Top Banner
20567651.3 December 2015 1 Project Report Stanton Territorial Hospital December 2015
32

Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

Apr 21, 2018

Download

Documents

duongthien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

1

Project Report

Stanton Territorial Hospital

December 2015

Page 2: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

2

Purpose of this project report

The purpose of this project report (“Project Report”) is to provide key information to the public about

the Stanton Territorial Hospital Renewal Project (the “Project”). This Project Report describes the need

for the Project, how it will be delivered, how different procurement delivery methods were analyzed,

and how project benefits and innovations are expected to be achieved. A summary of the key aspects of

the Project Agreement is also provided at Section 4 of this Project Report.

In all of its procurement processes, the Government of the Northwest Territories (“GNWT”) is

committed to a high standard of disclosure as part of its accountability for the delivery of public

projects. Departments, Crown Corporations and other government agencies are publicly accountable for

projects through regular budgeting, auditing and reporting processes.

GNWT is accountable for the contents of this Project Report.

Defined terms and abbreviations

Capitalized terms used in this Project Report that are not defined are set out in the Glossary of Terms at

Section 6 of this Project Report.

Page 3: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

3

Table of contents

1. EXECUTIVE SUMMARY .................................................................................................................................. 5

2. PROJECT OVERVIEW ..................................................................................................................................... 7

2.1 BACKGROUND AND OBJECTIVES ............................................................................................................................... 7

2.2 SCOPE OF THE PROJECT ......................................................................................................................................... 8

2.2.1 The new Stanton Territorial Hospital ..................................................................................................... 8

2.2.2 Existing Hospital..................................................................................................................................... 9

2.3 PROJECT BENEFITS AND KEY FEATURES .................................................................................................................... 10

3. COMPETITIVE SELECTION PROCESS ............................................................................................................. 12

3.1 REQUEST FOR QUALIFICATIONS ............................................................................................................................. 12

3.2 REQUEST FOR PROPOSALS .................................................................................................................................... 13

3.3 EVALUATION OF PROPOSALS ................................................................................................................................. 14

3.3.1 Technical submissions .......................................................................................................................... 14

3.3.2 Financial submissions ........................................................................................................................... 14

3.3.3 Overall outcome ................................................................................................................................... 15

3.4 NEW BUILD SOLUTION ......................................................................................................................................... 15

3.5 FAIRNESS ADVISOR ............................................................................................................................................. 17

4. THE FINAL PROJECT AGREEMENT ................................................................................................................ 18

4.1 OVERVIEW ........................................................................................................................................................ 18

4.2 PROFILE OF THE PRIVATE SECTOR PARTNER ............................................................................................................. 18

4.3 KEY TERMS OF THE PROJECT AGREEMENT ................................................................................................................ 19

4.3.1 New hospital ........................................................................................................................................ 19

4.3.2 Existing Hospital................................................................................................................................... 19

4.4 PERFORMANCE-BASED PAYMENT PRINCIPLES ........................................................................................................... 20

4.5 ADJUSTMENTS TO THE AVAILABILITY PAYMENTS ....................................................................................................... 20

4.6 RISK ALLOCATION SUMMARY ................................................................................................................................ 21

4.7 FINANCIAL SUMMARY .......................................................................................................................................... 23

4.8 QUANTITATIVE BENEFITS ...................................................................................................................................... 23

4.9 ACCOUNTING TREATMENT .................................................................................................................................... 24

5. ONGOING PROJECT AGREEMENT MONITORING ......................................................................................... 25

5.1 DESIGN AND CONSTRUCTION PHASE ....................................................................................................................... 25

5.2 MAINTENANCE AND REHABILITATION PHASE ............................................................................................................ 25

5.3 END OF PROJECT AGREEMENT .............................................................................................................................. 26

5.4 QUALITY MANAGEMENT THROUGHOUT THE PROJECT TERM ........................................................................................ 26

6. GLOSSARY OF TERMS .................................................................................................................................. 27

APPENDIX A – P3 PROCUREMENT PROCESS ......................................................................................................... 29

METHODOLOGY ........................................................................................................................................................... 29

PROCUREMENT OPTIONS ............................................................................................................................................... 31

RESULTS OF THE PROCUREMENT OPTIONS ANALYSIS ........................................................................................................... 32

Page 4: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

4

ACHIEVING VALUE FOR MONEY ....................................................................................................................................... 32

Page 5: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

5

1. Executive summary

Figure 1 - Preliminary rendering of the Facility

The Stanton Territorial Hospital Renewal Project is a high priority project for GNWT in order to meet

changing healthcare needs and population growth in the Northwest Territories. The Project will involve

the construction of a new facility as well as the redevelopment and repurposing of the existing hospital

building. The new facility will provide state of the art health care and diagnostic services to residents of

the Northwest Territories and surrounding regions, and is expected to meet population growth through

to 2050.

The procurement process for the Project, led by GNWT, began in June 2014 with the RFQ phase. Three

teams were shortlisted for the RFP Phase in September 2014:

Boreal Health Partnership

EllisDon Infrastructure

Plenary Health

In September 2015, following a competitive selection process based on the principles of openness,

fairness, and transparency, GNWT entered into a performance based, fixed price Project Agreement

with Boreal Health Partnership to deliver the Project. Boreal Health Partnership will design, build,

finance, operate, maintain and perform life cycle rehabilitation on the Facility for a 30 year term

following a construction period of approximately 3 years.

Page 6: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

6

The Facility will have 100 inpatient beds in single patient rooms, compared to 67 in the Existing Hospital,

as well as:

A larger and better equipped emergency department as well as more space for ambulatory care

including specialist clinics, medical day care and dialysis

Enhanced medical technology throughout the hospital to improve quality of care and clinical

efficacy

Incorporation of sustainable energy engineering practices

Boreal Health Partnership will provide a range of services during the operating period including

Housekeeping, waste management, laundry and linen, and catering services

Roads, grounds, and landscape maintenance

Parking management and security services

Customer-related services, including technical support and assistance and operation of a help

desk

Maintaining the Facility over a 30-year operating phase including routine, planned and

unplanned maintenance

Returning the Facility in a fully maintained condition at the end of the Project Agreement term.

Boreal Health Partnership will receive a monthly service payment for these services, subject to

performance standards including Facility availability and quality of service. Payments will be reduced if

Boreal Health Partnership does not meet the rigorous performance standards contained within the

Project Agreement.

The Project Agreement also contains well defined specifications regarding the quality of the Facility after

the 30 year operating term, outlining the required remaining life of various components of the Facility. If

these specifications are not met, Boreal Health Partnership will be subject to financial penalty.

The Project is estimated to achieve value for money of $174.5 million in Net Present Cost terms

compared to traditional procurement, with a significant proportion of Project risk transferred from

GNWT to Boreal Health Partnership, including construction schedule risk as well as cost and

performance risk over the operating period.

An independent external Fairness Advisor, RFP Solutions, was engaged to monitor the competitive

selection process and concluded that it was fair and impartial.

Page 7: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

7

2. Project overview

2.1 Background and objectives

The existing Stanton Territorial Hospital (the “Existing Hospital”), located in Yellowknife, Northwest

Territories, is the main hospital for the Stanton Territorial Health Authority (“STHA”). The STHA provides

acute secondary, tertiary and other specialized health care to the residents of the Northwest Territories

as well as the Kitikmeot Region of Nunavut, servicing a total population of 47,500 (Census, 2011). The

Existing Hospital offers the highest level of hospital care and diagnostic and therapeutic services

available in the Northwest Territories.

The Existing Hospital has been in service for over 26 years, constructed in 1985-1987. It is located on Lot

1, Block 162, between the Old Airport Road and Frame Lake, and consists of three floors plus a

penthouse with a building gross square meters (GSM) total of 13,300.

The need for the Project is driven by the following:

Technical renewal

o The Existing Hospital is more than 25 years old and technical renewal is considered a

necessity in order to sustain a modern, up-to-date, safe, and comfortable health care

environment

Changing healthcare needs and program renewal

o In the 25 years since the Existing Hospital was built, the nature of health care in the

Northwest Territories and Canada has changed, with advances in patient care and

medicine as well as in standards of service delivery; notably infection control and spatial

standards

o Additionally, there has been an increased focus on ambulatory care which has outpaced

the demand for inpatient beds. As such, many departments in the Existing Hospital are

ill equipped for the nature and volume of services now demanded of the facility

Population growth

o The population of the primary catchment area for the STHA, which includes the

Northwest Territories and the Kitikmeot Region of Nunavut, is expected to grow by

approximately 13% over the next 35 years

o In order to meet forecasted growth the Existing Hospital requires both larger and better

equipped facilities, capable of handling and providing for a diversity of clinical and

diagnostic needs

Page 8: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

8

2.2 Scope of the Project

2.2.1 The new Facility

The Project is anticipated to nearly double the current floor area (compared to the Existing Hospital),

and will include the following key components:

A new and larger emergency department

A bigger and better equipped medical laboratory

Additional space for diagnostic imaging

Enhanced medical technology throughout the hospital to improve quality of care and clinical efficacy

More space for surgery and day procedures

Additional space for ambulatory care including specialist clinics, medical day care and dialysis

More space for support services such as sterile reprocessing

More inpatient beds, all in single rooms. The Facility will have 100 inpatient beds, compared to 80

beds in the Existing Hospital (including 67 inpatient beds and 13 Extended Care beds)

Incorporation of sustainable energy engineering practices

Expansion of parking

Allowance for future growth and expansion.

Figure 2 - Preliminary rendering of the Facility

Page 9: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

9

2.2.2 Existing Hospital

With respect to the renewal of the Existing Hospital, a detailed technical status evaluation completed in

2012 indicated that the existing building envelope and structural elements were in very good condition

and have sufficient remaining life to accommodate a midlife retrofit. Accordingly, the indicative design

for the Project developed by the GNWT’s technical advisors involved a redevelopment of the Existing

Hospital. In addition, the competitive procurement process for the Project precluded demolition of the

Existing Hospital.

Proponents were not required to adopt the indicative design and were permitted to advance different

design concepts. Proponents were not required to use all, or any specific components, of the Existing

Hospital in their design solutions. However, to the extent that space within the Existing Hospital

structure was determined by proponents in the competitive process to exceed that necessary to

accommodate the specified requirements for the Project, GNWT was willing to consider proposed

solutions for the repurposing of this space provided that the solution was complementary to the

broader hospital campus (as determined by GNWT in its sole discretion).

In addition, the Existing Hospital must remain fully operational and continue to provide all services

during construction of the Facility.

Figure 3 - The Existing Hospital

Page 10: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

10

2.3 Project benefits and key features

The benefits and key features of the Project include:

Improved health care facilities for residents of the Northwest Territories and Nunavut

Improved patient care and patient safety, specifically in relation to infection control, reduced

patient stay times, and improved patient satisfaction

Increased staff satisfaction and effectiveness while decreasing staff injuries and stress

Implementation of current health care standards and current health management systems

Creation of new and expanded care spaces to match increased service demands

Reduction of energy demands on the local infrastructure

The benefits listed above are anticipated to be achieved through:

Construction of a new, stand-alone facility

Incorporation of:

o single patient, safe, secure rooms

o acuity-adaptable rooms, sufficient numbers of bariatric, airborne infection rooms (AIR) and

o access to natural light and green space

o LEAN design principles that lead to an efficient design that maximizes clinical operations

o a quality acoustic environment and effective ventilation systems

o improved work settings with better floor layouts, appropriate lighting, and effective

ergonomics

Integration of Shared Support Services

Use of a Clinical Information System

Improved data networking and systems for tele-health capabilities

Incorporation of sustainable energy sources, including the use of a biomass boiler plant

Page 11: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

11

Figure 4 - Preliminary rendering of the Facility

Page 12: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

12

3. Competitive Selection Process

In accordance with GNWT’s P3 Management Framework1, GNWT undertook a procurement options

analysis to determine an optimal procurement method for the Project. Thorough and robust qualitative

and quantitative analyses resulted in the P3 method in the form of Design Build Finance Maintain

contract being the most beneficial method for delivering the Project. Further discussion of the

procurement options analysis undertaken is provided in Appendix A.

The procurement followed a rigorous, competitive, open, transparent and fair process. A two-step

process based on Canadian best-practice precedent was undertaken, entailing a Request for

Qualifications (RFQ) phase and a Request for Proposals (RFP) phase. These phases are described further

below.

3.1 Request for Qualifications

The release of the RFQ initiated the procurement phase of the Project by inviting interested teams to

indicate their interest in the Project through submission of an RFQ response. The RFQ was issued on

June 25, 2014, with three teams making submissions. The evaluation considered each team’s financial

capacity to undertake the Project and their technical experience of delivering projects of a similar scope

and size. All three teams were evaluated in accordance with the evaluation process by the evaluation

committee which included representatives from Stanton Territorial Health Authority, the Department of

Finance, Department of Procurement and Shared Services as well as external expert advisors. The three

teams were shortlisted for the RFP stage.

Table 1 - Short-listed Proponent Teams

Name Design Construction Financing

(Equity and Debt)

Facilities

Management

Boreal Health

Partnership

Kasian

Architecture

Interior Design

Planning Ltd.

Bird Design-Build

Construction Inc.

Clark Builders Ltd.

Equity Carillion Private

Finance Ltd

Hochtief PPP

Solutions GMBH

Bird Capital LP

Debt

CIBC World Markets

Inc.

Carillion Canada

Inc.

1 GNWT P3 Management Framework dated 11/5/2012

Page 13: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

13

Name Design Construction Financing

(Equity and Debt)

Facilities

Management

EllisDon

Infrastructure

Parkin Architects

Limited

EllisDon Design-

Build Inc. Equity EllisDon Capital

Ontario Pension

Board

Debt TD Securities Inc.

Cofely Services Inc.

EllisDon Facility

Services Inc.

Plenary Health B+H Architects PCL Constructors

Northern Inc. Equity PCL Investments

Canada Inc.

Plenary Group

(Canada) Ltd.

Debt Manufacturers Life

Insurance

Company

Johnson Controls

Canada LP

Compass Group

Canada Ltd.

3.2 Request for Proposals

The RFP required each Proponent to submit a proposal to design, build, finance and maintain the

Project. During the RFP stage, collaborative and topic meetings were offered so that each team had the

opportunity to discuss issues or concerns related to commercial, legal, design and construction and

operational matters. Prior to the closing date for submissions, a final draft Project Agreement was issued

and it served as the common basis for all proposals. The timeline of the competitive selection process is

outlined in the table below.

Table 2 - Competitive selection process timeline

Procurement stage Timing Outcome

RFQ June 2014 to August 2014 The project was marketed locally, provincially, nationally

and internationally. Submissions from three respondents

were evaluated and all three were invited in September

2014 to participate in the RFP process

RFP October 2014 to June 2015 Each of the three teams participated in the RFP process

and submitted proposals.

Selection of Preferred

Proponent

August 2015 After evaluation of the proposals, Boreal Health

Partnership was selected as the Preferred Proponent.

Project Agreement

Finalization

September 2015 The Project Agreement was signed by the GNWT and

Boreal Health Partnership

Page 14: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

14

3.3 Evaluation of proposals

Proponents were required to submit technical and financial submissions as part of the RFP process. The

overall objective of the evaluation was to select the proposal that best met the requirements of the RFP

and achieved value for money. An evaluation committee was appointed to evaluate the proposals based

on the criteria set out in the RFP and to recommend a Preferred Proponent.

3.3.1 Technical submissions

Evaluation of technical submissions was completed in two stages:

1. evaluation of Initial Technical Submissions (“ITS”)

2. evaluation of Final Technical Submissions (“FTS”), submitted approximately 7 weeks after the

ITS.

The purpose of having both an Initial and Final Technical Submission was to reduce the potential for

proponents to be disqualified for non-compliance with the requirements of the RFP. The evaluation

committee first reviewed each proponent’s ITS to identify any areas of material non-compliance.

Proponents received feedback in respect of any related issues in advance of submitting their FTS, and

were allowed to make changes to address these issues subject to prior approval by GNWT.

Scoring in accordance with an Evaluation Framework was undertaken on the technical submissions, and

was divided across the following categories:

The proposed design and technical solution

Construction period work plans

Services and communications

Local and Northern content

Following proponents’ submission of the FTS, the evaluation committee determined whether these

submissions contained any material non-compliances and whether they satisfied the mandatory

requirements of the RFP and the Project Agreement.

3.3.2 Financial submissions

Proponents were required to submit a financial submission along with their FTS. The evaluation of the

financial submissions consisted of two steps:

The first step was to determine whether they substantially satisfied the financial requirements,

which included overall financial viability of the proponent team and the provision of sufficient

financing and a robust and deliverable financial plan.

If the Proponent satisfied all criteria in the first step above, the Net Present Cost (“NPC”) was

evaluated. NPC represents the sum of total payments made by GNWT to the Proponent over

the construction and operations terms discounted to today’s dollars. Proponents were assigned

a score based on their NPC.

Page 15: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

15

Affordability threshold

In addition to the evaluation criteria described above, the RFP included an affordability threshold

relating to capital costs included in financial submissions. This criterion sought to ensure that GNWT

received affordable proposals in the context of the available budget for the Project. This threshold was

set at $290 million in nominal terms, and captured all development, construction and commissioning

costs (including interest costs and financing fees). The threshold was not a mandatory requirement

linked to formal submission compliance, but submitting capital costs above the threshold did provide

GNWT with the discretion under the RFP to disqualify the submission.

The successful proposal from Boreal Health Partnership met the affordability threshold and will deliver

the Project scope as outlined in the Project Agreement.

3.3.3 Overall outcome

As a result of the final scoring from the FTS and financial submissions, it was determined that Boreal

Health Partnership had the highest overall score. Therefore the evaluation committee recommended

that Boreal Health Partnership be selected as the Preferred Proponent, and the Financial Management

Board accepted that recommendation.

3.4 New build solution

As discussed in Section 2.2, GNWT had prepared an indicative design for the Project that involved the

renovation and expansion of the Existing Hospital. Proponents were not required to adopt the

indicative design and were permitted to advance different design concepts. Proponents were not

required to use all, or any specific components, of the Existing Hospital in their design solutions.

However, components of the Existing Hospital which were not used for STHA purposes could not be

abandoned or demolished, but must be used and maintained in a manner permitted by the RFP.

Boreal Health Partnership’s successful proposal involved the development of a new stand-alone facility

to satisfy the requirements of STHA under the Project Agreement, and the repurposing of the Existing

Hospital to accommodate commercial tenancies (to the extent that the tenancies are complementary to

the hospital campus in GNWT’s sole discretion).

The proposed arrangement included:

Boreal Health Partnership and a third party developer jointly funding the initial remediation

work for the Existing Hospital, as well as providing additional funding to build out the Existing

Hospital to tenancy requirements pursuant to a business plan acceptable to GNWT

The developer bearing the risk associated with the occupancy, energy consumption and

operational and capital maintenance of the repurposed Existing Hospital throughout a 30 year

lease term. The developer is also responsible for the condition of the Existing Hospital upon

hand back to GNWT

GNWT sharing in the net commercial revenues generated by the repurposed Existing Hospital

(the evaluation of financial submissions did not reflect any potential future upside to GNWT).

The evaluation committee determined that:

the overall solution was compliant with the terms of the RFP and the Project Agreement;

Page 16: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

16

the key ownership, operation, tenancy, financial and lifecycle risks of the Existing Facility had

been transferred to Boreal Heath Partnership and a third party developer; and

GNWT had a realistic prospect of value capture through revenue sharing under the lease,

without retaining any economic downside risks (the evaluation of financial submissions did not

allocate any financial benefit or selection advantage to this potential economic benefit).

Page 17: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

17

3.5 Fairness Advisor

A Fairness Advisor, RFP Solutions, was engaged by GNWT to monitor the competitive selection process

and offer an assessment about the procedures and whether or not the competitive selection process

was carried out in a fair and reasonable manner.

The Fairness Advisor was provided access to all documents, meetings, and information related to the

evaluation processes throughout the RFQ and RFP stages. The Fairness Advisor issued reports to GNWT

for both the RFQ and RFP stages of the competitive selection process. The reports issued by the

Fairness Advisor concluded that the Evaluation Committee selected and recommended a Preferred

Proponent in accordance with the procurement process and evaluation criteria set out in the RFP. The

Evaluation Teams and Evaluation Committee acted in a professional and impartial manner while

reviewing the proposals of each Proponent.

Overall, the procurement process was followed in accordance with the terms of the RFQ and RFP and

appeared to be fair, transparent and unbiased. The final Fairness Advisor’s report has been released

publicly along with this Project Report.

Page 18: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

18

4. The Final Project Agreement

4.1 Overview

Private partner Boreal Health Partnership

Owner Government of the Northwest Territories

Government contributions to capital cost $152 million progress payments during construction

Construction complete 31 October 2018

Term of the Project Agreement 30 year operating term plus 38 months of construction

Total Availability Payments over the

operating term of the Project

$598.4 million

4.2 Profile of the Private Sector Partner

Boreal Health Partnership is the private partner for the Project. Boreal Health Partnership is a

consortium of companies qualified through the RFQ process and consisting of the following key

members identified in the figure below:

Figure 5 - Boreal Health Partnership structure

Page 19: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

19

4.3 Key terms of the Project Agreement

4.3.1 New Facility

Under the terms of the Project Agreement, Boreal Health Partnership is responsible for the following:

Construction Phase:

Arranging financing for the full construction cost of the Facility, with GNWT contributing $152

million during the period

Achieving required permits and approvals to commence construction

Designing and building the Facility within the specified and agreed timeline.

Operations Phase:

Housekeeping, waste management, laundry and linen, and catering services

Roads, grounds, and landscape maintenance

Parking management and security services

Customer-related services, including technical support and assistance and operation of a help

desk

Maintaining the Facility over a 30-year operating phase including routine, planned and

unplanned maintenance

Returning the Facility in a fully maintained condition at the end of the Project Agreement term.

4.3.2 Existing Hospital

As a companion contract to the Project Agreement, GNWT required Boreal Health Partnership and a

third party developer to enter into an Existing Hospital Remediation Agreement (the “Tripartite

Agreement”). The Tripartite Agreement includes terms requiring Boreal Health Partnership and the

developer to provide approximately $13 million of funding for undertaking a remediation of the Existing

Hospital, including removing any hazardous materials (which will be carried out by Boreal Health

Partnership) and completing certain renovation work (which will be carried out by the developer under

the Lease Agreement).

GNWT has entered into an Agreement to Lease with the developer, which contemplates that GNWT and

the developer will negotiate and enter into a Lease Agreement for the future development and use of

the Existing Hospital. Upon the completion of remediation work by Boreal Health Partnership at the

Existing Hospital, including removing any hazardous materials as set out in the Tripartite Agreement, the

Existing Facility will be leased to the developer. The Lease Agreement will more fully set out the

obligations of the developer to fund and carry out the renovation work required after handover to build

out the Existing Hospital to tenant requirements and pursuant to an acceptable business plan. Under the

terms of the Lease Agreement, the developer will assume occupancy, operational and capital

maintenance, energy and hand back risks associated with the Existing Hospital during the 30 year lease

term, and will share with GNWT the net commercial revenues generated by the Existing Hospital.

Page 20: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

20

4.4 Performance-based payment principles

During construction, GNWT will make construction payments based on a percentage of the eligible

construction costs incurred by Boreal Health Partnership in a specific month as certified by an

Independent Certifier2.

Boreal Health Partnership is incentivized to perform through a payment mechanism based on the

principles of performance, Facility availability and service quality. Once construction is complete and

Service Commencement has been achieved (the requirements of which are set out in the Project

Agreement), Boreal Health Partnership will begin receiving an Availability Payments from GNWT. These

payments will be made monthly and are based on the Facility availability and the quality of Facility

maintenance services provided by Boreal Health Partnership. Performance will be continuously

monitored based on key performance indicators. If the performance standards in the Project Agreement

are not met, GNWT may apply deductions to the Availability Payments.

Payment deductions are based on the severity of the failure to meet the performance indicator, the

importance of the room or department area affected, and the level of unavailability. An unavailability

deduction applies when a functional unit (room or department) fails to comply with the condition

specified in the Project Agreement. For example, if the temperature or humidity of a room is outside a

predetermined range, that room would be considered unavailable.

4.5 Adjustments to the Availability Payments

The Availability Payments may be adjusted according to the specific terms stated in the Project

Agreement, specifically:

Indexation: A proportion of the Availability Payment that will be adjusted for consumer price

index (CPI) on an annual basis, intended to reflect the proportion of index-linked operating

period costs relative to the overall cost base of the Contractor

Changes: In cases when GNWT requires changes to the physical infrastructure of the Facility or

the scope of services, GNWT will directly reimburse Boreal Health Partnership for the costs of

amendments either through a lump sum payment or a change to the Availability Payment

Change in Law: Under certain circumstances, GNWT may compensate Boreal Health Partnership

for changes in laws that cause them to incur additional costs

Market Testing: The housekeeping, janitorial, security, and catering services will be market

tested every six years

Compensation Events: The Project Agreement defines certain events, typically outside of Boreal

Health Partnership’s reasonable ability to control or mitigate impacts, where they are provided

the compensation to leave them in a no-better and no-worse position, potentially involving an

adjustment to Availability Payments.

2 The Independent Certifier is selected through a competitive tendering process and jointly funded by GNWT (50%) and Boreal

Health Partnership (50%) to provide independent oversight and monitoring of construction progress and quality

Page 21: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

21

4.6 Risk allocation summary

The Project Agreement includes detailed risk allocation provisions over the construction period and 30-

year operating term. This approach transfers key risks to Boreal Health Partnership — such as

construction, cost and schedule — and adds value through design and private sector innovation.

The table below summarizes key risk allocation retained by GNWT, transferred to Boreal Health

Partnership and shared between the two parties.

Table 3 - Risk allocation summary

Risk Retained by GNWT Transferred to Boreal

Health Partnership Shared

Approvals & Procurement

Government project approval

Procurement – schedule delay

Interest base rate – pre-Financial Close

Municipal and provincial approvals, including environmental, building and development permits

Design & Construction Period

Scope changes (owner-initiated)

Construction delays (owner-initiated)

Construction delays (Project Co-initiated)

Construction – labour shortage

Geotechnical

Design errors or omissions

Quantity of estimate errors

Weather-related construction delays

Commissioning delays

Unresolved deficiencies

Latent defect – construction

Page 22: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

22

Risk Retained by GNWT Transferred to Boreal

Health Partnership Shared

Maintenance Period

Inaccurate measurement of asset expected life

Facility maintenance costs

Life Cycle (excluding IMIT components)

Life Cycle (IMIT components only)

Supervening Events

Change in Law

Force Majeure

Furthermore, following Substantial Completion of the new Facility and STHA completing the process of

decanting from the Existing Hospital into the new Facility, the third party developer of will thereafter

assume the following risks related to the Existing Hospital:

Capital, operating (including energy) and lifecycle expenditures

Tenancy / occupancy risks

Hand-back of the Existing Hospital in a prescribed condition

Page 23: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

23

4.7 Financial summary

The chart below demonstrates the projected Construction Payments and Availability Payments (AP) to

Boreal Health Partnership from GNWT, assuming 2% annual CPI and no deductions for non-

performance:

Figure 6 - GNWT cash flows to Boreal Health Partnership ($ millions)

4.8 Quantitative benefits

The estimated NPC of the Project cash flows delivered using a DB approach is $711.2 million. The

estimated NPC of the Project delivered using Boreal Health Partnership‘s proposal under a DBFM

approach is $536.7 million. A comparison of these numbers is provided below.

Net Present Cost ($m) Final Project Cost DB

Construction Payments 140.9

Availability Payments 292.9

Capital costs 219.6

Life cycle and operating costs 176.0

Risk adjustment 40.6 253.7

Procurement and project management costs 62.2 61.9

Total 536.7 711.2

Cost differential 174.5

Percentage savings 24.5%

In financial terms, the final Project Agreement is estimated to achieve NPC savings of $174.5 million of

taxpayers’ dollars when compared to the alternative procurement option.

0.0

10.0

20.0

30.0

40.0

50.0

60.0

FY2016 FY2021 FY2026 FY2031 FY2036 FY2041 FY2046 FY2051

Mill

ion

s

Construction Payments Non-Indexing AP Indexed AP

Page 24: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

24

4.9 Accounting treatment

GNWT’s Office of the Comptroller General, responsible for the overall quality and integrity of the

Territory’s financial management and control systems, has established accounting guidelines for

partnership projects.

Based on accounting guidelines, and for accounting purposes, the nominal capital costs associated with

the PPP portion of the Project will be capitalized as an asset on GNWT’s balance sheet, including the

capital cost for the design and construction, the associated interest during construction, and Boreal

Health Partnership’s bid development and financing costs. It does not include costs for GNWT-

purchased equipment, the competitive selection process, implementation or contingencies. These costs

are accrued to GNWT through the construction period as the costs are incurred.

The total capitalized cost for the Project is $289m and the long term debt impact to GNWT is $137m.

Page 25: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

25

5. Ongoing Project Agreement monitoring

The Project Agreement with Boreal Health Partnership includes specific provisions to ensure project

delivery, performance and quality standards are met. Monitoring spans every phase of the Project, from

Financial Close through to design and construction, and maintenance.

There are a number of major phases in the project monitoring schedule, with roles and responsibilities

assigned to project participants at each stage.

5.1 Design and construction phase

The Project Agreement specifies monitoring mechanisms to ensure the timeliness of the Facility

completion and the quality of the construction:

During design and construction the Independent Certifier is responsible for reviewing and

monitoring construction progress and quality, as well as reviewing invoices for proposed design

changes.

In addition, at substantial completion, the Independent Certifier issues a certificate of

completion once Boreal Health Partnership has met the design and construction requirements

set out in the Project Agreement.

Boreal Health Partnership’s lenders will also review performance during the construction period.

The Construction Period Joint Committee oversees the construction of the Facility. The

committee comprises GNWT and Boreal Health Partnership design and construction

representatives. These key individuals will have the authority to act on each party’s behalf in the

matters of review, approval, confirmation and acceptance of design and construction issues. The

GNWT representative will be supported by a team of professionals and will have full access to

the construction site, design specifications and drawings. The GNWT representative will monitor

the construction and will report to GNWT regularly.

5.2 Maintenance and rehabilitation phase

Similarly to the design and construction phase, the Project Agreement provides service monitoring

protocols during the maintenance phase:

The Operating Period Joint Committee provides oversight and direction on matters related to

the maintenance and rehabilitation period. Both GNWT and Boreal Health Partnership will

appoint representatives. The role and authority of such representatives will be similar to the

representatives during the design and construction phase.

GNWT will perform inspections and testing to check reports and ensure the requirements

continue to be met.

Boreal Health Partnership’s lenders will also review performance during the maintenance and

rehabilitation period.

Boreal Health Partnership will provide various plans for GNWT’s review and approval, such as:

• Annual service plan and five year maintenance plan

Page 26: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

26

• Life cycle asset and rehabilitation plan

• Environment management plan

• Energy management plan

• Handback works plan

5.3 End of Project Agreement

At the end of the 30-year maintenance and rehabilitation period, the condition of the Facility must be in

compliance with the specifications in the Project Agreement. For example, the Facility’s structural

elements (walls, roofs, and floors) must have a minimum residual life expectancy of 30 years. As part of

the handback process, the following monitoring activities will take place:

GNWT and Boreal Health Partnership will undertake a number of activities to assess the

condition of the Facility prior to Project Agreement expiry. This assessment will ensure the asset

is in the condition specified in the Project Agreement prior to handback. Financial penalties will

be applied if the asset is not delivered to GNWT in the specified condition.

The compliance with handback requirements will be assessed by an independent qualified party,

similar to the Independent Certifier discussed in Section 5.1.

After the Project Agreement expires, GNWT will assume responsibility for maintaining the

Facility.

Under the terms of the Lease Agreement, upon expiry the developer must also return the Existing

Hospital to GNWT in a prescribed condition.

5.4 Quality management throughout the Project term

The performance-based structure of the Availability Payments creates an incentive for Boreal Health

Partnership to construct and maintain the Facility to the high standards described in the Project

Agreement. To enforce the performance standards and the above-mentioned structure, the Project

Agreement includes a performance monitoring plan. This plan is based on various types of service

performance reports delivered at different time intervals (monthly, quarterly, annually, etc) to GNWT by

Boreal Health Partnership, such as:

A summary of calls made to the facilities management help desk and their resolution

A summary of unavailability events and service failures, including resolution times

A calculation of the monthly Availability Payments owed to Boreal Health Partnership

The reports and underlying data are produced by Boreal Health Partnership, available to GNWT at the

scheduled reporting times, allow for a thorough review of provided services and performance. The

performance monitoring program ensures that the Facility is operated and maintained according to the

high standards stated in the Project Agreement. The Project Agreement contains strict penalties for

delay in provision or misrepresentation of data in the reports.

Page 27: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

27

6. Glossary of terms

Availability Payment The mechanism by which a private partner in a PPP arrangement is compensated.

According to performance standards specified in a Project Agreement, Availability

Payments are paid to the private partner for capital and operating costs, as well as

their required rate of return, over the term of the agreement

Discount Rate A rate used to relate present and future dollars. Discount rates are expressed as a

percentage and are used to reduce the value of future dollars in relation to present

dollars. This equalizes varying streams of costs and benefits so that different

alternatives can be compared on a like-for-like basis

Existing Hospital The existing hospital building and related structures, utility connections, and

landscaping present on the Existing Hospital lands

Facility The new Stanton Territorial Hospital that is to be constructed pursuant to the

Project Agreement

Financial Close The point in the procurement process where negotiations with a preferred

proponent are finalized, the lending requirements have been fulfilled and a Project

Agreement is executed, allowing construction to begin

GNWT Government of the Northwest Territories

Independent Certifier An independent, third-party certifier engaged jointly by the GNWT and the private

partner to verify and certify whether certain conditions of the Project Agreement

are being satisfied

Net Present Cost (NPC) The value of periodic future cost outlays when they are expressed in current, or

present day, dollars by discounting them using the Discount Rate.

Nominal Cost Costs calculated in nominal terms at current prices recognizing adjustments for

inflation

Performance

Specification

Specifications developed by GNWT that define the output and performance levels

required in relation to construction and life cycle performance of an asset, to

ensure the completed project satisfies the objectives of a project with respect to

meeting the GNWT’s service delivery needs

Preferred Proponent A proponent selected from a shortlist of bidders to enter into negotiations with

GNWT to reach Financial Close and deliver a project.

Project Stanton Territorial Hospital Renewal Project

Page 28: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

28

Project Agreement The Project Agreement sets out the requirements for the delivery of an asset

under a PPP in terms of cost, schedule and life cycle performance that typically

govern the performance-based payment of the ASP to a private partner.

Public Private

Partnership (PPP)

A project structured using a long-term, performance-based agreement with a

private sector partner to deliver and maintain an infrastructure asset, including

significant upfront capital investment

Request for Proposals

(RFP)

Document issued by GNWT for qualified proponents to submit formal proposals to

deliver a project

Request for

Qualifications (RFQ)

Document issued by GNWT inviting parties interested in participating in an RFP, to

submit their qualifications for delivering a project

Retained Risk Risks associated with delivering a project that are not transferred to the private

partner under a PPP, representing a cost to the project regardless of the

procurement approach

Service

Commencement

The date upon which the following activities have been achieved: the Independent

Certifier has issued a Certificate of Service Commencement with respect to the

Project; all necessary Permits have been issued for the use and operation of the

Facility; and Project Co has delivered to GNWT a report from the commissioning

agent retained by Project Co in accordance with the Project Agreement confirming

completion of all commissioning activities scheduled in the Commissioning Plan to

be completed before Service Commencement.

Traditional

Procurement

Methods by which the public sector has traditionally procured projects in the

Northwest Territories, through design bid build (DBB), design build (DB) contracts

or a combination of DBB and DB contracts

Transferred Risk Risk associated with delivering a project that is typically borne by the public sector

under traditional procurement that is transferred to the private sector under a PPP

Value for Money (VFM) Describes the benefits to the public expected to be realized through a particular

procurement method, which can be quantitative and/or qualitative in nature.

Quantitative value for money is achieved through the lower cost of a project

resulting from the procurement method, whereas qualitative value is achieved

when a particular procurement method better supports the goals and objectives of

a project without necessarily costing less.

Page 29: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

29

Appendix A – P3 Procurement Process

In accordance with GNWT’s P3 Management Framework3, GNWT undertook a procurement options

analysis to determine an optimal procurement method for the Project.

Methodology

The evaluation of procurement options is mainly concerned with identifying the method of delivering

the Project that will result in the greatest value for money on both a financial (quantitative) and

qualitative basis. The evaluation of procurement options involves two main steps:

The first step identifies key procurement objectives, against which a wide range of available

procurement options are compared, including both traditional and partnership methods, and

provides a qualitative assessment these options. This step is intended to identify the two

procurement methods most relevant to the project, which then form the basis of detailed

quantitative comparison

The second step in the assessment involves a more detailed, quantitative analysis that compares the

two methods

Multi Criteria Analysis was used to qualitatively assess a wide spectrum of potential procurement

options, including Design-Bid-Build, Design-Build, Design-Build-Finance, Design-Build-Finance-Maintain

and Design-Build-Finance-Operate-Maintain, for their alignment with the goals and objectives of the

Project. The Multi Criteria Analysis indicated that the DBFM procurement option was most closely

aligned with the criteria. Quantitative analysis was then undertaken to review whether DBFM would

provide VFM when compared to the DB procurement route which had traditionally been used to

procure projects of this nature by GNWT.

A VFM assessment was therefore completed to compare the life-cycle risk-adjusted costs of the two

selected procurement options: traditional DB and DBFM. The purpose of the VFM assessment was to

identify the procurement option that would provide the greatest value through the design, construction

and operations, maintenance and rehabilitation phases of the project. A financial model was developed

to compare which approach generated the greatest VFM.

The VFM assessment process included a comprehensive risk analysis to identify and quantify the risks

retained by the public sector under each procurement option. Other costs were also incorporated

including: design, construction, maintenance, and rehabilitation related costs; and transaction costs

(legal, fairness, technical advisors, project management, and contract management fees). Model

specific adjustments were made to ensure a fair comparison between procurement options. For

example, the DB model was adjusted to account for differences in tax treatment and insurance costs

between the public and private sectors (the “Competitive Neutrality” adjustment).

Differences in timing and cash flows between procurement options are an important consideration in

3 GNWT P3 Management Framework dated 11/5/2012

Page 30: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

30

the analysis of long term cash flows. In order to allow for these differences a discounted cash flow

approach was utilised. A discount rate was applied to the projected future cash flows to allow for timing

differences.

The figure below demonstrates the steps in the quantitative component of the procurement options

analysis.

Figure 7 - Quantitative procurement options analysis steps

Traditional model

P3 model

INPUTS

Construction Period Inputs Operating Period Inputs Owners Cost Inputs

• Duration• Capital Cost• Inflation• Quantified Risks• Efficiencies

• Operating Costs• Rehabilitation Costs• Inflation• Quantified Risks• Efficiencies

• Procurement• Engineering• Project Management• Contract Management• Equipment

Financing and Taxation Inputs

Estimate annual service payment by the Territory to

the private partner, plus owner’s costs over term of

analysis (30 years)

Calculate unfinanced cash flows for term of analysis

(30 years)

Competitive Neutrality Adjustments

Apply Discount Rate

Compare Net Present Costs

Page 31: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

31

Procurement options

The process of considering procurement options began with the definition of key procurement

objectives, which were based on the project objectives. The following procurement objectives were

developed by the project team to provide guidance in the selection and analysis of procurement

options:

Maximize competition (between proponents /bidders)

Cost certainty

Risk allocation

Fairness, transparency, and integrity

Overall value for money

The qualitative analysis concluded that Design Build (DB) and Design Build Finance Maintain (DBFM),

were the two most appropriate traditional and partnership procurement options, respectively, and

should be compared in detail. The two options are described below.

Design Build (DB)

The GNWT would issue a tender call for both the design and construction of the Facility as a single

contract. The GNWT would evaluate all detailed design in accordance with its output specifications and

functional program. Following design approval, the selected contractor would proceed with construction

of the Facility. The GNWT would make monthly progress payments to the contractor during construction

and would take possession and maintain and operate the infrastructure following completion.

In the past, the GNWT has successfully delivered projects on time and on budget using the DB model.

Design Build Finance Maintain (DBFM)

This partnership delivery model involves a two-stage competitive selection process. The first stage is a

Request for Qualifications (RFQ), whereby respondent teams would submit qualifications to be received

and evaluated, resulting in a shortlist of Proponent teams. The second stage invites the proponent

teams to submit proposals as part of the Request for Proposals (RFP) process. At the RFP stage, the

GNWT would provide performance specifications and seek proposals from the proponents to design,

build, finance, and maintain the Facility.

The project team would evaluate these proposals to determine a preferred proponent with which it

would enter into a final Project Agreement. Under the Project Agreement, the proponent would be

required to design, build, finance, and maintain the project over the specified term of the agreement.

Availability payments would be made monthly to the private partner over the life of the agreement, in a

fixed amount determined at Financial Close. Payments only commence once the infrastructure is

completed. To ensure that the private partner receives full payment, they must meet defined and

measurable performance and availability standards on a continuous basis. The DBFM approach provides

a financial structure that aligns the incentives of the private partner and the GNWT. Under the DBFM

option, the private partner would be responsible for:

Arranging project financing, including debt and equity

Developing and constructing the Facility in accordance with a defined output specification

Page 32: Project Report - Stanton Renewal Project Report... · 20567651.3 December 2015 2 Purpose of this project report The purpose of this project report (Project Report) is to provide key

20567651.3

December 2015

32

Maintaining the infrastructure over the life of the Project Agreement and handing it back at the

end of the contract term in the prescribed condition.

Results of the Procurement Options Analysis

Based on the procurement options analyzed, the DBFM method was determined to be the preferred

procurement option, expected to best meet the GNWT’s procurement objectives and overall project

objectives.

Achieving value for money

Value for money is a term that captures both the quantitative and qualitative benefits that are expected

to be achieved by the decision to deliver the project using the partnership method.

Quantitative value for money is achieved through the lower project cost resulting from a particular

procurement method. Qualitative value is achieved when a particular procurement method is best able

to support the broader objectives of a project.

Partnership projects typically provide the following qualitative benefits:

o Competition and innovation: The competitive nature of the bidding process encourages the private

partner teams to develop innovative solutions in all aspects of the project from design and

construction through to operations.

o Schedule certainty: The private partner receives a significant portion of their payment through

monthly availability payments once the infrastructure is available for use, thereby providing a

financial incentive to complete the project on time.

o Cost certainty: The Project Agreement is a fixed price contract.

o Integration: The private partner is responsible for the design and construction, maintenance and

rehabilitation of the infrastructure. This creates opportunities and incentives to integrate these

functions to optimize performance of the infrastructure over the duration of the Project

Agreement.

o Life cycle maintenance: The private partner is responsible and accountable for ensuring the

infrastructure is maintained and rehabilitated over the duration of the Project Agreement

otherwise the Availability Payments may be reduced.