Project charter presentations are used during the meeting with the Project Sponsor or Steering Committee. This meeting is organised in order to get the sign-off under the final copy of the project charter document. When during the meeting some alterations or new decisions are made then the corresponding document should be altered.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Project charter presentation

Project CharterPresentation TemplateAuthor: Bogdan Gorka, PMP

Page 2: Project charter presentation

The project charter (sometimes referred to as Project Definition Document) defines the key project dimensions such as scope, objectives and overall approach for the work to be completed. It is the most important point of reference for project stakeholders interested in the project rationale, its goals and scope. Project charter is also a written contract between the Project Team and Project Sponsor stating clearly what is expected from the project.This template can be used as a guideline about the contents for project charter presentationSuch presentation can be short for the overview purposes or can be detailed depending on the Sponsor’s appetite for details

About this presentation

Project Management Methodology Fundamentals

|2

Page 3: Project charter presentation

Meeting agenda

Welcome 09:00 - 09:15Project Overview 09:15 - 09:35Strategy Alignment and Scope 09:35 – 10:30Break 10:30 – 10:40Organisational Impact 10:40 – 11:00Identified Requirements overview 11:00 – 11:10Project Delivery Approach 11:10 – 11:30Decisions 11:30 – 12:00Other issues

Page 4: Project charter presentation

Project Overview

Project Tempo

Page 5: Project charter presentation

In this section describe the general project background and business context. This may come from your overall business strategy or be a result of the previously completed feasibility study. In this section describe briefly why the organisation is interested in pursuing with the project. Put enough information here so the general rationale for the rest of the documents is clear.An organization's business need or new opportunity may be based on a market demand, technological advance, required training, legal requirement, or governmental standard.This section may also refer to a separately prepared business case analysis and recommendations included there

Organisational Context

Project Management Methodology Fundamentals

|5

Page 6: Project charter presentation

Problem statement – justification for action

Instead of writing ever present ‘Project Scope’ I would suggest starting off with clearly stating problems that we are we addressing. That is why I propose the structure as below:1. Problem statement – state just facts that made you think that you want a change, what basically bothers you and why this induced you to action. This should shortly represent the nature and setting of difficulties that the organisation is currently facing and be powerful enough explaining by the organisation is determined to get rid of these difficulties. In other words it is the project’s business driver.2. Project Final Outcome – After project desired state – how it will look like when the problem is solved. The statements in this section becomes automatically the success criteria to be measured after the project completion. It is another name for project goal which describes the future and directs the planning activities.To help you understand the difference:

– Project output (Objective): New document management system installed and functioning

– Project outcome (Result): Incoming documents are processed more quickly and accurately (and that can be put in measurable dimensions)

Page 7: Project charter presentation

Project Mission

Although this section should be relatively short, it is pretty difficult to write it. Try to describe generally but in a straightforward way what effect you are trying to achieve by delivering project results.Example:To cut general effort required for paperwork in the office by introducing a new document management system enabling company-wide access to business documents along with electronic workflow and sign off. The project should be completed by the end of year 2010 with the budget not exceeding $1m in capex.In this way we have a short story for everyone interested in what the project is about and what are the limits set by the Sponsorship.

Page 8: Project charter presentation

Strategy Alignment

Project Tempo

Page 9: Project charter presentation

Business Strategy Alignment

Before stating further what the project is about, we must ensure that it is in this way or another aligned with the corporate strategyProject that are cross functional and are not aligned with strategy will be very difficult to run due to the following reasons:– Lack of interest in the project from the Project Sponsor’s

peers– Difficulty to find good and reliable internal resources to

deliver project scope– Lack of involvement from the internal resources will result in

underdeveloped scope statement and undiscovered risks– Eventually the project almost certainly will not get funded or

will be abandoned during or after the design phase.

Page 10: Project charter presentation

IT Strategy Fit

If the project will use the IT resources, it should state clearly how much the proposed solution is aligned with the existing systems and networks architecture

Page 11: Project charter presentation

Objectives and Scope

Project Tempo

Page 12: Project charter presentation

Project objectives describe what tangible results the project works will deliver. In order for the project objectives to be truly tangible, they have to be specific and concrete. It is best achievable when they are deliverable based.In this way, the completion of any given objective will be evident when one of more deliverables are done. 

Project Objectives

Project Management Methodology Fundamentals

|12

Page 13: Project charter presentation

Project Objectives and Scope of Delivery

Project Management Methodology Fundamentals

|13

Project Objective Deliverables

1) Standardise and update existing document flow procedures

1. Existing document flow procedures identified

2. Procedure owners identified

3. New procedures designed and written

2) Search and select software vendors for document management systems

1.Research systems vendors on the market

2. Perform Request For Information Process as per Vendor policy

3. Collect RFI feedback and prepare solution selection guidelines

3) Prepare Requirement statement 1. Select potential key users for workshops

2. Prepare and organise user requirements elicitation workshops

3. Summarise requirements in the User Requirements Traceability Matrix

4) Other objectives Other deliverables

Page 14: Project charter presentation

Out of scope:It is important to clearly state what results / deliverables will not be delivered. Sometimes key project stakeholders have some expectations they think will be delivered on the occasion of a new project. They should be informed, and especially the Steering Committee, that these features, results or deliverables are out of scope and will not be prepared. Managing expectations is crucial taking into account that the project charter serves the role of a contract between the Project Team and Project Sponsor.

Scope exclusions

Project Management Methodology Fundamentals

|14

Page 15: Project charter presentation

Impact on organisation

Project Tempo

Page 16: Project charter presentation

Organisational Impact

It is necessary, in order to get a full picture, to describe how this project will change the current status quo of the organisation. If the change is big, the project charter should include only a summary of the full change assessment analysis separate document.

Organisation/Department/Processes How will the be affected/No of people impacted

1. Mail Office Current practices in documents flow will be identified and changed considerably. No mail handling is currently done electronically and employees are not used to working on computers.

After the project both the procedures and tools will change. 1. Accounts Receivable Currently only some invoices are being signed-off

electronically. For now it is the project intention to include this work-flow fully in the scope. Affected 50 people.

1. Entire business – budget scope When the affected department will change into a fully electronic workflow this will mean that the budget of $10m spent annually will be managed differently. That is why this project is more risk sensitive and is business continuity critical. That is why only safe and proven solutions will be chosen.

Page 17: Project charter presentation

Another template for Business Impact

The Consequence of implementing the project:

Area Impact

Page 18: Project charter presentation

Process Change Impact

List which business processes will be affected by the project

Organisation area Process Name

1. Finance Department Accounts Receivable

Accounts Payable

Manual invoicing2. IT Department Application landscape update

3. Mail Office Invoice processing

TOTAL: 23 processes

Page 19: Project charter presentation

System Change Impact

Which existing systems be affected by the projectWhat existing interfaces will have to be upgraded, changedOverview of data to be migratedState generally if the change is considerable in terms of risks and resources

Page 20: Project charter presentation

Business RequirementsOverviewProject Tempo

Page 21: Project charter presentation

High Level Business Requirements

What the end result should be / look likeWhat business result are you trying to achieve. Describe it in such a way that the expected quality of results will be easy to understand

Page 22: Project charter presentation

Project Delivery ApproachProject Tempo

Page 23: Project charter presentation

Implementation Assumptions

(Assumptions made about the project related to resources, scope, expectations and schedules.)Implementation Approach - AssumptionsThe solution will be introduced with the implementation partner using the following assumptionsWe will use the pre-configured DocuNext solution dedicated for the mining industry. The re-design of existing processes will be based on the gap analysis between the AS-IS process map and the preferred TO-BE mapThe system launch will be performed at all locations in one time – the big bang approachWe will implement the system in two waves – most crucial functionalities first and additional remaining functionality nextWe will use the PRINCE2 methodology with PMBOK elementsWe will use the VISIO based process maps and convert them later into our ARIS corporate model

Page 24: Project charter presentation

Implementation Constraints

Implementation Approach – ConstraintsThe first way of implementation cannot exceed 1 April 2011The budget for this project cannot exceed $1.5 for both implementation wavesSome 25% of future system users are not competent in basic PC usage.

24

Page 25: Project charter presentation

Training Approach

The project will adopt the a train-the-trainer approach where project key users will be trained on the advanced usage of the systemUsers in other locations will be invited to one of the two training facilities in Adelaide or in MelbourneIn order to accelerate the training process we will use the Computer Based Training tools and pre-recorded short movies.

25

Page 26: Project charter presentation

Change and Communication Approach

Business Change and Communication ApproachThe impact of the project on the organisation will be considerable and it is very important for the business community to understand why the project is being commissioned and what benefits are expected after the implementation.Below is the outline of the approach to introduced in this project:Fixed dates of meetings with Project Sponsor and Steering Committee every six weeksSteering Committee Stage Gate meetings confirm the completion of each phase

26

Page 27: Project charter presentation

Project Communication Approach

HR Department will be involved in spreading the word-of-mouth about the project using their regular communication channels. They will be well briefed and equipped with the information pack.Project internal communication will be done via weekly Status and Risk Meetings as well as the project message board.Communication to the future users community will be executed by the monthly Newsletter containing the key milestones completion, information about project team and current progressWe will periodically do a research of users’ community perception of the project to be able to counterpart any misunderstanding or myths

27

Page 28: Project charter presentation

Project Reporting

Project reporting will include:– Weekly team leaders’ status reports – for Project Manager– Weekly project status report – for Sponsor– Monthly project status report – for Steering Committee and

external communication– Steering Committee status presentations – for cycle

meetings every 6 weeks

28

Page 29: Project charter presentation

Project Implementation Schedule- Project Approach -

Page 30: Project charter presentation

Project Schedule

Overview of Project Schedule:

Phase Phase Start / End dates

Milestone Deliverable

Discovery Phase

Scoping & Visioning

Design Phase

Construction Phase

Testing &Delivery Phase

Go live with Pilot Sites

Roll out and Project Close out Sign-off

Page 31: Project charter presentation

Project Organisation and Resourcing

Page 32: Project charter presentation

Project Team Structure

- Project Organisation and Resourcing -

Page 33: Project charter presentation

Project Team Structure

1 x Steering Committee

1 x Project Manager

Process Owners

Executive Sponsor

FunctionalityTeam

ApplicationsTeam

TechnicalTeam

Change Mgt &End User Training

Page 34: Project charter presentation

Roles and Responsibilities- Project Organisation and Resourcing -

Page 35: Project charter presentation

Steering Committee

The Steering Committee for this project includes the Executive Sponsor, Process Owner, Project Manager, Team Leader. On behalf of the Board, their responsibilities include:– Verify the business requirements and scope– Approve organisational, policy, and strategic changes.– Committee necessary resources and budget on enterprise

basis.– Authorise changes to the plan– Make timely decisions– Educate peers and staff on the merits of the project– Ensure integration across the project is attained

Page 36: Project charter presentation

Process Team Management

Executive Sponsor:– Ensuring process view of the Project.– Chairing monthly process team meetings.– Providing guidance and direction to process team (from

Board perspective).– Resolve process and organisational issues.– Resolve personnel issues.– Ensure broad base involvement and business ownership.– The executive sponsor is responsible to collect track and

analyse the benefits from a process change. He or she is also the primary point of contact with the business process owner. Together, they are responsible to improve the processes, using the measured benefits as feedback information

Page 37: Project charter presentation

Process Team Management (Cont)

Process Owner:

Page 38: Project charter presentation

Process Teams

(Functionality, Applications, Technical, Training and Change Management)

Page 39: Project charter presentation

Project Risk Assessment

Page 40: Project charter presentation

Project Risk Assessment Summary

Identified Risk $ Impact and mitigation strategy

Page 41: Project charter presentation

Project Financial JustificationProject Tempo

Page 42: Project charter presentation

Cost Justification Methodology

EstimatedPotential Benefits

EstimatedImplementation& Support Costs

Net Savings

Benefits

Costs

A

B

C

-

=

Minus:

Equals:

Over the Analysis Period

• Operational Benefits• Avoided future planned projects

One-Time Costs• Staff Related

Costs (internal and external)

• Hardware• Software• Facilities• Training• Other

On-Going Costs• Operational

support• Hardware• Software

Net Saving from Implementation

Page 43: Project charter presentation

Financial Assumptions

(The financial analysis presented in this document reflects the information and assumptions available to the project team at this time …)

Page 44: Project charter presentation

Project Implementation Costs

Paste the project preliminary budget including separate budget for identified risks

Page 45: Project charter presentation

Maintenance (ongoing) Costs

Present costs that will be borne to maintain the project results after the completionInclude additional headcount, licenses, service agreements

Page 46: Project charter presentation

Cost Savings

As a result of calculations show the logic behind and calculations which justify the costs of the project

Page 47: Project charter presentation

Benefit Realisation

- Project Justification -

Page 48: Project charter presentation

Benefit Realisation Plan

Who by name is the owner of the benefits to be reviewed after the project completionWhat is the role of this person during the project

Page 49: Project charter presentation

Cost vs Benefits Summary- Project Justification -

Page 50: Project charter presentation

Cost vs Benefits Summary

Page 51: Project charter presentation

Conclusion / Questions