Project Plan for the <insert name here> Project Version: 1.0.0
Project Plan
for the
<insert name here>
Project
Version: 1.0.0April 10, 2023
Sarasota County GovernmentProject Management Office
Sarasota County Government<project name> Project Plan
Document Control
Document Approval
Approvals Signature Date
Document History
Revision Author/Reviser Comments Date
Document Storage
This document is created in Microsoft Word 2000 and is maintained in the <insert web address or network drive/folder here>
Project Contact
The contact for this document is:
<project manager name>Phone: E-mail: Sarasota County GovernmentProject Management Office (PMO)
PMO Ver. 1.0.0ii
Sarasota County Government<project name> Project Plan
Preface
This Project Plan defines the activities to be performed, the products to be developed, the project schedule, and the resources required to develop the <project name here>. This Project Plan will be used as a tool to track and manage the project.
Table 1 Initial Distribution List
Name Project Role Delivery Information
Name Sponsor, Tester, etc
E-mail, Web, etc.
After Initial Distribution the lastest version of the project plan will be located on the EIT Project Page located at <insert web address or network drive/folder here>
PMO Ver. 1.0.0iii
Sarasota County Government<project name> Project Plan
Table of Contents
Approvals............................................................................................................................... III
1 INTRODUCTION..............................................................................................................61.1 Project Plan Purpose...........................................................................................................61.2 Evolution of the Project Plan.............................................................................................6
2 PROJECT OVERVIEW.....................................................................................................82.1 Project Scope....................................................................................................................... 82.2 Project Modules...................................................................................................................82.3 Project Assumptions and Constraints..............................................................................92.4 Software Life Cycle.............................................................................................................92.5 Project Issues....................................................................................................................... 92.6 Course Corrections.............................................................................................................92.7 Testing................................................................................................................................ 102.8 Training.............................................................................................................................. 10
3 PROJECT MANAGEMENT............................................................................................113.1 Project Management Objectives and Priorities.............................................................113.2 Procedures, Methods and Standards.............................................................................113.3 Quality Assurance Plan....................................................................................................12
4 SYSTEM OVERVIEW....................................................................................................134.1 Figure 1 – System Connectivity......................................................................................13
5 CRITICAL COMPUTER RESOURCES........................................................................155.1 Critical Computer Resource Assumptions.....................................................................15
6 PROJECT SCHEDULE AND LEVEL OF EFFORT ESTIMATES.............................15
7 RISK MANAGEMENT...................................................................................................17
8 EXTERNAL DEPENDENCIES......................................................................................18
APPENDIX A - MAJOR MILESTONE AND SCHEDULE SUMMARY...........................18
Appendix B – Initial Work Breakdown Structure...............................................................19
Index of Tables
Table 1 Reference Materials......................................................................................................7Table 2 Vendor Developed Modules..........................................................................................8Table 3 EIT Developed Modules.................................................................................................8Table 4 Project Roles................................................................................................................12Table 5 Project Contact List.....................................................................................................12Table 6 Summary of Critical Computer Resources for the Project.........................................15Table 7 Risk Management........................................................................................................17Table 8 Major Milestone LOE and Schedule Summary............................................................18
PMO Ver. 1.0.0iv
Sarasota County Government<project name> Project Plan
1 Introduction
1.1 Project Plan PurposeThe purpose of this document is to provide a mechanism to communicate the project scope, assumptions, constraints, project issues, risks, and Project Management objectives as well as other pertinent project information. Project details relating to work at the task level is in the Work Breakdown Structure (Appendix B).
This project plan will be used to manage tasks, milestones, the project schedule, project issues, risks, and resource assignments for the <project name> project.
The Project Major Milestone and Schedule Summary can be found in Appendix A. The Work Breakdown Structure, Schedule, and link to the Microsoft Project Plan are contained in Appendix B. Appendix C contains the latest version of the Project Issues Log.
1.2 Evolution of the Project Plan This Project Plan will be reviewed and updated if necessary at the end of each life cycle phase to ensure that it accurately reflects the status of the project. The Project Plan will also be reviewed in the Weekly Project Status meeting and modifications will be made if required.
If changes to the Project Plan’s Schedule Baseline are required, they will be made once an approved Scope Change Request has been completed and approved.
PMO Ver. 1.0.05
Sarasota County Government<project name> Project Plan
Table 1 Reference Materials
Document Overview Created By
Document File Location and/or Name
PMO Ver. 1.0.06
Sarasota County Government<project name> Project Plan
2 Project Overview
2.1 Project ScopeThis project will allow for planning, design, development, testing, and implementation of a <project name/short description>
2.2 Project Modules
Table 2 Vendor Developed Modules
Vendor Module(s)
Table 3 Internally Developed Modules
Group Module(s)
PMO Ver. 1.0.07
Sarasota County Government<project name> Project Plan
2.3 Project Assumptions and Constraints
2.3.1 Assumptions
2.3.2 Constraints
2.4 Software Life Cycle (If applicable, remove if not)Example: The software life cycle chosen for this project is Rapid Application Development (RAD). This life cycle was chosen because this project is on a fast track and as such must be developed in the shortest amount of time.
2.5 Project IssuesIssues and problems will be tracked in the Project Issues Log as they arise. (Appendix C). The issues log will be uploaded to the <Applicable Project Web Site> every <day of week/time>.
2.6 Course Corrections Course corrections will be made throughout the project. These course corrections will be discussed in the Weekly Project Status Meetings.
PMO Ver. 1.0.08
Sarasota County Government<project name> Project Plan
2.7 Testing
2.7.1 Testing
<organization name(s) here> will be responsible for testing the following components:
1. Component One2. Component Two3. etc.
2.7.2 User Acceptance Testing
Example: Business Center and PMO personnel will be responsible for the development and implementation of the user acceptance test. The User Acceptance Test (UAT) will ensure the primary sponsor and stakeholders are satisfied that the requirements have been me. A signoff of the UAT by the project sponsor is required prior to implementation.
Example: The User Acceptance Test will test at a minimum the following:
1. All GUIs and backend functionality2. Manager Portal, GUIs, and backend functionality3. Administration Portal, GUIs and backend functionality4. Merit Increase Process Functionality 5. Performance Review Process6. Performance Review Process – Multi-Rater Feedback7. Employee Information Update Process
2.8 TrainingA training plan will be developed outlining the roles and responsibilities of the <appropriate organizations here>.
PMO Ver. 1.0.09
Sarasota County Government<project name> Project Plan
3 Project Management
3.1 Project Management Objectives and PrioritiesExample
1. Ensure the project completes on the targeted implementation date.
2. Assist in obtaining needed development and support tools to support EIT development.
3. Assist (as needed) the development manager in identifying and distributing responsibilities to development resources by components.
4. Coordinate external issues through the appropriate departments.
5. Conduct and lead weekly Project Management status meetings to gather and report accurate status.
6. Report project progress through the creation of weekly status reporting.
3.2 Procedures, Methods and StandardsExample
1. Project status will be reported weekly. Status reports will be available on the EIT Project Web Site every Wednesday.
2. Changes to milestone dates, risks, or resources, which have the potential to result in a Scope Change Request (SCR), will be communicated to the project stakeholders in the weekly status report.
3. Project Schedule issues will be tracked and controlled by the project manager and the project team.
4. Project Schedule actuals in regards to Milestone Actual Start and Finished dates will be reported via the Project Status Report
5. Risk Management will be performed throughout this project.
6. Weekly Status meetings will be held with select members of the project team.
PMO Ver. 1.0.010
Sarasota County Government<project name> Project Plan
Table 4 Project Roles
Example- Delete and add applicable project information
Project Role Name Responsibilities
XXX General Manager Name Oversee EIT and External Development Efforts
Development Manager Name Development responsibilitiesProject Manager Name Day-To-Day Project OversightDepartment Manager Name Manage Development ResourcesAnalysis Name, Resource 2
Gustafson, Resource 1Gather and document project requirements
Development Developer/Vendor names Develop application processes, reports, custom modules and GUIs
Database Administration
DBA Design, develop, and support the Database
Quality Team Members Names Quality Team
Table 5 Project Contact List
Example
Name Department Phone # E-mail Address Location
Diana Allen Human Resources/Payroll 316-1206 [email protected] 6700 Clark Rd.
Brian Darley Enterprise Information Technology
861-5418 [email protected] SCTC
Barbara Thibault
Human Resources/Personnel 861-5326 [email protected] 1600 Ringling
Eleanor Zoppe Enterprise Information Technology
650-9489 [email protected] SCTC
Resource 2 Gustafson
Enterprise Information Technology
650-9196 [email protected] SCTC
Fred Dunayer Enterprise Information Technology
650-2216 [email protected] SCTC
Gayle Gursky Finance and Administration 861-6176 [email protected] 1301 Cattlemen
Nancy Fisher Administrative & Financial Services
861-6715 [email protected] 2817 Cattleman
Nikki Snyder Payroll (Finance - Clerk) 861-5159 [email protected] 1660 Ringling
3.3 Quality Assurance Plan
PMO Ver. 1.0.011
Sarasota County Government<project name> Project Plan
4 System Overview
4.1 Figure 1 – System Connectivity Example Only
4.1.1 PLANNINGExample High-Level Planning Milestones
Task StatusConduct a Database Model Review with the Database Architect
Complete – 02/07/03
Initial meeting with Web developers to discuss details surrounding the GUIs
Scheduled – 02/10/03
Meet with developers and Database Architect to map GUI fields to database tables/fields
Not scheduled. No resources identified as of 02/10/03.
Developers and Core team to meet to define data constraints
Not started
Define error processing for all GUIs Not started
PMO Ver. 1.0.012
Sarasota County Government<project name> Project Plan
4.1.2 DATABASE CLEANUP ACTIVITIESExample High-Level Planning Milestones
Task StatusCheck for dates and numbers outside of normal ranges
Not started
Payroll/HR comparison (pay, classification, position from standard download)
Not started
Classification and Transaction updates Not startedOther Maintenance reports Not startedEntry of employee change transactions through last full pay period prior to implementation.
Not started
Example High-Level Estimate (optional)
Staff: Tom – Entry of Corrections; Entry of change transactions.Resource 1 – Run Exception Reports and Comparisons; update code tables
Time: 40 hours
PMO Ver. 1.0.013
Sarasota County Government<project name> Project Plan
5 Critical Computer Resources
The following table summarizes the list of the critical computer resources required for this project for all impacted systems:
Table 6 Summary of Critical Computer Resources for the Project
Example
Resource New/Additional Type and/orApplication
Source
Workstations (development, testing, training, production, user)
N/A N/A N/A
Servers (Production, Test, Development, and Training)
2 (Production) Microsoft IISMicrosoft SQL Server 2000
EIT
Direct Access Storage Device (DASD)
N/A N/A
Communications requirements
Connectivity from all SCG County Offices to the Suncoast Technology Center
Connectivity to SCG iNet
EIT
System Software, Utilities, Software Tools
DevelopmentTestProduction
Identitech ComponentsSQL Server 2000 SoftwareMicrosoft IIS Software
EIT
5.1 Critical Computer Resource AssumptionsExample
1. The critical computer resources requirements as outlined above will be required to complete Phase I of the HRMS project.
2. The EIT/Network Applications group created the above Critical Computer Resource requirements.
6 Project Schedule and Level of Effort Estimates
Example Level of effort (LOE) information would normally be documented in the
Milestone and Schedule Summary in the table of Appendix B. Since this
PMO Ver. 1.0.014
Sarasota County Government<project name> Project Plan
project follows a RAD approach, LOE information by Milestone will not be supplied.
Schedule estimates would normally be derived by estimating the project at a task level, using task decomposition techniques, and by interviewing the resources on the development team. Since this project will utilize a RAD approach, the schedule has been built using the project completion date and backing into a schedule from there.
Estimates and timeframes noted in the Microsoft Project Plan (MPP) contain our best guesses as to when certain tasks will be complete. The MPP will evolve over time and be adjusted as needed. Milestone information is documented in Appendix B at a summary level and the schedule is documented in detail in the Work Breakdown Structure referenced in Appendix C.
PMO Ver. 1.0.015
Sarasota County Government<project name> Project Plan
7 Risk Management
Example
1. Risks will be identified throughout the project and reviewed in weekly project status meetings.
2. Risks that are discovered externally will be evaluated by the project lead/development team and considered for inclusion, then prioritized and addressed if necessary in the Risk Statement Table (below).
3. All action items resulting from the Risk assessments will be noted in the Project Issues log and reviewed in the Weekly Project Status meeting.
Table 7 Risk Management (Example)
# Risk RiskConsequence
Priority High,
Medium, Low
Risk resolution progress
1 Creeping requirements
DelayedImplementation
Increased Scope
High User interface prototype used to gather high-quality requirements.
Staged delivery approach will be employed to provide some ability to change features if needed.
2 Requirements or developer gold-plating
Delayed ImplementationIncreased Scope
High Project Status Meetings will check for suspected “gold-plating” concerns or evidence.
3 Unstable tools delay schedule
Delayed Implementation
High New tools are used on this project.
NOTE: No resolution known
4 Released software has low quality
Delayed Implementation
Low Customer Satisfaction
Medium User interface prototype developed to assure users would accept software.
Internal Technical reviews will be conducted in the EIT Network Applications group for requirements, designs, and code.
Test planning assures system testing will cover all functionality.
Independent testers perform system tests.
5 Unachievable schedule
Sponsor dissatisfaction
Customer dissatisfaction
Medium Schedule is re-estimated several times over the course of the project.
Active project tracking assures that schedule slips have better chance of being recognized.
Staged delivery allows for delivery of partial functionality even if whole project takes longer than expected.
6 Friction between developers and customers
Customer dissatisfaction
Project Failure
Low User interface prototype aligns developers and customers on same vision.
Staged deliveries provide customers with evidence of steady progress.
8 External Dependencies
PMO Ver. 1.0.016
Sarasota County Government<project name> Project Plan
8.1.1 This project is dependent upon …
PMO Ver. 1.0.017
Sarasota County Government<project name> Project Plan
Appendix A - Major Milestone and Schedule Summary
Example: The following high-level milestones will be tracked for this project. The detailed schedule and resources can be found in the Work Breakdown Structure referenced in Appendix C.
Table 8 Major Milestone LOE and Schedule Summary
Phase 1 ScheduledStart Date
ActualStart Date
ScheduledEnd
ActualEnd
Complete Draft RS/HLA 01/21/03 01/21/03 02/04/03
Complete Draft Project Plan 01/24/03 01/23/03 02/07/03
Coding and Testing 02/18/03 02/18/03 05/24/02
Establish User Acceptance Test (UAT) EnvironmentPromote Code/Tables to Production
05/26/03 05/28/03
Execute UAT 05/28/03 06/21/03
Production Implementation 06/25/03 06/26/03
Warranty 06/26/03 07/26/03
Project Close-out 07/28/03 07/30/03
PMO Ver. 1.0.018
Sarasota County Government<project name> Project Plan
Appendix B – Initial Work Breakdown Structure
<Next page>
PMO Ver. 1.0.019
<Project Name> Sarasota County Government
Example Only – Delete
ID Task Name Duration Start Date Finish Date Pred. Resource Names
1 HRMS Phase I WBS and Schedule 164 days? Fri 12/13/02 Thu 7/31/03
2 Analysis 57 days? Fri 12/13/02 Tue 3/4/03
3 Finalize Module Process Flows 27 days Fri 12/13/02 Tue 1/21/03
4 Merit Increase 0 days Fri 12/13/02 Fri 12/13/02 Resource 1, Resource 2
5 Performance Review 0 days Fri 12/13/02 Fri 12/13/02 Resource 1, Resource 2
6 Review Process Flow with EIT 0 days Fri 12/13/02 Fri 12/13/02 Resource 1, Resource 2
7 Performance Review (Multi-Rater Feedback Sub-Process) 0 days Fri 12/13/02 Fri 12/13/02 Resource 1, Resource 2
8 Employee Update 0 days Fri 12/13/02 Fri 12/13/02 Resource 1, Resource 2
9 Process Flows Complete 0 days Tue 1/21/03 Tue 1/21/03
10
11 Initial GUI Design 11.1 days Tue 1/21/03 Wed 2/5/03
12 Design HR Admin Screens 10 days Tue 1/21/03 Mon 2/3/03 Resource 1
13Send out HR Admin Screens and Business Center Data Cleanup Screens for Review
0.1 days Wed 2/5/03 Wed 2/5/03 Steve
14 Design HR/Business Center Data Cleanup Screens for review 0.1 days Wed 2/5/03 Wed 2/5/03 Resource 1
15 Design Portal Screens 10 days Tue 1/21/03 Mon 2/3/03 Resource 2
16 Send Portal Screens out for review 0.1 days Wed 2/5/03 Wed 2/5/03 Resource 2
17 Portal Design Complete 0 days Wed 2/5/03 Wed 2/5/03 16
18
19 Initial Requirements Definition 18.2 days Tue 1/21/03 Fri 2/14/03
20 Develop HRMS RS/HLA Document - First Cut 11 days Tue 1/21/03 Tue 2/4/03 Steve
21 Send out RS/HLA (ver.0.6) document for review 0.1 days Tue 2/4/03 Tue 2/4/03 20 Steve
22 Meet with Identitech to clarify project scope and objectives 0.2 days Tue 2/4/03 Tue 2/4/03 Steve, Resource 1, Resource 2
23 Send out meeting minutes from Identitech meeting 0.2 days Tue 2/4/03 Tue 2/4/03 Steve
24 Setup Kick-off Meeting 0.1 days Tue 2/4/03 Tue 2/4/03 Steve
25 Conduct Kick-off Meeting 0.2 days Thu 2/13/03 Thu 2/13/03 24 Steve
26 Update/Changes to RS/HLA document based on feedback from Kick- 1 day Thu 2/13/03 Fri 2/14/03 25 Steve
<project name WBS> 04/10/23
<Project Name> Sarasota County Government
off Meeting
27Baseline RS/HLA document established (the document is still a work in progress)
0 days Fri 2/14/03 Fri 2/14/03 26 Steve
28
29 HRMS Database 30 days? Tue 1/21/03 Tue 3/4/03
30 Initial meeting to discuss HRMS Database requirements 0.2 days Thu 1/23/03 Thu 1/23/03 Resource 2, Resource 1, Steve, Jim
31 Create Initial Design of Database Model 3 days Thu 1/23/03 Tue 1/28/03 30 Jim
32 Review Database Model with Analysis Team 0.2 days Tue 1/28/03 Tue 1/28/03 31 Resource 1, Jim
33 Create HRMS Database 13 days Tue 1/28/03 Fri 2/14/03 32 Jim
34 Populate new database with a few test records 1 day? Fri 2/14/03 Tue 2/18/03 33 Jim
35 Import ABRA data into HRMS Database 0 days Tue 1/21/03 Tue 1/21/03 34 Jim
36 HRMS Test Database Ready 30 days Tue 1/21/03 Tue 3/4/03 35Jim, Resource 2, Resource 1
37
38 Coding 94 days? Tue 1/21/03 Mon 6/2/03
39 HR Standalone Database Admin GUIs 50 days? Tue 1/21/03 Tue 4/1/03
40 HR Business Center Cleanup GUIs 48 days? Tue 1/21/03 Fri 3/28/03
41 Build Screens 18 days Mon 3/3/03 Wed 3/26/03 MethodFactory
42 Test Screens 2 days Thu 3/27/03 Fri 3/28/03 41Resource 2, Resource 1
43 Screens Ready to Deploy 0 days Fri 3/28/03 Fri 3/28/03 42
44
45 Test Screens 1 day? Tue 1/21/03 Tue 1/21/03
46 HR Administration GUIs 22 days Mon 3/3/03 Tue 4/1/03
47 Build Screens 18 days Mon 3/3/03 Wed 3/26/03 MethodFactory
48 Test Screens 4 days Thu 3/27/03 Tue 4/1/03 47Resource 2, Resource 1
49 Screens Ready to Deploy 0 days Tue 4/1/03 Tue 4/1/03 48
50
51 LDAP Functionality 28.2 days Tue 4/15/03 Fri 5/23/03
52 Receive LDAP Module From Identitech 0.2 days Tue 4/15/03 Tue 4/15/03 Team
53 LDAP Testing with E-directory 10 days Tue 4/15/03 Tue 4/29/03 52 Team
54 Beta Testing with select users 8 days Tue 4/29/03 Fri 5/9/03 53 Beta Users
<project name WBS> 04/10/23
<Project Name> Sarasota County Government
55 Testing with Large Test Group (100 plus users) 10 days Fri 5/9/03 Fri 5/23/03 54 Release Users
56 LDAP Module Ready 0 days Fri 5/23/03 Fri 5/23/03 55
57
58 NetFYI Modules 55.2 days? Tue 1/21/03 Wed 4/9/03
59 Merit Increase Process 32.2 days? Tue 1/21/03 Fri 3/7/03
60 Develop Detailed Requirements for Merit Increase Process 22.9 days? Tue 1/21/03 Fri 2/21/03
61 Clarify and nail down exact process steps and included functionality 0.5 days Tue 2/18/03 Tue 2/18/03 34 Team
62 Identify Data Types used in process steps 1 day Tue 2/18/03 Wed 2/19/03 61 Team
63Identify data elements to be read from/written to the HRMS Database
1 day Wed 2/19/03 Thu 2/20/03 62 Team
64 Document operations on specific fields 1 day Wed 2/19/03 Fri 2/21/03 63 Team
65 Define IFAS data requirements 0.5 days Fri 2/21/03 Fri 2/21/03 64Resource 1, Resource 2
66 Define flat file format for IFAS 1 day? Tue 1/21/03 Tue 1/21/03 Data Management
67 Coding 2.75 days Fri 2/21/03 Wed 2/26/03
68 Build Search Classes 0.5 days Fri 2/21/03 Mon 2/24/03 65 Team
69 Build database indexes 0.5 days Mon 2/24/03 Mon 2/24/03 68 Team
70 Build Work Flow 0.5 days Tue 2/25/03 Tue 2/25/03 69 Team
71 Build other required sub processes and modules? 0.5 days Mon 2/24/03 Wed 2/26/03 70 Team
72 Build Prototype of Merit Increase Process 0.5 days Wed 2/26/03 Wed 2/26/03 71 Team
73 Test 32.2 days? Tue 1/21/03 Fri 3/7/03
74 Test Prototype Process Flow utilizing test users in Roles database 0.5 days Wed 2/26/03 Thu 2/27/03 72 Team
75Unit test of Merit Increase Process utilizing live Data in HRMS Database
0.5 days Thu 2/27/03 Thu 2/27/03 74 Team
76 Test Prototype in Development Environment 0.5 days Thu 2/27/03 Fri 2/28/03 75 Team
77 Review Prototype and Functionality with Red Team 0.2 days Mon 3/3/03 Mon 3/3/03 76
78 Rework Prototype into final Process/Workflow 4 days Mon 3/3/03 Fri 3/7/03 77
79 Workflow ready for Testing 0 days Fri 3/7/03 Fri 3/7/03 78
80
81 Performance Management Process 23 days Fri 3/7/03 Wed 4/9/03
82Develop Detailed Requirements for Performance Management Process
12 days Fri 3/7/03 Tue 3/25/03
83 Clarify and nail down exact process steps and included functionality 2 days Fri 3/7/03 Tue 3/11/03 79 Team
<project name WBS> 04/10/23
<Project Name> Sarasota County Government
84 Identify Data Types used in process steps 2 days Tue 3/11/03 Thu 3/13/03 83 Team
85 Document operations on specific fields 2 days Thu 3/13/03 Mon 3/17/03 84 Team
86Identify data elements to be read from/written to the HRMS Database
2 days Mon 3/17/03 Wed 3/19/03 85 Team
87 Define IFAS data requirements 2 days Wed 3/19/03 Fri 3/21/03 86 Team
88 Define/Update flat file format for IFAS 2 days Fri 3/21/03 Tue 3/25/03 87 Team
89 Code 6 days Tue 3/25/03 Wed 4/2/03
90 Build Search Classes 1 day Tue 3/25/03 Wed 3/26/03 88 Team
91 Build database indexes 1 day Wed 3/26/03 Thu 3/27/03 90 Team
92 Build other required sub processes and modules? 1 day Thu 3/27/03 Fri 3/28/03 91 Team
93 Cleanup Efforts and final 1 day Fri 3/28/03 Mon 3/31/03 92 Team
94 Build Work Flow 1 day Mon 3/31/03 Tue 4/1/03 93 Team
95 Build Prototype of Performance Management Process 1 day Tue 4/1/03 Wed 4/2/03 94 Team
96 Test 5 days Wed 4/2/03 Wed 4/9/03
97 Test Prototype Process Flow utilizing test users in Roles database 1 day Wed 4/2/03 Thu 4/3/03 95 Team
98Unit test of Merit Increase Process utilizing live Data in HRMS Database
1 day Thu 4/3/03 Fri 4/4/03 97 Team
99 Test Prototype in Development Environment 1 day Fri 4/4/03 Mon 4/7/03 98 Team
100 Review Prototype and Functionality with Management 1 day Mon 4/7/03 Tue 4/8/03 99 Team
101 Rework Prototype into final Process/Workflow 1 day Tue 4/8/03 Wed 4/9/03 100 Team
102 Workflow ready for System Testing 0 days Wed 4/9/03 Wed 4/9/03 101 Team
103
104 Employee Information Update Process 45 days Tue 4/1/03 Mon 6/2/03
105Develop Detailed Requirements for Employee Information Update Process
6 days Tue 4/1/03 Tue 4/8/03
106 Clarify and nail down included functionality 1 day Tue 4/1/03 Tue 4/1/03 Web1
107 Identify Data Types 1 day Wed 4/2/03 Wed 4/2/03 106 Web1
108 Document operations on specific fields 1 day Thu 4/3/03 Thu 4/3/03 107 Web1
109Identify data elements to be read from/written to the HRMS Database
1 day Fri 4/4/03 Fri 4/4/03 108 Web1
110 Define IFAS data requirements 1 day Mon 4/7/03 Mon 4/7/03 109 Web1
111 Define/Update flat file format for IFAS 1 day Tue 4/8/03 Tue 4/8/03 110 Web1
112 Code 34 days Wed 4/9/03 Mon 5/26/03
<project name WBS> 04/10/23
<Project Name> Sarasota County Government
113 Build Search Classes 2 days Wed 4/9/03 Thu 4/10/03 111 Web1
114 Build database indexes 2 days Fri 4/11/03 Mon 4/14/03 113 Web1
115 Build other required sub processes and modules? 2 days Tue 4/15/03 Wed 4/16/03 114 Web1
116 Cleanup Efforts and final 2 days Thu 4/17/03 Fri 4/18/03 115 Web1
117 Employee Portal 26 days Mon 4/21/03 Mon 5/26/03
118 Develop Prototype Screen(s) 3 days Mon 4/21/03 Wed 4/23/03 116 Web1
119 Route to HR Subject Matter Experts for Feedback/Approval 1 day Thu 4/24/03 Thu 4/24/03 118 Web1
120 Build Screens 10 days Fri 4/25/03 Thu 5/8/03 119 Web1
121 Integrate into Identitech Processes and HRMS Structure 12 days Fri 5/9/03 Mon 5/26/03 120 Web1
122 Test 5 days Tue 5/27/03 Mon 6/2/03
123 Test of GUI and Employee Read/Update Processes 5 days Tue 5/27/03 Mon 6/2/03 121 Web1
124 Process ready for Testing 0 days Mon 6/2/03 Mon 6/2/03 123
125
126 Portal Development 30.5 days Tue 4/1/03 Tue 5/13/03
127 Manager Portal 30.5 days Tue 4/1/03 Tue 5/13/03
128 Develop Prototype Screen(s) 5 days Tue 4/1/03 Mon 4/7/03 Web2
129 Route to HR Subject Matter Experts for Feedback/Approval 0.5 days Tue 4/8/03 Tue 4/8/03 128 Web2
130 Build Screens 10 days Tue 4/8/03 Tue 4/22/03 129 Web2
131 Integrate into Identitech Processes 15 days Tue 4/22/03 Tue 5/13/03 130 Web2
132 Ready for Testing 0 days Tue 5/13/03 Tue 5/13/03 131
133
134 HR Administration Portal 30.5 days Tue 4/1/03 Tue 5/13/03
135 Develop Prototype Screen(s) 5 days Tue 4/1/03 Mon 4/7/03 Web3
136 Route to HR Subject Matter Experts for Feedback/Approval 0.5 days Tue 4/8/03 Tue 4/8/03 135 Web3
137 Build Screens 10 days Tue 4/8/03 Tue 4/22/03 136 Web3
138 Integrate into Identitech Processes 15 days Tue 4/22/03 Tue 5/13/03 137 Web3
139 Ready for Testing 0 days Tue 5/13/03 Tue 5/13/03 138
140
141 User Acceptance Testing (UAT)/System Test 22 days Mon 5/26/03 Tue 6/24/03
142 Obtain/Create System test data 2 days Mon 5/26/03 Tue 5/27/03 Team
143 Performance Review 5 days Wed 5/28/03 Tue 6/3/03 142 Users
144 Performance Review (Multi-Rater Feedback Sub-Process) 4 days Wed 6/4/03 Mon 6/9/03 143 Users
<project name WBS> 04/10/23
<Project Name> Sarasota County Government
145 Merit Increase 2 days Tue 6/10/03 Wed 6/11/03 144 Users
146 Employee Information Update Process 3 days Thu 6/12/03 Mon 6/16/03 145 Users
147 HR Administrators Portal 15 days Mon 5/26/03 Fri 6/13/03 Resource 2, Resource 1
148 Manager's Portal 4 days Tue 6/17/03 Fri 6/20/03 146 Users
149 Employee's Portal 2 days Mon 6/23/03 Tue 6/24/03 148 Users
150 User Acceptance Testing Complete 0 days Tue 6/24/03 Tue 6/24/03 149
151
152 Implementation 2 days Wed 6/25/03 Thu 6/26/03
153 Load Code in Production Environment 2 days Wed 6/25/03 Thu 6/26/03 150 Team
154 Load Production Data into Production Database 2 days Wed 6/25/03 Thu 6/26/03 150 Team
155 System Live in Production 0 days Thu 6/26/03 Thu 6/26/03 154,153 Team
156
157 Project Closeout Activities 2 days Fri 6/27/03 Mon 6/30/03
158 Archive all Project Documentation 2 days Fri 6/27/03 Mon 6/30/03 155 Team, PM
159 Place all code in Source Safe 1 day Fri 6/27/03 Fri 6/27/03 155 Team
160Conduct Lesson's Learned and Project Close-out Meeting with Stakeholders
0.5 days Mon 6/30/03 Mon 6/30/03 159 PM
161 Close-Out Activities Complete 0 days Mon 6/30/03 Mon 6/30/03 160
162
163 Warranty 24 days? Mon 6/30/03 Thu 7/31/03
164 Warranty Period for Phase I 23 days Mon 6/30/03 Wed 7/30/03 Team
165 Warranty Period Complete 1 day? Thu 7/31/03 Thu 7/31/03 164
166
167Project Complete - Warranty and Project Closeout Activities Complete
0 days Thu 7/31/03 Thu 7/31/03 165
<project name WBS> 04/10/23
<Project Name> Sarasota County Government
APPENDIX C – PROJECT ISSUES LOG
<next page>
<project name WBS> 04/10/23
<Project Name> Sarasota County Government
Project Issues Log - Examples – Delete
Issue # Issue Type, Description and Impact to Project
Priority(M/H/L)
Date Reported
Reported By
Assigned To
DateResolved
Status Resolution/Comments
1 Issue Type: ResourceDescription (revised) Need resource commitments to fully staff the “Red”, “Blue”, and “Quality” teams Impact: If the resources that have been identified aren’t assigned to this project, quality will suffer.
M 02/25/03 Jack Bill Open 02/25 – Will forward the list of requested resources to EIT management by COB on 02/28.03/03 – Have resource commitments for Red Team, part of Blue Team, and we are working on the rest of the list. Resources that are needed that can’t be obtained will be escalated to EIT management.
2 Issue Type: ResourceDescription: No resource commitments from development for GUI development.Impact: The project requires an Internet Presence resource now to review GUI requirements and estimate resources and Level of Effort (LOE).
H 02/26/02 Jack PMO Manager
Open 02/25 – Will forward this issue to the PMO Manager for action
<project name WBS> 04/10/23