Top Banner
SABINE PASS TO GALVESTON BAY, TEXAS COASTAL STORM RISK MANAGEMENT PORT ARTHUR AND VICINITY (PAV) UPDATE Charles Wheeler Project Manager SWD/Galveston District/PM-J Date: 13 February 2020
8

SABINE PASS TO GALVESTON BAY, TEXAS COASTAL STORM … · 2020-02-14 · Sabine Pass to Galveston Bay - Contract Acquisition Plan 4. 5 PROGRESS REPORT Dec 2017 –Chiefs Report signed.

Jul 19, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: SABINE PASS TO GALVESTON BAY, TEXAS COASTAL STORM … · 2020-02-14 · Sabine Pass to Galveston Bay - Contract Acquisition Plan 4. 5 PROGRESS REPORT Dec 2017 –Chiefs Report signed.

SABINE PASS TO GALVESTON BAY,

TEXAS COASTAL STORM RISK

MANAGEMENT

PORT ARTHUR AND VICINITY (PAV)

UPDATE

Charles Wheeler

Project Manager

SWD/Galveston District/PM-J

Date: 13 February 2020

Page 2: SABINE PASS TO GALVESTON BAY, TEXAS COASTAL STORM … · 2020-02-14 · Sabine Pass to Galveston Bay - Contract Acquisition Plan 4. 5 PROGRESS REPORT Dec 2017 –Chiefs Report signed.

2

NON FEDERAL SPONSOR FOR PORT ARTHUR

Study Sponsor

Texas General Land Office

Implementing Sponsors

Jefferson County Drainage District 7 (DD7)

Page 3: SABINE PASS TO GALVESTON BAY, TEXAS COASTAL STORM … · 2020-02-14 · Sabine Pass to Galveston Bay - Contract Acquisition Plan 4. 5 PROGRESS REPORT Dec 2017 –Chiefs Report signed.

3

PORT ARTHUR AND VICINITY PROJECT AREA

- Total Authorized Cost $863M

- 6 Separate Contracts

- Utilization of every tool available

- Scheduled to complete FY25

Page 4: SABINE PASS TO GALVESTON BAY, TEXAS COASTAL STORM … · 2020-02-14 · Sabine Pass to Galveston Bay - Contract Acquisition Plan 4. 5 PROGRESS REPORT Dec 2017 –Chiefs Report signed.

4

Sabine Pass to Galveston Bay - Contract Acquisition Plan

Page 5: SABINE PASS TO GALVESTON BAY, TEXAS COASTAL STORM … · 2020-02-14 · Sabine Pass to Galveston Bay - Contract Acquisition Plan 4. 5 PROGRESS REPORT Dec 2017 –Chiefs Report signed.

5

PROGRESS REPORT

Dec 2017 – Chiefs Report signed.

Feb 2018 - Bipartisan Budget Act of 2018 signed into law (BBA18)

Nov 2019 – Project Partnership Agreement was signed.

March 2020 – Award Contract #1

Page 6: SABINE PASS TO GALVESTON BAY, TEXAS COASTAL STORM … · 2020-02-14 · Sabine Pass to Galveston Bay - Contract Acquisition Plan 4. 5 PROGRESS REPORT Dec 2017 –Chiefs Report signed.

6

Port Arthur and Vicinity – Current Activities

DESIGN-

• Contract #2- Award of AE Task Order for Design Build Proposal February 2020

• Contracts #3/3B - 35% Design Phase will be complete April 2020

• Contract # 3A -Award of AE Design Task Order for Contract #3A- May 2020

CONSTRUCTION –

• Contract #1 Real Estate- DD7 working on obtaining Temporary Work Easement for

Contract 1 Construction

Page 7: SABINE PASS TO GALVESTON BAY, TEXAS COASTAL STORM … · 2020-02-14 · Sabine Pass to Galveston Bay - Contract Acquisition Plan 4. 5 PROGRESS REPORT Dec 2017 –Chiefs Report signed.

7

Port Arthur Contract 1

17 January 2020 Contract Advertised

18 February 2020 Proposals Due

30 March 2020 Award Contract

Key Features

• ~1 Mile of Deep Soil Mixing

• Raising the levee 2-4 ft.

• 5 Levee Repair Sites