utility TuNew Utility TunnelsNew Utility TunnelsNew Utility TunnelsNew Utility TunnelsNew Utility TunnelsNew Utility TunnelsNew Utility TunnelsUT31200.0 Site Clearing & Demolition - UT 3 100% 0 27-Sep-18 A 03-Oct-18 AUT03001.0 Excavation - UT 5 100% 0 04-Oct-18 A 17-Oct-18 AUT33400.0 Install Drainage Matt @ Base Slab - UT 3 100% 0 17-Oct-18 A 22-Oct-18 AUT03301.0 F/R/P Conc Base Slab & Footings - UT 12 100% 0 18-Oct-18 A 26-Oct-18 AUT03303.0 F/R/P Conc Walls - UT 15 100% 0 29-Oct-18 A 09-Nov-18 AUT03304.0 F/R/P Conc Top Slab - UT 10 100% 0 12-Nov-18 A 29-Nov-18 AUT23052.0 Install Pipe Supports - UT 5 100% 0 19-Nov-18 A 20-Nov-18 AUT33100.0 Install 4" Domestic Water Main @ UT 10 100% 0 19-Nov-18 A 28-Nov-18 AUT23211.0 HVAC - Install 10" Chilled Water Piping S & R - UT 13 100% 0 26-Nov-18 A 10-Dec-18 AUT23210.0 14 Day Notice - Chilled Water Shutdown - UT 1 100% 0 27-Nov-18 A 27-Nov-18 AUT23212.0 HVAC Install 10 Hot Water Piping S & R - UT 8 100% 0 29-Nov-18 A 13-Dec-18 AUT26053.0 Elec - Install Cable Tray - UT 3 100% 0 04-Dec-18 A 10-Dec-18 AMY01100.0 START - Chilled Water Shut Down 0 100% 0 08-Dec-18 AUT33401.0 Install Bentonite & Sub Drainage Piping - UT 1 100% 0 17-Dec-18 A 17-Dec-18 AUT31233.0 Backfill - UT 3 100% 0 19-Dec-18 A 21-Dec-18 AUT26054.0 Elec - Install Comm Cable - UT 3 100% 0 20-Dec-18 A 21-Dec-18 AUT02413.0 Demo Existing Tunnels & CT Foundations @ SET Bldg Pad 3 100% 0 26-Dec-18 A 02-Jan-19 AMY23005.0 Remove CT #1 2 100% 0 03-Jan-19 A 03-Jan-19 AMY23006.0 Remove CT #2 2 100% 0 03-Jan-19 A 03-Jan-19 AMY23214.0 Chilled Water Connect To New Piping @ - UT 3 100% 0 08-Jan-19 A 10-Jan-19 A

Mechanical YaMechanical YardMechanical YardMechanical YardMechanical YardMechanical YardMechanical YardMechanical YardMY31105.0 Demolition / Earthwork - MY 5 100% 0 19-Sep-18 A 26-Oct-18 AMY12311.0 HVAC - U/G 12" Piping - MY 10 100% 0 29-Oct-18 A 07-Nov-18 AMY26100.0 Electrical U/G Rough-in - MY 10 100% 0 29-Oct-18 A 09-Nov-18 ACU23210.0 HVAC - U/G CW Piping - MY 5 100% 0 01-Nov-18 A 08-Nov-18 AMY31230.0 Excavate Conc Slab / Fnd - MY 2 100% 0 09-Nov-18 A 12-Nov-18 AMY03300.0 F/R/P Conc Retaining Wall Fnd - MY 5 100% 0 12-Nov-18 A 15-Nov-18 AMY03301.0 F/R/P 12 Conc Retaining Walls - MY 10 100% 0 26-Nov-18 A 14-Dec-18 AMY22110.0 Plumb Sleeves Retaining Walls - MY 2 100% 0 29-Nov-18 A 29-Nov-18 AMY23004.0 Chilled Water Shutdown Period 24 100% 0 08-Dec-18 A 06-Mar-19 A

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

14 Day Notice -SQL Shutdown for PUD switchoverRelocate Generator & LP Tank

Relocate PUD Primary to SQLSQL Shutdown for PUD switchover

15-Mar-19 A, Water Service Relocation

Relocate Water to New Vault and CUP14 Day Notice -Water Service Shutdown - CUP

Install 8" Water South of New Bldg PadSet 6" Water MeterWater Service Shutdown - CUP

Demo Ex. Waterline in New Bldg PadComplete Water Loop

10-Jan-19 A, New Utility Tunnels

Site Clearing & Demolition - UTExcavation - UTInstall Drainage Matt @ Base Slab - UTF/R/P Conc Base Slab & Footings - UT

F/R/P Conc Walls - UTF/R/P Conc Top Slab - UT

Install Pipe Supports - UTInstall 4" Domestic Water Main @ UT

HVAC - Install 10" Chilled Water Piping S & R - UT14 Day Notice - Chilled Water Shutdown - UT

HVAC Install 10 Hot Water Piping S & R - UTElec - Install Cable Tray - UTSTART - Chilled Water Shut Down

Install Bentonite & Sub Drainage Piping - UTBackfill - UTElec - Install Comm Cable - UT

Demo Existing Tunnels & CT Foundations @ SET Bldg PadRemove CT #1Remove CT #2

Chilled Water Connect To New Piping @ - UT08-Jul-19, Mechanical Yard

Demolition / Earthwork - MYHVAC - U/G 12" Piping - MYElectrical U/G Rough-in - MYHVAC - U/G CW Piping - MYExcavate Conc Slab / Fnd - MYF/R/P Conc Retaining Wall Fnd - MY

F/R/P 12 Conc Retaining Walls - MYPlumb Sleeves Retaining Walls - MY

Chilled Water Shutdown Period

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 6

Page 7: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

MY03305.0 F/R/P Conc Slab - MY 5 100% 0 17-Dec-18 A 21-Dec-18 AMY23841.0 HVAC - Reinstall CT #1 3 100% 0 04-Jan-19 A 08-Jan-19 AMY23842.0 HVAC - Reinstall CT #2 3 100% 0 04-Jan-19 A 08-Jan-19 AMY26101.0 Electrical - Service - Pull Wire - MY 10 100% 0 04-Jan-19 A 17-Jan-19 AMY31100.0 Demo Existing CT Area 3 100% 0 04-Jan-19 A 08-Jan-19 AMY23001.0 Demo Existing Condenser Water Piping 3 100% 0 09-Jan-19 A 09-Jan-19 AMY23881.0 HVAC - Piping - Complete CT Installation #1 3 100% 0 14-Jan-19 A 21-Jan-19 AMY23882.0 HVAC - Piping - Complete CT Installation #2 3 100% 0 14-Jan-19 A 21-Jan-19 AMY31233.0 Backfill Retaining Walls - MY 2 100% 0 14-Jan-19 A 15-Jan-19 AMY26103.0 Elec - Hookup / Wire CT #2 3 100% 0 16-Jan-19 A 28-Jan-19 AMY26102.0 Elec - Hookup / Wire CT #1 3 100% 0 18-Jan-19 A 28-Jan-19 AMY23801.0 HVAC - Start-up CT #1 3 100% 0 28-Jan-19 A 06-Mar-19 AMY23802.0 HVAC - Start-up CT #2 3 100% 0 28-Jan-19 A 06-Mar-19 AUT23130.10 END - Chilled Water Shut Down 0 100% 0 06-Mar-19 AMY26000.0 New Generator 1 100% 0 05-Apr-19 A 05-Apr-19 AMY26000.10 New LP Tank 6 0% 6 01-Jul-19 08-Jul-19 61

Gas RelocatioGas RelocationGas RelocationGas RelocationGas RelocationGas RelocationGas RelocationGas RelocationUT33510.0 Install New Gas Service 5 100% 0 19-Oct-18 A 02-Nov-18 AUT33512.0 14 Day Notice - Gas Service Shutdown 1 100% 0 06-Dec-18 A 06-Dec-18 AUT33511.0 Coordinate Install New Gas Meters 1 100% 0 14-Dec-18 A 14-Dec-18 AUT33513.0 Gas Service Connect To Main 2 100% 0 18-Dec-18 A 20-Dec-18 AUT33515.0 Gas Service Shutdown 1 100% 0 21-Dec-18 A 21-Dec-18 AUT33514.0 Demo Exist Gas Service 1 100% 0 08-Jan-19 A 08-Jan-19 A

Sanitary SeweSanitary Sewer RelocationSanitary Sewer RelocationSanitary Sewer RelocationSanitary Sewer RelocationSanitary Sewer RelocationSanitary Sewer RelocationSanitary Sewer RelocationUT33300.0 Install Sanitary Sewer 10 100% 0 08-Nov-18 A 11-Jan-19 AUT33301.0 14 Day Notice - Sanitary Sewer Shutdown 1 100% 0 30-Nov-18 A 30-Nov-18 AUT33305.0 Sanitary Sewer Shutdown 1 100% 0 30-Nov-18 A 30-Nov-18 AUT33303.10 Side Sewer Connections 1 100% 0 11-Dec-18 A 11-Dec-18 AUT33403 Storm Drainage - Piping 10 100% 0 18-Dec-18 A 11-Jan-19 AUT33303.0 Sanitary Sewer Connect To Main 5 100% 0 19-Jan-19 A 24-Jan-19 AUT33304.0 Demo Exist Sanitary Sewer 5 100% 0 19-Jan-19 A 22-Jan-19 AUT33303.20 SS MH 4 to SS MH 8 8 100% 0 28-Jan-19 A 20-Feb-19 A

Domestic & HDomestic & Hot Water RelocationDomestic & Hot Water RelocationDomestic & Hot Water RelocationDomestic & Hot Water RelocationDomestic & Hot Water RelocationDomestic & Hot Water RelocationDomestic & Hot Water RelocationUT33101.0 14 Day Notice - Water Shutdown - UT 1 100% 0 21-Nov-18 A 21-Nov-18 AUT33102.0 Domestic Water Main Connect To New Piping 1 100% 0 02-Dec-18 A 02-Dec-18 AUT01105.0 START - Domestic Water Shutdown 0 100% 0 02-Dec-18 AUT01106.0 END - Domestic Water Shutdown 0 100% 0 02-Dec-18 AUT01103.0 14 Day Notice - Hot Water Shutdown - UT 1 100% 0 03-Dec-18 A 03-Dec-18 AUT23216.0 Chlorinate & Test Hot Water 3 100% 0 11-Dec-18 A 13-Dec-18 AUT23213.0 Hot Water Connect To New Piping 1 100% 0 17-Dec-18 A 17-Dec-18 AUT01104.0 START - Hot Water Shutdown 0 100% 0 17-Dec-18 AUT01104.10 END - Hot Water Shutdown 0 100% 0 18-Dec-18 AUT02411.0 Demo Existing Water Main 3 100% 0 19-Dec-18 A 21-Dec-18 A

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

F/R/P Conc Slab - MYHVAC - Reinstall CT #1HVAC - Reinstall CT #2

Electrical - Service - Pull Wire - MYDemo Existing CT AreaDemo Existing Condenser Water Piping

HVAC - Piping - Complete CT Installation #1HVAC - Piping - Complete CT Installation #2

Backfill Retaining Walls - MYElec - Hookup / Wire CT #2Elec - Hookup / Wire CT #1

HVAC - Start-up CT #1HVAC - Start-up CT #2END - Chilled Water Shut Down

New GeneratorNew LP Tank

08-Jan-19 A, Gas Relocation

Install New Gas Service14 Day Notice - Gas Service Shutdown

Coordinate Install New Gas MetersGas Service Connect To MainGas Service Shutdown

Demo Exist Gas Service20-Feb-19 A, Sanitary Sewer Relocation

Install Sanitary Sewer14 Day Notice - Sanitary Sewer ShutdownSanitary Sewer Shutdown

Side Sewer ConnectionsStorm Drainage - Piping

Sanitary Sewer Connect To MainDemo Exist Sanitary Sewer

SS MH 4 to SS MH 821-Dec-18 A, Domestic & Hot Water Relocation

14 Day Notice - Water Shutdown - UTDomestic Water Main Connect To New PipingSTART - Domestic Water ShutdownEND - Domestic Water Shutdown14 Day Notice - Hot Water Shutdown - UT

Chlorinate & Test Hot WaterHot Water Connect To New PipingSTART - Hot Water ShutdownEND - Hot Water ShutdownDemo Existing Water Main

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 7

Page 8: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

Science, EnScience, Engineering & Technology Bldg (SET)Science, Engineering & Technology Bldg (SET)Science, Engineering & Technology Bldg (SET)Science, Engineering & Technology Bldg (SET)Science, Engineering & Technology Bldg (SET)Science, Engineering & Technology Bldg (SET)Science, Engineering & Technology Bldg (SET)SET - StructuSET - StructureSET - StructureSET - StructureSET - StructureSET - StructureSET - StructureSET - Structure1sr Level - Ea1sr Level - East Side - Foundations & SOG1sr Level - East Side - Foundations & SOG1sr Level - East Side - Foundations & SOG1sr Level - East Side - Foundations & SOG1sr Level - East Side - Foundations & SOG1sr Level - East Side - Foundations & SOG1sr Level - East Side - Foundations & SOGSE31203.1 Earthwork - SET Bldg Pad - 1st Flr E 5 100% 0 10-Dec-18 A 14-Dec-18 ASE01011.1 Engineering / Layout - 1st Flr E 3 100% 0 12-Dec-18 A 26-Dec-18 ASE31230.1 Excavate Foundations - 1st Flr E 5 100% 0 13-Dec-18 A 28-Dec-18 ASE03300.1 F/R/P - Conc Fdns - 1st Flr E 3 100% 0 26-Dec-18 A 28-Dec-18 ASE03302.1 F/R/P Fdns Walls & Pilasters - 1st Flr E 3 100% 0 31-Dec-18 A 03-Jan-19 ASE31230.11 Resume Excavate Foundations - 1st Flr E 5 100% 0 04-Jan-19 A 29-Jan-19 ASE03302.11 Resume F/R/P Conc Fdns - 1st Flr E 12 100% 0 09-Jan-19 A 02-Feb-19 ASE03302.21 Resume F/R/P Fdns Walls & Pilasters - 1st Flr E 12 100% 0 22-Jan-19 A 02-Feb-19 ASE03302.31 Resume from Wx F/R/P Conc Fdns - 1st Flr E 2 100% 0 18-Feb-19 A 25-Feb-19 ASE03302.41 Resume from Wx F/R/P Fdns Walls/Pilasters - 1st Flr E 8 100% 0 21-Feb-19 A 05-Mar-19 ASE07111.1 Waterproofing - 1st Flr E 2 100% 0 06-Mar-19 A 07-Mar-19 ASE03002.1 Backfill Foundations - 1st Flr E 3 100% 0 07-Mar-19 A 12-Mar-19 ASE22050.1 Plumb Underslab Rough-In - 1st Flr E 8 100% 0 12-Mar-19 A 22-Mar-19 ASE26050.1 Electrical Underslab Rough-In - 1st Flr E 1 100% 0 18-Mar-19 A 25-Mar-19 ASE03301.1 Prep / Rebar & Pour SOG - 1st Flr E 6 100% 0 25-Mar-19 A 30-Mar-19 ASE03303.1 Conc - Pour Col Diamonds - 1st Flr E 3 100% 0 09-May-19 A 30-May-19 ASE03325.1 Concrete Stair Treads - 1st Flr E 5 100% 0 23-May-19 A 23-May-19 A

1st Level - W1st Level - West Side - Foundations & SOG1st Level - West Side - Foundations & SOG1st Level - West Side - Foundations & SOG1st Level - West Side - Foundations & SOG1st Level - West Side - Foundations & SOG1st Level - West Side - Foundations & SOG1st Level - West Side - Foundations & SOGSW31203.1 Earthwork - SET Bldg Pad - 1st Flr W 10 100% 0 26-Nov-18 A 21-Dec-18 ASW01011.1 Engineering / Layout - 1st Flr W 3 100% 0 26-Dec-18 A 28-Dec-18 ASW03000.1 Excavate Foundations - 1st Flr W 4 100% 0 09-Jan-19 A 15-Jan-19 ASW03300.1 F/R/P - Conc Fdns - 1st Flr W 14 100% 0 16-Jan-19 A 02-Feb-19 ASW03000.11 Resume Excavate Foundations - 1st Flr W 6 100% 0 16-Jan-19 A 01-Feb-19 ASW03302.1 F/R/P Fdns Walls & Pilasters - 1st Flr W 15 100% 0 24-Jan-19 A 02-Feb-19 ASW03300.11 Resume from Wx F/R/P - Conc Fdns - 1st Flr W 7 100% 0 18-Feb-19 A 08-Mar-19 ASW03000.21 Resume from Wx Excavate Foundations - 1st Flr W 2 100% 0 19-Feb-19 A 28-Feb-19 ASW03302.11 Resume from Wx F/R/P Fdns/Walls/Pilasters - 1st Flr W 12 100% 0 20-Feb-19 A 15-Mar-19 ASW03101.1 F/R/P - Elev Pit - 1st Flr W 10 100% 0 27-Feb-19 A 15-Mar-19 ASW07111.1 Waterproofing - 1st Flr W 2 100% 0 11-Mar-19 A 20-Mar-19 ASW03002.1 Backfill Foundations - 1st Flr W 2 100% 0 15-Mar-19 A 22-Mar-19 ASW22050.1 Plumb Underslab Rough-In - 1st Flr W 10 100% 0 18-Mar-19 A 28-Mar-19 ASW21011.1 Fire Sprinkler U/S Main Rough-In - 1st Flr W 5 100% 0 26-Mar-19 A 29-Mar-19 ASW26050.1 Electrical Underslab Rough-In - 1st Flr W 8 100% 0 02-Apr-19 A 09-Apr-19 ASW03301.1 Prep (Cap Break) SOG - 1st Flr W 2 100% 0 01-May-19 A 02-May-19 ASW03301.11 Vapor Barrier, Rebar & Pour SOG - 1st Flr W 4 100% 0 06-May-19 A 09-May-19 ASW03303.1 Conc - Pour Col Diamonds - 1st Flr W 3 100% 0 30-May-19 A 05-Jun-19 ASW03325.1 Concrete Stair Treads - 1st Flr W 5 100% 0 20-Jun-19 A 21-Jun-19 A

Steel PackagSteel Package - East Side - 1st Floor thru RoofSteel Package - East Side - 1st Floor thru RoofSteel Package - East Side - 1st Floor thru RoofSteel Package - East Side - 1st Floor thru RoofSteel Package - East Side - 1st Floor thru RoofSteel Package - East Side - 1st Floor thru RoofSteel Package - East Side - 1st Floor thru RoofSE05120.1 Structural Steel & Deck Erection - 1st thru Roof - E 7 100% 0 02-Apr-19 A 10-Apr-19 A

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

16-Apr-20, Science, Engine

05-Jul-19, SET - Structure

30-May-19 A, 1sr Level - East Side - Foundations & SOG

Earthwork - SET Bldg Pad - 1st Flr EEngineering / Layout - 1st Flr EExcavate Foundations - 1st Flr EF/R/P - Conc Fdns - 1st Flr EF/R/P Fdns Walls & Pilasters - 1st Flr E

Resume Excavate Foundations - 1st Flr EResume F/R/P Conc Fdns - 1st Flr EResume F/R/P Fdns Walls & Pilasters - 1st Flr E

Resume from Wx F/R/P Conc Fdns - 1st Flr EResume from Wx F/R/P Fdns Walls/Pilasters - 1st Flr EWaterproofing - 1st Flr EBackfill Foundations - 1st Flr E

Plumb Underslab Rough-In - 1st Flr EElectrical Underslab Rough-In - 1st Flr EPrep / Rebar & Pour SOG - 1st Flr E

Conc - Pour Col Diamonds - 1st Flr EConcrete Stair Treads - 1st Flr E

21-Jun-19 A, 1st Level - West Side - Foundations & SOG

Earthwork - SET Bldg Pad - 1st Flr WEngineering / Layout - 1st Flr W

Excavate Foundations - 1st Flr WF/R/P - Conc Fdns - 1st Flr WResume Excavate Foundations - 1st Flr WF/R/P Fdns Walls & Pilasters - 1st Flr W

Resume from Wx F/R/P - Conc Fdns - 1st Flr WResume from Wx Excavate Foundations - 1st Flr W

Resume from Wx F/R/P Fdns/Walls/Pilasters - 1st Flr WF/R/P - Elev Pit - 1st Flr WWaterproofing - 1st Flr WBackfill Foundations - 1st Flr WPlumb Underslab Rough-In - 1st Flr WFire Sprinkler U/S Main Rough-In - 1st Flr W

Electrical Underslab Rough-In - 1st Flr WPrep (Cap Break) SOG - 1st Flr WVapor Barrier, Rebar & Pour SOG - 1st Flr W

Conc - Pour Col Diamonds - 1st Flr WConcrete Stair Treads - 1st Flr W

29-Apr-19 A, Steel Package - East Side - 1st Floor thru Roof

Structural Steel & Deck Erection - 1st thru Roof - E

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 8

Page 9: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SE05510.1 Install Steel Stairs - 1st Flr E 5 100% 0 05-Apr-19 A 17-Apr-19 ASE05510.2 Install Steel Stairs - 2nd Flr E 5 100% 0 05-Apr-19 A 17-Apr-19 ASE05510.3 Install Steel Stairs - 3rd Flr E 5 100% 0 05-Apr-19 A 17-Apr-19 ASE05121.1 Structural Steel & Deck - Welding/Detailing - 1st Thru Roof 19 100% 0 12-Apr-19 A 29-Apr-19 A

Steel PackagSteel Package - West Side - 1st Floor thru RoofSteel Package - West Side - 1st Floor thru RoofSteel Package - West Side - 1st Floor thru RoofSteel Package - West Side - 1st Floor thru RoofSteel Package - West Side - 1st Floor thru RoofSteel Package - West Side - 1st Floor thru RoofSteel Package - West Side - 1st Floor thru RoofSW05120.1 Structural Steel Erection - 1st thru Roof - W 8 100% 0 10-Apr-19 A 19-Apr-19 ASW05121.1 Structural Steel & Deck - Welding / Detailing - 1st Thru Roof 23 100% 0 16-Apr-19 A 14-May-19 ASW05510.1 Install Steel Stairs - 1st Flr W 5 100% 0 25-Apr-19 A 01-May-19 ASW05510.2 Install Steel Stairs - 2nd Flr W 5 100% 0 25-Apr-19 A 02-May-19 ASW05510.3 Install Steel Stairs - 3rd Flr W 5 100% 0 03-May-19 A 09-May-19 A

2nd Level - E2nd Level - East Side - Concrete Slab2nd Level - East Side - Concrete Slab2nd Level - East Side - Concrete Slab2nd Level - East Side - Concrete Slab2nd Level - East Side - Concrete Slab2nd Level - East Side - Concrete Slab2nd Level - East Side - Concrete SlabSE03302.2 Form / Prep / Rebar Slab on Mtl Deck -2nd Flr E 6 100% 0 22-Apr-19 A 29-Apr-19 ASE22050.2 Plumbing Slab Rough-In - 2nd Flr E 4 100% 0 22-Apr-19 A 25-Apr-19 ASE26050.2 Electrical Rough Slab - 2nd Flr E 6 100% 0 22-Apr-19 A 29-Apr-19 ASE03303.2 Pour Slab on Metal Deck - 2nd Flr E 1 100% 0 30-Apr-19 A 30-Apr-19 ASE03325.2 Concrete Stair Treads - 2nd Flr E 5 100% 0 23-May-19 A 23-May-19 A

2nd Level - W2nd Level - West Side - Concrete Slab2nd Level - West Side - Concrete Slab2nd Level - West Side - Concrete Slab2nd Level - West Side - Concrete Slab2nd Level - West Side - Concrete Slab2nd Level - West Side - Concrete Slab2nd Level - West Side - Concrete SlabSW26050.2 Electrical Rough Slab - 2nd Flr W 8 100% 0 06-May-19 A 14-May-19 ASW22050.2 Plumbing Slab Rough-In - 2nd Flr W 8 100% 0 07-May-19 A 15-May-19 ASW03302.2 Form / Prep / Rebar Slab on Mtl Deck -2nd Flr W 8 100% 0 13-May-19 A 22-May-19 ASW03303.2 Pour Slab on Metal Deck - 2nd Flr W 1 100% 0 23-May-19 A 23-May-19 ASW03325.2 Concrete Stair Treads - 2nd Flr W 5 0% 5 01-Jul-19 05-Jul-19 19

3rd Level - Ea3rd Level - East Side - Concrete Slab3rd Level - East Side - Concrete Slab3rd Level - East Side - Concrete Slab3rd Level - East Side - Concrete Slab3rd Level - East Side - Concrete Slab3rd Level - East Side - Concrete Slab3rd Level - East Side - Concrete SlabSE22050.3 Plumbing Slab Rough-In - 3rd Flr E 5 100% 0 29-Apr-19 A 06-May-19 ASE26050.3 Electrical Rough Slab - 3rd Flr E 5 100% 0 01-May-19 A 08-May-19 ASE03302.3 F/ R & Prep Slab on Mtl Deck - 3rd Flr E 7 100% 0 03-May-19 A 13-May-19 ASE03303.3 Pour Slab on Metal Deck - 3rd Flr E 1 100% 0 14-May-19 A 14-May-19 ASE03325.3 Concrete Stair Treads - 3rd Flr E 5 100% 0 20-Jun-19 A 24-Jun-19 A

3rd Level - W3rd Level - West Side - Concrete Slab3rd Level - West Side - Concrete Slab3rd Level - West Side - Concrete Slab3rd Level - West Side - Concrete Slab3rd Level - West Side - Concrete Slab3rd Level - West Side - Concrete Slab3rd Level - West Side - Concrete SlabSW26050.3 Electrical Rough Slab - 3rd Flr W 8 100% 0 13-May-19 A 22-May-19 ASW22050.3 Plumbing Slab Rough-In - 3rd Flr W 8 100% 0 15-May-19 A 22-May-19 ASW03302.3 F/ R/ Prep Slab on Mtl Deck - 3rd Flr W 3 100% 0 22-May-19 A 29-May-19 ASW03303.3 Pour Slab on Metal Deck - 3rd Flr W 1 100% 0 30-May-19 A 30-May-19 ASW03325.3 Concrete Stair Treads - 3rd Flr W 5 0% 5 01-Jul-19 05-Jul-19 20

SET - ExterioSET - ExteriorSET - ExteriorSET - ExteriorSET - ExteriorSET - ExteriorSET - ExteriorSET - Exterior1sr Level - Ea1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East SideSE05401.N Ext Metal Framing - N. Elev - 1st Flr E 10 100% 0 07-May-19 A 20-May-19 ASE05401.E Ext Metal Framing - E. Elev - 1st Flr E 5 100% 0 21-May-19 A 28-May-19 ASE05401.S Ext Metal Framing - S. Elev - 1st Flr E 10 100% 0 30-May-19 A 12-Jun-19 ASE07151.N Ext Sheathing & Air Barrier - N Elev - 1st Flr E 10 100% 0 03-Jun-19 A 11-Jun-19 ASE07151.E Ext Sheathing & Air Barrier - E Elev - 1st Flr E 5 20% 4 10-Jun-19 A 04-Jul-19 -2SE07151.S Ext Sheathing & Air Barrier - S Elev - 1st Flr E 10 50% 5 24-Jun-19 A 05-Jul-19 23

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Install Steel Stairs - 1st Flr EInstall Steel Stairs - 2nd Flr EInstall Steel Stairs - 3rd Flr E

Structural Steel & Deck - Welding/Detailing - 1st Thru Roof14-May-19 A, Steel Package - West Side - 1st Floor thru Roof

Structural Steel Erection - 1st thru Roof - WStructural Steel & Deck - Welding / Detailing - 1st Thru Roof

Install Steel Stairs - 1st Flr WInstall Steel Stairs - 2nd Flr WInstall Steel Stairs - 3rd Flr W

23-May-19 A, 2nd Level - East Side - Concrete Slab

Form / Prep / Rebar Slab on Mtl Deck -2nd Flr EPlumbing Slab Rough-In - 2nd Flr EElectrical Rough Slab - 2nd Flr EPour Slab on Metal Deck - 2nd Flr E

Concrete Stair Treads - 2nd Flr E05-Jul-19, 2nd Level - West Side - Concrete Slab

Electrical Rough Slab - 2nd Flr WPlumbing Slab Rough-In - 2nd Flr W

Form / Prep / Rebar Slab on Mtl Deck -2nd Flr WPour Slab on Metal Deck - 2nd Flr W

Concrete Stair Treads - 2nd Flr W24-Jun-19 A, 3rd Level - East Side - Concrete Slab

Plumbing Slab Rough-In - 3rd Flr EElectrical Rough Slab - 3rd Flr EF/ R & Prep Slab on Mtl Deck - 3rd Flr EPour Slab on Metal Deck - 3rd Flr E

Concrete Stair Treads - 3rd Flr E05-Jul-19, 3rd Level - West Side - Concrete Slab

Electrical Rough Slab - 3rd Flr WPlumbing Slab Rough-In - 3rd Flr WF/ R/ Prep Slab on Mtl Deck - 3rd Flr WPour Slab on Metal Deck - 3rd Flr W

Concrete Stair Treads - 3rd Flr W20-Dec-19, SET - Exterior

16-Aug-19, 1sr Level - East Side

Ext Metal Framing - N. Elev - 1st Flr EExt Metal Framing - E. Elev - 1st Flr E

Ext Metal Framing - S. Elev - 1st Flr EExt Sheathing & Air Barrier - N Elev - 1st Flr E

Ext Sheathing & Air Barrier - E Elev - 1st Flr EExt Sheathing & Air Barrier - S Elev - 1st Flr E

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 9

Page 10: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SE04211.N Brick Veneer - N. Elev - 1st Flr E 10 0% 10 15-Jul-19 26-Jul-19 -8SE07421.E1 Metal Wall Panels - E. Elev - 1st Flr E 4 0% 4 22-Jul-19 25-Jul-19 10SE07421.S1 Metal Wall Panels - S. Elev - 1st Flr E 5 0% 5 22-Jul-19 26-Jul-19 13SE23070.1 HVAC - Pipe Insulation - 1st Flr E 15 0% 15 23-Jul-19 12-Aug-19 6SE04211.E Brick Veneer - E. Elev - 1st Flr E 5 0% 5 29-Jul-19 02-Aug-19 3SE08411.N Alum Storefront & Windows - N. Elev - 1E 5 0% 5 29-Jul-19 02-Aug-19 -8SE04211.S Brick Veneer - S. Elev - 1st Flr E 10 0% 10 05-Aug-19 16-Aug-19 5SE08411.E Alum Storefront & Windows - E. Elev - 1E 3 0% 3 05-Aug-19 07-Aug-19 12

1st Level - W1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West SideSW05401.S Ext Metal Framing - S. Elev - 1st Flr W 10 50% 5 24-Jun-19 A 05-Jul-19 5SW07151.S Ext Sheathing & Air Barrier - S Elev - 1st Flr W 10 30% 7 26-Jun-19 A 09-Jul-19 26SW05401.N Ext Metal Framing - N. Elev - 1st Flr W 10 0% 10 01-Jul-19 12-Jul-19 -9SW06100.1 Rough Carpentry - Wd Blocking - 1st Flr W 15 0% 15 01-Jul-19 19-Jul-19 52SW05401.W Ext Metal Framing - W. Elev - 1st Flr W 5 0% 5 12-Jul-19 18-Jul-19 5SW07151.N Ext Sheathing & Air Barrier - N Elev - 1st Flr W 10 0% 10 15-Jul-19 26-Jul-19 -9SW07151.W Ext Sheathing & Air Barrier - W Elev - 1st Flr W 5 0% 5 17-Jul-19 23-Jul-19 5SW07421.S1 Metal Wall Panels - S. Elev - 1st Flr W 4 0% 4 22-Jul-19 25-Jul-19 18SW07421.W1 Metal Wall Panels - W. Elev - 1st Flr W 3 0% 3 24-Jul-19 26-Jul-19 20SW04211.N Brick Veneer - N. Elev - 1st Flr W 10 0% 10 29-Jul-19 09-Aug-19 -9SW04211.W Brick Veneer - W. Elev - 1st Flr W 5 0% 5 12-Aug-19 16-Aug-19 -8SW08411.N Alum Storefront & Windows - N. Elev - 1W 5 0% 5 12-Aug-19 16-Aug-19 -8SW04211.S Brick Veneer - S. Elev - 1st Flr W 10 0% 10 19-Aug-19 30-Aug-19 5SW08411.W Alum Storefront & Windows - W. Elev - 1W 3 0% 3 19-Aug-19 21-Aug-19 -8SW08411.S Alum Storefront & Windows - S. Elev - 1W 5 0% 5 03-Sep-19 09-Sep-19 5

2nd Level - E2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East SideSE05402.N Ext Metal Framing - N Elev - 2nd Flr E 10 100% 0 14-May-19 A 24-May-19 ASE05402.E Ext Metal Framing - E Elev - 2nd Flr E 5 100% 0 23-May-19 A 29-May-19 ASE05402.S Ext Metal Framing - S Elev - 2nd Flr E 10 100% 0 30-May-19 A 19-Jun-19 ASE07152.N Ext Sheathing & Air Barrier - N Elev - 2nd Flr E 10 40% 6 04-Jun-19 A 08-Jul-19 -8SE07152.E Ext Sheathing & Air Barrier - E Elev - 2nd Flr 5 0% 5 10-Jun-19 A 05-Jul-19 24SE07152.S Ext Sheathing & Air Barrier -S Elev - 2nd Flr E 10 50% 5 24-Jun-19 A 05-Jul-19 28SE04212.N Brick Veneer - N. Elev - 2nd Flr E 10 0% 10 15-Jul-19 26-Jul-19 -2SE07421.N2 Metal Wall Panels - N. Elev - 2nd Flr E 3 0% 3 22-Jul-19 24-Jul-19 14SE07421.E2 Metal Wall Panels - E. Elev - 2nd Flr E 4 0% 4 26-Jul-19 31-Jul-19 10SE08412.N Alum Windows - N. Elev - 2nd Flr E 5 0% 5 29-Jul-19 02-Aug-19 27SE07421.S2 Metal Wall Panels - S. Elev - 2nd Flr E 2 0% 2 29-Jul-19 30-Jul-19 13SE04212.E Brick Veneer - E. Elev - 2nd Flr E 5 0% 5 05-Aug-19 09-Aug-19 3SE08412.W Alum Windows - E. Elev - 2nd Flr E 5 0% 5 05-Aug-19 09-Aug-19 27SE04212.S Brick Veneer - S. Elev - 2nd Flr E 10 0% 10 19-Aug-19 30-Aug-19 8SE08412.S Alum Windows - S. Elev - 2nd Flr E 5 0% 5 03-Sep-19 09-Sep-19 12

2nd Level - W2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West SideSW05402.N Ext Metal Framing - N Elev - 2nd Flr W 10 0% 10 15-Jul-19 26-Jul-19 -5SW07152.N Ext Sheathing & Air Barrier- N Elev - 2nd Flr W 10 0% 10 18-Jul-19 31-Jul-19 4

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Brick Veneer - N. Elev - 1st Flr EMetal Wall Panels - E. Elev - 1st Flr EMetal Wall Panels - S. Elev - 1st Flr E

HVAC - Pipe Insulation - 1st Flr EBrick Veneer - E. Elev - 1st Flr EAlum Storefront & Windows - N. Elev - 1E

Brick Veneer - S. Elev - 1st Flr EAlum Storefront & Windows - E. Elev - 1E

09-Sep-19, 1st Level - West Side

Ext Metal Framing - S. Elev - 1st Flr WExt Sheathing & Air Barrier - S Elev - 1st Flr WExt Metal Framing - N. Elev - 1st Flr WRough Carpentry - Wd Blocking - 1st Flr WExt Metal Framing - W. Elev - 1st Flr W

Ext Sheathing & Air Barrier - N Elev - 1st Flr WExt Sheathing & Air Barrier - W Elev - 1st Flr WMetal Wall Panels - S. Elev - 1st Flr WMetal Wall Panels - W. Elev - 1st Flr W

Brick Veneer - N. Elev - 1st Flr WBrick Veneer - W. Elev - 1st Flr WAlum Storefront & Windows - N. Elev - 1W

Brick Veneer - S. Elev - 1st Flr WAlum Storefront & Windows - W. Elev - 1W

Alum Storefront & Windows - S. Elev - 1W09-Sep-19, 2nd Level - East Side

Ext Metal Framing - N Elev - 2nd Flr EExt Metal Framing - E Elev - 2nd Flr E

Ext Metal Framing - S Elev - 2nd Flr EExt Sheathing & Air Barrier - N Elev - 2nd Flr EExt Sheathing & Air Barrier - E Elev - 2nd FlrExt Sheathing & Air Barrier -S Elev - 2nd Flr E

Brick Veneer - N. Elev - 2nd Flr EMetal Wall Panels - N. Elev - 2nd Flr E

Metal Wall Panels - E. Elev - 2nd Flr EAlum Windows - N. Elev - 2nd Flr EMetal Wall Panels - S. Elev - 2nd Flr E

Brick Veneer - E. Elev - 2nd Flr EAlum Windows - E. Elev - 2nd Flr E

Brick Veneer - S. Elev - 2nd Flr EAlum Windows - S. Elev - 2nd Flr E

23-Sep-19, 2nd Level - West Side

Ext Metal Framing - N Elev - 2nd Flr WExt Sheathing & Air Barrier- N Elev - 2nd Flr W

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 10

Page 11: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SW05402.W Ext Metal Framing - W Elev - 2nd Flr W 5 0% 5 26-Jul-19 01-Aug-19 1SW07152.W Ext Sheathing & Air Barrier - W Elev - 2nd Flr W 5 0% 5 31-Jul-19 06-Aug-19 13SW05402.S Ext Metal Framing - S Elev - 2nd Flr W 10 0% 10 01-Aug-19 14-Aug-19 1SW07421.N2 Metal Wall Panels - N. Elev - 2nd Flr W 3 0% 3 01-Aug-19 05-Aug-19 20SW06100.2 Rough Carpentry - Wd Blocking - 2nd Flr W 15 0% 15 05-Aug-19 23-Aug-19 40SW07152.S Ext Sheathing & Air Barrier - S Elev - 2nd Flr W 10 0% 10 06-Aug-19 19-Aug-19 1SW07421.W2 Metal Wall Panels - W. Elev - 2nd Flr W 4 0% 4 07-Aug-19 12-Aug-19 13SW04212.N Brick Veneer - N. Elev - 2nd Flr W 10 0% 10 09-Aug-19 22-Aug-19 -9SW04212.W Brick Veneer - W. Elev - 2nd Flr W 5 0% 5 19-Aug-19 23-Aug-19 30SW07421.S2 Metal Wall Panels - S. Elev - 2nd Flr W 6 0% 6 20-Aug-19 27-Aug-19 1SW08412.N Alum Windows - N. Elev - 2nd Flr W 5 0% 5 23-Aug-19 29-Aug-19 -9SW08412.W Alum Windows - W. Elev - 2nd Flr W 5 0% 5 26-Aug-19 30-Aug-19 30SW04212.S Brick Veneer - S. Elev - 2nd Flr W 10 0% 10 03-Sep-19 16-Sep-19 20SW08412.S Alum Windows - S. Elev - 2nd Flr W 5 0% 5 17-Sep-19 23-Sep-19 20

3rd Level - Ea3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East SideSE05403.N Ext Metal Framing - N Elev - 3rd Flr E 10 100% 0 23-May-19 A 17-Jun-19 ASE05403.E Ext Metal Framing - E. Elev - 3rd Flr E 5 60% 2 05-Jun-19 A 02-Jul-19 21SE07153.E Ext Sheathing & Air Barrier - E Elev - 3rd Flr E 5 20% 4 10-Jun-19 A 04-Jul-19 29SE05403.S Ext Metal Framing - S Elev - 3rd Flr E 10 100% 0 12-Jun-19 A 25-Jun-19 ASE07153.N Ext Sheathing & Air Barrier -N Elev-3rd Flr E 10 50% 5 24-Jun-19 A 05-Jul-19 -3SE07153.S Ext Sheathing & Air Barrier - S Elev - 3rd Flr E 10 50% 5 24-Jun-19 A 05-Jul-19 30SE04214.N Brick Veneer - N. Elev - 3rd Flr E 10 0% 10 22-Jul-19 02-Aug-19 -2SE07421.N3 Metal Wall Panels - N. Elev - 3rd Flr E 6 0% 6 25-Jul-19 01-Aug-19 14SE0421.S3 Metal Wall Panels - S. Elev - 3rd Flr E 3 0% 3 31-Jul-19 02-Aug-19 13SE07421.E3 Metal Wall Panels - E. Elev - 3rd Flr E 5 0% 5 01-Aug-19 07-Aug-19 10SE08413.N Alum Windows - N. Elev - 3rd Flr E 5 0% 5 05-Aug-19 09-Aug-19 -2SE04213.E Brick Veneer - E. Elev - 3rd Flr E 5 0% 5 12-Aug-19 16-Aug-19 3SE08413.E Alum Windows - E. Elev - 3rd Flr E 3 0% 3 12-Aug-19 14-Aug-19 35SE04213.S Brick Veneer - S. Elev - 3rd Flr E 10 0% 10 19-Aug-19 30-Aug-19 3SE08413.S Alum Windows - S. Elev - 3rd Flr E 5 0% 5 03-Sep-19 09-Sep-19 23

3rd Level - W3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West SideSW05403.N Ext Metal Framing - N Elev - 3rd Flr W 10 0% 10 29-Jul-19 09-Aug-19 -5SW07153.N Ext Sheathing & Air Barrier -N Elev-3rd Flr W 10 0% 10 01-Aug-19 14-Aug-19 4SW04214.N Brick Veneer - N. Elev - 3rd Flr W 10 0% 10 06-Aug-19 19-Aug-19 4SW05403.W Ext Metal Framing - W Elev - 3rd Flr W 5 0% 5 12-Aug-19 16-Aug-19 -5SW06100.3 Rough Carpentry - Wd Blocking - 3rd Flr W 15 0% 15 14-Aug-19 04-Sep-19 26SW07153.W Ext Sheathing & Air Barrier - W Elev - 3rd Flr W 5 0% 5 15-Aug-19 21-Aug-19 6SW07421.N3 Metal Wall Panels - N. Elev - 3rd Flr W 3 0% 3 15-Aug-19 19-Aug-19 13SW05403.S Ext Metal Framing - S Elev - 3rd Flr W 10 0% 10 19-Aug-19 30-Aug-19 -5SW04213.W Brick Veneer - W. Elev - 3rd Flr W 5 0% 5 20-Aug-19 26-Aug-19 12SW08413.N Alum Windows - N. Elev - 3rd Flr W 5 0% 5 20-Aug-19 26-Aug-19 4SW07153.S Ext Sheathing & Air Barrier - S Elev - 3rd Flr W 10 0% 10 22-Aug-19 05-Sep-19 -5SW07421.W3 Metal Wall Panels - W. Elev - 3rd Flr W 5 0% 5 22-Aug-19 28-Aug-19 6SW08413.W Alum Windows - W. Elev - 3rd Flr W 3 0% 3 27-Aug-19 29-Aug-19 31

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Ext Metal Framing - W Elev - 2nd Flr WExt Sheathing & Air Barrier - W Elev - 2nd Flr W

Ext Metal Framing - S Elev - 2nd Flr WMetal Wall Panels - N. Elev - 2nd Flr W

Rough Carpentry - Wd Blocking - 2nd Flr WExt Sheathing & Air Barrier - S Elev - 2nd Flr W

Metal Wall Panels - W. Elev - 2nd Flr WBrick Veneer - N. Elev - 2nd Flr WBrick Veneer - W. Elev - 2nd Flr WMetal Wall Panels - S. Elev - 2nd Flr WAlum Windows - N. Elev - 2nd Flr WAlum Windows - W. Elev - 2nd Flr W

Brick Veneer - S. Elev - 2nd Flr WAlum Windows - S. Elev - 2nd Flr W

09-Sep-19, 3rd Level - East Side

Ext Metal Framing - N Elev - 3rd Flr EExt Metal Framing - E. Elev - 3rd Flr EExt Sheathing & Air Barrier - E Elev - 3rd Flr E

Ext Metal Framing - S Elev - 3rd Flr EExt Sheathing & Air Barrier -N Elev-3rd Flr EExt Sheathing & Air Barrier - S Elev - 3rd Flr E

Brick Veneer - N. Elev - 3rd Flr EMetal Wall Panels - N. Elev - 3rd Flr EMetal Wall Panels - S. Elev - 3rd Flr EMetal Wall Panels - E. Elev - 3rd Flr EAlum Windows - N. Elev - 3rd Flr EBrick Veneer - E. Elev - 3rd Flr EAlum Windows - E. Elev - 3rd Flr E

Brick Veneer - S. Elev - 3rd Flr EAlum Windows - S. Elev - 3rd Flr E

23-Sep-19, 3rd Level - West Side

Ext Metal Framing - N Elev - 3rd Flr WExt Sheathing & Air Barrier -N Elev-3rd Flr WBrick Veneer - N. Elev - 3rd Flr WExt Metal Framing - W Elev - 3rd Flr W

Rough Carpentry - Wd Blocking - 3rd Flr WExt Sheathing & Air Barrier - W Elev - 3rd Flr WMetal Wall Panels - N. Elev - 3rd Flr W

Ext Metal Framing - S Elev - 3rd Flr WBrick Veneer - W. Elev - 3rd Flr WAlum Windows - N. Elev - 3rd Flr W

Ext Sheathing & Air Barrier - S Elev - 3rd Flr WMetal Wall Panels - W. Elev - 3rd Flr WAlum Windows - W. Elev - 3rd Flr W

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 11

Page 12: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SW04213.S Brick Veneer - S. Elev - 3rd Flr W 10 0% 10 03-Sep-19 16-Sep-19 8SW07421.S3 Metal Wall Panels - S. Elev - 3rd Flr W 6 0% 6 06-Sep-19 13-Sep-19 -6SW08413.S Alum Windows - S. Elev - 3rd Flr W 5 0% 5 17-Sep-19 23-Sep-19 20

Roof - East SRoof - East SideRoof - East SideRoof - East SideRoof - East SideRoof - East SideRoof - East SideRoof - East SideSE22131.4 Plbg - Install Roof Drains - Roof E 5 100% 0 28-May-19 A 10-Jun-19 ASW03302.4 F/R/P Conc Curb - Elev Acess - Roof W 4 100% 0 05-Jun-19 A 21-Jun-19 ASE05404.4 Ext Metal Framing - Roof E 12 83.33% 2 17-Jun-19 A 02-Jul-19 21SE05400.4 Metal Framing - Inside Parapet - Roof E 7 85.71% 1 20-Jun-19 A 01-Jul-19 12SE07153.4 Ext Sheathing & Air Barrier- Parapet - Roof E 5 0% 5 01-Jul-19 05-Jul-19 13SE07154.4 Ext Sheathing & Air Barrier - Roof E 12 0% 12 01-Jul-19 16-Jul-19 21SE06102.4 Rough Carpentry - Roof Blocking - Roof E 5 0% 5 02-Jul-19 08-Jul-19 12SE06100.4 Fire Rated Blocking @ Parapet - Roof E 3 0% 3 04-Jul-19 08-Jul-19 12SE07500.4 Roof Insulation / Dry in - Roof E 5 0% 5 09-Jul-19 15-Jul-19 12SE07542.4 Thermoplastic Roofing - Roof E 10 0% 10 16-Jul-19 29-Jul-19 12SE06101.4 Fire Rated Plywood @ Parapet - Roof E 4 0% 4 30-Jul-19 02-Aug-19 23SE07211.4 Rigid Insulation - Roof E 5 0% 5 30-Jul-19 05-Aug-19 12SE26155.4 Elec - Lightning Protection System - Roof E 10 0% 10 30-Jul-19 12-Aug-19 29SE07421.4 Metal Wall Panels - Roof E 10 0% 10 08-Aug-19 21-Aug-19 10SE07620.4 Metal Coping Cap @ Parapet - Roof E 4 0% 4 22-Aug-19 27-Aug-19 10SW26155.4 Elec - Lightning Protection System - Roof W 10 0% 10 26-Aug-19 09-Sep-19 25SE07501.4 Install Walk Pads - Roof E 3 0% 3 28-Aug-19 30-Aug-19 10SE04215.4 Brick Veneer - N. Elev - Roof E 12 0% 12 03-Sep-19 18-Sep-19 3SE23732.4 Hvac - Install AHUs 1 & 2 - Roof E 5 0% 5 03-Sep-19 09-Sep-19 10SE08611.4 Sloped SkyLights - Roof E 5 0% 5 18-Sep-19 24-Sep-19 -1SE07900.4 Ext Joint Sealants - Roof E 15 0% 15 25-Sep-19 15-Oct-19 -1

Roof - West SRoof - West SideRoof - West SideRoof - West SideRoof - West SideRoof - West SideRoof - West SideRoof - West SideSW05400.4 Metal Framing - Inside Parapet - Roof W 7 0% 7 02-Jul-19 10-Jul-19 19SW05404.4 Ext Metal Framing - Roof W 12 0% 12 11-Jul-19 26-Jul-19 19SW07154.4 Ext Sheathing & Air Barrier - Roof W 12 0% 12 16-Jul-19 31-Jul-19 24SW07211.4 Rigid Insulation - Roof W 5 0% 5 26-Jul-19 01-Aug-19 24SW06100.4 Fire Rated Blocking @ Parapet - Roof W 3 0% 3 29-Jul-19 31-Jul-19 21SW06102.4 Rough Carpentry - Roof Blocking - Roof W 5 0% 5 29-Jul-19 02-Aug-19 19SW07153.4 Ext Sheathing & Air Barrier - Parapet - Roof W 5 0% 5 29-Jul-19 02-Aug-19 19SW22131.4 Plbg - Install Roof Drains - Roof W 5 0% 5 29-Jul-19 02-Aug-19 19SW07210.4 Thermal Insulation (Walls) - Roof W 2 0% 2 01-Aug-19 02-Aug-19 32SW07155.4 Sheathing & Air Barrier - Elev Acess - Roof W 3 0% 3 05-Aug-19 07-Aug-19 32SW07500.4 Roof Insulation / Dry in - Roof W 5 0% 5 05-Aug-19 09-Aug-19 19SW07542.4 Thermoplastic Roofing - Roof W 10 0% 10 12-Aug-19 23-Aug-19 19SW06101.4 Fire Rated Plywood @ Parapet - Roof W 4 0% 4 26-Aug-19 29-Aug-19 19SW07421.4 Metal Wall Panels - Roof W 10 0% 10 16-Sep-19 27-Sep-19 -6SW04215.4 Brick Veneer - N. Elev - Roof W 12 0% 12 17-Sep-19 02-Oct-19 8SW08611.4 Sloped Glazing /08.5 SkyLights - Roof W 5 0% 5 30-Sep-19 04-Oct-19 -6SW07620.4 Metal Coping Cap @ Parapet - Roof W 4 0% 4 07-Oct-19 10-Oct-19 -6SW07501.4 Install Walk Pads - Roof W 3 0% 3 11-Oct-19 15-Oct-19 -6

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Brick Veneer - S. Elev - 3rd Flr WMetal Wall Panels - S. Elev - 3rd Flr W

Alum Windows - S. Elev - 3rd Flr W15-Oct-19, Roof - East Side

Plbg - Install Roof Drains - Roof EF/R/P Conc Curb - Elev Acess - Roof W

Ext Metal Framing - Roof EMetal Framing - Inside Parapet - Roof EExt Sheathing & Air Barrier- Parapet - Roof E

Ext Sheathing & Air Barrier - Roof ERough Carpentry - Roof Blocking - Roof EFire Rated Blocking @ Parapet - Roof ERoof Insulation / Dry in - Roof E

Thermoplastic Roofing - Roof EFire Rated Plywood @ Parapet - Roof ERigid Insulation - Roof E

Elec - Lightning Protection System - Roof EMetal Wall Panels - Roof EMetal Coping Cap @ Parapet - Roof E

Elec - Lightning Protection System - Roof WInstall Walk Pads - Roof E

Brick Veneer - N. Elev - Roof EHvac - Install AHUs 1 & 2 - Roof E

Sloped SkyLights - Roof EExt Joint Sealants - Roof E

20-Dec-19, Roof - West Side

Metal Framing - Inside Parapet - Roof WExt Metal Framing - Roof WExt Sheathing & Air Barrier - Roof WRigid Insulation - Roof WFire Rated Blocking @ Parapet - Roof WRough Carpentry - Roof Blocking - Roof WExt Sheathing & Air Barrier - Parapet - Roof WPlbg - Install Roof Drains - Roof WThermal Insulation (Walls) - Roof WSheathing & Air Barrier - Elev Acess - Roof WRoof Insulation / Dry in - Roof W

Thermoplastic Roofing - Roof WFire Rated Plywood @ Parapet - Roof W

Metal Wall Panels - Roof WBrick Veneer - N. Elev - Roof WSloped Glazing /08.5 SkyLights - Roof WMetal Coping Cap @ Parapet - Roof WInstall Walk Pads - Roof W

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 12

Page 13: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SW23732.4 Hvac - Install AHUs 1 & 2 - Roof W 5 0% 5 16-Oct-19 22-Oct-19 -6SW07900.4 Ext Joint Sealants - Roof W 15 0% 15 23-Oct-19 12-Nov-19 -6SW08142.1 Install Doors - 1st Flr W 10 0% 10 09-Dec-19 20-Dec-19 1

SET - Rough SET - Rough InSET - Rough InSET - Rough InSET - Rough InSET - Rough InSET - Rough InSET - Rough In1sr Level - Ea1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East SideSE22000.1 Install MEP Hangers - 1st Flr E 5 100% 0 22-Apr-19 A 26-Apr-19 ASE23211.1 HVAC Piping Rough - 1st Flr E 15 100% 0 30-Apr-19 A 20-May-19 ASE26059.1 Electrical OH Rough In - 1st Flr E 15 100% 0 14-May-19 A 14-Jun-19 ASE09221.1 Metal Framing Interior Walls - 1st Flr E 15 100% 0 20-May-19 A 24-Jun-19 ASE07811.1 Fire Proofing - 1st Flr E 5 100% 0 21-May-19 A 22-May-19 ASE22212.1 Plbg - OH - Sanitary Rough - 1st Flr E 15 100% 0 21-May-19 A 04-Jun-19 ASE26056.1 Electrical In Wall Rough In - 1st Flr E 15 100% 0 24-May-19 A 18-Jun-19 ASE22051.1 Plumbing In Wall Rough In - 1st Flr E 15 100% 0 28-May-19 A 25-Jun-19 ASE08100.1 Hollow Metal Door Frames - 1st Flr E 15 100% 0 03-Jun-19 A 07-Jun-19 ASE26058.1 Elec / Communication Rough-In - 1st Flr E 15 33.33% 10 24-Jun-19 A 12-Jul-19 25SE06100.1 Rough Carpentry - Wd Blocking - 1st Flr E 15 0% 15 01-Jul-19 19-Jul-19 30SE21050.1 Fire Sprinkler Sys Rough-In - 1st Flr E 15 0% 15 01-Jul-19 19-Jul-19 22SE22052.1 Plumbing - Water Piping Rough - 1st Flr E 15 0% 15 01-Jul-19 19-Jul-19 5SE08332.1 HVAC - Install Pumps - 1st Flr E 15 0% 15 02-Jul-19 22-Jul-19 38SE23521.1 HVAC - Install Bolier - 1st Flr E 15 0% 15 02-Jul-19 22-Jul-19 4SE23732.1 HVAC Equipment - 1st Flr E 15 0% 15 02-Jul-19 22-Jul-19 4SE26190.1 Electrical - Pull Wire - 1st Flr E 15 0% 15 11-Jul-19 31-Jul-19 9SE22055.1 Plumbing - Install Water Heater - 1st Flr E 5 0% 5 22-Jul-19 26-Jul-19 9SE22053.1 Plumbing - Pipe Insulation - 1st Flr E 15 0% 15 23-Jul-19 12-Aug-19 4SE26410.1 Electrical - Switchgear - 1st Flr E 15 0% 15 01-Aug-19 21-Aug-19 9SE23311.1 HVAC Ductwork Rough - 1st Flr E 15 0% 15 05-Aug-19 23-Aug-19 -8SE28310.1 Fire Alarm Rough In - 1st Flr E 10 0% 10 05-Aug-19 16-Aug-19 0SE07210.1 Thermal Insulation (Walls) - 1st Flr E 10 0% 10 19-Aug-19 30-Aug-19 0SE08411.S Alum Storefront & Windows - S. Elev - 1E 5 0% 5 19-Aug-19 23-Aug-19 5SE23075.1 HVAC Duct Insulation - 1st Flr E 15 0% 15 26-Aug-19 16-Sep-19 -8SE23900.1 Bldg Mgmt - HVAC Control Rough - 1st Flr E 15 0% 15 26-Aug-19 16-Sep-19 -1SE09222.1 Metal Framing Clgs & Soffits - 1st Flr E 15 0% 15 03-Sep-19 23-Sep-19 -8SE23901.1 Bldg Mgmt - HVAC Controls Wiring - 1st Flr E 15 0% 15 17-Sep-19 07-Oct-19 -1SE23902.1 Bldg Mgmt - HVAC Install / Wire Panel -1st Flr E 15 0% 15 08-Oct-19 28-Oct-19 -1

1st Level - W1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West SideSW22000.1 Install MEP Hangers - 1st Flr W 5 100% 0 06-May-19 A 13-May-19 ASW22212.1 Plbg - OH - Sanitary Rough - 1st Flr W 15 100% 0 04-Jun-19 A 24-Jun-19 ASW07811.1 Fire Proofing - 1st Flr W 5 100% 0 05-Jun-19 A 10-Jun-19 ASW23211.1 HVAC Piping Rough - 1st Flr W 15 100% 0 10-Jun-19 A 28-Jun-19 ASW09221.1 Metal Framing Interior Walls - 1st Flr W 15 100% 0 17-Jun-19 A 27-Jun-19 ASW26059.1 Electrical OH Rough In - 1st Flr W 15 66.67% 5 17-Jun-19 A 05-Jul-19 25SW26056.1 Electrical In Wall Rough In - 1st Flr W 15 53.33% 7 19-Jun-19 A 09-Jul-19 23SW26058.1 Elec / Communication Rough-In - 1st Flr W 15 13.33% 13 27-Jun-19 A 17-Jul-19 98

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Hvac - Install AHUs 1 & 2 - Roof WExt Joint Sealants - Roof W

Install Doors - 1st Flr W16-Dec-19, SET - Rough In

28-Oct-19, 1sr Level - East Side

Install MEP Hangers - 1st Flr EHVAC Piping Rough - 1st Flr E

Electrical OH Rough In - 1st Flr EMetal Framing Interior Walls - 1st Flr E

Fire Proofing - 1st Flr EPlbg - OH - Sanitary Rough - 1st Flr E

Electrical In Wall Rough In - 1st Flr EPlumbing In Wall Rough In - 1st Flr E

Hollow Metal Door Frames - 1st Flr EElec / Communication Rough-In - 1st Flr ERough Carpentry - Wd Blocking - 1st Flr EFire Sprinkler Sys Rough-In - 1st Flr EPlumbing - Water Piping Rough - 1st Flr EHVAC - Install Pumps - 1st Flr EHVAC - Install Bolier - 1st Flr EHVAC Equipment - 1st Flr E

Electrical - Pull Wire - 1st Flr EPlumbing - Install Water Heater - 1st Flr E

Plumbing - Pipe Insulation - 1st Flr EElectrical - Switchgear - 1st Flr EHVAC Ductwork Rough - 1st Flr E

Fire Alarm Rough In - 1st Flr EThermal Insulation (Walls) - 1st Flr E

Alum Storefront & Windows - S. Elev - 1EHVAC Duct Insulation - 1st Flr EBldg Mgmt - HVAC Control Rough - 1st Flr EMetal Framing Clgs & Soffits - 1st Flr E

Bldg Mgmt - HVAC Controls Wiring - 1st Flr EBldg Mgmt - HVAC Install / Wire Panel -1st Flr E

16-Dec-19, 1st Level - West Side

Install MEP Hangers - 1st Flr WPlbg - OH - Sanitary Rough - 1st Flr W

Fire Proofing - 1st Flr WHVAC Piping Rough - 1st Flr WMetal Framing Interior Walls - 1st Flr W

Electrical OH Rough In - 1st Flr WElectrical In Wall Rough In - 1st Flr W

Elec / Communication Rough-In - 1st Flr W

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 13

Page 14: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SW08100.1 Hollow Metal Foor Frames - 1st Flr W 15 0% 15 01-Jul-19 19-Jul-19 40SW08332.1 HVAC - Install Pumps - 1st Flr W 15 0% 15 01-Jul-19 19-Jul-19 66SW22051.1 Plumbing In Wall Rough In - 1st Flr W 15 0% 15 01-Jul-19 19-Jul-19 0SW23070.1 HVAC - Pipe Insulation - 1st Flr W 15 0% 15 01-Jul-19 19-Jul-19 32SW23732.1 HVAC Equipment - 1st Flr W 15 0% 15 02-Jul-19 22-Jul-19 9SW23521.1 HVAC - Install Bolier - 1st Flr W 15 0% 15 09-Jul-19 29-Jul-19 9SW22052.1 Plumbing - Water Piping Rough - 1st Flr W 15 0% 15 22-Jul-19 09-Aug-19 0SW22053.1 Plumbing - Pipe Insulation - 1st Flr W 15 0% 15 12-Aug-19 30-Aug-19 0SW22055.1 Plumbing - Install Water Heater - 1st Flr W 5 0% 5 12-Aug-19 16-Aug-19 7SW23311.1 HVAC Ductwork Rough - 1st Flr W 15 0% 15 19-Aug-19 09-Sep-19 -8SW21050.1 Fire Sprinkler Sys Rough-In - 1st Flr W 15 0% 15 21-Aug-19 11-Sep-19 -5SW26190.1 Electrical - Pull Wire - 1st Flr W 15 0% 15 22-Aug-19 12-Sep-19 -8SW28310.1 Fire Alarm Rough In - 1st Flr W 10 0% 10 29-Aug-19 12-Sep-19 -8SW23075.1 HVAC Duct Insulation - 1st Flr W 15 0% 15 10-Sep-19 30-Sep-19 -8SW07210.1 Thermal Insulation (Walls) - 1st Flr W 10 0% 10 13-Sep-19 26-Sep-19 -8SW26410.1 Electrical - Switchgear - 1st Flr W 15 0% 15 13-Sep-19 03-Oct-19 74SW09222.1 Metal Framing Clgs & Soffits - 1st Flr W 15 0% 15 17-Sep-19 07-Oct-19 -8SW23900.1 Bldg Mgmt - HVAC Control Rough - 1st Flr W 15 0% 15 17-Sep-19 07-Oct-19 11SW14240.1 Elevator - Equip - 1st Flr W 15 0% 15 04-Oct-19 24-Oct-19 -1SW14241.1 Elevator - Rails - 1st Flr W 5 0% 5 04-Oct-19 10-Oct-19 -8SW23901.1 Bldg Mgmt - HVAC Controls Wiring - 1st Flr W 15 0% 15 08-Oct-19 28-Oct-19 11SW23902.1 Bldg Mgmt - HVAC Install / Wire Panel -1st Flr W 15 0% 15 29-Oct-19 18-Nov-19 11SW14242.1 Elevator - Cabs - 1st Flr W 30 0% 30 05-Nov-19 16-Dec-19 -8SW23800.1 Install Unit Heaters @ Stairs - 1st Flr W 5 0% 5 19-Nov-19 25-Nov-19 19

2nd Level - E2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East SideSE22000.2 Install MEP Hangers - 2nd Flr E 5 100% 0 29-Apr-19 A 06-May-19 ASE23211.2 HVAC Piping Rough - 2nd Flr E 15 100% 0 21-May-19 A 04-Jun-19 ASE07811.2 Fire Proofing - 2nd Flr E 5 100% 0 22-May-19 A 23-May-19 ASE22212.2 Plbg - OH - Sanitary Rough - 2nd Flr E 15 100% 0 28-May-19 A 18-Jun-19 ASE26059.2 Electrical OH Rough In - 2nd Flr E 14 100% 0 29-May-19 A 19-Jun-19 ASE09221.2 Metal Framing Interior Walls - 2nd Flr E 15 20% 12 30-May-19 A 16-Jul-19 -5SE08100.2 Hollow Metal Foor Frames - 2nd Flr E 15 0% 15 01-Jul-19 19-Jul-19 47SE23070.2 HVAC - Pipe Insulation - 2nd Flr E 15 0% 15 01-Jul-19 19-Jul-19 42SE06100.2 Rough Carpentry - Wd Blocking - 2nd Flr E 15 0% 15 03-Jul-19 23-Jul-19 45SE23311.2 HVAC Ductwork Rough - 2nd Flr E 15 0% 15 08-Jul-19 26-Jul-19 8SE21050.2 Fire Sprinkler Sys Rough-In - 2nd Flr E 15 0% 15 10-Jul-19 30-Jul-19 65SE22051.2 Plumbing In Wall Rough In - 2nd Flr E 15 0% 15 17-Jul-19 06-Aug-19 -5SE23732.2 HVAC Equipment - 2nd Flr E 15 0% 15 17-Jul-19 06-Aug-19 70SE26056.2 Electrical In Wall Rough In - 2nd Flr E 15 0% 15 17-Jul-19 06-Aug-19 5SE26058.2 Elec / Communication Rough-In - 2nd Flr E 15 0% 15 17-Jul-19 06-Aug-19 70SE23900.2 Bldg Mgmt - HVAC Control Rough - 2nd Flr E 15 0% 15 26-Jul-19 15-Aug-19 8SE23075.2 HVAC Duct Insulation - 2nd Flr E 15 0% 15 29-Jul-19 16-Aug-19 22SE22052.2 Plumbing - Water Piping Rough - 2nd Flr E 15 0% 15 07-Aug-19 27-Aug-19 -5SE26190.2 Electrical - Pull Wire - 2nd Flr E 15 0% 15 07-Aug-19 27-Aug-19 5

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Hollow Metal Foor Frames - 1st Flr WHVAC - Install Pumps - 1st Flr WPlumbing In Wall Rough In - 1st Flr WHVAC - Pipe Insulation - 1st Flr WHVAC Equipment - 1st Flr WHVAC - Install Bolier - 1st Flr W

Plumbing - Water Piping Rough - 1st Flr WPlumbing - Pipe Insulation - 1st Flr W

Plumbing - Install Water Heater - 1st Flr WHVAC Ductwork Rough - 1st Flr WFire Sprinkler Sys Rough-In - 1st Flr WElectrical - Pull Wire - 1st Flr WFire Alarm Rough In - 1st Flr W

HVAC Duct Insulation - 1st Flr WThermal Insulation (Walls) - 1st Flr WElectrical - Switchgear - 1st Flr WMetal Framing Clgs & Soffits - 1st Flr WBldg Mgmt - HVAC Control Rough - 1st Flr W

Elevator - Equip - 1st Flr WElevator - Rails - 1st Flr W

Bldg Mgmt - HVAC Controls Wiring - 1st Flr WBldg Mgmt - HVAC Install / Wire Panel -1st Flr W

Elevator - Cabs - 1st Flr WInstall Unit Heaters @ Stairs - 1st Flr W

02-Oct-19, 2nd Level - East Side

Install MEP Hangers - 2nd Flr EHVAC Piping Rough - 2nd Flr E

Fire Proofing - 2nd Flr EPlbg - OH - Sanitary Rough - 2nd Flr EElectrical OH Rough In - 2nd Flr E

Metal Framing Interior Walls - 2nd Flr EHollow Metal Foor Frames - 2nd Flr EHVAC - Pipe Insulation - 2nd Flr ERough Carpentry - Wd Blocking - 2nd Flr EHVAC Ductwork Rough - 2nd Flr EFire Sprinkler Sys Rough-In - 2nd Flr EPlumbing In Wall Rough In - 2nd Flr EHVAC Equipment - 2nd Flr EElectrical In Wall Rough In - 2nd Flr EElec / Communication Rough-In - 2nd Flr E

Bldg Mgmt - HVAC Control Rough - 2nd Flr EHVAC Duct Insulation - 2nd Flr E

Plumbing - Water Piping Rough - 2nd Flr EElectrical - Pull Wire - 2nd Flr E

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 14

Page 15: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SE28310.2 Fire Alarm Rough In - 2nd Flr E 10 0% 10 14-Aug-19 27-Aug-19 5SE23901.2 Bldg Mgmt - HVAC Controls Wiring - 2nd Flr E 15 0% 15 16-Aug-19 06-Sep-19 8SE09222.2 Metal Framing Clgs & Soffits - 2nd Flr E 15 0% 15 28-Aug-19 18-Sep-19 5SE22053.2 Plumbing - Pipe Insulation - 2nd Flr E 15 0% 15 28-Aug-19 18-Sep-19 -5SE26410.2 Electrical - Switchgear - 2nd Flr E 15 0% 15 28-Aug-19 18-Sep-19 5SE07210.2 Thermal Insulation (Walls) - 2nd Flr E 10 0% 10 19-Sep-19 02-Oct-19 -5

2nd Level - W2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West SideSW22000.2 Install MEP Hangers - 2nd Flr W 5 100% 0 14-May-19 A 17-May-19 ASW07811.2 Fire Proofing - 2nd Flr W 5 100% 0 05-Jun-19 A 10-Jun-19 ASW22212.2 Plbg - OH - Sanitary Rough - 2nd Flr W 15 100% 0 10-Jun-19 A 28-Jun-19 ASW23211.2 HVAC Piping Rough - 2nd Flr W 15 33.33% 10 24-Jun-19 A 12-Jul-19 60SW26059.2 Electrical OH Rough In - 2nd Flr W 15 33.33% 10 24-Jun-19 A 12-Jul-19 35SW23070.2 HVAC - Pipe Insulation - 2nd Flr W 15 0% 15 01-Jul-19 19-Jul-19 60SW09221.2 Metal Framing Interior Walls - 2nd Flr W 15 0% 15 29-Jul-19 16-Aug-19 0SW08100.2 Hollow Metal Foor Frames - 2nd Flr W 15 0% 15 31-Jul-19 20-Aug-19 43SW22051.2 Plumbing In Wall Rough In - 2nd Flr W 15 0% 15 05-Aug-19 23-Aug-19 0SW26056.2 Electrical In Wall Rough In - 2nd Flr W 15 0% 15 05-Aug-19 23-Aug-19 10SW23732.2 HVAC Equipment - 2nd Flr W 15 0% 15 19-Aug-19 09-Sep-19 66SW26058.2 Elec / Communication Rough-In - 2nd Flr W 15 0% 15 19-Aug-19 09-Sep-19 66SW22052.2 Plumbing - Water Piping Rough - 2nd Flr W 15 0% 15 26-Aug-19 16-Sep-19 0SW26190.2 Electrical - Pull Wire - 2nd Flr W 15 0% 15 26-Aug-19 16-Sep-19 10SW23311.2 HVAC Ductwork Rough - 2nd Flr W 15 0% 15 30-Aug-19 20-Sep-19 -9SW28310.2 Fire Alarm Rough In - 2nd Flr W 10 0% 10 03-Sep-19 16-Sep-19 10SW21050.2 Fire Sprinkler Sys Rough-In - 2nd Flr W 15 0% 15 04-Sep-19 24-Sep-19 44SW22053.2 Plumbing - Pipe Insulation - 2nd Flr W 15 0% 15 17-Sep-19 07-Oct-19 0SW26410.2 Electrical - Switchgear - 2nd Flr W 15 0% 15 17-Sep-19 07-Oct-19 10SW23075.2 HVAC Duct Insulation - 2nd Flr W 15 0% 15 23-Sep-19 11-Oct-19 1SW23900.2 Bldg Mgmt - HVAC Control Rough - 2nd Flr W 15 0% 15 23-Sep-19 11-Oct-19 -9SW09222.2 Metal Framing Clgs & Soffits - 2nd Flr W 15 0% 15 30-Sep-19 18-Oct-19 1SW07210.2 Thermal Insulation (Walls) - 2nd Flr W 10 0% 10 08-Oct-19 21-Oct-19 0SW14241.2 Elevator - Rails - 2nd Flr W 5 0% 5 11-Oct-19 17-Oct-19 -8SW23901.2 Bldg Mgmt - HVAC Controls Wiring - 2nd Flr W 15 0% 15 14-Oct-19 01-Nov-19 -9

3rd Level - Ea3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East SideSE22000.3 Install MEP Hangers - 3rd Flr E 5 100% 0 20-May-19 A 23-May-19 ASE23211.3 HVAC Piping Rough - 3rd Flr E 15 100% 0 30-May-19 A 20-Jun-19 ASE22212.3 Plbg - OH - Sanitary Rough - 3rd Flr E 15 100% 0 04-Jun-19 A 28-Jun-19 ASE26059.3 Electrical OH Rough In - 3rd Flr E 15 13.33% 13 24-Jun-19 A 17-Jul-19 30SE23070.3 HVAC - Pipe Insulation - 3rd Flr E 15 0% 15 01-Jul-19 19-Jul-19 58SE09221.3 Metal Framing Interior Walls - 3rd Flr E 15 0% 15 17-Jul-19 06-Aug-19 2SE08100.3 Hollow Metal Foor Frames - 3rd Flr E 15 0% 15 19-Jul-19 08-Aug-19 44SE06100.3 Rough Carpentry - Wd Blocking - 3rd Flr E 15 0% 15 24-Jul-19 13-Aug-19 240SE22051.3 Plumbing In Wall Rough In - 3rd Flr E 15 0% 15 24-Jul-19 13-Aug-19 2SE23732.3 HVAC Equipment - 3rd Flr E 15 0% 15 24-Jul-19 13-Aug-19 76SE26056.3 Electrical In Wall Rough In - 3rd Flr E 15 0% 15 24-Jul-19 13-Aug-19 11

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Fire Alarm Rough In - 2nd Flr EBldg Mgmt - HVAC Controls Wiring - 2nd Flr E

Metal Framing Clgs & Soffits - 2nd Flr EPlumbing - Pipe Insulation - 2nd Flr EElectrical - Switchgear - 2nd Flr E

Thermal Insulation (Walls) - 2nd Flr E01-Nov-19, 2nd Level - West Side

Install MEP Hangers - 2nd Flr WFire Proofing - 2nd Flr W

Plbg - OH - Sanitary Rough - 2nd Flr WHVAC Piping Rough - 2nd Flr WElectrical OH Rough In - 2nd Flr WHVAC - Pipe Insulation - 2nd Flr W

Metal Framing Interior Walls - 2nd Flr WHollow Metal Foor Frames - 2nd Flr WPlumbing In Wall Rough In - 2nd Flr WElectrical In Wall Rough In - 2nd Flr W

HVAC Equipment - 2nd Flr WElec / Communication Rough-In - 2nd Flr WPlumbing - Water Piping Rough - 2nd Flr WElectrical - Pull Wire - 2nd Flr WHVAC Ductwork Rough - 2nd Flr W

Fire Alarm Rough In - 2nd Flr WFire Sprinkler Sys Rough-In - 2nd Flr W

Plumbing - Pipe Insulation - 2nd Flr WElectrical - Switchgear - 2nd Flr WHVAC Duct Insulation - 2nd Flr WBldg Mgmt - HVAC Control Rough - 2nd Flr WMetal Framing Clgs & Soffits - 2nd Flr WThermal Insulation (Walls) - 2nd Flr W

Elevator - Rails - 2nd Flr WBldg Mgmt - HVAC Controls Wiring - 2nd Flr W

14-Oct-19, 3rd Level - East Side

Install MEP Hangers - 3rd Flr EHVAC Piping Rough - 3rd Flr E

Plbg - OH - Sanitary Rough - 3rd Flr EElectrical OH Rough In - 3rd Flr EHVAC - Pipe Insulation - 3rd Flr E

Metal Framing Interior Walls - 3rd Flr EHollow Metal Foor Frames - 3rd Flr ERough Carpentry - Wd Blocking - 3rd Flr EPlumbing In Wall Rough In - 3rd Flr EHVAC Equipment - 3rd Flr EElectrical In Wall Rough In - 3rd Flr E

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 15

Page 16: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SE26058.3 Elec / Communication Rough-In - 3rd Flr E 15 0% 15 07-Aug-19 27-Aug-19 66SE23311.3 HVAC Ductwork Rough - 3rd Flr E 15 0% 15 12-Aug-19 30-Aug-19 -2SE22052.3 Plumbing - Water Piping Rough - 3rd Flr E 15 0% 15 13-Aug-19 03-Sep-19 2SE21050.3 Fire Sprinkler Sys Rough-In - 3rd Flr E 15 0% 15 14-Aug-19 04-Sep-19 16SE26190.3 Electrical - Pull Wire - 3rd Flr E 15 0% 15 14-Aug-19 04-Sep-19 11SE28310.3 Fire Alarm Rough In - 3rd Flr E 10 0% 10 21-Aug-19 04-Sep-19 16SE23075.3 HVAC Duct Insulation - 3rd Flr E 15 0% 15 03-Sep-19 23-Sep-19 13SE23900.3 Bldg Mgmt - HVAC Control Rough -3rd Flr E 15 0% 15 03-Sep-19 23-Sep-19 -2SE22053.3 Plumbing - Pipe Insulation - 3rd Flr E 15 0% 15 04-Sep-19 24-Sep-19 2SE26410.3 Electrical - Switchgear - 3rd Flr E 15 0% 15 05-Sep-19 25-Sep-19 11SE09222.3 Metal Framing Clgs & Soffits - 3rd Flr E 15 0% 15 10-Sep-19 30-Sep-19 13SE23901.3 Bldg Mgmt - HVAC Controls Wiring - 3rd Flr E 15 0% 15 24-Sep-19 14-Oct-19 -2SE07210.3 Thermal Insulation (Walls) - 3rd Flr E 10 0% 10 25-Sep-19 08-Oct-19 2

3rd Level - W3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West SideSW22000.3 Install MEP Hangers - 3rd Flr W 5 100% 0 22-May-19 A 29-May-19 ASW23211.3 HVAC Piping Rough - 3rd Flr W 15 33.33% 10 24-Jun-19 A 12-Jul-19 55SW22212.3 Plbg - OH - Sanitary Rough - 3rd Flr W 10 0% 10 01-Jul-19 12-Jul-19 44SW23070.3 HVAC - Pipe Insulation - 3rd Flr W 15 0% 15 15-Jul-19 02-Aug-19 55SW26059.3 Electrical OH Rough In - 3rd Flr W 15 0% 15 15-Jul-19 02-Aug-19 35SW09221.3 Metal Framing Interior Walls - 3rd Flr W 15 0% 15 07-Aug-19 27-Aug-19 5SW08100.3 Hollow Metal Door Frames - 3rd Flr W 15 0% 15 09-Aug-19 29-Aug-19 46SW22051.3 Plumbing In Wall Rough In - 3rd Flr W 15 0% 15 14-Aug-19 04-Sep-19 5SW23732.3 HVAC Equipment - 3rd Flr W 15 0% 15 14-Aug-19 04-Sep-19 74SW26056.3 Electrical In Wall Rough In - 3rd Flr W 15 0% 15 14-Aug-19 04-Sep-19 13SW23311.3 HVAC Ductwork Rough - 3rd Flr W 15 0% 15 27-Aug-19 17-Sep-19 4SW26058.3 Elec / Communication Rough-In - 3rd Flr W 15 0% 15 28-Aug-19 18-Sep-19 23SW21050.3 Fire Sprinkler Sys Rough-In - 3rd Flr W 15 0% 15 29-Aug-19 19-Sep-19 12SW22052.3 Plumbing - Water Piping Rough - 3rd Flr W 15 0% 15 03-Sep-19 23-Sep-19 5SW26190.3 Electrical - Pull Wire - 3rd Flr W 15 0% 15 05-Sep-19 25-Sep-19 13SW28310.3 Fire Alarm Rough In - 3rd Flr W 10 0% 10 12-Sep-19 25-Sep-19 18SW23075.3 HVAC Duct Insulation - 3rd Flr W 15 0% 15 18-Sep-19 08-Oct-19 19SW23900.3 Bldg Mgmt - HVAC Control Rough -3rd Flr W 15 0% 15 18-Sep-19 08-Oct-19 4SW22053.3 Plumbing - Pipe Insulation - 3rd Flr W 15 0% 15 24-Sep-19 14-Oct-19 5SW22611.3 Plumb - Compressed Air Piping Rough - 3rd Flr W 10 0% 10 24-Sep-19 07-Oct-19 10SW09222.3 Metal Framing Clgs & Soffits - 3rd Flr W 15 0% 15 26-Sep-19 16-Oct-19 18SW26410.3 Electrical - Switchgear - 3rd Flr W 15 0% 15 26-Sep-19 16-Oct-19 13SW23901.3 Bldg Mgmt - HVAC Controls Wiring - 3rd Flr W 15 0% 15 09-Oct-19 29-Oct-19 4SW07210.3 Thermal Insulation (Walls) - 3rd Flr W 10 0% 10 15-Oct-19 28-Oct-19 5SW14241.3 Elevator - Rails - 3rd Flr W 5 0% 5 18-Oct-19 24-Oct-19 -8

Roof - West SRoof - West SideRoof - West SideRoof - West SideRoof - West SideRoof - West SideRoof - West SideRoof - West SideSW14242.4 Elevator - Doors / Frame - Elev Acess - Roof W 2 0% 2 08-Aug-19 09-Aug-19 45SW14240.4 Elevator - Equip - Elev Acess - Roof W 10 0% 10 25-Oct-19 07-Nov-19 -8

SET - FinisheSET - FinishesSET - FinishesSET - FinishesSET - FinishesSET - FinishesSET - FinishesSET - Finishes

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Elec / Communication Rough-In - 3rd Flr EHVAC Ductwork Rough - 3rd Flr EPlumbing - Water Piping Rough - 3rd Flr EFire Sprinkler Sys Rough-In - 3rd Flr EElectrical - Pull Wire - 3rd Flr EFire Alarm Rough In - 3rd Flr E

HVAC Duct Insulation - 3rd Flr EBldg Mgmt - HVAC Control Rough -3rd Flr EPlumbing - Pipe Insulation - 3rd Flr EElectrical - Switchgear - 3rd Flr EMetal Framing Clgs & Soffits - 3rd Flr E

Bldg Mgmt - HVAC Controls Wiring - 3rd Flr EThermal Insulation (Walls) - 3rd Flr E

29-Oct-19, 3rd Level - West Side

Install MEP Hangers - 3rd Flr WHVAC Piping Rough - 3rd Flr WPlbg - OH - Sanitary Rough - 3rd Flr W

HVAC - Pipe Insulation - 3rd Flr WElectrical OH Rough In - 3rd Flr W

Metal Framing Interior Walls - 3rd Flr WHollow Metal Door Frames - 3rd Flr WPlumbing In Wall Rough In - 3rd Flr WHVAC Equipment - 3rd Flr WElectrical In Wall Rough In - 3rd Flr W

HVAC Ductwork Rough - 3rd Flr WElec / Communication Rough-In - 3rd Flr WFire Sprinkler Sys Rough-In - 3rd Flr WPlumbing - Water Piping Rough - 3rd Flr WElectrical - Pull Wire - 3rd Flr WFire Alarm Rough In - 3rd Flr W

HVAC Duct Insulation - 3rd Flr WBldg Mgmt - HVAC Control Rough -3rd Flr WPlumbing - Pipe Insulation - 3rd Flr W

Plumb - Compressed Air Piping Rough - 3rd Flr WMetal Framing Clgs & Soffits - 3rd Flr WElectrical - Switchgear - 3rd Flr W

Bldg Mgmt - HVAC Controls Wiring - 3rd Flr WThermal Insulation (Walls) - 3rd Flr W

Elevator - Rails - 3rd Flr W07-Nov-19, Roof - West Side

Elevator - Doors / Frame - Elev Acess - Roof WElevator - Equip - Elev Acess - Roof W

16-Apr-20, SET - Finishes

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 16

Page 17: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

1sr Level - Ea1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East Side1sr Level - East SideSE09211.1 Hang Sheetrock @ Walls - 1st Flr E 10 0% 10 03-Sep-19 16-Sep-19 0SE09212.1 FInish Sheetrock @ Walls - 1st Flr E 10 0% 10 10-Sep-19 23-Sep-19 12SE09213.1 Hang Sheetrock @ Ceilings - 1st Flr E 10 0% 10 24-Sep-19 07-Oct-19 -8SE09214.1 FInish Sheetrock @ Ceilings - 1st Flr E 10 0% 10 08-Oct-19 21-Oct-19 -8SE09910.1 Paint: Prime - 1st Flr E 10 0% 10 22-Oct-19 04-Nov-19 -8SE05519.1 Steel Handrails - 1st Flr E 10 0% 10 29-Oct-19 11-Nov-19 4SE09301.1 Ceramic Tile @ R/R - 1st Flr E 10 0% 10 05-Nov-19 18-Nov-19 -8SE09510.1 Acoustic Ceiling Grid - 1st Flr E 10 0% 10 05-Nov-19 18-Nov-19 -6SE23800.1 Install Unit Heaters @ Stairs - 1st Flr E 5 0% 5 05-Nov-19 11-Nov-19 2SE26500.1 Light Fixtures - 1st Flr E 10 0% 10 11-Nov-19 22-Nov-19 -5SE23505.1 HVAC Diffusers & Grills - 1st Flr E 10 0% 10 12-Nov-19 25-Nov-19 -6SE08142.1 Install Doors - 1st Flr E 10 0% 10 19-Nov-19 02-Dec-19 -8SE09302.1 Ceramic Tile @ Hallway - 1st Flr E 10 0% 10 19-Nov-19 02-Dec-19 -8SE09772.1 Install FRP Paneling - 1st Flr E 5 0% 5 19-Nov-19 25-Nov-19 -6SE09650.1 VCT Flooring - 1st Flr E 10 0% 10 26-Nov-19 09-Dec-19 -6SE08420.1 Automatic Glass Doors - 1st Flr E 10 0% 10 03-Dec-19 16-Dec-19 -6SE09303.1 Ceramic Tile @ Stairs - 1st Flr E 10 0% 10 03-Dec-19 16-Dec-19 -8SE22440.1 Plumbing Fixtures - 1st Flr E 10 0% 10 03-Dec-19 16-Dec-19 11SE06411.1 Custom Casework - 1st Flr E 10 0% 10 10-Dec-19 23-Dec-19 -6SE06412.1 Arch Woodwork - Tops - 1st Flr E 10 0% 10 17-Dec-19 30-Dec-19 -6SE10222.1 Install Cubical Track & Curtain - 1st Flr E 5 0% 5 31-Dec-19 06-Jan-20 -6SE22441.1 Plumbing Trim - 1st Flr E 10 0% 10 31-Dec-19 13-Jan-20 8SE09512.1 Ceiling Tile - 1st Flr E 5 0% 5 07-Jan-20 13-Jan-20 -6SE03352.1 Polish / Seal ConcFloor - 1st Flr E 2 0% 2 08-Jan-20 09-Jan-20 12SE09911.1 Paint Finish - 1st Flr E 10 0% 10 09-Jan-20 22-Jan-20 -6SE26611.1 Electrical Trim - 1st Flr E 10 0% 10 13-Jan-20 24-Jan-20 5SE28311.1 FA Devices / Trim - 1st Flr E 10 0% 10 14-Jan-20 27-Jan-20 -4SE08710.1 Door Hardware - 1st Flr E 10 0% 10 16-Jan-20 29-Jan-20 -6SE09681.1 Carpet Tile - 1st Flr E 5 0% 5 17-Jan-20 23-Jan-20 5SE09651.1 Rubber Base - 1st Flr E 3 0% 3 23-Jan-20 27-Jan-20 3SE10400.1 Interior Signage - 1st Flr E 5 0% 5 23-Jan-20 29-Jan-20 -6SE26711.1 Elec - Communications - Trim - 1st Flr E 10 0% 10 23-Jan-20 05-Feb-20 -1SE28130.1 Install Access Control - 1st Flr E 10 0% 10 23-Jan-20 05-Feb-20 -1SE12241.1 Roller Shades - 1st Flr E 3 0% 3 24-Jan-20 28-Jan-20 5SE10261.1 Corner Guards - 1st Flr E 3 0% 3 28-Jan-20 30-Jan-20 3SE28230.1 Install Video System- 1st Flr E 10 0% 10 28-Jan-20 10-Feb-20 -4SE10520.1 Fire Extinguishers - 1st Flr E 5 0% 5 30-Jan-20 05-Feb-20 -6SE10110.1 Install Visual Display Devices - 1st Flr E 5 0% 5 06-Feb-20 12-Feb-20 -6SE45000.1 Clean up - 1st Flr E 10 0% 10 13-Feb-20 26-Feb-20 -6SE45001.1 Preliminary Contractor Punch List - 1st Flr E 10 0% 10 27-Feb-20 11-Mar-20 -6SE45002.1 Architect Inspection - 1st Flr E 2 0% 2 12-Mar-20 13-Mar-20 -2

1st Level - W1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West Side1st Level - West SideSW09211.1 Hang Sheetrock @ Walls - 1st Flr W 10 0% 10 27-Sep-19 10-Oct-19 -8

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

13-Mar-20, 1sr Level - East Side

Hang Sheetrock @ Walls - 1st Flr EFInish Sheetrock @ Walls - 1st Flr E

Hang Sheetrock @ Ceilings - 1st Flr EFInish Sheetrock @ Ceilings - 1st Flr E

Paint: Prime - 1st Flr ESteel Handrails - 1st Flr ECeramic Tile @ R/R - 1st Flr EAcoustic Ceiling Grid - 1st Flr E

Install Unit Heaters @ Stairs - 1st Flr ELight Fixtures - 1st Flr EHVAC Diffusers & Grills - 1st Flr E

Install Doors - 1st Flr ECeramic Tile @ Hallway - 1st Flr E

Install FRP Paneling - 1st Flr EVCT Flooring - 1st Flr EAutomatic Glass Doors - 1st Flr ECeramic Tile @ Stairs - 1st Flr EPlumbing Fixtures - 1st Flr ECustom Casework - 1st Flr E

Arch Woodwork - Tops - 1st Flr EInstall Cubical Track & Curtain - 1st Flr EPlumbing Trim - 1st Flr ECeiling Tile - 1st Flr EPolish / Seal ConcFloor - 1st Flr E

Paint Finish - 1st Flr EElectrical Trim - 1st Flr EFA Devices / Trim - 1st Flr EDoor Hardware - 1st Flr E

Carpet Tile - 1st Flr ERubber Base - 1st Flr EInterior Signage - 1st Flr EElec - Communications - Trim - 1st Flr EInstall Access Control - 1st Flr E

Roller Shades - 1st Flr ECorner Guards - 1st Flr E

Install Video System- 1st Flr EFire Extinguishers - 1st Flr EInstall Visual Display Devices - 1st Flr

Clean up - 1st Flr EPreliminary Contractor Punch LisArchitect Inspection - 1st Flr E

15-Apr-20, 1st Level - West

Hang Sheetrock @ Walls - 1st Flr W

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 17

Page 18: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SW09212.1 FInish Sheetrock @ Walls - 1st Flr W 10 0% 10 04-Oct-19 17-Oct-19 4SW09213.1 Hang Sheetrock @ Ceilings - 1st Flr W 10 0% 10 08-Oct-19 21-Oct-19 -8SW09214.1 FInish Sheetrock @ Ceilings - 1st Flr W 10 0% 10 22-Oct-19 04-Nov-19 -8SW09910.1 Paint: Prime - 1st Flr W 10 0% 10 05-Nov-19 18-Nov-19 -8SW05519.1 Steel Handrails - 1st Flr W 10 0% 10 12-Nov-19 25-Nov-19 21SW09301.1 Ceramic Tile @ R/R - 1st Flr W 10 0% 10 19-Nov-19 02-Dec-19 17SW11532.1 Install Lab Fume Hoods - 1st Flr W 10 0% 10 19-Nov-19 02-Dec-19 1SW09302.1 Ceramic Tile @ Hallway - 1st Flr W 10 0% 10 03-Dec-19 16-Dec-19 17SW09510.1 Acoustic Ceiling Grid - 1st Flr W 10 0% 10 03-Dec-19 16-Dec-19 1SW08420.1 Automatic Glass Doors - 1st Flr W 10 0% 10 09-Dec-19 20-Dec-19 44SW23505.1 HVAC Diffusers & Grills - 1st Flr W 10 0% 10 09-Dec-19 20-Dec-19 2SW26500.1 Light Fixtures - 1st Flr W 10 0% 10 09-Dec-19 20-Dec-19 2SW14243.1 Elevator - Cab Finishes - 1st Flr W 20 0% 20 17-Dec-19 13-Jan-20 -8SW09303.1 Ceramic Tile @ Stairs - 1st Flr W 10 0% 10 23-Dec-19 03-Jan-20 1SW09650.1 VCT Flooring - 1st Flr W 10 0% 10 23-Dec-19 03-Jan-20 2SW22440.1 Plumbing Fixtures - 1st Flr W 10 0% 10 25-Dec-19 07-Jan-20 2SW06411.1 Custom Casework - 1st Flr W 10 0% 10 06-Jan-20 17-Jan-20 3SW10211.1 Toliet Partitions - 1st Flr W 10 0% 10 08-Jan-20 21-Jan-20 2SW06412.1 Arch Woodwork - Tops - 1st Flr W 10 0% 10 13-Jan-20 24-Jan-20 3SW10281.1 Toilet Accessories - 1st Flr W 10 0% 10 14-Jan-20 27-Jan-20 2SW14244.1 Elevator Testing - 1st Flr W 15 0% 15 14-Jan-20 03-Feb-20 -8SW22441.1 Plumbing Trim - 1st Flr W 10 0% 10 20-Jan-20 31-Jan-20 8SW22112.1 Plumbing Pump Hook-up - 1st Flr W 5 0% 5 03-Feb-20 07-Feb-20 8SW14245.1 Elevator Inspections - 1st Flr W 5 0% 5 04-Feb-20 10-Feb-20 -8SW09911.1 Final Paint - 1st Flr W 10 0% 10 11-Feb-20 24-Feb-20 -8SW26611.1 Electrical Trim - 1st Flr W 10 0% 10 13-Feb-20 26-Feb-20 2SW28311.1 FA Devices / Trim - 1st Flr W 10 0% 10 14-Feb-20 27-Feb-20 -6SW08710.1 Door Hardware - 1st Flr W 10 0% 10 18-Feb-20 02-Mar-20 -8SW09512.1 Ceiling Tile - 1st Flr W 5 0% 5 19-Feb-20 25-Feb-20 2SW09681.1 Carpet Tile - 1st Flr W 5 0% 5 19-Feb-20 25-Feb-20 2SW03352.1 Polish / Seal ConcFloor - 1st Flr W 2 0% 2 20-Feb-20 21-Feb-20 2SW09651.1 Rubber Base - 1st Flr W 3 0% 3 25-Feb-20 27-Feb-20 1SW10400.1 Interior Signage - 1st Flr W 5 0% 5 25-Feb-20 02-Mar-20 2SW11530.1 Lab Equipment - 1st Flr W 10 0% 10 25-Feb-20 09-Mar-20 -3SW26711.1 Elec - Communications - Trim - 1st Flr W 10 0% 10 25-Feb-20 09-Mar-20 -3SW28130.1 Install Access Control - 1st Flr W 10 0% 10 25-Feb-20 09-Mar-20 -3SW12241.1 Roller Shades - 1st Flr W 3 0% 3 26-Feb-20 28-Feb-20 3SW10261.1 Corner Guards - 1st Flr W 3 0% 3 28-Feb-20 03-Mar-20 1SW28230.1 Install Video System- 1st Flr W 10 0% 10 28-Feb-20 12-Mar-20 -6SW10520.1 Fire Extinguishers - 1st Flr W 5 0% 5 03-Mar-20 09-Mar-20 -8SW10110.1 Install Visual Display Devices - 1st Flr W 5 0% 5 10-Mar-20 16-Mar-20 -8SW45000.1 Clean up - 1st Flr W 10 0% 10 17-Mar-20 30-Mar-20 -8SW45001.1 Preliminary Contractorunch List - 1st Flr W 10 0% 10 31-Mar-20 13-Apr-20 -8SW45002.1 Architect Inspection - 1st Flr W 2 0% 2 14-Apr-20 15-Apr-20 -8

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

FInish Sheetrock @ Walls - 1st Flr WHang Sheetrock @ Ceilings - 1st Flr W

FInish Sheetrock @ Ceilings - 1st Flr WPaint: Prime - 1st Flr WSteel Handrails - 1st Flr W

Ceramic Tile @ R/R - 1st Flr WInstall Lab Fume Hoods - 1st Flr W

Ceramic Tile @ Hallway - 1st Flr WAcoustic Ceiling Grid - 1st Flr WAutomatic Glass Doors - 1st Flr WHVAC Diffusers & Grills - 1st Flr WLight Fixtures - 1st Flr W

Elevator - Cab Finishes - 1st Flr WCeramic Tile @ Stairs - 1st Flr WVCT Flooring - 1st Flr WPlumbing Fixtures - 1st Flr W

Custom Casework - 1st Flr WToliet Partitions - 1st Flr WArch Woodwork - Tops - 1st Flr WToilet Accessories - 1st Flr WElevator Testing - 1st Flr WPlumbing Trim - 1st Flr WPlumbing Pump Hook-up - 1st Flr WElevator Inspections - 1st Flr W

Final Paint - 1st Flr WElectrical Trim - 1st Flr WFA Devices / Trim - 1st Flr WDoor Hardware - 1st Flr W

Ceiling Tile - 1st Flr WCarpet Tile - 1st Flr WPolish / Seal ConcFloor - 1st Flr WRubber Base - 1st Flr WInterior Signage - 1st Flr WLab Equipment - 1st Flr WElec - Communications - Trim - 1sInstall Access Control - 1st Flr W

Roller Shades - 1st Flr WCorner Guards - 1st Flr W

Install Video System- 1st Flr WFire Extinguishers - 1st Flr WInstall Visual Display Devices - 1

Clean up - 1st Flr WPreliminary ContractorunchArchitect Inspection - 1st F

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 18

Page 19: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

2nd Level - E2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East Side2nd Level - East SideSE09211.2 Hang Sheetrock @ Walls - 2nd Flr E 10 0% 10 03-Oct-19 16-Oct-19 -5SE09212.2 FInish Sheetrock @ Walls - 2nd Flr E 10 0% 10 10-Oct-19 23-Oct-19 5SE09213.2 Hang Sheetrock @ Ceilings - 2nd Flr E 10 0% 10 10-Oct-19 23-Oct-19 -5SE09214.2 FInish Sheetrock @ Ceilings - 2nd Flr E 10 0% 10 24-Oct-19 06-Nov-19 -5SE09910.2 Paint: Prime - 2nd Flr E 10 0% 10 07-Nov-19 20-Nov-19 -5SE05519.2 Steel Handrails - 2nd Flr E 10 0% 10 14-Nov-19 27-Nov-19 -5SE09300.2 Ceramic Tile - 2nd Flr E 10 0% 10 21-Nov-19 04-Dec-19 15SE09510.2 Acoustic Ceiling Grid - 2nd Flr E 10 0% 10 21-Nov-19 04-Dec-19 -5SE08142.2 Install Doors - 2nd Flr E 10 0% 10 27-Nov-19 10-Dec-19 -4SE08420.2 Automatic Glass Doors - 2nd Flr E 3 0% 3 27-Nov-19 29-Nov-19 3SE23505.2 HVAC Diffusers & Grills - 2nd Flr E 10 0% 10 27-Nov-19 10-Dec-19 -4SE26500.2 Light Fixtures - 2nd Flr E 10 0% 10 27-Nov-19 10-Dec-19 -4SE09960.2 Paint / Coating - Stair Rails - 2nd Flr E 10 0% 10 28-Nov-19 11-Dec-19 -5SE09772.2 Install FRP Paneling - 2nd Flr E 5 0% 5 05-Dec-19 11-Dec-19 -5SE09650.2 VCT Flooring - 2nd Flr E 10 0% 10 12-Dec-19 25-Dec-19 -5SE09303.2 Ceramic Tile @ Stairs - 2nd Flr E 10 0% 10 17-Dec-19 30-Dec-19 -8SE06411.2 Custom Casework - 2nd Flr E 10 0% 10 26-Dec-19 08-Jan-20 -5SE22440.2 Plumbing Fixtures - 2nd Flr E 10 0% 10 31-Dec-19 13-Jan-20 -3SE06412.2 Arch Woodwork - Tops - 2nd Flr E 10 0% 10 02-Jan-20 15-Jan-20 -5SE22441.2 Plumbing Trim - 2nd Flr E 15 0% 15 14-Jan-20 03-Feb-20 -2SE09911.2 Final Paint - 2nd Flr E 10 0% 10 16-Jan-20 29-Jan-20 -5SE26611.2 Electrical Trim - 2nd Flr E 10 0% 10 20-Jan-20 31-Jan-20 5SE28311.2 FA Devices / Trim - 2nd Flr E 10 0% 10 21-Jan-20 03-Feb-20 -3SE08710.2 Door Hardware - 2nd Flr E 10 0% 10 23-Jan-20 05-Feb-20 -5SE10400.2 Interior Signage - 2nd Flr E 5 0% 5 30-Jan-20 05-Feb-20 5SE26711.2 Elec - Communications - Trim - 2nd Flr E 10 0% 10 30-Jan-20 12-Feb-20 0SE28130.2 Install Access Control - 2nd Flr E 10 0% 10 30-Jan-20 12-Feb-20 0SE09512.2 Ceiling Tile - 2nd Flr E 5 0% 5 04-Feb-20 10-Feb-20 -2SE09681.2 Carpet Tile - 2nd Flr E 5 0% 5 04-Feb-20 10-Feb-20 -2SE22112.2 Plumbing Pump Hook-up - 2nd Flr E 5 0% 5 04-Feb-20 10-Feb-20 2SE28230.2 Install Video System - 2nd Flr E 10 0% 10 04-Feb-20 17-Feb-20 -3SE03352.2 Polish / Seal ConcFloor - 2nd Flr E 2 0% 2 05-Feb-20 06-Feb-20 -2SE10520.2 Fire Extinguishers - 2nd Flr E 5 0% 5 06-Feb-20 12-Feb-20 -5SE09651.2 Rubber Base - 2nd Flr E 3 0% 3 07-Feb-20 11-Feb-20 -2SE12241.2 Roller Shades - 2nd Flr E 3 0% 3 11-Feb-20 13-Feb-20 -1SE10261.2 Corner Guards - 2nd Flr E 3 0% 3 12-Feb-20 14-Feb-20 -2SE10110.2 Install Visual Display Devices - 2nd Flr E 5 0% 5 13-Feb-20 19-Feb-20 -5SE45000.2 Clean up - 2nd Flr E 10 0% 10 20-Feb-20 04-Mar-20 -5SE45001.2 Preliminary Contractor Punch List - 2nd Flr E 10 0% 10 06-Mar-20 19-Mar-20 -6SE45002.2 Architect Inspection - 2nd Flr E 2 0% 2 20-Mar-20 23-Mar-20 -6

2nd Level - W2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West Side2nd Level - West SideSW09211.2 Hang Sheetrock @ Walls - 2nd Flr W 10 0% 10 04-Nov-19 15-Nov-19 -9SW09212.2 FInish Sheetrock @ Walls - 2nd Flr W 10 0% 10 11-Nov-19 22-Nov-19 1

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

23-Mar-20, 2nd Level - East Sid

Hang Sheetrock @ Walls - 2nd Flr EFInish Sheetrock @ Walls - 2nd Flr EHang Sheetrock @ Ceilings - 2nd Flr E

FInish Sheetrock @ Ceilings - 2nd Flr EPaint: Prime - 2nd Flr ESteel Handrails - 2nd Flr ECeramic Tile - 2nd Flr EAcoustic Ceiling Grid - 2nd Flr EInstall Doors - 2nd Flr E

Automatic Glass Doors - 2nd Flr EHVAC Diffusers & Grills - 2nd Flr ELight Fixtures - 2nd Flr EPaint / Coating - Stair Rails - 2nd Flr EInstall FRP Paneling - 2nd Flr E

VCT Flooring - 2nd Flr ECeramic Tile @ Stairs - 2nd Flr E

Custom Casework - 2nd Flr EPlumbing Fixtures - 2nd Flr EArch Woodwork - Tops - 2nd Flr E

Plumbing Trim - 2nd Flr EFinal Paint - 2nd Flr EElectrical Trim - 2nd Flr EFA Devices / Trim - 2nd Flr EDoor Hardware - 2nd Flr EInterior Signage - 2nd Flr EElec - Communications - Trim - 2nd FlInstall Access Control - 2nd Flr ECeiling Tile - 2nd Flr ECarpet Tile - 2nd Flr EPlumbing Pump Hook-up - 2nd Flr EInstall Video System - 2nd Flr E

Polish / Seal ConcFloor - 2nd Flr EFire Extinguishers - 2nd Flr ERubber Base - 2nd Flr ERoller Shades - 2nd Flr ECorner Guards - 2nd Flr EInstall Visual Display Devices - 2nd F

Clean up - 2nd Flr EPreliminary Contractor Punch LArchitect Inspection - 2nd Flr E

13-Apr-20, 2nd Level - West

Hang Sheetrock @ Walls - 2nd Flr WFInish Sheetrock @ Walls - 2nd Flr W

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 19

Page 20: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SW09213.2 Hang Sheetrock @ Ceilings - 2nd Flr W 10 0% 10 11-Nov-19 22-Nov-19 -9SW09214.2 FInish Sheetrock @ Ceilings - 2nd Flr W 10 0% 10 25-Nov-19 06-Dec-19 -9SW09910.2 Paint: Prime - 2nd Flr W 10 0% 10 09-Dec-19 20-Dec-19 -9SW05519.2 Steel Handrails - 2nd Flr W 10 0% 10 16-Dec-19 27-Dec-19 -9SW11532.2 Install Lab Fume Hoods - 2nd Flr W 5 0% 5 16-Dec-19 20-Dec-19 -8SW09300.2 Ceramic Tile - 2nd Flr W 10 0% 10 23-Dec-19 03-Jan-20 -2SW09510.2 Acoustic Ceiling Grid - 2nd Flr W 10 0% 10 23-Dec-19 03-Jan-20 -8SW08142.2 Install Doors - 2nd Flr W 10 0% 10 27-Dec-19 09-Jan-20 -3SW23505.2 HVAC Diffusers & Grills - 2nd Flr W 10 0% 10 27-Dec-19 09-Jan-20 -8SW26500.2 Light Fixtures - 2nd Flr W 10 0% 10 27-Dec-19 09-Jan-20 -8SW09960.2 Paint / Coating - Stair Rails - 2nd Flr W 10 0% 10 30-Dec-19 10-Jan-20 -9SW09303.2 Ceramic Tile @ Stairs - 2nd Flr W 10 0% 10 10-Jan-20 23-Jan-20 -3SW09650.2 VCT Flooring - 2nd Flr W 10 0% 10 13-Jan-20 24-Jan-20 -9SW22440.2 Plumbing Fixtures - 2nd Flr W 10 0% 10 15-Jan-20 28-Jan-20 -9SW06411.2 Custom Casework - 2nd Flr W 10 0% 10 27-Jan-20 07-Feb-20 -8SW10211.2 Toliet Partitions - 2nd Flr W 10 0% 10 29-Jan-20 11-Feb-20 -9SW06412.2 Arch Woodwork - Tops - 2nd Flr W 10 0% 10 03-Feb-20 14-Feb-20 -8SW22441.2 Plumbing Trim - 2nd Flr W 15 0% 15 03-Feb-20 21-Feb-20 1SW10281.2 Toilet Accessories - 2nd Flr W 10 0% 10 04-Feb-20 17-Feb-20 -9SW09911.2 Final Paint - 2nd Flr W 10 0% 10 18-Feb-20 02-Mar-20 -9SW26611.2 Electrical Trim - 2nd Flr W 10 0% 10 20-Feb-20 04-Mar-20 -1SW28311.2 FA Devices / Trim - 2nd Flr W 10 0% 10 21-Feb-20 05-Mar-20 -9SW22112.2 Plumbing Pump Hook-up - 2nd Flr W 5 0% 5 24-Feb-20 28-Feb-20 5SW08710.2 Door Hardware - 2nd Flr W 10 0% 10 25-Feb-20 09-Mar-20 -6SW09512.2 Ceiling Tile - 2nd Flr W 5 0% 5 26-Feb-20 03-Mar-20 -1SW09681.2 Carpet Tile - 2nd Flr W 5 0% 5 26-Feb-20 03-Mar-20 -1SW03352.2 Polish / Seal ConcFloor - 2nd Flr W 2 0% 2 27-Feb-20 28-Feb-20 -1SW09651.2 Rubber Base - 2nd Flr W 3 0% 3 03-Mar-20 05-Mar-20 -2SW10110.2 Install Visual Display Devices - 2nd Flr W 5 0% 5 03-Mar-20 09-Mar-20 -1SW10400.2 Interior Signage - 2nd Flr W 5 0% 5 03-Mar-20 09-Mar-20 -1SW11530.2 Lab Equipment - 2nd Flr W 10 0% 10 03-Mar-20 16-Mar-20 -6SW26711.2 Elec - Communications - Trim - 2nd Flr W 10 0% 10 03-Mar-20 16-Mar-20 -6SW28130.2 Install Access Control - 2nd Flr W 10 0% 10 03-Mar-20 16-Mar-20 -6SW12241.2 Roller Shades - 2nd Flr W 3 0% 3 04-Mar-20 06-Mar-20 0SW10261.2 Corner Guards - 2nd Flr W 3 0% 3 06-Mar-20 10-Mar-20 -2SW28230.2 Install Video System - 2nd Flr W 10 0% 10 06-Mar-20 19-Mar-20 -9SW10520.2 Fire Extinguishers - 2nd Flr W 5 0% 5 10-Mar-20 16-Mar-20 -6SW45000.2 Clean up - 2nd Flr W 5 0% 5 20-Mar-20 26-Mar-20 -9SW45001.2 Preliminary Punch List - 2nd Flr W 10 0% 10 27-Mar-20 09-Apr-20 -9SW45002.2 Architect Inspection - 2nd Flr W 2 0% 2 10-Apr-20 13-Apr-20 -6

3rd Level - Ea3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East Side3rd Level - East SideSE09211.3 Hang Sheetrock @ Walls - 3rd Flr E 10 0% 10 15-Oct-19 28-Oct-19 -2SE09212.3 FInish Sheetrock @ Walls - 3rd Flr E 10 0% 10 22-Oct-19 04-Nov-19 8SE09213.3 Hang Sheetrock @ Ceilings - 3rd Flr E 10 0% 10 22-Oct-19 04-Nov-19 -2

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Hang Sheetrock @ Ceilings - 2nd Flr WFInish Sheetrock @ Ceilings - 2nd Flr W

Paint: Prime - 2nd Flr WSteel Handrails - 2nd Flr W

Install Lab Fume Hoods - 2nd Flr WCeramic Tile - 2nd Flr WAcoustic Ceiling Grid - 2nd Flr WInstall Doors - 2nd Flr WHVAC Diffusers & Grills - 2nd Flr WLight Fixtures - 2nd Flr WPaint / Coating - Stair Rails - 2nd Flr W

Ceramic Tile @ Stairs - 2nd Flr WVCT Flooring - 2nd Flr WPlumbing Fixtures - 2nd Flr W

Custom Casework - 2nd Flr WToliet Partitions - 2nd Flr WArch Woodwork - Tops - 2nd Flr W

Plumbing Trim - 2nd Flr WToilet Accessories - 2nd Flr W

Final Paint - 2nd Flr WElectrical Trim - 2nd Flr WFA Devices / Trim - 2nd Flr W

Plumbing Pump Hook-up - 2nd Flr Door Hardware - 2nd Flr W

Ceiling Tile - 2nd Flr WCarpet Tile - 2nd Flr WPolish / Seal ConcFloor - 2nd Flr WRubber Base - 2nd Flr WInstall Visual Display Devices - 2nInterior Signage - 2nd Flr WLab Equipment - 2nd Flr WElec - Communications - Trim - 2Install Access Control - 2nd Flr W

Roller Shades - 2nd Flr WCorner Guards - 2nd Flr W

Install Video System - 2nd Flr WFire Extinguishers - 2nd Flr W

Clean up - 2nd Flr WPreliminary Punch List - 2ndArchitect Inspection - 2nd F15-Apr-20, 3rd Level - East

Hang Sheetrock @ Walls - 3rd Flr EFInish Sheetrock @ Walls - 3rd Flr EHang Sheetrock @ Ceilings - 3rd Flr E

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 20

Page 21: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SE09214.3 FInish Sheetrock @ Ceilings - 3rd Flr E 10 0% 10 05-Nov-19 18-Nov-19 -2SE09910.3 Paint: Prime - 3rd Flr E 10 0% 10 19-Nov-19 02-Dec-19 -2SE05519.3 Steel Handrails - 3rd Flr E 10 0% 10 26-Nov-19 09-Dec-19 7SE09300.3 Ceramic Tile - 3rd Flr E 10 0% 10 03-Dec-19 16-Dec-19 2SE09510.3 Acoustic Ceiling Grid - 3rd Flr E 10 0% 10 03-Dec-19 16-Dec-19 -2SE08142.3 Install Doors - 3rd Flr E 10 0% 10 09-Dec-19 20-Dec-19 -2SE23505.3 HVAC Diffusers & Grills - 3rd Flr E 10 0% 10 09-Dec-19 20-Dec-19 8SE26500.3 Light Fixtures - 3rd Flr E 10 0% 10 09-Dec-19 20-Dec-19 8SE09960.3 Paint / Coating - Stair Rails - 3rd Flr E 10 0% 10 10-Dec-19 23-Dec-19 7SE09772.3 Install FRP Paneling - 3rd Flr E 5 0% 5 17-Dec-19 23-Dec-19 7SE09303.3 Ceramic Tile @ Stairs - 3rd Flr E 10 0% 10 31-Dec-19 13-Jan-20 -8SE09650.3 VCT Flooring - 3rd Flr E 10 0% 10 14-Jan-20 27-Jan-20 -8SE22440.3 Plumbing Fixtures - 3rd Flr E 10 0% 10 16-Jan-20 29-Jan-20 0SE06411.3 Custom Casework - 3rd Flr E 10 0% 10 28-Jan-20 10-Feb-20 -8SE22441.3 Plumbing Trim - 3rd Flr E 15 0% 15 30-Jan-20 19-Feb-20 0SE09911.3 Final Paint - 3rd Flr E 10 0% 10 11-Feb-20 24-Feb-20 -8SE26611.3 Electrical Trim - 3rd Flr E 10 0% 10 13-Feb-20 26-Feb-20 -4SE28311.3 FA Devices / Trim - 3rd Flr E 10 0% 10 14-Feb-20 27-Feb-20 -6SE08710.3 Door Hardware - 3rd Flr E 10 0% 10 18-Feb-20 02-Mar-20 -8SE09512.3 Ceiling Tile - 3rd Flr E 5 0% 5 19-Feb-20 25-Feb-20 -4SE09681.3 Carpet Tile - 3rd Flr E 5 0% 5 19-Feb-20 25-Feb-20 -4SE03352.3 Polish / Seal ConcFloor - 3rd Flr E 4 0% 4 20-Feb-20 25-Feb-20 -4SE22112.3 Plumbing Pump Hook-up - 3rd Flr E 5 0% 5 20-Feb-20 26-Feb-20 0SE10400.3 Interior Signage - 3rd Flr E 5 0% 5 25-Feb-20 02-Mar-20 2SE26711.3 Elec - Communications - Trim - 3rd Flr E 10 0% 10 25-Feb-20 09-Mar-20 -3SE28130.3 Install Access Control - 3rd Flr E 10 0% 10 25-Feb-20 09-Mar-20 -3SE09651.3 Rubber Base - 3rd Flr E 3 0% 3 26-Feb-20 28-Feb-20 0SE12241.3 Roller Shades - 3rd Flr E 3 0% 3 26-Feb-20 28-Feb-20 3SE28230.3 Install Video System - 3rd Flr E 10 0% 10 28-Feb-20 12-Mar-20 -6SE10262.3 Corner Guards - 3rd Flr E 3 0% 3 02-Mar-20 04-Mar-20 0SE10520.3 Fire Extinguishers - 3rd Flr E 5 0% 5 03-Mar-20 09-Mar-20 -8SE10110.3 Install Visual Display Devices - 3rd Flr E 5 0% 5 10-Mar-20 16-Mar-20 -8SE45000.3 Clean up - 3rd Flr E 10 0% 10 17-Mar-20 30-Mar-20 -8SE45001.3 Preliminary Contractor Punch List - 3rd Flr E 10 0% 10 31-Mar-20 13-Apr-20 -8SE45002.3 Architect Inspection - 3rd Flr E 2 0% 2 14-Apr-20 15-Apr-20 -8

3rd Level - W3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West Side3rd Level - West SideSW09211.3 Hang Sheetrock @ Walls - 3rd Flr W 10 0% 10 13-Nov-19 26-Nov-19 -6SW09212.3 FInish Sheetrock @ Walls - 3rd Flr W 10 0% 10 20-Nov-19 03-Dec-19 4SW09213.3 Hang Sheetrock @ Ceilings - 3rd Flr W 10 0% 10 20-Nov-19 03-Dec-19 -6SW09214.3 FInish Sheetrock @ Ceilings - 3rd Flr W 10 0% 10 04-Dec-19 17-Dec-19 -6SW09910.3 Paint: Prime - 3rd Flr W 10 0% 10 18-Dec-19 31-Dec-19 -6SW05519.3 Steel Handrails - 3rd Flr W 10 0% 10 25-Dec-19 07-Jan-20 -6SW11532.3 Install Lab Fume Hoods - 3rd Flr W 10 0% 10 25-Dec-19 07-Jan-20 -5SW09300.3 Ceramic Tile - 3rd Flr W 10 0% 10 01-Jan-20 14-Jan-20 9

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

FInish Sheetrock @ Ceilings - 3rd Flr EPaint: Prime - 3rd Flr ESteel Handrails - 3rd Flr ECeramic Tile - 3rd Flr EAcoustic Ceiling Grid - 3rd Flr EInstall Doors - 3rd Flr EHVAC Diffusers & Grills - 3rd Flr ELight Fixtures - 3rd Flr EPaint / Coating - Stair Rails - 3rd Flr EInstall FRP Paneling - 3rd Flr E

Ceramic Tile @ Stairs - 3rd Flr EVCT Flooring - 3rd Flr EPlumbing Fixtures - 3rd Flr E

Custom Casework - 3rd Flr EPlumbing Trim - 3rd Flr EFinal Paint - 3rd Flr EElectrical Trim - 3rd Flr EFA Devices / Trim - 3rd Flr EDoor Hardware - 3rd Flr E

Ceiling Tile - 3rd Flr ECarpet Tile - 3rd Flr EPolish / Seal ConcFloor - 3rd Flr EPlumbing Pump Hook-up - 3rd Flr EInterior Signage - 3rd Flr EElec - Communications - Trim - 3rInstall Access Control - 3rd Flr E

Rubber Base - 3rd Flr ERoller Shades - 3rd Flr E

Install Video System - 3rd Flr ECorner Guards - 3rd Flr EFire Extinguishers - 3rd Flr EInstall Visual Display Devices - 3

Clean up - 3rd Flr EPreliminary Contractor PunArchitect Inspection - 3rd F16-Apr-20, 3rd Level - West

Hang Sheetrock @ Walls - 3rd Flr WFInish Sheetrock @ Walls - 3rd Flr WHang Sheetrock @ Ceilings - 3rd Flr W

FInish Sheetrock @ Ceilings - 3rd Flr WPaint: Prime - 3rd Flr WSteel Handrails - 3rd Flr WInstall Lab Fume Hoods - 3rd Flr WCeramic Tile - 3rd Flr W

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 21

Page 22: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SW09510.3 Acoustic Ceiling Grid - 3rd Flr W 10 0% 10 01-Jan-20 14-Jan-20 -5SW08142.3 Install Doors - 3rd Flr W 10 0% 10 07-Jan-20 20-Jan-20 0SW23505.3 HVAC Diffusers & Grills - 3rd Flr W 10 0% 10 07-Jan-20 20-Jan-20 -5SW26500.3 Light Fixtures - 3rd Flr W 10 0% 10 07-Jan-20 20-Jan-20 -5SW09960.3 Paint / Coating - Stair Rails - 3rd Flr W 10 0% 10 08-Jan-20 21-Jan-20 -6SW09303.3 Ceramic Tile @ Stairs - 3rd Flr W 10 0% 10 17-Jan-20 30-Jan-20 -3SW09650.3 VCT Flooring - 3rd Flr W 10 0% 10 22-Jan-20 04-Feb-20 -6SW22440.3 Plumbing Fixtures - 3rd Flr W 10 0% 10 24-Jan-20 06-Feb-20 2SW06411.3 Custom Casework - 3rd Flr W 10 0% 10 05-Feb-20 18-Feb-20 -6SW22441.3 Plumbing Trim - 3rd Flr W 15 0% 15 07-Feb-20 27-Feb-20 4SW08710.3 Door Hardware - 3rd Flr W 10 0% 10 19-Feb-20 03-Mar-20 -4SW09911.3 Final Paint - 3rd Flr W 10 0% 10 19-Feb-20 03-Mar-20 -6SW26611.3 Electrical Trim - 3rd Flr W 10 0% 10 21-Feb-20 05-Mar-20 -6SW28311.3 FA Devices / Trim - 3rd Flr W 10 0% 10 24-Feb-20 06-Mar-20 -2SE12352.3 Install Lab Casework - 3rd Flr - W 5 0% 5 26-Feb-20 03-Mar-20 -4SW09681.3 Carpet Tile - 3rd Flr W 5 0% 5 27-Feb-20 04-Mar-20 -4SW22112.3 Plumbing Pump Hook-up - 3rd Flr W 5 0% 5 28-Feb-20 05-Mar-20 4SW09512.3 Ceiling Tile - 3rd Flr W 5 0% 5 02-Mar-20 06-Mar-20 -4SW28230.3 Install Video System - 3rd Flr W 10 0% 10 02-Mar-20 13-Mar-20 -2SE11500.3 Install Lab Equipment - 3rd Flr - W 5 0% 5 04-Mar-20 10-Mar-20 -4SW03352.3 Polish / Seal ConcFloor - 3rd Flr W 4 0% 4 04-Mar-20 09-Mar-20 -4SW10400.3 Interior Signage - 3rd Flr W 5 0% 5 04-Mar-20 10-Mar-20 1SW10520.3 Fire Extinguishers - 3rd Flr W 5 0% 5 04-Mar-20 10-Mar-20 -4SW28130.3 Install Access Control - 3rd Flr W 10 0% 10 04-Mar-20 17-Mar-20 -4SW12241.3 Roller Shades - 3rd Flr W 3 0% 3 05-Mar-20 09-Mar-20 2SW26711.3 Elec - Communications - Trim - 3rd Flr W 10 0% 10 06-Mar-20 19-Mar-20 -6SW09651.3 Rubber Base - 3rd Flr W 3 0% 3 10-Mar-20 12-Mar-20 -4SW10110.3 Install Visual Display Devices - 3rd Flr W 5 0% 5 11-Mar-20 17-Mar-20 -4SW09777.3 install PCP Panels @ Chem Lab - 3rd Flr W 3 0% 3 13-Mar-20 17-Mar-20 -4SW10262.3 Corner Guards - 3rd Flr W 3 0% 3 13-Mar-20 17-Mar-20 -4SW45000.3 Clean up - 3rd Flr W 7 0% 7 20-Mar-20 30-Mar-20 -6SW45001.3 PrelIminary Punch List - 3rd Flr W 9 0% 9 03-Apr-20 15-Apr-20 -9SW45002.3 Architect Inspection - 3rd Flr W 1 0% 1 16-Apr-20 16-Apr-20 -9

CUP RampCUP RampCUP RampCUP RampCUP RampCUP RampCUP RampCUP RampCU02411.0 Demolition / Earthwork Exist Ramp - CUP 10 100% 0 26-Oct-18 A 05-Nov-18 ACU31234.0 Excavate / Grade - CUP Ramp 5 0% 5 01-Jul-19 05-Jul-19 82CU03300.0 F/R/P Conc Stairs - CUP Ramp 10 0% 10 08-Jul-19 19-Jul-19 92CU26052.0 Elec - U/G Rough-in - CUP Ramp 5 0% 5 08-Jul-19 12-Jul-19 82CU32840.0 Irrigation Sleeves - CUP Ramp 2 0% 2 08-Jul-19 09-Jul-19 90CU32113.0 Aggregate Base @ Ramp - CUP Ramp 5 0% 5 15-Jul-19 19-Jul-19 82CU00420.0 Block Retaining Wall @ Ramp - CUP 10 0% 10 22-Jul-19 02-Aug-19 82CU32161.0 F/R/P Conc Ramp Walkway - CUP Ramp 15 0% 15 05-Aug-19 23-Aug-19 82CU05520.0 Hand Rails - CUP Ramp 5 0% 5 03-Sep-19 09-Sep-19 77CU07281.R Pedestrian Traffic Coating - CUP Roof 5 0% 5 20-Sep-19 26-Sep-19 122

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Acoustic Ceiling Grid - 3rd Flr WInstall Doors - 3rd Flr WHVAC Diffusers & Grills - 3rd Flr WLight Fixtures - 3rd Flr WPaint / Coating - Stair Rails - 3rd Flr W

Ceramic Tile @ Stairs - 3rd Flr WVCT Flooring - 3rd Flr WPlumbing Fixtures - 3rd Flr W

Custom Casework - 3rd Flr WPlumbing Trim - 3rd Flr WDoor Hardware - 3rd Flr WFinal Paint - 3rd Flr WElectrical Trim - 3rd Flr WFA Devices / Trim - 3rd Flr WInstall Lab Casework - 3rd Flr - WCarpet Tile - 3rd Flr WPlumbing Pump Hook-up - 3rd FlrCeiling Tile - 3rd Flr WInstall Video System - 3rd Flr WInstall Lab Equipment - 3rd Flr - WPolish / Seal ConcFloor - 3rd Flr WInterior Signage - 3rd Flr WFire Extinguishers - 3rd Flr WInstall Access Control - 3rd Flr W

Roller Shades - 3rd Flr WElec - Communications - Trim -

Rubber Base - 3rd Flr WInstall Visual Display Devices - 3install PCP Panels @ Chem LabCorner Guards - 3rd Flr W

Clean up - 3rd Flr WPrelIminary Punch List - 3rdArchitect Inspection - 3rd F

16-Oct-19, CUP Ramp

Demolition / Earthwork Exist Ramp - CUPExcavate / Grade - CUP Ramp

F/R/P Conc Stairs - CUP RampElec - U/G Rough-in - CUP RampIrrigation Sleeves - CUP Ramp

Aggregate Base @ Ramp - CUP RampBlock Retaining Wall @ Ramp - CUP

F/R/P Conc Ramp Walkway - CUP RampHand Rails - CUP Ramp

Pedestrian Traffic Coating - CUP Roof

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 22

Page 23: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

CU05522.R Hand Rails - CUP Roof 5 0% 5 27-Sep-19 03-Oct-19 64CU07542,R Membrane Roofing - CUP Roof 5 0% 5 03-Oct-19 09-Oct-19 122CU07900.R Ext Joint Sealants - CUP Roof 5 0% 5 10-Oct-19 16-Oct-19 122

CUP Bldg ReCUP Bldg RenovationsCUP Bldg RenovationsCUP Bldg RenovationsCUP Bldg RenovationsCUP Bldg RenovationsCUP Bldg RenovationsCUP Bldg RenovationsCU23052.0 Install Pipe Supports - CUP 10 100% 0 08-Oct-18 A 19-Oct-18 ACU23211.0 HVAC - CW & HW Piping - CUP 15 100% 0 15-Oct-18 A 29-Nov-18 ACU26051.0 Elec - Rough-in - CUP 10 100% 0 29-Oct-18 A 30-Nov-18 ACU22112.0 Plbg - Piping Rough-in - CUP 9 100% 0 02-Dec-18 A 27-Dec-18 ACU26053.0 Elec - Install Cable Tray - CUP 10 100% 0 11-Dec-18 A 17-Jan-19 ACU02415.0 Elect Demolition - CUP 10 100% 0 21-Dec-18 A 15-Jan-19 ACU02413.0 Plumbing Demolition - CUP 10 100% 0 26-Dec-18 A 10-Jan-19 ACU26054.0 Elec - Install Comm Cable - CUP 5 100% 0 26-Dec-18 A 27-Dec-18 ACU26382.0 Elec - Transfer Switch - CUP 5 100% 0 23-Jan-19 A 31-Jan-19 ACU21010.0 Fire Sprinkler Main Piping - CUP 10 0% 10 01-Jul-19 12-Jul-19 30CU26241.0 Elec - Panels - CUP 10 0% 10 08-Jul-19 19-Jul-19 150CU26270.0 Elec - Wiring - CUP 10 0% 10 22-Jul-19 02-Aug-19 150CU02414.0 HVAC Demolition - CUP 20 0% 20 15-Aug-19 12-Sep-19 64

CUP RoofCUP RoofCUP RoofCUP RoofCUP RoofCUP RoofCUP RoofCUP RoofCU02410.R Selective Demolition - CUP Roof 5 100% 0 13-May-19 A 30-May-19 ACU03450.R Demo Precast Concrete @ Roof 5 100% 0 28-May-19 A 04-Jun-19 ACU03302.R F/R/P Conc Curbs - CUP Roof 10 100% 0 03-Jun-19 A 21-Jun-19 ACU07141.R HRA Waterproofing - CUP Roof 4 100% 0 17-Jun-19 A 27-Jun-19 ACU02411.R Plumb Demolition Roof Drains - CUP Roof 2 0% 2 01-Jul-19 02-Jul-19 98CU05521.R Guard Rails - CUP Roof 10 0% 10 01-Jul-19 12-Jul-19 112CU02414.R Core Conc Roof Drains - CUP Roof 2 0% 2 03-Jul-19 04-Jul-19 98CU22131.R Plumb Roof Drains - CUP Roof 5 0% 5 05-Jul-19 11-Jul-19 98CU23112.R HVAC Demo Exhaust Stacks - CUP Roof 5 0% 5 22-Aug-19 28-Aug-19 64CU23510.R Install HVAC - Exhaust Flues - CUP Roof 4 0% 4 26-Aug-19 29-Aug-19 131CU05310.R Metal Decking Infill @ Demo - CUP Roof 2 0% 2 29-Aug-19 30-Aug-19 64CU05050.R Replace Grates & Frames - CUP Roof 2 0% 2 30-Aug-19 03-Sep-19 131CU03301.R F/R/P Conc Infill @ Demo - CUP Roof 3 0% 3 03-Sep-19 05-Sep-19 64CU26092.R Elec - Lighting Control - CUP Roof 1 0% 1 04-Sep-19 04-Sep-19 131CU03303.R F/P/R Conc Landing - CUP Roof 5 0% 5 06-Sep-19 12-Sep-19 64CU03351.R Clean / Seal Existing Conc - CUP Roof 3 0% 3 06-Sep-19 10-Sep-19 138CU26052.R Elec - Rough-in - CUP Roof 3 0% 3 06-Sep-19 10-Sep-19 127CU26560 Elec - Lighting Fixtures - CUP Roof 2 0% 2 11-Sep-19 12-Sep-19 127CU03451.R Precast Arch Conc Ramp - CUP Roof 10 0% 10 13-Sep-19 26-Sep-19 64CU04255.R Pavers - CUP Roof 4 0% 4 27-Sep-19 02-Oct-19 122

Site ImprovemSite ImprovementsSite ImprovementsSite ImprovementsSite ImprovementsSite ImprovementsSite ImprovementsSite ImprovementsSI31200 Site Clearing - Pond 5 100% 0 25-Sep-18 A 27-Sep-18 ASI31235 Excavate / Fill Pond 9 100% 0 27-Sep-18 A 16-Nov-18 ASI31210 Site Clearing / Demolition - Site 10 100% 0 09-Jan-19 A 22-Feb-19 ASI02411 Elec Demolition - Site 10 100% 0 20-Feb-19 A 21-Feb-19 A

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Hand Rails - CUP RoofMembrane Roofing - CUP RoofExt Joint Sealants - CUP Roof

12-Sep-19, CUP Bldg Renovations

Install Pipe Supports - CUPHVAC - CW & HW Piping - CUPElec - Rough-in - CUP

Plbg - Piping Rough-in - CUPElec - Install Cable Tray - CUPElect Demolition - CUP

Plumbing Demolition - CUPElec - Install Comm Cable - CUP

Elec - Transfer Switch - CUPFire Sprinkler Main Piping - CUPElec - Panels - CUP

Elec - Wiring - CUPHVAC Demolition - CUP

02-Oct-19, CUP Roof

Selective Demolition - CUP RoofDemo Precast Concrete @ Roof

F/R/P Conc Curbs - CUP RoofHRA Waterproofing - CUP RoofPlumb Demolition Roof Drains - CUP Roof

Guard Rails - CUP RoofCore Conc Roof Drains - CUP Roof

Plumb Roof Drains - CUP RoofHVAC Demo Exhaust Stacks - CUP RoofInstall HVAC - Exhaust Flues - CUP RoofMetal Decking Infill @ Demo - CUP RoofReplace Grates & Frames - CUP RoofF/R/P Conc Infill @ Demo - CUP RoofElec - Lighting Control - CUP Roof

F/P/R Conc Landing - CUP RoofClean / Seal Existing Conc - CUP RoofElec - Rough-in - CUP RoofElec - Lighting Fixtures - CUP Roof

Precast Arch Conc Ramp - CUP RoofPavers - CUP Roof

01-Apr-20, Site Improvements

Site Clearing - PondExcavate / Fill Pond

Site Clearing / Demolition - SiteElec Demolition - Site

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 23

Page 24: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

SI33400 Storm Drainage - Piping - Site 10 100% 0 21-Feb-19 A 06-Mar-19 ASI33402 Storm Drainage - Rain Water Leaders - Site 10 100% 0 04-Mar-19 A 25-Mar-19 ASI33401 Storm Dranage Catch Basins - Site 10 100% 0 07-Mar-19 A 12-Apr-19 ASI32131 Temporary Fire Lane - Prep / Paving 5 100% 0 20-Mar-19 A 21-Mar-19 ASI31203 Earthwork - Site 10 100% 0 25-Mar-19 A 16-Apr-19 ASI26054 Electrical U/G - Primary / Secondary / Generator 5 100% 0 08-Apr-19 A 16-Apr-19 ASI03300 F/R/P Conc Retaining Walls Fnd - Site 10 100% 0 17-Apr-19 A 22-Apr-19 ASI03301 F/R/P Conc Retaining Walls - Site 15 100% 0 23-Apr-19 A 03-Jun-19 ASI33411 Pre-cast Detention Vault 20 100% 0 06-May-19 A 31-May-19 ASI31236 Backfill / Compact Subgrade - Site 10 100% 0 19-Jun-19 A 27-Jun-19 ASI32123 Asphalt - West Site 5 40% 3 27-Jun-19 A 03-Jul-19 78SI26053 Electrical U/G Rough-In - Site 10 0% 10 01-Jul-19 12-Jul-19 70SI31246 Aggregate Base - West Site 5 0% 5 01-Jul-19 05-Jul-19 268SI33132 F/R/P Concrete Curbs - Site 15 0% 15 15-Jul-19 02-Aug-19 70SI31233 Backfill Curbs / Grade - Site 10 0% 10 05-Aug-19 16-Aug-19 70SI26063 Elec - Pull Wiring - Site 10 0% 10 19-Aug-19 30-Aug-19 77SI32161 F/R/P Conc Sidewalks - Site 10 0% 10 19-Aug-19 30-Aug-19 70SI31258 F/R/P Sog - Dumpster Enclosure - Site 5 0% 5 20-Aug-19 26-Aug-19 96SI03302 F/R/P Conc Stairs / Landings - Site 10 0% 10 27-Aug-19 10-Sep-19 64SI32310 Galvanized Fence & Gates - Site 10 0% 10 03-Sep-19 16-Sep-19 92SI05510 Install Bollards - Site 10 0% 10 03-Sep-19 16-Sep-19 77SI27050 Comm - Pull Wiring - Site 10 0% 10 03-Sep-19 16-Sep-19 77SI31234 Backfill Sidewalks - Site 5 0% 5 03-Sep-19 09-Sep-19 70SI32113 Aggregate Base - Site 10 0% 10 10-Sep-19 23-Sep-19 70SI32840 Irrigation Piping - Site 10 0% 10 10-Sep-19 23-Sep-19 87SI03303 F/R/P Conc Ramp Walls - Site 10 0% 10 11-Sep-19 24-Sep-19 64SI32121 Asphalt Base Course - Site 5 0% 5 24-Sep-19 30-Sep-19 70SI31237 Backfill / Compact Ramp - Site 2 0% 2 25-Sep-19 26-Sep-19 64SI26030 Elec Reinstall Poles & Fixtures - Site 10 0% 10 26-Sep-19 09-Oct-19 70SI03304 F/R/P Conc Ramp Slab - Site 5 0% 5 27-Sep-19 03-Oct-19 64SI05520 Hand Rails / Guard Rails - Site 15 0% 15 04-Oct-19 24-Oct-19 64SI28230 Video System / Cameras - Site 10 0% 10 10-Oct-19 23-Oct-19 80SI32122 Asphalt Surface Course - Site 5 0% 5 10-Oct-19 16-Oct-19 70SI31248 Finish Grade - Site 10 0% 10 25-Oct-19 07-Nov-19 64SI26560 Elec - Lighting Fixtures & Controls - Site 7 0% 7 01-Nov-19 11-Nov-19 67SI32841 Irrigation Heads / Device - Site 10 0% 10 01-Nov-19 14-Nov-19 64SI32930 Landscaping / Grassing - Site 15 0% 15 15-Nov-19 05-Dec-19 64SI11123 Install Lift Arm Parking Gates - Site 5 0% 5 04-Feb-20 10-Feb-20 2SI32172 Parking Lot Striping - Site 5 0% 5 11-Feb-20 17-Feb-20 2SI12930 Site Signage & Furnishings - Site 10 0% 10 18-Feb-20 02-Mar-20 2SI45000 Clean Up - Site 10 0% 10 03-Mar-20 16-Mar-20 2CL45504 HVAC - Test & Balance 15 0% 15 09-Mar-20 27-Mar-20 5SI45001 Pre Punch List - Site 10 0% 10 17-Mar-20 30-Mar-20 2SI45002 Architect Inspection - Site 2 0% 2 31-Mar-20 01-Apr-20 2

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

Storm Drainage - Piping - SiteStorm Drainage - Rain Water Leaders - Site

Storm Dranage Catch Basins - SiteTemporary Fire Lane - Prep / Paving

Earthwork - SiteElectrical U/G - Primary / Secondary / GeneratorF/R/P Conc Retaining Walls Fnd - Site

F/R/P Conc Retaining Walls - SitePre-cast Detention Vault

Backfill / Compact Subgrade - SiteAsphalt - West Site

Electrical U/G Rough-In - SiteAggregate Base - West Site

F/R/P Concrete Curbs - SiteBackfill Curbs / Grade - Site

Elec - Pull Wiring - SiteF/R/P Conc Sidewalks - Site

F/R/P Sog - Dumpster Enclosure - SiteF/R/P Conc Stairs / Landings - SiteGalvanized Fence & Gates - SiteInstall Bollards - SiteComm - Pull Wiring - Site

Backfill Sidewalks - SiteAggregate Base - SiteIrrigation Piping - SiteF/R/P Conc Ramp Walls - SiteAsphalt Base Course - Site

Backfill / Compact Ramp - SiteElec Reinstall Poles & Fixtures - Site

F/R/P Conc Ramp Slab - SiteHand Rails / Guard Rails - SiteVideo System / Cameras - Site

Asphalt Surface Course - SiteFinish Grade - SiteElec - Lighting Fixtures & Controls - SiteIrrigation Heads / Device - Site

Landscaping / Grassing - SiteInstall Lift Arm Parking Gates - SiteParking Lot Striping - Site

Site Signage & Furnishings - SiteClean Up - Site

HVAC - Test & BalancePre Punch List - SiteArchitect Inspection - Site

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 24

Page 25: SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE …SCIENCE / SCIENCE / ENGINEERING & TECHNOLOGYE Milestones M-01042.0 Notice To Proceed 0 100% 009-Aug-18 A M-01043.0 Site Preconstruction

Activity ID Activity Name OriginalDuration

%Complete

Remaining Duration

Start Finish TotalFloat

Seaview HallSeaview HallSeaview HallSeaview HallSeaview HallSeaview HallSeaview HallSeaview HallSH-21000 Fire Sprinkler Main Piping @ Exist - SVH 5 0% 5 15-Jul-19 19-Jul-19 30SH-21001 Fire Sprinkler Main Piping @ Exist - UT 5 0% 5 29-Jul-19 02-Aug-19 30

Mount Lake TMount Lake Terrace HallMount Lake Terrace HallMount Lake Terrace HallMount Lake Terrace HallMount Lake Terrace HallMount Lake Terrace HallMount Lake Terrace HallMH02411 Temporary Enclosure Of Entrance 2 100% 0 25-Sep-18 A 03-Oct-18 AMH-02412 Demolish Precast Conc Bridge 10 100% 0 02-Oct-18 A 15-Oct-18 AMH-08411 Install Infill Storefront 5 0% 5 17-Jul-19 23-Jul-19 182MH-21000 Fire Sprinkler Main Piping @ Exist - MLTH 5 0% 5 22-Jul-19 26-Jul-19 30MH-02413 Remove Barricades 1 0% 1 24-Jul-19 24-Jul-19 181

CompletionCompletionCompletionCompletionCompletionCompletionCompletionCompletionCL45500 Substantial Completion 0 0% 0 16-Apr-20 -9CL45501 Punchlist Adjustments 64 0% 64 17-Apr-20 15-Jul-20 -8CL45502 Closeout 40 0% 40 21-Apr-20 15-Jun-20 14CL45503 Final Completion 0 0% 0 15-Jul-20 -8

Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sepr 3, 2018 Qtr 4, 2018 Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019 Qtr 1, 2020 Qtr 2, 2020 Qtr 3, 2020

02-Aug-19, Seaview Hall

Fire Sprinkler Main Piping @ Exist - SVHFire Sprinkler Main Piping @ Exist - UT

26-Jul-19, Mount Lake Terrace Hall

Temporary Enclosure Of EntranceDemolish Precast Conc Bridge

Install Infill StorefrontFire Sprinkler Main Piping @ Exist - MLTHRemove Barricades

15-Jul-20, C

Substantial CompletionPunchlist A

CloseoutFinal Comp

SCIENCE / ENGINEERING TECHNOLOGY KASSEL & ASSOCIATES Data Date 01-Jul-19

Actual WorkRemaining Work

Critical Remaining WorkMilestone

Summary June 2019 Update 25