Top Banner
Bi-annual Environmental Monitoring Report December 2015 Loan 2971-PAK: Punjab Irrigated Agriculture Investment Project Tranche 3 Pakpattan Canal and Suleimanki Barrage Improvement Project (PCSBIP) Prepared by the Project Management Office, Irrigation Department, Government of Punjab. The bi-annual environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
77

Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Mar 23, 2020

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Bi-annual Environmental Monitoring Report

December 2015

Loan 2971-PAK: Punjab Irrigated Agriculture

Investment Project – Tranche 3

Pakpattan Canal and Suleimanki Barrage

Improvement Project (PCSBIP)

Prepared by the Project Management Office, Irrigation Department,

Government of Punjab.

The bi-annual environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

PSS Consultants i

BI-ANNUAL ENVIRONMENTAL MONITORING REPORT

PROJECT: PAKPATTAN CANAL & SULEMANKI BARRAGE IMPROVEMENT

PROJECT (PCSBIP) ADB Loan No. 2971-PK

Financed by: Asian Development Bank and Government of the Punjab

July - December 2015

Prepared by: Ahsan Iqbal Bela (Environmental / Resettlement Specialist)

Checked by: Malik Parvez Arif (Dy. Director Environment PMO Barrages)

Page 3: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

PSS Consultants ii

TABLE OF CONTENTS

Page No.

1. INTRODUCTION .............................................................................................. 1

2. BACKGROUND ............................................................................................... 1

2.1 Pakpattan Main Canal (Upper & Lower), Khadir Branch and PI-Link Canal .. 2

2.2 Sulemanki Barrage ........................................................................................ 4

3. PROJECT PROFILE ........................................................................................ 4

4. PROJECT PURPOSE ...................................................................................... 5

5. PROJECT ORGANIZATION AND ENVIRONMENTAL TEAM MANAGEMENT APPROACH .............................................................................................................. 7

5.1 Project Management Office ........................................................................... 7

5.2 Construction Supervision Consultants .......................................................... 8

5.3 Contractor ..................................................................................................... 8

6. MAJOR PROJECT ACTIVITIES PERFORMED ............................................ 10

7. IMPLEMENTATION OF EMP ........................................................................ 14

7.1 Site Specific Environmental Management Plan (SSEMP) ........................... 14

7.2 Environmental Progress Review Meetings .................................................. 14

7.3 Implementation of Environmental Monitoring Plan ...................................... 15

7.4 Site Visit of ADB’s Mission and Site Inspections ......................................... 18

7.5 Implementation of Waste Management Plan .............................................. 20

7.6 Implementation of Training Plan .................................................................. 21

7.7 Implementation of LARP ............................................................................. 21

ANNXURES ANNEXURE-1: Environmental Progress Review Meetings (EPRMS) Minutes ........ 22 ANNEXURE-2: Environmental Test Results ............................................................ 50 ANNEXURE-3: Agreement with TMA ....................................................................... 85 ANNEXURE-4: Proposed Training Schedule for January to July 2016 .................... 89

Page 4: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

PSS Consultants iii

LIST OF ABBREVIATIONS

CSC Construction Supervision Consultants

D/S Downstream

EMP Environmental Management Plan

EPA Environmental Protection Agency

ESU Environmental and Social unit

HSE Health, Safety & Environment

LARP Land Acquisition and Resettlement Plan

mg/l Milligrams per liter

NEQS National Environmental Quality Standards

NTU Nephelometric Turbidity Unit

N2O Nitrous Oxide

PCSBIP Pakpattan Canal Sulemanki Barrage Improvement Project

PM Particulate Matter

ppm parts per million

ppb parts per billion

PID Punjab Irrigation Department

PMO Project Management Office

PPEs Personal Protective Equipments

PSSC Pakpattan Sulemanki Supervision Consultant

RSC Residual Sodium Carbonate

RE Resident Engineer

SAR Sodium Absorption Ratio

SOx Oxides of Sulphur

SFA Social Framework Agreement

SSEMP Site Specific Environmental Management Plan

TDS Total Dissolved Solids

TSS Total Suspended Solids

TBT Tool Box Talk

U/S Upstream

μS/cm MicroSiemens per centimeter

μg/m3 Microgram per cubic meter

Page 5: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 1

1. INTRODUCTION

This is third Bi-Annual Environmental Monitoring Report prepared for Pakpattan Canal &

Sulemanki Barrage Improvement Project (PCSBIP). Details of activities performed under

environmental aspects of the project during July 2015 to December 2015 are described in

this report. Construction activities carried out on both contracts of PCSBIP i.e. Rehabilitation

of Sulemanki Barrage and Rehabilitation of Pakpattan Canal Main Canal, Khadir Branch &

PI Link Canal are included.

Sulemanki Barrage is the first barrage on Satluj River after the river enters into Pakistan

tertiary. The barrage is designed to for 325,000 cusecs discharge and located about 20km

(12 miles) from Haveli Lakha and about 150km (94miles) from Lahore (capital of Punjab

Province). Three Irrigation Canals viz Pakpattan, Fordwah and Eastern Sadiqia Canals are

fed from this barrage. The total canal command area of three canals is 2.5 million acres,

which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable

contribution in the agricultural production of Punjab. Three canal command area spread over

the six districts of Punjab i.e. Bahawalnagar, Bahawalpur, Okara, Pakpattan, Vehari and

Lodhran.

Pakpattan Canal off takes from River Sutlej at right side of Sulemanki Barrage. The design

discharge of canal is 6,594 cusecs at head. The total canal command area is about one

million acres distributed in districts Okara, Pakpattan, Vehari and Lodhra on the right side of

the River Sutlej. The main Pakpattan canal is perennial and only close for annual

maintenance requirement during the months of December and January. Khadir Branch and

PI Link Canal are non-perennial and closed during summer.

2. BACKGROUND

Pakistan Irrigation system originally developed during mid 19th and early 20th century and

therefore the major chunk of the system is more than 80 years old. Upgrading and/or proper

maintenance of the irrigation system has not been carried out since the system is

constructed. Pakpattan Canal and distribution network and Sulemanki Barrage were

commissioned in 1926. Feasibility and detail design study of rehabilitation & upgrading of

Pakpattan Canal Main line, Khadir Branch, Pakpattan-Islam Link Canal and Sulemanki

Barrage were completed in 2013. The project named as “Pakpattan Canal & Sulemanki Barrage Improvement Project (PCBIP)” was awarded for construction in mid 2014. The project is divided into two construction contract:

Page 6: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 2

ICB-01

Rehabilitation and Upgrading of Pakpattan Canal, Khadir Branch and Pakpattan Islam Link

Contract No. PCSBIP/ICB–01.

ICB-02

Rehabilitation and Upgrading of Sulemanki Barrage

Contract No. PCSBIP/ICB-02

2.1 Pakpattan Main Canal (Upper & Lower), Khadir Branch and PI-Link Canal

Pakpattan Canal and distribution network cultivating about 1.25 million acres was

commissioned in June 1926. The design discharge of Pakpattan Canal was 6,594 cusecs at

head regulator built on the right flank of Suleimanki Barrage. Pakpattan Canal irrigates land

in the districts of Okara, Pakpattan, Vehari, and Lohdran. Pakpattan canal has perennial as

well as non perennial irrigation system and shut down for annual maintaining requirements

during December/January. Khadir Branch and PI Link Canal is a non perennial part of the

system.

Pakpattan Main Canal

In pursuance of Indus Water Treaty (1960), India got the usage rights of the eastern

tributaries of River Indus (Ravi, Sutlej and Beas). Consequently upon the construction of

Bhakra/Nangal Dam on river Sutlej and Pandoh & Pong Dam on Beas, discharges in Sutlej

were reduced significantly. The reduction in average annual flow of Sutlej River after the

treaty is provided in Water Resources Management Directorate WAPDA and given below

River Average Annual Flow from 1922 to 1961

Average Annual Flow from 1985 to 1995

Average Annual Flow 2000 to 2009

Sutlej 7 MAF 5 MAF 1.1 MAF

Significant works for conveying water from western rivers through link canals to overcome

the shortfall in the eastern rivers were devised and constructed. Balloki-Suleimanki Link

canal (B.S Link) brings about 25,000 cusecs from Balloki barrage to feed the off taking

canals of the Suleimanki Barrage. With construction of Sidhni Mailsi Bahawal Link (SMB

Link) Canal Pakpattan main canal was split into two parts i.e. Pakpattan Canal Upper (PC

(U)) from RD 0 to 567 and Pakpattan Canal Lower (PC (L)) from RD 568 to 667. Due to this

intervention, PC (L) now draws its supplies from SMB Link.

Page 7: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 3

Khadir Branch

Khadir branch off-taking from PC (upper) at RD 112+104/L draws a discharge of 2250

cusecs and irrigates an area of about 329,000 acres and is one of the large non-perennial

canal systems. Khadir branch system has, over the years of use, sustained substantial

damages to the hydraulic structures and the canal prism. The fall structures on this channel

were first remodeled in late thirties by Mr. Prothero & Mr. Burkitt, who changed the fall

sections to stepped and in some cases to expanding glacis type. These falls and some

bridge decks were repaired in the early ninetees but are still facing serious problems and

demand rehabilitation and remodeling, some to the extent of reconstruction which has been

provided in this project.

PI Link Canal

The Pakpattan Islam Link (PI Link) off-takes from RD 406+828/L of Pakpattan Canal (upper)

and transfers about 1000 cs from Pakpattan canal back to Sutlej river U/S of Islam

headworks to feed the Upper Bahawal and Qaim Canals. The water so abstracted from

Pakpattan canal is recouped at RD 267+000 through another link canal named Montgomery

Pakpattan link (MP Link) from LBD canal whose discharge, in consequence, has been

increased by about 1100 cs at its head at Balloki Barrage.

Figure 1: Pakpattan Canal Location Map

Page 8: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 4

2.2 Sulemanki Barrage

Sulemanki Barrage is one of the four barrages/ headworks constructed under Sutlej Valley

Project (SVP), the other 3 being Ferozepur on its upstream; and Islam and Panjnad on the

downstream side. Sulemanki Barrage was built during 1921-1926 with a designed discharge

capacity of 325,000 cs to irrigate vast tracts of fertile agricultural land lying on both sides of

the Sutlej River. The barrage was formally inaugurated on April 12, 1926. Sadiqia and

Fordwah Canals commenced irrigation on May 1 and Pakpattan canal on June 1, 1926.

Since signing of the Indus Water Treaty 1960, India has construction two storage dams on

Sutlej River and almost all of the flows of the river, except the floods that cannot be stored in

the dams, are being used in India. Historical discharge data indicates that the flood

discharge in the river exceeded the designed capacity of the barrage four times; in 1947

(325,000 cfs), 1950 (332,000 cfs), 1955 (597,000 cfs) and 1988 (499,000 cfs).

Figure 2. Sulemanki Barrage Location Map

3. PROJECT PROFILE

The project profile is summarized in following table:

Page 9: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 5

Table 1: Project Profile

4. PROJECT PURPOSE

Ever since the construction, the structure of Sulemanki Barrage has suffered heavily from

floods during the monsoon seasons. The barrage is about 86 years old now and aging

process with inadequate / deferred maintenance has also contributed towards general

deterioration of the different components of the barrage.

Similarly, Pakpattan Canal was heavily damaged during floods of 1988 when the discharge

escaping through the breaches in RMB of Sulemanki Barrage destroyed the canal prism in

the first ten miles or so and damaged the allied structures. The uncontrolled flow discharge

entered the canal and also obliterated the canal prism with scours and erosion in many

places. The hydraulic structures have also sustained substantial ageing defects. No major

rehabilitation works have been carried out during the 80 years of life time of the Pakpattan

Canal system consequently the main canal and its distribution system have become less

efficient.

The project is designed to rehabilitate and upgrading of Pakpattan Main Canal (upper &

lower), Khadir Branch, Pakpattan-Islam Link canal and Sulemanki Barrage. The scope of

work includes the following:

Pakpattan Canal

Channel prisms to be rehabilitated and restored to designed sections. This will be

achieved through construction of studs or berm cutting. Where brushwood is

available, killa bushing will be done for berm formation;

Page 10: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 6

Pakpattan canal Lower will be remodeled to carry the increased discharge of 1160

cs;

Regulators and falls without stilling basin will be reconstructed; downstream of many

fall structures especially on Khadir Branch deep scour pits and embayments have

been formed due to improper energy dissipation. These will be rehabilitated with

proper design of stilling basins.

Structures in deteriorated condition will be rehabilitated and where rehabilitation cost

is not much different from reconstruction, the structures will be re-constructed;

New VR bridges will be constructed to cater for the changed requirements;

Foot bridges will be constructed/rehabilitated;

Raising and strengthening banks of the channels to provide required free board and

cater for hydraulic safety;

Additional cattle ghats will be constructed and the damaged ghats will be

rehabilitated;

Protection works will be provided to minimize embayment near the structures;

Defective & worn out gates and hoisting arrangements will be replaced/rehabilitated;

In Khadir branch, gates are proposed to be installed on the distributary head

regulators as well as cross regulators;

Distribution complex will be constructed at the tail of Pakpattan Canal Upper; and

Residences, offices of staff and regulation quarters at the regulators/falls and

selected Rest Houses to be renovated/constructed.

Sulemanki Barrage

Civil Works

Upstream Floor Extension with Sheet Piles;

Downstream Floor repairs including inverted filters and flexible apron etc;

Instrumentation and Telecommunication System Works;

Rehabilitation of civil works of existing barrage and Road Bridge;

Provision of Piezometers to monitor uplift pressures beneath the structures; and

Works pertaining to correcting Oblique River approach to the barrage.

Mechanical and Electrical Works (M&E)

Rehabilitation of Gates and Hoisting Mechanism of the Barrage;

Electrification and motorized operation of gates with facilities for local control and

provision of backup power supply;

Installing Discharge Monitoring and Communication network; and

Instrumentation for Barrage Monitoring

Page 11: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 7

5. PROJECT ORGANIZATION AND ENVIRONMENTAL TEAM MANAGEMENT APPROACH

The responsibility of different parties of the project are summarized below

5.1 Project Management Office

The overall responsibility for the implementation of Environmental Management/Monitoring

Plan rests with the Project Management Office (PMO) along with the assistance of

Environment and Social Unit (ESU) of PMO. The ESU consists of Director Environment &

Social Safeguards, Deputy Directors Social and Environment and Deputy Director

Community Relations. Construction Supervision Consultants will assist and advise PMO in

implementation of EMP.

PMO will assume overall responsibility for ensuring:

That while executing the contract and undertaking the construction all environmental

norms, regulations and requirements promulgated by Pakistan Environmental

Protection Act (PEPA), Environmental Protection Agency (EPA) Punjab and

particularly Asian Development Bank environmental safeguard policy, with respect to

the work site and adjacent areas are fully respected and implemented

That Contractor and Construction Supervision Consultant (CSC) appoint a dedicated

environmental officer and allied staff with complete facilities and capacities. PMO will

also ensure that all environmental personnel are authorized to implement the socio-

environmental policies and requirements of the EMP

Coordination with relevant government departments and stakeholders on concerned

socio-environmental issues

Inspection and monitoring of residual impacts of the rehabilitation work and observe

documentation of the impacts during the construction phase

Inspection of significant impact in case of emergency condition arises due to

accidental spill, breach etc. The detailed Emergency Response Plan (ERP) has been

prepared by the contractor and included as Annexure 1.

Environment and Social Unit (ESU) of PMO

- Environment and Social Unit (ESU) within PMO will monitor Project performance

- ESU will function in coordination with the Construction Supervision Consultants and

will receive reports from them on behalf of PMO

Page 12: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 8

- ESU will prepare and submit periodical Progress and Monitoring Reports to all

stakeholders as per their schedules. In this task they will seek assistance/ guidance

from Construction Supervision Consultants as and when required

Head / Project Director

The Project Director shall provide or arrange the logistics including communication,

transport and accommodation to all visiting persons/teams and experts from any of the

above monitoring units and shall coordinate with the Contractor(s) to facilitate their

visits/inspections.

5.2 Construction Supervision Consultants

The Pakpattan Sulemanki Supervision Consultant (PSSC) is a joint venture of NDC,

NESPAK and BURQAB Consultants. The Consultancy Services Contract was signed on 02-

04-2014 and became effective form the same date. The consultancy services were

commenced from April 28, 2014. The Consultants’ Project Manager and first batch of staff was deployed on April 28, 2014 to mark commencement of Consultancy Services.

Environmental / Resettlement Specialist of PSSC was deployed on 18th of August 2014. Site

based Sociologist / Environmentalist commenced his duties on site from May 2015.

PSSC is responsible to ensure quality of work and fulfilment of contractual obligations.

Environmental Specialist of the CSC will ensure that all the environmental and social

provisions comply with the applicable standards. He will confirm that the day-to-day

construction activities are carried out in environment friendly manner and periodic

environmental training programmes and workshops are organized for the Consultant’s, Contractor’s and Client’s staff.

5.3 Contractor

Letter of acceptance for Rehabilitation and Upgrading of Pakpattan Canal, Khadir Branch

and Pakpattan Islam Link Contract No. PCSBIP/ICB–01 was issued to the Joint Venture of

Sinohydro Corporation Ltd. and Nishan Engineers (Pvt.) Ltd. by Project Management Office

for Barrages (PMO) on March 12, 2014. The construction contract was signed on April 03,

2014

The construction contract for ICB-02 for “Rehabilitation and Upgrading of Sulemanki Barrage” was signed with Sinohydro Corporation Ltd on June 10, 2014.

The Contractor will ensure that EMP for the project is implemented fully and must be

integrated into the Project implementation and made integral part of the Contract document.

Page 13: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 9

For any default damages so caused will be remediated by the Contractor at his own cost and

expenses. In case the Contractor fails to rectify the damage the employer will remediate at

the risk and cost of the contractor. The amount will be determined by the PSSC which will be

adjusted from amount due to the Contractor. The Contractor/ Consultant will also be

responsible for communicating with and training of his staff in environmental aspects and

implementation of the EMP. The Contractor will take approval from Construction Supervision

Consultants before commencement of any work activity and in case of any uninformed work

the Contractor will be penalised according to the contract.

Organizational Chart for EMP Implementation

Project Management Office (PMO) Project Director (PD)

(Mr. Amjad Seed)

Director Environment and Social Safeguards (Mr. Nazim Shah)

Contractor (Sinohydro-NEL Joint Venture)

Construction Supervision Consultants

(PSSC)

Deputy Director Social and

Environment (Mr. Parvaiz Arif

Malik)

Environmental / Resetlement

Specialist (Mr. Ahsan Bela)

Deputy Director Environment

(Ms. Naila Jabeen)

Deputy Director Communication (Qasar Mustafa)

HSE / Environmental Manager (Mr. Zain ul Abedin)

Environmental Officers (Muhammad Razwan) (M. Ammar Iftakhar)

(Asif Karim) Sociologist /

Environmentalist (Haji Aman Ullah)

Page 14: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 10

6. MAJOR PROJECT ACTIVITIES PERFORMED

ICB-01

Work has been done in the following field during July - December 2015

Earthwork for embankments strengthening including vegetation clear and borrowing

material from the approved sites.

Construction of Gauge readers huts on Khadir Branch and Pakpattan main Canal

Construction of 21 No Cattle Gaht (Cattle Bath stations) on Pakpattan Canal Upper

and 4 No Cattle Gaht on PI Link Canal

Construction of Area Water Board Office in Pakpattan City

Construction / Repair Cross Regulators and Fall Structures on Khadir Branch

Construction of Stone Studs along Pakpattan Canal Upper

Construction of Distribution Complex Structure at the tail of Pakpattan Main Canal

Upper (RD 547)

Canal Lining Work along Pakpattan Main Canal Upper

Construction of New Cross Regulators Structures on Pakpattan Main Canal and

Khadir Branch including the construction of temporary diversions. Other activities

performed for the provision of diversions include:

Up-rotting of trees has been carried out by Punjab Forest Department and

replenishment cost has been given to the Forest Department.

Borrow material acquired from the designated sites as per the approved

SSEMPs for Borrow Areas.

Temporary structures dismantled at the completion of the construction work

and the site rehabilitated according to the EMP.

ICB – 02

Contractor’s Camp

- Improvement work in the contractor’s Camp remained in progress with slow pace. Walking tracks and batching plant area including material storage area is fenced. Oil

storage and generator kept at impermeable paved area. Construction of living area

for the security staff is completed. Other security concerns raised by the relevant

authorities are being implementing at camp site e.g. installing more CCTV cameras,

search lights along boundary wall, provision of elevated monitoring staff etc. Oil

storage area is constructed

Bridge Deck Slab Replacement

Dismantling of existing deck slab, installation of new stringers and pouring of concrete for the

new deck slab remained in progress during this period. Approximately right half of the bridge

is constructed with new deck slab

Page 15: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 11

Road Diversion Work

Maintenance and safety arrangements for road diversion at D/S of Sulemanki Barrage

remained in progress. Adoption of extra safety measures were emplaced to maintain the

traffic flow while the local traffic use the alternative route due to closure of right half of the

bridge.

Bela Removal at U/S of Barrage

Bela removal activity remained in progress with slow pace in the left pocket and at left bank

of feeding channel. Some excavated material is being used for the construction of coffer

dam.

Barrage Floor Repair Work

- Steel fixing and pouring of concrete for the U/S floor extension slab is completed.

- Rawl Bolt installation and 9 inch thick overlay of 4000 psi RC concrete at D/S floor

(14 No Bays) is completed

Comparison of planned and actual work completed till November 2016 is presented in below

S curves for ICB-01 and ICB-02 contracts.

Page 16: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 12

Page 17: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 13

Page 18: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 14

7. IMPLEMENTATION OF EMP

During July to December 2015 following activities related to the environmental aspects of

the project were performed:

7.1 Site Specific Environmental Management Plan (SSEMP)

As per the requirement of EMP (also a part of the contract), Site Specific Environmental

Management Plans (SSEMPs) were prepared and submitted by the contractor for additional

areas utilized as Borrow Areas and for temporary diversions. Following submitted SSEMPs

were reviewed and approved with necessary amendments by PSSC for the implementation

on site.

SSEMP for temporary canal diversion at RD 216 + 200 of Pakpattan Canal Upper

SSEMP for temporary canal diversion at RD 355 + 422 of Pakpattan Canal Upper

SSEMP for temporary canal diversion at RD 384 + 875 of Pakpattan Canal Upper

SSEMP for temporary canal diversion at RD 303 + 675 of Khadir Branch

SSEMP for temporary canal diversion at RD 286 + 843 of Pakpattan Canal Upper

SSEMP for temporary canal diversion at RD 470 + 500 od Pakpattan Canal Upper

SSEMP for temporary canal diversion at RD 319 + 893 of Pakpattan Canal Upper

SSEMP for Borrow Area for the construction of Cofferdam at right half of the Barrage

7.2 Environmental Progress Review Meetings

Three Environmental Progress review meetings conducted during the reported period.

1. On 8th of September 2015 at Sulemanki Barrage Camp Office for ICB-01 (EPRM-5)

2. On 8th of September 2015 at Sulemanki Barrage Camp Office for ICB-02 (EPRM-3)

3. On 5th of November 2015 at Sulemanki Barrage Camp office for ICB-02 (EPRM-4)

4. On 4th of December 2015 at Sulemanki Barrage Camp Office for ICB-02 (EPRM-5)

Meeting minutes are attached as Annexure 1. Major issues and future plans discussed in the

meetings are listed below:

Ensure transparency in the third party environmental monitoring conducted by the

contractor on bi-annual basis. Original report of external monitoring conducted by the

approved laboratory from EPA Punjab was obtained and distribution among other

parties of the project.

Initially contractor struggle to find MBBS doctor working at their camps as per the

requirement of EMP. However by consistent perusing by PSS Consultant and raising

Page 19: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 15

the issue in EPRMs and other progress review meetings, now MBBS doctors and

ambulance are available at Contractor’s Camp Officses.

Ensure SSEMPs for borrow areas, diversion route, establishing / dismantling of

cofferdam are prepared and submitted by the contractor as per the requirement of

the EMP.

Safeguard plans including traffic management, waste management, training etc are

updated according to the site conditions and implement on site.

Public Consultation carried out on regular basis and their outcomes presented in the

relevant documents i.e. monthly monitoring reports etc.

Implementation of the LARP as per the approved scheduled by ADB and PMO.

DD Environment Malik Parvez is conducting EPRM in the office of Contractor (SB)

7.3 Implementation of Environmental Monitoring Plan

External Monitoring

The Contractor hired the services of Apex Laboratory (approved laboratory from EPA

Punjab) for bi-annual environmental monitoring as per the requirement of the contract i.e.

EMP. Apex Laboratory carried out ambient air and water quality testing / monitoring during

August 2015, original test report submitted by the contractor is attached as an Annexure 2.

Monitoring parameters and water quality test results meet the NEQS limits and it can be

concluded that project activities including wastewater disposal at contractor’s camps do not adversely impacting on environmental resources of the area.

Internal Monitoring

Physical Environment

Internal instrumental monitoring of water quality and noise carried out on monthly basis

according to EMP. Five parameters of water quality including pH, Ec, DO, TDS and

temperature were monitored along Pakpattan Canal, Sulemanki Barrage and Camps area.

Page 20: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 16

Monitoring results are attached under Annexure 2. Water quality monitoring indicates the

project activities do not adversely affect water resources of the area.

Dust monitoring carried out on regular basis as specified in the EMP. All the dust prone

tracks/roads sprinkle with water twice a day during dray and hot weather or at when required

basis.

Noise monitoring conducted at the camp site and at construction site the record is attached

under Annexure 2. Elevated noise levels were found occasionally particularly next to the

generators and plant operation. As an remedial measure the out of order machinery was

immediately repaired or silencer installed to bring the level within the NEQS i.e. 75dB. In

addition it was ensured that ear plugs are used by the machine operators and other workers

near the noise producing activities.

Consultant and Contractor are conducting Noise and surface water quality monitoring at site.

Biological Environment

Uprooting of trees was required for provision of temporary diversions and canal lining work

along Pakpattan Main Canal and Khadir Branch. There was no uprooting of trees required at

Sulemanki Barrage for project activities. Compensation as refurbishment cost was given to

Punjab Forest Department as the plantation along the canals is managed by Forest

Department. Following payments are made to DFO Sahiwal as refurbishment cost.

Page 21: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 17

Sr. # Date Amount Paid (Rs.)

01 15-09-2015 100,800/- 02 15-09-2015 377,940/- 03 15-09-2015 377,940/- 04 23-09-2015 377,940/-

Forest Department utilized these funds in their annual plantation plan in the vicinity of the

project area.

Fish trapped in the cofferdam, constructed at Sulemanki Barrage, was released to the

downstream of the river by the contractor’s environmental team. All forest, wildlife and

fisheries laws were respected and abided by the site workers and monitored by the

contractor and consultant environmental team. All vehicles, machinery, equipment and

generators used during construction activities were kept in good working condition and be

properly tuned to minimize the adverse impact on waterfowl habitat by reducing noise,

exhaust and land disturbance. Necessary sign boards were displayed to remind the

obligation of labour, visitors and members of public towards Biota.

Social Environment

Public consultations were conducted at villages or daras located near the construction site.

Social Framework Agreements were completed during the consultations in case the

contractor’s utilize any local privately owned resources e.g. tube well, land for borrow

material, public path etc. Redresal Mechanism is followed by keeping the complaint register

on site. So far no complain registered by any community member against the project related

activity. Details of few consultations are given below:

Public consultation was held at RD 384 of PC Upper canal regarding the construction of

temporary diversion channel for construction of new x-Regulator in the canal. Community

was worried about the rehabilitation of their private land at the completion of work. It was

ensured to the land owners that their land will be returned by properly rehabilitated i.e.

level the area, remove all the demolition waste, replace contaminated soil if any with

fertile soil etc.

Public Consultation was held at RD 216 of PC Upper. People were made aware about

the new construction activity of temporary diversion channel. Land acquisition schedule

was properly conveyed to people & they were made sure that they will get full crop

compensation. SFA was also completed with the land owner in the consultation.

A Public Consultation was held at RD 53 PC Upper. People were told about the

construction of new temporary diversion channel from their fields. People were worried

that how will they get crop compensation. They were made assure that a proper crop

Page 22: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 18

compensation & lease of land will be paid against land acquisition. Also they were told

that they will get job opportunity during company’s scope of work.

Public Consultation was held at settlement near the barrage. The purpose of the

consultations was awareness campaign of the project activities, traffic movement from

borrow area to barrage & status of the employment opportunities provided to the local

community. Overall community was satisfied from the contractor’s working style and happy with the progress in the work at the barrage and handling public traffic issued due

the closure of the road bridge and provision of temporary river crossing at downstream of

the barrage. However, few guys were complained about late payments to local labour by

the contractor. The late payment issue was raised in the EPRM and contractor showed

will to rectify this issue.

Consultant and contractor are conducting Public Consultation with communities at

Pakpattan Canal.

7.4 Site Visit of ADB’s Mission and Site Inspections

ADB mission visited at Suleamnki Barrage and Pakpattan Canal on 8th & 9th of October

2015. The mission started their joint visit from Sulemanki Barrage and inspects deck

replacement and main weir gate rehabilitation work at the barrage. After inspecting the

Suleamnki Barrage Camp, a brief presentation on the progress of project in all disciplines

was given to the mission at Sulemanki Barrage Camp Office. Next day three working area

along Pakpattan Main Canal including canal lining and cross regulator construction site and

Contractor’s Camp near Burewala on PI Link Canal were visited. Systematic monitoring and

implementation of the EMP at both contracts was appreciated by the mission in their closing

remarks of the visit. Site inspections and monitoring of implementation of the EMP was also

monitored through regular site visits conducted by PSSC office based staff jointly with PMO.

Page 23: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 19

ADB’s Environmental Specialist & Sociologist are conducting jointly visit with PMO,

Consultant and Contractor staff at project site.

PMO, Consultant and Contractor staff jointly conducting Site Inspection visit at Sulemanki

Barrage

Page 24: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 20

PMO, Consultant and Contractor staff jointly visiting the Borrow Area and Burewala

Contractor’s Camp site

7.5 Implementation of Waste Management Plan

The excavated waste material generated from bela removal activity is disposed off at the low

line area at upstream of the barrage along LMB and main river creek. The disposal sites

were approved by The Engineer and other stakeholder including Pakistan Defense Forces at

Sulemanki Barrage, land owners etc.

Waste generated at camp sites is classified as domestic waste. Domestic Waste collection

and disposal is carrying out by the local TMA (Tahsil Municipal Authority). Clinical waste

generated at the Camp’s dispensary dispose of separately at the local hospitals i.e. Haveli

Lakha Tahsil Hospital, Pakpattan District Hospital and Burewala Tahsil Hospital. Agreement

with TMA is attached as an Annexure 3.

Photographs collected during collection and dumping waste at designated site by TMA

Page 25: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 21

7.6 Implementation of Training Plan

A Training Schedule for last quarter of 2015 (Sep – Dec) was prepared and implement by

the contractor with the collaboration of PSSC. In addition to the planned training session

conducted at all the contractor’s camp weekly toolbox talks were conducted at camp and work sites to cover minimum training of temporary or short period worker. Proposed

Training Schedule for first half of 2016 is attached as an annexure 4.

Contractor is conducting training

Page 26: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report - 3

PSS Consultants 22

ANNEXURE-1: Minutes of Environmental Progress Review Meetings (EPRMs)

Page 27: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 23

EPRM -3

Rehabilitation and Upgrading of Suleimanki Barrage Project

08-09-15 held at Contractor Camp Site Office Suleimanki Barrage

List of participants: : Malik Parvez Arif (DD Environment) PMO, Ahsan Bela (Environment Specialist) PSSC, Haji Amanullah (Sociologist/Environmentalist),

Abdual Star NiaZi-Deputy Construction Manager ( Contractor) Muhammad Razwan (Environmental Officer ) Burewala Camp (Contractor), Muhammad

Ammar Iftaqar Environmental Officer Pakparttan Camp site (Contractor) . Muhammad Deen( Safetr nspector( Contractor)Sulemanki Barrage. Muhammad

Safder (Safety supervisor)Contractor Barrage. Osama Gillani (Safety Suprviser) Contractor

1 2 3 4 5 6 7 8 9

Sr# Action Main

Responsibility

Monitoring

Responsibility Target Date

Previous

decisions Up date.

Decision /

Remarks Status

A Environmental

Monitoring

1 Instrumental

Monitoring/laboratory

based.

Contractor Consultant

Environmentalist

and /PMO (ESU).

Bi -Annual The consultant

will monitor the

contractor in this

regard and will

ensure their

presence during

the 2nd round of

instrumental

monitoring and

keep all

photographic

record of the

monitoring. .

2nd round of

instrumental

monitoring has

been done. All

the parameters

are with in

limit,. Third

round is due in

the month of

November,

2015.

The consultant is

requested to send

the instrumental

monitoring results

to PMO before

next EPRM.

2nd round of

instrumental

Monitoring has been

done. Third round is

due in the month of

November, 2015.

2 Internal Instrumental

Monitoring field based

Contractor Consultant

Environmentalist

and /PMO (ESU).

Daily/ when

required

The Consultant

are advised to

show their

presence during

internal

instrumental

monitoring and

keep all records

Consultants are

showing their

presence during

internal

instrumental

monitoring.

They are

conducting

The consultant

will provide all

instrumental

records in coming

EPRM.

On going Activities.

Page 28: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 24

1 2 3 4 5 6 7 8 9

Sr# Action Main

Responsibility

Monitoring

Responsibility Target Date

Previous

decisions Up date.

Decision /

Remarks Status

with

photographs and

provide all

instrumental

monitoring

results in next

EPRM. .

internal

instrumental

monitoring

regularly

together with

Contractor staff.

3 Compliance Monitoring

improvement

Contractor Consultant

Environmentalist

and /PMO (ESU).

before next

EPRM

The consultants

are requested to

improve the

compliance

monitoring and

instruct the

contractor to

implement the

monitoring plan

according to the

specification as

laid down in the

EMP .

Check lists are

not filled

correctly. Lot of

gaps are there

which needs to

be filled and

corrected

immediately.

The consultant

will look into the

matter and try to

rectify the

checklist

accordingly.

Ongoing Activities.

B Capacity

Building/Training

1 Public Consultation

Contractor Consultant

Environmentalist

and /PMO (ESU).

before next

EPRM

The consultant

Sociologist was

advised to

maintain the

complaint

register and

enter each

complaint with

attribute data.

The complaint

register is not

well maintained.

The format is

not compatible.

No public

consultation was

done in the

month of

August, 2015.

The consultant is

requested to

correct the format

of the complaint

register and also

do purposeful

consultation

regularly. DD

(Environment)

will send the right

format regarding

complaint

register.

On going Activities.

Page 29: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 25

1 2 3 4 5 6 7 8 9

Sr# Action Main

Responsibility

Monitoring

Responsibility Target Date

Previous

decisions Up date.

Decision /

Remarks Status

2 Training Contractor Consultant

Environmentalist

and /PMO (ESU).

before next

EPRM

The consultant

will get all the

training records

along with

photographs and

attendance sheet

from the

contractor (Soft

copy) and send

to PMO

accordingly.

The consultant

did not provide

the training

records to PMO.

Training is

going on

according to the

Training plan.

Consultants are

requested to get

the requisite

information from

the contractor and

send to PMO

before next

EPRM.

On going Activities.

C Institutional

Arrangement

1 The key issues

identified / discussed

during the EPRMs will

be shared with the

HPMO/DPD and SM

(Deacon) on a regular

basis.

PMO Consultant/PMO when

required

The consultants

are advised to

look into the

issues as

discussed under

column 7 and

update about

these issues to

PMO

accordingly.

Regarding

Chines Security,

all the necessary

arrangements s

have been made

by the

Contractor.

On going Activities.

D Management Plans

1 SSEMPs (Barrage)

Approval and

implementation

Contractor Consultant /PMO Before

Construction

Activities.

The Consultant

should be very

vigilant

regarding

supervising the

implementation

of SSEMPs.

SSEMPs

(Barrage) is

being

implemented

and supervised

by the

consultant.

Some gapes are

found which

needs to be

fulfilled by the

DD

(Environment)

advised the

consultant and

Contractor to

fulfill the gapes in

implementation &

supervision of the

SSEMP .

implementation is

continues

Page 30: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 26

1 2 3 4 5 6 7 8 9

Sr# Action Main

Responsibility

Monitoring

Responsibility Target Date

Previous

decisions Up date.

Decision /

Remarks Status

consultant.

2 Waste Disposal Plan

Approval &

implementation

Contractor Consultant/PMO Before next

EPRM

The consultant

were advised to

monitor the

implementation

of the plan

regularly and

provide update

in the next

EPRM.

Approval has

been accorded,

however

implementation

is not doing

well.

The consultants

are requested to

improve the

implementation of

WDP.

implementation is

continues.

4 Traffic Management

Plan (Approval) &

implementation

Contractor Consultant /PMO Before

December

2014

The Consultant

and Contractor

both are advised

to monitor the

implementation

of TMP

carefully and

also pass the

traffic through

diversion

vigilantly.

TMP is being

implemented by

the Contractor

and supervised

by the

consultant

vigilantly.

Sinology

regarding traffic

speed limit and

safety were

inadequate.

Flag man on

both side of the

diversion were

present.

Consultant will

instruct the

Contractor to

fixed proper signe

board at proper

places.

Implementation is

continues

5 Health Safety &

Environment Plan

approval and

implementation

Contractor Consultant /PMO Before

December

2014

The consultant

will check the

Employee's

Safety Violation

Form and also

supervise the

implementation

of HSE plan

diligently.

Approval is

accorded and

being

implemented by

the contractor

and monitored

by the

Consultant

regularly. The

DD (Environment

) instructed the

Consultant

Environmentalist /

Sociologist to

look into the

matter and update

in the coming

EPRM.

Implementation is

continues.

Page 31: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 27

1 2 3 4 5 6 7 8 9

Sr# Action Main

Responsibility

Monitoring

Responsibility Target Date

Previous

decisions Up date.

Decision /

Remarks Status

consultant did

not check the

quality of the

employees

safety violation

form.

E Employments

Opportunity /Status

1 Local Communities Contractor PMO/Consultant Before next

EPRM

The consultant

is reminded to

provide the

employment list

and also monitor

the employment

records

vigilantly.

Maximum

locals’ labours

have been

appointed by the

Contractor.

Consultant will

get the monthly

employment list

from the

Contractor

regularly and

submit to PMO

before next

EPRM.

ongoing activity

F Operation of Camps

1 House keeping Contractor Consultant /PMO before next

EPRM

The Consultant

look into the

matter and ask

the Contractor to

improve the

house keeping at

desired

locations.

There is

improvement in

housekeeping at

work places but

little work is

needed to

improve

housekeeping at

camp site.

The consultant

Environmentalist /

Sociologist will

complete the Job

before next

EPRM.

In progress

2 Surface Drainage Contractor Consultant /PMO before next

EPRM

The consultant

will instruct the

Contractor

strictly to

complete the left

over surface

drainage system

before coming

Surface drainage

conditions are

much better than

previous. Chines

has constructed

a concrete pad in

their working

area and some

The consultant

will instruct the

contractor to

complete the left

over work

regarding surface

water drainage

In progress

Page 32: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 28

1 2 3 4 5 6 7 8 9

Sr# Action Main

Responsibility

Monitoring

Responsibility Target Date

Previous

decisions Up date.

Decision /

Remarks Status

monsoon

season.

work regarding

surface water

drainage are left

in the camp.

3 Construction of Walk

Ways

Contractor Consultant /PMO Before next

EPRM

The consultant

will look into

the matter.

Most of the

work in this

regard has been

completed.

Contractor has

promised to

finish left over

work regarding

walk ways

before next

EPRM.

The Consultant

will monitor the

contractor in this

regard and

ensured the

completion of the

Job.

In progress

G Health

&Safety/Security

1 Doctor/Paramedical

staff availability.

Contractor Consultant /PMO Before next

EPRM

The Consultant

will check all

the things as

narrated under

column 7.

The consultant

checked the

arrangement and

found that only

paramedical

staff is available

at site. MBBS

Doctor is not

appointed yet.

The consultants

are advised to

instruct the

contractor strictly

to fulfill the

requirement of the

contractual

obligation.

In process.

2 Ambulance availability Contractor Consultant /PMO Immediate Continues

inspection is

needed.

Permanent

arrangement of

ambulance is not

existed. On

intermittent

basis the

contractor

arrange the

ambulance and

The consultant is

requested to

instruct the

Contractor strictly

to have

Ambulance 24

hours at site.

In process.

Page 33: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 29

1 2 3 4 5 6 7 8 9

Sr# Action Main

Responsibility

Monitoring

Responsibility Target Date

Previous

decisions Up date.

Decision /

Remarks Status

also Doctor..

3 Safety fencing at

construction site.

Contractor Consultant /PMO Before next

EPRM

The consultant

will monitor

this.

Almost the

construction site

has been

protected by the

Safety Fencing

except 1-2

places where it

was not done.

Consultant will

take care the

matter and intend

to accomplish the

job immediately.

Continues

4 Sinology Contractor Consultant /PMO Before next

EPRM

The Consultant

will pursue in

this regard.

In adequate

sinology were

seen at site.

Consultant will

look into the

matter and place

traffic and safety

sign at proper

places.

In process.

H Social Issue

1 Infrastructure

Development Work Contractor PMO/ Consultant

Not yet

finalized

The consultant

will update to

PMO in next

EPRM. Mr. .

Shiraz PMO is

also requested to

pursue the case.

XEN office

building

construction is

in progress.

The consultant

will pursue the

case

in progress

2 Establishment of Park Contractor PMO/ Consultant Before next

EPRM

The consultant

may look into

the matter.

Not yet started DD (Environment

) instructed the

Consultant

Environmentalist /

Sociologist to

look into the

matter and update

in the coming

EPRM.

In process.

3 Fatal Accident Contractor PMO/ Consultant Before next

EPRM

No previous

decision

A fatal accident

was occurred at

Batch Plant on

The consultant

will pursue the

case and provide

Page 34: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 30

1 2 3 4 5 6 7 8 9

Sr# Action Main

Responsibility

Monitoring

Responsibility Target Date

Previous

decisions Up date.

Decision /

Remarks Status

25-8-2015. The

contractor

managed all his

expenses

regarding

medical

treatment and

funeral.

factual report to

the PMO in this

regard before next

EPRM.

Proposed Date . First week of November.2015.

Page 35: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 31

ANNEXURE-2: Environmental Test Results

Page 36: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 32

Page 37: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 33

Page 38: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 34

Page 39: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 35

Page 40: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 36

Page 41: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 37

Page 42: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 38

Page 43: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 39

Page 44: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 40

Page 45: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 41

Page 46: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 42

Page 47: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 43

Page 48: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 44

Page 49: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 45

Page 50: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 46

Page 51: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 47

Page 52: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 48

Page 53: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 49

Page 54: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 50

Page 55: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 51

Page 56: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 52

Page 57: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 53

Page 58: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 54

Page 59: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 55

Surface Water Quality Monitoring Date: 13-07-2015 Sr# Parameters NEQs

S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Khadir Branch RD 240

PC Upper Canal RD 399

PC Lower Canal RD 629

Instrument

01 PH

6.6-8.5 Ions Concentration

7.6 7,6 7.3 Multi-meter

02 Electrical Conductivity

1055 µs/cm 631 764 808 Multi-meter

03 Total Dissolved Solids (TDS)

350 mg/l

291 287 307 Multi-meter

04 Temperature ≤30 ºC 30 29 31 Multi-meter 05 Dissolved

Oxygen (DO)

4 (at least) mg/l 6.1 9.0 6.8 DO meter

Surface Water Quality Monitoring Date: 06-08-2015 Sr# Parameters NEQs

S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Khadir Branch RD 240

PC Upper Canal RD 399

PC Lower Canal RD 629

Instrument

01 PH

6.6-8.5 Ions Concentration

7.2 7,9 7.4 Multi-meter

02 Electrical Conductivity

1055 µs/cm 751 787 909 Multi-meter

03 Total Dissolved Solids (TDS)

350 mg/l

291 287 307 Multi-meter

04 Temperature

≤30 ºC 34 30 33 Multi-meter

05 Dissolved Oxygen (DO)

4 (at least) mg/l 6.2 9.3 6.7 DO meter

Page 60: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 56

Surface Water Quality Monitoring Date: 14-09-2015 Sr# Parameters NEQs

S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Khadir Branch RD 240

PC Upper Canal RD 399

PC Lower Canal RD 629

Instrument

01 PH

6.6-8.5 Ions Concentration

7.3 7,0 6.7 Multi-meter

02 Electrical Conductivity

1055 µs/cm 809 831 917 Multi-meter

03 Total Dissolved Solids (TDS)

350 mg/l

281 277 367 Multi-meter

04 Temperature

≤30 ºC 29 30 31 Multi-meter

05 Dissolved Oxygen (DO)

4 (at least) mg/l 6.2 9.3 6.7 DO meter

Surface Water Quality Monitoring Date: 17-10-2015 Sr# Parameters NEQs

S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Khadir Branch RD 240

PC Upper Canal RD 399

PC Lower Canal RD 629

Instrument

01 PH

6.6-8.5 Ions Conc

7.3 7,0 7.4 Multi-meter

02 Electrical Conductivity

1055 µs/cm 814 765 965 Multi-meter

03 Total Dissolved Solids (TDS)

350 mg/l

298 297 367 Multi-meter

04 Temperature ≤30 ºC 29 29 31 Multi-meter 05 Dissolved

Oxygen (DO)

4 (at least) mg/l 6.1 5.9 6.7 DO meter

Surface Water Quality Monitoring Date: 22-11-2015

Page 61: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 57

Sr# Parameters NEQs S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Khadir Branch RD 240

PC Upper Canal RD 399

PC Lower Canal RD 629

Instrument

01 PH

6.6-8.5 Ions Conc

6.9 7,6 7.4 Multi-meter

02 Electrical Conductivity

1055 µs/cm 790 765 803 Multi-meter

03 Total Dissolved Solids (TDS)

350 mg/l

291 291 307 Multi-meter

04 Temperature

≤30 ºC 29 33 31 Multi-meter

05 Dissolved Oxygen (DO)

4 (at least) mg/l 6.1 5.9 6.7 DO meter

Surface Water Quality Monitoring Date: 11-12-2015 Sr# Parameters NEQs

S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Khadir Branch RD 240

PC Upper Canal RD 399

PC Lower Canal RD 629

Instrument

01 PH

6.6-8.5 Ions Conc

7.5 7,6 7.4 Multi-meter

02 Electrical Conductivity

1055 µs/cm 626 765 803 Multi-meter

03 Total Dissolved Solids (TDS)

350 mg/l

291 287 307 Multi-meter

04 Temperature

≤30 ºC 29 30 31 Multi-meter

05 Dissolved Oxygen (DO)

4 (at least) mg/l 6.1 9.3 6.7 DO meter

Page 62: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 58

Noise Level Monitoring Month: July, 2015 Sr# Location Date Time Distance

from source Condition Noise

Level dB(A)

01 Batching Plant 10-07-15 8 pm 15 feet Opertational 74 02 Excavators 12-07-15 12 pm 30 feet Working 68 03 Excavators 12-07-15 1 pm 20 feet Stationary 60 04 Tractors 16-07-15 4 pm 30 feet Working 66 05 Camp Generator 22-07-15 11 am 30 feet Operational 67 06 Water Pump 22-07-15 3 pm 30 feet Working 45 07 Machinery

Workshop 28-07-15 3 pm 30 feet Operational 57

Noise Level Monitoring Month: August, 2015 Sr# Location Date Time Distance

from source Condition Noise

Level dB(A)

01 Batching Plant 18-08-15 8 pm 15 feet Opertational 73 02 Excavators 18-08-15 12 pm 30 feet Working 69 03 Excavators 18-08-15 1 pm 20 feet Stationary 67 04 Tractors 18-08-15 4 pm 30 feet Working 69 05 Camp Generator 27-08-15 11 am 30 feet Operational 69 06 Water Pump 27-08-15 3 pm 30 feet Working 44 07 Machinery

Workshop 27-08-15 3 pm 30 feet Operational 56

Noise Level Monitoring Month: September, 2015 Sr# Location Date Time Distance

from source

Condition Noise Level dB(A)

01 Generator Camp-I

12-09-15 3 pm 35 feet Working 77

02 Batching Plant Camp-I

13-09-15 12 pm 30 feet Working 68

03 Generator Camp-II

13-09-15 12 pm 30 feet Working 77

04 Batching Plant Camp-II

23-09-15 4 pm 30 feet Working 69

05 Generator Maachiwal

23-09-15 5 pm 30 feet Working 79

06 Batching Plant Machiwal

23-09-15 3 pm 30 feet Working 70

07 Accommodation Block Camp-I

27-09-15 3 pm 250 feet Operational 48

08 Accommodation Block Camp-II

28-09-15 4pm 100 feet Operational 57

Page 63: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 59

Noise Level Monitoring Month: October, 2015 Sr# Location Date Time Distance

from source

Condition Noise Level dB(A)

01 Generator Camp-I

12-10-15 3 pm 35 feet Working 75

02 Batching Plant Camp-I

13-10-15 12 pm 30 feet Working 64

03 Generator Camp-II

13-10-15 12 pm 30 feet Working 73

04 Batching Plant Camp-II

23-10-15 4 pm 30 feet Working 68

05 Generator Maachiwal

23-10-15 5 pm 30 feet Working 71

06 Batching Plant Machiwal

23-10-15 3 pm 30 feet Working 72

07 Accommodation Block Camp-I

27-10-15 3 pm 250 feet Operational 45

08 Accommodation Block Camp-II

28-10-15 4pm 100 feet Operational 58

Noise Level Monitoring Month: November, 2015 Sr# Location Date Time Distance

from source

Condition Noise Level dB(A)

01 Generator Camp-I

22-11-15 11 am 35 feet Working 74

02 Batching Plant Camp-I

22-11-15 11 am 30 feet Working 69

03 Generator Camp-II

22-11-15 3 pm 30 feet Working 72

04 Batching Plant Camp-II

22-11-15 3 pm 30 feet Working 68

05 Generator Maachiwal

22-11-15 5:30 pm

30 feet Working 85

06 Batching Plant Machiwal

22-11-15 5:30 pm

30 feet Working 70

07 Accommodation Block Camp-I

22-11-15 11:30 am

250 feet Operational 48

08 Accommodation Block Camp-II

22-11-15 3:30 am

100 feet Operational 55

Page 64: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 60

Noise Level Monitoring Month: December, 2015 Sr# Location Date Time Distance

from source

Condition Noise Level dB(A)

01 Generator Camp-I

14-12-15 11:30 am

35 feet Working 73

02 Batching Plant Camp-I

14-12-15 11 am 30 feet Working 68

03 Generator Camp-II

26-12-15 2:30 pm

30 feet Working 76

04 Batching Plant Camp-II

26-12-15 3 pm 30 feet Working 67

05 Generator Maachiwal

23-12-15 5 pm 30 feet Working 83

06 Batching Plant Machiwal

23-12-15 5: pm 30 feet Working 69

07 Accommodation Block Camp-I

14-12-15 11:30 am

250 feet Operational 47

08 Accommodation Block Camp-II

26-12-15 3:30 pm

100 feet Operational 56

INSTRUMENTAL MONITORING RESULTS (ICB-02)............. July, 2015

Location: Suleimanki Barrage Date: 17-07-15 Sr. No

Parameters NEQs S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Upstream Coffer Dam

Down Stream Coffer Dam

Any other Site

Instrument

1 PH 6.6-8.5 Ions Concentration

6.9

7.2

N/A

Multi-meter

2 ELECTRICAL CONDUCTIVITY

1055 µs/cm 682 720

N/A Multi-meter

3 DISSOLVED OXYGEN

4 mg/l

3.4 6.1 N/A DO- meter

4 TEMPERATURE ≤30 ºC 32 31.5 N/A Multi-meter

5 TOTAL DISSOLVED SOLIDS (TDS)

350 mg/l 223 199 N/A Multi-meter

Page 65: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 61

Monthly Noise Monitoring results for PCSBIP/ICB-02 17-07-2015 SR.NO LOCATION NOISE LEVEL

1 GENERATOR AT LEFT SIDE OF BARRAGE 75dB

2 DURING ACTIVITY AT DEK SLAB 69dB

3 GENERATOR AT GATE NO.8 82dB

4 PEETER AT UNDER SLUCE 80dB

INSTRUMENTAL MONITORING RESULTS (ICB-02).......August, 2015

Location: Slueimanki Barrage Date: 25-08-15 SR. NO

Parameters NEQs S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Upstream Coffer Dam

Down Stream Coffer Dam

Any other Site

Instrument

1 PH 6.6-8.5 Ions Conc

7.5 7.1 N/A Multi-meter

2 ELECTRICAL CONDUCTIVITY

1055 µs/cm 800 790 N/A Multi-meter

3 DISSOLVED OXYGEN

4 mg/l

4.5 5.6 N/A DO- meter

4 TEMPERATURE ≤30 ºC 32 32 N/A Multi-meter

5 TOTAL DISSOLVED SOLIDS (TDS)

350 mg/l 300 295 N/A Multi-meter

Monthly Noise Monitoring results for PCSBIP/ICB-02 Date: 25-08-15

SR.NO LOCATION NOISE LEVEL

1 GENERATOR AT LEFT SIDE OF BARRAGE 80dB

2 DURING ACTIVITY AT DEK SLAB 75dB

3 GENERATOR AT GATE NO.8 80db

Page 66: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 62

4 PEETER AT UNDER SLUCE

75db

INSTRUMENTAL MONITORING RESULTS (ICB-02)...September, 2015

Location: Slueimanki Barrage Date: 15-09-15 Sr. No

Parameters NEQs S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Upstream Coffer Dam

Down Stream Coffer Dam

Any other Site

Instrument

1

PH

6.6-8.5

Ions Conc

7.5

7.6

N/A

Multi-meter

2

ELECTRICAL CONDUCTIVITY

1055

µs/cm

907

943

N/A

Multi-meter

3

DISSOLVED OXYGEN

4

mg/l

7.2

7.5

N/A

DO- meter

4

TEMPERATURE ≤30

ºC

28

27.5

N/A

Multi-meter

5

TOTAL DISSOLVED SOLIDS (TDS)

350

mg/l

287

2296

N/A

Multi-meter

Monthly Noise Monitoring results for PCSBIP/ICB-02 Date: 15-09-15 SR.NO LOCATION NOISE LEVEL

1 GENERATOR AT LEFT SIDE OF BARRAGE 77dB

2 DURING ACTIVITY AT DEK SLAB 72dB

3 GENERATOR AT GATE NO.8 82db

4 PEETER AT UNDER SLUCE 79db

INSTRUMENTAL MONITORING RESULTS (ICB-02)......OCTOBER, 2015

Surface Water Quality Tests

Page 67: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 63

Date; 17-10-2015 Sr #

Parameters NEQs S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Upstream Coffer Dam

Down Stream Coffer Dam

Any other Site

Instrument

1 PH

6.6-8.5 Ions Conc

9.8 8.5 N/A Multi-meter

2 ELECTRICAL CONDUCTIVITY

1055 µs/cm

900 850 N/A Multi-meter

3 DISSOLVED OXYGEN

4 mg/l

3.5 7.5 N/A DO-

meter

4 TEMPERATURE

≤30 ºC 30 29.8 N/A Multi-

meter

5 TOTAL DISSOLVED SOLIDS (TDS)

350 mg/l 260 240 N/A Multi-

meter

Noise Level Monitoring Date:17-10-2015

Sr# Location Date Time Distance

from

source

Condition Noise Level

dB(A)

01 Batching Plant

17-10-15 11 am 15 feet Operational 62

02 Generator at left side

of Barrage

17-10-15 12 pm 30 feet Working 79

03 Deck Slab Activity

17-10-15 12 pm 20 feet Stationary 77

04 Generator at

gate# 8

17-10-15 1 pm 30 feet Working 71

Page 68: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 64

INSTRUMENTAL MONITORING RESULTS (ICB-02)....November, 2015

Location: Slueimanki Barrage Date: 19-11-15 SR. NO

Parameters NEQs S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Upstream Coffer Dam

Down Stream Coffer Dam

Any other Site

Instrument

1 PH 6.6-8.5 Ions Conc

8.5 8.2 N/A Multi-meter

2 ELECTRICAL CONDUCTIVITY

1055 µs/cm 780 720 N/A Multi-meter

3 DISSOLVED OXYGEN

4 mg/l

3.0 6.2 N/A DO- meter

4 TEMPERATURE ≤30 ºC 22 21 N/A Multi-meter

5 TOTAL DISSOLVED SOLIDS (TDS)

350 mg/l 210 200 N/A Multi-meter

Monthly Noise Monitoring results for PCSBIP/ICB-02 Date: 19-11-15 SR.NO LOCATION NOISE LEVEL

1 GENERATOR AT LEFT SIDE OF BARRAGE 80dB

2 DURING ACTIVITY AT DEK SLAB 72dB

3 GENERATOR AT GATE NO.8 76db

4 PEETER AT UNDER SLUCE 82db

Page 69: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 65

INSTRUMENTAL MONITORING RESULTS (ICB-02)..DECEMBER, 2015

Surface Water Quality Tests Date; 15-12-2015 Sr #

Parameters NEQs S.R.O 1062 (1) 2010 Effective from 01/01/2015

Unit Upstream Coffer Dam

Down Stream Coffer Dam

Any other Site

Instrument

1 PH

6.6-8.5 Ions Conc

9.8 8.5 N/A Multi-meter

2 ELECTRICAL CONDUCTIVITY

1055 µs/cm

900 850 N/A Multi-meter

3 DISSOLVED OXYGEN

4 mg/l

3.5 7.5 N/A DO-

meter

4 TEMPERATURE

≤30 ºC 30 29.8 N/A Multi-

meter

5 TOTAL DISSOLVED SOLIDS (TDS)

350 mg/l 260 240 N/A Multi-

meter

Noise Level Monitoring

Date:15-12-2015

Sr# Location Date Time Distance from source

Condition Noise Level dB(A)

01 Batching Plant

17-10-15 11 am 15 feet Operational 62

02 Generator at left side of Barrage

17-10-15 12 pm 30 feet Working 79

03 Deck Slab Activity

17-10-15 12 pm 20 feet Stationary 77

04 Generator at gate# 8

17-10-15 1 pm 30 feet Working 71

Page 70: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 66

ANNEXURE-3: Agreement with TMA

Page 71: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 67

Page 72: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 68

Page 73: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 69

Page 74: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 70

ANNEXURE-4: Proposed Training Schedule for January to July 2016

Page 75: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 71

Training Plan For PCSBIP ICB-01 & ICB-02 (January to June 2016)

Sr #

Date Training Contents Trainer Trainee Venue & Time

01 28-01-2016

HSE plan; Camp operation, Waste disposal, Natural resource conservation & Housekeeping

Environmental Officer of Contractor in the presence of Consultant's Environmentalist

Camp Staff & Construction Site Supervisors

At Each Contractor’s Camp 11:00 am

02 23-02-2016

Electrical / Mechanical Safety Environmental Officer of Contractor in the presence of Consultant's Environmentalist

Camp Staff & Construction Site Supervisors

At Each Contractor’s Camp 11:00 am

03 22-03-2016

Fire Fighting Environmental Officer of Contractor in the presence of Consultant's Environmentalist

Camp Staff & Local Office Staff

At Each Contractor’s Camp 11:00 am

04 19-04-2016

House Keeping Environmental Officer of Contractor in the presence of Consultant's Environmentalist

Camp Staff, Construction Site Supervisors & Local Office Staff

At Each Contractor’s Camp 11:00 am

05 13-05-2016

How to Use PPEs & First Aid Environmental Officer of Contractor in the presence of Consultant's

Construction Site Workers At Each Contractor’s Camp 11:00 am

Page 76: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 72

Sr #

Date Training Contents Trainer Trainee Venue & Time

Environmentalist & MBBS Doctor

06 22-05-2016

HSE plan; Road safety; Road restrictions; Vehicle restrictions; Defensive driving; Waste disposal; Social and cultural values of the area

Environmental Officer of Contractor in the presence of Consultant's Environmentalist & MBBS Doctor

Drivers At Each Contractor’s Camp 11:00 am

07 To be Confirmed

Environmental and social aspects, particularly the sensitivities of the project; Wildlife and vegetation related sensitivities of the project; Key finding of the EMP; Mitigation measures; Contingency plan; Community issues; Social and cultural values of the area

Consultant's Environmental / Resettlement Specialist (Mr. Ahsan Bela) With collaboration of PMO’s DD Environment (Mr. Parvez Malik)

All site supervisors, Site Managerial staff, site engineers, Environment, social, health and safety staff. Consultants: Site Managerial staff and engineers

(to be confirmed)

Page 77: Punjab Irrigated Agriculture Investment Program - Tranche ...which is 9.25% of the total irrigated area of Punjab (27 million acres) and has considerable contribution in the agricultural

Pakpattan Canal and Sulemanki Barrage Bi-Annual Environmental Improvement Project (PCSBIP) Progress Report

PSS Consultants 73