Overview
Review of Organizational Elements andMaster Data
Overview of Projects using the PS moduleand how it is integrated with othermodules in the R/3 System
Become familiar with the basic functions inthe PS module
8/12/2019 SAP PS Module
3/38
PS
Organizational Areas in R/3
Accounting
Cost accounting
Production
Sales organization
Sales area
Purc.organization
Company code
Business area
Controlling area
Prof.segment
FM
area
Human resources
Personnel
area
Planning
Plant
Treasury
Sales
Purchasing
Warehouse
Plant Maintenance/
Service
Plant
8/12/2019 SAP PS Module
4/38
Organizational Structures: Accounting
Controlling area
1000
Company code
1000
Fin.mgt area
1000
Company code
1000
Company code
2000
Business
area 4000
Business
area 6000
Business
area 1000
Business
area 2000
Business
area 4000
Operating concern
IDEA
8/12/2019 SAP PS Module
5/38
Valuation level
Organizational Structure: Logistics
Storage loc.003
(WMS store)
Controlling area
1000
Company code
1000
Sales organization
0001
Sales path
01
Division 06
Division 08
Plant 1200
Plant 1300
Shipping point
0006
Shipping point
1200
Storage location
0001
Storage location
0002
Purchasing organization
1000
8/12/2019 SAP PS Module
6/38
Organizational Elements and Master
Data
Operating Concern - (CO) Part of organization forwhich the sales market is structured in a uniformmanner (product group, customer group) cancontain >1 controlling area
Controlling Area - (CO) Identifies a self-contained,organizational unit within a group, for which costaccounting can be performed
Company Code - (FI) Smallest organ unit for which acomplete self-contained set of accounts can bedrawn up for purposes of external reporting
8/12/2019 SAP PS Module
7/38
Organizational Elements and Master
Data
Division -(SD) Based on responsibility for sales or profitsfrom salable materials or services
Plant - (LO) Within Logistics, a place where either materials
are produced or goods and services are provided. Assumesvariety of roles (Maintenance Plant, retail or wholesale site)
Storage Location - (LO) Allows the differentiation ofmaterials stocks within a plant
Shipping Points - (SD) Fixed location that carries out shippingactivities (companys mail department)
8/12/2019 SAP PS Module
8/38
Organizational Elements and Master
Data
Business Area - (FI) Represents a separate area of operations orresponsibilities within an organization. Can have several CompanyCodes
Purchasing Organization - (MM) Procures materials and services,negotiates conditions of purchase with vendors, and bearresponsibilities for such transaction
Sales Organization - (SD) Sells and distributes products, negotiatesterms of sales, and is responsible for these transaction
Organizational Structure is prerequisite for making correct application
- specific system setting in customizing - it is the framework
8/12/2019 SAP PS Module
9/38
Cost center
Cost element
Activity type
Profit Center
Master Data Central FunctionsClasses
Characteristics
Object dependencies
Documents
Person
Qualification
profile
Human Resources
Treasury
Commt
item
Capital investment management
Purchasing
Material
Activity master
Vendor
Purc.info record
Work center
BOM
PRT
G/L account
Chart of accounts
Plant Maintenance/
ServiceEquipment
Asset
CI program
Accounting
Network
Production
WBS
Cost Acctg
8/12/2019 SAP PS Module
10/38
Controlling Levels
Capital Investment Costs Revenues
Personnel Assets Materials Departments
Result
Resources
Value Time
Vendor CustomerS & DProduct ionProcurement
Management
Controlling
Execution
8/12/2019 SAP PS Module
11/38
Project TasksCross-department
AgreementsHierarchy
of tasks
Planning and Controlling
Production
AccountingSales
Costs
Dates
Resources
Purchasing
Budget
8/12/2019 SAP PS Module
12/38
Overview of Projects Tasks with particular characteristics
Complex, unique, and involve a high degree of risk Limited duration, and cost and capital intensive
To execute a project: Need a project-specific organizational form
Must describe the project objective Structure the project activities you want toperform Structured according to:
How it is organized using Work BreakdownStructure (WBS) The processes involved using Networks
8/12/2019 SAP PS Module
13/38
- Investment
- Marketing- Make-to-order
production
- Asset
construction
- Shutdown
- Services
- Plantmaintenance
- R & D
- EDP projects
- Structures
- Time scheduling- Project plannimg
board
- Cost planning
- Financial data
- Budget
- Info system
Use Views
- Materials
Management
- Cash Management- Resources
- Operating results
- Controlling
- Periodic processing
- Configuration
- Workflow
- Investment
Management
PSFunctions
Project System
8/12/2019 SAP PS Module
14/38
IntegrationPPSD
Quotation
Order
Billing
document
Purchase requisition
Purchase orderGoods receipt
Invoice receipt
Material issue
CO
FI
Order
SurchargesDistribution
Assessment
Activity allocation
Invoice
Asset under
construction
Settlement
Plant maintenance
order
Settlement
Plan order
Production order
Settlement
PM AM
MM
8/12/2019 SAP PS Module
15/38
Integration of Financial Data
Purchaserequisition Purchaseorder
Down paymentrequest
Quotation
Financial
budget
Expenditure
Revenue
PaymentBankclearing
Goodsissue
Downpayment
Bankclearing
Invoiceissue
PaymentSalesorder Down
paymentrequest
Downpayment
Delivery
Invoicereceipt
FI
SD
MM
FI
PS
> 3.0
> 3.0
> 3.0
8/12/2019 SAP PS Module
16/38
Integration Example: Vendor Down
PaymentPurchase
order item
Down payment clearing
Invoice checked against
down payment document
Down payment
Invoice
Payment
Difference between
invoice and down
payment clearing
Down payment
request
8/12/2019 SAP PS Module
17/38
Integration Example: Purchasing
Ordering
Invoiceverification
BE
Goodsreceipt
Purchaserequisition
Purchase order
monitoring
Bid
invitation
Entry of
quotation
Vendor
selection
?=
8/12/2019 SAP PS Module
18/38
Function Model (5)Status/
Phase
Projectdefinition
Network
Workbreakdownstructure
.
.
.Budget
Release. . .
PPorder
.
.
.
Commitment,
costs,revenu
es
Confirm-mation
T I M E
Structuring Planning Approval Execution
Concept Structure CostsDates Budget Actual data
Costs
Dates
Structuring Closing
Settlement
.
.
.
Settlement
Settlement
8/12/2019 SAP PS Module
19/38
Operative Structures in Projects
WBS
Project definition
Network
8/12/2019 SAP PS Module
20/38
Operative Structures in Projects
Project definition Defines task to carry Contains data which is binding on the wholeproject
such as start and finish dates and organizationdata
WBS is the model of the project Project services to be rendered in graphicalform Operative basis for cost planning, timescheduling, and budget
allocation in projects Network reproduces the activities from theproject
Operative basis for the planning and control ofdates, costs andresources (personnel, machines, PRTs,materials)
8/12/2019 SAP PS Module
21/38
Master Data
Basic dates
Organizational units
Work breakdown structure
Budget
Costs
Basic dates
Responsibility-oriented
organization
Network
Process-oriented
organization
Dates
Resources
Resource costs
1:N
Project definition
8/12/2019 SAP PS Module
22/38
Project Definition
Default values
Company code
Currency
Settlement rule
Organizational
outline
Controlling area
Planning
parameters
For dates
For costs
April
7
Dates
Basic dates for
entire project
March
31
April
6
8/12/2019 SAP PS Module
23/38
Projection Definition
First Step in creating a project
Outline connecting all objects createdwithin a project
Contains data used for the entire project
Default values that are copied into the new
WBS elementsyou create for this project
8/12/2019 SAP PS Module
24/38
Work Breakdown Structure
Financial data
Customer
Vendor
Periodic processing
Surcharges
Settlement
Commitment
Purchase requisition
Purchase order
Purchase
order
Budget
Original budget
Release budget
Dates
Basic dates
Scheduled datesActual dates
April
7
Costs
Planned costs
Actual costs
8/12/2019 SAP PS Module
25/38
Work Breakdown Structure Focus is on planning, analysis, description, control and
monitoring costs, basic dates and budgets
It forms the basis for organization and coordination inthe project
Shows amount of work, time required, and cost involved
Operative basis for further steps Structured according to different criteria depending on
level detail
Tasks and Activities are describe as individual elements
8/12/2019 SAP PS Module
26/38
Work Breakdown Structure WBS Elements
Can be:
Tasks
Partial Tasks which are subdivided further
Work Packages
Start and finished dates
Text describing the work to be performed
Responsible cost centers
Cost centers carrying out the project
8/12/2019 SAP PS Module
27/38
Structure of a WBS
Currency
DocumentsPS textsMilestones
Subproject
8/12/2019 SAP PS Module
28/38
Network
Scheduling
RelationshipsConstraints
Floats
Critical activities
April
7
Controlling
Earned value reports
Capacity load
Periodic processingSurcharges
Settlement
MaterialPurch. parts / assemblies
Dates
Costs, commitment
External processingServices
Dates
Costs
Internal processingWork
Dates
Costs
8/12/2019 SAP PS Module
29/38
Network
Networks represent processes or task in a project
Essential elements of a network are:
Activities
Work Center, Duration, S&F, Resources Required, Texts
Activity elements
Relationship
The Network Header contains data required for theentire network
8/12/2019 SAP PS Module
30/38
Network Question that are answered using network
information Where are we unclear?
Where are the Scheduling uncertainties?
When and what amount are cost incurred?
When and what quantity do resources are madeavailable?
Relationships
FS (finish-start) FF (finish-finish) SS (start - start) SF (start-finish)
8/12/2019 SAP PS Module
31/38
Structure of a NetworkNetwork header
Internal
processing
PS texts
Externalprocessing
Services
Internal
processing
Material components
Production resources/tools
Qualification
Int. processed
element
Gen. costs
element
Ext. processed
element
Documents
Generalcosts activity
External
processing
Milestones
8/12/2019 SAP PS Module
32/38
Relationships
AssemblyProduction
FS relationship
DesignPurc.order
Purc.order
SS relationship
Start
-upSF relationship
Work
scheduling
BOM
FF relationshipDesign
Acceptance
8/12/2019 SAP PS Module
33/38
Work Breakdown Structures and
NetworksNetworkWBS
13 Elevator13-1 Engineering
13-1-1 Elec.parts
13-1-2 Mech.parts
1000 Layout
1030 Engineering: Mech.parts
1050 Engineering: Elec.parts
1120 Procurement:: Car
1080 Procurement: Mech.parts
13-2 Procurement13-2-1 Elec.parts
13-2-2 Mech.parts
1060 Procurement::Motor
1100 Procurement: Elec.
parts
1140 Assembly
2000 Acceptance
1170 Release
3000 Insurance
13-3 Assembly13-4 Insurance
13-1-1
13-1
13-1-2
13-1 13-2
13-2-1 13-2-2
13-413-3
13
1000 1170
1080
1120
1060
1100
10301050
1000
1140
2000
3000
1170
1100
1060
1050
1000
3000
1140
2000
1170
1030
1120
1080
8/12/2019 SAP PS Module
34/38
Planning (Cost and Dates)
Various ways of planning dates
Plan dates in the WBS, binding on any further planning
Dates in the network are determined by the system ormanually
Plan dates in lists, or using the various PS graphicinterfaces.
Types of dates
Basic Dates - Binding basis of time schedule in the WBS
elements Forecast Dates - Expected dates for WBS elements
8/12/2019 SAP PS Module
35/38
Planning (Cost and Dates)
Plan cost at different levels of cost planning
Structure planning (by WBS)
Plan cost without the reference to a cost element
Cost element planning (detailed planning) Plan cost with reference to a cost element
Unit Costing
If information on sources of supply, quantities, andprices is available, you can use unit costing to produce aproject cost plan
8/12/2019 SAP PS Module
36/38
Approval (Budget)
Approval Phase
Prescribe the project funds in the form of abudget
Budget differs from the cost plan in that it is binding
Starts with defining an original budget for theWBS element
Store as overall, then distribute it
Release the budget in stages, prevents exceedingearly
8/12/2019 SAP PS Module
37/38
Execution (Actual data)
Actual dates and costs are confirmed
status of activity processing is documented
system checks the dates of the WBS elementand set actual dates
Actual cost create activity allocation
Tolerance limits
Integration
8/12/2019 SAP PS Module
38/38
Closing
Project closing
Collecting all costs
Settling the costs
Closing the structures