RFP Reference No :NSDC/RFP/SDMS Dt. 4 th , January, 2011 FOR Implementation of a web-based application environment to generate an effective management framework for the skill development initiatives of the National Skill Development Corporation (NSDC) on SaaS (Software as a Service) model. REQUEST FOR PROPOSAL Date of commencement of proposal Process : January05, 2011 Date and time for Pre- proposalConference: 3pm on January07, 2011 Last date for receipt of queries on RFP : January11, 2011 Date of issue of Clarifications: January14, 2011 Last date for submission of proposals : January21, 2011 Date of opening of proposals : 4 pm on January 24, 2011 Short-listing of Service providers for proposal Presentations: January24, 2011 Proposal Presentations: January 25 to 27, 2011 Date of Award: January31, 2011 Commencement of Implementation: February 15, 2011 Address for Communication:National Skill Development Corporation D-4, Clarion Collection, (Qutab Hotel) ShaheedJeet Singh Marg New Delhi 11 0 016 Tel: 011 46 56 0414 Fax: 011 4656 0417 Cost of RFP: A copy of the RFP can be downloaded free of cost from www.nsdcindia.org Contact Person: Jaikant Singh , [email protected]
88
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: rfp

Date Text

RFP Reference No :NSDC/RFP/SDMS Dt. 4th, January, 2011

FOR

Implementation of a web-based application environment to generate an effective management framework

for the skill development initiatives of the National Skill Development Corporation (NSDC) on SaaS

(Software as a Service) model.

REQUEST FOR PROPOSAL

• Date of commencement of proposal Process : January05, 2011 • Date and time for Pre- proposalConference: 3pm on January07, 2011 • Last date for receipt of queries on RFP : January11, 2011 • Date of issue of Clarifications: January14, 2011 • Last date for submission of proposals : January21, 2011 • Date of opening of proposals : 4 pm on January 24, 2011 • Short-listing of Service providers for proposal Presentations: January24, 2011 • Proposal Presentations: January 25 to 27, 2011 • Date of Award: January31, 2011 • Commencement of Implementation: February 15, 2011 • Address for Communication:National Skill Development Corporation D-4, Clarion

Collection, (Qutab Hotel) ShaheedJeet Singh Marg New Delhi 11 0 016 Tel: 011 46 56 0414 Fax: 011 4656 0417

• Cost of RFP: A copy of the RFP can be downloaded free of cost from www.nsdcindia.org

• Contact Person: Jaikant Singh , [email protected]

Page 2: rfp

2

Table of Contents REQUEST FOR PROPOSAL .............................................................................................................. I

TABLE OF CONTENTS ................................................................................................................ 2

SECTION 1. INTRODUCTION ....................................................................................................... 51.1 NATIONAL SKILL DEVELOPMENT CORPORATION (NSDC), AT A GLANCE .......................................................... 51.2 OBJECTIVES AND MISSION STATEMENT OF NSDC ........................................................................................... 5

1.2.1 Mission Statement ............................................................................................................................................ 51.3 ORGANISATION OVERVIEW ........................................................................................................................... 6

1.3.1 NSDC Structure ................................................................................................................................................. 61.3.2 NSDC’s Role ...................................................................................................................................................... 61.3.3 Focus Areas ....................................................................................................................................................... 8

SECTION 2. STRUCTURE OF THE RFP ......................................................................................... 102.1 ABOUT THIS RFP .......................................................................................................................................... 10

SECTION 3. CRITERIONS AND PARAMETERS .............................................................................. 113.1 PRE-QUALIFICATION (ELIGIBILITY) CRITERIONS ............................................................................................ 113.2 ELIGIBILITY PARAMETERS ............................................................................................................................ 12

SECTION 4. SCOPE OF WORK .................................................................................................... 144.1 GENERAL SCOPE OF WORK ........................................................................................................................... 144.2 HARDWARE AND NETWORK EQUIPMENT CONSIDERATIONS ....................................................................... 154.3 SERVICE RESPONSIBILITIES ........................................................................................................................... 154.4 SIZING AND SCALABILITY REQUIREMENTS ................................................................................................... 164.5 APPLICATION EXPECTATION AND STAKEHOLDER NEEDS .............................................................................. 16

4.5.1 Proposal Management ....................................................................................... Error! Bookmark not defined.4.5.2 Operations Management 0 ............................................................................................................................. 214.5.3 Portlets for Operation Managementl 2 ............................................................... Error! Bookmark not defined.4.5.4 Faculty Information Portal 5 ........................................................................................................................... 274.5.5 Student Information Portal 6 ........................................................................................................................... 284.5.6 Assessment Module: 7 ..................................................................................................................................... 294.5.7 Placement Exchange: 7 ................................................................................................................................... 294.5.8 Sector Skills Council’s functions – (future requirement) 8 ............................................................................... 294.5.9 Other Stake Holders 8 ...................................................................................................................................... 30

4.6 IMPLEMENTATION TIMELINE....................................................................................................................... 30 4.7 SERVICE LEVEL REQUIREMENTS AND PENALTIES .......................................................................................... 31

4.7.1 Definitions ...................................................................................................................................................... 31 4.7.2 CategoryofSLAs 3 ............................................................................................................................................ 354.7.3 Servicelevels 4 ................................................................................................................................................. 364.7.4 Prompt Service: 4 ............................................................................................................................................. 36

SECTION 5. INSTRUCTIONS TO PROPOSERS 5 ............................................................................ 375.1 DEFINITIONS USED 5 ......................................................................................................................................... 375.2 PROPOSER ENQUIRIES & NSDC RESPONSE 6 ................................................................................................. 385.3 PRE- PROPOSAL CONFERENCE 6 .................................................................................................................... 385.4 VENUE & DEADLINE FOR SUBMISSION OF PROPOSAL 7 ................................................................................. 395.5 PROPOSAL PREPARATION COST 7 ................................................................................................................. 395.6 RIGHT TO TERMINATION/CANCELLATION 7 .................................................................................................. 395.7 CORRUPT OR FRAUDULENT PRACTICE 8 ........................................................................................................ 40

Page 3: rfp

3

5.8 LATE PROPOSALS 8 ...................................................................................................................................... 405.9 PROPOSAL OPENING.................................................................................................................................... 38 5.10 GENERAL TERMS OF PROPOSAL SUBMISSION.............................................................................................. 38 5.11 PREPARATION OF PROPOSAL ...................................................................................................................... 39 5.12 PROPOSAL FORMAT..................................................................................................................................... 40 5.13 TECHNICAL PROPOSAL ................................................................................................................................ 42 5.14 COMMERCIAL PROPOSAL ............................................................................................................................ 42

SECTION 6. PROPOSAL EVALUATION 4 ....................................................................................... 466.1 EVALUATION COMMITTEE(S) 4 ..................................................................................................................... 466.2 PROPOSAL OPENING AND EVALUATION 4 .................................................................................................... 46

6.2.1 Technical evaluation: 5 .................................................................................................................................... 466.2.2 Financial evaluation: 5 .................................................................................................................................... 47

6.3 CONFIDENTIALITY OF PROCESS 5 .................................................................................................................. 476.4 CLARIFICATIONS OF PROPOSALS 6 ................................................................................................................ 486.5 INITIAL EXAMINATION OF PROPOSALS 6 ...................................................................................................... 486.6 CORRECTIONS OF ERRORS 6 .......................................................................................................................... 486.7 TECHNICAL EVALUATION CRITERIONS 7 ........................................................................................................ 496.8 FINANCIAL EVALUATION CRITERIONS 7 ........................................................................................................ 50

SECTION 7. TERMS AND CONDITIONS 9 ...................................................................................... 517.1 CONTRACT DOCUMENTS 9 ............................................................................................................................ 517.2 INTERPRETATION 9 ....................................................................................................................................... 517.3 COMMUNICATIONS 9 ................................................................................................................................... 517.4 LANGUAGE 50 .............................................................................................................................................. 517.5 TIME FOR COMMENCEMENT AND COMPLETION.......................................................................................... 50 7.6 PROPOSER’S ROLES AND RESPONSIBILITIES ................................................................................................ . 50 7.7 EMPLOYER’S (AND OTHER STAKEHOLDERS) ROLES AND RESPONSIBILITIES .................................................. 51 7.8 TERMS OF PAYMENT 2 .................................................................................................................................. 557.9 TAXES AND DUTIES 3 .................................................................................................................................... 557.10 INTELLECTUAL PROPERTY RIGHTS (IPR)........................................................................................................ 53 7.11 SOFTWARE SERVICES AND LICENSE AGREEMENTS 5 ...................................................................................... 577.12 CONFIDENTIAL INFORMATION 5 ................................................................................................................... 587.13 AUTHORISED REPRESENTATIVES 5 ................................................................................................................ 58

7.13.1 Employer’s Representative 6 ........................................................................................................................... 587.13.2 Proposer’s Representative 6 ............................................................................................................................ 597.13.3 Objections and Removals 6 ............................................................................................................................. 59

7.14 PROJECT PLANNING AND PERFORMANCE 7 .................................................................................................. 597.15 SUBCONTRACTING (AREAS THAT CAN BE SUBCONTRACTED, EXTENT ETC) 7 .................................................. 607.16 TRANSPORT AND DELIVERY 7 ....................................................................................................................... 607.17 PRODUCT UPGRADES 8 ................................................................................................................................. 607.18 INSPECTION AND TESTING 8 ......................................................................................................................... 617.19 COMMISSIONING AND OPERATIONAL ACCEPTANCE 8 .................................................................................. 617.20 COMPLETION TIME GUARANTEE 9 ................................................................................................................ 627.21 DEFECT LIABILITY 9 ....................................................................................................................................... 627.22 FUNCTIONAL GUARANTEES ......................................................................................................................... 60 7.23 LIMITATION OF LIABILITY............................................................................................................................. 60 7.24 CRIMINAL CHARGES AND CONVICTION ........................................................................................................ 61 7.25 CARE OF IT PRODUCTS AND/OR SERVICES .................................................................................................... 61 7.26 LOSS OF OR DAMAGE TO PROPERTY; ACCIDENT OR INJURY TO WORKERS.................................................... 61

Page 4: rfp

4

7.27 INSURANCE 2 ................................................................................................................................................ 647.28 FORCE MAJEURE 2 ........................................................................................................................................ 647.29 CHANGE IN LAWS AND REGULATIONS 3 ........................................................................................................ 657.30 COMPLIANCE WITH LAWS 3 .......................................................................................................................... 657.31 EXTENSION OF TIME FOR COMPLETION 4 ..................................................................................................... 667.32 SUSPENSION 4 .............................................................................................................................................. 667.33 TERMINATION FOR PROPOSER’S DEFAULT 4 ............................................................................................... 667.34 DISPUTES AND ARBITRATION 5 ..................................................................................................................... 67

7.34.1 Arbitration 5 .................................................................................................................................................... 677.34.2 JURISDICTION 5 ............................................................................................................................................... 67

7.35 REPRESENTATIONS AND WARRANTIES 6 ...................................................................................................... 68

SECTION 8. ANNEXURE A 7 ........................................................................................................ 708.1 LIST OF MIS STATEMENTS TO BE SUBMITTED * 7 ........................................................................................... 708.2 REPORT 1 - MIS REPORT SHOWING PERFORMANCE OF A TRAINING PROJECT FUNDED BY NSDC: 8 ................ 718.3 REPORT 2 – OWNERSHIP DETAILS OF THE AGENCIES BEING FUNDED 8 .......................................................... 718.4 REPORT 3 - MIS REPORT SHOWING PARTNERWISE PROGRESS REPORT: 9 ..................................................... 728.5 REPORT 4 – TRAINEES REGISTRATION DETAILS 9 ........................................................................................... 72

8.5.1 FORM - I.......................................................................................................................................................... 70 8.5.2 FORM -II .......................................................................................................................................................... 748.5.3 FORM III - COMMERCIAL PROPOSAL 4 ........................................................................................................... 768.5.4 FORM IV - TECHNICAL BID FORM 6 ................................................................................................................. 79

Page 5: rfp

5

SECTION 1. INTRODUCTION

1.1 NATIONAL SKILL DEVELOPMENT CORPORATION (NSDC), AT A GLANCE

The National Skill Development Corporation (NSDC)has been institutedto address the compelling need

tostrategize and operationalize a world-class skill development solutionpertinent to the Indian context,

to effectively drive the speedy development of skills essential to sustain the country’s growing economy.

NSDC is a first-of-its-kind Public-Private Partnership (PPP) model in India with a focus toward skill

development. A major part of NSDC’s skill development effort is aimed at the unorganised sector.

1.2 OBJECTIVES AND MISSION STATEMENT OF NSDC

The main objective of NSDC is to achieve the overall target of skilling/ up-skilling 150 million people by

the year 2022, mainly by fostering private sector initiatives in skill development.

• Mission Statement

• Upgrade the quality of skills to match international standards through significant industry

involvement and to develop the necessary frameworks to address the development and

sustainability of a dynamic management system regarding relevant curriculum, content,

pedagogy, assessment and evaluation, quality assurance process and standards.

• Enhance, support and coordinate private sector initiatives for skill development through

appropriate Public-Private Partnership (PPP) models; strive for significant operational and

financial involvement from the private sector.

• Focus on the underprivileged sections of society and the backward regions of the country,

thereby enabling their move out of poverty; similarly focus on the workforce from the

unorganized or the informal sector.

Page 6: rfp

6

1.3 ORGANISATION OVERVIEW NSDC acts as a catalyst, enabling skill development initiatives to scale, by providing viability gap

funding to enterprises, companies and organisations that provide skill training. NSDCmay also develop

appropriate PPP models to enhance, support and coordinate private sector initiatives to achieve its

objectives.

NSDC’s understanding of the need for skill development has spurred varied approaches towards each of

the 21 skill sectors under it’s purview, making each and every sector attractive for private investment.

1.3.1 NSDC Structure

NSDC is a non-profit company,under the aegis of the Ministry of Finance, registered under Section 25 of

the Companies Act. It has an equity base of Rs. 10 crore, of which the Government of India’s contribution

accounts for 49%, while the private sector has a 51% stake

To ensure superior decision-making, the NSDC requires a structure and governance model that provides

it with autonomy, stature and continuity. Thus, the organisation has a four tiered decision-making

structure comprising of:

• Board of Directors • Board of Sub Committees • Executive Council • National Skill Development Fund (NSDF)

Each tier has a clear-cut role in the NSDC’s operations, activities and strategy to facilitate the

organisation’s mandate of coordinating and stimulating private sector initiatives towards skill

development with enhanced flexibility and effectiveness.

The 12-member Board has four government nomineesand eight private sector members. The Chairman

of NSDC is from amongst the private sector. NSDF is a 100% government-owned trust that invests in the

NSDC, and is run by professional fund managers.

1.3.2 NSDC’s Role

Page 7: rfp

7

The role of NSDC is to facilitate or catalyse initiatives which would have a multiplier effect In doing so, it

will strive to involve the industry in all aspects of skill development. The approach will be to develop

partnerships with multiple stakeholders and build on current efforts, rather than undertake too many

initiatives, directly or by duplicating efforts that are currently underway.

To scale up efforts that are necessary to achieve the objective of skilling and or up skilling 150 million

people, NSDC will strive to:

• Develop ultra low cost, high-quality, innovative business models • Attract significant private investment • Ensure that its funds are largely “re-circulating”; i.e. loan or equity rather than grant • Create leverage for itself • Build a strong corpus • DevelopLabour Market Information System

In cognisance of the above mentioned points,, NSDC will focus on the following four key roles:

Funding and incentivising:In the near term this is a key role. This involves financing initiatives

either as loans or as equity vis’-a-‘vis providing grants, thus providing financial incentives, as support,

to select private sector initiatives, improving their financial viability. The exact nature of funding

(equity, loan or grant) will depend on the viability or attractiveness of the segment/skill sector and, to

some extent, the type of player (for-profit private, non-profit industry association or non-profit NGO).

Over time, the NSDC aspires to create strong viable business models and reduce its ‘grant-awarding’

role.

Enabling support services:Skill development institutions require a number of inputs such as

relevant curriculum and courseware, appropriate pedagogy tailored to respond to the desired outcomes,

faculty and their training, assessment and evaluation, quality assurance processes and finally

certification; and standards, multiple support services that include technology platforms and student

placement mechanisms are also essential. NSDC will play a significant enabling role in some of these

support services, and most importantly in the near term set up standards and accreditation systems in

partnership with industry associations.

Shaping/creating:In the near term, the NSDC will proactively seed and facilitate the requisite

momentum for large scale participation by private players in skill development. NSDC will identify

Page 8: rfp

8

critical skill groups, develop models for skill development and attract potential private players and

provide the required support to kick off these efforts.

Sector Skills Council:Sector Skills Council: NSDC has the mandate from Govt of India to setup the

Sector Skills Council for 20 identified Industry Sector, who would be looking after the industry related

skilling concept, processes, certification, accreditation and quality framework

a. Conducting researchdevelop competency standards, skill inventory database,

international trends, technology trends etc

b. Improving the delivery mechanism developing and improving modules, developing

training delivery mechanisms, training the trainers, apprenticeship etc

c. Building quality assurance -certification and accreditation process, other pedagogy.

1.3.3 Focus Areas

Skill development: The challenge of skilling and or up-skilling 500 million individuals by 2022 will

require both, fundamental education reforms across all levels of the formal the educational system and

significant enhancement of supplementary skill development. In the near term, NSDC will focus

primarily on supplementary skill development and strive to create seamless tracks within both the

formal and in formal segments of the same.

Foster private sector initiatives: Towards the strengthening of the supplementary skill development

segment of the existing educational system, NSDC will focus on fostering private sector led efforts that

will only include both ‘not –for -profit’ and ‘for-profit’ models that are scalable.

Depending on the target segment NSDC will adopt a differential approach in supporting private sector

initiatives.. Based on the marketability of the skill group concerned and the achievable income levels of

the student population therein, there are three broad segments across which NSDC will focus:

• Attractive segment: Given that the market automatically works, the NSDC will only play a reactive role and support the scale-up by various players.

• Viable segment but with marginal economics or involving high risk/uncertainty: This will be a key focus area of NSDC particularly in the near term, with the aim being to make this segment much more attractive for private investment.

• Completely unviable segment: Over time, NSDC will aspire to work in this segment in collaboration with government departments and help develop innovative business models

Page 9: rfp

9

which can move players from this segment to the viable segment.

Page 10: rfp

10

SECTION 2. STRUCTURE OF THE RFP 2.1 ABOUT THIS RFP The National Skill Development Corporation invites service providers/suppliers to submit the technical

as well as commercial offers forthe deployment of a web based application on SaaS (Software as a

Service) model, a customizable readymade solution, which will be called the Skill Development

Management System (SDMS.) Under SaaS model the service provider is responsible for creation,

updating and maintenance of the web based application. .) SDMS will be used by NSDC and its partner

organizations, each one of which will be a separate legal entity in the application, and hence will have

security of its data from each other. NSDC and its funded companies and their centers and other stake

holder shall have access to the application. The web based application should enable NSDC effectively

manage its skill development programs directly and or with its affiliated centersand for its partners

to manage their entire operation of skill development through efficient administration of their

centers, managing content and industry partnerships. The overall scope, conditions, and

expectations are prescribed in this Request for Proposal (RFP) document.

This RFP includesrequirement study, setup, integration, customization/development, implementation,

training, documentation and maintenance of the said SDMS including upgrade as per specifications,

terms and conditions and scope defined and prescribed in this Request For Proposal (RFP) document.

This RFP is with regard to appointment of a vendor for:

REQUIREMENT STUDY, ANALYSIS, APPLICATION DESIGN, PROTOTYPE DESIGN, CUSTOMISATION AND/OR REQUISITE DEVELOPMENT, TESTING, INTEGRATION, DEPLOYMENT, PREPERATION OF TECHNICAL AND USER DOCUMENTATION, TRAINING &MAINTENANCE OF APPLICATIONON THENETWORK (LAN & WAN). CAPTURE AND STORE CRITICAL DATA RELATING TO THE SKILL DEVELOPMENT SCHEMES AND ENSURING ACCESS TO THE DATA AND DETAILS OF STUDENTS, FACULTY AND CENTERS AT MULTIPLE LEVELS AND FROM THEREON AT THE TRAINING PROVIDER LEVEL ON A REGULAR BASIS. This RFP is not an offer by NSDC, but an invitation to receive response from Proposers. No contractual

obligation whatsoever shall arise from the RFP process unless and until a formal contract is signed and

executed by duly authorized representatives of respective parties.

Page 11: rfp

11

A vendor submitting the proposal in response to RFP for providing the solution may hereinafter

interchangeably be referred to as “Vendor/ Proposer/Service Provider”.

SECTION 3. CRITERIONS AND PARAMETERS 3.1 PRE-QUALIFICATION (ELIGIBILITY) CRITERIONS

NSDC’s prime criterion is that the Proposers should be able to demonstrate a working model and

ability to design and customise / develop of the Skills Development Management Software a skilling,

and administration system as outlined in this document and should be able to provide evidenceof

existing deployment ineducation / skill development centers.

The prospective Proposers should comply with the following criteria to be eligible for participation

in the RFP:

• Proposer should demonstrate the ability to provide the requisite application design inclusive

of customisation, implementation, and training services to NSDC and its associates with a

strong understanding of the challenges and issues in skill development space.

• The Web-Based Application Software should be able to provide / demonstrate expertise in

the following areas:

o Facilitate overall management of training, skilling, technical and financial monitoring,

control and risk management , and reporting with respect to modules handled by all stake

holders concerned and the other training center’s management for total solution.

o Enable the administrative management at the training center/institute.

o Labour market analysis data is made integral to the Labour Management Information System

(LMIS). It should capture / collect and collate data for LMIS i.e both supply and demand

market.

o Ability to segment data by industry, trade, geography, timelines, education/ vocation/ trade /

curriculum and other qualifications, etc.

o The Proposer should have demonstrated experience in scaling organizations.

o Provision for a continuous feedback, review and improvement of the system

• The Proposer must not have been blacklisted by any government organization in India at the

time of submission of the RFP.

Page 12: rfp

12

• Permanent Account Number (PAN) of Proposer/each consortium member should be

available from Income Tax authorities.

• The Proposershould provide all necessary documents as part of the proposal process to

indicate financial, technical and administrative capability and stability to support NSDC in

achieving its objective of creating a strong technology backbone in its skill development

program.

• Preferably Proposers should be capable of independently providing all the requirements of

this RFPor they can form a pre- proposal consortium with companies in compliance of the

necessaryrequirements of this RFP. Post proposal alliances or outsourcing or other vendor

partnerships to provide the necessary services covered in the scope of RFP is not permitted.

Participating companies in the pre- proposal consortium should identify and clearly

articulate their independent role/s and responsibilities as a part of the overall solution as

indicated in the scope of work in this RFP.

• NSDC reserves the right to carry out the capability assessment of the Proposer and the

decision of the NSDC shall be final in this regard. Acceptance certificate towards this clause

must be submitted.

3.2 ELIGIBILITY PARAMETERS The following eligibility parameters shall be used for defining the eligibility criterion forProposers:

S. No.

Criteria Documents to be submitted asqualifying documents

1. The Proposer/ at least one partner in the consortium should have developed / implemented or associated with similar / relevant solution. Any one Partner having filed income tax returns in Information Technology and related services(Application Development, Datacenter Management etc.) would be an added advantage.

Audited financial statements of the Proposer and if the Proposer is forming part of a larger group or conglomerate of companies reflecting overall turnover of the group and the turnover specific to the proposer, its services / product lines for the past financial years, if any and other satisfactory evidences such as authorized signatory, auditor’s certificate etc. The Income Tax Returns filed by the company for the last assessment years should also be submitted, if available.

2. Proposer / Proposer Consortium should be an established Information Technology Company and should be able to demonstrate its experience in implementing similar solutions

Certificate of Incorporation of thecompany. Memorandum of Association and Articles of Association of the Proposer/all the partners.

Page 13: rfp

13

in India or overseas. 3. The Proposer/Proposer Consortium should

have expertise, experience and potential in its people and in developing Web Based Integrated Solution and have worked on / provided similar products/ services as envisaged in this RFP. Proposer should demonstrate their understanding of the on-the-ground challenges in implementing such systems, preferably in the Indian context.

Demonstration of the tool, credentials endorsing the claim.

4. Proposer / Proposer Consortium should demonstrate a good understanding of the landscape, policies, stakeholders and challenges in the education / skill development space. We believe that this knowledge will help in creating a scalable all-encompassing web based tool that addresses functionality.

Engagements in the education / vocational skill domain space

5. Proposer shall not be under declaration of ineligibility for corrupt or fraudulent practices by any government agency.

Declaration signed by the highest level in the Proposer/Proposer consortium’s management.

1. A power of attorney in the name of the person signing the proposal. In case of consortium, the same

should be signed by legally authorized signatories of all the partners nominating one of the partners

as the Lead Proposer.

2. In case of consortium, the consortium must submit:

• The details of roles and responsibilities of each partner. The same should be endorsed by

authorized representative of the each partner.

• The original stamped consortium agreement shall be attached along with Technical proposal.

• The approximate stakes of each partner of the consortium, authorized by the lead partner,

should also be submitted along with the proposal document.

Page 14: rfp

14

The formats for the checklist along with the required supporting documents have been provided in FORM-

II hereinafter. All the documents / certificates submitted by the Proposer should be duly signed by the

Authorized Representative of the Proposer / consortium.

SECTION 4. SCOPE OF WORK 4.1 GENERAL SCOPE OF WORK On a broader level the scope of work involves:

1. Requirement Study, Design, Application Customization/ Development, Testing, Implementation,

Integration, Training, Documentation and Deployment .

2. Feature set to manage, monitor and track all NSDC funded beneficiaries.

3. Hardware hosting, network facilitation, management and support

4. Data Migration where necessitated & Integration from different software’s of NSDC’s Partners and

other stake holders.

5. Job Platform - Job seekers, businesses, and institutions public and private are likely to make many

labourmarket related choices and decisions over their lifetime; hence the LMIS must be able to

support this.

6. Provisioning for UID Nos. being created by the Govt. of India on each certificate of trainees.

7. Security and Risk Management of the Application and of the data belonging to NSDC and its partners.

8. Support and maintenance ongoing for an initial subscription period of 5 years.

The System implementation roadmap should be as per the following exhibit which depicts astep by step

process of system implementation:

Page 15: rfp

15

4.2 HARDWARE AND NETWORK EQUIPMENT CONSIDERATIONS 1. The basic premise of the hardware and network equipment is to enable a high quality of service

performance to support the SDMS. The hardware and network equipments and their

corresponding specifications should be determined taking into consideration the requirement of

the software application, number of users, number of students, number of centers, performance

parameters and system security.

2. The Proposer should address in their response their current hardware, networking and other

infrastructure setup specifically the uptime guaranteed and the security layers at their data

centers, failure switchover mechanism, backup procedures (automated and on-demand),

disaster recovery and also their approach and plan to deal with/scale the hardware and network

infrastructure as the number of users increase

4.3 SERVICE RESPONSIBILITIES The selected Proposer should participate in scope enhancement discussions and proactively implement

ongoing changes/updates in consultation with NSDC with a committed timeframe for facilitating such

changes at free of cost and beyond which it could be chargeable.

Page 16: rfp

16

4.4 SIZING AND SCALABILITY REQUIREMENTS 1. It is most important that the SDMS and MIS Solution with all its components should be scalable to

handle additional MIS Reports as NSDC may require, from time to time. Scalability must be in terms

of Hardware, Software, database design, Network Support, Geography, No of Partners, Additional

MIS Reports, etc. keeping in view to next 5 Year MIS requirements. Upon the implementation of

SDMS, by virtue of an integrated solution, the proposer is able to visualize and understand the

scaling of the activity (specifically from NSDC Governance module – refer 4.5) and accordingly

should be able to plan proactively to support and meet the scaling requirements.

2. The Sizing of the Solution should be done keeping in view all the above points, including a 5 Year

plan in terms of scaling of the hardware, network and other infrastructure.

3. The solution must be sized to provide a good response time as will be decided during Systems

Requirement Study on the User Terminal with registered users of as the SDMS could gather from

various other integrated modules.

4.5 APPLICATION EXPECTATION AND STAKEHOLDER NEEDS NSDC receives several proposals for funding. All of thesetoday aretracked and monitored manually. The

NSDC Management module below is intended to enable receiving funding applications, tracking and

monitoring all beneficiaries who have been eventually funded.

The beneficiaries are who would setup centers or undertake activity as proposed in their application to

NSDC. The SDMS would need to facilitate bringing the beneficiaries on to the application and track spend

against funding and other parameters. Also it is NSDCs intent to get a view into the operational

parameters of the beneficiaries and their centers using a standard platform.

NSDC believes the SDMS is what will help it enable achieve this goal given that the center’s entire faculty,

students etc., will be using the same platform and will ensure it provides standardised reports and

information on a dynamic and real time basis. Hence the module under the beneficiary are classified as

sub modules like setting up of center, center administration, mobilization of students, student

management system, fee and loan management, training management, , market network, LMS (Learning

Management System), Question Bank Management and Assignment Generator, Assessments, Online

Page 17: rfp

17

Entrance, Content Management, Consultants Registration, feedback mechanism, content management,

alumni tracking. Human Resource Management, Payroll, Integration to Tally and other interfaces,etc.,

that aggregate views all the way to beneficiaries, NSDC, Sector Skill Council (SSC), PMO and other stake

holders.

The assessments module is to build a standardised framework of assessments spanning across all

students, centers, trades etc., and the placement exchange module to help all of these students resumes

to be stored in a centralised database where the prospective potential employers could login, search,

review and recruit the suitable candidates.

Below is a modular representation of the SDMS functional requirement:

Page 18: rfp

18

Basic pre-requisites from the developed/customized application are that it be

1. User friendly 2. Intuitive 3. Robust 4. Have a strong, well conceptualized foundation that would enable the application

administrator to configure new partners in the said application, as and when required, as per their internal structure/ processes

5. Strong Analytical dashboards/reports that would enable various stakeholders at NSDC and at each partner organization to, on an ongoing basis, take immediate corrective actions for enhanced controls and increased productivity

In general the key capabilities envisaged from the system are below. However this is only an indicative

feature set for the proposer to be able to price. There could be a slight variation in terms of prioritisation

/ change in feature set at the time of finalising the SRS (Systems Requirements Specification) and NSDC

may ask for such revisions to submit a revised financial quote.

SDMS should facilitate effective capture of the financial, administrative and operational information for

each center operated by the agencies /companies funded by NSDC. This should include but not be

limited to the following general features through the application:

1 The reports generated from the application should be exportable into multiple formats as required

by NSDC and its partners, stakeholders as government and others.NSDC would expect the Vendor to

provide a initial setup of report formats.

2 Messaging and communication – The system in general should have email based alerts, intimations

etc., built in besides mobile being one of the fastest penetrating communication media alerts on

mobile and updates/ feedback to system through mobile devices to be incorporated.

3 Ability for center’s to take picture and mail / upload into the system for audit and other reviews if

provided – would be an added advantage. Ability to host audio, video files for sharing if provided –

would be an added advantage.

4 Directory of all users and their contact details – to be updated and maintained

5 Ability to evaluate performance of NSDC Partners and of training Centres or franchises belonging to

each partner based on defined parameters.

Page 19: rfp

19

6 API access - The system should provide password-protected, read-only API access to selected

sections of data. This will help partners develop in-house custom apps (for example, SMS

marketing).

7 Integration with inbound SMS service for capturing leads. Partners can run marketing campaigns through various media and invite responses through SMS.

8 Ability to create UID no. and track certificates being issued, avoid duplication and forgery. System should check on other parameters (contact numbers, driver’s license number etc) to identify, if the candidate is already registered in the system w/o UID. Create no. post issue of certificates also.

9 Automated back-up of data on periodic basis (which can be set by each partner/NSDC) on remote servers in a geographically different location from where the main data server resides

10 System should allow capture of Student picture using web camera and attach it with Student’s profile during the registration process.

11 CRM function for market data being captured for probable candidates / aspirants.

12 Capture the demand and supply data and prepare the analytical report of the Labour Market.

13 Ability to have separate dash board for different stake holders of each NSDC Partner and meet their MIS requirements and have adequate safety and security provisions to ensure that the data of one partner is secure and invisible to another partner .

14 System should have a provision for creation of database of consultants thereby provisioning consultants to provide and update their profiles online

15 System should throw automated escalations to defined NSDC authorities/stake holders in the partner organizations for any exceptions or delays of process steps.

16 System should extract data/ report on various required parameters as region, geography, sector, skill trades, associate, state, student wise, center wise, etc

17 System should allow the IT administrator of each legal entity on this application (i.e.. NSDC and each one of its partners) to generate ad-hoc reports as per their internal demand.

18 Secured Certificate Authentication should be there to this web site and it should be trusted

Below are a brief description of the feature set of each of the modules:

4.5.1 Proposal Management

Page 20: rfp

20

All the organisations/entities funded by NSDC and their contracts would be required to be updated on

this module and this module will be operated by NSDC to track deliverables of the contracts it enters

into with its funded organisations/entities.

1 All proposals submitted by organizations/entities would be assigned a unique number to be

generated by the system itself with an user login id and password.

2 Proposed system should be able to give the on-line status of the Proposal and should provide the

details of the stage at which the proposal is pending.

3 System should throw automated requirements/information necessary for the proposal to move to

the next stage.

4 In the event of grant of funding by NSDC, the system should facilitate automatic update of the

details of the proposal/application in the existing database of NSDC

5 In the event of the rejection of the proposal/application, the system should produce adequate

closure report for the same

6 System should have the ability to generate escalation messages in case of delays in response/ action

then prescribed for each stage.

7 The system should have the ability generate stage wise consolidated report of proposal say Test of

Response (TOR) Proposal Evaluation (PEC) and Proposal Approval (PAC) committee and the Board

of Approval level.

8 Capture of information pertaining to the agencies / projects funded.

9 Credentials including financial information, ownership details, leases etc

10 Proposal management system to track the status of applications/ proposals on-line.

11 Centers operated- capacity, courses offered, fee structures, faculty credentials etc.

12 Ability to record the contracts and multiple parameters of the agreements of the contract

Page 21: rfp

21

13 Ability to define committed/agreed levels of services as per the contract such as number of students

per Training Centers, no. of Training Centers, Geography, no. of Courses/ Skill Trades , the

placement no. / %age, amount of fees, collection schedule likely companies to be placed and

provisions for actual progress against those projected figures, capturing funds under various heads

capex and opex at center and nodal level of partners etc.

14 Proposed system should be able to give exception reports at multiple levels on agreed vs. actual on

all the parameters/levels defined on monthly, quarterly and annual basis.

15 System should provide online approval workflows for any exceptions, where the approvers can be

defined at different levels based on the nature of exception.

4.5.2 Operations Management

This module would have necessary portlets / platforms to manage the day to operations of the NSDC’s

Partners as below:

(A) Configuration of New Partner

(B) Setting up of center

(C) Mobilization (CRM)

(D) Center Administration

(E) Student Loan Management

(F) Training Management

(G) Alumni Tracking

(H) Strategic Partnerships & Alliances

(I) Content Management (J) Content dissemination (K) Incorporation of Business Models

(L) HR, Payroll Management, Integration to Tally

(M) Application Administrator

Page 22: rfp

22

The system should be able to collate requisite data from the aforesaid portlets and provide a needful

information / report on a dash board to enable NSDC monitor, track and review the operations of the

funded organisations/entities and their centers. This module also helps NSDC reach out and

communicate with all of such organisations/entities and theircenters.

1. Key Performance Indicators of NSDC funded organisations/entities and further drill down to

their Training Center from a management perspective

2. Further drill down to students performance, placement, admission, Capacity Utilisation, Facility

Performance Report, Notices and Information, training by trade etc,

3. Fee collections, budgeted vs. actual, other financial information like P&L, BS etc., with drill down

to center level.

4. Ability to message and cascade information down to all channels, ability to seek feedback etc.

5. Drill down to employee’s strength, their details and faculty etc.

6. Aggregate reports on the overall skilled manpower availability, capacities by trade

7. Funds allocated and achievement of targeted financial goals

8. Issues and challenges by region, sector, associate wise, etc

9. System should provision to extract the report of “Projector Monitors” centerwise, batchwise,

tradewise etc

10. Ability to issue, track and monitor certificates with auto system generation of the numbers for

control and governance. Providing of UID nos. As given by Central Govt.

11. Enable enquiries tracking and responses at center level and further aggregation of all center’s at

the organisation/entity level, which is funded by NSDC

12. Student registration including courses studies, economic background and other demographic

information

Page 23: rfp

23

13. Enable tracking and audit of attendance, status of completion of courses, test scores including

practical tests, etc

14. Fee structure and status of collection of fees

15. Issues, challenges and feedback at the center level

16. Information pertaining to the classroom sessions, test notification to be provided to the students

17. Managing access levels to various users at center/region /national level for each partner and for

NSDC

18. Online registration for students.

19. On line generation of Certificates and printing facility. Automatic numbering of Certificates.

20. Provision of incorporating the UID no. On all certificates generated till date.

21. Managing Training Programs, Course Curriculum, Course Completion, Faculty,

attendance, fee collections, loan tracking, schedules, communication etc.

22. Online Learning Content Repository – Teachers/Content Adminsitrators or NSDC

Admin(s) can upload any online content such as class notes, question bank etc, which

can be made available online to students / faculty. Strict access controls will define teh

roles that can upload and those who can access selected parts of this content.

23. Student Evaluations: Continuous Evaluation through Tests, Assignments, Quizzes, Group

Discussions, Presentations, Seminars etc.

24. Exam and Quiz: Manage Date Sheets, Detailed Mark Sheets and Teachers can conduct online

exams related to the course or to the whole program, which can be automatically graded and can

be re-graded if necessary

25. Printing of receipts for students

26. Smart card / RF card for students tracking

Page 24: rfp

24

4.5.3 Operation Portlets requirements – as relevant to NSDC’s Partners

A) Configuration of New Partner

• Define new partner Organization as a new legal entity in the application

• Setup Organization Chart, Map Roles, Define Access, Set approval limits for each role (e.g..extension in fee payment due date, discount on fee, petty cash approval limits etc)

• Setup database instance for the new partner

• Setup Automated backup procedures

(B) Setting up of center

• Project management tool for managing setting up of the center

• Plan setup of centre - prepare project sheet with detailed list of tasks, timelines and budgets

• Track Progress of work and raise flags when tasks which have interdependencies are delayed.

• Monitor Expenses against Budgets

• Feed to Finance module

(C) Mobilization (CRM)

• Tracking of the mobilisation process, which flows as - Identify Field Executives --> Map them to specific programs --> Capture Leads Generated -> Track and set reminders/alarms for Follow up (phone calls or visits) -> Walk In (Counseling) ->Registration -> Admission

• Status of each lead needs to be tracked and recorded upto the converstion (i.e. registration fee paid)

• Weekly plan/forecast of mobilization needs to be prepared by the field team.

• Result of previous weeks efforts needs to be reported & compared with the plan

• Field staff mobilisation reports need to be generated to monitor performance and take actions to further improve productivity.

• Monitor payments/incentives paid to Field Executives and feed into Finance module;

• Monitor Field Executive's drop out rates and black list if drop out rate is above predefined x%

• Excel Upload required for Prospect data Entry in addition to front end data entry form.

Page 25: rfp

25

(D) Center Administration

• When enrolled, change status from Prospect to Student

• Track the students attendance and fee deposition track dropout, delays in fee payments, feed to Finance module. Enabling alerts on fee payment, send intimation of launch of advanced courses via SMS on mobile phones

• Attendance of staff -Biometric Enablement - needs to be connected to HR for Salary processing and then to Finance

• Batch creation, mapping faculty and students to a future/current batch

• Lesson plans to be recorded for testing of adherence to content & trainer productivity

• Apprenticeship/Placement forecast to be prepared by center head monthly for the next 3 months for the Placement Team

• Student feedback to be recorded on content, trainer and centre facilities Enabling feedback from students, alumni and trainers through Mobile phone (SMS)

• Trainer feedback to be recorded for content and centre facilities Enabling feedback from trainers on-line

• Trainer Utilization and Effectiveness Assessment

• Asset management

• P & L tracking

(E) Student Loan Management

• Track students who have applied for loans & scholarships with partner agencies

• Track loan processing timelines, facilitation and reciept of money from agency

(F) Training Management

• Training details - performance records

• Lesson plans to be recorded for tracking of adherence to content and trainer productivity

• Student & Trainer feedback to be recorded and escalated wherever necessary

(G) Alumni Tracking

Page 26: rfp

26

• Record details of alumni and track them

• Jobs – track how many are working in the line in which they were trained

• Retraining -inform them via SMS/online portal

• Alumni and Employer online feedback on effectiveness of training and industry readiness of the student

(H) Strategic Partnerships & Alliances

• Database of employers who might be interested in hiring our students to be maintained

• Database of corporates who we can partner in several different types of partnerships other than employment oriented ones as above.

• Track follow-up status of dialogue with potential industry partners/ employers including tracking of creation of proposals, MoUs and agreements.

• Effective monitoring and management of relations with partners.

• Feedback from employers about our alumni's performance

• Feedback from partners engaged with students in training

• Enabling feedback from Industry partners on-line

(I)Content Management

• Tool for effective management of the process of content development through its entire lifecycle

• feed to Finance module of the costs incurred

• IT enablement of courses wherever possible

• Feedback MIS and Action taken /closure on all feedback

• Knowledge Bank management

• Question Bank Management and Assignment Generator

(J) Content dissemination

a. Disseminate the content across all centers from a central location - one location to many.

b. Run Training of Trainers remotely and continuously

(K) Business Models

Page 27: rfp

27

a) Franchisee model - Each partner Organization can engage with Franchisee’s, who will in turn setup multiple centres in a given region. Such centres too will have access to this application and function as the partner owned centres. Application will provide the partner, functionality to track performance of self owned and franchisee owned centres cumulatively and separately

b. Satellite and mobile centers - Centers may have one or more satellite centers and many mobile centers (like mobile vans) attached to them. These are considered to be components of teh main center. However, we would require a MIS would track these cumulatively and separately.

c. Consultany – A partner organization may engage with another organization to provide management consultancy to their centres.

(L) HR, Payroll Management, Integration to Tally

c. Payroll Management for Part Time, Full Time, Contractual, Consultants

d. Employees - Hiring Process, Exit Process, Promotion, Change of Role

e. Holiday and Leave Management

f. Competency Management

g. Integration to Tally

(M)Application Administration for each Partner e.g..user creation, mapping / remapping of

roles and access rights, setting/updating control parameters

This module would be implemented at each centre of all NSDC funded organizations/entities. MIS would

need to be collated from different centres at the organization level to facilitate effective monitoring and

management of operations.

4.5.4 Faculty Information Portal

This module would be for all of thefaculty at each of the centers and the faculty would be able to login to

view all information relating to batches, schedules, grades of students, attendance concerning their

centers, such as:

1 Calendar showing staff meetings, examination, class, seminars, workshops and other

schedules.

Page 28: rfp

28

2 Attendance: Faculty can view their attendance detail on their portal

3 Course Activity: Faculty can view their course activity such as assignments given etc on

their portal

4 News, Notices and other Information

5 Grades: Faculty can view the grades of their students on their portal

6 Enter Course Completion Status

4.5.5 Student Information Portal

This module would be accessed by students and would help them in knowing their schedules, news, fee

related information, performance etc.

1 Calendar showing examination, Assignments, classes, seminars, workshop and other

schedules.

2 Attendance details

3 News, notices and access to other Information hosted online for students

4 Fee related details, online receipts

5 Student online feedback: Students can view their feedbacks about the programs or any

other relevant concern or input.

6 My Grades: Student can view their grades real time on their portal

7 Allowing students to update their employment details upon completion of studies

8 Alumni login

9 Students can see latest news, information about their eligibility for new levels of certificates,

possible employable opportunities

Page 29: rfp

29

4.5.6 Registration of Consultants, Instructors, Certifying Agency:

This moduleshould facilitate access by all of the assessors and assist the assessment managers to track

and manage all assessments, results etc.

1 Facility to empanel assessors and help conduct assessments

2 Maintaining database of all types of consultants for Vocational Training

3 Registration of Infrastructure Providers

4 Registration of Certifying Agency

5 Rating of Agencies

4.5.7 Placement Exchange:

Module which will be accessed by both the job providers and job seekers. All of the students/trainees

resumes upon passing out will move into this module as their resumes. This module will also help

connecting both ends and help categorise resumes etc.

1 Online repository and login for job-seekers and job providers

2 Classification of resumes by skill sets, tagging and ability to search jobs for job seekers and vice

versa for job providers to seek candidates.

3 Multi search capability by skill, location, pay, years of experience etc.

4 Email, mobile based communication built into the system with alerts.

5 Listing of open opportunities by Job providers.

4.5.8 Sector Skills Council’s functions – (future requirement)

Page 30: rfp

30

Sector skills Council would belike a forum for specific sectors and will devote their time to research,

promote, manage, build specific sectors of their focus. TheSector Skills Council would have focus on the

following:

1 Solution for LMIS to assist planning and delivery of training

2 Identification of skills and preparation of catalogue of skill types

3 Maintain skill inventory

4 Competency standards and qualifications

5 Standards, Certification and accreditation process

6 Rating of training providers

7 Renewal of certificates of Training , certifying and assessment agencies and associations

8 Job seekers, businesses, and institutions public and private are likely to make many labour market

related choices and decisions over their lifetime; hence the LMIS must be able to support this.

9 Provision for a continuous feedback, review and improvement of the system Data Migration where

necessitated & Integration with different LMISAbility to providing functionalities for conducting

entrance tests

10 Analysis and setting the parameters for an industry sector specific LMIS

4.5.9 Other Stake Holders

The other stakeholders in the success of the program include Prime Minister’s Office (PMO), Director

General Employment and Training (DGET), Employment Exchanges, State Govts, National /

International Government Agencies, Micro Finance Companies, Recruiter firms etc.

As the activities intensify for NSDC and the skill development, there will be several other stake holders,

some of whom listed above may require an access or an ability to connect to the NSDC application

Page 31: rfp

31

backbone to interface with their office and exchange of information and access to reports, data etc., the

application being built will need to have capability and flexibility to talk to all of these stake holders.

Students

Faculty/ Administrator

Faculty/ Administrator

Training Centers

Project Owners Students

Faculty/ Administrator

Faculty/ Administrator

Training Centers

Project Owners

NSDC Skills Development

Management System

PMO, Ministry of Finance National and International Government Agencies

DGET NSDC - Primary Responsibility Financing

Companies

Governance, Reports, Standards, Issues/challenges & Audit Micro Financing

Recruitment Platform

Connect Recruiters and Candidates

With other third party applications such as content management

Administrative Management Administrative

Management

Planning Commission National Skills Coord’n Board

Page 32: rfp

32

4.6 IMPLEMENTATION TIMELINE Thetotaltimelimitforthesuccessfulimplementationofthe solutionin NSDC and its associates shalln o t

be more than6monthsfromthedateofsigningthecontract,

whichwillbeexcludingthetimerequiredforapprovalsforthecritical intermediate

submissions.Timerequiredforapproval innormalcircumstances may not exceed 20 working days for

each such criticaldeliverables . (list of likely intermediaries should be submitted)

MilestonesfortheaccomplishmentofvariousstagesofNSDC projectshallbeasunder:

Activity TimelinesinWeeks Deliverables

PhaseI–DesignandImplementation

ProjectInitiation&TeamMobilization

T Detailingof Project Plan, Detailing ofResource Profile

1. BusinessRequirements Analysis.

2. Application Design

3. Prototype Creation

4. Placementofworkorder for Procurementof Hardware&Networking

T + 1. AS-IS processes Report and TO-BE processes Report

2. Submission of design document

3. Prototype Delivery and Demonstration – feedback to be incorporated and finalization

4. Issue of W.O

5. Development &Customisation / Installation and Configuration of or System and Completion of Design and Customizations of

T + 6. All customizations delivered

System installed and ready for testing

7. Testing&UAT

Modules

T + TestCases,Test Reports, UATSign-offCertificate

8. Installation&testingof Hardware&Networking components of application

T+ Installation&Test Report(8 weeks from the placement of work order)

PhaseII–Commissioning&Go Live

Page 33: rfp

33

Activity TimelinesinWeeks Deliverables

ApplicationTraining&HandholdingSupportofall themodulesmentionedin GroupI,IIandIII

T+ Training&Change Managementreport, Training Schedule/Plan, SatisfactoryTraining CompletionFeedback Report

Commissioning&Go-Live T+ Certificate of successful commissioning

Helpdesk SupportafterGo Live

For the initial

subscription period

of 5Years

PhaseIII–Operation&Supportover subscription period

Operation&SupportforApplication Enhancements and MaintenanceforHardware&Networking components.

For the

initialsubscription

period of 5years

MonitoringFramework,Escalation Reports,MIS reports withdetailsof Maintenance /Support/ Warranty Activities carried out.The frequencyofthese reports will be notified later.

4.7 SERVICE LEVEL REQUIREMENTS AND PENALTIES The proposer should be willing to offer the following Service Level Agreement (hereinafter referred to

as SLA) commitments, which shall form part of the contractual agreement. For the stated scope of work

and for the initial subscription period, the service provider shall be able to support the whole SDMS and

also the related Software, Hardware, Networking, Training for users to ensure the application uptime.

NSDC shall regularly review the performance of the services being provided by the Service Provider and

the effectiveness of this SLA.

4.7.1 Definitions

For purposes of Service Level Agreement, the definitions and terms which will also be specified in

the contract along with the following terms shall have the meanings set forth below:

Page 34: rfp

34

a. “Uptime”shall mean the time period for which the specified services / components with specified

technical and service standards are available to NSDC and its partner institutes. Uptime, in

percentage, of any IT component can be calculated as:

Uptime % = (uptime) / (Total Time – Maintenance Time) * 100

Where, Total Time is 24 hrs as its an web based application.

b. “Downtime”shallmeanthetimeperiodforwhichthespecifiedservices/

componentswithspecifiedtechnicalandservicestandardsasperSLAsarenot availableto NSDC and user

departments.

c. “Incident”referstoanyevent/abnormalities inthefunctioningofNSDC application or

infrastructureEquipment/specifiedservicesthatmayleadtodisruptioninnormaloperationsofNSDC

servicesandrelatedinfrastructure.

d. “ResolutionTime”shallmeanthetimetaken(aftertheincidenthasbeen reported a t the concerned

reporting center), in resolving (diagnosing,

troubleshootingandfixing)orescalating(tothesecondlevelortorespectiveVendors,

gettingtheconfirmatorydetailsaboutthesamefromtheVendorandconveyingthesametotheenduser),the

servicesrelatedtroublesduringthefirstlevelescalation.Theresolutiontimeshallvarybasedontheseverit

yoftheincidentreportedatthehelpdesk.

Theseveritywouldbeasfollows:

1.

Critical:Incidentswhoseresolutionshallrequireadditionalinvestmentincomponentsortime

.Theseincidentsshallimpacttheoverallfunctioning oftheNSDCapplication.Forexamplewhich

involves, purchaseofanyadditionalhardware/networking

componentlikeroutersetc,softwarebugfixing,etc.

2. Medium: Incidents, whose resolution shall require replacement of hardware or software

parts, requiring significant interruption in working of that individual component. For example,

installation of operating system, replacement of switch, etc.

Page 35: rfp

35

3. Low:Incidentswhoseresolutionshallrequirechangesinconfigurationof

hardwareorsoftware,whichwillnotsignificantlyinterruptworkingofthatcomponent.Forexample,in

stallationofprinteronaclient,replacementofLANchordetc.

4.7.2 CategoryofSLAs

This SLA document provides for the minimum level of services required as per contractual obligations

based on performance indicators and measurementsthereof.TheService

Providershallensureprovisioningofallrequiredserviceswhilemonitoringtheperformanceofthesametoeffe

ctivelycomplywiththeperformancelevels.TheservicesprovidedbytheService

ProvidershallbereviewedbyNSDC thatshall:

• RegularlycheckperformanceoftheService Provideragainstthis SLA. • Discussescalatedproblems,newissuesandmattersstilloutstandingfor resolution. • Review of statistics related to rectification of outstanding faults and agreed changes. • Robustness/ flexibility of the system to generate various reports as required by various stake

holders as NSDC, SSCs, Govt. Ministries, State Govt., DGET, associates, trainees, and other Govt, non Govt and international bodies

• Obtainsuggestionsforchangestoimprovetheservicelevels. • Feedback from NSDC’s associates about the level, quality and response time of support while

attending to / resolving the operational issues. • Response time of the Service Provider to escalated issues / noticed defaults/ complaints

TheSLAshall belogicallysegregatedinthefollowingcategories:

1. ImplementationServiceLevels

2. ITInfrastructurerelatedservicelevels

3. Support Service Levels

4. Risk Mitigation – inbuilt provision

The following measurements and targets shall be used to track and report performanceon aregular

basis. Thetargets shownin thefollowing table are applicableforthedurationofthecontract.

Page 36: rfp

36

4.7.3 Servicelevels

TheseSLAsshallbestrictlyenforcedandasoftwareaudit/certificationshallbecarriedoutatthesolediscretiono

fNSDC

forcertifyingtheperformanceoftheapplicationagainstthetargetperformancemetricsasoutlinedinthetableb

elow:

ServiceCategory Target Severity Penalty

Successful completion of Design,

Implementation and Customization of

all the modules mentioned in the RFP

as per the delivery schedule

As per delivery

Schedule

Critical A Penaltyof 0.5% of contract valueof

ApplicationandImplementation per

delayedweek and subject to a maximum of 5%

of contract value of

Application&Implementation Value.

Commissioning & Go- Live of

Hardware and Networking Equipment

As per delivery

Schedule

Critical A Penalty of 0.5% of contract value of

Application Development perdelayed week and

subject to a maximum of5% of hardware and

networking equipments value

Operation, Support and Management

of SDMS application

Service Provider

is required to

maintain up

time of98.5% in

a quarter.

Critical 5% penalty on the support fee for that quarter

if the down time goes below 98.5%. Incase

below 95% it would be 20%

Related hardware / networking

components. Availability (including

the OS and the database provided by

the Service )

Service Provider

is required to

maintain up

time of99.0% in

a quarter.

Critical 5% penalty on the support fee for that quarter

if the down time goes below 99% and 10%

penalty if the downtime goes below 96%

4.7.4 Prompt Service:

Service provider shall be responsible for maintaining the desired performance and availability of the

system/services/ manpower. Service provider should ensure prompt service support during Service

period.

Page 37: rfp

37

SECTION 5. INSTRUCTIONS TO PROPOSERS 5.1 Definitions Used 5.1.1 “Agreement” means the Agreement to be signed between the successful Proposer and

NSDC,including all attachments, appendices, all documents incorporated by reference together

withany subsequent modifications, the RFP, the proposal offer, the acceptance and all

relatedcorrespondences, clarifications, presentations.

5.1.2 “Authorized Representative” shall mean any person authorized by either of the parties.

5.1.3 “Proposer / Vendor / Proposer” means any firm or group of firms (called consortium)

offeringthe solution(s), service(s) and /or materials as required in the RFP. The word Proposer/

vendorwhen used in the pre-award period shall be synonymous with parties proposing for this RFP,

andwhen used after award of the Contract shall mean the successful party with whom NSDC signs

the agreement for rendering of services for implementation of this project.

5.1.4 “Contract” is used synonymously with Agreement.

5.1.5 “Default Notice” shall mean the written notice of Default of the Agreement issued by oneParty to

the other in terms hereof.

5.1.6 “Law” shall mean any Act, notification, bylaws, rules and regulations, directive, ordinance,order

or instruction having the force of law enacted or issued by the Central Government and/or any other

Government or regulatory authority.

5.1.7 “LoI” means Letter of Intent, which shall constitute the intention of NSDC to placethe Purchase

Order with the successful Proposer.

5.1.8 “Party” means the NSDC or Proposer, individually and “Parties” mean the NSDC and

Proposer,collectively.

5.1.9 “Proposal / proposal” means the Technical and Financial proposals all together, i.e., complete

proposalfor the implementation of scope of work as mentioned hereinabove

Page 38: rfp

38

5.1.10 “Request for Proposal (RFP)” means this document and its annexure, forms, enclosures etc etc.,

seeking a set ofsolution(s), services(s) and/or any combination of them.

5.1.11 “Requirements” shall mean and include schedules, details, description, statement of

technicaldata, performance characteristics and standards (Indian & International) as applicable

andspecified in the RFP.

5.1.12 “Termination Notice” means the written notice of termination of the Agreement issued by

oneParty to the other in terms hereof.

5.2 PROPOSER ENQUIRIES &NSDC RESPONSE A prospective Proposer requiring any clarification of the RFP documents shall notify the NSDC inwriting,

either by post, fax or email before 1500 hrs, of 7th

January 2011 at the following address:

National Skill Development Corporation D-4, Clarion Collection, (Qutab Hotel) ShaheedJeet Singh Marg New Delhi 11 0 016 Tel: 011 46 56 0414 Fax: 011 4656 0417 Email: [email protected]

NSDC will respond to the queries at the earliest but not later than 14th

5.3 PRE- PROPOSAL CONFERENCE

January, 2011

It is proposed to schedule a pre proposal conference at 1500 hrs, January 4th 2011. The Proposers are

requested to attend this pre- proposal conference to seek clarifications in matters related to the project

or the proposal process of this project. The reply to the queries of various Proposers in the pre-

proposal conference would be put up on the NSDC website (http://www.nsdcindia.org). Such

corrigendum, if issued, would form part of this RFP and the Proposers would be advised to prepare

their technical and financial proposals in accordance with such corrigendum.

Page 39: rfp

39

The pre proposal conference shall be held at the Office of CEO& MD of NSDC at D4-Clarion Collection,

Qutub Institutional Area, New Delhi. Only those Proposers, who have intimated NSDC about their

participation in pre proposal conference, will be allowed to attend the pre proposal conference.

However, non-attendance at the pre- proposal conference will not be a cause for disqualification of a

Proposer. Queries received after the set time limit shall not be addressed in the pre proposal conference

or any later stage.

5.4 VENUE & DEADLINE FOR SUBMISSION OF PROPOSAL The proposals duly completed as per the instructions given in this document and the amendments

issuedif any, shall be submitted to the following address on or before the last date of proposal

submission.

National Skill Development Corporation D-4, Clarion Collection, (Qutab Hotel) ShaheedJeet Singh Marg New Delhi 11 0 016 Tel: 011 46 56 0414 Fax: 011 4656 0417 Email: proposal @nsdcindia.org

Proposals must be received by NSDC at the address specified above on any working day from 10:30a.m.

to 5:00 p.m. and not later than 1500 hrs, 21st

5.5 PROPOSALPREPARATION COST

January’2011. The NSDC may, in exceptionalcircumstances

and at his discretion, extend the deadline for submission of Proposals by issuing aCorrigendum or by

intimating all Proposers who have purchased the RFP document, in writing bypost or email. In this case,

all rights and obligations of the NSDC and the vendors previously subjectto the original deadline will

thereafter be subject to the deadline as extended.

The Proposer shall bear all costs associated with the preparation and submission of its proposal, and

NSDC will in no case be responsible or liable for those costs, regardless of the conduct oroutcome of the

proposal process.

5.6 RIGHT TO TERMINATION/CANCELLATION

Page 40: rfp

40

Notwithstanding anything contained in this document, NSDC, reserves the rightto cancel/terminate the

proposal process without assigning any reason whatsoever, at any time prior to signingthe contract and

NSDC shall have no liability for above-mentioned actions.

5.7 CORRUPT OR FRAUDULENT PRACTICE In the event of the Proposer engaging in any corrupt or fraudulent practices during the

proposalprocess, as per the judgment of NSDC, the proposalwill be rejected. Any decision in thisregard

will be final and binding on the Proposer.

For the purpose of this clause: “Corrupt Practice” means the offering, giving, receiving or solicitingof

anything of value to influence the action of NSDC in the selection process. It also includesbringing undue

influence through any quarter or interfering directly or indirectly in the selectionprocess to affect its

outcome.

“Fraudulent Practice” means a misrepresentation of facts in order to influence selection process tothe

detriment of NSDC.

5.8 LATE PROPOSALS Any proposal received by NSDC after the deadline for submission of proposals prescribed in RFP will be

summarily rejected andwill be returned unopened to the Proposer.

5.9 PROPOSAL OPENING Total transparency will be observed while opening of proposals. Sealed proposal envelopes will

beopened on 1600 hrs on 24th

5.10 GENERAL TERMS OF PROPOSAL SUBMISSION

January. Technical proposal envelope will be opened and verified

forcompleteness. The opening of financial proposalwill be intimated later to the successful Proposers.

NSDC reserves the right at all times to postpone or cancel a scheduled RFP opening.

The venue for the opening of proposalis:

National Skill Development Corporation D-4, Clarion Collection, (Qutab Hotel) ShaheedJeet Singh Marg New Delhi 11 0 016 Tel: 011 46 56 0414 Fax: 011 4656 0417

Page 41: rfp

41

5.10.1 The Proposer must use the entire information furnished in the RFP includingscope, detailed

requirements of architecture of application, hardware,functional and technical specifications, other

annexure, forms, enclosures etc and other terms andconditions, bill of materials while submitting

the response.

5.10.2 All responses should be in English language. All responses by the Proposers tothis RFP

document shall be binding on such Proposers.

5.10.3 All responses including commercial and technical proposals would be deemed tobe irrevocable

offers / proposals from the Proposers and may, if accepted byNSDC, form part of the final contract

between NSDC and Proposer.

5.10.4 Proposers are advised to attach a letter from an authorized signatory attestingthe veracity of the

information provided in the response.

5.10.5 Any technical or commercial proposal submitted cannot be withdrawn / modifiedafter

theclosing date and time for submission of the proposal offers unlessspecifically permitted by NSDC.

5.10.6. Each offer should specify only a single solution which is cost effective andmeeting the tender

specifications and it is the responsibility of the Proposer todecide the best of breed solution.

5.10.7. In the event the Proposer has not quoted for any mandatory or optional items asrequired by

NSDC and forming a part of the RFP document circulated to the Proposers and responded to by the

Proposers, the same shall be deemed to beprovided by the Proposer at no extra cost to NSDC.

5.10.8. NSDC concludes that everything as mentioned in the RFP documentscirculated to the Proposers

and responded by the Proposers have been quoted forby the Proposers and there shall be no extra

cost associated with the same otherthan the cost quoted by the Proposer.

5.10.9. In the event, NSDC has not asked for the quotes for alternative prices and the Proposer furnishes

the alternative quotes in the Proposer’s financial proposals, thehigher of the quotes shall be taken

for evaluation purposes. However,payment by NSDC shall be made for the lowest quote.

Page 42: rfp

42

5.10.10 The Proposer at no point of time can excuse themselves from any claims by NSDC whatsoever

for their deviations in conforming to the terms andconditions, payment schedules, timeframe for

implementation etc. asmentioned in RFP documents.

5.10.11 By submitting a proposal, the Proposer agrees to promptly contract with NSDC for any work

awarded to the Proposer.

5.10.12 This RFP or clarifications or writings issued pursuant thereto shall not beconstrued as an

obligation on the part of NSDC to award a purchase contractfor any services or combination of

services.

5.10.13 NSDC reserves the right to reject any or all proposals in full without assigning anyreason

whatsoever.

5.10.14 The Proposer has to adhere to the time schedule of activities mentioned in theRFP and no

request to change the last date or extend period / time forsubmission shall be entertained by NSDC.

However, NSDC reserves its right toextend the date/time for submission of the responses without

assigning anyreason by notifying in the Website / displayed on the Notice Board.

5.10.15. Any additional or different terms and conditions proposed by the Proposerwould be

rejected unless expressly assented to, in writing by NSDC.

5.10.16 The offers containing erasers or alterations shall not be considered. Thereshould be no hand-

written material, corrections or alterations in the offer.Correct / proper technical information of the

product being offered must befilled in.

5.10.17 The response to the proposal should not carry any sections like ‘Clarifications’,‘As orally told’, ‘to

be discussed’, ‘interpretations’, ‘assumptions’ etc.

5.10.18 To assist in the scrutiny, evaluation and comparison of offers, NSDC may, atits discretion, ask any

of Proposers for clarifications to their offer.

5.10.19 NSDC reserves the right to separate the scope of hardware supply andany other licenses from

the total contract and procure the same itself.

Page 43: rfp

43

5.11 PREPARATION OF PROPOSAL The Proposer has to submit its response to the proposal in:

• Technical proposal form indicating the response to the technical andfunctional requirement

specificationsalong with Commercial proposal form furnishing all the relevant information.

• The Proposer has to submit his response inhardcopy and softcopy in a file format compatible

with Microsoft Office.

• The proposalmust be submitted in English Language, as per this RFP.

5.12 PROPOSAL FORMAT 5.12.1 The Proposer’s proposal should effectively communicate their solution and bepresented in the

specified formats for NSDC to assess alternatives. The proposalshould contain an

ExecutiveSummary.

5.12.2 The Proposer needs to provide an undertaking on the veracity of soft copy submittedwith the

Hard copy.

5.12.3 The Executive Summary should provide an overview of the Proposer’s organization, Proposer’s

products and services provided as part of the procurement. A briefdescription of the unique

qualifications of the Proposer should then be providedfollowed by a summary on capabilities and

past experience in implementing suchprojects.

5.12.4 The proposal should explain in detail with regard to the consortium vendors in casethe offer is a

consortium proposal. A summary of the activities of each vendor and therelevant expertise is to be

enclosed as a part of the Technical.

5.12.5 The Proposer needs to follow the terms and conditions envisaged in the RFP and should submit

an undertaking to the said effect as per theformat in FORM I.

5.12.6 The Principal Proposer, on behalf of all the Proposers forming the consortium need toprovide a

confirmation of a proposal by the Terms and conditions envisaged in this RFPand shouldprovide an

undertaking to the said effect individually as perFORM I.

Page 44: rfp

44

5.13 TECHNICAL PROPOSAL 5.13.1 Against each of the technical / functional requirements, Proposer’s response is required to be

notedfor each of the sections as described under specific sections. The details as required should be

specifically mentioned and presented in the manner as per FORM III hereinbelow.

5.13.2 The Proposer must provide his response to technical requirements in MS Word-2000/3format in

a structured and neat form.

5.13.3 Under no circumstances, the Proposer while giving their response should change

theinformation furnished by NSDC under Technical, Functional and other requirements inany of the

columns.

5.13.4 The commercial proposal should not contradict or deviate from the technical proposal in

anymanner.

5.14 COMMERCIAL PROPOSAL 5.14.1 The commercial proposal should be enclosed in a separate sealed envelope. The Schedule of

Pricesshould be presented and mentioned as per FORM IV herein below.

5.14.2 All costs should be inclusive of all taxes, duties, charges and levies of State or

CentralGovernments, as applicable, at the date of signing the Agreement and subject todeduction of

allstatutory deductions applicable, if any. The benefits realized by Proposer due to lower rates of

taxes, duties, charges and levies shall be passed on by Proposer to NSDC.

5.14.3 The Proposer has to include all costs like Travel, Lodging & Boarding, Local Travelexpenses, etc

incurred during the implementation as a part of the Bill of Materials andNSDC will not bear any

additional costs on these.

5.14.4 The prices quoted by the Proposers shall include all costs such as Taxes, Excise,Service Tax,

Custom Duties, VAT, Levies, Cess, Installation, Insurance, etc. that need to beincurred.

5.14.5 The prices quoted shall include transportation to the respective sites and insurance

tillcompletion of the acceptance process by NSDC. The prices should include the chargespayable for

Page 45: rfp

45

carrying out any modification, changes / upgrades to the “ Skill Development Management System”

solution or other equipment / software that is required to bemade in order to comply with any

statutory or regulatory requirements.

5.14.6 In case of any downward revision in Government levies, taxes, VAT,cess,excise, service tax,

custom duty etc. after the submission of the price proposal and up to the dateof invoice, the benefit

of the same shall be passed on or adjusted to NSDC.

5.14.7 Terms of payment indicated in the RFP shall be final and binding on the Proposer andno

alternate terms and conditions proposed in the Proposal shall be considered.

5.14.8 The Proposermust also furnish separately in the commercial proposal the recurring /

revenueexpenditure, if any.

5.14.9 For arriving at the total cost of the Solution, the Proposer should include costs forFacility

Management and Maintenance in the Bill of Materials for a period of 5years excluding 5 year

warranty period.

5.14.10 A detailed cost that includes initial deployment and ongoing support and approach to pricing for

enhancement and relative costs should be provided in proposal. Following should also be included

in proposal price:

a. Deployment of the application tools to support administrative management, tracking of

effectiveness of the skill development initiative, and placement of students. The application

should enable strong governance architecture.

b. Management of ongoing upgrades to the application in line with changing needs

c. Fee structure should include the costs that will apply to NSDC, project owner and training

centers, students, faculty etc

d. Placement modules and charges for the same.

e. Details of costs that may have to be borne by the different stakeholder groups need to be

provided by Proposer.

Page 46: rfp

46

SECTION 6. PROPOSAL EVALUATION 6.1 EVALUATION COMMITTEE(S) The Evaluation Committee(s) constituted by NSDC shall evaluate the technical and financialproposals.

The Committee(s) may choose to conduct negotiation or discussion with Proposers as per the

procedures of NSDC. The decisions of the Evaluation Committee(s) inthe evaluation of Technical and

Financial proposals shall be final. No correspondence will be entertainedoutside the process of

negotiation / discussion with the Committee(s).

6.2 PROPOSALOPENING AND EVALUATION The evaluation of the proposals will be carried out in following stages:

6.2.1 Technical evaluation:

The Proposer shall be examined prima facie to substantiate the compliancewith the Proposer’s

eligibility criteria as set out for this project in terms of organizational, financialand technical experience

etc. The proposal will be rejected, in case it does not meet the prequalification criteria. The next stage of

the evaluation will be an assessment of the technical proposal.Based on the short-listing of the pre-

qualified Proposers, the Committee will proceed to a detailedevaluation of the Technical proposals of

such pre-qualified Proposers in order to determine whetherthey are substantially responsive to the

requirements set forth in the RFP. Inorder to reach such a determination, NSDC will examine the

information supplied by the Proposers, and shall evaluate the same as per the evaluation criteria

specified in this RFP.

The Technical proposal Opening Committee will open all the parts of Technical Proposals, in

thepresence of Proposers’ designated representatives who choose to attend, at the time, date,

andlocation, to be intimated by NSDC.

NSDC shall review the submitted proposaland a proposalshall be rejected at thisstage if it does not

respond to important aspects of the RFP or if it fails to comply with thetechnical requirements.

Proposalmay be rejected at any stage of the evaluation if it is found that the company hasprovided

misleading information or has been black-listed by a central or any stategovernment or has indulged in

any malpractice/ unethical practice and has not honoredcontractual obligation elsewhere.

Page 47: rfp

47

The Proposers would/may be asked to make presentation on technical and operational aspect of

theproposal.

After the technical evaluation is completed and approved, NSDC shall inform the Proposers who have

submitted proposals, the detailed compliance of their Technicalproposals and shall notify those

Proposers whose Proposals did not meet the minimumtechnical criterion or were considered non-

responsive to the RFP and Scope of Work, thattheir Financial Proposals will be returned unopened after

completing the evaluation process.

NSDC shall simultaneously notify in writing to the Proposers that have complied with the Technical

criterion specified in the RFP the date, time and location for reviewing theFinancial Proposals.

A conditional proposal will not be entertained under any circumstances.

6.2.2 Financial evaluation:

Based on the results of the technical evaluation, duly constituted financialevaluation committee will then

proceed to open and evaluate the financial proposalof thetechnically acceptableProposers. The financial

evaluation will take into account the informationsupplied by theProposers in their financial

proposal.The Proposershould furnish detailed break up of costs.

6.2.2.1 Substantially responsive proposal: A substantially responsive proposal is one, which

conforms to therequirements, terms, conditions and specifications of the RFP withoutmaterial

deviation. A material deviation is one which affects in any substantial way thefunctionality, scope,

quality, or performance of the Deliverables, or which limits in anysubstantial way, inconsistent with

the RFP, NSDC’s rights or the Proposer’s obligations for, performance of the Project and the

rectification of which deviationwould affect unfairly the competitive position of other Proposers

presenting substantiallyresponsive proposals.

6.2.2.2 Technical Evaluation:Technical evaluation committee may recommend waiver of any minor

informality or nonconformityor irregularity in a proposal, which does not constitute a material

deviation,provided such a waiver does not prejudice or affect the relative ranking of any Proposer.

6.3 CONFIDENTIALITY OF PROCESS Information relating to the examination, clarification, evaluation and comparison of proposals,

andrecommendations for the award of the Project shall not be disclosed to Proposers or any

Page 48: rfp

48

otherpersons not officially concerned with such process until the award to the successfulProposer has

beenannounced.

6.4 CLARIFICATIONS OF PROPOSALS To assist in the examination, evaluations, and comparison of proposals, the Committee may, at

itsdiscretion, ask any Proposer for clarification of its proposal submissions. The request for clarification

and theresponse shall be in writing by post or email or by facsimile, but no change in the price

orsubstance of the Proposal shall be sought, offered, or permitted except as required to

confirmthecorrection of arithmetic errors discovered by the committee in the evaluation of the

proposals.

6.5 INITIAL EXAMINATION OF PROPOSALS Prior to the detailed evaluation of proposals, the committee and/or its nominees will determinewhether

the proposalhas been properly signed;and/or it has not beenproperly signed and/or there is a

discrepancy between the items on the checklist and the actualdocuments/material submitted etc. The

Evaluation committee reserves its right to declare such proposals as invalid.

6.6 CORRECTIONS OF ERRORS Proposers are advised to exercise greatest care in entering the pricing figures. No requests

regardingcorrection of mistakes in the financial proposals will be entertained after the quotations are

opened. Allcorrections like cutting or overwriting etc., if any, should be initialed by the person signing

thetender form before submission, failing which the figures for such items may not be considered.

Arithmetic errors in proposals will be corrected as follows:

• Where there is a discrepancy between the amounts in figures and in words, the amount inwords shall govern.

• Where there is a discrepancy between the unit rate and the line item total resulting frommultiplying the unit rate by the quantity, the unit rate will govern unless, in the opinioncommittee, there is obviously a gross error such as a misplacement of a decimal point, inwhich case the line item total will governor whichever is logically correct and lower.

• Where there is a discrepancy between the amount mentioned in the proposal and the line itemtotal present in the Schedule of Prices, the amount obtained on totaling the line items in theBill of Materials will govern.

• The amount stated in the proposal, adjusted in accordance with the above procedure, shallbe considered as binding, unless it causes the overall tender price to rise, in which case the proposal price shall govern.

Page 49: rfp

49

6.7 TECHNICAL EVALUATION CRITERIONS Technical proposals shall be evaluated for only those Proposers who meet the pre-qualificationcriterion.

The Evaluation Committee will evaluate the technical proposals on the basis of thetechnical evaluation

criterion as provided below.

At the option of NSDC, the Proposers qualifying the technical evaluation may be invited to

makepresentation on technical and operations aspect of the Scope of Work. Subsequently, in case of

anychange in Scope of Work etc., the Proposers qualifying the technical evaluation may be allowed

tosubmit their revised Financialproposals within 2 days (48hours) of formal notification of the same.

During the technical evaluation, the responses provided in technical proposal will be evaluated outof 40

marks. The Proposer will have to score at least 60 marks on the overall technical score of 100 to be

declared as technicallyqualified. Any proposalachieving a Technical Score less than 60 will be treated as

“NotTechnically Qualifying the Requirements” and will not be considered for further evaluation of

thefinancial proposals. The following evaluation parameters shall be used for defining the Evaluation

criterion for Proposers:

S. No

Particulars Max Marks

1 The Proposer/ Proposer Consortium experience in providing web based application and deployment of solution in the education and vocational skill development space in India/abroad. And its potential in developing Web Based Integrated skill training, Administration and MIS systems to NSDC and its Partners

15

2 Quality of Solution offered and the time required for the solution to be implemented is a key requirement

10

3 Approach and methodology, project implementation and management methodology must be defined / indicated in the proposal. Highlight in your response your commitment to transformation of the vocational training framework and a partnership driven approach/governance framework

10

4 Compliance with the scope of work indicated in the RFP without exclusion 10 5 Solution Design and architecture of the web based SaaS model solution

1. Scalability a. Robustness of the software

10

Page 50: rfp

50

S. No

Particulars Max Marks

b. Simplicity of implementation

2. Approach to addressing the needs of multiple stakeholders

3. Pricing innovation- reducing costs to stakeholders and creation of self-sustaining model for revenue generation and deployment of these funds for enhancements

4. Approach to ongoingaddition of centers and other stake holders and

support

6 Project execution team including

a) Profile of the each of the key leadership team member

b) Demonstrated experience in education / skill development space

Each CV will be evaluated on the basis of the following parameters. Percentage credit for the parameter is provided in parentheses.

• Academic qualifications – degrees and academic institutes (5%)

• Years of total experience (40%), highlight in your response your experience in new age industries

• Provide proof of working application for at least 6 months (30%)

• Strong knowledge of the skill industry (25%)

20

7 Understanding of the Skill Domain space 10

8 Technical Presentation and Demonstration of the short listed 15

100

THE SOLUTION PROVIDER WILL BE SELECTED BASED ON EVALUATION OF TECHNICAL &FINANCIAL

PROPOSALS, PREVIOUS TRACK RECORD ETC.

6.8 FINANCIAL EVALUATION CRITERIONS The Proposer having lowest overall financial quote will be given high priority while the evaluation

committee (s) may choose to conduct negotiation or discussion with any or all the Proposers as

deemed fit by NSDC.

The prices, once offered, must remain firm and must not be subject to escalation for any

reasonwhatsoever within the period of validity of the proposaland subsequent contract, if any.

Page 51: rfp

51

SECTION 7. TERMS AND CONDITIONS 7.1 CONTRACT DOCUMENTS The Proposer shall not, without prior written consent from NSDC, disclose the Contract or anyprovision

thereof or any specification, plan, drawing, pattern, sample or information furnished byor on behalf of

NSDC in connection therewith, to any person other than a person employed bythe Proposer in the

performance of the Contract. Disclosure to any such employed person shallbe made in confidence and

shall extend only so far, as may be necessary for purposes of suchperformance.

The Proposer shall not, without prior written consent of NSDC, make use of any document

orinformation made available for the project, except for purposes of performing the Contract.

All project related documents issued by NSDC, other than the Contract itself, shall remain theproperty of

NSDC and shall be returned (in all copies) to NSDC, on completion of the Proposer’s performance under

the Contract if so required by NSDC.

7.2 INTERPRETATION In case of any ambiguity in the interpretation of any of the clauses in the tender document,

theinterpretation of the clauses by Authorized Representative of NSDC shall be final and binding onall

parties.

7.3 COMMUNICATIONS Wherever Conditions provide for the giving or issuing of approvals, certificates,

consents,determinations, notices, requests and discharges, these communications shall be:

(a) in writing and delivered against receipt; and

(b) delivered, sent or transmitted to the address for the recipient’s communications asstated in the

Contract.

7.4 LANGUAGE The proposal and all correspondence and documents related to the proposalexchanged by theProposer

and NSDC should be in English. Supporting documents and printed literaturefurnished by the Proposer

Page 52: rfp

52

may be in any language other than English provided they areaccompaniedby an accurate translation of

the relevant passages in English language. Supporting material, whichis not translated in English, will

not be considered for evaluation. For the purpose of evaluationand interpretation of the proposal, the

English language translation shall prevail.

7.5 TIME FOR COMMENCEMENT AND COMPLETION The Proposer shall commence work on the Facilities within the period specified and withoutprejudice,

the Proposer shall thereafter proceed in accordance with the time schedule specified inthe

Implementation Schedule and any refinements made in the agreed and finalized Project Plan.

The Proposer shall attain completion of the project or of a part where a separate time forcompletion of

such part is specified in the Contract, within the time stated or within such extendedtime to which the

Proposer shall be entitled.

Deemed fit by NSDC, at mutually negotiated pricing, itmay opt to extend the subscription to the SaaS

application for additional term upon completion of the initial 5 year period subscription.

7.6 PROPOSER’S ROLES AND RESPONSIBILITIES The Proposer will be responsible for:

Preparation of Detailed Project Plan in line with the overall plan provided in the RFP.

Thesame should be prepared in consultation with NSDC.

Site preparation at NSDC Head Office, district and other field offices.

Seek approval from NSDC’s Project Implementation team on Application Design

Seek Approval on Prototypes from NSDC’s Project Implementation team

Share Unit, String and Application Test cases with NSDC’s Project Implementation team

Share test results at each stage with Project Implementation team

Handover the application for UAT to Project Implementation team only when it has been

thoroughly tested and has less than 5% overall failures of non-critical nature on its

submitted test cases and NSDC’s business test cases Procure, install, commission, operate

Page 53: rfp

53

and maintain requisite hardware & system software asper the requirements mentioned

in this RFP.

Addressing technology obsolescence by appropriate up-gradation, replacement

and/orreplenishment of Hardware deployed at various locations.

Insurance cover for the entire hardware infrastructure deployed at various locations for

theentire duration of the contract against vandalism, theft, fire and lightening.

Keep all system software at Data Center and other locations, up to date by installing

regularupgrades / patches.

Rectification of system software problems due to crashing or malfunctioning of

theOperating System within the time limits to meet the SLAs.

Facility Management including management of infrastructure, utilities, ensuring safety

andsecurity of equipment, resources, data etc at various locations during the contract

period.

Provide infrastructure & manpower as necessitated at various locations and provide

training and technicalsupport to NSDC.

Deployment of requisite resources for managing all the operations at various locations

(likeData Center, Helpdesk) and a dedicated team for the project.

Deployment of Application and upgrades / patches at Data Center & relatedagencies

offices.

Generation of MIS reports as per the requirements of NSDC or related agencies etc.

Ensuring the SLAs for downtime of system, delivery of various services, errors in

dataentry, etc., as defined in details in the RFP, are met.

Training and assistance to the staff members of NSDC and related agencies for using the

data etc as prescribed under the Scope of Work hereinabove.

Management and quality control of all services and infrastructure.

Any other services which is required for the successful execution of the Project.

Regular Backup as per the policy.

Page 54: rfp

54

Report all the problems related to the Software and Hardware to NSDC.

7.7 EMPLOYER’S (AND OTHER STAKEHOLDERS)ROLES AND RESPONSIBILITIES

It will be the responsibility of NSDC:

To create a dedicated team for overall supervisory and co-ordination for the project

including data supply, data verification, data analysis, MIS, etc.

Provide User Team for Systems Requirement Study

Approval/Acceptance of Requirement Specifications

Approval / Acceptance of Prototypes

Procuring Sandbox for development

Submission of Business Test Cases

Resources for UAT.

To monitor detailed SLAs and defined policies

To provide data for migration

To monitor detailed SLAs and defined policies

To suggest and approve plan/ schedule survey camps for data capturing i.e. data

verification etc.

To providing adequate support for data authentication/modification & smooth execution

of the survey camps.

To compile the feedback on application modules received from various users.

Freezing of change requests/additions/modification of application software.

To monitor the maintenance of proper records for inventory, receipt of infrastructureetc.

To monitor the feedback from the citizens, public & other stakeholders

To monitor computation of penalties, release of payments.

Page 55: rfp

55

Verification of data digitization

7.8 TERMS OF PAYMENT 7.8.1 NSDC shall follow the payment schedule as given in Form III and also the proposer should quote

in line with the terms of payment and payment schedule in form III

7.8.2 NSDC representative or its nominated committee shall certify actual implementation. The

Service Provider must provide support upto initial subscription of five years and after completion of

five years unless extended for another term, the Service Provider has to ensure proper hand‐holding

of the system to any new parties that NSDC may contract with.

7.8.3 The Service Provider’s request(s) for payment shall be made to NSDC in writing, accompanied

by an invoice describing, as appropriate, the service provided. The Service Provider will define the

services performed and substantiate with documents the fulfillment of obligations as stipulated in

the Contract.

7.8.4 Payments shall be made promptly by NSDC after submission of the invoice or claim by the

Service Provider and upon verification and certification by the concerned official.

7.8.5 Payments shall be made in Indian Rupees/ INR.

7.8.5 Prices:

7.8.5.1 Amount payable to the Service Provider as stated in the Contract shall remain non-

negotiable and fixed during the tenure of the Contract.

7.8.5.2 The prices quoted shall not be conditional /optional and it should be in line with the

technology andapproach presented during the Approach & Methodology Presentation by the

Service Provider before the Committee and in compliance with RFP and all corrigendum

uploaded on website. The Proposer shall not submit conditional/optional proposals.

Conditional/optional proposals are liable to be out rightly rejected.

7.9 TAXES AND DUTIES

Page 56: rfp

56

For all services supplied, the Proposer shall be entirely responsible for all taxes, duties, licensefees, etc.,

incurred until delivery of the contracted products or services to the Employer.If any rates of Tax are

increased or decreased, a new Tax is introduced, an existing Tax is abolished,or any change in

interpretation or application of any Tax occurs in the course of the performanceof Contract, which was

or will be assessed on the Proposer or its employees in connection withperformance of the Contract, an

adjustment as per the terms of this RFP shall be applicable and Contract Price shall be made to take into

account any such change in such manner as prescribed herein the RFP.

7.10 INTELLECTUAL PROPERTY RIGHTS (IPR) 7.10.1 During the Subscription phase, the responsibility to maintain the IPR of the Application(s)

providedby the selected Proposer would lie with the selected Proposer and the Proposer will

transferthe IPR to NSDC or its nominated agency during the Transfer stage, which could be post the

subscription period or an extended subscription period. Following conditions apply:

7.10.2 Ownership and Title: Title to the software, any enhancements, point updates and

documentation,including ownership rights to patents, copyrights, trademarks and trade secrets

therein shall bethe exclusive property of NSDC.

7.10.3 Reverse Engineering: The operator shall not reverse engineer any minor,major enhancementor

point update.

7.10.4 Confidentiality: The Proposer hereby acknowledges that the minor enhancements,

pointupdates, and documentation may contain information that may be trade secret and

proprietaryto NSDC. The Proposer hereby agrees not to disclose such information except to

personsand organizations expressly authorized by NSDC to receive such information. The Proposer

shall not remove or alter any copyright notices or proprietary legends affixed by NSDC to such minor

enhancements, point updates or documentation.

7.10.5 Copies: The Proposer shall make available to NSDC an additional copy of the

minorenhancements, point updates and documentation for back-up use on the computer.

7.10.6 Limitation of Damages: The Proposer shall not be liable for any failure to perform itsservices

because of circumstances beyond the control of Proposer, where such circumstancesshall include

Page 57: rfp

57

(without limitation) natural disaster, terrorism, labor disputes, war, declarationsofgovernments,

transportation delays, and misuse of the Software by NSDC.

7.10.7 NSDC requires retaining IPR, for all proposed applications (packages and custom-

madedevelopments) in the following manner:

• A copy of the application with current source code (and the means of compiling that code)

• A copy of all applications and all versions of source code (and the means of compiling thatcode)

• A copy of the source code for each application upgrade acquired (and the means ofcompiling that

code)

• Copies of the current and upgrade design documents or technical documents that can beused by

IT staff in supporting the applications or in making modifications to existing code.

• Any other artifacts created for/during the assignment

7.10.8 WARRANTY/ INDEMNITY:

The Proposer hereby represents and warrants that (i) the Services/Products as supplied, installed,

tested and accepted; (ii) use of the Services/Products in accordance with the Contract; and (iii) copying

of the Software and Documentation provided to the Employer in accordance withthe Contractdo not and

will not infringe any Intellectual Property Rights held by any third party and that it hasall necessary

rights or at its sole expense shall have secured in writing all transfers of rights andother consents

necessary to make the assignments, licenses, and other transfers of IntellectualProperty Rights and the

warranties set forth in the Contract, and for the Employer to own orexercise all Intellectual Property

Rights as provided in the Contract. Without limitation, the Proposer shall secure all necessary written

agreements, consents, and transfers of rights from itsemployees and other persons or entities whose

services are used for Project execution.

7.11 SOFTWARE SERVICES AND LICENSE AGREEMENTS

Page 58: rfp

58

The licenses of all software(s) to be deployed as part of the project would be in the name of NSDC and

the original copy of the same shall be deposited by the successful Proposer at the office of NSDC after

signing of the contract and before the installation of the software at any of the sites.

7.12 CONFIDENTIALINFORMATION The Employer/NSDC (“the Disclosing Party”) and the Proposer/ Proposer (“the Receiving Party”) shall

keepconfidential and shall not, without the written consent of the other Party hereto, divulge to anythird

Party any documents, data or other information furnished directly or indirectly by theotherParty hereto

in connection with the Contract (Confidential Information), whether such informationhas been

furnished prior to, during or following termination of the Contract.

The Proposer is deemed to be the Receiving Party of Confidential Information generated by the

Proposer itself in the course of the performance of its obligations under the Contract and relatingto the

businesses, finances, Proposers, employees, or other contracts of the Employer.

The Employer shall not, without the Proposer’s prior written consent, use any ConfidentialInformation

received from the Proposer for any purpose other than the operation andmaintenance of the project.

Similarly, the Proposer shall not, without the Employer’s priorwritten consent, use any Confidential

Information received from the Employer for any purposeother than those that are required for the

performance of the Contract.

7.13 AUTHORISEDREPRESENTATIVES

7.13.1 Employer’s Representative

The Employer/NSDC shall appoint and notify the Proposer/ Proposer in writing the name of the

Competent Authority /Officer. The Employer may from time to timeappoint some other person as the

Competent Authority /Officer in place of the person previously so appointedand shall give a notice of the

name of such other person to the Proposer without delay. No suchappointment shall be made at such a

time or in such a manner as to impede the progress of workon the Facilities. Such appointment shall

only take effect upon receipt of such notice by the Proposer.

Page 59: rfp

59

The Competent Authority /Officer shall represent and act for the Employer at all times during

theperformance of the Contract. All notices, instructions, orders, certificates, approvals and all

othercommunications under the Contract shall be given by the Competent Authority /Officer, except as

herein otherwiseprovided.

All notices, instructions, information and other communications given by the Proposer to theEmployer

under the Contract shall be given to the Competent Authority /Officer, except as herein

otherwiseprovided.

7.13.2 Proposer’s Representative

If the Proposer’s Representative is not named, the Proposer shall appoint the

Proposer’sRepresentative and shall request the Employer in writing to approve the person so appointed.

Therequest must be accompanied by detailed curriculum vitae for the nominee, as well as description

ofany other responsibilities the nominee would retain while performing the duties of the

Proposer’sRepresentative. If the Employer does not object to the appointment,

theProposer’sRepresentative shall be deemed to have been approved. If the Employer objects to

theappointment giving the reason therefore, then the Proposer shall appoint a replacement of

suchobjection.

7.13.3 Objections and Removals

The Employer may by notice to the Proposer object to any representative or person employed bythe

Proposer in the execution of the Contract who, in the reasonable opinion of the Employer,may have

behaved inappropriately, be incompetent, or be negligent. The Employer shall provideevidence of the

same, whereupon the Proposer shall remove such person from work.

7.14 PROJECT PLANNING AND PERFORMANCE 7.14.1 The agreed and finalized Project Plan will be prepared by the Proposer and approved by

the Employer/ NSDC.If required, the impact on the Implementation Schedule of

modifications agreed during finalizationof the agreed and finalized Project Plan shall be

incorporated in the Contract by amendment.

7.14.2 Proposer shall undertake to supply, install, test, and commission the Services in

accordance withthe agreed and finalized Project Plan.

Page 60: rfp

60

7.14.3 The progress report and other reports shall be prepared by the Proposer and submitted

to the Employer in the format and frequency specified.

7.14.4 If at any time the Proposer’s actual progress falls behind the project schedule described

in theagreed and finalized Project Plan, or it becomes apparent that it will so fall behind, the

Proposershall, at the request of the Employer’sCompetent Authority /Officer, prepare and

submit to the Competent Authority /Officer,a revised project schedule, taking into account

the prevailing circumstances, and shall notify the Competent Authority /Officer of the steps

being taken to expedite progress so as to attain completion of thefacilities within the stated

time for completion.

7.14.5 NSDC, as per rules, through its officials can undertake audit of the information

providedby the vendor at any point of time. The vendor must provide support and access to

the data and itsoffices meant for the project. In case of any dispute, NSDC’s decision will be

final and bindingon the vendor.

7.14.6 In case NSDC through audit or otherwise finds that the vendor has

purposefullycommitted any irregularity, NSDC has the right to terminate the contract with

immediate effect.

7.15 SUBCONTRACTING (AREAS THAT CAN BE SUBCONTRACTED, EXTENT ETC)

In case required, the Proposer shall seek permission and submit the list of sub- Proposers to

theEmployer for its prior approval in writing. Suchapproval by the Employer of a sub- Proposer(s) shall

not relieve the Proposer from any of itsobligations, duties, or responsibilities under the Contract.

7.16 TRANSPORT AND DELIVERY Delivery Schedule will require the explicit written consent of the Employer.The Proposer shall bear

responsibility for deliveries and cost of transport to the Project Sites.Unless otherwise specified, the

Proposer shall be free to use transportation through carriers registered in the Country.

7.17 PRODUCT UPGRADES At any point during performance of the Contract, should technological advances be introduced bythe

Proposer for the IT Services originally offered by the Proposer in its proposal and still to bedelivered,

Page 61: rfp

61

the Proposer shall be obligated to offer to the Employer the latest versions of theavailable information

technologies having equal or better performance or functionality at the sameor lesser unit prices.

7.18 INSPECTION AND TESTING NSDC and/or its representative reserve the right of inspection of processes being followed bythe

Proposer anytime during the period of the contract. NSDC reserves the right to inspect, test and,

wherever necessary, reject the hardware delivered atProject Site. This shall in no way be limited or

waived by reason of the Hardware having previouslybeen inspected, tested and passed by NSDC or its

representative prior to the Hardware shipment.

7.19 COMMISSIONING AND OPERATIONAL ACCEPTANCE Commissioning of the Project shall be commenced by the Proposer immediately afterintimation of

acceptance is issued by the Employer’s Representative.

The Employer shall supply the operating and technical personnel and all materials

andinformationreasonably required to enable the Proposer to carry out its obligations with respect

toCommissioning of project. Production use of the IT or Services shall not commence prior to thestart of

the formal Operational Acceptance Testing.

The Operational Acceptance Tests shall be the primary responsibility of the Employer, butshallbe

conducted with the full cooperation of the Proposer during Commissioning of the ITApplication to

ascertain whether they conform to the requirements and meets the standard ofperformance quoted in

the Proposer’s proposal, including, but not restricted to, the functional andtechnical performance

requirements.

If, for reason attributable to the Employer, the Operational Acceptance Test of the IT Applicationcannot

be successfully completed within the period specified, from the date of Installation oranyother period

agreed upon in writing by the Employer and the Proposer, the Proposer shall bedeemed to have

fulfilled its obligations with respect to the technical and functional aspects.

If the IT Application fails to pass the Operational Acceptance Test(s) then either:

• the Employer may consider terminating the Contract, or • If the failure to achieve Operational Acceptance within the specified time period is a

result of the failure of the Employer to fulfill its obligations under the Contract, then

Page 62: rfp

62

theProposer shall be deemed to have fulfilled its obligations with respect to the relevanttechnical and functional aspects of the Contract.

7.20 COMPLETION TIME GUARANTEE The Proposer guarantees that it shall complete the Commissioning of project within the timeperiods

specified in the Implementation Schedule and/or Agreed and Finalized Project Plan orwithin such

extended time to which the Proposer shall be entitled to.

7.21 DEFECT LIABILITY The Proposer warrants that all Services/Products to be delivered under this contract:

• shall be free from defects in the design and workmanship; • are newly manufactured, unused, and incorporate all recent material improvements

in design; and • complies with or exceeds the Technical Specifications • commercial warranty provisions of products supplied under the Contract shall apply

to theextent that they do not conflict with the provisions of this Contract. In addition, the Proposer warrants that: The Warranty Period shall commence from the date of Operational Acceptance of the ITServices.If

during the Warranty Period any defect should be found in the design, documentation, andworkmanship

of the Services provided by the Proposer, the Proposer shall promptly, inconsultation and agreement

with the Employer regarding appropriate remedying of the defects, andat its sole cost, repair, replace, or

otherwise make good (as the Proposer shall, at its discretion,determine) such defect as well as any

damage to the Products and/or Services caused by suchdefect.

7.22 FUNCTIONAL GUARANTEES The Proposer guarantees that during the Operational Acceptance, the IT Services shall attain

theFunctional Guarantees, subject to and upon the conditions therein specified.

If, for reasons attributable to the Proposer, the minimum level of the Functional Guarantees is notmet

either in whole or in part, the Proposer shall at its own cost and expense make such

changes,modifications and/or additions to the Services or any part thereof as may be necessary to meet

atleast the minimum level of such Guarantees. The Proposer shall notify the Employer uponcompletion

of the necessary changes, modifications and/or additions, and shall request theEmployer to repeat the

Page 63: rfp

63

Operational Acceptance Test until the minimum level of the Guarantees hasbeen met. If the Proposer

eventually fails to meet the minimum level of Functional Guarantees,the Employer may consider

termination of the Contract.

7.23 LIMITATION OF LIABILITY Except in cases of criminal negligence or willful misconduct and Intellectual Property RightsIndemnity

claims:

• neither Party shall be liable to the other Party, whether in contract, tort, or otherwise, for anyindirect or consequential loss or damage, loss of use, loss of production, or loss of profits orinterest costs, which may be suffered by the other Party in connection with the Contract, otherthan specifically provided as any obligation of the Party in the Contract, and

• The aggregate liability of the Proposer to the Employer, whether under the Contract, in tortor otherwise, shall not exceed the Contract Price, provided that this limitation shall not applyto any obligation of the Proposer to indemnify the Employer with respect to patentinfringement.

7.24 CRIMINAL CHARGES AND CONVICTION The Proposer warrants that it has disclosed and will continue to disclose during the term of

thisContract full details of all criminal convictions and all pending criminal charges against it or any ofits

personnel and associates that would reasonably be expected to adversely affect theProposer orthe

Proposer’s capacity to fulfill its obligations under this contract.

7.25 CARE OF IT PRODUCTS AND/OR SERVICES The Proposer shall be responsible for the care and custody of the IT Products and/or Services orany

part thereof until the date of completion of the Project, where the contract provides for completion of

the in parts, until the date of completion of the relevant part, and shall make good atits own cost any loss

or damage that may occur to the IT Products and/or Services or the relevantpart thereof from any cause

whatsoever during such period.

7.26 LOSS OF OR DAMAGE TO PROPERTY; ACCIDENT OR INJURY TO WORKERS

The Proposer shall aabide by the job safety, insurance, customs, and immigration measuresprevalent

and laws in force in the India. The Proposer shall indemnify and hold the Employer and its employees

and officers harmlessfrom and against any and all suits, actions or administrative proceedings, claims,

demands, losses,damages, costs, and expenses of whatsoever nature, including attorney’s fees and

Page 64: rfp

64

expenses, inrespect of the death or injury of any person or loss of or damage to any property by reason

of thenegligence of the Proposer or its employees, officers or agents.

7.27 INSURANCE The Proposer shall maintain standard forms of comprehensive insurance including liabilityinsurance,

system and facility insurance and any other insurance for the personnel, assets, data,software, etc. and

submit the list of all the insured items to NSDC prior to the start ofoperations.

7.28 FORCE MAJEURE • Neither Party to this Agreement or to the SLA shall be liable to the other for any loss ordamage

which may be suffered by the other due (directly) to the extent and for the duration ofany cause beyond the reasonable control of the Party unable to perform (“Force Majeure”)events such as but not limited to acts of God not confined to the premises of the Partyclaiming the Force Majeure, flood, drought, lightning or fire, earthquakes, strike, lock-outsbeyond itscontrol, labor disturbance not caused at the instance of the Party claiming ForceMajeure, acts of government or other competent authority, war, terrorist activities, militaryoperations, riots, epidemics, civil commotions etc. No failure, delay or other default of any Proposer to either Party shall entitle such Party to claim Force Majeure.

• The Party seeking to rely on Force Majeure shall promptly, within 2 days, notify the other Partyof the occurrence of a Force Majeure event as a condition precedent to the availability of thisdefense with particulars detail in writing to the other Party and shall demonstrate that it has andis taking all reasonable measures to mitigate the events of Force Majeure.

• In the event the Force Majeure substantially prevents, hinders or delays the Proposer’sperformance of Services necessary for the operation of Project’s critical business functions for aperiod in excess of 5 days, NSDC may declare that an emergency exists. NSDC will issue anotice to the Proposer to resume normal services at all affected sites and for all operationswithin a period of 7 days. In the event that the Proposer is not able to resume services withinthe next 7 days, NSDCmay terminate the Agreement and/or obtain substitute performancefrom an alternate Proposer. However, the event of Force Majeure is to be reviewed undertwo categories i.e. prior to commencement of operations and post commencement ofoperations respectively.

• Prior to commencement of operations: If the event of Force Majeure occurs prior tocommencement of operations and continues for a period in excess of 10 days, then NSDC will grant a period of 7 days to the Proposer to resume normal activities under thisAgreement. In case the default continues, then NSDC may discuss the issue with theProposer and revise the existing timelines for the Project. If the Proposer does notcomplete the Project Implementation in accordance with the revised timeless, NSDC will havethe option to terminate thisAgreement.

• Post commencement of operations: If Force Majeure occurs post commencement ofoperations and continues for a period in excess of five days, then NSDC will grant a period of7 days to the Proposer to resume normal services under this Agreement. In case the defaultcontinues, NSDC may grant an extension of time to the Proposer for rectifying thesituation. However, NSDC will deduct for each day of the extension period a percentageproportionate to the number of days

Page 65: rfp

65

and the affected areas/s from the next payable amount asper Payment Schedule. If there is any further delay despite the extended period, NSDC willhave the option to terminate theAgreement.

• Notwithstanding the terms of this section, the failure on the part of the Proposer under theSLA to implement any disaster contingencyplanning and back-up and other data safeguards in accordance with the terms of the SLA against natural disaster, fire, sabotage or other similaroccurrence shall not be an event of Force Majeure.

7.29 CHANGE IN LAWS AND REGULATIONS If after the date of proposal submission, any law, regulation, ordinance, order or by-law having the

forceof law is enacted, promulgated, abrogated or changed which shall be deemed to include any

changein interpretation or application by the competent authorities, that subsequently affects the costs

andexpenses of the Proposer and/or the Time for Completion, the Contract Price shall

becorrespondingly increased or decreased, and/or the Time for Completion shall be reasonablyadjusted

to the extent that the Proposer has thereby been affected in the performance of any ofits obligations

under the Contract.

7.30 COMPLIANCE WITH LAWS • The Proposer shall undertake to observe, adhere to, comply with and notify NSDC about all laws in

force or as are made applicable in future, pertaining to or applicable to the Proposer, their business, their employees or their obligations towards employees and all purposes of this tender and shall indemnify, keep indemnified, hold harmless, defend and protect NSDC and its employees/officers/staff/ personnel/representatives/agents from any failure or omission on its part to do so and against all claims or demands of liability and all consequences that may occur or arise for any default or failure on its part to conform or comply with the above and all other statutory obligations arising there from.

• The Proposer shall promptly and timely obtain all such consents, permissions, approvals, licenses, etc, as may be necessary or required for any of the purposes of this project or for the conduct of their own business under any applicable Law, Government Regulation/Guidelines and shall keep the same valid and in force during the term of the project, and in the event of any failure or omission to do so, shall indemnify, keep indemnified, hold harmless, defend, protect and fully compensate NSDC and its employees/ officers/ staff/ personnel/ representatives/agents from and against all claims or demands of liability and all consequences that may occur or arise for any default or failure on its part to conform or comply with the above and all other statutory obligations arising there from and NSDC shall give notice of any such claim or demand of liability within reasonable time to the Proposer.

• The Proposeragrees that the Proposershall not be entitled to assign / sub lease any or all of its rights and or obligations under this tender and subsequent Agreement to any entity including Proposer’s affiliate without the prior written consent of NSDC.

Page 66: rfp

66

7.31 EXTENSION OF TIME FOR COMPLETION The Time(s) for Completion shall be extended if the Proposer is delayed or impeded in theperformance

of any of its obligations under the Contract by reason of any of the following:

• any occurrence of Force Majeure or unforeseen conditions • any changes in laws and regulations • any default or breach of the Contract by the Employer, or any activity, act or omission of

theEmployer, or the Nodal Officer, or any other Proposers employed by the Employer; or • any other matter specifically mentioned in the Contractby such period as shall be fair and

reasonable in all the circumstances and as shall fairly reflect thedelay or impediment sustained by the Proposer.

7.32 SUSPENSION No order of suspension or termination of implementing Proposer would be issued by NSDCexcept after conducting an enquiry by an officer of NSDC, authorized in this regard. The grounds for suspension / termination of implementing Proposer may include inter alia

• Contravention of the conditions/clauses as would be specified in the Contract/Letter ofAppointment.

• Inability to perform the duties and requirements as would be specified in the contract.

7.33 TERMINATION FOR PROPOSER’S DEFAULT The Employer, without prejudice to any other rights or remedies it may possess, may terminate theContract forthwith in the following circumstances by giving a notice of termination and its reasonstherefore to the Proposer:

• if the Proposer becomes bankrupt or insolvent, has a receiving order issued against it,compounds with its creditors, or, if the Proposer is a corporation, a resolution is passed ororder is made for its winding up, (other than a voluntary liquidation for the purposes ofamalgamation or reconstruction), a receiver is appointed over any part of its undertaking orassets, or if the Proposer takes or suffers any other analogous action in consequence of debt;

• if the Proposer, in the judgment of the Employer has engaged in corrupt, fraudulent, coerciveor collusive practices in competing for or in executing the Contract, including but not limitedto willful misrepresentation of facts concerning ownership of Intellectual Property Rights in, orproper authorization and/or licenses from the owner to offer the hardware, software, ormaterials provided under the Contract.

If the Proposer:

Page 67: rfp

67

• has abandoned or repudiated the Contract; • has without valid reason failed to commence work on the project promptly; • persistently fails to execute the Contract in accordance with the Contract or persistentlyneglects

to carry out its obligations under the Contract without just cause; • refuses or is unable to provide sufficient Documentation, Services, or labor to execute

andcomplete the project in the manner specified in the agreed and finalized Project Planthen the Employer may, without prejudice to any other rights it may possess under the Contract,give a notice to the Proposer stating the nature of the default and requiring the Proposer toremedy the same. If the Proposer fails to remedy or to take steps to remedy the same withinfourteen (14) days of its receipt of such notice, then the Employer may terminate the Contractforthwith by giving a notice of termination to theProposer.

Upon receipt of the notice of termination, the Proposer shall, either immediately or upon such

date as is specified in the notice of termination,

• cease all further work, except for such work as the Employer may specify in the notice oftermination for the sole purpose of protecting that part of the project already executed, or any

• work required to leave the Site in a clean and safe condition; • deliver to the Employer the part of the project executed by the Proposer up to the date

oftermination; • to the extent legally possible, assign to the Employer all rights, title and benefit of theProposer to

the Project as of the date of termination, and, as may be required by theEmployer • deliver to the Employer all drawings, specifications, and other documents prepared by the

Proposer as of the date of termination in connection with the Project.

7.34 DISPUTES AND ARBITRATION 7.34.1 Arbitration

Any controversy or claim arising out of or relating to this project and the services to be rendered by

Proposer under or pursuant to this project Agreement, the interpretation hereof, or its breach shall, if

not resolved by mutual discussions between the parties, be settled by binding arbitration in accordance

with the Arbitration and Conciliation Act, 1996. Arbitration shall be conducted in New Delhi in English

language.

7.34.2 JURISDICTION

Page 68: rfp

68

All disputes and controversies between NSDC and Proposer shall be subject tothe exclusive jurisdiction

of the Courts at New Delhi the parties agree to submit themselves to the jurisdiction of such court.

ThisProject agreement shall be governed by the laws of India.

7.35 REPRESENTATIONS AND WARRANTIES

a) The Proposer warrants that they have obtained all necessary corporateapprovals to enter into

an Agreement and that no consent, approval, orRFP Document for Skill Development

Management System for NSDC, no withholding of objection is required from any governmental

authority withrespect to the entering into or the performance of this project.

b) The Proposerfurther warrants that they are under no obligation or restriction, nor shall

theyassume any such obligation or restriction, that would in any way interfere orconflict with, or

that would present a conflict of interest concerning, anyobligations under this project .

c) Proposer warrants that it shall perform the Services in a professional andworkmanlike manner

and materially in accordance with the applicablespecifications in the RFP.

d) The Proposer represents that it is duly incorporated, validly existing and ingood standing under

as per the laws of the state in which such Party isincorporated.

e) The Proposer represents that it has the corporate power and authority to enterinto Agreements

and perform its obligations there under. The execution,delivery and performance of terms and

conditions under Agreements by suchParty and the performance of its obligations there under

are duly authorizedand approved by all necessary action and no other action on the part of

suchParty is necessary to authorize the execution, delivery and performance underan

Agreement.

f) The Proposer represents that the submission of responses to the RFP execution,delivery and

performance under an Agreement entered in case the Proposer isselected:

• Will not violate or contravene any provision of its documents ofincorporation; • Will not violate or contravene any law, statute, rule, regulation,licensing

requirement, order,writ, injunction or decree of any court,governmental instrumentality or other regulatory, governmental orpublic body, agency or authority by which it is bound or by whichany of its properties or assets are bound;

Page 69: rfp

69

• Except to the extent that the same have been duly and properlycompleted or obtained, will not require any filing with, or permit,consent or approval of or license from, or the giving of any notice to,any court, governmental instrumentality or other regulatory,governmental or public body, agency or authority, joint ventureparty, or any other entity or person whatsoever;

• To the best of its knowledge, after reasonable investigation, norepresentation or warranty by such Party in this Agreement, and nodocument furnished or to be furnished to the other Party to thisAgreement, or in connection herewith or with the transactionscontemplated hereby, contains or will contain any untrue ormisleading statement or omits or will omit any fact necessary tomake the statements contained herein or therein, in light of thecircumstances under which made, not misleading. There have beenno events or transactions, or facts or information which has come to,or upon reasonable diligence, should have come to the attention ofsuch Party and which have not been disclosed herein or in a schedulehereto, having a direct impact on the transactions contemplatedhereunder.

Page 70: rfp

70

SECTION 8. ANNEXURE A

8.1 LIST OF MIS STATEMENTS TO BE SUBMITTED * REPORT NO

PARTICULARS PERIODICITY

1. Performance of a Training Project To be confirmed by NSDC

2. Ownership details of the Agencies being funded To be confirmed by NSDC

3. Partner-wise Progress Report To be confirmed by NSDC

4. Trainees Registration Details To be confirmed by NSDC

5. Directors’ Report To be confirmed by NSDC

6. Number of Proposals Approved To be confirmed by NSDC

7. Fulfillment of disbursement conditions To be confirmed by NSDC

8. Statement of Staff Details To be confirmed by NSDC

9. Statement of Disbursal (Category wise) To be confirmed by NSDC

10. Statement of vacancies notified in a particular time

period.

To be confirmed by NSDC

11. Statement of overall skilled manpower availability To be confirmed by NSDC

12 Statement of milestones achieved by the Service

Provider

To be confirmed by NSDC

Please note that the above list is only illustrative / indicative list and you may fill in other List of MIS Reports to suit NSDC’s specific requirements.

Page 71: rfp

71

8.2 REPORT 1 - MIS REPORT SHOWING PERFORMANCE OF A TRAINING

PROJECT FUNDED BY NSDC: REPORT FOR THE PERIOD OF …… DATE OF REPORT GENERATION – DD/MM/YYYY Particulars No of Students No of Centers Placement of

Trainees Average Cost per Trainee

Name of Project

Projected Actual Projected Actual Projected Actual Projected Actual

8.3 REPORT 2 – OWNERSHIP DETAILS OF THE AGENCIES BEING

FUNDED REPORT FOR THE PERIOD OF …… DATE OF REPORT GENERATION – DD/MM/YYYY ORGANISATION/ ENTITY

STRUCTURE /TYPE (E.g.Pvt Limited Company, Trust/ Society etc)

DETAILS OF SHAREHOLDERS/ TRUSTEES ACQUIRED ASSETS

TOTAL AMOUNT SANCTIONED

AMOUNT UTILISED

S. No. Description Head * Performa Invoice Price

Suppliers Name and Address

Import or Local

* The Head should fall under one of the following Land Building Plant & Mach. Office Equipment Computer Furniture Fixture and Electric Fittings Books

Page 72: rfp

72

8.4 REPORT 3 - MIS REPORT SHOWING PARTNERWISE PROGRESS REPORT:

REPORT FOR THE Period OF …… DATE OF REPORT GENERATION – DD/MM/YYYY Particulars No of Students No of Centers Placement of Trainees Average Cost per

Trainee Name of Partner

Projected Actual Projected Actual Projected Actual Projected Actual

8.5 REPORT 4 – TRAINEES REGISTRATION DETAILS 1. TRAINEE ID/ UID

2. NAME OF TRAINEE

3. FATHER’S NAME

4. DATE OF BIRTH

5. ADDRESS

6. EDUCATION UPTO 5TH STANDARD

PASS DROP OUT/FAIL

7. EDUCATION UPTO 10TH STANDARD

PASS DROP OUT/FAIL

8. EDUCATION UPTO 12TH STANDARD

PASS DROP OUT/FAIL

9. EDUCATION UPTO GRADUATION

PASS DROP OUT/FAIL

10.

EXPERIENCE

SECTOR GRADE NO OF YEARS

CONSTRUCTION UNSKILLED SKILLED

INFRASTRUCTURE UNSKILLED SKILLED

REAL ESTATE UNSKILLED SKILLED

11. TRADE REGISTERED FOR TRAINING

MASONRY / PAINTING / ELECTRICAL / PLUMBING / BAR BENDING /OPERATOR

12. TRAINING DURATION

13. NAME OF EMPLOYER

14. CURRENT WAGE

15. PRIOR TRAINING DETAILS, IF ANY

16. NAME OF ACCREDITATION AGENCY

17. LEVEL OF CERTIFICATION

** Please note that the above list is only illustrative / indicative list and you may fill in other List of MIS

Reports to suit NSDC’s specific requirements.

Page 73: rfp

73

8.5.1 FORM - I

(RFP for Skill Development Management System (SDMS) for NSDC)

PRINCIPAL PROPOSER’s UNDERTAKING LETTER

To:

National Skill Development Corporation D-4, Clarion Collection, (Qutab Hotel) ShaheedJeet Singh Marg New Delhi 11 0 016 Tel: 011 46 56 0414 Fax: 011 4656 0417 Email: ____________________

Dear Sir,

We, the undersigned, as principal Proposer, having examined the complete RFP document(along

with its annexures, forms etc), do hereby offer to produce, deliver, install, support and maintainSkill

Development Management System in full conformity of your requirements aselaborated in above

said RFP for the amounts mentioned by us in the Commercial proposal or suchother sums as may be

agreed to between us.

We hereby agree to all the terms and conditions stipulated in the RFP and submitherewith our

proposal for the said Project.

We undertake as a part of this contract for successful operation of the Skill Development

ManagementSystem in future by NSDC during the warranty and AMC period (ifcontracted).

Yours faithfully,

(Authorised Signatory)

In the capacity of ______________

Duly authorized to sign the proposal for and on behalf of Principal Proposer.

Page 74: rfp

74

Format of letter to NSDC on the Proposer’s letterhead

8.5.2 FORM -II

PROPOSERS’ PROFILE

National Skill Development Corporation

D-4, Clarion Collection, (Qutab Hotel)

ShaheedJeet Singh Marg

New Delhi 11 0 016 Tel: 011 46 56 0414 Fax: 011 4656 0417

Dear Sir,

Sub: Your RFP for Skill Development Management System Solution

With reference to the above RFP, having examined and understood the instructions, terms

andconditions forming part of the RFP, we hereby enclose our offer for the supply,

Installation,Integration, implementation and maintenance of the MIS as detailed in your above

referredRFP. We also hereunder submit the required information:

NSDC’s requirements

Proposer response

Year of establishment of the Company Mention date of establishment

Names and background of main promoters Give details

Nature of business Specify

Net Worth as of the last financial Year (specify year) of

the Proposer / Group as applicable.

Mention figures in Rs. in lacand

enclose supporting audited financial

statements Profits for last 3 years Year 1 (specify year) Year 2 (specify year)

Page 75: rfp

75

of the proposer /

li bl Year 3 (specify year)

Turnover for the last 3 years

of the proposer / group as

applicable.

Year 1 (specify year) Year 2 (specify year) Year 3 (specify year)

Major centers where the Proposer has developed

andinstalled similar MIS solution / applications

Give complete details/description of

such similar installed MIS solution

Number of software engineers employed Mention number and give listwith

names and qualifications

Major technology platforms on which the Proposer

offers

Give details

Type of quality certification obtained, if any

(ISO9001:2000/ SEI CMM etc., enclose photocopy)

Attach photocopies of certificates

Availability of MIS solutions from well known software

companies

Mention Yes/No

We confirm that a) we own the IPR of those parts of the software that are developed by usand b) we

have the permission to use third party components of the software from therespective Proposers.

We understand that NSDC is not bound to accept the offer and that NSDC has the rightto reject the offer

without assigning any reasons whatsoever.

Yours faithfully,

Authorised Signatory of Principal Proposer

(Name & Designation, seal of the firm)

Page 76: rfp

76

8.5.3 FORM III - COMMERCIAL PROPOSAL

FORM – III(RFP for Skill Development Management System for NSDC )

To: Date National Skill Development Corporation D-4, Clarion Collection, (Qutab Hotel) ShaheedJeet Singh Marg New Delhi 11 0 016 Tel: 011 46 56 0414 Fax: 011 4656 0417 Email: ____________________ Dear Sir,

Reg: RFP for Sill Development Management System for NSDC

Having examined the proposal Documents, the receipt of which is hereby duly acknowledged, we, theundersigned, offer to supply and deliver the Skill Development Management System Solution, in conformitywith the said proposal documents for the sum of .…………….(Rs.) or such other sums as may be ascertained in accordance with the Schedule of Prices attachedherewith and made part of this proposal. We undertake, if our proposal is accepted, to deliver, install and commission the technical solution inaccordance with the delivery schedule specified in the Schedule of Requirements/ purchase ordersissued from time to time. We agree to the proposal and the rates quoted therein for the orders awarded by NSDC up tothe period prescribed in the proposal which shall remain binding upon us. Until a formal contract is prepared and executed, this proposal, together with your written acceptancethereof and your notification of award, shall constitute a binding Contract between us.

We undertake that, in competing for (and, if the award is made to us, in executing) the abovecontract, we

will strictly observe the laws against fraud and corruption in force in India namely“Prevention of

Corruption Act 1988”.

We understand that you are not bound to accept the lowest or any proposal you may receive.

Dated this…………………… Day of………………………..2009.

(Signature)

(Name) (in the capacity of)

Duly authorized to sign proposal for and on behalf of the Principal Proposer.

Page 77: rfp

77

Schedule of prices (Commercial Proposal)

Sr. No

Activity Payment (%)

1 Application Deployment

One time setup costs for existing web based solution on a SaaS model.

To be paid only after commissioning and go live. The proposer to provide the criteria for charges illustrating what is applicable for NSDC, its stake holders etc.

2

Ongoing subscription costs for existing web based solution on a SaaS model

To be paid on quarterly basis and applicable from the date of go live. The proposer to provide the criteria for charges illustrating what is applicable for NSDC, its stake holders etc.

Customization and Implementation

On Contracting 10% of the total customization cost.

Business Requirement Analysis Sign off

10% of the total customization cost, if completed within the time frame mentioned in RFP

Completion of Design, Development and Coding of Customization

20% of the total customization cost, if completed within the time frame mentioned in RFP

Testing & UAT 25% of the customization cost, if completed within the time frame mentioned in RFP

Page 78: rfp

78

Sr. No

Activity Payment (%)

Sign off on Commissioning & Go‐Live

30% of the total customization cost, if completed within the time frame mentioned in RFP and declared bug free by NSDC 0r any PBG required for a yr for 5 % of Contract Value

5 year Support Services after Go‐ Live

To be paid quarterly and applicable from the date of Go-Live and1 year warranty support

3 Hardware & Networking Components (as applicable)

Supply, installation, commissioning & successful inspection of the goods ordered.

70% payment of the total Hardware and Networking Components Cost. The inspections will be done as decided by NSDC.

After Go Live of application 20% payment of the total Hardware & Networking Components Cost.

Project go‐live – 6 months after

10% payment will be paid against a PBG for 1 year

4 Additional customization costs during the initial first 5 year subscription period. Warranty support as applicable for the Hardware and networking components from the vendor source and costing for support post warranty period

Helpdesk support for initial 5 year subscription period

Paid quarterly after the end of every quarter

(Signature)

(Name) (in the capacity of)

Duly authorized to sign proposal for and on behalf of the Principal Proposer.

Page 79: rfp

79

8.5.4 FORM IV - TECHNICAL BID FORM

Technical specifications checklist

MIS Solution for NSDC:

Si

No

System requirement/ Technical specification Bidder compliance (Yes/No)

Bidder comments

1. List of Projects developed and delivered highlighting the ones in Education/Skill development field. List of all projects that are currently under development highlighting the ones in Education/Skill development field

2. Systems Requirement Study for customization: 2.1 The selected Proposer shall study and review the

objectives, business needs, business processes of all the NSDC departments / Partners and define the user requirement in detail. The Proposer shall carry out detailed discussions with NSDC & its associates, its training centers, and understand the existing systems and procedures, hierarchy of data, and document flow, authorization procedures etc. in various process areas including any opportunities of re-engineering the existing processes to align with the SDMS. Identification of the source of data

2.2 Identification of the nature and function of the data and their possible inter- linkages

2.3 Identification of the use of data with respect to its usage in information generation / system requirements

2.4 Assessment of the Information Flow across various Business Functions /Organizations /Locations/Branches and thereby arriving at the internal and external Interface Requirements.

In this phase, the Proposer is supposed to prepare the AS-IS process maps and get it approved from NSDC’s competent Authority.

Page 80: rfp

80

Si

No

System requirement/ Technical specification Bidder compliance (Yes/No)

Bidder comments

On the basis of the above, the need for the Skill Development Management System (SDMS) required at various levels of NSDC & its associate Training Centers shall be identified and documented by the Service Provider in the form of comprehensive report. Assessment of the various Reports required by stakeholders. At the end of this phase the TO-BE requirements have to be submitted. Deliverables: a. User’s Requirement Specifications (AS-IS) b. System Requirement Specifications documents (TO-BE)

3. System Requirements Specifications: Analysis of information requirements resulting in a Software Requirement Specifications (SRS) document that would form the basis of the MIS solution development once it is accepted by NSDC. The SRS would consist of, but not restricted to the following:

Database design, Description of the application structure, Prototype of screens and Description of the reports, manner/ scheduling of delivery, target users etc.The logical data model,Interface requirements to other systems of NSDC as applicable. Description of the Gap (manual) data capture application for data elements not available in any of the above processing systems of NSDC, The phasing of the application delivery. Integrating a reporting tool, Description of the tools that will be used. Routines for report distribution to various users Integration of an information portal.

The Proposer should develop the MIS solution based on

Page 81: rfp

81

Si

No

System requirement/ Technical specification Bidder compliance (Yes/No)

Bidder comments

the approved SRS. The scope would include, illustratively, database design, , integration of reporting tool, data entry software for capturing dataunavailable in the processing systems of the NSDC, routines for report distribution to various users, integration of an information portal etc.

4. General Application Requirements: 4.1 The system should be based on a Centralized MIS

database. 4.2 The application should allow any-time/any-where

access. Several remote centers may either have connectivity using data cards or may sporadically not have internet connectivity- Proposers are absolutely required to suggest alternate semi-online mechanisms to address this issue and the application should be light enough to work off a data card..

4.3 The application comprises of modules as defined in Clause 4.5 of the RFP. This is the indicative functionality requirement for the purpose of pricing by the proposer.

4.4 The users should be provided with restricted access to the information depending upon their security level.

4.5 The system must have the following security features and shall be in conformity with the Information Security Policy of NSDC on the lines of ISO 27001 including :

4.5.1 Idle user logout 4.5.2 Minimum password length should be 8 character

long 4.5.3 User lock after pre-defined unsuccessful login

attempts 4.5.4 Force password change after pre-defined periods 4.5.5 At the time of changing password, new password

should not be same 4.5.6 User ID and password cannot be same.

Page 82: rfp

82

Si

No

System requirement/ Technical specification Bidder compliance (Yes/No)

Bidder comments

4.5.7 Provision of security at every level of sub-portals / port lets

4.5.8 Facilitate to adopt an optimum solution platform, database management, front-end and backend tools, so that on integration it leads to an overall cost effectiveness minimizing the number of licenses at the client level.

4.5.9 There must be a complete Administration Management Systems.

4.5.10 24X7 Concept anytime anywhere. 4.5.11 Online Registration Management System. Option of

Payment Gateway would be an added advantage. 4.5.12 Facility to daily upload News, Events,

Announcements, Notices on your website.

5. Hardware, Network, Security and other Requirements: 5.1 Optimum design of the network based on

Data Communication and Networking Requirements the network design shall adequately address the issues like optimum latency, elimination of re-entry of data, scalability (both scaling up and scaling out), geographical redundancy of data etc.

5.2 The software solution shall contain all suitable security features and firewalls using the latest features to protect and secure the databases used by the proposed system, data in transit etc.Proposed solution should ensure all Security Aspects viz. Database Security, Application Access Security, Communication Channel Security, User level Security, etc and Compliance of all Terms and Conditions of this RFP.

5.3 The software solution shall be designed and developed in a manner so that the solution is scalable or can be upgraded as required. Also it should enable incorporation of any commercially available security solution.

Page 83: rfp

83

Si

No

System requirement/ Technical specification Bidder compliance (Yes/No)

Bidder comments

5.4 Appropriate access and authorization controls should be incorporated into policies and procedures.

5.5 The Service Provider should also address the issues relating to Business Continuity / Disaster recovery etc. in their solution set.

5.6 The Bidder must provide specification of the hardware configuration as well as the associated system software and database on which the application would be run including the hardware for web server, portal server, database server, application server, storage, the relative operating system and databases etc.

5.6.1 Application server /report server/ database server/ web server should be based on either X86 processor based servers running Windows Server 2003 or RISC processor based servers

5.6.2 The clients should be Windows XP or above based PCs with Internet Explorer as the browser.

5.7 Proposer is required to host the application on servers that provide high availability of the application. The Proposer is required to provide the required bandwidth and should furnish the proposed network diagram and details of the data center.

5.8 All technology equipment required to access the services at the NSDC vocational training provider’s premises will be procured by the vocational training providers. The Proposer may suggest the configurations of critical equipment such as desktops, and any other devices required to ensure effective data capture and controls.

5.9 The hardware should be planned keeping in mind the fact that NSDC’s skill development programmes will grow rapidly over the next five

years.

6. Testing: After the Customisation / Development and Implementation is complete the Service Provider (SP)

Page 84: rfp

84

Si

No

System requirement/ Technical specification Bidder compliance (Yes/No)

Bidder comments

shall have to start the testing of the software which delivers the user requirements as per the duly approved System Requirement Specifications document/Functional Specifications (FS). Deliverables: a. Results of tests b. Integration Test Plan and Results c. MIS reports

7. User Acceptance Testing: On completion of the implementation and testing of the fully integrated system by the Service Provider, the users of the system as per the acceptance criteria will test the system. The Service Provider shall conduct the User Acceptance Testing in co-ordination with the users & make all suitable changes suggested by the end-users. If after making suitable changes in the solution, the final software has some bugs, the service provider shall fix them. The test plan should address at least following issues: 7.1 System functionality 7.2 Accuracy of the system 7.3 Response time of the system 7.4 Data capture 7.5 Menu, screen and other navigation 7.6 Abnormal usage and system response. 7.7 Flexibility and susceptibility of the system to generate

various reports from various users 7.8 Validation, security and authorization 7.9 Integration 7.10 User friendliness as experienced by various users 7.11 Report generation – sample formats 7.12 The major activities involved at this stage of the

assignment are as follows: 7.12.1 Testing and debugging of programs

Page 85: rfp

85

Si

No

System requirement/ Technical specification Bidder compliance (Yes/No)

Bidder comments

7.12.2 Module testing 7.12.3 Develop test data along with expected outputs. 7.12.4 Integrated testing with the prepared data 7.12.5 Setup and enable access to the application at all

the offices. 7.13 The Bidder should install the application on a test

environment and assist NSDC’s team in carrying out the User Acceptance Test

8. Training:

8.1 The Service Provider shall be responsible for providing

Sensitization Training for 2 days to a majority of available employees of NSDC and its associate training centers. This training will cover general IT awareness and advantages that would accrue at 3 levels i.e junior, middle and senior level in the organization. The content for Sensitization Training may be finalized in consultation with NSDC.

8.2 Training to be taken care for all of the users at center

level as well

8.3 The Service Provider shall be responsible for providing training to the users at various levels. The training should be including the operational and administrative aspects of the system. The Service Provider should conduct extensive training for the relevant NSDC personnel. The training shall comprise of classroom training as well as hands-on training on the implemented system according to the functions of operators, supervisors, officers, executives and the application administrator

8.4 A detailed training schedule, including the dates, areas covered, time and the training literature in Hard/Soft

Page 86: rfp

86

Si

No

System requirement/ Technical specification Bidder compliance (Yes/No)

Bidder comments

Copy (to be supplied to the NSDC & its associate training centers) at various stages of the cycle must be provided in the technical proposal.

8.5 The Bidder should train NSDC’s project team in the database design, use of reporting tool and information portal

8.6 The Bidder should train the user team of NSDC in Application analysis and software implementation

Deliverables: • Training Plan

9. Application Support: 9.1 The Service Provider shall provide support for the

application and related hardware /networking components of SDMS solution for a period of five years (subscription period) from the date of acceptance of software (date of Go-Live o f the project). Service Provider shall continuously strive for improvement in package during the subscription period. In the event of any problems in the application software and related hardware /networking components, the Service Provider(s) will be entirely responsible to analyze and rectify the problems immediately for which no extra charges shall be paid. As part of the support, the Service Provider shall also submit a quarterly log report depicting the module wise changes made in the software with reasons thereof.

9.2 Also up gradation of all the application modules used in NSDC and supplied by the Service Provider, with the latest version available in the market shall be the responsibility of the Service Provider.

9.3 The Bidder should provide application maintenance for error fixes, additions/ modifications to the software to

Page 87: rfp

87

Si

No

System requirement/ Technical specification Bidder compliance (Yes/No)

Bidder comments

cater to changes to data sources and/or new reporting requirements during warranty period of one year as well as, optionally, during the post-warranty period

9.4 The technical documentation involving detailed instruction for operation and support is to be delivered with installation of the application.

9.5 The Bidder should provide comprehensive documentation of the application including the application architecture, description of the interfaces, data model, database table structure, complete description of the data element (in the form of metadata etc.

9.6 Proposer should provide a helpdesk to support users for any issues / clarifications / guidance etc.

10. Reports: 10.1 The scope of work as detailed hereinabove would

include submission of periodic MIS reports as may be required and specified by NSDC. An indicative list of the MIS reports to be submitted along with their periodicity is in ANNEXURE A

10.2 Reporting toolshould be capable of providing report design, generation, distribution and archiving features as further described below:

10.2.1 Provision of graphical interface with drag-and drop functionality for report design

10.2.2 Ability to extract data from multiple databases, 10.2.3 Ability to design simple tabular reports as well as

complex reports 10.2.4 Support for embedding subtotals in columns as

well as built-in functions like AVERAGE, MAXIMUM, and MINIMUM etc.

10.2.5 Support for placing charts on the report 10.2.6 Ability to add various formatting features such as

lines, boxes, shades etc.

Page 88: rfp

88

Si

No

System requirement/ Technical specification Bidder compliance (Yes/No)

Bidder comments

10.2.7 10.2.8 The reporting feature should be able to provide

cross dimensional views of information. 10.3 The application should be able to export information

in various formats and also accept information from different sources in standard formats.

10.4 The application should use an enterprise information (or report) portal for publishing reports through a single point access. The portal should support the following features:

10.4.1 Support for personalization that provides links to only those reports that the user is interested in

10.4.2 Support for grouping of various reports 10.4.3 Facility for search for a report based on name,

author or key word 10.4.4 Suggest and implement an appropriate Reporting

tool to handle the above requirements.

11. Other Features if any