-
Page 1 of 63
REPUBLIC OF TRINIDAD AND TOBAGO
IN THE COURT OF APPEAL
C.A. No. 281 of 2008
H.C.C. No. CV2007-02224
In the Matter of the Arbitration Act Chapter 5:01, Sections 18,
19 and 32
And
In the Matter of an Application under Parts 60 and 61 of the
Civil
Proceedings Rules 1998 (as amended)
And
In the Matter of the Decision of Dr. Robert Gaitskell QC, the
Sole Arbitrator
of an Arbitration under the ICC Rules of Arbitration 1998
BETWEEN
NATIONAL INSURANCE PROPERTY DEVELOPMENT COMPANY LIMITED
Appellant
And
NH INTERNATIONAL (CARIBBEAN) LIMITED
Respondent
PANEL: A. MENDONA, J.A.
P. JAMADAR, J.A.
N. BEREAUX, J.A.
APPEARANCES: A. Newman QC, A. Ali, N. Bisram and S. Harrison
for
the Appellant
A. Fitzpatrick SC, L. Lucky-Samaroo and J. Mootoo
for the Respondent
DATE DELIVERED: 20 December 2013
I have read in draft, the judgment of Bereaux J.A. I agree with
it and have
nothing to add.
A. Mendona
Justice of Appeal
-
Page 2 of 63
I also agree.
P. Jamadar
Justice of Appeal
JUDGMENT
DELIVERED BY BEREAUX, J.A.
[1] This appeal arises out of an arbitral award in respect of a
contract between
National Insurance Property Development Company Limited (NIPDEC)
and NH
International (Caribbean) Limited (NHIC) by which NHIC was
contracted to
construct a new hospital in Scarborough, Tobago.
[2] NIPDEC challenged the award by filing these proceedings. By
its fixed
date claim filed on 26th
June 2007, it sought -
(i) an extension of time for filing its claim
(ii) an order directing the arbitrator to state a case as to the
proper construction
of clause 2.4 of the FIDIC conditions of contract
(iii) an order setting aside the award
(iv) the remission of the award to the arbitrator together with
the opinion of the
Court on the proper construction of clause 2.4.
[3] On 14th
November 2008, the judge dismissed NIPDECs claim. NIPDEC
now seeks to reverse the decision. It seeks the same orders set
out at paragraph 2.
The grounds upon which the orders are sought are that the
arbitrator erred on the
face of the award, that the arbitrator wrongly refused to state
a case for the
opinion of the court, that there was procedural mishap and that
the arbitrator
technically misconducted the proceedings.
Facts
[4] By agreement in writing dated 6th
March 2003, NIPDEC engaged NHIC to
construct the Scarborough hospital. The works were jointly
financed by the
-
Page 3 of 63
Government of the Republic of Trinidad and Tobago (GORTT) and
the Inter-
American Development Bank (IDB). The parties agreed to be bound
by the
Conditions of Contract for Construction, First Edition 1999
(International
Federation of Consulting Engineering - General Conditions (FIDIC
COC).
[5] The time frame for completion was seven hundred and thirty
(730) days
from the date of commencement of the works. The works began on
17th
March
2003. The original date of completion was 17th
March 2005. The original contract
price was in the sum of TT$118,185,069.15. When value added tax
was included
the total sum amounted to TT$135,912,829.52. Disputes arose
however and by
letter dated 24th
August 2004, addressed to the International Court of
Arbitration
(ICC), NHIC referred several areas of dispute to arbitration
pursuant to clause
20.6 of FIDIC COC.
[6] The cost of the project rose as the works were executed. By
April 2005,
the estimated contractual price was TT$286,992,070.00. This was
subsequently
adjusted by the Engineer to TT$224,129,801.99. There was some
dispute as to
the accuracy of that figure and an Independent Quantity Surveyor
was appointed
who ultimately verified the Engineers certification of the
contract price at
TT$224,129,801.99.
[7] Dr. Robert Gaitskell QC was appointed the sole arbitrator on
3rd
October
2005. The parties agreed terms of reference to the arbitration
on 1st December
2007. These were subsequently amended on 15th
January 2007. The arbitrator
published four partial awards. His fifth and final award was
published on 14th
September 2011. It is the second partial award (SPA) which is
the subject matter
of this appeal. It was given on 16th
April 2007. The arbitrator found that NHIC
was entitled to suspend the contract by its notice dated 3rd
November 2006.
[8] Clause 2.4 of FIDIC COC is extremely pertinent to this
appeal as it was to
the SPA. Its interpretation was not directly referred to
arbitration. What was
referred was the validity of NHICs suspension and subsequent
termination of the
-
Page 4 of 63
works under clause 16(1) and (2) respectively of FIDIC COC. The
validity of the
suspension was one of a list of ten items of dispute. NHICs
subsequent
termination of the contract under clause 16(2) was the fourth
item on the list. The
efficacy of that termination is dependant on whether the
suspension under 16(1)
was valid. The other eight areas of dispute are not relevant to
this appeal.
[9] By clause 16, NHIC was entitled to suspend work, or reduce
the rate of
work and to terminate the contract if NHIC did not receive
reasonable evidence,
as required by clause 2.4, within a specified period of time.
Clause 16 provides,
inter alia:
16.1 If the Engineer fails to certify in accordance with
Sub-
Clause 14.6 [issue of Interim Payment Certificates] or the
Employer fails to comply with Sub-Clause 2.4 [Employers
Financial arrangements] or Sub-Clause 14.7 [Payment], the
Contractor may, after giving not less than 21 days notice to
the
Employer, suspend work (or reduce the rate of work) unless
and
until the Contractor has received the Payment Certificate,
reasonable evidence or payment, as the case may be and as
described in the notice . If the Contractor subsequently
receives such Payment Certificate, evidence or payment (as
described in the relevant Sub-Clause and in the above
notice)
before giving a notice of termination, the Contractor shall
resume normal working as soon as is reasonably practicable
16.2 The Contractor shall be entitled to terminate the
Contract
if: (a) the Contractor does not receive the reasonable
evidence
within 42 days after giving notice under Sub-Clause 16.1
[Contractors Entitlement to Suspend Work] in respect of a
failure to comply with Sub-Clause 2.4 [Employers Financial
Arrangements]
-
Page 5 of 63
Clause 2.4 provides as follows:
The Employer shall submit, within 28 days after receiving
any
request from the Contractor, reasonable evidence that
financial
arrangements have been made and are being maintained which
will enable the Employer to pay the Contract price (as
estimated
at that time) in accordance with Clause 14 [Contract Price
and
Payment]. If the Employer intends to make any material
change
to his financial arrangements, the Employer shall give notice
to
the Contractor with detailed particulars.
On 28th
April, 2005, NHIC invoked clause 2.4. On the 31st May, 2005, on
the
basis that it had not received any reasonable evidence, it
issued a twenty one day
notice under clause 16.1, threatening to suspend/reduce
work.
[10] On the 23rd
September, 2005, NHIC suspended work under the contract,
alleging that NIPDEC was in breach of clause 2.4. On 3rd
November 2006 it gave
notice of termination of the contract pursuant to clause 16.2 on
the same ground.
Between September 2005 and November 2006, the parties appeared
to have been
in discussions aimed at securing a mutual disengagement from the
contract
pursuant to its terms. Those discussions did not bear fruit and
NHIC purported to
terminate pursuant to clause 16.2 in November 2006. NIPDEC
denied that it was
breach of clause 2.4. NIPDEC contended that its correspondence
to NHIC dated
28th
December, 2004, 29th
December, 2004, 5th
July, 2005, 6th
July, 2005, 6th
October, 2006 and 20th
October, 2006, satisfied the evidential threshold required
clause 2.4. One of the questions in this appeal is whether the
arbitrator was right
to hold that the correspondence of 5th
and 6th
July 2005, 6th
October 2006 and 20th
October 2006 did not satisfy the evidential threshold under
clause 2.4. NIPDEC
contends that he was wrong and that this is an error on the face
of the award.
[11] The arbitrator in his SPA upheld NHICs contentions that
NIPDEC did not
provide reasonable evidence that financial arrangements had been
made and were
-
Page 6 of 63
being maintained so as to enable NIPDEC to pay the contract
price. NHIC was
therefore entitled to reduce its rate of work and to suspend and
to terminate the
contract in the manner that it had.
[12] By letter dated 18th
May, 2007, (after the SPA had been made) NIPDEC
invited the arbitrator to state a special case for the courts
consideration pursuant
to section 32 of the Arbitration Act, Chap 5:01, with respect to
the proper
interpretation of clause 2.4. In its letter, NIPDEC set out
certain considerations
for the Court in respect of clause 2.4.
[13] The arbitrator, by e-mail dated the 31st May, 2007,
rejected NIPDECs
request for a case stated. In summary, he concluded as
follows:
(i) s. 32(1) and (2) do not permit a case to be stated, where a
binding
decision has already been produced on the issues in
question.
(ii) The SPA was made on 16 April, 2007 and was issued by the
ICC shortly
thereafter. NIPDECs request for a case stated was dated 18 May,
2007.
The SPA deals with questions formulated by the parties and at no
time
prior to receipt of the request did NIPDEC suggest that there be
any case
stated.
(iii) In such circumstances he was functus officio in respect of
those issues, and
did not have the jurisdiction, to state a case for the
court.
Further Submissions
[14] We reserved judgment in the appeal, on 23 November 2011. By
letter of
29th
June 2012 to the Clerk of Appeals, NHIC raised a further issue.
It alleged
that NIPDEC had abandoned the appeal because it had made an
unequivocal final
election to adopt the final award and, consequently, all awards
which had
preceded it. The final award was the product of the previous
four partial awards.
-
Page 7 of 63
The SPA forms a basis upon which the final award was made. If
NIPDEC
accepted the final award it meant that NIPDEC was no longer
interested in
pursuing its challenge to the SPA.
[15] NHIC further submitted that the unequivocal election had
come in the
form of an application by NIPDEC, filed on 23rd
February 2012, seeking to strike
out NHICs claim form in civil action, CV2011-04420. In its
affidavit in support,
NIPDEC requested that the Court enforce the final award under
section 20 of the
Arbitration Act and give judgment in terms.
[16] NHIC contends that NIPDEC by its defence, counterclaim and
affidavit in
that civil action and by its conduct in pursuing its
application, finally and
irrevocably abandoned this appeal. NHIC sought a further hearing
of the appeal.
The parties were directed to file written submissions on the
issue with which
direction they have complied. The matter now falls for
decision.
The delay in giving judgment
[17] Before dealing with the questions which arise in this
appeal, we must
apologise to the parties for the considerable delay in giving
this judgment. By the
way of explanation (as opposed to excuse) we say that, apart
from the volume of
the documents which we had to examine in this case, events
occurred, during the
course of consideration of this matter, which resulted in the
depletion of the
complement of appeal judges available to deal with an ever
increasing list of
appeals (particularly procedural appeals which must be heard
within a particular
time period). These events have been the subject of official
comment and it is
unnecessary to elaborate here. Rather than reduce the number of
appeals to be
listed for hearing, we endeavoured to increase the number of
times each judge sat
monthly. The result is that while, in fact, more appeals were
heard and
completed, the reserve time for more difficult and complicated
appeals rose.
Happily, the Court of Appeal was finally back to full complement
as at 1st
November 2013. Further administrative arrangements are also
being made to
-
Page 8 of 63
address the problem of protracted reserve time.
The issues
[18] The three broad issues in this case are:
(i) Did NIPDECs application to strike out NHICs claim in
CV2011-04420
constitute an abandonment of the appeal?
(ii) Was the judge right to refuse to direct the arbitrator to
state a special case?
(iii) Was the judge also right to refuse to remit or set aside
the award?
[19] The first issue is a straight forward question. As to the
second broad issue
the question arises as to the true purport and meaning of
section 32 of the
Arbitration Act (the Act).
As to the third broad issue several subsidiary questions
arise:
(i) Was there a procedural mishap arising out of NIPDECs failure
to request
that the arbitrator state a case for consideration by the High
Court?
(ii) Was there referral to arbitration a general or specific
reference?
(iii) Was there an error on the face of the record?
Summary of Decision
[20] (i) NIPDECs application to strike out NHICs claim in
CV2011-
04420 did not constitute an abandonment of the appeal. Its
decision to
apply to enforce the Final Award was not an irrevocable election
because
it was not faced with a choice between alternative rights. A
successful
challenge to the SPA would necessarily result in a payment to
NIPDEC of
-
Page 9 of 63
a greater sum that made under the Final Award
(ii) The judge was right to refuse to direct that the arbitrator
state a special
case because on a proper interpretation of section 32 of the
Act, it did not
contemplate the direction of a case stated after the arbitrator
had made his
award.
(iii) The judge was also right to refuse to remit the award or
to set it aside on
the basis of procedural mishap or miscarriage of justice,
because
NIPDECs failure to request that the arbitrator state a case for
the High
Court under section 32 did not result in an injustice to NIPDEC,
neither
did it constitute a deviation from the route which the reference
should
have taken toward its destination.
(iv) However, the judge fell into error in finding that the
reference to
arbitration was a specific reference. The referral of the
dispute to
arbitration was in fact a general reference. The Court is free
to review the
arbitral award and to remit it or set it aside, if there is in
fact an error on
the face of the record.
(v) There were several errors on the face of the record. The
arbitrator
committed several errors of law on the face of the record. These
were:
(a) His finding that reasonable evidence that financial
arrangements have
been made and are being maintained would ordinarily involve
prima facie
some evidence of Cabinet approval having been maintained.
(b) His finding that the letters of 5th
and 6th
July 2005 and 6th
October 2006
did not satisfy the provisions of clause 2.4.
(c) His finding that the letter of 5th
July 2005 was equivocal because of the
use of the words without prejudice.
-
Page 10 of 63
(d) His finding that the letter of 6th
October 2006 in any event did not satisfy
the 28th
April 2005 notice because it referred to a contract price
($224,129,801.99) which was lower than the contract price
($286,992,070) to which the notice related and for which
assurance of
financial arrangements were sought.
These were errors of law because:
(i) He placed too much emphasis on necessity for Cabinet
approval to satisfy
the requirement of reasonable evidence. He set the bar too high
and set
too high a standard as to the meaning of reasonable evidence in
clause
2.4.
(ii) His finding that the 6th
October 2006 letter, by its reference to the lower
contract price of $224,129,801.99, did not amount to reasonable
evidence,
was a finding to which no reasonable arbitrator could come.
Did NIPDEC abandon the appeal
[21] NHIC submits that NIPDEC by seeking to enforce judgment on
the final
award, elected to abandon this appeal. This principle of
election has a common
law and equitable element. In this case, NHIC contends that
NIPDECs election
was a common law election. At common law, election arises when a
party is
faced with two inconsistent courses of action and it elects one
of these alternative
courses over the other. The decision must be unequivocal. The
election
irrevocably binds the party making the choice. See Motor Oil
Hellas Refineries
v Shipping Corporation of India [1990] 1 Lloyds Rep 390. Lord
Goff at page
398 stated that:
it is a prerequisite of election that the party making the
election
must be aware of the facts giving rise to this new right. Where
with
-
Page 11 of 63
knowledge of the relevant facts a party has acted in a
manner
consistent only with his having chosen one of the two
alternative
and inconsistent courses of action open to him, he is held to
have
made his election accordingly. It requires an unequivocal
representation
[22] It is sufficient to show that the electing party has made
an unequivocal
representation of his decision, in circumstances in which his
knowledge of the
facts and of his legal rights allowed him to make an informed
choice and that he
communicated that decision to the other party.
[23] At paragraph 26 of his further written submissions Mr.
Fitzpatrick
submitted that the Final Award, which was based upon all the
interim awards
which preceded it, including the SPA, was produced on 14th
September 2011. At
that point NIPDEC had a choice: it could either withdraw the
current appeal
against the SPA (which was pending decision) and proceed to
enforce the Final
Award; or it could continue with the prosecution of the appeal
to decision, taking
no steps in the interim to enforce the Final Award. He relied on
the decision in
Meng Leong Development Pte Ltd. v. Jip Hong Trading Co. Pte.
Ltd. (1985)
1 ALL E.R. 120.
[24] He added that the alternative courses of action open to
NIPDEC were
entirely inconsistent with each other. A court has no power in
this jurisdiction to
affirm part and disaffirm part of an arbitral award. It must
decide whether the
award is good or whether it should go in its entirely, either by
way of setting aside
or referral. In those circumstances a party which enforces an
award cannot
afterwards be heard to say that he wishes to appeal it, for by
so doing, he would
be claiming that the award was entirely wrong, and should be set
aside or
remitted, a circumstance which would mean that he would have no
right to any
benefit thereunder.
[25] He submitted that NIPDEC by its Defence and Counterclaim
and by its
-
Page 12 of 63
affidavit filed on 23rd
February 2012 in the recent action, as well as by its
subsequent arguments before the court chose to seek an order
under section 20 of
the Arbitration Act enforcing the Final Award.
[26] In exercising its right under section 20, NIPDEC was
relying on the SPA
and was acting in a manner consistent only with having chosen
not to appeal the
SPA or to challenge any of the partial awards on which the final
award is
founded.
[27] In additional submissions filed on 26th
September 2012 Mr. Fitzpatrick
further submitted that the arbitral award can only be set aside
or remitted in its
entirety. It is indivisible. NIPDEC could not pursue the
challenges to the SPA
and the third partial award while seeking to enforce the final
award. Once the
final award had been published, any options to withdraw its
challenges to the SPA
and the third partial award were closed.
[28] I agree with Mr. Newmans submission that NIPDECs decision
to apply
to the Court to enforce the final award did not constitute an
irrevocable election.
NIPDECs conduct was not unequivocal. The challenge to the SPA,
if successful,
(as it has been) can result in (and has so resulted) in the
award being set aside and
remitted to the arbitrator with a direction that the suspension
and termination of
the award by NHIC was wrongful. Such a consequence necessarily
meant the
payment of a greater sum by NHIC to NIPDEC than that granted by
the final
award.
[29] The dictum of Lord Atkin in Lissenden v. CAV Bosch Ltd
[1940] AC
412 at 429 (helpfully cited by Mr. Newman) is apt:
The applicant is not faced with alternative rights: it is the
same
right that he claims but in larger degree. In Mills v.
Duckworth
(1), a plaintiff who has been awarded damages for negligence
had taken the judgment sum out of a larger sum paid into
Court
-
Page 13 of 63
and then had appealed against the quantum of damages and was
met by a similar objection to his appeal. Lord Fairfield in
overruling the objection pointedly said: The plaintiff said I
am
not going to blow hot and cold. I am going to blow hotter.
Here the applicant is not faced with a choice between
alternative
rights: he has exercised an undisputed right to
compensation:
and claims to have a right to more. You have not lost your
right
to a second helping because you have taken the first
[30] I do not accept that the Final Award renders the entire
award indivisible.
In my judgment a successful challenge of the SPA simply requires
the SPA to be
reconsidered by the arbitrator as directed by the Courts. It is
severable from other
partial awards.
[31] I turn then to the issues raised in the substantive
appeal.
Jurisdiction of the Court
(i) Power to Remit
[32] NIPDEC seeks to have the award set aside for error on the
face of the
record. It also seeks to have the award remitted to the
arbitrator on the ground
that there was a procedural mishap resulting in an injustice to
it. The courts
jurisdiction to remit is statutory. It is set out in section
18(1) of the Act which
provides
(1) In all cases of reference to arbitration, the court may
from time to time remit the matters referred, or any of them to
the
reconsideration of the arbitrators or umpire.
[33] The judge, following the decision of Jamadar J (as he then
was) in ICS
Grenada Limited v. NH International (Caribbean) Limited, H.C.A.
1541 of
-
Page 14 of 63
2002 accurately sets out, at paragraph 53 of her judgment the
bases upon which a
court of law will order the remission of an award to the
arbitrator. These are:
(i) Where the award is bad on its face.
(ii) Where there is misconduct on the part of the
arbitrator.
(iii) Where there has been a mistake by the arbitrator.
(iv) Where, after the award has been made, fresh evidence has
been
discovered.
[34] NIPDEC in its written submissions had contended that both
Jamadar J and
the judge had adopted a restrictive construction of section 18.
The submission is
not accurate. Like Jamadar J., the judge held that these
categories had been
extended to include situations in which there had been a
misunderstanding
leading to injustice or (as the judge opined) some procedural
mishap which led
to injustice. I agree.
[35] The latter category has been the subject of juridical
controversy. See the
comments of the authors of Mustill and Boyd, 2nd
edition 1989, at pages 549-
550 as follows:
In recent years it has been held that an award may be
remitted
if there has been a misunderstanding leading to injustice,
even
though the arbitrator has not committed misconduct. These
decisions undoubted go beyond the list set out above.
Whether
they are sustainable on the law as it now stands depends
upon
whether the list is exclusive, or whether the Court has a
general
discretion to remit whenever justice so demands, the list
furnishing no more than illustrations and guidance as to the
way
in which the Court will intervene. This question is
controversial:
there is strong authority for each view. The weight of the
existing authority is in favour of the more restricted view
[36] In Indian Oil Corporation v. Coastal (Bermuda) Ltd. [1990]
2 Lloyds
-
Page 15 of 63
Rep. 407, Evans J in considering section 22 of the English
Arbitration Act 1950
[CHECK] (the equivalent of our section 18(1)) concluded, after
some discussion,
that the power to remit an award under section 22 can and should
be
exercised when there is otherwise the likelihood of a
substantial miscarriage of
justice, either because the arbitrator has been mishandled (that
is misconduct) or
where there has been some other procedural mishap, even if the
mishap is due
to the party seeking remission. His comments, as they relate to
the law in respect
of section 22(1) bear full reproduction. He said, starting at
page 414:
The statutory power of remission is discretionary and it is
not
subject to any statutory limits. However, the discretion
although
unlimited in terms may be subject to restrictions imposed by
judicial decision (Mustill and Boyd (2nd
ed) P. 548). There have
been many decisions revealing two lines of authority, and
the
question remains controversial (Mustill and Boyd again, p.
550).
Some authorities support the view that the power may be
exercised whenever justice so demands, others the narrower
view
that the circumstances must fall within one of a number of
categories which have been recognized in past judgment of
the
Courts (ibid).
According to Russell on Arbitration (19th
and 20th
eds.):
there is a never-ending war between two irreconcilable
principles, the high principle which demands justice though
the
heavens fall, and the low principle which demands that there
should be an end to litigation.
I must admit that I do not read the authorities in this way.
True,
the power should not be exercised unless the failure to do
so
would or might cause injustice to the applicant: compare The
Aros, [1978] 1 Lloyds Rep. 456 at p. 463 per Mr. Justice
-
Page 16 of 63
Brandon. But at the same time it is of over-riding
importance
that the finality of awards hall be preserved which, on any
view
of the matter , imposes severe restraints on the exercise of
the
statutory power: per Sir Roger Ormrod in The Montan, [1985]
1
Lloyds Rep. 189 at p. 198.
These two factors, in my view, are not inconsistent with
each
other. If either of them is to prevail, then it should be
the
requirement of justice. But justice, even fairness, is not
an
abstract concept. It has to be applied in this context between
two
parties who were in dispute with each other and who agreed
that
the dispute should be resolved by an arbitral tribunal. They
agreed that the tribunals award should be final. But they
agreed
this on the basis that the arbitration procedures would be
regulated by law. The Court has statutory power to set aside
an
award when the arbitrators misconduct themselves or the
reference - s. 25 of the 1950 Act - but it also has to
unqualified
discretion to remit the award to the chosen tribunal under s.
22.
If the power is exercised, but only in circumstances when it
would be unjust not to do so, then there is not, in my
judgment,
an uncovenanted nor an unacceptable restriction on the
agreed
finality of the tribunals award. As Lord Atkin said in a
different
context, recently cited with approval by the Court of Appeal
(Criminal Division) Finality is a good thing, but justice is
better. (Ras Behari Lal v. The King-Emperor, (1933) 50
T.L.R.1).
It remains, of course, a matter for judicial decision whether
such
injustice exists, or would exist, in the particular case, and in
the
nature of things previous cases will provide examples of the
circumstances in which it can be recognized. In addition,
some
judgments will be binding on inferior Courts whenever the
same
-
Page 17 of 63
or indistinguishable facts arise again. So far as binding
authority is concerned, the extent of the jurisdiction arose
for
consideration in The Montan (above) and Sir John Donaldson,
M.R. said this (at p. 192):
Section 22 empowers the Court to remit an award to an
arbitrator
for reconsideration. It provides the ultimate safety net
whereby
injustice can be prevented, but it is subject to the
consideration
that it cannot be used merely to enable the arbitrators to
correct
errors of judgment, whether on fact or law, or to have
second
thoughts, even if they would be better thoughts.
Lord Justice Robert Goff, agreed that the award in that case
should be remitted, and Sir Roger Ormrod at p. 198, in the
passage already referred to, said that the section preserved
the
power to order remission:
if the interest of justice demanded and the circumstances
permitted.
I respectfully agree with these descriptions of the Courts
power,
and I would probably be bound to adopt them, even if I did
not.
It would be unusual if the unqualified statutory discretion
was
limited by decisions in previous cases, binding precedent
apart,
and it would be surprising if the statutory power is so
encrusted
(the apt word used in argument in the present case) by
judicial
statements that it cannot be exercised when justice so requires.
I
must respectfully dissent, therefore, from the conclusion
reached
in The Apollon, [1985] 1 Lloyds Rep. 597, that there is only
power to order remission on one of the four grounds listed by
the
Court of Appeal in 1898 (quoted in Mustill & Boyd p. 549)
or
otherwise when a further category has been expressly
recognized
-
Page 18 of 63
by the Courts.
[37] In MF King v. Thomas McKenna Ltd. [1991] 2 W.L.R. 1234
Lord
Donaldson of Lymington, MR added his voice to the view that the
jurisdiction of
the Court under section 22(18) was unlimited. He stated at 1241
(under the
rubric scope of the power to remit):
In ascertaining the limits of the court's jurisdiction, properly
so
called, I see no reason why section 22 and the other
sections
should not be construed as meaning what they say. Certainly
so
far as section 22 is concerned, there is no element of doubt
or
ambiguity. The jurisdiction is wholly unlimited.
[38] Later at page 1243 letter A he added:
In my judgment the remission jurisdiction extends beyond the
four traditional grounds to any cases where, notwithstanding
that
the arbitrators have acted with complete propriety, due to
mishap
or misunderstanding, some aspects of the dispute which has
been
the subject of the reference has not been considered and
adjudicated upon as fully or in a manner which the parties
were
entitled to expect and it would be inequitable to allow any
award
to take effect without some further consideration by the
arbitrator. In so expressing myself I am not seeking to define
or
limit the jurisdiction or the way in which it should be
exercised in
particular cases, subject to the vital qualification that it
is
designed to remedy deviations from the route which the
reference
should have taken towards its destination (the award) and not
to
remedy a situation in which, despite having followed an
unimpeachable route, the arbitrators have made errors of fact
or
law and as a result have reached a destination which was not
that which the court would have reached. This essential
-
Page 19 of 63
qualification is usually underlined by saying that the
jurisdiction
to remit is to be invoked, if at all, in relation to
procedural
mishaps or misunderstandings. This is, however, too narrow a
view since the traditional grounds do not necessarily
involve
procedural errors. The qualification is however of
fundamental
importance. Parties to arbitration, like parties to litigation,
are
entitled to expect that the arbitration will be conducted
without
mishap or misunderstanding and that, subject to the wide
discretion enjoyed by the arbitrator, the procedure adopted
will
be fair and appropriate. What they are not entitled to expect of
an
arbitrator any more than of a judge is that he will
necessarily
and in all circumstances arrive at the "right" answer as a
matter
of fact or law. That is why there are rights of appeal in
litigation
and no doubt would be in arbitration were it not for the fact
that
in English law it is left to the parties, if they so wish, to
build a
system of appeal into their arbitration agreements and few
wish
to do so, preferring "finality" to "legality," to adopt Lord
Diplock's terminology.
These decisions have since been eroded by the repeal of the 1950
Act and by the
case law deriving from the new legislation. They remain apposite
to section 18
and reflect what is the appropriate approach to its
application.
(ii) The courts power to set aside
[39] As the judge stated at paragraph 72 of her judgment, the
Courts of
Trinidad and Tobago have both an inherent jurisdiction and a
statutory
jurisdiction to set aside an arbitral award. The statutory power
to set aside (as set
out in section 19(2) of the Act) arises where the arbitrator has
misconducted
himself or the proceedings, or, where an arbitration or an
arbitration award, has
been improperly procured. The courts inherent jurisdiction to
set aside arises
where:
-
Page 20 of 63
(i) there is an error on the face of the award
(ii) the award is made in excess of jurisdiction, whether wholly
or partly
(iii) there is a patent substantive defect.
See Mustill and Boyd - second edition - The Law and Practice of
Commercial
Arbitration at page 91.
[40] As noted by Jamadar J in ICS:
The inherent power of the court to set aside an award was
given
statutory recognition by section 3 of the local Act (section 1
of the
1889 UK act). The situation is well summarised in Commercial
Arbitration by Mustill and Boyd (1989 ed.) at page 447,
where
the authors state:
As regards the inherent powers of the Court,
section 1 of the 1889 Act provided that all
submissions should, unless a contrary intention
was expressed thereon, take effect as if they had
been made an order of court. The effect was thus
to bring virtually all references under the direct
and continuous supervision of the Court, which
would exercise powers by virtue of its own
inherent right of control, quite distinct from the
statutory powers to intervene by setting aside and
remission.
Thus, all voluntary references to arbitration attracted the
courts
inherent powers of enforcement and supervision.
The courts discretion to remit or aside an arbitral award is
also circumscribed by
the nature of the dispute. The court will refuse to remit or to
set aside the award if
what is referred is a specific question of factor law or some
principle of
construction for the determination of the arbitrator. This is so
even if the error is
-
Page 21 of 63
clear on the face of the award. Neither will the award be
remitted or set aside
because the court disagrees with the conclusion to which the
arbitrator came,
unless of course it is clear on the face of the award that the
arbitrator has
proceeded illegally. Two leadings cases fall to be considered
here. Kelantan
Government v. Duff Development Co. [1923] A.C. 395 and F.R.
Absalom Ltd.
v. Great Western (London) Garden Village Society [1973] A.C.
592.
[41] In Kelantan, the Government of Kelantan granted to an
English company
certain portion of State lands and certain mining rights, by a
deed of indenture. A
dispute as to the construction of the deed was referred to
arbitration (as provided
for by the deed). The arbitrator decided against the Government.
A motion to set
aside his award was refused by Russell J and by the Court of
Appeal. The
Government appealed to the House of Lords which affirmed the
decision of the
Court of Appeal. Viscount Cave at page 408 stated:
it is desirable to refer to a question which was mentioned
(though not decided) in the judgments of the learned judges
of
the Court of Appeal and which was again raised in the
argument
before this House - namely, the question whether there was
not
here such a reference to the arbitrator on the construction of
the
deed of cancellation that his conclusions on that point must
be
accepted as final and not open to be questioned on application
to
the Court. My Lords, in my opinion there was in this case a
reference to the arbitrator of the questions which had arisen
on
the construction of the deed of cancellation. The
arbitration
clause in the deed applied in terms to every dispute, difference
or
question which might arise between the parties touching the
"construction, meaning, or effect" of the deed. The
appointment
of the arbitrator showed that differences had arisen as to
construction, and the arbitrator was appointed to determine
those
differences. In the pleadings delivered in pursuance of the
arbitrator's direction, the questions of construction were
again
-
Page 22 of 63
clearly raised. Lastly, the appellants in their case delivered
for
the purpose of this appeal (para. 13) stated that among the
points
to be determined by the arbitrator were: "(1.) What, upon
the
true construction of the Deed of Cancellation, was the
nature
and extent of the obligation of the Government in regard to
the
making of the cart road? (2.) Whether, upon the true
construction of the Deed of Cancellation, the Government had
entered into a covenant with the Company to construct the
railway, and if so, in what terms, and what was the nature
and
extent of the obligation of the Government under such
covenant?" The reference, therefore, was a reference as to
construction.
If this be so. I think it follows that, unless it appears on the
face
of the award that the arbitrator has proceeded on principles
which were wrong in law, his conclusions as to the
construction
of the deed must be accepted. No doubt an award may be set
aside for an error of law appearing on the face of it; and
no
doubt a question of construction is (generally speaking) a
question of law. But where a question of construction is the
very
thing referred for arbitration, then the decision of the
arbitrator
upon that point cannot be set aside by the Court only because
the
Court would itself have come to a different conclusion. If
it
appears by the award that the arbitrator has proceeded illegally
-
for instance, that he has decided on evidence which in law
was
not admissible or on principles of construction which the
law
does not countenance, then there is error in law which may
be
ground for setting aside the award; but the mere dissent of
the
Court from the arbitrator's conclusion on construction is
not
enough for that purpose.
-
Page 23 of 63
At page 410 he said:
To the same effect are the decisions of this House in Holmes
Oil Co. v. Pumpherston Oil Co. (4) and of the Judicial
Committee of the Privy Council in Attorney-General for
Manitoba v. Kelly (5); and in In re King and Duveen (6)
Channell J. stated the rule concisely as follows: "It is no
doubt a
well-established principle of law that if a mistake of law
appears
on the face of the award of an arbitrator, that makes the
award
bad, and it can be set aside ...., but it is equally clear that
if a
specific question of law is submitted to an arbitrator for
his
decision, and he does decide it, the fact that the decision
is
erroneous does not make the award bad on its face so as to
permit of its being set aside. Otherwise it would be futile ever
to
submit a question of law to an arbitrator.
[42] Lord Parmoor at page 417 put the issue the other way:
Where a question of law has not specifically been referred to
an
umpire, but is material in the decision of matters which
have
been referred to him, and he makes a mistake, apparent on
the
face of the award, an award can be set aside on the ground that
it
contains an error of law apparent on the face of the award
He added at page 418 that:
In the present appeal it was argued by the counsel on behalf
of
the appellants that the question of the construction of the
deed
had not been specifically referred to the arbitrator, although
the
construction of the deed was absolutely necessary for the
determination of the disputes which had been referred to him.
In
my opinion this contention is not maintainable. Whether,
-
Page 24 of 63
however, a question of law has been specifically submitted
to
arbitration, falls in each case to be determined on the terms
of
the particular submission. If the Court, before which the
award
is sought to be impeached, comes to the conclusion that the
alleged error in law, even if it can be maintained, arises in
the
decision of a question of law directly submitted to the
arbitrator
for his decision then the principle stated by Channell J. in In
re
King and Duveen (2) applies, and the parties having chosen
their
tribunal, are not in a position to question the award, or to
claim to set it aside.
[43] F.R. Absalom Ltd. v. Great Western (London) Garden Village
Society
[1993] AC 592 was a decision which went the other way. The facts
bear
repetition because they are comparable to this case and raise a
similar legal issue.
A building contract provided by clause 30 that:
The contractor shall be entitled .... under certificates to be
issued
by the architect to the contractor .... to payment by the
employer
from time to time by instalments, when in the opinion of the
architect actual work to the value of 1000l. has been executed
in
accordance with the contract, at the rate of 90 per cent. of
the
value of the work so executed in the building and materials
actually on the site for use on the works until the balance in
hand
amounts to the sum of 2000l.
[44] The contract also provided that if any dispute should arise
between the
employer, or the architect on his behalf, and the contractors as
to the construction
of the contract or as to the withholding by the architect of any
certificate to which
the contractors might claim to be entitled, the dispute was to
be referred to an
arbitrator. By clause 26, if the contractors should suspend the
work, except in
case of a certificate being withheld, the architect was
empowered to give notice to
the contractors to proceed with the work with all reasonable
dispatch. Disregard
-
Page 25 of 63
of this notice might involve the contractors in serious
consequences.
[45] After 9000l. or more had been paid by the employers to the
contractors
upon certificates given by the architect, the contractors
claimed that on March 11,
1929, they were entitled to a further substantial sum which had
not been included
in the architect's certificates. The employers insisted that the
contractors had been
overpaid, and that no certificate was due to them. The
contractors thereupon
stopped work, and the architect served upon them a notice under
clause 26.
[46] The parties then submitted to an arbitrator the disputes in
regard to (1)
the issue of certificates and (2) the validity of the notice
served by the architect
under clause 26 of the contract. The arbitrator found that on
May 11, 1929, there
remained due to the contractors a sum of 793l. 17s. 10d., and
awarded that
having regard to the provisions of clause 30 the architect had
up to the said
11th day of March, 1929, issued to the contractor certificates
in accordance with
the terms of the contract. He further awarded that the notice
given under clause
26 was properly given and was valid.
[47] It was held that the construction of clause 30 had not been
specifically left
to the arbitrator and the award should be set aside for error of
law appearing on
the face of it because he erred in his construction of clause
30. Lord Russell of
Killowen in his speech at page 607 stated:
My Lords, it is, I think, essential to keep the case where
disputes
are referred to an arbitrator in the decision of which a
question
of law becomes material distinct from the case in which a
specific
question of law has been referred to him for decision. I am
not
sure that the Court of Appeal has done so. The authorities
make
a clear distinction between these two cases, and, as they appear
to
me, they decide that in the former case the Court can interfere
if
and when any error of law appears on the face of the award,
but
that in the latter case no such interference is possible upon
the
-
Page 26 of 63
ground that it so appears that the decision upon the question
of
law is an erroneous one.
At page 608 he said:
The same distinction appears in the judgment of the Privy
Council in the case of Attorney-General for Manitoba v.
Kelly
(3), in which the following passage occurs: "Where a question
of
law has not specifically been referred to an umpire, but is
material in the decision of matters which have been referred
to
him, and he makes a mistake, apparent on the face of the
award,
an award can be set aside on the ground that it contains an
error
of law apparent on the face of the award.
[48] Mr. Newman, for NIPDEC submitted the distinction between
general and
specific is far too narrow a distinction. The focus in modern
cases (none of which
he cited) was to permit a review if there is shown, an error of
law on the face of
the award even if the award under review was in respect of a
specific reference to
arbitration. He added that an error of law can be shown, he
said, even where there
is a mixed question of law and fact. When one is looking at an
error of law on the
face of the award, the focus is not on the general (or generic)
but rather on the
specific. He submitted that this was the slightly more modern
approach. He
described the Kelantan decision as having adopted a more
rigorous approach to
the question of general versus specific references. Where there
is an error of law
on the face of the award it is reviewable even though it is a
specific referral to the
arbitrator. I have found no authority which supports this
approach. Suffice it to
say therefore that I shall continue to follow the more
restrictive approach.
I turn then to the issues in this case.
Conclusions
(a) Whether the award should be remitted to the arbitrator
-
Page 27 of 63
(i) Failure to request a case stated
[49] It is unclear from the written submissions whether NIPDEC
was still
challenging the arbitrators decision not to state a special case
for the
court, pursuant to section 32 of the Act. But it still relies on
its full written
submissions before the judge. Moreover, Mr. Newman addressed
the
matter in argument before us. He submitted that section 32 of
the Act
permitted an arbitrator to state a question in the form of a
special case after
an award is given. The relevant provisions of section 32 state
as follows:
(1) An arbitrator or umpire may, and shall if so
directed by the Court, state -
(a) any question of law arising in the course of the
reference, or
(b) an award or any part of an award
in the form of a special case for the decision of the Court.
(2) A special case with respect to an interim award or
with respect to a question of law arising in the
course of a reference may be stated, or may be
directed by the Court to be stated, notwithstanding
that proceedings under the reference are still
pending.
(3)
[50] He added that there is nothing in the wording in section 32
which provides
that the application to state a special case must be made before
the award is given.
Rather, it was a matter of judicially imposed restrictions in
the interpretation of
the statute. But those restrictions have been loosened as time
has gone on. He
added that in this case the judge adopted a restrictive view. If
this Court took a
restricted view of section 32, (i.e. by saying that section 32
does not contemplate
a special case being stated after the award has been made) then
there was a
procedural mishap. If it took a more expansive view, then there
is jurisdiction to
-
Page 28 of 63
remit the matter back to the arbitrator on the basis of an error
law on the face of
the award.
[51] I return to the issue of procedural mishap at paragraph 53
below. The
judge found that the request to state a special case came too
late. She held that the
arbitrator was functus officio in relation to the SPA and could
thereafter state a
case for the court in respect of issues on which he had already
made definite
findings of fact and law. She relied on the decision in
Fidelitas Shipping Co Ltd
v. V/O Exportchleb, [1965] 1 Lloyd's Rep. 223 and London Dock
Company v.
Shadwell 1862 7 L.T. 381.
[52] The judge was correct in her interpretation of the section
32. It is a
sufficient answer to Mr. Newmans submissions to say that on a
proper
interpretation of section 32, the clear contemplation of
Parliament was for a case
to be stated prior to the making of the award. I do not see such
a construction of
section 32 as restrictive. It is the only reasonable
interpretation of the section.
More so from a business perspective. Why should the arbitrator
seek the
guidance of the court by way of case stated, after he has
already given a decision.
The decisions in Fidelitas and London Dock Company v. Shadwell
give clear
guidance on the point. The passages relied on by the judge at
page 228
(Fidelitas) and page 382 (London Dock Company v. Shadwell) give
strong
support for the decision to which she came and with which I
agree. It is
unnecessary to cite them here.
(ii) Procedural mishap
[53] Mr. Newman also submitted that there was a procedural
mishap which led
to an injustice in the making of the award. He contended that
the procedural
mishap was NIPDECs misunderstanding of the requirement to ask
the arbitrator
to state a case for the opinion of the Court on the critically
important provision
of clause 2.4 of the FIDIC COC, before making the award. The
serious injustice
was the prospective loss of an important ruling from the Court
on the
-
Page 29 of 63
interpretation of an important contractual provision which [had]
far reaching
implications not only for the contract but other Government/IDB
contracts
where the FIDIC COC are generally adopted by the parties.
[54] Further, given NIPDECs stated intention always to seek an
opinion from
the Court on this question (as confirmed by the evidence of its
acting general
manager, Wendy Ali), there was in fact a deviation from the
route which the
reference should have taken towards its decision. Put another
way, there was a
procedural mishap because of NIPDECs misunderstanding, with the
result that
the arbitration did not proceed in the manner that it should
have. He relies on the
decision in Indian Oil Corporation v. Coastal (Bermuda) Ltd.
[1990] 2
Lloyds Rep. 407, and on the decision in King v. Thomas McKenna
(supra):
[55] Mr. Fitzpatrick for NHIC also relies on the King decision,
in particular, on
the dictum of Lord Donaldson MR cited above at paragraph 24. He
contends,
inter alia, that, arising out of the King decision, in order to
constitute a procedural
mishap:
(i) The event must have arisen during the course of the
reference to the
arbitration and must have resulted in a deviation from the route
which the
reference should ordinarily have taken towards the award.
(ii) The event must have resulted in some aspect of the dispute
not being
considered and adjudicated upon as filling or in the manner that
the parties
were entitled to expect and it would be inequitable to allow the
award to
have effect without some further consideration by the
arbitrator.
He contended that on NIPDECs own evidence, the arbitration
proceeded exactly
as NIPDEC intended, since it was NIPDECs conscious decision not
to request
that a case be stated for the court prior to the issue of the
award.
[56] The decisions in Indian Oil Corporation and King fall to be
considered
-
Page 30 of 63
here. In King there was an arbitration of a building dispute.
During the course of
argument before the arbitrator on the issue of costs, counsel
for the building
owners decided not to reveal to the arbitrator that there was a
sealed offer from
the owners in the sum of five thousand pounds (5000) for the
outstanding works
claimed by the contractor. In error, she failed to indicate
either to the arbitrator or
the contractors that she wanted the issue of costs to be held
over until questions of
liability and quantum were determined. The arbitrator awarded
the sum of four
thousand, seven hundred and forty-three pounds (4,743) in full
settlement of all
claims and not knowing of the sealed offer, awarded the
contractors the costs of
the arbitration.
[57] The trial judge held that a deliberate but mistaken
tactical decision by
counsel, not to inform the arbitrator of the sealed offer, or to
request an interim
award thus reserving the issue of costs, constituted a
procedural mishap, entitling
a court to exercise its discretion to remit the award. The
decision was upheld an
appeal.
[58] In Indian Oil Corporation v. Coastal (Bermuda) Ltd. (supra)
(also
relied on by NIPDEC) the arbitrators had found in favour of
Coastal as a result of
the decision by IOCs counsel not to amend the pleaded case to
include facts
already in evidence. This would have permitted them to advance a
stronger case;
one which in the opinion of one arbitrator, might very well have
succeeded.
[59] Evans J remitted the matter to the arbitrators. He held,
inter alia, that the
consequences for IOC of the failure of its counsel to seek leave
to amend the
pleadings (even when that had been raised by the tribunal
itself), had been very
serious; that if the evidence disclosed facts which established
a defence in law to
the claim but the tribunal failed to take account of that
defence because the legal
issues were not correctly formulated in IOC pleadings, then
(even if the failure
was due to IOCs own counsel) there had been an injustice to IOC
which could be
remedied by remitting the award under section 22.
-
Page 31 of 63
[60] In this case the judge (adopting the language of Lord
Donaldson) held that
there had been no deviations from the route which the reference
should have
taken toward its destination. She found that arbitrator dealt
properly and fairly
with the issues raised by the parties and the questions posed to
him by the
amended TOR. There was no serious or substantial injustice to
NIPDEC as a
result of its not requesting the arbitration.
[61] The judge was correct to reject NIPDECs arguments. In both
Indian Oil
Corporation v. Coastal (Bermuda) Ltd. and King v. Thomas
McKenna,
counsels error occurred during the arbitration and resulted in
material issues both
factual and legal not being considered by the arbitrator. These
errors resulted in
decisions adverse to the aggrieved party. There was a real
probability, in both
cases, that, had those issues been considered by the
arbitrators, the awards would
have been different.
[62] In this case, the failure to request a case stated referral
was a matter of
choice for NIPDEC (however inadvertent that might have been).
Its decision not
to ask for a referral did not cause the arbitrator to ignore or
to fail to consider
material issues in the arbitration, which resulted in an
injustice to NIPDEC.
Neither was it a deviation from the course which the arbitration
would ordinarily
have taken towards its conclusion. The judge was right to reject
the contention.
While the non referral may have deprived the parties of the
benefit of an
important ruling from the court on the purport of an important
contractual
provision, there was no injustice to NIPDEC.
[63] Indeed, it is in the nature of arbitration proceedings,
that court proceedings
are generally excluded. The provisions of clause 2.4 are not so
much a matter of
rocket science, as to require some earth shaking decision of the
Supreme Court of
Trinidad and Tobago, such that its non delivery leaves the
parties bereft of advice
on the interpretation of the clause. There is no demonstrable
injustice to NIPDEC
resulting from the non referral of the matter to the High Court.
The submission
fails.
-
Page 32 of 63
(b) Should the award be remitted or set aside for error on the
face of the
record
(i) General or specific reference
[64] The first question is whether, in this case, the reference
to arbitration was
specific or general. The judge found at paragraph 86 that
Specific questions of
law and the construction of clause 2.4 of FIDIC COC were indeed
referred to the
decision of the arbitrator and the award of the arbitrator ought
not to be set
aside or remitted unless I find on the face of the award that
the Arbitrator had
proceeded illegally or on principles of construction which I do
not countenance.
[65] Mr. Newman contended that the judge is wrong. The matters
before the
arbitrator were part of a general reference to arbitration. He
asserts that the
production of a list of issues for hearing and determination in
a partial award (set
out in the 5th
December letter) did not serve to change the nature of the
reference.
[66] Mr. Fitzpatrick responded in his written submissions
that:
(a) NIPDECs complaint is, in reality, not one of construction.
Rather, it is
that the arbitrator should not have found that evidence of
the
Governments wealth did not constitute reasonable evidence of
NIPDEC
having made and maintained financial arrangements to pay the
contract
price at the relevant time.
(b) NIPDEC is really seeking to attack the arbitrators findings
of fact.
(c) What constitutes reasonable evidence is not a matter of
construction but
is to be determined in light of all the circumstances.
(d) It is clear that the arbitrators findings on what was
required to comply
with the reasonable evidence requirements of clause 2.4 were
arrived at
after a consideration of the circumstances of the case and all
relevant facts.
-
Page 33 of 63
(e) The arbitrators findings are in answer to the specific
question posed by
NIPDEC, to wit:
Assuming, without admitting, that [NHIC] was entitled to
make
the request pursuant to sub-clause 2.4 did the facts and
circumstances including inter alia, the [financial
arrangements
correspondence] satisfy the evidential threshold required by
sub-clause 2.4?
[67] In his oral submissions Mr. Fitzpatrick stated that whether
the financial
correspondence constitutes sufficient evidence was a question of
fact. That was
demonstrated by the positions of both parties and the approach
of the arbitrator in
coming to his conclusion. Mr. Fitzpatrick submitted further,
that specific
questions of law having been asked and answered, the general
rule is that the
arbitrator is the sole and final judge of all questions of law
and fact. The Court
will not interfere with the award, even if it is erroneous,
unless it appears on its
face that the arbitrator has proceeded illegally.
[68] In my judgment, the reference was not a specific reference.
The
construction of clause 2.4 is at the heart of the issue of
validity under section 16
but its interpretation arises in the course of deciding whether
the invocation of
clause 16 by NHIC was correct.
[69] An examination of the amended Terms of Reference and
Appendix B to
the amended Terms of Reference is required. The issues addressed
in the SPA
were not originally referred to the arbitrator. The disputed
events occurred in
November 2006, well after the date of the initial request for
arbitration and the
original Terms of Reference which were dated 1st December 2005.
The parties
therefore agreed to amend the Terms of Reference to enlarge the
arbitrators
jurisdiction to include matters not originally referred. The
liability issues which
formed the subject matter of the SPA were then expressly
included in the
amended Terms of Reference.
-
Page 34 of 63
[70] The parties agreed, by a jointly signed letter of agreement
dated 5th
December 2006, that certain liability issues should be dealt
with in the first
substantive hearing. Thereafter they also agreed the following
broad issues:
1. Validity of NHICs Suspension.
2. Whether the Engineer suspended any portion of the Works.
3. Whether Nipdec agreed to NHICs suspension and/or reduction in
the rate
of work.
4. Validity of NHICs termination.
5. Validity of Nipdecs termination - 15.2/acceptance of
repudiation.
6. Nipdecs seizure of NHICs Goods and Equipment following
termination.
7. Contractual requirements for notification of claims by the
Employer and
by the Contractor - DEFERRED TO SECOND HEARING.
8. Extent of legal responsibility for design.
9. Compliance by NHICs with sub-clause 8.3 of the Contract -
DEFERRED
TO SECOND HEARING.
10. Reviewability of Engineers awards of extension of time.
[71] An examination of the list reveals that the interpretation
of clause 2.4 was
not directly listed as an issue for arbitral decision. What was
actually referred
was the validity of NHICs suspension and subsequent termination
of the contract
pursuant to clause 16(1) and (2) respectively of the contract
(items 1 and 4 of the
list). There was no specific referral of clause 2.4. Rather
(consistent with
Absalom) the interpretation of clause 2.4 arises in the course
of consideration of
clause 16.
[72] Appendix B to the amended Terms of Reference bears this
out. Paragraph
1-3 plainly states that the parties having agreed the broad
issues (set out above);
Thereafter, at the invitation of the arbitrator (emphasis mine)
the
parties formulated specific questions to reflect issues 1-6, 8
and 10
aforesaid.
-
Page 35 of 63
Therefore, the questions which were posed to the arbitrator,
arose after the
validity of NHICs suspension, pursuant to clause 16(1), had
already been
referred to him. The arbitrator, in order to obtain assistance
on that broad issue,
asked that specific questions to be posed no doubt in an effort
to focus on the
issues.
[73] The arbitrator then decided that certain of those questions
were to be dealt
with at the first hearing. Among them were the following
questions (which alone
are relevant to this appeal). I shall set them out in the format
in which they are set
out in Appendix B (subject to contextual changes).
Broad Issue (1): Validity of the Claimants suspension
1.4.1 Claimants [NHICs] Questions
(a) Was [NHIC] entitled to reduce the rate of work under
sub-
clause 16.1 on 23rd
June 2005 by reason of [NIPDEC]
failure to provide reasonable evidence as required by sub-
clause 2.4 that financial arrangements had been made and
were being maintained so as to enable [NIPDEC] to pay
the contract price as estimated at the time?
(b) Was [NHIC] entitled to suspend the works under sub-
clause 16.1 from 23rd
September 2005 until termination by
reason of [NIPDECs] failure to provide reasonable
evidence as required by sub-clause 2.4 that financial
arrangements had been made and were being maintained
so as to enable NIPDEC to pay the contract price as
estimated at the time?
1.4.2 Respondents [NIPDECs] Questions.
-
Page 36 of 63
(i) Given the true meaning and effect of sub-clause 2.4 of
the
Contract and in the events which have transpired, was
[NHIC] entitled to request from NIPDEC reasonable
evidence that financial arrangements had been made and
were being maintained and which enable the Employer to
pay the Contract Price as contemplated by Sub-Clause 2.4
of FIDIC (the request)?
(Question IV on the list)
(ii) Assuming, without admitting, that NHIC was entitled to
make the request pursuant to Sub-Clause 2.4, did the facts
and circumstances including, inter alia, [Nipdecs] letters
and memoranda dated 28th
December 2004, 29th
December
2004, 5th
July 2005, 6th
July 2005, 6th
October 2006 and
20th
October 2006 (the financial arrangements
correspondence) satisfied the evidential threshold
required by sub-clause 2.4?
(Question V on the list)
[74] In my judgment therefore, the questions raised by the
parties, were posed
at the direction of the arbitrator to assist him in coming to a
decision on the
validity of NHICs decision to suspend under clause 16. Clause
2.4, though
central to the decision, was a provision which fell to be
interpreted by the
arbitrator in the course of his consideration of clause 16. It
was not specifically
referred to the arbitrator as a question of law.
[75] The judge therefore erred in holding that the questions
were specific
references to arbitration. She did not give full consideration
to the contents of
Appendix B of the amended Terms of Reference which showed that
the questions
were requested by the Arbitrator after the referral had been
made to him. The
matter not being a specific question, this court can remit the
matter for the
arbitrator, or set the award aside if there is shown to be an
error on the face of the
-
Page 37 of 63
award.
(ii) Is there an error on the face of the award
[76] I find it necessary to look at the arbitrators findings and
pattern of
reasoning. I have summarised the arbitrators decision, including
the questions he
poses and considers, as follows:
(a) The mere fact that an Employer is wealthy is inadequate for
the
purposes of Sub-Clause 2.4. Similarly, the mere fact that an
Employer
has good reasons for wanting a project completed does not itself
mean
he has made and maintained the necessary financial
arrangements.
Accordingly, the evidence given at the hearing to the effect
that the
GORTT has very substantial funds is, prima facie, insufficient
by itself
for satisfying 2.4. Does the mere fact that the GORTT has funds
in
general mean it has made arrangements enabling it to pay?
The
answer emerging from the evidence as regards the significance
of
cabinet approval, is that (quite property, and for very good
public policy
reasons) the GORTT cannot pay large sums of public money in
respect
of cost overruns on construction contracts unless cabinet
approval is
given in advance or, perhaps, retrospectively. The issue of
cabinet
approval cannot simply be ignored. It is, at some point, an
essential
element of any arrangement to pay.
(b) The first point to arise is whether the letters of 5th
and 6th
July 2005
satisfied the 2.4 requirements i.e. whether the letters
contained
reasonable evidence of arrangements enabling the Employer to
pay
the then - current estimated Contract Price (TT$286 million -
see MoH
letter of 5th
July 2005). In determining whether the letters constitute
reasonable evidence, all relevant circumstances must be
considered.
(c) It is noteworthy that Sub-Clause 2.4 does not simply require
evidence
-
Page 38 of 63
that the Employer is able to pay. Instead it requires evidence
that
financial arrangements have been made and are being
maintained
which will enable the Employer to pay. Proper weight has to be
given to
all the words which have been included in Sub-Clause 2.4.
(d) Reasonable evidence that financial arrangements have been
made
and are being maintained which will enable the employer to pay
the
contract Price would ordinarily involve, prima facie, some
evidence of
cabinet approval having been obtained (see Sub-Clause 2.4).
(e) As at 5th
and 6th
July 2005 it was probable that no financial
arrangements had in fact been made to enable the Government of
the
Republic of Trinidad and Tobago to pay NHIC for the sums, beyond
the
initial IDB loan, that were being incurred and that, consistent
with that
position, the letters of 5th
and 6th
July 2005 did not provide (as required
by 2.4) reasonable evidence that financial arrangements had
been
made and were being maintained which would enable the employer
to
pay the estimated contract price.
(f) Although the letters of 5th
and 6th
July had the potential to convey
reasonable evidence for the purposes of clause 2.4, Mr. Elias by
his
letter of 8th
July raised the issue of the use of the terms without
prejudice and whether Cabinet approval had been obtained. If
Ministry of Health had responded to these queries by explaining
that the
term without prejudice did not mean that the Ministry was
avoiding
taking responsibility for the contents of the letter and
that
notwithstanding the absence of Cabinet approval these were
adequate
arrangements to pay, then the letter would, when read in light
of those
subsequent clarifications, have amounted to reasonable evidence.
But
this did not happen. Mr. Elias received no response to his
letter. The
failure to respond is a relevant circumstance in deciding
whether the
employer submitted reasonable evidence.
-
Page 39 of 63
(g) The letter of 5th
July was equivocal because of use of the phrase
without prejudice and because of the absence of reference to
Cabinet
approval.
(h) There being no response to Elias letter of 8th
July and by choosing to
leave the letters of 5th
and 6th
July in their equivocal state, the employer
failed to provide reasonable evidence of financial arrangements.
A
timely reply to Mr. Elias letter may well have rendered the
letters
reasonable evidence because the letters did supply some evidence
of
financial arrangements. Since no such reply was produced at all,
the
evidence remained inadequate for the purposes of sub clause
2.4.
(i) The earliest date at which it could be said that financial
arrangements
had been made which would enable the employer to pay the
Contract
Price was the point at which the letter dated 29th
September 2006 from
Nipdec was approved and signed on 3rd
October 2006 by the Attorney
General and Minister Enil, in circumstances where the Minister
of
Health (the Honourable John Rahael) had held discussions with
the
Prime Minister and Minister Enil and the Attorney General on the
same
day (3rd
October 2006).
(j) Thus, the necessary financial arrangements had been made on
3rd
October 2006. Clause 2.4 further requires that the employer
should
submit to the contractor reasonable evidence that those
financial
arrangements have been made. Thus the question arises, was
such
reasonable evidence provided?
(k) Until the employer passed on the information about approval
of 3 key
Cabinet Ministers to the course of action of the letter of
6th
October
2006, it had not submitted reasonable evidence. The employer did
not
take the opportunity until 3rd
November 2006 to explain the steps to get
Cabinet approval.
-
Page 40 of 63
(l) The MoH 6th
October 2006 letter was drafted after Nipdec had taken
legal advice. It was produced on 6th
October, 2006, but Nipdec only
hand-delivered it to NHIC on 19th
October 2006. On 27.10.06 NHIC
requested confirmation of cabinet approval. Since two weeks
before, the
Permanent Secretary had taken action to go to cabinet for
approval
(T4/80/lines 3-5). Although the Permanent Secretary had by
30th
October 2006 actually prepared a Cabinet Note she did not
succeed in
telling NHIC of that prior to the expiry of the deadline of 31st
October
2006. The deadline was stated in NHICs 27th
October 2006 letter. She
got the NH letter on 27th
October, which was a Friday. So NH were not
told about the steps to get cabinet approval, and on 3rd
November 2006
NH issued a notice of termination.
Did the employer provide reasonable evidence pursuant to clause
2.4 on
or after 3rd
October 2006?
(m) The suspension in mid-2005 arose by reason of the Clause 2.4
request
preceding the suspension. The cost report No. 5 issued on
23rd
May
2005 showed an estimated contract price of TT$286,992,070.
NHICs
21 days notice under Clause 16.1, in respect of suspending work
unless
2.4 evidence was produced, was dated 31st May 2005. The
Permanent
Secretarys letter of 5th
July 2005 refers to funds in the sum of
TT$286,992,070 to meet the estimated final cost to completion.
This
remained the estimated final cost until, on 5th
October 2006, Mr. Zak of
Stantec determined a figure of TT$224,129,801.99. It is this
latter,
lower, figure that is referred to in the MoH letter of 6th
October 2006.
(n) It is Nipdecs case, that the relevant Clause 2.4 request is
that made at a
time when the estimated contract price was the higher figure
of
TT$286,992,070. Certainly, Permanent Secretary Jones letter of
6th
October 2006 does not provide reasonable evidence of
financial
arrangements having been made and maintained which would
enable
-
Page 41 of 63
the employer to pay the higher figure (about TT286 million) as
distinct
from the lower figure (TT$224 million). Thus, even if the
information
had been passed on about the approval by the three key
Cabinet
Ministers, that would simply have been to give reasonable
evidence as
regards a payment limited to $224,129,801.99, and not in respect
of the
higher figure of $286,922,070. Yet it is Nipdecs case that the
request
from the contractor that underlies the reasonable evidence that
the
Employer was seeking to submit to the Contractor by the Ministry
of
Healths letter of 6th
October 2006 was the request made at the time
when the relevant estimated final cost to completion was
$286,992,070.
Hence, (on Nipdecs own case) even if the information about the
three
Cabinet Ministers had been provided, the letter of 6th
October 2006
would not have satisfied the requirements of Clause 2.4. In
such
circumstances, assuming NHIC satisfied all the other
requirements as
regards time periods, and procedure as set out in Clauses 2.4
and 16, it
was entitled by Clause 16.2(a) to terminate the contract in
November
2006.
[77] I also find it necessary to set out the correspondence
before the arbitration
as it relates to the financial arrangements to satisfy clause
2.4. I shall set out in
their entirety the letters of 5th
and 6th
July 2005 respectively from the Permanent
Secretary, Ministry of Health and the general manager of NIPDEC.
These letters
are in response to NHICs letter of 28th
April 2005 invoking clause 2.4 and
requesting reasonable evidence that financial arrangements have
been made
and are being maintained to pay the then contract price at this
time. The then
estimated contract price was then $286,992,070.00.
[78] I shall also set out in some detail NIPDECs letter of
29th
September 2006,
to the Minister of Health, the letter of 6th
October 2006 from the Permanent
Secretary Ministry of Health (the draft of which was submitted
to the Minister by
NIPDECs September 29th
letter), NIPDECs letter of 20th
October 2006 and
NHICs reply dated 27th
October 2006
-
Page 42 of 63
July 6, 2005
Mr. John Connon
Managing Director
NH International (Caribbean) Limited
39 Long Circular Road
St. James
Dear Sir,
Re: Scarborough Hospital - Confirmation of Funds
In accordance with Clause 2.4 please note that the Ministry
of
Health has advised without prejudice that funds are available
in
the sum of TT$286,992,070.00 to meet the final cost to
completion
for the Scarborough Hospital. Attached is a copy of a letter
from
the Permanent Secretary, Ministry of Health to NIPDEC on
this
matter.
Please note that the Ministrys interim declaration is made in
good
faith pending a Final Cost Agreement by the relevant parties
concerned as per the procedural rules governing the
determination
of the Final Cost to completion.
Yours faithfully
/s/ Margaret Mc Dowall-Thompson
Margaret Mc Dowall-Thompson
General Manager
July 05, 2005
Mr. Kenneth Crichlow
Programme Manager
National Insurance Property Development Co. Ltd.
56-60, St. Vincent Street
PORT OF SPAIN
Dear Mr. Crichlow
IDB Loan No. 937/OC - TT - Scarborough Hospital - Request
for
evidence of Financial Arrangements
Reference is made to your fax dated June 29, 2005 and to the
legal
advice from your Attorneys Mr. M. Hamel-Smith & Co. on
the
-
Page 43 of 63
captioned subject.
The Ministry of Health is aware of the procedural matters
pertaining to the determination of the final estimated
contract
price, which is yet to be finalized and agreed upon. Given
the
prevailing circumstances, the only document the Ministry can
rely
on is the Quantity Surveyors Cost Report No. 5 (as at 30th
April,
2005) dated May 23, 2005. This report indicated an Estimated
Final Cost to completion of TT$286,992,070.
In this regard, the Ministry of Health hereby advise,
without
prejudice, that funds are available in the sum of
TT$286,992,070
to meet the estimated final cost to completion for the
Scarborough
Hospital.
Please be advised that the Ministrys interim declaration is
made
in good faith pending a Final Cost Agreement by the relevant
parties concerned as per the procedural rules governing the
determination of the Final Cost to completion.
Please be guided accordingly.
Yours sincerely,
/s/ Reynold Cooper
Permanent Secretary
29th
September 2006
Honourable John Rahael
Minister of Health
Ministry of Health
63 Park Street
Port of Spain
Dear Honourable Mr. Rahael,
Re: New Scarborough Hospital, Tobago -
We refer to the mater at caption and particularly our
numerous
discussions as to the immediate re-possession of the
Scarborough
Hospital site to facilitate the resumption of construction
work.
You will be reminded that, notwithstanding the position taken
by
NIPDEC and the Government to NH International on the 5th
July
-
Page 44 of 63
2005, that the sum of TT$286,992,070.00 was available to meet
the
estimated final cost to completion of the project, NH
International
proceeded to suspend works on the site.
As part of the ongoing arbitration proceedings, both NIPDEC
and
NH International have been engaged in considerable work with
the
Independent Quantity Surveyor. This has helpfully resulted
in
agreement between the parties on many items, with some items
clearly disagreed.
As a result of this, NIPDEC requested, and our Engineer,
Stantec
Consulting International Limited, has by letter dated the
28th
September 2006 made a determination that the current
Contract
Price is now estimated to be TT$224,129,801.99 VAT inclusive
which is lower than the contract price as previously approved
by
the Ministry of Health (above).
In light of the same, our external Attorneys-at-Law have,
after
consultation with Mr. Stuart Catchpole Queens Counsel,
advised
that a renewed letter should be issued by the Ministry of Health
to
NH International stating that financial arrangements have
been
made and continue to be maintained, which will enable the
Employer to pay the Contract Price. We now enclose a draft
copy
of this letter.
This course of action, at the present time, is the best
available
method to achieve the pressing objective of lawfully
re-gaining
possession of the site.
Once you are in agreement, we kindly request that the
permanent
Secretary sign the attached letter and return the same to
our
offices for delivery to NH International. We have enclosed a
soft
copy of the draft letter herein for your convenience.
As always, I am available to discuss the same with you.
We look forward to your urgent response.
Yours faithfully,
NATIONAL INSURANCE PROPERTY
DEVELOPMENT COMPANY LIMITED,
October 06 2006
N.H. International (Caribbean) Limited
39 Long Circular Road
St. James
-
Page 45 of 63
Attention: Mr. Peter V. Morris
Dear Sir,
Re: Scarborough Hospital, Tobago: Reasonable Evidence of
Employers Financial Arrangements.
We refer to your letter of 3rd
September, 2004 requesting pursuant
to Clause 2.4 of FIDIC that the Employer submit reasonable
evidence that financial arrangements have been made and are
being maintained which will enable the Employer to pay the
Contract Price (as estimated at that time) in accordance
with
Clause 14. Your letter erroneously refers to NIPDEC as the
Employer. As you are aware, Employer is defined in the
Particular Conditions as being The Government of Trinidad
and
Tobago.
We also refer to NIPDECs letter to you of 29th
December, 2004
enclosing a Memo addressed to NIPDEC from the Project
Administration Unit of the Ministry of Health dated 28th
December, 2004 confirming the availability of funds from
Government (as approved by Cabinet) and including the
allocation
of funds for the Tobago House of Assembly Public Sector
Investment Programme. We also refer to NIPDECs letter of 6th
July, 2005 enclosing a letter to NIPDEC from the Acting
Permanent Secretary, Ministry of Health dated 5th
July 2005
submitting further reasonable evidence of financial
arrangements
in compliance with Clause 2.4. NIPDECs letters and the
Ministry
of Health correspondence and memoranda are hereafter
referred
to as the Financial Arrangements correspondence.
In light of the definition of Employer given in the
Particular
Conditions as well as the content of the correspondence referred
to
above, it is clear that NHIC has always been aware that the
Government is the Employer under the relevant contract
wherein
NIPDEC acts as agent of the Government only. In the
circumstances, both NIPDEC and the Government maintain that
the Financial Arrangements correspondence fully complies
with
the requirements of C