Page 1
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 1
Adjudication Application No. 1057877_1453
This is a decision made under the Building and Construction Industry Payments Act 2004 (Qld): Authorised Nominating Authority: Adjudicate Today Pty Limited
Adjudicator: Andrew Bruce Wallace
Registration Number: J47895
Claimant: Simcorp Developments and Constructions
Pty Ltd
ACN: 096 658 776 Respondent: Gold Coast Titans (Property) Pty Ltd ATF
Gold Coast NRL Property Trust
ABN: 51 826 843 853
Project: Construction of Titans Training Facility –
Centre of Excellence, Robina Queensland
Date of Service of Payment Claim: 10 March 2010
Amount of Payment Claim: $5,205,068.13 (including GST)
Date of Payment Schedule: 24 March 2010
Amount of Payment Schedule: -$33,682.00
Date of Section 21(2) Notice (if any): N/A
Date of Adjudication Application: 9 April 2010
Date of Adjudicator’s Acceptance: 15 April 2010
Date of Adjudication Response (if any): 19 April 2010 Date of Adjudication Decision: 14 May 2010
Adjudicated Amount: $2,230,212.991
Due Date for Payment: 24 March 2010
(including GST)
Rate of Interest: Penalty rate prescribed under s.67P(3)(a) of
Queensland Building Services Authority Act
1991
Apportionment of Adjudication Fees: Respondent: 75%
Claimant: 25%
1 The Adjudicated amount must be read subject to my remarks in paragraph 491 herein
Page 2
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 2
Decision This is a decision made under the Building and Construction Industry Payments
Act 2004 (Qld) (“the Act”).
In respect of the Claimant’s Payment Claim, I decide that:
• The amount of the progress payment to be made by the Respondent to
the Claimant is the adjudicated amount referred to on page 1 herein;
• The date upon which the payment became due is the Due Date for
Payment referred to on page 1 herein;
• The rate of interest on the adjudicated amount is the rate referred to on
page 1 herein; and
• The Parties are liable to pay the adjudication fees in accordance with the
details referred to on page 1 herein.
______________________________________________________________
Introduction and Background 1. This is an adjudication application arising from a written AS4000-1997
building contract entered into by the Claimant building contractor (“the
Claimant”) and the Respondent principal (“the Respondent”) on or about 29
June 2009 (“the contract”), whereby the Claimant agreed to complete the
construction of training facilities for the Respondent (“the works”), otherwise
known as “The Titan’s Centre of Excellence” in Robina, Queensland.
2. The contract sum was in the amount of $16,405,394.00 including GST. There
is a very long and complicated history surrounding the contract formation, to
which I shall return below.
3. After what appeared to be a successful relationship between the parties, a
dispute has arisen involving a number of different issues including:
Page 3
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 3
3.1. What I shall call “jurisdictional issues” which if I accept, may preclude me
having the legislative authority to make an adjudication decision pursuant
to the Act;
3.2. The contract sum;
3.3. The monies paid to the Claimant under the contract;
3.4. The Claimant’s entitlement to variations; and
3.5. Various set-off amounts propounded by the Respondent.
Procedural history and jurisdiction 4. I accept the following information details the procedural history of this
application and find that there is jurisdiction for making a decision pursuant to
the Act.
5. The details of the timing of the issue of the relevant documents and work are:
5.1. The relevant contract in respect of this Application was entered into on
or about 29 June 2009.
5.2. A valid Payment Claim was served on the Respondent on or about 10
March 2010. The Payment Claim was in the amount of $5,205,068.13
(“including GST”) (“the claimed amount”).
5.3. The Respondent did serve a Payment Schedule on the Claimant in
accordance with the requirements of s.18(4)(b)(ii) of the Act (“the
Division 1 Payment Schedule”) on 24 March 2010. It provided a
scheduled amount in the sum of -$33,682.00.
5.4. The Claimant made an application for Adjudication (“the Application”) on
9 April 2010 to a Registered Authorised Nominating Authority, Adjudicate
Today. This is within the required 10 business days after the Claimant
received the Payment Schedule.2
2 Section 21(3)(c)(i) of the Act
Page 4
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 4
5.5. I am satisfied that the Claimant also served a copy of the Application on
the Respondent on 12 April 2010 by way of personal service.3
6. The Application was properly made with regard to the time frames stipulated
by the Act. Specifically, I have considered the following:
6.1. Does a construction contract exist between the parties to which the Act
applies?
6.2. Has the Claimant served on the Respondent a valid Payment Claim?
6.3. Has this Application been made to an Authorised Nominating Authority?
6.4. Has the Application been properly referred to me and have I caused a
notice of acceptance to be served on the Parties?
7. I am satisfied that these elements, essential to bring this decision within the
requirements of the Act have all been satisfied.
8. I also find as facts that:
8.1. the work was construction work;
8.2. the work was performed in Queensland;
8.3. there existed at the relevant time a relationship of contract between the
parties;
8.4. a right to a progress claim existed;
8.5. the Payment Claim was properly endorsed;
8.6. the Payment Claim details some element of work undertaken within 12
months of the date of service of the Payment Claim;
8.7. in other regards the Payment Claim and my appointment comply with the
Act;
8.8. the Respondent did serve a valid Payment Schedule under s.18(2) of the
Act;
8.9. the Application:
3 See correspondence from Sawford Voll Lawyers to Adjudicate Today, dated 14 April 2010
Page 5
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 5
8.9.1. identifies the Payment Claim; and
8.9.2. was accompanied with the relevant application fee (if any).
9. In reaching my decision I have considered:
9.1. the requirements of the Act;
9.2. the contract between the parties;
9.3. the Payment Claim and the Application, together with properly made
submissions and documents provided therein;
9.4. the Payment Schedule together with properly made submissions and
documents contained therein; and
9.5. the Adjudication Response.
10. In reaching my decision, I have not taken into consideration:
10.1. Nil.
Reasons for the Decision Jurisdictional Issues 11. The Respondent in the Payment Schedule objected to the validity of the
Payment Claim on the following bases:
11.1. The Claimant failed to follow the contractual requirements for the
delivery of a Payment Claim or final claim pursuant to clause 37.2 or
clause 37.4 of the contract;
11.2. The purported Payment Claim was in breach of the Act as there were
at the time of its issuance, two claims on foot under the Act for the
same works; and
11.3. The purported Payment Claim was in breach of s.17(5) of the Act as
there was more than one payment claim in relation to each reference
date.
Page 6
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 6
Condition Precedent
12. In respect to the Respondent’s allegations that the Claimant has failed to
comply with the requirements of clause 37 of the contract, the Claimant
argues in the Application:
12.1. The terms of the contract must give way to the Act. In that regard, it
seeks to rely on what Hodgson JA remarked in Plaza West Pty
Limited v Simon’s Earthworks (NSW) Pty Limited [2008] NSWCA 279
at 53-54.
12.2. The failure of a party to follow a “condition precedent” does not
prevent or obstruct the operation of the Act, nor does it invalidate
entitlement to either make a claim or receive payment for that claim.
12.3. Or at least appears to argue that clause 37 should be read pursuant
to s.99 of the Act because it purports to annul, exclude, modify,
restrict or otherwise change the effect of a provision of the Act.
13. In the Adjudication Response, the Respondent:
13.1. Sought to distinguish the applicability of Plaza West.
13.2. Argued that as the Payment Claim was not served on the 30th of the
month pursuant to Item 28(b) of the contract Annexure Part A, it was
invalid;
13.3. Sought to rely on the decisions of F.K Gardner & Sons Pty Ltd v
Dimin Pty Ltd [2007] 1 Qld R 10 per Lyons J at [24] and the decisions
of Walter Construction Group Ltd v CPL (Surry Hills) Pty Ltd [2003]
NSWSC 266 at para [59] and Jemzone Pty Ltd v Trytan Pty Ltd
(2002) 42 ACSR 42 at 50 in relation to the statutory regime requiring
strict compliance with the provisions of the Act.
14. It is not entirely clear from the Respondent’s submissions in the Payment
Schedule as to the extent of its complaint about the Claimant’s failure to
comply with clause 37 of the contract.
Page 7
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 7
15. Item 28(b) of Annexure Part A of the contract requires Payment Claims to be
served on the 30th day of each month following the delivery of a progress
claim under Item 27(a).
16. At paragraph 13 of the Adjudication Response, the Respondent submits that
“There is clearly no restriction on the ability to serve a payment claim every
month as the clause sets up a monthly regime. To the extent that the regime
provided for the response (sic) by the 30th day of each month it is clear that
the proper construction of the contract would have provided for the last day of
February as being the reference date.”
17. On balance, I agree with the submissions of the Claimant on this point.
Clearly, the contract does not allow for a reference date of the 30th of
February. The reference date is therefore, according to Schedule 2 of the
Act, taken to be the last day of the relevant month. Both parties appear to
agree (although by different methods of calculation) that the reference date
was in fact 28 February 2010.
18. The fact that the Payment Claim was served on 10 March 2010 and not on 28
February 2010 is of no importance. Section 12 of the Act provides:
‘From each reference date under a construction contract, a person is entitled to a progress payment if the person has undertaken to carry out construction work, or supply related goods and services, under the contract.” [My emphasis].
19. Support for the ongoing entitlement to claim from and not necessarily on
each reference date is obtained from the decision of Fryberg J in Tenix
Alliance Pty Ltd v Magaldi Power Pty Ltd [2010] QSC 7 where his Honour at
pp 8-10 declined to follow the reasoning of Daubney J in Reed Construction
(Qld) Pty Ltd v Martinek Holdings Pty Ltd [2009] QSC 345. Respectfully, I
agree with Fryberg J’s interpretation of when the entitlement arises under
s.12.
Page 8
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 8
20. I also agree with the Claimant’s submissions, relying on what Hodgson JA
said in Plaza West at [54] that a failure to comply with a condition precedent
under the contract, ought not prevent entitlement to make a claim under the
Act.
21. I am in any event not satisfied that the Claimant’s obligation to serve a
progress claim under the contract was a condition precedent to the service of
a payment claim under the Act. Whilst clause 37 of the contract seems to
require the service of a progress claim on the Superintendent prior to the
service of a payment claim, clause 37.2 (as amended by special condition)
seems to allow for the issuing of a certificate by the Superintendent even if a
progress claim has not been issued.
“37.2 Certificates … If the Contractor does not make a progress claim in accordance with Item 33(a), the Superintendent may issue the progress certificate with details of the calculations and shall issue the certificate in paragraph (b).”
22. In addition to this, the service of a progress claim and the resultant
Superintendent’s certificate seems to be duplicitous to the service of a
payment claim and payment schedule under the Act. To prescribe under the
contract (if in fact it does) that such a progress claim must first be issued prior
to the service of a payment claim under the Act is in my view an attempt to
modify, restrict or otherwise change the effect of a provision of the Act and is
therefore void pursuant to s.99 of the Act as submitted by the Claimant in
paragraph 5.4 of the Application.
23. This is not an issue which invalidates the Payment Claim, nor is it a valid
reason for withholding payment.
Abuse of Process
24. In respect of the Respondent’s submission that there were two claims on foot
for the same works, the Claimant relies upon s.17(6) of the Act.
Page 9
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 9
25. The Respondent argues that by the Claimant’s act of issuing the Payment
Claim on 10 April 2010, whilst it had proceedings on foot to recover much of
the same monies under ss.19(2) and 20(2) of the Act was an abuse of
process.
26. This submission of the Respondent’s at first examination has some merit.
27. On or about 5 February 2010, the Claimant filed an application in the
Supreme Court seeking judgment pursuant to ss.19(2) and 20(2) of the Act in
the sum of $4,224,272.50.
28. The contract was terminated by one or the other party between 17 and 19
February 2010. For the purposes of this Application, I neither have
jurisdiction to determine the validity of the termination, nor is it relevant for
present purposes.
29. The Claimant’s Supreme Court application was listed for hearing on 19
February 2010. However, due to some evidentiary matters in relation to
service of the Payment Claims the subject of that application, it appears that
the parties agreed by consent to treat the application as being one started by
way of claim and statement of claim. Certain Orders were made by Byrne
SJA which required the filing and exchange of pleadings and certain
undertakings.
30. In or about 8 March 2010, at the instigation of the Claimant’s solicitors, the
parties via their respective solicitors exchanged correspondence in relation to
the discontinuance of the Claimant’s proceedings.
31. On 10 March 2010, the Claimant’s solicitors served the Payment Claim on the
Respondent’s solicitors.
Page 10
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 10
32. An application for leave to discontinue the Claimant’s proceedings was filed in
the Supreme Court on 11 March 2010.
33. On 18 March 2010, the Respondent filed an originating application seeking
declaratory and injunctive relief in respect of the validity of the Payment
Claim.
34. On 23 March 2010, Douglas J heard both parties’ respective applications.
His Honour’s decision has been reserved. I have confirmed with his Honour’s
associate that no interim injunctive relief preventing me from making my
decision was made by his Honour. It is unknown to me whether the
Respondent sought any such interim relief.
35. The Respondent now complains that the prosecution of the Application before
me, whilst proceedings remain on foot in the Supreme Court is an abuse of
process “where it is clear that Simcorp has an election to proceed with a claim
for a debt in court or to claim the matter through adjudication.”4
36. However, in Senior Counsel’s submissions to the Court on behalf of the
Respondent5
“the court will, normally at any rate, allow a plaintiff to discontinue if he wants to provided that no injustice will be caused to the defendant. It is not desirable that a plaintiff should be compelled to litigate against his will. The court should therefore grant leave, if it can without injustice to the defendant, but in doing so should be careful to see that the defendant is not deprived of some advantage which he has already gained.”
, it appears to be conceded by the Respondent that the Claimant
ought to be given leave to discontinue the proceedings on certain terms. Mr
Dunning SC referred to the decision of Graham J in Covell Matthews &
Partners v French Wools Ltd [1977] 1 WLR 876 at 879, where he said:
37. Whilst not wanting to preempt his Honour’s decision, it is likely, given that it is
not contested, that the Claimant will be given leave to discontinue. The only
matters which appear contested are the Respondent’s entitlement to costs 4 See para 10 of the Adjudication Response 5 See para 12
Page 11
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 11
and whether or not the Claimant ought to be prevented from further
prosecuting its claim under the Act until such time as it pays the
Respondent’s costs of the discontinued proceedings.
38. In my view, given that the application for leave to discontinue was made,
albeit one day after service of the Payment Claim and given that that aspect
of the application appears to be uncontested, it is not an abuse of process to
maintain the Application before me. In hindsight, it would have perhaps been
preferable for leave to have been granted prior to the Payment Claim being
served, but it appears to me on the facts available to me that the result is
likely to be the same. If I am wrong in that regard, then his Honour will no
doubt rule accordingly and the Respondent’s originating application will be
successful and the Payment Claim and the Application will be rendered void.
39. I should add at this point that on 23 April 2010, I wrote to the parties and
invited them to in effect, “suspend” the adjudication process until such time as
his Honour had made his decision. Unfortunately, whilst the Respondent
agreed to that request the Claimant did not. This in effect has placed me in
the rather unenviable position where I have had no choice but to continue
with the making of my decision and the resultant “second guessing” of what
his Honour may ultimately determine. For completeness, I attach and mark
as Annexure “A”, a copy of my correspondence to the parties dated 23 April
2010.
40. If leave of the Court is not so granted and given that as I understand it,
pleadings have not been filed6
6 See para 6 of the Respondent’s Submissions to the Supreme Court
, as there was consent by the parties to treat
the matter as though it had been commenced by way of claim and statement
of claim, there is nothing preventing the Claimant from prosecuting its claim in
Page 12
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 12
the Court under the contract, rather than the Act, and proceeding with parallel
proceedings under Part 3 of the Act pursuant to s.100.
41. This is not an issue which invalidates the Payment Claim, nor is it a valid
reason for withholding payment.
Multiple Payment Claims
42. The Claimant denies the Respondent’s allegations that there were multiple
payment claims in respect of the one reference date.
43. Section 17(5) of the Act provides:
“(5) A claimant can not serve more than 1 payment claim in relation to each reference date under the construction contract.”
44. However, s.17(6) qualifies subsection (5) by the following:
“(6) However, subsection (5) does not prevent the claimant from including in a payment claim an amount that has been the subject of a previous claim.”
45. In my view, the Payment Claim seeks to recover all of the alleged unpaid
amounts of the previous 12 progress claims together with additional claims
made in respect of alleged variations to the contract. That does not in my
view offend s.17(5) of the Act. On the contrary s.17(6) expressly permits
such a course of action.
46. This is not an issue which invalidates the Payment Claim, nor is it a valid
reason for withholding payment.
Further Objection(s)
47. The Respondent in the Adjudication Response raised a further objection to
the Payment Claim as it was amended in the Application. The value of the
amount originally claimed in the Payment Claim was $5,205,068.13 (including
GST). The Claimant in the Application reduced the claimed amount to the
Page 13
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 13
sum of $4,092,328.31. However, in so doing, whilst reducing some aspects,
the Claimant actually increased the claimed amount for certain variations from
$844,692.55 to $915,406.45.
48. The Respondent argues that these amendments constitute an “amended
payment claim” which had never been served on the Respondent. It also
argues that the Act does not permit such an action and that if I were to
consider the “amended payment claim”, it would be denied natural justice.
49. The Respondent’s complaints are to some extent, legitimate but I do not
consider that the actions of the Claimant have resulted in “voiding” either the
Payment Claim or the Application. No authority was provided to me which
has held otherwise. It would be improper of me to allow the Claimant to
amend its Payment Claim if the amendments would lead to the disadvantage
of the Respondent because as the Respondent argues, it has no vehicle
under the Act to respond to those amendments.
50. The amending of a payment claim in my experience, is not an unusual
occurrence. In fact, in complicated matters such as this, it is quite common.
However any amendments should in my view because of the operation of
s.24(4) of the Act, only be considered if they are for the benefit of the
Respondent. Just as a plaintiff in curial proceedings ought not be compelled
to prosecute a proceeding7
7 See Covell Matthews & Partners v French Wools Ltd [1977] 1 WLR 876 at 879 as referred to in para 24 of Dunning SC’s written submissions to the Court dated 23 March 2010
against its will, a claimant in an adjudication
application ought to be entitled to abandon or amend parts of its claim for
whatever reason, but only if those amendments are in the favour of the
Respondent. In such cases, natural justice issues do not arise. If there are
any disadvantages to the Respondent in the abandoning or reduction of
certain aspects of the claim, such as the costs of preparing a detailed
payment schedule which are then “thrown away”, then such disadvantage
Page 14
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 14
may be addressed in appropriate cost orders under ss.34(3)(b) and 35(3) of
the Act.
51. In the premises, I am satisfied that where any amendments made to the
Payment Claim are an increase to the claimed amount for a particular item, I
should disallow that increase and consider the original claimed amount.
Where the Claimant has “revised down” the claimed amount for a particular
item, I am satisfied that because it is to the benefit of the Respondent, I am
able to consider the amended sum. I shall act accordingly.
52. The Respondent further argues in the Adjudication Response that the
Claimant’s failure to comply with clause 37 of the contract, by not serving a
progress claim in accordance with Item 28(a) of Annexure Part A of the
contract, it has been further disadvantaged by having to address the broader
scope of the Payment Claim. The Respondent argues that if the Claimant
had complied with its obligations under clause 37, the adjudication process
may have been streamlined by the intervention of the Superintendent.
53. Whether or not an assessment of a progress claim would have resulted in
less issues being ventilated in the Adjudication process is of course unknown.
There is no evidence upon which I could be satisfied that such an outcome
would result by the Claimant making a progress claim in accordance with Item
28(a) of Annexure Part A of the contract.
54. These are not issues which invalidate the Payment Claim, nor are they valid
reasons for withholding payment.
Valuation of the Claim 55. The parties’ respective positions in relation to many issues surrounding this
dispute are as diverse as they are many. Each party has provided numerous
affidavits in support of their respective submissions. On some issues such as
the contract sum and amounts paid to the Claimant, it is difficult to see how
Page 15
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 15
there can be any explanation other than at least one party not being entirely
honest.
56. It is extremely difficult in this forum, without the benefit of cross examination
and in a “pressure cooker environment” to value a claim when the parties
cannot even agree on the contract sum, how much money has been paid to
the Claimant and how the claim should calculated. However, despite the
disparate submissions and documentary evidence, I must do the best I can
on the evidence and submissions available to me “on the papers”.
57. The value of the Payment Claim is calculated by the following:
Contract Price $14,913,995.00
Variations $ 844,692.55
GST $ 1,575,868.75
Total adjusted contract price $17,334,556.30
Value of work performed (inc GST) $16,667,537.00
Amount paid to date $11,462,468.87
Value of this claim (inc GST) $5,205,068.13
58. The Respondent submits that the amounts owed and paid under the
construction contract are as follows:
Contract Amount paid prior to
entering into fixed price contracts
$ 2,937,343.08
Varied construction contract amount
from March 2009
$10,600,000.00
Variations allowed by the
Superintendent Rob Real from March
2009
$ 437,761.00
GST $ 1,397,510.41
TOTAL $15,372,614.49
Page 16
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 16
Less cash paid by the Respondent $14,201,901.79
Subtotal $ 1,170,712.70
Less Builder’s Equity Payment $ 1,000,000.00
Sub total $ 170,712.70
Less ‘clawback’ amounts still owing $ 447,006.39
Total owing by Respondent -$ 329,293.69 This should be ($276,293.69)
59. It is worthwhile therefore examining the value of the contract sum as a
starting point.
Contract Sum
60. The Claimant alleges that the contract sum was in the amount of
$14,913,995.00 (excluding GST).
61. The Respondent alleges that an agreement was reached between the parties
whereby the Claimant as from March 2009 would complete the works for the
fixed sum of $10.6 million plus GST plus a sum for profit in the amount of $1.6
million payable within 5 years after completion of the works, subject to offsets,
reductions and additions.
62. It is worthwhile at this point examining the relatively complicated contractual
history between the parties in relation to the construction of the works.
63. In or about February 2008, the parties initially entered into a Construction
Management Agreement whereby the Claimant would ostensibly manage and
supervise the construction of the works, whilst the Respondent would contract
with and independently pay all contractors performing work at the site. In
consideration for the Claimant’s services, the Respondent agreed to pay the
Claimant the sum of $520,000.00 plus GST plus bonuses. The construction
of the works continued under the Construction Management contract between
Page 17
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 17
March 2008 and August 2008. At or around September or October 2008, the
works were suspended as the Respondent required additional funding to
complete.
64. At around this time, the Claimant attempted to seek its own finance to
purchase the land on which the works were being constructed and to
complete the works and lease them back to the Respondent. The Claimant
was ultimately unsuccessful in obtaining such finance.
65. As a result of the lending requirements of the Respondent’s financier, the
Commonwealth Bank (“CBA”), the Claimant and Respondent subsequently
entered into an undated Master Builders Association Commercial Building
Contract to complete the construction of the works in the sum of
$16,405,394.50 (including GST) which sum accords with an estimate to
complete the works by independent quantity surveyors GMP Management.
66. Michael Searle a director and controlling mind of the Respondent alleges at
paragraph 10 of his affidavit dated 18 February 2010, that any works
performed by the Claimant between November 2008 and January 2009 were
works done of the Claimant’s own volition in the expectation that it would
receive finance and that in effect it would be progressing its own works. This
allegation was denied by Alexander Simpson, the director and controlling
mind of the Claimant, in his affidavit dated 9 April 2010.
67. During the period of 16 February 2009 and 15 April 2009, it was agreed by
Simpson and Searle that the works should be suspended pending finalisation
of finance approval from the CBA.
68. On or about 19 June 2009, Simpson was advised by the Respondent’s
finance broker that the CBA required a more detailed fixed price commercial
building contract be entered into by the parties. Consequently, on 26 June
Page 18
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 18
2009, the parties agreed to novate8
the Master Builders Association Building
Contract to a fixed price AS4000-1997 building contract in the sum of
$16,405,394.50 (including GST) for the completion of the works.
69. The Claimant submits that the AS4000-1997 building contract is the contract
which governs the parties’ rights and obligations. Whilst acknowledging the
existence of the AS4000-1997 building contract, the Respondent argues that
that contract sum included all of the works performed to date and that an oral
agreement in March 20099 had been entered into between Simpson for the
Claimant and Searle for the Respondent whereby the Claimant had offered to
complete the works for $10,600,000.00 plus GST plus $1,600,000.00 plus
sponsorship plus hospitality for profit, the repayment of which sum was to be
deferred for up to 5 years.10
70. I note that the Claimant’s accountant, Mr Adam Saunders provided an
affidavit dated 19 February 2010 which actually supports the Respondent’s
argument.
71. The Claimant relies upon the parol evidence rule as explained in the seminal
authority of the High Court of Australia in Codelfa Construction Pty Ltd v State
Rail Authority of New South Wales11
in arguing that any pre-contractual
discussions do not form part of the contract. I note in particular that on the
Respondent’s own evidence the discussions as referred to in paragraphs 69
and 70 above are alleged to have occurred between March 2009 and May
2009, whereas the contract is dated 26 June 2009.
72. I note that the Master Builders Association Commercial Building Contract
which was entered into prior to the AS4000-1997 contract described the
works at Item 1(a) of the schedule as: 8 See para 17 of affidavit of Searle and para 3.5 of the Claimant’s submissions 9 See para 24 of affidavit of Searle 10 See paras 21 to 22 of affidavit of Searle 11 (1982) 149 CLR 237 at 352
Page 19
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 19
“To complete Titan’s Training Facility”. [Empahsis added].
73. Although not strictly relevant for the reasons expressed below, it is of some
note that both of the aforementioned contracts have an identical contract
sum.
74. The AS4000-1997 contract is much more detailed about the scope of works
than its predecessor, the QMBA contract. In Annexure Part E of the AS4000-
1997 contract, the parties set out the contract scope of works. On the
Respondent’s own evidence, at 1 September 2008, that is well before the
AS4000-1997 contract was entered into, the Respondent had spent
$2,500,000.00 on construction costs and $1,300,000.00 in preliminary
costs12
. If the contract sum included all works to construct the building “from
scratch”, not just to complete it, I would have expected to see in the scope of
works an allowance for preliminaries and costs for the early stages of
construction. On the contrary, a careful examination of the scope of works
reveals to me that there is a significant quantity of work which appears not to
be included. For example, there is no reference to preliminaries, earthworks,
or what may be called the major components of construction such as
concrete slabs and blockwork etc.
75. It appears to me that the scope of works details an unfinished or partly
completed work. It does not appear to me to have been prepared as a scope
of works which includes all facets of construction for a project of the type
being built.
76. This view is supported by the Initial Bank Report prepared by quantity
surveyors GMP Management dated November 2008. Paragraph 2.3.1 the
report states:
“We have reviewed the architectural, structural and landscape drawings and prepared an estimated construction cost based on the development
12 See para 6 of the affidavit of Searle
Page 20
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 20
being completed in one stage. However, we have inspected the site and understand that the contract sum for the works is for the remaining building work which is predominantly from the underside of the podium slab i.e. the cost of the basement works to date is not included. GMP Management are of the opinion that the proposed Contract Sum of $14,913,995 [excluding GST] is sufficient to complete the proposed development.”
77. Section 26(2) of the Act compels me to consider among other things the
terms of the contract. I note that clause 5.1 of the Formal Instrument of
Agreement is an acknowledgment by the Respondent that:
(a) No representations, promises, guarantees or warranties have been made by or on behalf of the Contractor:
(i) To induce the execution of this agreement; or (ii) In connection with the negotiation or operation of this
Agreement; (iii) Which are not expressly contained in this agreement;
(b) The Principal’s decision to enter into this agreement (and all agreements contemplated by it) was made with a full appreciation of its terms and after taking (or having had the opportunity to take) such independent professional advice in relation to it as the Principal considered necessary, desirable or appropriate.”
78. Clause 8.11 of the Formal Instrument of Agreement also provides an entire
agreement clause which provides the following:
“The parties acknowledge that:
(a) This agreement comprises the whole of the agreement between the
parties in relation to the subject matter of it; and
(b) No further or other covenants are implied or arise between the parties
by way of collateral or other agreement or by reason of any alleged
promise, representation, warranty or undertaking given or made by
either party to the other on or before the execution of this agreement
and the existence of any implied , collateral or other agreement is
negatived.”
Page 21
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 21
79. With the inclusion of clauses 5.1 and 8.11, if the Respondent wanted to
include the terms of previous discussions or terms from oral agreements, it
was incumbent upon it to ensure that such terms were expressly included in
the AS4000-1997 contract. In their absence and based on the parol evidence
rule as explained in Codelfa, I am satisfied that the contract sum was as
described in the contract, namely $16,405,394.00 including GST and that
sum was for the completion of the building rather than its entire construction
from start to finish.
Monies paid under the Construction Management Agreement
80. The Claimant admits to having received payment for its work performed under
the Construction Management Contract in the sum of $1,082,481.50. It is
difficult to ascertain from the material what monies the Respondent alleges it
paid the Claimant under the Construction Management Contract. At
paragraph 27 of the Adjudication Response submissions, the Respondent
does not appear to contest the amount stated. However, as I understand it,
the claimed amount does not include monies paid under the Construction
Management Contract, nor should it. It is a separate contract for a separate
scope of works, namely project management of the works which was
superseded by the QMBA contract for the completion of the construction of
the works. I have in the premises, not taken into account the payment of
monies by the Respondent under the Construction Management Contract in
my calculations.
Monies paid to the Claimant under the QMBA Contract and AS4000 Contract 81. The amount the Claimant alleges it has been paid by the Respondent in
paragraph 10.6 of the Application submissions, namely $12,492,028.95 is
consistent with the payments alleged in respect of GMP1 to GMP13 as
detailed in paragraph 5.23 of its submissions. That is in relation to payments
made under the QMBA Contract which was novated to the AS4000-1997
Contract. This amount is some $1,029,560.08 greater than what the Claimant
Page 22
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 22
alleged it was paid in the Payment Claim. No explanation appears to have
been offered by the Claimant for the discrepancy. However, for the reasons I
have expressed above, I am prepared to accept the Claimant’s concession
because it is in favour of the Respondent. That does not of course mean that
I accept the Claimant was paid the sum of $12,492,028.95 on that basis. The
Claimant must still satisfy me that it has received that amount and no more.
82. The Respondent alleges to have paid the Claimant the sum of
$14,201,901.79 on the following bases:
Payment Allocation Amount of Payment Payments made to or on behalf of the Claimant in January and February 2009
$1,919,772.47
Payments made directly to Suppliers February 2009
$1,017,570.34
Payments made by CBA to Claimant
$8,939,816.88
Payments made by the Respondents GMP 2 to GMP 4
$2,324,742.10
TOTAL $14,201,901.79
83. The amounts listed above appear to have been extracted from Exhibit SG-15
to the Affidavit of Scott Green dated 18 February 2010. However, a closer
inspection of the “Payments made directly to suppliers in February 2009” in
the sum of $1,017,570.34 appear to me to be included in the sum of
$1,919,772.47. This miscalculation or “double dip” therefore reduces the
amount the Respondent can allege it has paid to the Claimant to the sum of
$13,184,331.00. However, the fact that those figures have been provided in a
spreadsheet prepared by Mr Scott does not prove that those amounts were in
fact paid to the Claimant.
84. There are significant difficulties in reconciling the payments which the parties
allege to have been paid by the Respondent. This is in no small part by the
loose manner in which all of the three contracts appear to have been
Page 23
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 23
administered by both parties. Having read all of the material provided by both
parties, I must say that I am left with the distinct impression that neither party
has been entirely frank and honest with each other and more particularly, with
me. There is some evidence throughout the material provided, which
appears to suggest there were a number of “side deals” between the parties
involving sponsorship, hospitality and even the construction of a house13
although in respect of the latter there is insufficient evidence before me to
conclude that the house construction formed part of any such “arrangement”.
85. Notwithstanding those difficulties, I have a statutory function among other
things, to ascertain to the best of my ability on the material before me, what
monies were paid to the Claimant in respect of the contract.
86. In respect to GMP 1:
86.1. The Claimant issued a progress claim # 14 made payable by the
“Jetstar Gold Coast Titans” in the sum of $1,984,483.17 including
GST on or about 7 January 2009.
86.2. Paragraph 5.23 of the Application submissions and paragraph 26 of
the affidavit of Mr Simpson suggests that the Respondent paid the
Claimant the sum of $1,029,560.58.
86.3. However, according to the affidavit of the Claimant’s contract
administrator Paul Botica dated 9 April 2010, the Respondent paid
the sum of $1,018,048.37 which was constituted by a payment in
the sum of $447,699.57 for contractor’s costs under the Trade
Management Contract and $570,348.00 was paid to the Claimant’s
suppliers under the QMBA Contract14
86.4. I have numerous difficulties with both parties’ approach to this part
of the claim.
.
13 See the email dated 9 December 2009 from Alex Simpson to Michael Searle in Exhibit MTS 5 to the affidavit of Michael Searle 14 See para 32 and Exhibit PB-4 of the affidavit of Paul Botica dated 9 April 2010
Page 24
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 24
86.4.1. The amounts alleged to have been paid in satisfaction of
the progress claim are inconsistent between the
evidence of Simpson and Botica.
86.4.2. Unlike subsequent claims, the Claimant has provided no
evidence of GMP’s assessment of the value of this claim.
GMP Management’s letter to the Claimant dated 6
January 200915
86.4.3. The Respondent has provided no satisfactory evidence
upon which I can rely that it has paid any sum in relation
to CM14/GMP1.
, appears to value the overall work that
has been completed to date in the sum of $3,818,191.00
(excluding GST) but it does not specifically ascribe a
value to CM4/GMP1.
86.5. In the premises, doing the best I can with the material before me
and in the absence of any credible evidence from the Respondent, I
am only able to value this part of the claim in the sum that Mr
Simpson attests that the Claimant has been paid, namely in the
sum of $1,029,560.58, being the greater amount than which was
alleged to have been paid by Mr Botica.
87. In respect to GMP 2:
87.1. The Claimant issued a progress claim # GMP2 made payable by the
“Jetstar Gold Coast Titans” in the sum of $853,681.02 including GST
on or about 31 January 2009.
87.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 29 of the affidavit of Mr Simpson suggests that the
Respondent paid the Claimant the sum of $853,681.02.
15 See Exhibit AHS-13 to the affidavit of Simpson
Page 25
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 25
87.3. The Claimant provided evidence16
87.4. The Claimant provided evidence
that GMP Management assessed
the value of that stage of the works in the sum of $853,681.02
excluding GST. However, given the identical nature of the sums in
the report (at page 2) I have assumed this to be an error on the part
of GMP Management and shall consider the certified amount as
being $853,681.02 including GST. 17
87.5. The Respondent has provided no evidence which refutes the
Claimant’s material.
by way of a copy of its bank
statement showing payment on 5 May 2009 in the sum of
$853,681.02.
87.6. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $853,681.02 and did receive the sum of $853,681.02.
88. In respect to GMP 3:
88.1. The Claimant issued a progress claim # GMP3 made payable by the
“Jetstar Gold Coast Titans” in the sum of $937,925.71 including GST
on or about 22 March 2009.
88.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 32 of the affidavit of Mr Simpson suggests that the
Respondent paid the Claimant the sum of $937,927.71.
88.3. The Claimant provided evidence18
88.4. The Claimant provided evidence
that GMP Management .assessed
the value of that stage of the works in the sum of $937,925.71
including GST. 19
16 See Exhibit AHS-11 to the affidavit of Simpson
by way of a copy of its bank
statement showing payments on 4 May 2009 in the sum of
$852,659.74 and $85,265.97 on 19 May 2009.
17 See Exhibit AHS-12 to the affidavit of Simpson 18 See Exhibit AHS-14 to the affidavit of Simpson 19 See Exhibit AHS-15 to the affidavit of Simpson
Page 26
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 26
88.5. The Respondent has provided no evidence which refutes the
Claimant’s material.
88.6. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $937,925.71 and did receive the sum of $937,925.71.
88.7. In the premises, I am satisfied that the Claimant was entitled to claim
that sum and did in fact receive payment for that amount from the
Respondent.
89. In respect to GMP 4:
89.1. The Claimant issued a progress claim # GMP4 made payable by the
“Jetstar Gold Coast Titans” in the sum of $1,167,608.20 including
GST on or about 29 May 2009.
89.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 35 of the affidavit of Mr Simpson suggests that the
Respondent paid the Claimant the sum of $533,135.39.
89.3. The Claimant provided evidence20
89.4. The Claimant provided evidence
that GMP Management assessed
the value of that stage of the works in the sum of $1,167,608.20
including GST. 21
89.5. The Respondent has provided no evidence which refutes the
Claimant’s material.
by way of a copy of its bank
statement showing a payment on 2 June 2009 in the sum of
$589,345.79. In the absence of any contradictory evidence, I accept
Mr Simpson’s explanation, as evidenced by the Claimant’s bank
deposit slips that $56,210.40 of this sum was payment by the
Respondent for an unrelated contract.
89.6. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $1,167,608.20 but only received the sum of $533,135.39.
20 See Exhibit AHS-17 to the affidavit of Simpson 21 See Exhibit AHS-18 to the affidavit of Simpson
Page 27
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 27
90. In respect to GMP 5:
90.1. The Claimant issued a progress claim # GMP5 made payable by the
“Jetstar Gold Coast Titans” in the sum of $1,485,257.40 including
GST on or about 2 July 2009.
90.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 39 of the affidavit of Mr Simpson suggests that the
Respondent paid the Claimant the sum of $708,275.56.
90.3. The Claimant provided evidence22
90.4. The Claimant provided evidence
that GMP Management assessed
the value of that stage of the works in the sum of $1,485,257.60
including GST. 23
90.5. The Respondent has provided no evidence which refutes the
Claimant’s material.
by way of a copy of its bank
statement showing payment on 20 July 2009 in the sum of
$708,275.56.
90.6. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $1,485,257.40 but only received the sum of $708,275.56.
91. In respect to GMP 6:
91.1. The Claimant issued a progress claim # GMP6 made payable by the
“Jetstar Gold Coast Titans” in the sum of $1,220,227.47 including
GST on or about 30 July 2009.
91.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 42 of the affidavit of Mr Simpson suggests that the
Respondent paid the Claimant the sum of $1,109,297.70.
22 See Exhibit AHS-21 to the affidavit of Simpson 23 See Exhibit AHS-22 to the affidavit of Simpson
Page 28
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 28
91.3. The Claimant provided evidence24
91.4. The Claimant provided evidence
that GMP Management assessed
the value of that stage of the works in the sum of $1,220,227.47
including GST. 25
91.5. The Respondent has provided no evidence which refutes the
Claimant’s material.
by way of a copy of its bank
statement showing payment on 31 July 2009 in the sum of
$1,109,297.70 which equates to the claimed amount excluding GST.
91.6. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $1,220,227.47 but only received the sum of
$1,109,297.70.
92. In respect to GMP 7:
92.1. The Claimant issued a progress claim # GMP7 made payable by the
“Jetstar Gold Coast Titans” in the sum of $1,783,887.63 including
GST on or about 2 September 2009.
92.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 48 of the affidavit of Mr Simpson suggests that the
Respondent’s financier the CBA paid the Claimant the sum of
$1,621,716.03.
92.3. The Claimant provided evidence26 that GMP Management assessed
the value of that stage of the works in the sum of $1,783,887.64
including GST whilst the Superintendent valued the claim in the sum
of $1,877,777.00 including GST27
24 See Exhibit AHS-24 to the affidavit of Simpson
.
25 See Exhibit AHS-25 to the affidavit of Simpson 26 See Exhibit AHS-27 to the affidavit of Simpson 27 See Exhibit AHS-28 to the affidavit of Simpson
Page 29
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 29
92.4. The Claimant provided evidence28
92.5. The Respondent has provided no evidence which refutes the
Claimant’s material.
by way of a copy of its bank
statement showing payment on 2 September 2009 in the sum of
$1,621,716.03 which equates to the claimed amount excluding GST.
92.6. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $1,783,887.63 but only received the sum of
$1,621,716.03.
93. In respect to GMP 8:
93.1. The Claimant issued a progress claim # GMP8 made payable by the
“Jetstar Gold Coast Titans” in the sum of $1,107,827.60 including
GST on or about 30 September 2009.
93.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 53 of the affidavit of Mr Simpson suggests that the
Respondent’s financier the CBA paid the Claimant the sum of
$965,015.59.
93.3. The Claimant provided evidence29 that GMP Management assessed
the value of that stage of the works in the sum of $1,107,827.15
including GST whilst the Superintendent valued the claim in the sum
of $1,166,133.00 including GST, less 5% retention30
93.4. The Claimant provided evidence
. 31
93.5. The Respondent has provided no evidence which refutes the
Claimant’s material.
by way of a copy of its bank
statement showing payment on 1 October 2009 in the sum of
$965,015.59.
28 See Exhibit AHS-29 to the affidavit of Simpson 29 See Exhibit AHS-31 to the affidavit of Simpson 30 See Exhibit AHS-32 to the affidavit of Simpson 31 See Exhibit AHS-33 to the affidavit of Simpson
Page 30
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 30
93.6. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $1,107,827.15 but only received the sum of $965,015.59.
94. In respect to GMP 9:
94.1. The Claimant issued a progress claim # GMP9 made payable by the
“Jetstar Gold Coast Titans” in the sum of $1,677,050.10 including
GST on or about 29 October 2009.
94.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 58 of the affidavit of Mr Simpson suggests that the
Respondent’s financier the CBA paid the Claimant the sum of
$1,494,500.00.
94.3. The Claimant provided evidence32 that GMP Management assessed
the value of that stage of the works in the sum of $1,677,050.18
including GST whilst the Superintendent valued the claim in the sum
of $1,834,076 including GST, less 5% retention33
94.4. The Claimant provided evidence
. 34
94.5. The Respondent has provided no evidence which refutes the
Claimant’s material.
by way of a copy of its bank
statement showing payment on 2 November 2009 in the sum of
$1,494,500.00.
94.6. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $1,677,050.10 but only received the sum of
$1,494,500.00.
95. In respect to GMP 10:
95.1. The Claimant issued a progress claim # GMP10 made payable by
the “Jetstar Gold Coast Titans” in the sum of $1,297,334.80 including
GST on or about 1 December 2009.
32 See Exhibit AHS-35 to the affidavit of Simpson 33 See Exhibit AHS-36 to the affidavit of Simpson 34 See Exhibit AHS-37 to the affidavit of Simpson
Page 31
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 31
95.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 63 of the affidavit of Mr Simpson suggests that the
Respondent’s financier the CBA paid the Claimant the sum of
$1,149,395.00.
95.3. The Claimant provided evidence35 that GMP Management assessed
the value of that stage of the works in the sum of $1,297,334.80
including GST whilst the Superintendent valued the claim in the sum
of $1,391,976.00 including GST, less 5% retention36
95.4. The Claimant provided evidence
. 37
95.5. The Respondent has provided no evidence which refutes the
Claimant’s material.
by way of a copy of its bank
statement showing payment on 3 December 2009 in the sum of
$1,149,395.00.
95.6. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $1,297,334.80 but only received the sum of
$1,149,395.00.
96. In respect to GMP 11:
96.1. The Claimant issued a progress claim # GMP11 made payable by
the “Jetstar Gold Coast Titans” in the sum of $1,179,429.54 including
GST on or about 21 December 2009.
96.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 68 of the affidavit of Mr Simpson suggests that the
Respondent’s financier the CBA paid the Claimant the sum of
$1,072,209.00.
96.3. The Claimant provided evidence38
35 See Exhibit AHS-39 to the affidavit of Simpson
that GMP Management assessed
the value of that stage of the works in the sum of $1,179,429.54
36 See Exhibit AHS-40 to the affidavit of Simpson 37 See Exhibit AHS-41 to the affidavit of Simpson 38 See Exhibit AHS-43 to the affidavit of Simpson
Page 32
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 32
including GST whilst the Superintendent valued the claim in the sum
of $1,241,506.00 including GST, less 5% retention39
96.4. The Claimant provided evidence
. 40
96.5. The Respondent has provided no evidence which refutes the
Claimant’s material.
by way of a copy of its bank
statement showing payment on 22 December 2009 in the sum of
$1,072,209.00.
96.6. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $1,179,429.54 but only received the sum of
$1,072,209.00.
97. In respect to “Variation December”:
97.1. The Claimant issued a progress claim on or about 17 December
2009 entitled “Variation December” which Mr Simpson refers to in his
affidavit as “DECVAR”, made payable by the “Gold Coast Titans
(Property) Pty Ltd” in the sum of $307,097.38 including GST.
97.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 70 of the Affidavit of Mr Simpson suggests that the
Respondent’s financier the CBA paid the Claimant the sum of
$198,000.00.
97.3. Mr Simpson alleges that this claim was for variations to the contract
in addition to those listed in the affidavit of Paul Botica.
97.4. The Claimant did not provide any evidence of the assessment of this
claim by either GMP Management or the Superintendent.
97.5. The Claimant provided evidence41
39 See Exhibit AHS-44 to the affidavit of Simpson
by way of a copy of its bank
statement showing payment in the sum of $150,000.00 on 13
January 2010 and $48,000.00 on 21 January 2010.
40 See Exhibit AHS-45 to the affidavit of Simpson 41 See Exhibit AHS-47 to the Affidavit of Simpson
Page 33
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 33
97.6. The Respondent has provided no evidence which refutes the
Claimant’s material. However, the Respondent submits that this
payment was for the fitout of offices at the site. Neither party
provided any relevant documentary evidence to support their
respective submissions. In the absence of any independent
assessment of the amount claimed and in the absence of any
supporting material, I am not prepared to value the claim in excess of
that which has already been paid by the Respondent.
97.7. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $198,000.00 and has been paid that sum.
98. In respect to GMP 12:
98.1. The Claimant issued a progress claim # GMP12 made payable by
the “Jetstar Gold Coast Titans” in the sum of $901,249.66 including
GST on or about 27 January 2010.
98.2. The contents of paragraph 5.23 of the Application submissions and
paragraph 76 of the Affidavit of Mr Simpson suggests that the
Respondent’s financier the CBA paid the Claimant the sum of
$819,318.00.
98.3. The Claimant provided evidence42 that GMP Management assessed
the value of that stage of the works in the sum of $901,249.65
including GST whilst the Superintendent valued the claim in the sum
of $948,682.00 including GST, less 5% retention43
98.4. The Claimant provided evidence
. 44
98.5. The Respondent has provided no evidence which refutes the
Claimant’s material.
by way of a copy of its bank
records showing payment by the Respondent’s financier, the CBA on
1 February 2010 in the sum of $819,318.00.
42 See Exhibit AHS-49 to the affidavit of Simpson 43 See Exhibit AHS-50 to the affidavit of Simpson 44 See Exhibit AHS-45 to the affidavit of Simpson
Page 34
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 34
98.6. In the premises, I am satisfied that the Claimant was entitled to claim
the sum of $901,249.66 but only received the sum of $819,318.00.
99. In my view there is no impediment to the efficacy of the Payment Claim when
many of the progress claims listed above were made out to the “Jetstar Gold
Coast Titans”. It is clear that although misnamed, the Respondent
considered itself liable for the bulk of the claimed amounts and paid the
Claimant accordingly.
100. Pursuant to the spreadsheet attached to this decision and marked
Annexure B, the claimed amounts are summarised accordingly:
Claimed Amounts for GMP1 – GMP12 $15,903,059.66 Adjudicated Amount $14,839,039.26 Amount Paid by Respondent - $12,492,029.58 Amount owing to Claimant $ 2,347,009.68
Builder’s Equity 101. The Respondent alleges that:
101.1. Pursuant to the finance facility provided by the CBA, the
Respondent was to contribute to the cost of the works the sum of
$4,600,000.00 and the Claimant was to contribute builder’s equity in
the sum of $1,000,000.00.
101.2. By agreement between the parties, the builder’s equity was
contributed by the Claimant agreeing to accept partial payments in
respect of previous claims GMP4 and GMP5.
102. Mr Simpson in his affidavit at paragraph 112 agrees that the CBA required
the Claimant to “put up” $1,000,000.00 in equity into the project. However, Mr
Simpson says that in discussing this bank requirement with Mr Searle, “it was
agreed that the Titans would pay this money to Simcorp so that Simcorp did
not have to, in effect, provide $1,000,000.00 in on site work as ‘equity’ so I
advised Searle that Simcorp could not fund this money together with the
Page 35
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 35
funding of the retentions. I would not have agreed to become a guarantor on
the loan if I thought the Titans and Searle would not pay the $1 million on
behalf of Simcorp.”
103. The “builder’s equity” issue is a prime example of how this contract was
mal-administered by both parties. Mr Simpson admits that it was a
requirement of the bank loan that he put up the $1,000,000.00. Just why the
CBA required that, or indeed for him to guarantee the Respondent’s loan, is
not known. However, Simpson in the extract above raises more allegations of
oral “side agreements” which beggar belief why they were not reduced to
writing.
104. Both parties have provided extremely scant evidence of whose
responsibility it was to pay the “builder’s equity” of $1,000,000.00. Mr
Searle’s letter to Scott Brooks of the CBA could only be described as “self-
serving” and in my view, is not credible evidence of the Claimant’s liability.
The Respondent has provided no evidence in the Adjudication Response to
refute the allegations of Mr Simpson extracted above.
105. Given that it is the Respondent who is claiming the $1,000,000.00 as a
set-off from the claimed amount, it is the Respondent who bears the onus of
proof. Given the amount involved and the prior conduct of the parties, on
balance I simply cannot be satisfied that there was not some other oral
arrangement entered into by Messrs Simpson and Searle whereby the
Respondent would “cover” the builder’s equity, which after all was merely a
bank requirement to fund the loan.
106. I have referred to the “prior conduct of the parties” because it is
abundantly clear that there was some degree of mutual “back scratching”
between Messrs Simpson and Searle on behalf of their respective
organisations. For example, in Exhibit MTS6 to the affidavit of Mr Searle is a
Page 36
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 36
string of emails between Mr Seale and Mr Simpson. A review of those emails
reveals that the parties are attempting to negotiate an on-going sponsorship
arrangement for the Claimant.
Mr Simpson writes on 24 October 2009: “Mate my point is I’m leaving $1.6 million in its not a smart business decision if I was getting full mezz interest rates I would be happy to pay full freight on sponsorship but im not In fact you get a sweet deal on interest I should get a sweet deal on sponsorship Im really doing you a favour which im happy to do but I want to be looked after.” Mr Seale responds on the same date: “I think we both know at 10% profit margin on $16 Million job is a good earner … I stuck solid with you mate as you and I had been through it together … I copped 10% for total job when I had others like Southern Cross coming at me with 2.5% - 3.5%. I think it is fair to say we have both done each other a favour …” “The Claw Back Agreement”
107. Mr Searle in paragraph 26 of his affidavit describes “the claw back
agreement” as:
“At the time of entering into the initial fixed price construction agreement
[the QMBA contract] with Simcorp in late January 2009, GCTP had
already spent in excess of $3,800,000.00 on the project of which
approximately $2,500,000.00 was included in the total costs of
construction detailed in the contract price of $14,913,995.00.”
108. In effect, the clawback agreement was an arrangement which would
enable the Respondent to receive some of those costs back via the CBA
facility.
109. In paragraph 6.5 of the Payment Schedule, the Respondent argued that
the balance held by the Claimant pursuant to the “claw back agreement” is
calculated as follows:
Page 37
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 37
(a) Total Claw back $1,688,827.45 (b) GST refunds received $1,241,821.06 (c) Claw back and GST received $1,241,821.06 (d) Net owing $ 447,006.39.
110. The Claimant in paragraph 5.25 of the Application submissions argues
that there was no concluded agreement reached in relation to the “claw back
agreement”.
111. The Claimant’s submissions on this point are vague and quite non-
responsive. It is clear to me that there must have been some arrangement
between the parties which entitled the Respondent to withhold some of the
GST monies from the progress claims issued by the Claimant.
112. I reject the Claimant’s submissions at paragraph 5.25(d) of the Application
submissions that I cannot take such matters into account because it is a
“separate agreement”. If anything, it is an oral variation to the contract. The
management of the contract and the construction of the works are not
performed in a legal vacuum. I am satisfied that s.26(2) of the Act permits me
to consider the Respondent’s submissions.
113. In the absence of any meaningful submissions from the Claimant on this
point, I prefer the submissions of the Respondent.
114. I am prepared to allow a set-off from the claimed amount in the sum of
$447,006.39.
Variations 115. The Payment Claim includes claims for a number of variations being new
work not previously claimed (being variations 45 to 71).
116. The total value of the variations claimed in the Payment Claim is purported
to be in the sum of $844,692.00 excluding GST. As extrapolated in Annexure
C attached hereto, I calculate the original claimed amount for variations to be
Page 38
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 38
in the sum of $1,039,542.15. The main cause of this discrepancy between
the original claimed amount in Annexure C and the Claimant’s “Variation
Analysis” contained in TAB ‘C’ of the Payment Claim is the omission in the
latter of the claim for Variation 9. I shall return to this point below.
117. Annexure C attached hereto, contains a table which lists the parties’
respective positions in relation to the variations. It should be read in
conjunction with these reasons. All amounts unless otherwise stated are
excluding GST.
118. The contract provides a mechanism for variations pursuant to clause 36. I
express my reasons below as to why in my opinion, the strict terms of clause
36 do not apply.
119. The bases of the Respondent’s challenge to the Claimant’s entitlement to
the variations is provided in the affidavit of Rob Real dated 24 March 2010
who was the contract superintendent. In essence, the Respondent argues
that:
119.1. Some of the variations were approved by Mr Real;
119.2. Others were not;
119.3. Some of the work, the subject of the alleged variations have not
been undertaken;
119.4. Others have not been preceded by a quote; or
119.5. The work was undertaken, but the Claimant failed to comply with its
obligations pursuant to clause 36 of the contract.
120. In addition to that, the Respondent objects to the affidavit of Paul Botica
sworn 9 April 2010 “as it is outside the scope of s.26 of the BCIPA and seeks
to amend Payment Claim 13.”
121. As I have indicated previously, to afford the Respondent procedural
fairness, I will not allow the Claimant to increase the claimed amount in the
Page 39
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 39
Application (from the Payment Claim). Where it has sought to do so, I will
simply assess the value of the variation as it was claimed in the Payment
Claim. Where on the other hand the Claimant has sought to reduce or delete
a variation in the Application, I will allow such conduct because it is of no
disadvantage to the Respondent.
Variation 1 – Structural steel changes to pool roof
122. The Claimant seeks payment in the sum of $26,160.75 in relation to this
item. It has in fact been paid that sum according to the schedule in Tab “C” of
the Payment Claim and as detailed in the schedule attached to Mr Real’s
affidavit. I note that the claimed sum accords with the value ascribed by GMP
Management in their report dated 27 January 201045
.
123. Mr Real, the contract Superintendent values the work at $20,000.00. No
basis is given for that valuation.
124. As GMP Management, an independent quantity surveyor has valued the
works at $26,160.75 and in the absence of any contrary evidence, I am
satisfied the Claimant is entitled to that sum.
Variation 2 – Changes to fitout of Ground Floor and Level 1
125. The Claimant seeks payment in the sum of $153,052.00 in relation to this
item. It has in fact been paid that sum according to the schedule in Tab “C” of
the Payment Claim and as detailed in the schedule attached to Mr Real’s
affidavit. I note that the value ascribed for this item by GMP Management in
their report dated 27 January 201046
is $137,747.12.
126. Mr Real, the contract Superintendent values the work at $120,000.00 in
the schedule attached to his affidavit. No basis is given for that valuation
45 See Exhibit AHS-49 to the affidavit of Simpson 46 See Exhibit AHS-49 to the affidavit of Simpson
Page 40
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 40
although in paragraph 5 of his affidavit he considers the valuation of this item
as “unresolved”.
127. The Claimant has provided a number of documents and plans in its
Payment Claim to substantiate the amount claimed. Many of the individual
component costs which make up the claimed amount are PC items and
quotations rather than evidence of actual expenditure.
128. In the Claimant’s Variation Register attached to Mr Real’s progress
certificate dated 28 October 2009, it is alleged that Mr Real has approved the
variation in the sum of $137,747.12 which accords with the valuation of GMP
Management. Although the Variation Register appears to have been
authored by the Claimant, Mr Real in his report states:
“The approved builder’s works variations which are identified on the Simcorp Variation Register, are for additional works which have been required on the project in order to meet statutory standards or revised engineering designs or previously undocumented details, and their total value is included in this recommendation for payment. The Simcorp Variation Register is attached to this certificate for reference.”
129. I am in the premises, satisfied that Mr Real has previously valued the
variation item in the sum of $137,747.12. In addition, GMP Management, an
independent quantity surveyor has valued the works at $137,747.12 and in
the absence of any contrary evidence, I am satisfied the Claimant is entitled
to that sum.
Page 41
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 41
Variation 3 – Tiles to Southern Pool – Mosaic wall
130. There is no dispute between the parties in relation to this item, the
Claimant is entitled to and has been paid the sum of $14,878.50.
Variation 4 – Otis storage costs
131. There is no dispute between the parties in relation to this item, the
Claimant is entitled to and has been paid the sum of $14,500.00.
Variation 5 – Steel support frames
132. There is no dispute between the parties in relation to this item, the
Claimant is entitled to and has been paid the sum of $4,345.00.
Variation 6 – Power reticulation to pool equipment
133. There is no dispute between the parties in relation to this item, the
Claimant is entitled to the sum of $7,507.50. It is however, unclear on the
material provided whether the Claimant has been provided this sum.
Variation 7 – Deleted
134. There is no dispute between the parties in relation to this item.
Variation 8 – Metz Pool Tiles
135. There is no dispute between the parties in relation to this item, the
Claimant is entitled to the sum of $64,500.00. It is however, unclear on the
material provided whether the Claimant has been provided this sum.
Variation 9 – Stage 2 Cabinet and Joinery
136. The Claimant did not include a claim for Variation 9 in TAB ‘C’ of the
Payment Claim. Ordinarily, I would not then allow it to be claimed in the
Application. However, in this instance, it is clear from the affidavit of Mr Real
that he was aware of its existence and he has in fact valued the claim in the
Page 42
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 42
sum of $70,205.00 which the Claimant now accepts as its entitlement
according to Exhibit PB-5 to the affidavit of Paul Botica. It is unclear on the
material before me whether the Claimant has already been paid the sum of
$70,205.00.
Variation 10 – Mosaic wall anti graffiti protection
137. There is no dispute between the parties in relation to this item, the
Claimant is entitled to the sum of $1,188.00. It is unclear on the material
whether the Claimant has been paid this sum.
Variation 11 – Deleted
138. There is no dispute between the parties in relation to this item.
Variation 12 – Roof plant area screen
139. There is no dispute between the parties in relation to this item, the
Claimant accepts the scheduled amount of $3,300.00 but has been paid the
sum of $7,180.00.
Variation 13 – Cage to pool equipment in basement
140. There is no dispute between the parties in relation to this item, the
Claimant is entitled to the sum of $2,200.00. It is unclear on the material
provided whether the Claimant has been paid this sum.
Variation 14 – Deleted
141. There is no dispute between the parties in relation to this item.
Variation 15 – Deletion to partitions to level 2, 3 & 4
142. There is no dispute between the parties in relation to this item, the
Claimant accepts the Respondent is entitled to a credit in the sum of
($20,235.00).
Page 43
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 43
Variation 16 – Two extra air con units required on Level 4 143. The Claimant seeks payment in the sum of $5,159.00 in relation to this
item. There is some debate by the parties whether the scheduled amount of
$4,690.00 has been paid by the Respondent.
144. It appears from the material contained in Tab 16 of PB-6 to Mr Botica’s
affidavit that the source of the argument between the parties is the Claimant’s
entitlement to claim a 10% margin on its cost of the variation.
145. In the Claimant’s Variation Register attached to Mr Real’s progress
certificate dated 28 October 2009, it is alleged that Mr Real has approved the
variation in the sum of $5,159.00. Although the Variation Register appears to
have been authored by the Claimant, Mr Real in his report states:
“The approved builder’s works variations which are identified on the Simcorp Variation Register, are for additional works which have been required on the project in order to meet statutory standards or revised engineering designs or previously undocumented details, and their total value is included in this recommendation for payment. The Simcorp Variation Register is attached to this certificate for reference.”
146. I am in the premises, satisfied that Mr Real has previously valued the
variation item in the sum of $5,159.00.
147. On balance, I agree with the submissions of the Claimant on this point.
Clause 36.4(d) of the contract allows for the addition of a reasonable amount
for profit and overheads. The express terms of the contract appear to be
silent in relation to the percentage rate of profit on variations.
148. As to what is “reasonable” I refer to the parties “arrangement” as extracted
at paragraph 106 above. In the premises, I am satisfied that the Claimant
was entitled to 10% profit and is therefore entitled to the sum of $5,159.00. It
is unclear on the material provided whether the Claimant has been paid this
amount.
Page 44
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 44
Variation 17 – Extra height to windows on south side 149. The Claimant seeks payment in the sum of $2,486.00 in relation to this
item. It appears to be accepted that the CBA has paid the Claimant the sum
of $2,486.00 for this item.
150. The only detail given by Mr Real is that contained in the schedule attached
to his affidavit where he rejects outright the claimed amount and says
“Rejected. Builder error”.
151. In the Claimant’s Variation Register attached to Mr Real’s progress
certificate dated 28 October 2009, it is alleged that Mr Real has approved the
variation in the sum of $2,113.10 the difference being, according to the
Register, that the work was only 85% complete. For the reasons I have
expressed previously47
, I am satisfied that Mr Real has previously valued the
variation item in the sum of $2,113.10. Whether that work has progressed
since Mr Real last valued it is unknown. However, I am not prepared to allow
Mr Real to resile from his previous position and now argue that it was a
builder’s error without demonstrating reasonable grounds to do so.
152. In the absence of any evidence to confirm that the works have been
completed, I shall value this item in accordance with Mr Real’s assessment
on 28 October 2009, that is in the sum of $2,113.10.
Variation 18 - Pool ceiling flashing
153. The Claimant seeks payment in the sum of $1,064.00 in relation to this
item. It appears to be accepted that the CBA has paid the Claimant the sum
of $1,064.00 for this item.
47 See the extract at paragraph 145 herein
Page 45
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 45
154. The only detail given by Mr Real is that contained in the schedule attached
to his affidavit where he rejects outright the claimed amount and says
“Rejected”.
155. In the Claimant’s Variation Register attached to Mr Real’s progress
certificate dated 18 December 2009, it is alleged that Mr Real has approved
the variation in the sum of $1,064.80. Mr Real had made a comment in the
Register attached to the progress certificate dated 28 October 2009 that “No
details to finish pool ceiling”. That comment is not repeated in the current
Register. In any event, Mr Real appears to have valued the claim in full.
156. For the same reasons I have expressed previously, I am satisfied that Mr
Real has previously valued the variation item in the sum of $1,064.00. In the
absence of any contradictory evidence, I am not prepared to allow Mr Real to
resile from his previous position and now argue that the claim ought to be
rejected.
157. In the premises, I shall value this item in accordance with Mr Real’s
assessment on 18 December 2009, that is in the sum of $1,064.00.
Variation 19 – Window W126 not shown on drawings
158. The Claimant seeks payment in the sum of $11,462.00 in relation to this
item. It appears to be accepted that the CBA has paid the Claimant the sum
of $11,462.00 for this item.
159. Mr Real in paragraph 5 of his affidavit considers that this claim is
“unresolved”. Mr Real in the schedule attached to his affidavit states “Value
assessed due to lack of supporting information from Simcorp”. However, it
must be said that Mr Real’s supporting material in response is also lacking
substance. For instance, Mr Real in Exhibit ‘B’ to his affidavit provides no
basis for his costings of $500 square metre whatsoever.
Page 46
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 46
160. In the Claimant’s Variation Register attached to Mr Real’s progress
certificate dated 18 December 2009, it is alleged that Mr Real has approved
the variation in full for the sum of $11,462.00. The works are listed as being
100% complete.
161. For the same reasons I have expressed previously, I am satisfied that Mr
Real has previously valued the variation item in the sum of $11,462.00. In the
absence of any contradictory evidence, I am not prepared to allow Mr Real to
resile from his previous position and now argue that the claim ought to be
reduced to $8,000.00.
162. The Claimant has provided evidence of the cost of the windows from Total
Concept Group Pty Ltd and as I have stated previously, I am satisfied that the
Claimant is entitled to claim a 10% profit on its costs of the variation.
163. In the premises, I shall value this item in accordance with Mr Real’s
assessment on 18 December 2009, that is in the sum of $11,462.00.
Variation 20 – Tiled floors to foyer entry 164. According to the schedule at Exhibit PB-5 of the affidavit of Mr Botica, the
Claimant now accepts the scheduled amount of $13,870.00.
165. There appears to be some question whether the Claimant has been paid
the scheduled amount of $13,870.00. Neither party has provided any
evidence one way or the other.
Variation 21 – Plumber’s costs 166. The Claimant originally sought payment for this item in the sum of
$47,433.00. The Claimant has since amended this amount to $38,385.00
which sum the Claimant accepts it has been paid. However, notwithstanding
that the Claimant has been paid $38,385.00, the Respondent maintains that
the value of the variation is only $10,985.00.
Page 47
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 47
167. The only detail given by Mr Real is that contained in the schedule attached
to his affidavit where he states “Value assessed due to works not completed.”
In the Variation Register attached to Mr Real’s progress certificate dated 27
January 2010, he values the work at “-“ but comments that the work is 50%
“in progress” which I assume means 50% completed.
168. Mr Real in Exhibit ‘C’ to his affidavit calculates that the value of the
incomplete work is in the sum of $27,400.00, which when subtracted from the
claimed amount leaves the sum of $10,985.00.
169. The Claimant has provided evidence of additional costs charged by H & G
Plumbing for variations arising out of “client changes” and “drawing changes
by the Hydraulics Engineer”. Those costs equate to the sum of $38,385.00
excluding margin. The Claimant also argues that “all of the materials were on
site” when the contract was terminated. Therefore, the Respondent has
obtained or will obtain the benefit of those materials.
170. On balance, I prefer the submissions of the Claimant. The Claimant has
been able to substantiate its costs by referring to its subcontractor’s actual
costs. Mr Real has not demonstrated to me that any of the alleged
incomplete works have in fact been omitted. I note that there are no photos
on Mr Real’s CD of this particular variation. In the premises, I am satisfied
the Claimant is entitled to the sum of $38,385.00.
Variation 22 – Additional power to server room
171. The Claimant seeks payment in the sum of $1,403.60 in relation to this
item. The parties are in dispute as to whether the Claimant has been paid the
sum of $1,160 which is the scheduled amount.
172. The Claimant has provided evidence from its electrician of its costs in the
sum of $1,160.00. For the reasons I have already expressed, the Claimant is
Page 48
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 48
entitled to claim a 10% margin on those costs. In the premises, I am satisfied
that the Claimant is entitled to receive the amount of $1,276.00.
Variation 23 – New aircon to ground floor tenancy - deleted
173. There is no dispute between the parties in relation to this item.
Variation 24 – Striker plates 174. The Claimant seeks payment in the sum of $1,054.00 in relation to this
item. There is no dispute involving the quantum claimed, however the parties
are in dispute as to whether the Claimant has been paid that sum. Neither
party provided any evidence of payment one way or the other.
175. I accept that the Claimant is entitled to the sum of $1,054.00.
Variation 25 – Coloured Concrete – deleted
176. There is no dispute between the parties in relation to this item.
Variation 26 – Alterations to kitchen level 1 177. The Claimant originally sought payment for this item in the sum of
$11,605.00. The Claimant has since amended this amount to $10,444.50.
The Respondent alleges to have paid the sum of $6,000.00 for this item but
has provided no evidence of having done so. The Claimant alleges to have
received no monies.
178. The Respondent has valued this item in the sum of $8,124.00. The only
detail given by Mr Real is that contained in the schedule attached to his
affidavit where he states “Value assessed due to works not completed.”
179. The Claimant concedes that the works are incomplete.
180. On balance, I agree with Mr Real’s view that the supporting material
provided by the Claimant in this instance is inadequate. Many details of the
Page 49
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 49
costs provided in Mr Simpson’s email dated 11 November 2009 are
“unconfirmed”. Whilst it is not known to me how Mr Real valued the works in
the sum of $8,124.00 that appears to be a generous amount based on the
Claimant’s documentation.
181. In the premises, as the Respondent has indicated a willingness to pay
$8,124.00, I shall award that sum.
Variation 27 – Café alterations
182. The Claimant originally sought payment for this item in the sum of
$21,294.00. The Claimant has since amended this amount to $17,652.60.
183. The Respondent alleges that this item is valued at $11,000.00 and that it
has paid the Claimant the sum of $9,000.00 but has provided no evidence of
having done so.
184. In the schedule attached to his affidavit, Mr Real states “Value assessed
due to works not completed.” In the Variation Register attached to Mr Real’s
progress certificate dated 27 January 2010, he values the work at
“$21,294.00” but comments that the work is 30% “in progress” which I
assume means 30% completed. The Claimant argues that it is 90%
completed.
185. The Respondent has provided no evidence to support its estimated value
in the sum of $11,000.00, nor the estimated completion of 50% for the
partitions and 60% for the electrical and plumbing.
186. I have viewed the relevant photos of this variation on the CD attached to
Mr Real’s affidavit. In my view, the photos do not indicate that the works are
90% complete.
Page 50
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 50
187. The Claimant’s invoices attached to TAB 27 of Exhbit PB-6 indicate that
the Claimant would have incurred additional costs in the sum of $19,614.00.
On the material available to me I am prepared to estimate that the work
appears to be approximately 75% complete. In the premises, I allow the sum
of $14,710.50.
Variation 28 – Power and data to level L5, fibre optic to Level 1 and ground
188. The Claimant originally sought payment for this item in the sum of
$23,190.00. The Claimant has since amended this amount to $19,580.00
and then again during the adjudication process sought to amend the claim to
$19,711.50. For the reasons which I have previously expressed, I am not
willing to allow the Claimant the opportunity to increase a particular claimed
amount for a variation. I therefore shall consider the claimed amount to be in
the sum of $19,580.00.
189. The Claimant has provided an estimate for the variation from its electrician
in the sum of $23,190.00. This figure when compared with the claimed
amount makes no allowance for the Claimant’s margin, nor in this instance is
the margin claimed.
190. The Respondent alleges that this item is valued at $10,753.00 and that it
has paid that sum to the Claimant but has provided no evidence of having
done so, nor any evidence in support of its valuation. The Claimant alleges
not to have received any payment.
191. The only detail given by Mr Real is that contained in the schedule attached
to his affidavit where he states “Value assessed due to works not completed.”
192. Mr Real had previously certified the value of this variation in the sum of
$23,190.00 on basis of it having been 100% complete48
48 See Exhibit RR-1 to the Affidavit of Rob Real dated 24 March 2010
.
Page 51
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 51
193. The Respondent has provided no evidence to support its estimate of a
value in the sum of $11,000.00 apart from some crude costings performed by
Mr Real. Those costings provide no basis upon which Mr Real assessed the
percentage of works complete.
194. I have viewed the relevant photos of this variation on the CD. In my view,
the photos indicate that the works have been “roughed in” and are awaiting fit
off. The Claimant asserts that 85% of the works are complete.
195. The Claimant has not provided any evidence to support its submission
that the works are 85% complete. Having viewed the photos, I am of the view
that 85% is likely to be a little overstated. In my view, the works are likely to
be closer to 75% complete. However, consistent with the Claimant’s
concessions contained in Variation 45 below, I am satisfied that it is
appropriate in the circumstances that the Claimant receive 50% of the
claimed amount.
196. In the premises, I allow the sum of $11,595.00 (being 50% of $23,190.00).
Variation 29 – Reception desk, wall and floor
197. The Claimant seeks payment in the sum of $4,495.00 in relation to this
item. There is no dispute involving the quantum claimed, however the parties
are in dispute as to whether the Claimant has been paid the sum of $3,173.00
as alleged by the Respondent. Neither party provided any evidence of
payment one way or the other.
198. I accept that the Claimant is entitled to the sum of $4,495.00.
Variation 30 – Carpet to Level 5 - Deleted
199. There is no dispute between the parties in relation to this item.
Page 52
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 52
Variation 31 – Café block work and concrete floors 200. The Claimant originally sought payment for this item in the sum of
$12,000.00. The Claimant has since amended this amount to $4,700.00.
201. The Respondent alleges that this item is valued at $3,700.00 and that it
has paid the Claimant the sum of $2,700.00 but has provided no evidence of
having done so. The Claimant denies having been paid any amount for this
variation.
202. Mr Real’s “Approved Value” as demonstrated in Exhibit RR-1 is in the sum
$4,700.00. The only detail given by Mr Real is where he states “Value
assessed due to works altered from quote.”
203. The Claimant asserts that it has completed the works.
204. In an email to Mr Botica dated 10 December 2009, Mr Real approved the
cost of the variation in the sum of $4,700.00. Mr Real has at Annexure G to
his affidavit provided some background to the construction of the blockwall
but has provided no evidence of his reduction in the sum of $1,000.00.
Ultimately, Mr Real agreed to the $4,700.00 variation. If he wanted to make a
deduction for the Claimant’s error, that should have been stated and costed in
the variation approval.
205. On balance, I am satisfied that the Claimant is entitled to the sum of
$4,700.00.
Variation 32 – Level 5 Office Furniture - deleted
206. There is no dispute between the parties in relation to this item.
Variation 33 – Lighting to Level 5 207. The Claimant originally sought payment for this item in the sum of
$6,215.00. The Claimant has since amended this amount to $5,282.75.
Page 53
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 53
208. The Respondent alleges that this item is valued at the sum of $5,650.00
but Mr Real is of the view that only 60% of the work has been completed.
Therefore, the Respondent asserts that the Claimant is only entitled to the
sum of $3,390.00. Both parties agree that the Claimant has not been paid for
this variation.
209. According to the estimate provided by the Claimant’s electrician, the value
of the variation is $5,650.00. When a 10% margin is applied, one arrives at
the value of $6,215.00. The Claimant alleges to have completed 85% of that
work.
210. Having viewed Mr Real’s photographs, it appears that the rough in has
been performed but the fit-off is yet to be done. Consistent with the
Claimant’s concessions in Variation 45, I am of the view that approximately
50% of the work has been performed. However, the Respondent has
calculated a figure of 60%, so I will allow the latter amount.
211. In the premises, I am satisfied that the Claimant is entitled to the sum of
$3,729.00 ($6,215.00 x 60%).
Variation 34 – Partitions and flush ceilings to Level 5
212. The Claimant originally sought payment for this item in the sum of
$34,004.00 but has since amended the claim to the sum of $29,923.53.
213. The Respondent agrees that this item is valued at the sum of $34,004.00
but Mr Real is of the view that only 65% of the work has been completed.
Therefore, the Respondent asserts that the Claimant is only entitled to the
sum of $22,103.00. Both parties agree that the Claimant has not been paid
for this variation.
214. According to the estimate provided by the Claimant’s plastering contractor,
the value of the variation is $34,004.00. I note that the Claimant is not
Page 54
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 54
claiming for its 10% margin on this item. The Claimant alleges to have
completed 88% of that work.
215. Having viewed Mr Real’s photographs, it appears that in relation to the
areas photographed that external angles have not been set, nor has the top
coat of the ceiling and wall joints been applied nor sanded.
216. Whilst it is difficult to accurately assess the completion stage of this item, I
am of the view that the truth of the matter lays somewhere in between the
competing figures. Doing the best I can, I am satisfied that the work is
approximately 75% complete.
217. In the premises, I am satisfied that the Claimant is entitled to the sum of
$25,503.00 ($34,004.00 x 75%).
Variation 35 – Media centre power and special cabling
218. The Claimant originally sought payment for this item in the sum of
$12,336.50 but has since amended the claim to the sum of $10,979.49. It
has provided a copy of its electrician’s estimate in the sum of $11,215.00
which when the 10% margin is applied, equates to the claimed amount.
219. The Respondent argues that this item, if it was completed would be valued
in the sum of $11,215.00. However, Mr Real is of the view that the work is
incomplete. Consequently, the Respondent asserts that the Claimant is only
entitled to the sum of $6,600.00. Both parties agree that the Claimant has not
been paid for this variation.
220. In an email dated 10 December 2009 to Mr Botica, Mr Real approved the
variation in the sum of $12,336.50. Mr Real’s assessment of the completion
of the works as detailed in Exhibit ‘H’ to his affidavit does not provide any
basis for his calculations and he appears by no means certain of what work
has and has not been completed.
Page 55
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 55
221. In the absence of any meaningful contrary evidence, on balance, I prefer
the submissions of the Claimant on this point. I am satisfied that the 89% of
the work has been completed and that the Claimant is entitled to the sum of
$10,979.49.
Variation 36 – A/C Altitude room
222. The Claimant seeks payment for this item in the sum of $4,380.00.
223. The Respondent agrees that this item is valued in the sum of $4,380.00
but Mr Real is of the view that only 80% of the work has been completed.
Therefore, the Respondent asserts that the Claimant is only entitled to the
sum of $3,504.00. Both parties agree that the Claimant has not been paid for
this variation.
224. According to the estimate provided by the Claimant’s air conditioning
contractor, the value of the variation is $4,380.00. I note that the Claimant is
not claiming for its 10% margin on this item. The Claimant alleges to have
completed 100% of that work.
225. Having viewed Mr Real’s photograph on the CD, it appears that the work
is 100% complete, although I concede that the external unit has not been
photographed. Having said that, I would have expected that if the external
unit was not installed, Mr Real would have photographed that omission
instead of the internal unit which was installed.
226. In the premises, I am satisfied that the Claimant is entitled to the sum of
$4,380.00.
Variation 37 – Reception Counter and Café stone - deleted
227. There is no dispute between the parties in relation to this item.
Page 56
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 56
Variation 38 – Lay café floor tiles 228. The Claimant originally sought payment for this item in the sum of
$1,912.00. However, it concedes that only 95% of the work has been
completed. Therefore it has amended the claimed amount to the sum of
$1,816.40.
229. The Respondent agrees that this item is valued at the sum of $1,912.00
but Mr Real is of the view that only 70% of the work has been completed.
Therefore, the Respondent asserts that the Claimant is only entitled to the
sum of $1,338.00. Both parties agree that the Claimant has not been paid for
this variation.
230. Neither party has provided any independent assessment of the completion
of the work. Mr Real has provided no real justification for arguing that the
work is 30% incomplete. Having viewed Mr Real’s photographs from the CD,
the slab core drilling indicates that some form of joinery and waste is to cover
the bare slab. Noting that the remainder of the work appears to be grouted, I
am satisfied that the works are approximately 95% complete.
231. In the premises, I am satisfied that the Claimant is entitled to the sum of
$1,816.40 ($1,912.00 x 95%).
Variation 39 – Level 5 Door hardware 232. The Claimant originally sought payment for this item in the sum of
$3,690.75. However, it concedes that it is entitled to only 50% of the claimed
amount because it was prevented from installing the hardware as a result of
the termination of the contract. However, the Claimant asserts that the
hardware was on site. Therefore it has amended the claimed amount to the
sum of $1,845.38.
Page 57
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 57
233. The Respondent argues that the Claimant is entitled to nil because the
works were “not proceeded with”. Both parties agree that the Claimant has
not been paid for this variation.
234. Neither party has provided any independent assessment of whether or not
the goods have or have not been delivered to site. The Claimant provided in
second numbered Tab 9 of Exhibit PB-6 to Mr Botica’s affidavit an internal Bill
of Quantities schedule in the sum of $3,690.75. The difficulty I have with this
Bill of Quantities is that it only refers to materials. If the Claimant had these
goods delivered to site but they were uninstalled, why would it not claim the
full amount instead of reducing the claim by 50% for labour that was not
performed?
235. Given that the Claimant has not provided a delivery docket, or any other
evidence to prove that the materials are in fact on site as alleged, I am
unsatisfied that the Claimant is entitled to this amount. For the purposes of
s.27(2) of the Act, I am not valuing this item at nil, I am simply not satisfied
that the Claimant has made out its entitlement.
Variation 40 – Cut in 2 x electric strikes
236. The Claimant seeks payment for this item in the sum of $363.00.
237. The Respondent argues that the Claimant is entitled to nil because the
works were “not proceeded with”. Both parties agree that the Claimant has
not been paid for this variation.
238. Neither party has provided any independent assessment of whether or not
the goods have or have not been delivered and installed. However, as
distinct from Variation 39, the electric strikes or at least where they should
have been installed could have been photographed by Mr Real. I am
prepared to draw an adverse inference from the fact that he has not provided
Page 58
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 58
photographs of this variation when it would have been quite easy and from an
evidentiary perspective, quite compelling had he done so.
239. In the premises, I am satisfied that the Claimant is entitled to the sum of
$363.00.
Variation 41 – Sanitary fixture supply to level 5 ensuite - deleted
240. There is no dispute between the parties in relation to this item.
Variation 42 – Painting to Level 5, media room and ground floor foyer 241. The Claimant originally sought payment for this item in the sum of
$37,300.00. However, it concedes that it is entitled to the scheduled amount
of $3,800.00. Both parties agree that the Claimant has not been paid for this
variation.
242. In the premises, there is no dispute between the parties in relation to this
item.
Variation 43 – Deleted 243. The claim for this item has been deleted.
Variation 44 – Internal windows and door frames L5 244. The Claimant originally sought payment for this item in the sum of
$46,950.00. However, it concedes that only 10% of the work has been
completed. Therefore it has amended the claimed amount to the sum of
$4,695.00.
245. The Respondent agrees that this item is valued at the sum of $46,950.00
but Mr Real is of the view that only 2% of the work has been completed.
Therefore, the Respondent asserts that the Claimant is only entitled to the
sum of $940.00. Both parties agree that the Claimant has not been paid for
this variation.
Page 59
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 59
246. Neither party has provided any independent assessment of the extent of
the completion of the work. In this instance as the Claimant bares the onus of
proof, I prefer the submissions of the Respondent.
247. In the premises, I am satisfied that the Claimant is entitled to the sum of
$940.00.
Variation 45 – New lights in Michael Searle’s office
248. The Claimant originally sought payment for this item in the sum of
$990.00. However, it concedes that it is entitled to only 50% of the claimed
amount because only the rough in has been performed. Therefore it has
amended the claimed amount to the sum of $495.00.
249. The Respondent argues that the Claimant is entitled to nil because the
works were “not proceeded with”. Both parties agree that the Claimant has
not been paid for this variation.
250. Neither party has provided any independent assessment of whether or not
the work the subject of this variation has been performed. However, as
distinct from Variation 39, the wiring for the lights or at least where they
should have been roughed in could have been photographed by Mr Real. I
am prepared to draw an adverse inference from the fact that he has not
provided photographs of the absence of this work when it would have been
quite easy and from an evidentiary perspective, quite compelling had he done
so.
251. In the premises, I am satisfied that the Claimant is entitled to the sum of
$495.00.
Variation 46 – Extra wall over plumber’s pipes (Strapping room)
252. The parties agree that the Claimant is entitled to the sum of $295.00 for
this item.
Page 60
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 60
253. Both parties agree that the Claimant has not been paid for this variation.
Variation 47 – Extra wall over plumber’s pipes (Kitchen Level 1)
254. The parties agree that the Claimant is entitled to the sum of $185.00 for
this item.
255. Both parties agree that the Claimant has not been paid for this variation.
Variation 48 – Dwarf wall to cafe 256. The Claimant seeks payment for this item in the sum of $925.00.
257. The Respondent argues that the completed value of the variation would
have been $925.00 but Mr Real asserts that it is only 80% complete.
Therefore, the Respondent submits that the Claimant is only entitled to the
sum of $740.00.
258. Both parties agree that the Claimant has not been paid for this variation.
259. The Claimant provided evidence in the way of:
259.1. A direction from Mr Real that the work be performed;
259.2. A variation order from its plastering sub-contractor in the sum of
$925.00;
259.3. A photo evidencing the completed work.
260. The Respondent has provided no bases for the proposed deduction.
261. In the premises, I am satisfied that the Claimant is entitled to the sum of
$925.00.
Variation 49 – Fire rate columns to Level 5
262. The Claimant seeks payment for this item in the sum of $1,295.00.
Page 61
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 61
263. The Respondent argues that the Claimant is entitled to payment for only
one column in the sum of $55.00 as the balance was work that should have
been performed under the contract.
264. Both parties agree that the Claimant has not been paid for this variation.
265. The Claimant has been provided with a variation for this work from its
plastering sub-contractor in the sum of $1,295.00 for the fire rating of seven
steel columns on Level 5.
266. The Respondent has not provided me with any supporting material
whatsoever on this point.
267. I accept that there is no evidence that the Claimant has complied with its
obligations pursuant to clause 36 of the contract in relation to this and various
other variations. However, in my view, for the reasons I have previously
expressed, it could not reasonably be argued that the parties, through their
conduct, consistently applied the strict terms of the contract. I accept that the
Superintendent, in what must have been a very challenging role, has sought
to “do his best” under the circumstances. However, given the factual matrix
of the parties’ dealings with one another, I am not prepared to strike out a
variation claim because the Claimant did not comply with the strict terms of
clause 36 of the contract.
268. On balance, on the strength of the subcontractor’s variation, I prefer the
submissions of the Claimant. The Claimant is entitled to receive the sum of
$1,295.00.
Variation 50 – Steel wall fire rating to Level 5
269. The Claimant seeks payment for this item in the sum of $1,325.00.
Page 62
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 62
270. The Respondent argues that the Claimant is entitled to nil monies as the
work should have been performed under the contract.
271. Both parties agree that the Claimant has not been paid for this variation.
272. The Claimant has been provided with a variation for this work from its
plastering sub-contractor in the sum of $1,325.00 for the framing and fire
rating of a “small steel wall to the opening above Level 5 fire check ceiling.”
273. The Respondent has not provided me with any supporting material
whatsoever on this point.
274. On balance, on the strength of the subcontractor’s variation, I prefer the
submissions of the Claimant. The Claimant is entitled to receive the sum of
$1,325.00.
Variation 51 – Altitude room access panels and light boxes
275. The Claimant seeks payment for this item in the sum of $1,490.00.
276. The Respondent argues that the completed value of the variation would
have been $1,490.00 but Mr Real asserts that it is only 50% complete.
Therefore, the Respondent submits that the Claimant is only entitled to the
sum of $745.00.
277. Both parties agree that the Claimant has not been paid for this variation.
278. The Claimant provided evidence in the way of:
278.1. A direction from Mr Real that the work be performed;
278.2. A variation order from its plastering sub-contractor in the sum of
$1,490.00;
278.3. A photo evidencing the completed work.
279. The Respondent has provided no bases for the proposed deduction.
Page 63
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 63
280. In the premises, I am satisfied that the Claimant is entitled to the sum of
$1,490.00.
Variation 52 – Level 5 kitchen wall, mez L1 air plenum
281. The Claimant seeks payment for this item in the sum of $1,905.00.
282. The Respondent argues that the Claimant is entitled to nil because it has
not provided supporting information for the Claim.
283. Both parties agree that the Claimant has not been paid for this variation.
284. I have reviewed the Claimant’s subcontractor variation for this item and
compared the amended drawings provided by Mr Rule with the plans
contained in Exhibit PB-7 to the affidavit of Mr Botica. On reflection, I cannot
decipher the variation which is being claimed.
285. On balance, I agree with the Respondent’s submissions. I am of the view
there is insufficient evidence to establish an entitlement to this aspect of the
claim. To be clear, for the purposes of s.27(2) of the Act, I am not valuing this
work at nil or zero, I am simply not satisfied that the Claimant has established
its entitlement.
Variation 53 – Altitude room duct, bulkhead, ply ceiling
286. The Claimant seeks payment for this item in the sum of $550.00, being 4
hours labour for the A/C duct work and 6 hours labour to remove and replace
the ply sheeting in the gym.
287. The Respondent argues that the value of the claim is $55.00 based on 1
hour of work to complete the duct work. It rejected the claim for the bulkhead
and was unable to assess the claim for the ply ceiling.
288. Both parties agree that the Claimant has not been paid for this variation.
Page 64
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 64
289. The Claimant provided evidence in the way of:
289.1. A direction from Mr Real that the work be performed;
289.2. A variation order from its plastering sub-contractor in part
evidencing the 10 hours claimed, in the sum of $550.00;
289.3. A photo evidencing the completed work.
290. The Respondent has provided no supporting material for the proposed
deduction.
291. In the premises, on the strength of the evidence in the subcontractor’s
variation order, I am satisfied that the Claimant is entitled to the sum of
$550.00.
Variation 54 – WG12 highlight panel
292. The Claimant seeks payment for this item in the sum of $1,060.00, being
for aluminium cover plates to match internal window frames.
293. The Respondent rejects the claim and implies that the omission of the
plates was an error by the Claimant.
294. Both parties agree that the Claimant has not been paid for this variation.
295. I have reviewed the variation order from Total Concept Group, the
Claimant’s glazing supplier and in my view, the amount claimed in the sum of
$1,060.00 pertains more to the reconfiguration of a window (WG-12) than it
does in relation to the provision of cover plates.
296. On balance, whilst drawing WD 3.02 Rev 6 does indicate the presence of
2 x steel columns to engineer’s details, that does not equate to the claimed
cost in my view. In the premises, I am not satisfied that the claimant has an
entitlement to the claimed amount. To be clear, for the purposes of s.27(2) of
Page 65
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 65
the Act, I am not valuing this work at nil or zero, I am simply not satisfied that
the Claimant has established its entitlement.
Variation 55 – Sauna and steam room doors and highlights 297. The Claimant seeks payment for this item in the sum of $10,026.00, being
for additional doors, side light and highlight windows.
298. The Respondent rejects the claim. Mr Real in the schedule attached to
his affidavit argues that the doors and side light windows were part of the
original documentation and that the highlight panels were amended at the
Claimant’s request.
299. Both parties agree that the Claimant has not been paid for this variation.
300. The Claimant provided evidence in the way of:
300.1. A direction dated 18 September 2009 from Mr Real that the
work be performed, together with a sketch diagram for the work.
However, I note that that sketch does not require glazed
highlight panels. Rather it specifies the use of villaboard;
300.2. A variation order from its supplier evidencing the additional cost
in the sum of $10,026.00;
300.3. A photo evidencing the completed work.
301. The Respondent has provided no supporting material to substantiate its
submissions.
302. In the premises, I am satisfied that the Claimant was directed to supply
and install the amended design for the doors and side lights, however it
appears that the variation did not require the highlight panels to be glazed.
Whilst I have not been provided with a breakdown of the costs of each item, I
am satisfied that when taking into account the credit available for the
Page 66
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 66
villaboard, it is appropriate to deduct a nominal sum for the glazed highlights
in the amount of $1,000.00.
303. In the premises, the Claimant is entitled to the sum of $9,026.00.
Variation 56 – One way film to gym office 304. The Claimant accepts the scheduled amount for this item in the sum of
$600.00.
305. Both parties agree that the Claimant has not been paid for this variation.
Variation 57 – Gym storage room door schedule incorrect
306. The Claimant originally sought payment for this item in the sum of
$6,357.00, being for an amendment to the design of the doors in the storage
room of the gym. The Claimant has since reduced the claimed amount by
$1,200.00 to credit the cost of the original timber doors. Therefore, the
Claimant now seeks payment in the sum of $5,157.00.
307. The Respondent rejects the claim. Mr Real in the schedule attached to
his affidavit argues that the design of the doors was changed at the
Claimant’s request.
308. Both parties agree that the Claimant has not been paid for this variation.
309. The Claimant provided evidence in the way of:
309.1. A variation order from its supplier evidencing the additional cost
in the sum of $6,357.00;
309.2. A photo evidencing the completed work;
309.3. But it did not provide a copy of the direction purportedly made
by Mr Real dated 18 September 2009.
Page 67
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 67
310. The Respondent has provided no supporting material to substantiate its
submissions.
311. On balance, without evidence of Mr Real’s direction, I have no way of
knowing whether the work was performed at the request of the builder. I
accept that the work as it has been constructed would have been at a greater
cost to the Claimant, although I note that the cost as it has been presented in
the Total Concept Group variation order seems quite high, in my opinion. In
the premises, I am not satisfied that the Claimant has an entitlement to the
claimed amount. To be clear, for the purposes of s.27(2) of the Act, I am not
valuing this work at nil or zero, I am simply not satisfied that the Claimant has
established its entitlement.
Variation 58 – Media/production room double glazing
312. The Claimant seeks payment for this item in the sum of $7,043.00.
313. The Respondent rejects the claim. Mr Real in the schedule attached to
his affidavit argues that the double glazing has not been installed to the
production and media rooms.
314. Both parties agree that the Claimant has not been paid for this variation.
315. The Claimant provided evidence in the way of:
315.1. A variation order from its supplier evidencing the additional cost
in the sum of $7,043.00;
315.2. A string of emails between the parties dated 17 July 2009.
However there is no evidence in those emails of an instruction
for double glazing.
316. The Respondent has provided no supporting material to substantiate its
submissions apart from two photographs of the glass which are not helpful.
Page 68
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 68
317. In my view, the Claimant has provided no evidence that the work is a
variation. The fact that its supplier has provided it with a variation order does
not of itself prove that there is a variation to the contract between the
Claimant and the Respondent. In addition to this, the Claimant has not
satisfied me that the work has been performed.
318. In the premises, I am not satisfied that the Claimant has an entitlement to
the claimed amount. To be clear, for the purposes of s.27(2) of the Act, I am
not valuing this work at nil or zero, I am simply not satisfied that the Claimant
has established its entitlement.
Variation 59 – Glazed infills to offices - Deleted
319. The parties agree that this item is to be deleted.
Variation 60 – Walls and partitions - Deleted 320. The parties agree that this item is to be deleted.
Variation 61 – Curtain wall south side elevation (W102) 321. The Claimant seeks payment for this item in the sum of $19,332.00. It
argues that the architectural drawings are inconsistent in the number of
glazing panels to be installed to the south elevation of the works.
322. The Respondent rejects the claim. Mr Real in the schedule attached to
his affidavit argues that “where a discrepancy exists between documents, the
greater cost takes precedence.”
323. Both parties agree that the Claimant has not been paid for this variation.
324. The Claimant provided evidence in the way of:
324.1. A variation order from its supplier evidencing the additional cost
in the sum of $19,332.00;
Page 69
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 69
324.2. Copies of the relevant architectural drawings highlighting the
discrepancy; and
324.3. A photograph of the completed work showing a glass curtain
wall 11 modules wide.
325. The Claimant seeks to rely on clause 8.1 of the contract which provides
that “Figured [dimensions] are to prevail over scaled dimensions in a
discrepancy.”
326. The Respondent has provided no supporting material to substantiate its
submissions.
327. In my view, there is a discrepancy in the architectural drawings. WD10.01
Rev 3 provides figured dimensions showing the curtain wall to be 10 panels
wide whilst WD 10.02 Rev 5 shows 11 panels wide but there are no
dimensions on that elevation.
328. Mr Real’s has not provided me with any contractual basis for his
contention that the drawing (design) which costs greater should prevail.
329. In my view, clause 8.1 of the contract applies. In the premises, the
Claimant is entitled to the claimed amount in the sum of $19,332.00.
Variation 62 – Spa spandrel change
330. The Claimant seeks payment for this item in the sum of $527.00. It argues
that after this work had already been completed, Mr Real directed that the
colour of the spandrel panels be changed to beige royale.
331. The Respondent rejects the claim. Mr Real in the schedule attached to
his affidavit argues that the need for the work arose out of builder error.
332. Both parties agree that the Claimant has not been paid for this variation.
Page 70
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 70
333. The Claimant provided evidence in the way of:
333.1. A variation order from its supplier evidencing the additional cost
in the sum of $527.00. However, the variation order also
includes the cost of changing the colour of the glass doors to
the sauna; and
333.2. A photograph of the completed work.
334. The Respondent has provided no supporting material to substantiate its
submissions.
335. The Claimant did not provide any documentary evidence of the instruction
purportedly issued by Mr Real. In the premises, I am not satisfied that the
claimant has an entitlement to the claimed amount. To be clear, for the
purposes of s.27(2) of the Act, I am not valuing this work at nil or zero, I am
simply not satisfied that the Claimant has established its entitlement.
Variation 63 – Angle trim to the external side of the altitude room 336. The Claimant seeks payment for this item in the sum of $800.00. It argues
that additional aluminium trim was required when the rehab/physio room was
later changed to become an “altitude room” to enable pressurisation of the
room.
337. The Respondent rejects the claim. Mr Real in the schedule attached to
his affidavit argues that the trim was part of the glazing system.
338. Both parties agree that the Claimant has not been paid for this variation.
339. The Claimant provided evidence in the way of:
339.1. A variation order from its supplier evidencing the additional cost
in the sum of $800.00; and
339.2. A photograph of the completed work.
Page 71
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 71
340. The Respondent has provided no supporting material to substantiate its
submissions, nor does it challenge the Claimant’s assertion that the use of
the room was changed from being a Rehab/physio room to an “altitude room”
which I assume is akin to a hyperbaric chamber. The Claimant when it
costed the project could not have anticipated the requirement for additional
trim to ensure the pressurisation of the room.
341. In the absence of any meaningful submissions from the Respondent on
this issue, on balance, I agree with the submissions of the Claimant and find
that the Claimant is entitled to the sum of $800.00.
Variation 64 – Glass partitions to walls in level 1 lower offices - Deleted
342. The parties agree that this item is to be deleted.
Variation 65 – Concrete plinth in basement 343. The parties agree that the Claimant is entitled to the sum of $2,392.00.
344. Both parties agree that the Claimant has not been paid for this variation.
Variation 66 – Level 5 kitchen changes - Deleted 345. The parties agree that this item is to be deleted.
Variation 67 – Pool fence gate - Deleted 346. The parties agree that this item is to be deleted.
Variation 68 – Joinery changes to player’s cabinets 347. The parties agree that the Claimant is entitled to the sum of $1,800.00.
348. Both parties agree that the Claimant has not been paid for this variation.
Variation 69 – Level 5 doors 349. The Claimant originally sought payment for this item in the sum of
$12,229.27, being for an amendment to the design of the doors to the offices
Page 72
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 72
on level 5. The Claimant has since reduced the claimed amount by
$2,966.09 to take into account its assessment that the work is only 76%
complete. Therefore, the Claimant now seeks payment in the sum of
$9,263.18.
350. The Respondent rejects the claim. Mr Real in the schedule attached to
his affidavit argues that the doors were not delivered to site.
351. Both parties agree that the Claimant has not been paid for this variation.
352. The Claimant provided evidence in the way of:
352.1. An instruction from Mr Real dated 10 December 2009 varying
the size of the doors;
352.2. A quotation from its supplier evidencing the cost for the doors in
the sum of $10,489.87.
353. I accept the Claimant’s submissions that the doors are a special order and
cannot be returned to the supplier. The fact that they were not delivered to
site is immaterial in my view. The Claimant will still be liable to pay its
supplier for the doors.
354. There is no evidence, from either party as to whether there should have
been a credit due to the Respondent for the cost of the original doors. In the
absence of that submission from the Respondent I accept there must have
been some other arrangement in place.
355. On balance, I prefer the submissions of the Claimant. I am satisfied that
the Claimant is entitled to the sum of $9,263.18. However, once paid for, the
doors should be provided to the Respondent.
Page 73
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 73
Additional Plumbing changes
356. The Claimant originally sought payment for this item as a lump sum of
$47,181.82. As I understand the Claimant’s position, it has now itemised this
part of the claim into 6 discrete claims [70(a) to 70(f)] now totaling
$21,666.00.
Variation 70(a) – 600 bend for stormwater 357. The Claimant seeks payment for this item in the sum of $318.00.
358. The Respondent via Mr Real, values the work at $200.00 because he
says the work is incomplete.
359. Both parties agree that the Claimant has not been paid for this variation.
360. The Claimant provided evidence in the way of:
360.1. A quotation from its plumbing subcontractor evidencing the cost
for the work in the sum of $318.18.
361. There is no evidence that the work is incomplete. Mr Real’s photographs
on the CD do not, as best I can tell, reveal incomplete work for this item. In
the absence of more detailed submissions from the Respondent and on the
strength of the H & G Plumbing variation request, I accept that the Claimant is
entitled to the sum of $318.00.
Variation 70(b) – Changes to L5 ensuite 362. The Claimant seeks payment for this item in the sum of $1,941.00.
363. The Respondent via Mr Real, values the work at nil because he says it is
a “builder error”.
364. Both parties agree that the Claimant has not been paid for this variation.
Page 74
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 74
365. The Claimant provided evidence49
365.1. A quotation from its plumbing subcontractor evidencing the cost
for the work in the sum of $1,940.91;
in the way of:
365.2. Its variation register for H & G Plumbing’s work dated 25
January 2010 indicating that the work was 100% complete.
366. There is no evidence that the work was performed due to an error
performed by the Claimant. If the Respondent wishes to pursue that type of
reasoning, it is incumbent upon it to provide some evidence to justify its
position. It has not.
367. In the absence of more detailed submissions from the Respondent and on
the strength of the H & G Plumbing variation request, I accept that the
Claimant is entitled to the sum of $1,941.00.
Variation 70(c) – Grease trap upgrade - Deleted 368. The parties agree that this item is to be deleted.
Variation 70(d) – Café works - Deleted 369. The parties agree that this item is to be deleted.
Variation 70(e) – Level 5 Kitchen works 370. The Claimant appears to have originally claimed the sum of $15,864.00
for this item but has since amended its claim to the sum of $8,000.00. The
Claimant has assessed its work as being 50% complete.
371. The Respondent via Mr Real, values the work at $5,000.00 because it is
incomplete.
372. Both parties agree that the Claimant has not been paid for this variation.
49 Albeit in an unmarked Tab in Exhibit PB-6 to the affidavit of Paul Botica
Page 75
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 75
373. The Claimant provided evidence in the way of:
373.1. A quotation from its plumbing subcontractor evidencing the cost
for the work in the sum of $15,863.65;
373.2. Its variation register for G & G Plumbing’s work dated 25
January 2010 indicating that the work was 50% complete.
374. Neither party has provided any substantial evidence as to the completion
stage of the work. However, on balance in the absence of more detailed
submissions from the Respondent, I accept that the Claimant is entitled to the
sum of $8,000.00.
Variation 70(f) - Hot water pipe work to Level 1 bar and cafe 375. The Claimant seeks payment for this item in the sum of $11,000.00.
376. The Respondent via Mr Real, values the work at $3,000.00 because he
asserts that there was a lack of supporting documentation and he was unable
to determine if the work was completed.
377. Both parties agree that the Claimant has not been paid for this variation.
378. The Claimant provided evidence in the way of:
378.1. A quotation from its plumbing subcontractor evidencing the cost
for the work in the sum of $15,409.09;
378.2. Its variation register for H & G Plumbing’s work dated 25
January 2010 indicating that the work was 100% complete.
379. Neither party has provided any substantial evidence as to the completion
stage of the work. According to the Claimant’s payment schedule for H & G
Plumbing, the Claimant has approved payment to H & G Plumbing for this
item in the sum of $11,000.00.
Page 76
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 76
380. On balance in the absence of more detailed submissions from the
Respondent, I accept that the Claimant is entitled to the sum of $11,000.00.
Additional pool works
381. The Claimant seeks payment for this item as a lump sum of $35,242.73.
The Respondent in Exhibit RR-1 to the affidavit of Mr Real has itemised this
part of the claim into 19 discrete claims [71(a) to 71(s)] totaling $35,243.00.
Accordingly I shall address each of them in turn.
Variation 71(a) – Extra footing 382. The Claimant seeks payment for this item in the sum of $2,000.00.
383. The Respondent via Mr Real, argues that the claim is unable to be
assessed due to lack of supporting information.
384. Both parties agree that the Claimant has not been paid for this variation.
385. The Claimant provided evidence in the way of:
385.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $2,000.00.
386. In the absence of more detailed submissions or contrary evidence from
the Respondent and on the strength of the Pool FX invoice dated 18 February
2010, I accept that the Claimant is entitled to the sum of $2,000.00.
Variation 71(b) – Engineer’s Inspection 387. The Claimant seeks payment for this item in the sum of $436.00.
388. The Respondent via Mr Real, rejects the claim and argues that this item
was the Claimant’s responsibility.
389. Both parties agree that the Claimant has not been paid for this variation.
Page 77
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 77
390. The Claimant provided evidence in the way of:
390.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $436.00.
391. The Pool FX invoice dated 18 February 2010 reveals that the engineer’s
inspections were required because of “work stoppages due to no payments”.
In the premises, I agree with the Respondent. The payment of the Claimant’s
subcontractors is the Claimant’s responsibility, even if the Respondent has
not promptly or adequately paid the Claimant its accounts. I reject this claim.
Variation 71(c) – Foam replacement 392. The Claimant seeks payment for this item in the sum of $5,345.00.
393. The Respondent via Mr Real, rejects the claim and argues that this item
was the Claimant’s responsibility.
394. Both parties agree that the Claimant has not been paid for this variation.
395. The Claimant provided evidence in the way of:
395.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $5,345.00.
396. The Pool FX invoice dated 18 February 2010 reveals that the foam
replacement was required because of “work stoppages due to no payments”.
In the premises, I agree with the Respondent. The payment of the Claimant’s
subcontractors is the Claimant’s responsibility, even if the Respondent has
not promptly or adequately paid the Claimant its accounts. I reject this claim.
Variation 71(d) – Extra pipework 397. The Claimant seeks payment for this item in the sum of $636.00.
Page 78
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 78
398. The Respondent via Mr Real, argues that the claim is unable to be
assessed due to lack of supporting information.
399. Both parties agree that the Claimant has not been paid for this variation.
400. The Claimant provided evidence in the way of:
400.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $636.00.
401. In the absence of more detailed submissions or contrary evidence from
the Respondent and on the strength of the Pool FX invoice dated 18 February
2010, I accept that the Claimant is entitled to the sum of $636.00.
Variation 71(e) – Extra booster pump 402. The Claimant seeks payment for this item in the sum of $4,000.00.
403. The Respondent via Mr Real, argues that the claim is unable to be
assessed due to lack of supporting information.
404. Both parties agree that the Claimant has not been paid for this variation.
405. The Claimant provided evidence in the way of:
405.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $4,000.00.
406. In this instance there has been no explanation for the requirement for the
additional pump. Without more information, it is impossible to determine the
merits of this claim. Without more substantiation, I am of the view that the
Respondent ought not have to pay for this item. To be clear for the purposes
of s.27(2) of the Act, I am not valuing this item at nil, I am simply not satisfied
that the Claimant is entitled to the amount claimed.
Page 79
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 79
Variation 71(f) – Tile transport cost 407. The Claimant seeks payment for this item in the sum of $4,451.00.
408. The Respondent via Mr Real, rejects the claim and argues that the cost
cannot be substantiated.
409. Both parties agree that the Claimant has not been paid for this variation.
410. The Claimant provided evidence in the way of:
410.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $4,451.00.
411. The Pool FX invoice dated 18 February 2010 reveals that the cost arose
out of having to organise delivery from Sydney to Brisbane. On balance, I
agree with the submissions of the Respondent. Without more substantiation,
I am of the view that the Respondent ought not have to pay for this item. To
be clear for the purposes of s.27(2) of the Act, I am not valuing this item at nil,
I am simply not satisfied that the Claimant is entitled to the amount claimed.
Variation 71(g) – Expansion joint 412. The Claimant seeks payment for this item in the sum of $1,000.00.
413. The Respondent via Mr Real, rejects the claim and argues that an
expansion joint would have been required using the original tiles.
414. Both parties agree that the Claimant has not been paid for this variation.
415. The Claimant provided evidence in the way of:
415.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $1,000.00.
Page 80
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 80
416. The Pool FX invoice dated 18 February 2010 reveals that the cost arose
out of having to install an expansion joint every 5 metres to comply with the
manufacturer’s specifications. I am of the view that it is more likely than not
that the original tiles would also have required a similar number of expansion
joints. However, without more information, it is impossible to determine the
merits of this claim. Without more substantiation, I am of the view that the
Respondent ought not have to pay for this item. To be clear for the purposes
of s.27(2) of the Act, I am not valuing this item at nil, I am simply not satisfied
that the Claimant is entitled to the amount claimed.
Variation 71(h) – Depth marker 417. The parties agree that the Claimant is entitled to receive payment in the
sum of $800.00 for this item.
418. Both parties agree that the Claimant has not been paid for this variation.
Variation 71(i) – Colour match grate 419. The Claimant seeks payment for this item in the sum of $773.00.
420. The Respondent via Mr Real, rejects the claim but provides no reason for
doing so.
421. Both parties agree that the Claimant has not been paid for this variation.
422. The Claimant provided evidence in the way of:
422.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $773.00.
423. In the absence of more detailed submissions or contrary evidence from
the Respondent and on the strength of the Pool FX invoice dated 18 February
2010, I accept that the Claimant is entitled to the sum of $773.00.
Page 81
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 81
Variation 71(j) – Cut tiles around lights 424. The Claimant seeks payment for this item in the sum of $391.00.
425. The Respondent via Mr Real, rejects the claim but provides no reason for
doing so.
426. Both parties agree that the Claimant has not been paid for this variation.
427. The Claimant provided evidence in the way of:
427.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $391.00.
428. In the absence of more detailed submissions or contrary evidence from
the Respondent and on the strength of the Pool FX invoice dated 18 February
2010, I accept that the Claimant is entitled to the sum of $391.00.
Variation 71(k) – Extra tiles 429. The Claimant seeks payment for this item in the sum of $1,865.00.
430. The Respondent via Mr Real, argues that the claim is unable to be
assessed due to lack of supporting information.
431. Both parties agree that the Claimant has not been paid for this variation.
432. The Claimant provided evidence in the way of:
432.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $1,865.00.
433. In this instance there has been no explanation for the requirement for the
additional tiles. Without more information, it is impossible to determine the
merits of this claim. Without more substantiation, I am of the view that the
Respondent ought not have to pay for this item. To be clear for the purposes
Page 82
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 82
of s.27(2) of the Act, I am not valuing this item at nil, I am simply not satisfied
that the Claimant is entitled to the amount claimed.
Variation 71(l) – Hot water lines 434. The Claimant seeks payment for this item in the sum of $773.00.
435. The Respondent via Mr Real, argues that the claim is unable to be
assessed due to lack of supporting information.
436. Both parties agree that the Claimant has not been paid for this variation.
437. The Claimant provided evidence in the way of:
437.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $773.00.
438. The Pool FX invoice dated 18 February 2010 states that the work was
necessary because the heater position was not located on the plans. In the
absence of more detailed submissions or contrary evidence from the
Respondent, I accept that the Claimant is entitled to the sum of $773.00.
Variation 71(m) – Extra non-return valve 439. The Claimant seeks payment for this item in the sum of $527.00.
440. The Respondent via Mr Real, argues that the claim is unable to be
assessed due to lack of supporting information.
441. Both parties agree that the Claimant has not been paid for this variation.
442. The Claimant provided evidence in the way of:
442.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $527.00.
Page 83
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 83
443. The Pool FX invoice dated 18 February 2010 states that the work was
necessary because the filter position was not located on the plans. In the
absence of more detailed submissions or contrary evidence from the
Respondent, I accept that the Claimant is entitled to the sum of $527.00.
Variation 71(n) – Anti flow pipes 444. The Claimant seeks payment for this item in the sum of $364.00.
445. The Respondent via Mr Real, argues that the claim is unable to be
assessed due to lack of supporting information.
446. Both parties agree that the Claimant has not been paid for this variation.
447. The Claimant provided evidence in the way of:
447.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $364.00.
448. The Pool FX invoice dated 18 February 2010 states that the work was
necessary because these items were not located on the plans. In the
absence of more detailed submissions or contrary evidence from the
Respondent, I accept that the Claimant is entitled to the sum of $364.00.
Variation 71(o) – 38 kw heater 449. The Claimant seeks payment for this item in the sum of $1,091.00.
450. The Respondent via Mr Real, argues that the claim is unable to be
assessed due to lack of supporting information.
451. Both parties agree that the Claimant has not been paid for this variation.
452. The Claimant provided evidence in the way of:
Page 84
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 84
452.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $1,091.00.
453. In this instance there has been no adequate explanation for the
requirement for the larger size heater. Without more information, it is
impossible to determine the merits of this claim. Without more substantiation,
I am of the view that the Respondent ought not have to pay for this item. To
be clear for the purposes of s.27(2) of the Act, I am not valuing this item at nil,
I am simply not satisfied that the Claimant is entitled to the amount claimed.
Variation 71(p) – Extra core holes 454. The Claimant seeks payment for this item in the sum of $291.00.
455. The Respondent via Mr Real, argues that the claim is unable to be
assessed due to lack of supporting information.
456. Both parties agree that the Claimant has not been paid for this variation.
457. The Claimant provided evidence in the way of:
457.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $291.00.
458. In this instance there has been no adequate explanation for the
requirement for the core holes. The specified heater would also have
required such core holes to have been drilled. Without more information I am
of the view that the Respondent ought not have to pay for this item. To be
clear for the purposes of s.27(2) of the Act, I am not valuing this item at nil, I
am simply not satisfied that the Claimant is entitled to the amount claimed.
Variation 71(q) – Extra Plinth 459. The Claimant seeks payment for this item in the sum of $1,727.00.
Page 85
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 85
460. The Respondent via Mr Real, argues that the claim is unable to be
assessed due to lack of supporting information.
461. Both parties agree that the Claimant has not been paid for this variation.
462. The Claimant provided evidence in the way of:
462.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $1,727.00.
463. In this instance there has been no adequate explanation for the
requirement for the work. Without more information I am of the view that the
Respondent ought not have to pay for this item. To be clear for the purposes
of s.27(2) of the Act, I am not valuing this item at nil, I am simply not satisfied
that the Claimant is entitled to the amount claimed.
Variation 71(r) – Hydraulic changes 464. The Claimant seeks payment for this item in the sum of $8,182.00.
465. The Respondent via Mr Real, argues that the claim is unable to be
assessed due to lack of supporting information.
466. Both parties agree that the Claimant has not been paid for this variation.
467. The Claimant provided evidence in the way of:
467.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $8,182.00.
468. In this instance there has been no adequate explanation for the
requirement for the design changes. Without more information I am of the
view that the Respondent ought not have to pay for this item. To be clear for
the purposes of s.27(2) of the Act, I am not valuing this item at nil, I am simply
not satisfied that the Claimant is entitled to the amount claimed.
Page 86
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 86
Variation 71(s) – Raise pool coping 469. The Claimant seeks payment for this item in the sum of $591.00.
470. The Respondent via Mr Real, rejects this claim on the basis that it is the
Claimant’s responsibility.
471. Both parties agree that the Claimant has not been paid for this variation.
472. The Claimant provided evidence in the way of:
472.1. A tax invoice from its pool subcontractor evidencing the cost for
the work in the sum of $591.00.
473. The Pool FX invoice dated 18 February 2010 states that the work was
necessary to suit the tiled surrounds instead of the rubber matting. In the
absence of more detailed submissions or contrary evidence from the
Respondent, I accept that the Claimant is entitled to the sum of $591.00.
Variation Summary
474. For the reasons I have expressed above and as detailed in Annexure C
attached hereto, I am satisfied that the Claimant is entitled to the sum of
$573,702.54 (excluding GST) for all of the variations listed therein. In my
view, although the parties are in dispute about whether the Claimant has
received payment for many of the individual variations, it is incumbent upon
the Respondent to provide some evidence that payment has been made.
Obviously, the Claimant cannot prove that it has not been paid, so in
instances where the issue is in dispute and where the Respondent has
provided no or insufficient evidence that the variation has been paid, I prefer
the Claimant’s submissions. In the premises, I am satisfied that the Claimant
has been paid the sum of $273,511.90 (excluding GST) for the variations
listed in Annexure C.
Page 87
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 87
Value of Works Completed 475. I have calculated the value of the works performed to date according to
the following:
475.1. The adjudicated amount contained in $14,839,039.26
Annexure B:
475.2. The value of the variations contained in $ 573,702.54
Annexure C + GST: $ 57,370.25
475.3. Less value of variations paid as detailed $ - 273,511.90
In Annexure C - GST: $ - 27,351.19
Sub-total $15,169,248.96
Costs to complete
476. It is not entirely clear from the Respondent’s submissions whether it is
seeking to claim as a set-off the cost of completion of the works which it
estimates in the sum of $1,976,734.5050
. The Respondent does not
expressly make that submission, nor does it claim such in paragraph 21of the
Adjudication Response.
477. The Claimant in its Application submissions submits that the proper
valuation for the costs to complete is the sum of $1,220,758.41 as determined
in GMP Management’s assessment dated 27 January 2010.51
478. The Claimant also refers me to clause 39.6 of the contract and argues that
it does not apply because the Respondent did not take the work out of the
hands of the Claimant. I have already found that the Respondent did in fact
do as much on 3 February 2010. However, in my view, even if the
Respondent was seeking to set off the costs of completion (and I don’t think it
is), I would not allow it. When clause 39.6 is read in the context of clause
39.4, clause 39.6 does not operate to allow the Respondent to set-off such
50 See the cost estimate provided by the Reed Group at TAB ‘N’ of the Payment Schedule 51 See Exhibit AHS-49 to the affidavit of Simpson
Page 88
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 88
completion costs where the contract has been terminated. No doubt,
assuming the contract was properly terminated, a matter of which I do not
have jurisdiction to determine, damages may flow from any losses incurred by
the Respondent (if any). Any such damages would need to be recovered in
another forum.
Retention Monies 479. Pursuant to Item 13 of Annexure Part A of the Contract, the Respondent is
entitled to retain 5% of each progress certificate until the limit of 5% of the
Contract Sum has been reached.
480. Item 13 (f) of Annexure Part A of the Contract requires that 100% of the
retention held must be released to the Claimant upon the works reaching
practical completion.
481. There is no evidence and I think it would be accepted that practical
completion has not been achieved.
482. The Claimant seeks to rely on s.67J of the Queensland Building Services
Authority Act 1991 (“QBSA Act”) to prevent the Respondent from withholding
the return of the retention monies.
483. However, I agree with the submissions of the Respondent on this point.
The Respondent took the work out of the hands of the Claimant by written
notice on or about 3 February 2010 and terminated the contract on or about
17 February 2010. Therefore, pursuant to s.67J(4)(a) of the QBSA Act, s.67J
does not apply.
484. It is not entirely clear to me just how much money is currently being held in
retention. That may be because of the way the contract has been
administered that not even the parties themselves are fully aware of it (I mean
no disrespect to Mr Real in that regard). However, notwithstanding that, in
Page 89
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 89
my view the contract has not reached practical completion and neither party
has provided me with any authority to support how or when the retention
should be released. I do not consider it my role to assist the parties in that
regard. The Respondent may retain the retention monies held.
485. However, for the purposes of s.27(2) of the Act, I wish to make it clear that
my assessment of the retention monies is purely based on the Claimant’s
present entitlement. Clearly at some stage in the future, presumably when
the works have reached practical completion, the Claimant will be entitled to
their release, less any set-offs the Respondent may be able to justify (if any),
but that is not a matter which concerns me at this point in time.
Withholding payment 486. Both parties agree that pursuant to clause 38 of the contract, the
Respondent may withhold monies payable to the Claimant, until the Claimant
can satisfy the Superintendent of the monies due and payable to the
Claimant’s workers and subcontractors.
487. The Claimant, assumedly pursuant to clause 38.3(c) of the contract,
submits that the Respondent is entitled to withhold the sum of $1,809,688.15
and pay this amount directly to the subcontractors listed in Exhibit A to the
statutory declaration of Alexander Simpson contained in TAB ‘Q’ attached to
the Payment Claim.
488. However, the Respondent argues that there is evidence52
that some of the
Claimant’s subcontractors are owed greater sums than is alleged by the
Claimant and that in the case of Metro Tiles Tweed Heads no allowance has
been made for their alleged debt at all.
52 See the affidavit of Ronald Behlau dated 19 April 2010
Page 90
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 90
489. The fact that a subcontractor of the Claimant has commenced
proceedings against the Claimant and/or the Respondent does not of itself
prove the debt is in fact and in law owing to the subcontractor. For instance,
the Claimant may have a valid set-off against some or even all of the
subcontractor’s claim(s).
490. As the Claimant has expressly authorised the Respondent to withhold the
sum of $1,809,688.15 and to pay its subcontractors directly in accordance
with the details in Mr Simpson’s affidavit attached to the Payment Claim, I am
of the view that it is not open to me to alter the amounts given by that express
authority assumedly made pursuant to clause 38.3(c) of the contract. If those
amounts are inadequate that is a matter to be determined in another forum.
Whilst s.26(2) of the Act permits me to inter alia take into account the
provisions of the contract, it does not53
permit me to take into consideration
the provisions of the Subcontractors’ Charges Act 1974.
491. For these reasons I am satisfied on the express direction of the Claimant54
and pursuant to clause 38.3(c) of the contract, that the Respondent is entitled
to withhold from the Claimant, the sum of $1,809,688.15. Those monies must
be paid directly to the Claimant’s subcontractors in accordance with the
Directions contained in Mr Simpson’s affidavit dated 9 March 2010 attached
to the Payment Claim. I do note however, that I am inclined to the view that
as an adjudicator I have no power to make such Orders under the Act. In the
premises, I have not deducted this sum from the Adjudicated Amount and it
will be incumbent upon the parties to ensure that the Respondent pays the
Claimant’s subcontractors from the withheld amount.
Amount Determined 492. Subject to my reasons above I am satisfied that the Claimant has:
53 Subject to s.4 of the Act, which does not apply in this instance 54 See paragraph 5.46 of the Claimant’s Application submissions
Page 91
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 91
492.1. Performed the work the subject of the Payment Claim; and
492.2. Has not been paid the claimed amount.
493. Based on my reasons above I decide that the amount due to the Claimant
is calculated in the following manner:
Value of contract work performed to date as
detailed in Annexure B (including GST)
$14,839,039.26
Value of variations contained in Annexure C
(including GST)
$ 631,072.79
Less value of variations already paid as detailed
in Annexure C (including GST)
-$ 300,863.09
Sub-total $15,169,248.96
Less amount paid to date as detailed in
Annexure B (including GST)
-$12,492,029.58
Less Builder’s Equity -$ 0.00
Less Clawback Agreement -$ 447,006.39
TOTAL ADJUDICATED AMOUNT $ 2,230,212.9955
Due date for payment and Interest 494. Pursuant to s.26(1)(b) of the Act, I must determine when the adjudicated
amount is payable by the Respondent pursuant to s.15 of the Act.
495. The Claimant submits that the due date for payment was 24 March 2010.
496. The Respondent made no submissions on the matter.
497. Payment terms are contained within clause 37.2 of the contract. However,
for the reasons I have already expressed, clause 37.2 of the contract does
55 The Adjudicated amount must be read subject to my remarks in paragraph 491 herein
Page 92
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 92
not provide for instances where the Superintendent has not issued a progress
certificate. In the premises, I am satisfied that the statutory provisions apply
namely, pursuant to s.15(1)(b) payment was due 10 business days after the
Payment Claim was served.
498. The Payment Claim was served on 10 March 2010. Therefore, the due
date for payment was 24 March 2010.
499. Section 26(1)(c) of the Act provides that I must also decide the rate of
interest payable on any amount.
500. When determining the rate of interest payable on the unpaid amount of a
progress payment that has become payable, reference must be had to
s.15(2) and where applicable s.15(3) of the Act.
501. Those provisions provide:
“(2) Subject to subsection (3), interest for a construction Contract is payable on the unpaid amount of a progress payment that has become payable at the greater of the following rates— (a) the rate prescribed under the Supreme Court Act 1995,
section 48(1) for debts under a judgment or order; (b) the rate specified under the Contract.
(3) For a construction Contract to which Queensland Building Services Authority Act 1991, section 67P applies because it is a building Contract, interest is payable at the penalty rate under that section.”
502. The Claimant submits that the contract was a “building contract” within the
meaning of that term in Part 4A of the QBSA Act.
503. The Respondent made no submissions on the issue.
504. I am satisfied that the contract falls within the definition of a “building
contract” as defined in s.67A of the QBSA Act because the works are
Page 93
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 93
classified as “building work” as defined in Schedule 2 of the QBSA Act.
Therefore, I find that s.67P(3)(a) of the QBSA Act and correspondingly,
s15(3) of the Act applies.
Costs
505. Pursuant to s.34(3)(a) of the Act, the Claimant and Respondent are jointly
and severally liable to pay the fees of the ANA.
506. Pursuant to s.34(3)(b) of the Act, each party is liable to contribute to the
payment of the ANA’s fees in equal proportions unless otherwise decided by
me.
507. Pursuant to s. 35(2) of the Act, the Claimant and Respondent are jointly
and severally liable to pay the adjudicator’s fees and expenses.
508. Pursuant to s.35(3) of the Act, the Claimant and Respondent are each
liable to contribute to the payment of the adjudicator’s fees and expenses in
equal proportions unless otherwise decided by me.
509. Therefore, ss.34(3)(b) and 35(3) of the Act provide me with a discretion to
decide the proportion that the Claimant and the Respondent are liable to
contribute to the payment of the ANA’s fees and my fees and expenses.
510. In this case, the Claimant has been forced to make an application to
recover monies owing under the contract. The Claimant has been relatively
successful in its Application, although the respondent has managed to “claw
back” a not insignificant part of the claimed amount. I was greatly assisted in
my decision of what was a complex and difficult application by the well
prepared material and submissions of both parties’ lawyers for which I am
grateful.
Page 94
Adjudication Application Number: 1057877_1453 Claimant: Simcorp Developments and Constructions Pty Ltd Respondent: Gold Coast Titans (Property) Pty Ltd ATF Gold Coast NRL Property Trust Adjudicator: Andrew Wallace Page 94
511. On balance however, I believe this is an appropriate matter for me to
exercise my discretion. Taking all of the facts and circumstances surrounding
this Application into account, I decide that the Respondent is 75% liable and
the Claimant is 25% liable for the payment of the ANA’s fees and the
Adjudicator’s fees and expenses pursuant to ss.34 and 35 of the Act.
Mr Andrew Wallace, Adjudicator
14 May 2010
Page 95
Resoluing Bulldtng and CoflstrucUon l)tsPures
FffiTO:
CC:
TO:
CC:
FROM:
DATE:
SUBJEGT:
NO OF PAGES:
URGENT FAXSawford Voll Lawyers IAttn: Crystal Ray07 323|J Z52S
Simcorp Developments and Constructions Pty LtdAttn: Alex Simpson07 5569 2453
Nyst LawyersAttn: Ashley Tiplady07 s57r 0949
Gold Coast Titans (Property) Pty Ltd as trustee for GoldCoast NRL Propefty TrustAttn: Michael Searle07 5581 0199
' Lorraine Djuricin
23 Apri l 2010
Adjudication Application 1057877 -L453 - SimcorpDevelopments and Constructions Pty Ltd and Gold CbastTitans (Property) Pty Ltd as trustee for Gold Coast NRLProperty Trust
2 (inc cover sheet)
MESSAGE:
Dear Madam and Sir
We refer to the above mentioned matter and acknowledge receipt of correspondencefrom Nyst Lawyers dated 22 April 2010, We confirm the correspondence was forwardedthe Adjudicator, Andrew Wallace.
The Adjudicator makes the following comments: .i
"I am in receipt of correspondence from the Respondent's solicitors dated 22 April2010. In that correspondence, I am advised that an Application for declaratoryand injunctive relief has been made to the Supreme Court seeking certain ordersregarding the validity of the Payment Claim and the Adjudication Application. Iam told that his Honour Douglas J's decision has been reserved.
I am cognisant of the costs involved in such an application and the costs.involvedin the adjudication process and in my view I am satisfied that it is appropriate
ADJUDICATE TODAY PTY LTD ABI{ 39 109 605 O21Level lE, 333 Ann Street BRISBANE QLD 4O0O
"n "" "i l'"?uo i'l%3?i,;'lxaf'""1 7 60 22o
The information Contrlned In thls f!3clmll€ message and any atta€hed docum€nt3 may bc confldcntial lnformation' and may also b€
iir" "uoti.i "f
rccat professionii piiritlge, tf you are_ not the intended re.lplent, any u3e, dlaclotule ol coeviry- ?f_tl{t-f:sclmlle 13-'' - - - 'tjnauthoiisjO. ft you have recelved tli,ls fascimlle In error, please notify the sender lmmedlatcly on 1300 760 297
Page 96
that the adjudication process be "suspended" unti l such t ime as his Honourmakes a decision on the merits of the application before him, although I note thatno interim injunction appears to have been made which would otherwise restrainme from making my decision. I have made that decision on the basis that theRespondent's solicitors have sought agreement from the solicitors acting for theClaimant and that "they (Sawford Voll Lawyers) have responded that their clientwil l be guided by any request for an extension of t ime made by the adjudicator,"
In that regard and relying on the information contained in the solicitors for theRespondent's correspondence dated 22 April2010, I urgently seek the partiesagreement in writing to the following request for an extension of time to makemy decision, pursuant to s.25(3)(b) of the Building and Construction IndustryPayments Act 2004:
Unless a further extension of time is granted by the parties, which extension shallnot be unreasonably withheld, my decision shall be due on or before 15 businessdays after the date of the Claimant providing me with a copy of Douglas J'sdecision in the application for declaratory and injunctive relief in the event thathis Honour upholds the validity of the Adjudication Application and Payment Claim1 3 .
I have specifically stated "Unless a further extension of time is grant'ed by thepart ies, which extension shall not be unreasonably withheld .. ." because, as I amsure the parties would understand, I cannot lay in wait for his Honour's decisionand immediately drop al l of my other work commitments i f a decision is made infavour of the Claimant. I t is l ikely that I wil l be able to complete the decision inthe 15 business days, but of course I cannot be restrained from accepting otherapplications and briefs in the meantime.
I require the parties' consent to the abovementioned timeframes by no later than12:0O midday 27 APrilzOtO."
Thank you for your cooperation,
ADJUDICATE TODAY PTY LTD ABN 39 109 605 O21Level 18,333 Ann Street BRISBANE QLD 4OO0
Phone: 13OO 760 297' Fax: 13OO 760 22OEmai l : q [email protected]
The informltlon contained h thls fascimile message and any attach€d documents may be confidential Information, and may also be-iir"
"uOi".i of r"gal proressionai piiuii"s.. rf wu_".€_ n?l tlre Intended reclpl€nt, any us€, dlsclosure or copvlng ol this fascimile i8
unauthoris€d, rr yo, tti Je iecejved ttits tascimlle in error, plcase notify the sender immedaately on 1300 760 297
Yours sincere
Page 97
ANNEXURE BGMP Claim Date of Claim Amount of Claim
Scheduled Amount
Amount Paid by Respondent
Adjudicated Amount
1 7 January 2009 1,984,483.15$ N/A 1,029,560.58$ 1,029,560.58$ 2 30 January 2009 853,681.02$ 853,681.02$ 853,681.02$ 3 22 March 2009 937,925.71$ 937,925.71$ 937,925.71$ 4 29 May 2009 1,167,608.20$ N/A 533,135.39$ 1,167,608.20$ 5 2 July 2009 1,485,257.40$ N/A 708,275.56$ 1,485,257.40$ 6 30 July 2009 1,220,227.47$ N/A 1,109,297.70$ 1,220,227.47$ 7 2 September 2009 1,783,887.63$ 1,877,777.00$ 1,621,716.03$ 1,783,887.63$ 8 30 September 2009 1,107,827.60$ 1,166,133.00$ 965,015.59$ 1,107,827.15$ 9 29 October 2009 1,677,050.10$ 1,834,076.00$ 1,494,500.00$ 1,677,050.10$
10 1 December 2009 1,297,334.80$ 1,391,976.00$ 1,149,395.00$ 1,297,334.80$ 11 21 December 2009 1,179,429.54$ Not known 1,072,209.00$ 1,179,429.54$
DECVAR 17 December 2009 307,097.38$ Not known 198,000.00$ 198,000.00$ 12 27 January 2010 901,249.66$ 948,682.00$ 819,318.00$ 901,249.66$
Totals 15,903,059.66$ 12,492,029.58$ 14,839,039.26$
Page 98
ANNEXURE C
Original Claimed Amount
Amended Claimed Amount
Scheduled Amount
Amount Allegedly
Paid By CBA
Amount Allegedly Paid By Titans
Adjudicated Amount
Amount found to have been paid to date
1
Structural steel to pool roof $ 26,160.75 26,160.75$ 20,000.00$ 26,160.00$ $26,160.75 $26,160.00
2
Changes to fitout of Ground Floor and Level 1 $ 153,052.35 153,052.35$ 120,000.00$ 153,052.00$ $137,747.12 $153,052.00
3
Mosaic tiles to exterior pool wall $ 14,878.50 14,878.50$ 14,878.00$ 14,878.00$ $14,878.50 $14,878.00
4
Otis lift storage costs $ 14,500.00 14,500.00$ 14,500.00$ 14,500.00$ $14,500.00 $14,500.00
5
Steel support frames to pool sunshading $ 3,444.90 4,345.00$ 4,345.00$ 4,345.00$ $4,345.00 $4,344.90
6
Power reticulation to pool equipment $ 7,507.50 7,507.50$ 7,507.00$ 7,507.00$ $7,507.50 ?
7 deleted
8
Pool tiles upgrade from original allowance $ 80,000.00 64,500.00$ 64,500.00$ 64,500.00$ $64,500.00 ?
Variation
Page 99
9Cabinet work and joinery $ 171,490.00 70,205.00$ 70,205.00$ 70,205.00$ $70,205.00 ?
10
Anti graffiti coating to mosaic tiles $ 1,188.00 1,188.00$ 1,188.00$ 1,188.00$ $1,188.00 ?
11 deleted
12Roof plant area screen $ 7,109.98 3,300.00$ 3,300.00$ 7,110.00$ $3,300.00 $7,180.00
13Pool plant area fence $ 4,889.50 2,200.00$ 2,200.00$ 2,200.00$ $2,200.00 ?
14 deleted
15
Deletion of partitions to Level 2,3,4 20,235.00-$ 20,235.00-$ -$20,235.00
16
Additional Aircon to Level 4 $ 5,159.00 5,159.00$ 4,690.00$ 4,690.00$ $5,159.00 ?
17
Extra height windows to southside $ 2,486.00 2,486.00$ -$ 2,486.00$ $2,113.10 $2,486.00
18Pool ceiling flashing $ 1,064.80 1,064.00$ -$ 1,065.00$ $1,064.00 $1,064.00
19Window W126 $ 11,462.00 11,462.00$ 8,000.00$ 11,462.00$ $11,462.00 $11,462.00
20 Tiled foyer $ 15,000.00 13,870.00$ 13,870.00$ 13,870.00$ $13,870.00 ?
21
Additional plumbing works $ 47,433.00 38,385.00$ 10,985.00$ 38,385.00$ $38,385.00 $38,385.00
22
Additional power to server room $ 1,403.60 1,403.60$ 1,160.00$ 1,160.00$ $1,276.00 ?
23
New Aircon Ground Floor tenancy $ 29,190.00 -$ -$ -$ $0.00 $0.00
Page 100
24
Fitting security strikes to door frames Basement and Ground Floor $ 1,054.00 1,054.00$ 1,054.00$ 1,054.00$ $1,054.00 ?
25
Multi coloured concrete to driveway and parking area -$ -$ $0.00 $0.00
26
Alternations to kitchen Level 1 $ 11,605.00 10,444.50$ 8,124.00$ 6,000.00$ $8,124.00 ?
27Cafe alterations $ 21,294.00 17,652.60$ 11,000.00$ 9,000.00$ $14,710.50 ?
28
Power and data to L5, fibre optoic to Level 1 and Ground $ 23,190.00 19,711.50$ 10,753.00$ 10,753.00$ $11,595.00 ?
29
Reception desk, wall and floor $ 4,495.00 4,495.00$ 4,495.00$ 3,173.00$ $4,495.00 ?
30 Carpet to L5 $ 29,100.00 -$ -$ $0.00
31
Cafe wall and concrete floor $ 12,000.00 4,700.00$ 3,700.00$ 2,700.00$ $4,700.00 ?
32 Deleted $0.00
33Lighting to Level 5 $ 6,215.00 5,282.75$ 3,390.00$ $3,729.00 $0.00
Page 101
34
Partitions and flush ceiling to Level 5 $ 34,004.00 29,923.53$ 22,103.00$ $25,503.00 $0.00
35
Media centre power and special cabling $ 12,336.50 10,979.49$ 6,600.00$ $10,979.49 $0.00
36
Airconditioning to altitude room $ 4,380.00 4,380.00$ 3,504.00$ $4,380.00 $0.00
37
reception and cafe stone facing $ 15,900.00 -$ -$ $0.00 $0.00
38Lay cafe floor tiles $ 1,912.00 1,816.40$ 1,338.00$ $1,816.40 $0.00
39
Door hardware Level 5 $ 3,690.75 1,845.38$ -$ Not Valued
40
Fitting security strikes to door frames Level 5 $ 363.00 363.00$ -$ $363.00 $0.00
41
Sanitary fixture supply to Level 5 ensuite $ 12,917.00 -$ -$ $0.00 $0.00
42
Painting Level 5, media room and Ground Floor foyer $ 37,300.00 3,800.00$ 3,800.00$ $3,800.00 $0.00
Page 102
43 Deleted
44
Glazed partitions to Level 5 $ 46,950.00 4,695.00$ 940.00$ $940.00 $0.00
45New light to Md office $ 990.00 495.00$ -$ $495.00 $0.00
46
Wall to conceal pipes in strapping room $ 295.00 295.00$ 295.00$ $295.00 $0.00
47
Wall to conceal pipes in Level 1 $ 185.00 185.00$ 185.00$ $185.00 $0.00
48Dwarf wall to cafe $ 925.00 925.00$ 740.00$ $925.00 $0.00
49Fire columns to Level 5 $ 1,295.00 1,295.00$ 55.00$ $1,295.00 $0.00
50
Fire rate steel wall Level 5 $ 1,325.00 1,325.00$ -$ $1,325.00 $0.00
51
Altitude room access panel and light boxes $ 1,490.00 1,490.00$ 745.00$ $1,490.00 $0.00
52
Additional partition works $ 1,905.00 1,905.00$ -$ Not valued
53
Altitude room duct, bulkhead, ply ceiling $ 550.00 550.00$ 55.00$ $550.00 $0.00
Page 103
54
WG12 highlight panel $ 1,060.00 1,060.00$ -$ Not valued
55
Sauna and steam room doors and highlights $ 10,026.00 10,026.00$ -$ $9,026.00 $0.00
56
Glazing to head trainer office $ 4,260.00 600.00$ 600.00$ $600.00 $0.00
57Gym storage room doors $ 6,357.00 5,157.00$ -$ Not valued
58
Double glazing to media and production rooms $ 7,043.00 7,043.00$ -$ Not valued
59Glazed infills to office $ 500.00 -$ -$ $0.00
60 Deleted61 W102 $ 19,332.00 19,332.00$ -$ $19,332.00 $0.00
62Spa spandrel change $ 527.00 527.00$ -$ Not valued
63Trim to altitude room $ 800.00 800.00$ -$ $800.00
64Glass partition $ 520.00 -$ -$ $0.00 $0.00
65
Concrete plinth in basement $ 2,392.00 2,392.00$ 2,392.00$ $2,392.00 $0.00
Page 104
66
Level 5 kitchen changes $ 2,770.00 -$ -$ $0.00 $0.00
67 Pool fence $ 2,414.50 -$ -$ $0.00 $0.00
68
Changes to backpack cabinet $ 1,800.00 1,800.00$ 1,800.00$ $1,800.00 $0.00
69Doors for Level 5 $ 12,229.97 9,263.18$ -$ $9,263.18 $0.00
70
Additional plumbing changes $ 47,181.82
70 (a)600 bend for stormwater 318.00$ 200.00$ $318.00 $0.00
70 (b)Changes to L5 ensuite 1,941.00$ -$ $1,941.00 $0.00
70 (c)Greasetrap upgrade -$ -$ $0.00 $0.00
70 (d) Cafe works -$ -$ $0.00 $0.00
70 (e)
Level 5 kitchen works 8,000.00$ 5,000.00$ $8,000.00 $0.00
70 (f)
Hot water pipes to L1 bar and cafe 11,000.00$ 3,000.00$ $11,000.00 $0.00
71Additional pool works $ 35,242.73
71 (a) Extra footing 2,000.00$ -$ $2,000.00 $0.00
71 (b)Engineer inspection 436.00$ -$ $0.00 $0.00
71 (c)Foam replacement 5,345.00$ -$ $0.00 $0.00
71 (d)Extra pipe work 636.00$ -$ $636.00 $0.00
Page 105
71 (e)
Extra booster pump 4,000.00$ -$ Not valued
71 (f)Tile transport cost 4,451.00$ -$ Not valued
71 (g)Expansion joint 1,000.00$ -$ Not valued
71 (h)Depth marker 800.00$ 800.00$ $800.00 $0.00
71 (i)Colour match grate 773.00$ -$ $773.00 $0.00
71 (j)Cut tiles around lights 391.00$ -$ $391.00 $0.00
71 (k) Extra tiles 1,865.00$ -$ Not valued
71 (l)Hot water lines 773.00$ -$ $773.00 $0.00
71 (m)Extra non return value 527.00$ -$ $527.00 $0.00
71 (n)Anti flow pipes 364.00$ -$ $364.00 $0.00
71 (o)38 KW heater 1,091.00$ -$ Not valued
71 (p)Extra core holes 291.00$ -$ Not valued
71 (q) Extra plinth 1,727.00$ -$ Not valued
71 (r)Hydraulic changes 8,182.00$ -$ Not valued
71 (s)Raise pools coping 591.00$ -$ $591.00 $0.00
$ 1,039,542.15 659,542.03$ 437,761.00$ 273,443.00$ 198,000.00$ $573,702.54 $273,511.90
NOTE "?" DENOTES WHERE THE AMOUNT ALLEGED TO HAVE BEEN PAID IS CONTESTED
Total