Page 1: Project Appraisal

04/07/2023

DELHI METRO

Subject : Project Appraisal

Faculty:Prof. M.Zakaria

BY: Subhank Modi

SS11/13 SPABF

1/26

Page 2: Project Appraisal

04/07/2023

DELHI METRO

• The Delhi Metro is a rapid transit system serving Delhi, Gurgaon, Noida and Ghaziabad in the National Capital Region of India.

• Delhi Metro is being built and operated by the Delhi Metro Rail Corporation Limited (DMRC).

• Began operation: 24 December 2002.

2/26

Page 3: Project Appraisal

04/07/2023

Market Demand Analysis

• Delhi, the capital city of India, is one of the fastest growing cities in the world with a population of 13 million .

• The road length(1340km) is not at par with the phenomenal growth in the number of vehicles on these roads in Delhi.

3/26

Page 4: Project Appraisal

04/07/2023

Market Demand Analysis

• With gradual horizontal expansion of the city, the average trip length of buses has gone up to 13 km and the increased congestion on roads has made the corresponding journey time of about one hour.

• Delhi has now become the fourth most polluted city in the world.

4/26

Page 5: Project Appraisal

04/07/2023

Break down of demand

5/26

Page 6: Project Appraisal

04/07/2023

MARKET DEMAND ANALYSIS (PRICE)

• RITES (1995b) considered four rates per trip: Rs 3, 4, 5, 6 at April 1995 prices and the fare sensitivity of ridership.

• The main source of revenue of the MRTS system is the fare box collection, which is a product of the total passenger ridership on the MRTS and the fare charged.

• The financial model consisting of Rs. 5 per passenger trip and an annual fare increase of 7.5 per cent was considered optimal by RITES.

6/26

Page 7: Project Appraisal

04/07/2023

Market Demand Analysis

Govt Policy:• Planning for the metro started in 1984, when

the Delhi Development Authority and the Urban Arts Commission came up with a proposal for developing a multi-modal transport system for the city.

• The Government of India and the Government of Delhi jointly set up the Delhi Metro Rail Corporation (DMRC) in 1995.

7/26

Page 8: Project Appraisal

04/07/2023

PRICES• Tourist Card:• For unlimited travel over short periods. There are two kinds of

cards - 1 day and 3 day.• - Value of 1-Day Card: Rs 100• - Value of 3-Day Card: Rs 250• - Refundable Deposit: Rs 50/- payable at purchase (refundable on

return of card) • Token:• - Single-Journey Token: For one way journey• - Value will depend on the destination. Valid only on the day of

purchase.• - Minimum Fare Rs. 8/- and Maximum Fare Rs. 30/-

8/26

Page 9: Project Appraisal

04/07/2023 9

Method of Distribution• How to use your Token:• - Hold your token close to the

machine for the gates to open.• - At exit, drop a Single-Journey

token into the machine. • How to use your Smart Card/

Tourist Card:• - For entry to the station, please

exhibit your travel card at the entry gate for the flap to open.

• - For exit please exhibit your travel card at the exit gates for the flap to open and to do an exit from the station.

9/26

Page 10: Project Appraisal

04/07/2023

Government Policy• The DM had been provided with the following concessions by GOI to

make the project viable, namely a) The cost of land equivalent to Rs. 2180 million has been provided as

an interest free subordinate loan by GOI/GNCTD to be repaid by the DM.

(b) The risk associated with the exchange rate fluctuations is borne by government in case of foreign debt,

(c) The DM is exempted from payment of income tax, capital gains tax, property tax and customs duty on imports,

(d) The DM is permitted to generate resources through property development over a period of 6-20 years and

(e) No dividend is paid on GOI share of equity till the senior debt is repaid fully by the twentieth year.

10/26

Page 11: Project Appraisal

04/07/2023 11

TECHNICAL ANALYSIS

7772 56341 6406311/26

Page 12: Project Appraisal

04/07/2023 12

Distribution of Total costs

Engineer-ing

Works; 31327

Electrical Works; 6970

Signalling and

Telecom-munication;

4504

Rolling Stock; 10999

Land; 3339

General Es-tablishment and Consul-

tancy Charges,

5101Contingencies;

1823

Total Cost

Engineering WorksElectrical WorksSignalling and TelecommunicationRolling StockLandGeneral establishment and Consultancy ChargesContingencies

12/26

Page 13: Project Appraisal

04/07/2023

TECHNICAL ANALYSIS

• The Delhi Metro (DM) planned in four phases is part of the MRTS.

• As of August 27, 2011, the whole of Phase-I and Phase-II are complete, with the network comprising six lines with 142 metro stations and a total length of 189.7 km (117.9 mi)

• Phases III (112 km) and IV (108.5 km) are planned to be completed by 2015 and 2021 respectively, with the network spanning 413 km (257 mi) by then.[

13/26

Page 14: Project Appraisal

04/07/2023 14

14/26

Page 15: Project Appraisal

04/07/2023 15/26

Page 16: Project Appraisal

04/07/2023 16

PHASE 1

Corridor Length (Km)

Under Ground Corridor

13.17

Elevated Corridor

47.43

Grade Rail Corridor

4.5

The 1st Phase consists of 3 corridors divided in to 9 sections

Total Length 65.10 km

16/26

Page 17: Project Appraisal

04/07/2023

PHASE 2The 1st Phase consists of 3 corridors divided in to 12 sections

Corridor Length (Km)

Under Ground Corridor

8.93

Elevated Corridor

42.24

Grade Rail Corridor

1.85

Total Length 53.02 km

17/26

Page 18: Project Appraisal

04/07/2023

FINANCIAL ANALYSIS

18/26

Page 19: Project Appraisal

04/07/2023 19/26

Page 20: Project Appraisal

04/07/2023 20/26

Page 21: Project Appraisal

04/07/2023

Net Present Value

• An estimate of NPEB of the Metro using the first approach and an 8 percent rate of discount is Rs. 432387.5 million while the estimate using the second approach and a 10 percent rate of discount is Rs. 232050.7 million.

• The estimates of the economic internal rate of return (IRR) corresponding to the first and second approaches are 23.86 and 23.88 percent, respectively.

21/26

Page 22: Project Appraisal

04/07/2023

SOCIAL COST BENEFIT ANALYSIS

• The social cost-benefit analysis of the Metro requires the identification of benefits and the economic agents affected by it. The incremental changes in the incomes of various economic agents:

• passengers, transporters, public and government and unskilled labour due to the Metro could be estimated by considering the Delhi economy with and without the Metro.

22/26

Page 23: Project Appraisal

04/07/202323/26

Page 24: Project Appraisal

04/07/2023 24/2624/26

Page 25: Project Appraisal

04/07/2023

SOCIAL COST BENEFIT ANALYSIS

• Savings in Foreign Exchange due to reduced Fuel Consumption

• Reduction in Pollution • Savings in Time for all passengers using Metro and Roads • Savings in Accidents • Savings in Vehicle Operating Cost (VOC) due to

decongestion for residual traffic • Savings in Capital and Operating cost of diverted vehicles • Savings in the cost of Road Infrastructure

25/26