    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    ECAD/MCAD-Collaboration

    General, underlying Use Case

    "Moving a mounting hole

    May 2007

    Chairman: Hans-Ulrich Heidbrink, Mentor GraphicsProSTEP Contact: Dr. Arnulf Frhlich, PROSTEP AG

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    2/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    ECAD/MCAD-Collaboration: Project Aim

    Aim of the ProSTEP iViP Associations

    ECAD/MCAD-Collaboration is to

    facilitate collaboration between the ECADand MCAD domains in such a way that

    users in one domain have access to all

    relevant information in the other domain.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    3/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    Current Project Participants

    Delphi

    Siemens VDO

    :em

    Mentor Graphics

    PDTec

    PROSTEP PTC

    UGS

    xPLM

    FU Hagen

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    4/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    Use Case: Moving a mounting hole 1/3

    Engineer Knut

    Engineer Paula

    I want tomove this

    hole

    to thisnew

    position

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    5/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    Use Case: Moving a mounting hole 2/3

    Engineer Knut

    Engineer Paula

    This newposition is

    not suitable

    what isabout this

    one.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    6/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    Use Case: Moving a mounting hole 3/3

    Engineer Knut

    Engineer Paula

    This newposition is

    suitablefor me.

    Thankyou!

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    7/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    Use case preconditions

    A design of the mechanical surrounding is available (majormechanical/electrical elements were placed (plugs, connections, LEDsetc.))

    The PCB board outline is defined within the

    mechanical CAD-system The use case can be done in synchronous or asynchronous mode:

    In synchronous mode the changes are shown while designers communicatethrough another channel.

    In asynchronous mode the information is stored and the designers canupdate the models on demand.

    There are there spaces, where data is stored: ECAD: Represents the ECAD-System including the collaboration module

    MCAD: Represents the MCAD-System including the collaboration module Collaboration Space: Represents the shared data, where all relevant data

    is stored.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    8/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    1

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    MCAD starts the design of the 3D geometry in the MCAD system.Designs also components with electrical/mechanical function(plugs, LEDs, switches) or big mechanical impact (big ICs,capacitors). Also the mounting holes of the PCB are defined. Thiscomponents need to be marked within the 3D CADmodel in order

    to distinguish between the pure 3D geometry like a hole and thesemantic information that this hole represents a "mounting hole"

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    9/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    MCAD starts the design of the

    3D geometry in the

    MCADsystem. Designs also

    components withelectrical/mechanical function(plugs, LEDs, switches) or bigmechanical impact (big ICs,

    capacitors). Also the mounting

    holes of the PCB are defined.This components need to bemarked within the 3D

    CADmodel in order to

    distinguish between the pure3D geometry like a hole and thesemantic information that this

    hole represents a "mounting

    hole"

    1

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    Starts the schematic design based on the functionalrequirements.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    10/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    Starts the schematic design

    based on the functional

    requirements.

    MCAD starts the design of the

    3D geometry in the

    MCADsystem. Designs also

    components withelectrical/mechanical function(plugs, LEDs, switches) or bigmechanical impact (big ICs,

    capacitors). Also the mounting

    holes of the PCB are defined.This components need to bemarked within the 3D

    CADmodel in order to

    distinguish between the pure3D geometry like a hole and thesemantic information that this

    hole represents a "mounting

    hole"

    1

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    11/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    2

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    After finishing the first version of the design a 2Dboardoutline with position information about thecomponents with mechanical/electrical interfacefunction needs to be generated

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    12/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    After finishing the first version

    of the design a 2D boardoutline

    with position information about

    the components withmechanical/electrical interfacefunction needs to be generated

    2

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    Schematic generates the netlist with the componentsand their interconnection.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    13/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    Schematics generates the

    netlist with the components and

    their interconnection.

    After finishing the first version

    of the design a 2D boardoutline

    with position information about

    the components withmechanical/electrical interfacefunction needs to be generated

    2

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    14/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    MCAD sends board outline to

    the Collaboration Space3

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    MCAD sends board outline to the Collaboration Space

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    15/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    Collaboration Space includes all

    collaboration relevant parts of

    the design.

    MCAD sends board outline to

    the Collaboration Space3

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    Collaboration Space includes all collaborationrelevant parts of the design.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    16/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    The synchronization of

    components IDs is done within

    the communication

    Collaboration Space includes all

    collaboration relevant parts of

    the design.

    MCAD sends board outline to

    the Collaboration Space3

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    The synchronization of components IDs is done withinthe communication

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    17/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    The synchronization of

    components IDs is done within

    the communication

    Collaboration Space includes all

    collaboration relevant parts of

    the design.

    MCAD sends board outline to

    the Collaboration Space3

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    A 1 2 3 3

    B 2 3 5 4C 3 4 5 4D 3 4 5 4E 2 3 4 4

    A 1 2 3 3B 2 3 5 4C 3 4 5 4D 3 4 5 4E 2 3 4 4

    ECAD reads base line from collaboration space andnet list from Schematic, so layout can be done.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    18/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    ECAD reads base line from

    collaboration space and net list

    from layout, so layout can bedone.

    The synchronization of

    components IDs is done within

    the communication

    Collaboration Space includes all

    collaboration relevant parts of

    the design.

    MCAD sends board outline to

    the Collaboration Space3

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    A 1 2 3 3

    B 2 3 5 4C 3 4 5 4D 3 4 5 4E 2 3 4 4

    A 1 2 3 3B 2 3 5 4C 3 4 5 4D 3 4 5 4E 2 3 4 4

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    19/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    4

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    Due to additional mechanical requirements (blueelement). The position of a mounting hole needs to beupdated. MCAD opens the 3D-model and modifies thehole-feature with the semantic "mounting hole" (an ID

    mapping already exist, see step 3)

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    20/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    Due to additional mechanical

    requirements (blue element).

    The position of a mounting holeneeds to be updated. MCAD

    opens the 3D-model andmodifies the hole-feature withthe semantic "mounting hole"

    (an ID mapping already exist,

    see step 3)

    4

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    21/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    5

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    Due to the fact that the electrical designer has done aPCB layout based on the first version the mechanicaldesigner wants see if the placement modification isOK from the PCB point of view. He starts to send the

    changes to the collaboration space.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    22/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    Due to the fact that the

    electrical designer has done a

    PCB layout based on the firstversion the mechanical

    designer wants see if theplacement modification is OKfrom the PCB point of view. He

    starts to send the changes to

    the collaboration space.

    5

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    The collaboration model for the change request isinitialized with reduced information (releasedinformation) and the new position of the mountinghole.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    23/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    The collaboration model for the

    change request is initialized

    with reduced information(released information) and the

    new position of the mountinghole.

    Due to the fact that the

    electrical designer has done a

    PCB layout based on the firstversion the mechanical

    designer wants see if theplacement modification is OKfrom the PCB point of view. He

    starts to send the changes to

    the collaboration space.

    5

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    The change request is send via EDMDService.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    24/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    The change request is send via

    EDMDService.

    The collaboration model for the

    change request is initialized

    with reduced information(released information) and the

    new position of the mountinghole.

    Due to the fact that the

    electrical designer has done a

    PCB layout based on the firstversion the mechanical

    designer wants see if theplacement modification is OKfrom the PCB point of view. He

    starts to send the changes to

    the collaboration space.

    5

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    Message is received and the user is asked if he wantsto collaborate.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    25/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    Message is received and the

    user is asked if he wants to

    collaborate.

    The change request is send via

    EDMDService.

    The collaboration model for the

    change request is initialized

    with reduced information(released information) and the

    new position of the mountinghole.

    Due to the fact that the

    electrical designer has done a

    PCB layout based on the firstversion the mechanical

    designer wants see if theplacement modification is OKfrom the PCB point of view. He

    starts to send the changes to

    the collaboration space.

    5

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    After accepting the collaboration request the modelwill be retrieved and opened in collaboration mode,the changes are loaded to the ECAD-System. Howchanges are visualized and shown to the user is up to

    the special application (e.g. integrated in the CAD-System, special collaboration viewer, ).

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    26/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    After accepting the

    collaboration request the model

    will be retrieved and opened incollaboration mode, the

    changes are loaded to theECAD-System. How changesare visualized and shown to the

    user is up to the special

    application (e.g. integrated inthe CAD-System, specialcollaboration viewer, ).

    Message is received and the

    user is asked if he wants to

    collaborate.

    The change request is send via

    EDMDService.

    The collaboration model for the

    change request is initialized

    with reduced information(released information) and the

    new position of the mountinghole.

    Due to the fact that the

    electrical designer has done a

    PCB layout based on the firstversion the mechanical

    designer wants see if theplacement modification is OKfrom the PCB point of view. He

    starts to send the changes to

    the collaboration space.

    5

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    Remark:There could be some components with nocorrespondence in the MCAD world and vice versa.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    27/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    After accepting the

    collaboration request the model

    will be retrieved and opened incollaboration mode, the

    changes are loaded to theECAD-System. How changesare visualized and shown to the

    user is up to the special

    application (e.g. integrated inthe CAD-System, specialcollaboration viewer, ).

    Message is received and the

    user is asked if he wants to

    collaborate.

    The change request is send via

    EDMDService.

    The collaboration model for the

    change request is initialized

    with reduced information(released information) and the

    new position of the mountinghole.

    Due to the fact that the

    electrical designer has done a

    PCB layout based on the firstversion the mechanical

    designer wants see if theplacement modification is OKfrom the PCB point of view. He

    starts to send the changes to

    the collaboration space.

    5

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    Remark:There could be somecomponents with no

    correspondence in the

    MCAD world and vice versa.

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    28/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    6

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    The ECAD designer checks the change request, in thiscase the new position of the mounting hole. ECADsystem will provide assistance. In this sample themounting hole color turns to red. If there is a special

    collaboration viewer it checks the change against thenative data.

    LMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    29/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    The ECAD designer checks the

    change request, in this case the

    new position of the mountinghole. ECAD system will provide

    assistance. In this sample themounting hole color turns tored. If there is a special

    collaboration viewer it checks

    the change against the nativedata.

    6

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    L tMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    30/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    7

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    On recognizing the problem the ECAD-System sendsa reject to the collaboration space.

    L tMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    31/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    On recognzing the problem the

    ECAD-System sends a reject

    to the collaboration space.7

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    The changed version is marked as rejected in thecollaboration space.

    S h tiLa o tC ll b tiEDMDS iC ll b tiMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    32/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    On recognzing the problem the

    ECAD-System sends a reject

    to the collaboration space.

    The changed version is marked

    as rejected in the collaboration

    space.7

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    The reject mark is transfered via EDMDService.

    SchematicLayoutCollaborationEDMDSer iceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    33/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    On recognzing the problem the

    ECAD-System sends a reject

    to the collaboration space.

    The changed version is marked

    as rejected in the collaboration

    space.

    The reject mark is transfered

    via EDMDService.7

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    The MCAD designer is informed about the rejection.

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    34/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    On recognzing the problem the

    ECAD-System sends a reject

    to the collaboration space.

    The changed version is marked

    as rejected in the collaboration

    space.

    The reject mark is transfered

    via EDMDService.

    The MCAD designer is

    informed about the rejection.7

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    35/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    8

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    ECAD designer moves the mounting hole to validposition based in the routing. ECAD supports ECADdesigner by checking the new position against hislayout.

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    36/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    ECAD designer moves the

    mounting hole to valid position

    based in the routing. ECADsupports ECAD designer by

    checking the new positionagainst his layout.

    8

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    The new position is loaded to the collaboration space.

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    37/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    ECAD designer moves the

    mounting hole to valid position

    based in the routing. ECADsupports ECAD designer by

    checking the new positionagainst his layout.

    The new position is loaded to

    the collaboration space.8

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

    The new position is send as change request byEDMDService

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    38/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    ECAD designer moves the

    mounting hole to valid position

    based in the routing. ECADsupports ECAD designer by

    checking the new positionagainst his layout.

    The new position is loaded to

    the collaboration space

    The new position is send as

    change request by

    EDMDService8

    Sc e at cLayoutCo abo at oSe ceCo abo at oMCAD

    The new position is loaded to MCAD and shown to theuser. It is up to the application in which way this isdone.

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    39/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    ECAD designer moves the

    mounting hole to valid position

    based in the routing. ECADsupports ECAD designer by

    checking the new positionagainst his layout.

    The new position is loaded to

    the collaboration space

    The new position is send as

    change request by

    EDMDService

    The new position is loaded to

    MCAD and shown to the user.

    It is up to the application inwhich way this is done.

    8

    LayoutMCAD

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    40/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    9

    LayoutMCAD

    The MCAD designer checks the change request, inthis case the new position of the mounting hole.MCAD system will provide assistance. If there is aspecial collaboration viewer it checks the change

    against the native data.

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    41/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    The MCAD designer checks the

    change request, in this case the

    new position of the mountinghole. MCAD system will provide

    assistance. If there is a specialcollaboration viewer it checksthe change against the native

    data.

    9

    y

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    42/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    10

    y

    After checking the new data was successfull theMCAD designer accepts the new position of themounting hole.

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    43/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    After checking the new data

    was successfull the MCAD

    designer accepts the newposition of the mounting hole.

    10

    y

    The changed version is marked as accepted in thecollaboration space.

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    44/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    The changed version is marked

    as accepted in the

    collaboration space.

    After checking the new data

    was successfull the MCAD

    designer accepts the newposition of the mounting hole.

    10

    The accept mark is transfered via EDMDService.

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    45/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    The accept mark is transfered

    via EDMDService.

    The changed version is marked

    as accepted in the

    collaboration space.

    After checking the new data

    was successfull the MCAD

    designer accepts the newposition of the mounting hole.

    10

    The ECAD designer is informed about the acceptance.

    SchematicLayoutCollaborationEDMDServiceCollaborationMCAD

  • 8/3/2019 ProSTEP iViP Use Case ECAD MCAD Collaboration 1.0

    46/46

    Establishing Leadership in IT-Based Engineering

    2007, ProSTEP iViP e.V. 07-08-09

    The ECAD designer is informed

    about the acceptance.

    The accept mark is transfered

    via EDMDService.

    The changed version is marked

    as accepted in the

    collaboration space.

    After checking the new data

    was successfull the MCAD

    designer accepts the newposition of the mounting hole.

    10