Top Banner
Project & Quality Management Day 3 Technology Project Management
57
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project Management

Project & Quality Management

Day 3 Technology

Project Management

Page 2: Project Management

Syllabus Core: PQM

Three main topics

Project Management

• Quality Management

• Reliability Management

Page 3: Project Management

Project Management• Overview of project management,• Project planning;

→Work Breakdown Structure,→The Gantt Chart,→Network Diagram,→Critical Path Diagram,

• Project planning for Technology projects, • Using Microsoft Project to generate charts.

Structure of the Presentation

Page 5: Project Management

What is a Project?

“Any task within an organisation that does not fit neatly into ‘business-as-usual’”

• Port Tunnel

• Luas

• Development of New Engine

• Set up a Quality System in Company

• Technology Design & Make project.

Page 6: Project Management

What is a Project?Projects have the following characteristics:

• Each project is specific and unique.

• Each project has a specific deliverable item when complete.

• This deliverable is aimed at meeting a specific need or purpose.

• There is usually a specific due date for completion of the project.

Design is not necessarily a central part of the project activity.

Page 7: Project Management

What is Managed?

PM focuses on the management of resources and time in a systematic manner.

• The administration of the project

• The supervision of the project

• The organisation of the project

Page 8: Project Management

What is Managed?

For the student it means:

• Analysing the objectives of the project,

• Defining the tasks needed to achieve these objectives,

• Controlling the execution of them.

Page 9: Project Management

Who manages the projeect?

Large projects usually involve a project team.

Project Manager

Specialist Specialist Specialist

Page 12: Project Management

Project Planning

What is a project plan?

• Can be as simple as a list of sequences for a small project

• Can be more complex with charts, tables, costings etc. for a larger project

Page 13: Project Management

Project Planning

1. Analyse the brief,

2. List the steps involved,

3. Draw up a Work Breakdown Structure (WBS).

A WBS is a diagram that shows→ Primary Tasks→ Sub-Tasks

Page 14: Project Management

Example

Draw up a Work Breakdown Structure for the erection of a garden shed.

1. The shed will come prefabricated but will need to be assembled.

2. A foundation will need to be prepared in advance.

Page 15: Project Management

List of Tasks

No. Activity

1 Order Shed

2Buy Blocks, Sand &

Cement

3 Build Foundation

4 Assemble Shed

Page 16: Project Management

WBS for Garden Shed

Garden ShedPrepare Foundation

Buy Blocks and Cement

Place order for shed

Assemble Shed when it arrives

Page 17: Project Management

The Gantt Chart – a Preview

A Gantt Chart is a horizontal bar chart showing the times for each task

Page 18: Project Management

Looking at the Gantt Chart

• Delivery time for the shed is nine days,• One day for buying materials,• Two days for making the foundation,• One day for assembly.

Note:

• Making the foundation is timed so that it is ready just in time for the delivery of the shed

• Could have been completed at an earlier date if desired.

Page 19: Project Management

Exercises

Redraw the Gantt chart so that the maximum amount of time is allowed for the curing of the foundation.

Buy Blocks

Build Foundation

Assemble

Day 0 1 2 3 4 5 6 7 8 9 10

Order Shed from Supplier

Page 20: Project Management

ExercisesShown is a picture of a Christmas Tree Star

1. Draw a WBS for the Star

2. Draw a Gantt chart for manufacturing the Star

Page 21: Project Management

List of Tasks:Star

No. Activity Time

1 Mark Out Star 1

2 Drill Holes 1

3 Cut Out & File 3

4 Solder Circuit 2

5 Assemble 2

6 Test 1

Page 22: Project Management

WBS for Star

Star

Mark Out Drill Cut Out & File

Solder Circuit

Assemble Test

Circuit

Structure

Sub Task

Sub Task

Page 23: Project Management

Gantt Chart for Star

Cut Out & File

Drill

Solder Circuit

Day 0 1 2 3 4 5 6 7 8 9 10

Mark Out

Assemble

Test

Page 24: Project Management

Network DiagramsFor larger or more complex projects a

network diagram is required.

Network Diagrams show:

1. The relationships between the tasks,2. The sequence in which each task is

performed,3. The interdependencies between the

tasks.

Page 25: Project Management

Drawing up a Network Diagram

• Start with task list and draw up a WBS

• Decide on the order of tasks

WBS

Network Diagram

Gantt Chart

Page 26: Project Management

Sample WBS

A WBS needs to be analysed and redrawn frequently to arrive at the best production sequence.

(Use ‘Post its’)

Page 27: Project Management

Network Table

Task Predecessor

A -

B -

C A

D B

E B

F C,D

G E

The tasks and theirpredecessorscan be drawn as a table

Page 28: Project Management

Part Complete Network Diagram

Note that task C has A as a predecessor

D and E have B as predecessors.

A and B have no predecessors and are connected to the starting node.

Page 29: Project Management

Complete Network Diagram

Task Predecessor

A -

B -

C A

D B

E B

F C,D

G E

Exercise:Complete the diagram using the remainder of the tasks

Page 30: Project Management

Network Diagram for Garden Shed

Draw up a network diagram for the garden shed project described previously.

Page 31: Project Management

Some Definitions and TermsTerms used for network diagrams:Activity – A task or set of tasks required by the project.Network – Diagram of nodes representing activities

connected by directional arrows that defines the project and shows the relations between all of the activities. Networks are usually drawn with a ‘Start’ node on the left and a ‘Finish’ node on the right.

Path – A series of connected activities in the networkCritical Path – the set of activities on a path from the

project’s start event to its finish event that if delayed, will delay the completion date of the project.

Critical Time – The time required to complete all activities on the critical path.

Page 32: Project Management

Adding Times to the Network Diagram

• Duration of each task can be added to network diagram

• From this, start and finish times can be found for each task

• Some tasks can be allowed to vary their start and finish times without affecting overall time taken

Page 33: Project Management

Example

Task Predecessor Duration

A - 5 (days)

B - 4

C A 3

D A 4

E A 6

F B,C 4

G D 5

H D,E 6

I F 6

J G,H 4

Consider the following project

Page 34: Project Management

Network with Tasks & Times

Page 35: Project Management

Adding Further Information

We can add the following information to each node in the diagram:

Earliest Start Time (EST)Earliest Finish Time (EFT)

Latest Start Time (LST)Latest Finish Time (LFT)

Page 36: Project Management

Critical Path Diagram

Critical path in orange

See notes for a detailed explanation

Page 37: Project Management

Conclusions from Critical Path Diagram

• Critical path is path that requires the most time (A-E-H-J)

• Critical time is 21 days which is the earliest possible completion time

• Any delay on critical path will delay the project

• Some delay (within limits) can be tolerated on other tasks.

Page 38: Project Management

Critical Path Diagram for the Garden ShedComplete the critical path diagram for the garden shed

State critical path and critical time

Page 39: Project Management

Solution

CP: Order Shed – AssembleCT= 10 Days

Page 40: Project Management

Slack = LFT-EFT = LST-EST

Calculating Activity Slack

Slack or Float is the amount of time a non-critical task can be delayed

Slack = Latest Finish Time – Earliest Finish Time

or

Latest Start Time – Earliest Start Time

Page 41: Project Management

Slack Times from Shed Example

Both non-critical tasks have a slack of (9-3)=(7-1)=(7-1)=(6-0) = 6 days

Page 42: Project Management

The Gantt Chart

• Generated from network diagram

• Gives visual representation of activities and times

• Gantt charts can show:• Timeline for each task• Dependencies of tasks• Critical path

Page 43: Project Management

Network DiagramUsing the Network Diagram from previous example

Page 44: Project Management
Page 45: Project Management
Page 46: Project Management

Application of PM to Tech. ProjectsNow we will apply the techniques we have

met to a hypothetical LC project.

The procedure for project work is:• List the tasks and sub-tasks involved• Draw up a WBS• Draw up a Network Table• Draw up a Network Diagram• Insert times and determine the Critical

Path

Page 47: Project Management

Consider the following project brief

Design and manufacture a personal alarm that will incorporate an electronic circuit as well as a suitable casing

From analysing the brief:• General plan on how to approach the project• Identify the main tasks involved• Derive a Work Breakdown Schedule• Draw up a Network Diagram• Add times and find the critical path, critical

time and slack for the activities.

Page 48: Project Management

A possible WBS for the project

Personal Alarm

Research Circuit

Design Circuit

Order Components

User Survey Design Casing

Manufacture & Assemble

Test

Design Specification

Order Materials

Casing

Circuit

Sub Task

Sub Task

Page 49: Project Management

Network TableFirst draw up a list of tasks and preceding tasks

Task Description Duration Predecessor

A Research Circuit 14 -

B User Survey 7 -

C Device Spec 1 B

D Circuit Design 3 A

E Order Components 10 D

F Design Casing 7 C

G Order Materials 7 F

H Manufacture and assembly

7 E,G

I Test 4 H

Page 50: Project Management

Network Diagram

7

7

Page 51: Project Management

Critical Path Diagram

CP = Circuit Research -Circuit Design-Order Components-Build-Test

CT = 38 class periods

Page 52: Project Management

Gantt Chart for Project

Page 53: Project Management

Student Workbook

List the tasks needed to complete the project

Page 54: Project Management

Example 2

List the tasks

Estimate the times

Draw up WBS and Gantt chart

Page 55: Project Management

Example – Contains circuit

List the tasks & Estimate timesOrder tasks and optimise themDraw up WBS and Gantt chartEstimate project duration

Page 56: Project Management

Example:

Page 57: Project Management

Example