PROYEK PURIINDAHFINANCIALTOWERPKP 1053 DAFTAR ISIINFORMASI PROYEKITEM PARETOTARGET MUTUMETODE KERJAPROGRAM KERJASCHEDULE HOLD POINTSTRUKTUR ORGANISASIRAPP

INFORMASI PROYEK DATA PROYEK PURI INDAH FINANCIAL TOWERNAMA PROYEK : PURI INDAH FINANCIAL TOWERPEMILIK PROYEK: PT. ANTILOPE MADJU PURI INDAHKONSULTAN PERENCANA: ARC PAC PT. ARGO CALISTA DESAINKONSULTAN STRUKTUR : DAVY SUKAMTA & PARTNERSKONSULTAN QS: WILDE & WOLLARD INDONESIANILAI KONTRAK: Rp. 85.859.510,418 Excl. PPNMASA PELAKSANAAN :

330 HARI KALENDER Mulai tgl 17 September 2013 s/d 13 Agustus 2014 11 Bulan (STRUKTUR,ARS. DAN PLUMBING)465 HARI KALENDER (KOORDINASI NSC) 15 Bulan

LINGKUP PEKERJAAN :

BANGUNAN:

LUASAN BANGUNAN:PEKERJAAN STRUKTURPEKERJAAN ARSITEK PASANGAN BATAPEMASANGAN HTRAILLING TANGGAPEMASANGAN SANITAIRPLUMBING4 (EMPAT) BASEMENT25 (DUA PULUH LIMA) LANTAI DAN ATAPBASEMENT 20.000 M2 TYPICAL FLOOR 1.750 M2

PEKERJAAN BESI VOL: 3.643 TON (BESI SUPPLY BY OWNER)PEKERJAAN BETON: 28.125 M3 (SUPPLY BY OWNER)PEKERJAAN BEKISTING: 136.128 M2PASANGAN BATA DINDING: 25.394 M2

ITEM MAJOR

PETA PROYEK LOKASI PROYEK

TAMPAK BANGUNAN

DENAH B4

DENAH B3

DENAH B2

DENAH B1

DENAH GF

DENAH L2-L4

DENAH L5

DENAH L6 - L25

DENAH LANTAI MECHANICAL

LAYOUT DIREKSI KEET

LAYOUT PLAN

ITEM PARETOA. Pek. Persiapan Prasarana & Penunjang1. Peralatan, Bahan & Tenaga kerja7.598.081.5009 %B. Pek. Struktur1. Pek. Bekesting23.127.766.63327 %2. Pek. Pembesian5.373.206.3616 %3. Pek. Beton4.785.894,6716 %4. Pek. Atap3.845.389,7443 %C. Pek. Finishing 1. Pek.Dinding8.983.330.04410% 2. Pek. Plafond1.636.292.4912% 3. Pek. Lantai4.734.086.5246%D. Pek. Plumbing 1. Pek. Plumbing4.410.445.4705%E. Nominated Subcontractor, Direct contractor and suppliers1. Biaya Koordinasi dan management fee7.531.000.0009%2. Pek. Pintu dan Pengecatan5.000.000.0006%

Jumlah77.025.493.43990%ITEM PARETO

TARGET MUTU

TARGET MUTU

TARGET MUTU

TARGET MUTU

TARGET MUTU

METODE KERJA

REKAP VOLUME BESI, BEKESTING DAN BETON

RENCANA PENEMPATAN TCRENCANA TC : 2 BHTC 1 = 50 MTC 2 = 55 M

Basement 4~1ZONING PENGECORAN PLAT DAN BALOK

ZONA P2ZONA P3ZONA P4ZONA P1ZONA P6ZONA T2ZONA P5ZONA T1TC2TC150 mtr55 mtr

GroundfloorZONING PENGECORAN PLAT DAN BALOK

ZONA P2ZONA P3ZONA P4ZONA P1ZONA P6ZONA T2ZONA P5ZONA T1TC2TC150 mtr 55 mtr

Lantai 2~5ZONING PENGECORAN PLAT DAN BALOK

ZONA P2ZONA P3ZONA P1ZONA T2ZONA T1TC1 TC250 MTR 55 MTR

Lantai 6~26ZONING PENGECORAN PLAT DAN BALOK

ZONA T2ZONA T1Siklus Pengecoran

Potongan Siklus Pengecoran BSM 4 BSM 1

Potongan Siklus Pengecoran LT Dasar LT 4

Potongan Siklus Pengecoran LT 5 LT 9

Potongan Siklus Pengecoran LT 10 LT 14

Potongan Siklus Pengecoran LT 15 LT 19

Potongan Siklus Pengecoran LT 20 LT 25PengPengecoran terakhir 21 Mei 2014

PROGRAM KERJA

SCHEDULE HOLD POINT & WITNESS POINT

SCHEDULE HOLD POINT & WITNESS POINT

STRUKTUR ORGANISASI

STRUKTUR ORGANISASITarget-1Q S H E P L A NNo. PKP:1053PURI INDAH TOWERHalaman:1/4Revisi:0TARGET MUTUTanggal:10 Juni 2013DAFTAR TARGET MUTUDibuat Oleh:Budi SetiadiDisetujui Oleh:Sugeng SubagyoNOITEM PEKERJAANPENJELASANSPESIFIKASI1Pekerjaa persiapan- Pengukuran siku harus menggunakan alat ukurSpesifikasi Teknisdan pengukuran- Pembersihan site dan improvement sebelum pelaksanaan proyek,dan membuang semua sisa material selama dan setelah pekerjaan2Pekerjaan Persiapan- Beton bench mark ukuran 20x20 cm tertanam sedalam 1 m,bagian di atas tanah min setinggi 40 cm- Papan bowplank dari kayu Meranti 5/7, jarak maks 2m- Ukuran papan patok ukur tebal 3cm, lebar 20 cm, lurus dan diserut- Pagar pengaman proyek seng gelombang BJLS 20 dicat, tinggi 180 cm- Pondasi pagar pengaman cor beton setempat minimum penampangdiameter 30cm, dalam 50cm dari permukaan tanah ,adukan 1:3:53Pekerjaan beton- ASTM C 33 : Agregat berat normalSpesifikasi Tekniscor di tempat- ATM C 33 : Agregat beton ringan- ASTM C 150 : Portland cement-Bahan batu bersih dari bahan-bahan yang merugikanQ S H E P L A NNo. PKP:1053PURI INDAH TOWERHalaman:2/4Revisi:0TARGET MUTUTanggal:10 Juni 2013DAFTAR TARGET MUTUDibuat Oleh:Budi SetiadiDisetujui Oleh:Sugeng SubagyoNOITEM PEKERJAANPENJELASANSPESIFIKASI4Pekerjaan Beton-Mutu BetonSpesifikasi TeknisTolerasi selimut beton--Semen yang di gunakan hanya semen portlandKadar Semen 290 kg/m3Ukuran agregat maks 37 mmKuat tekan benda uji silinder Minimum 7 hariKuat tekan benda uji kubus Minimum 7 hari5Pembesian- Kekuatan besi sesuai jenisnyaSpesifikasi Teknis- Mutu besi U-24 (polos) untuk diameter kurang dari 13 mmdan U-39 (ulir) untuk diameter lebih besar dari dan samadengan 13 mm- Besi tidak berkarat, tidak kotor, bebas oli,catdan lain-lain- Diameter, jarak, jenis dan jumlah sesuai dengan gambar- Besi terikat kuat satu dengan yang lain- Saat pengecoran tidak berubah posisi- Jarak besi dengan bekisting sesuai dengan gambar6Bekisting- Plywood (Phenol Film), permukaan halus dan lurus baik satu atau dua mukaSpesifikasi Teknis- Kayu lurus dan kuat- PD-8, Schaffolding Cs, tidak keropos- Dapat memberikan kesan permukaan ekspose yang menerus lurus dan halus- As finish +/- 5 mm- Toleransi deviasi garis vertikal & horisontalmax : 6 mm. Pada jarak 3 m10 mm, pada jarak 6 m20 mm, pada jarak > 12 m- Deviasi > 3 m +/- 10 mm- Penyangga kuat oleh beban beton yang akan dicor- Celah dan sambungan tertutup dengan rapi- Mudah pembongkarannyaQ S H E P L A NNo. PKP:1053PURI INDAH TOWERHalaman:3/4Revisi:0TARGET MUTUTanggal:10 Juni 2013DAFTAR TARGET MUTUDibuat Oleh:Budi SetiadiDisetujui Oleh:Sugeng SubagyoNOITEM PEKERJAANPENJELASANSPESIFIKASI7Pekerjaan langit-langit-Bahan dan persyaratan sesuai dengan gambarSpesifikasi Teknis(plafon)-Pemasangan ceiling sesudah pekerjaan ME-Pekerjaan harus rata, tidak bergelombang dan rapih-Semua pekerjaan menggunakan bahan yang baru, tidak cacat8Pekerjaan Pasangan Celcon- Menggunakan Celcon uk 60 x 20 x 10 cmSpesifikasi Teknis- Untuk spesi digunakan semen instan khusus celcon dg tebal 3 mm- Pemasangan dilakukan dengan cara selang seling- Pemasangan harus lot dan siku secara vertikal dan sesuai dengan marking9Pekerjaan Plesteran- Menggunakan Semen instanSpesifikasi Teknis- Tebal spesi plesteran 1 cm- Tebal spesi acian 1 cm- Harus dibuat kepalaan dengan jarak antara maks 1,5 m10Pekerjaan Ralling-Pipa besi untuk railling/pagar/tiang adalah pipa galvanish sesuai gambarSpesifikasi Teknis-Pipa besi dicat dasar anti karat dengan finishing cat minyak / cat duco-AWS D10-69 : Penyambungan las-Railling tangga terbuat dari galvanis diameter 2 1/2"11Pekerjaan Pasangan keramik- Ukuran dan tipe keramik harus sesuai dengan persetujuan materialSpesifikasi Teknis- Menggunakan semen instan (lem keramik)- Start keramik harus sesuai dengan gambar- Pasangan harus level rapi, ukuran nat harus seragamQ S H E P L A NNo. PKP:1053PURI INDAH TOWERHalaman:4/4Revisi:0TARGET MUTUTanggal:10 Juni 2013DAFTAR TARGET MUTUDibuat Oleh:Budi SetiadiDisetujui Oleh:Sugeng SubagyoNOITEM PEKERJAANPENJELASANSPESIFIKASI12Pemasangan sanitair-Semua perlengkapan dipasang menurut petunjuk pabrik dan spesifikasi teknis, kecuali diisyaratkan lainSpesifikasi teknis-Pemasangan semua sambungan harus kedap air dan udara-Tidak menggunakan bahan penutup sambungan, cat, vernis, dempul, dll sampai sambungan dipasang kuat dan diuji-Bak cuci tangan dipasang ada meja pada ketinggian sesuai Gambar Kerja---Sistem penumpu dan penoang harus sesuai dengan rekomendasi pabrik pembuat sanitasi-

Sheet1PURI INDAH TOWERTARGET MUTUDAFTAR TARGET MUTUNOITEM PEKERJAANPENJELASANSPESIFIKASI1Pekerjaa persiapan- Pengukuran siku harus menggunakan alat ukurSpesifikasi Teknisdan pengukuran- Pembersihan site dan improvement sebelum pelaksanaan proyek,dan membuang semua sisa material selama dan setelah pekerjaan2Pekerjaan Persiapan- Beton bench mark ukuran 20x20 cm tertanam sedalam 1 m,bagian di atas tanah min setinggi 40 cm- Papan bowplank dari kayu Meranti 5/7, jarak maks 2m- Ukuran papan patok ukur tebal 3cm, lebar 20 cm, lurus dan diserut- Pagar pengaman proyek seng gelombang BJLS 20 dicat, tinggi 180 cm- Pondasi pagar pengaman cor beton setempat minimum penampangdiameter 30cm, dalam 50cm dari permukaan tanah ,adukan 1:3:53Pekerjaan beton- ASTM C 33 : Agregat berat normalSpesifikasi Tekniscor di tempat- ATM C 33 : Agregat beton ringan- ASTM C 150 : Portland cement- Bahan batu bersih dari bahan-bahan yang merugikan4Pekerjaan Beton- Mutu BetonSpesifikasi TeknisTolerasi selimut betonSemen yang di gunakan hanya semen portlandKadar Semen 290 kg/m3Ukuran agregat maks 37 mmKuat tekan benda uji silinder Minimum 7 hariKuat tekan benda uji kubus Minimum 7 hari5Pembesian- Kekuatan besi sesuai jenisnyaSpesifikasi Teknis- Mutu besi U-24 (polos) untuk diameter kurang dari 13 mmdan U-39 (ulir) untuk diameter lebih besar dari dan samadengan 13 mm- Besi tidak berkarat, tidak kotor, bebas oli,catdan lain-lain- Diameter, jarak, jenis dan jumlah sesuai dengan gambar- Besi terikat kuat satu dengan yang lain- Saat pengecoran tidak berubah posisi- Jarak besi dengan bekisting sesuai dengan gambar6Bekisting- Plywood (Phenol Film), permukaan halus dan lurus baik satu atau dua mukaSpesifikasi Teknis- Kayu lurus dan kuat- PD-8, Schaffolding Cs, tidak keropos- Dapat memberikan kesan permukaan ekspose yang menerus lurus dan halus- As finish +/- 5 mm- Toleransi deviasi garis vertikal & horisontalmax : 6 mm. Pada jarak 3 m10 mm, pada jarak 6 m20 mm, pada jarak > 12 m- Deviasi > 3 m +/- 10 mm- Penyangga kuat oleh beban beton yang akan dicor- Celah dan sambungan tertutup dengan rapi- Mudah pembongkarannya7Pekerjaan langit-langit-Bahan dan persyaratan sesuai dengan gambarSpesifikasi Teknis(plafon)-Pemasangan ceiling sesudah pekerjaan ME-Pekerjaan harus rata, tidak bergelombang dan rapih-Semua pekerjaan menggunakan bahan yang baru, tidak cacat8Pekerjaan Pasangan Celcon- Menggunakan Celcon uk 60 x 20 x 10 cmSpesifikasi Teknis- Untuk spesi digunakan semen instan khusus celcon dg tebal 3 mm- Pemasangan dilakukan dengan cara selang seling- Pemasangan harus lot dan siku secara vertikal dan sesuai dengan marking9Pekerjaan Plesteran- Menggunakan Semen instanSpesifikasi Teknis- Tebal spesi plesteran 1 cm- Tebal spesi acian 1 cm- Harus dibuat kepalaan dengan jarak antara maks 1,5 m10Pekerjaan Ralling-Pipa besi untuk railling/pagar/tiang adalah pipa galvanish sesuai gambarSpesifikasi Teknis-Pipa besi dicat dasar anti karat dengan finishing cat minyak / cat duco-AWS D10-69 : Penyambungan las-Railling tangga terbuat dari galvanis diameter 2 1/2"11Pekerjaan Pasangan keramik- Ukuran dan tipe keramik harus sesuai dengan persetujuan materialSpesifikasi Teknis- Menggunakan semen instan (lem keramik)- Start keramik harus sesuai dengan gambar- Pasangan harus level rapi, ukuran nat harus seragam12Pemasangan sanitair-Semua perlengkapan dipasang menurut petunjuk pabrik dan spesifikasi teknis, kecuali diisyaratkan lainSpesifikasi teknis-Pemasangan semua sambungan harus kedap air dan udara-Tidak menggunakan bahan penutup sambungan, cat, vernis, dempul, dll sampai sambungan dipasang kuat dan diuji-Bak cuci tangan dipasang ada meja pada ketinggian sesuai Gambar Kerja---Sistem penumpu dan penoang harus sesuai dengan rekomendasi pabrik pembuat sanitasi-

Rekap Vol. PuriREKAPVolume Beton, Besi dan Bekesting1.0000.0010.050BANGUNANCOREWALLT O T A LT O T A LNo.Area PekerjaanBetonBesiBekestingBetonBesiBekestingBetonBesiBekestingBetonBesiBekesting( m3 )( kg )( m2 )( m3 )( kg )( m2 )( m3 )( kg )( m2 )tonton( m2 )

1Bsm 410,219.001,534,299.9814,227.0097.7520,782.12544.7510,316.751,555,082.1014,771.7510,316.751,555.08738.592Bsm 31,040.00134,002.994,606.0097.7520,782.12544.751,137.75154,785.115,150.751,137.75154.79257.543Bsm 21,113.00146,620.834,832.0097.7520,782.12544.751,210.75167,402.955,376.751,210.75167.40268.844Bsm 11,044.00117,475.784,501.0097.7520,782.12544.751,141.75138,257.905,045.751,141.75138.26252.295LantaiDasar1,121.00110,800.906,295.00147.0033,522.29773.501,268.00144,323.187,068.501,268.00144.32353.436Lantai2626.0078,822.354,703.00147.0033,522.29773.50773.00112,344.645,476.50773.00112.34273.837Lantai3639.0085,892.464,839.00137.0025,848.19721.00776.00111,740.655,560.00776.00111.74278.008Lantai4542.0076,703.704,020.00137.0025,848.19721.00679.00102,551.904,741.00679.00102.55237.059Lantai5541.0063,725.614,126.00137.0025,848.19721.00678.0089,573.814,847.00678.0089.57242.3510Lantai6339.1448,009.502,536.4395.4017,223.74502.80434.5465,233.243,039.23434.5465.23151.9611Lantai7339.1448,009.502,536.4395.4017,223.74502.80434.5465,233.243,039.23434.5465.23151.9612Lantai8339.1448,009.502,536.4395.4017,223.74502.80434.5465,233.243,039.23434.5465.23151.9613Lantai9339.1448,009.502,536.4395.4017,223.74502.80434.5465,233.243,039.23434.5465.23151.9614Lantai10339.1448,009.502,536.4395.4017,223.74502.80434.5465,233.243,039.23434.5465.23151.9615Lantai11339.1448,009.502,536.4394.2516,676.73629.25433.3964,686.243,165.68433.3964.69158.2816Lantai12339.1448,009.502,536.4394.2516,676.73629.25433.3964,686.243,165.68433.3964.69158.2817Lantai13341.0048,009.502,525.0094.2516,676.73629.25435.2564,686.243,154.25435.2564.69157.7118Lantai14341.0048,009.502,537.0094.1414,221.11629.29435.1462,230.613,166.29435.1462.23158.3119Lantai15341.0047,580.502,537.0094.1414,221.11629.29435.1461,801.603,166.29435.1461.80158.3120Lantai16345.8647,873.302,577.2694.1414,221.11629.29440.0062,094.413,206.54440.0062.09160.3321Lantai17345.8647,873.302,577.2694.1414,221.11629.29440.0062,094.413,206.54440.0062.09160.3322Lantai18345.8647,873.302,577.2694.1414,221.11629.29440.0062,094.413,206.54440.0062.09160.3323Lantai19345.8647,873.302,577.2694.1414,221.11629.29440.0062,094.413,206.54440.0062.09160.3324Lantai20345.8647,873.302,577.2694.1414,221.11629.29440.0062,094.413,206.54440.0062.09160.3325Lantai21345.8647,873.302,577.2698.8012,345.08657.80444.6660,218.383,235.06444.6660.22161.7526Lantai22345.8647,873.302,577.2698.8012,345.08657.80444.6660,218.383,235.06444.6660.22161.7527Lantai23348.0047,873.302,575.0098.8012,345.08657.80446.8060,218.383,232.80446.8060.22161.6428Lantai24348.0047,873.302,575.0098.8012,345.08657.80446.8060,218.383,232.80446.8060.22161.6429Lantai25350.0047,873.302,602.0098.8012,345.08657.80448.8060,218.383,259.80448.8060.22162.9930Lantai26Atap442.8559,316.003,091.0094.2516,676.73629.25537.1075,992.733,720.25537.1075.99186.01Jumlah24,191.853,366,059.68106,386.803,103.00541,816.3918,614.0027,294.853,907,876.07125,000.8027,294.853,907.886,250.04

31,487.804,158,828.45132,615.6231,487.804,158,828.45132,615.62(4,192.95)(250,952.39)(7,614.82)28,358.804,158,828.45132,425.6228,358.804,158,828.45132,425.62

Perh TC (2)Operational TC Dari Pabrikasi ke Lokasi AktifitasBESIBEKESTINGBETONFaktor Lantai

Muat 0.00.01.00Ikat1.502.000.0Angkat & Putar2.001.501.500.50menitAtur Posisi2.000.501.00Turun1.000.501.00Cor0.00.03.00Buka Ikat1.001.000.0Angkat & Putar1.001.001.00Turun0.500.500.500.25menit

Cycle time Lt Bsm 412.0010.0011.00Cycle time Lt Bsm 311.259.2510.25Cycle time Lt Bsm 210.508.509.50Cycle time Lt Bsm 19.757.758.75Cycle time Lt Dasar9.007.008.00Cycle time Lt 29.757.758.75Cycle time Lt 310.508.509.50Cycle time Lt 411.259.2510.25Cycle time Lt 512.0010.0011.00Cycle time Lt 612.7510.7511.75Cycle time Lt 713.5011.5012.50Cycle time Lt 814.2512.2513.25Cycle time Lt 915.0013.0014.00Cycle time Lt 1015.7513.7514.75Cycle time Lt 1116.5014.5015.50Cycle time Lt 1217.2515.2516.25Cycle time Lt 1318.0016.0017.00Cycle time Lt 1418.7516.7517.75Cycle time Lt 1519.5017.5018.50Cycle time Lt 1620.2518.2519.25Cycle time Lt 1721.0019.0020.00Cycle time Lt 1821.7519.7520.75Cycle time Lt 1922.5020.5021.50Cycle time Lt 2023.2521.2522.25Cycle time Lt 2124.0022.0023.00Cycle time Lt 2224.7522.7523.75Cycle time Lt 2325.5023.5024.50Cycle time Lt 2426.2524.2525.25Cycle time Lt 2527.0025.0026.00Cycle time Lt 2627.7525.7526.75

Efisiensi ( E )0.800.800.80Faktor bentuk ( a )0.800.900.90Kap Ujung TC ( K )2.007.500.90Kap Bucket m3

Kapasitas TC (T/Angkat)2.007.500.9060/Ct x K x E x aTon dpt diangkut / Jam)6.4032.403.53Kap/jamKap Bsm 46.4032.403.53Kap Bsm 36.8335.033.79Kap Bsm 27.3138.124.09Kap Bsm 17.8841.814.44Kap Lt Dasar8.5346.294.86Kap Lt 27.8841.814.44Kap Lt 37.3138.124.09Kap Lt 46.8335.033.79Kap Lt 56.4032.403.53Kap Lt 66.0230.143.31Kap Lt 75.6928.173.11Kap Lt 85.3926.452.93Kap Lt 95.1224.922.78Kap Lt 104.8823.562.64Kap Lt 114.6522.342.51Kap Lt 124.4521.252.39Kap Lt 134.2720.252.29Kap Lt 144.1019.342.19Kap Lt 153.9418.512.10Kap Lt 163.7917.752.02Kap Lt 173.6617.051.94Kap Lt 183.5316.411.87Kap Lt 193.4115.801.81Kap Lt 203.3015.251.75Kap Lt 213.2014.731.69Kap Lt 223.1014.241.64Kap Lt 233.0113.791.59Kap Lt 242.9313.361.54Kap Lt 252.8412.961.50

VOLUMETonTonM3Volume Bsm. 465.23738.5910,316.75Volume Bsm. 365.23257.541,137.75Volume Bsm. 265.23268.841,210.75Volume Bsm. 164.69252.291,141.75Volume Lt Dasar144.32353.431,268.00Volume Lt 2112.34273.83773.00Volume Lt 3111.74278.00776.00Volume Lt 4102.55237.05679.00Volume Lt 589.57242.35678.00Volume Lt 665.23151.96434.54Volume Lt 765.23151.96434.54Volume Lt 865.23151.96434.54Volume Lt 965.23151.96434.54Volume Lt 1065.23151.96434.54Volume Lt 1164.69158.28433.39Volume Lt 1264.69158.28433.39Volume Lt 1364.69157.71435.25Volume Lt 1462.23158.31435.14Volume Lt 1561.80158.31435.14Volume Lt 1662.09160.33440.00Volume Lt 1762.09160.33440.00Volume Lt 1862.09160.33440.00Volume Lt 1962.09160.33440.00Volume Lt 2062.09160.33440.00Volume Lt 2160.22161.75444.66Volume Lt 2260.22161.75444.66Volume Lt 2360.22161.64446.80Volume Lt 2460.22161.64446.80Volume Lt 2560.22162.99448.80

TOTAL JAM

Total Jam Bsm 410.1922.802,918.83Total Jam Bsm 39.567.35299.95Total Jam Bsm 28.927.05295.84Total Jam Bsm 18.216.03256.95Total Jam Dasar16.917.64260.91Total Jam 214.266.55173.96Total Jam 315.287.29189.61Total Jam 415.026.77179.01Total Jam 514.007.48191.82Total Jam 610.835.04131.32Total Jam 711.475.39139.71Total Jam 812.105.75148.09Total Jam 912.746.10156.47Total Jam 1013.386.45164.85Total Jam 1113.907.08172.78Total Jam 1214.537.45181.14Total Jam 1315.167.79190.31Total Jam 1415.198.18198.66Total Jam 1515.698.55207.05Total Jam 1616.379.03217.85Total Jam 1716.989.40226.34Total Jam 1817.599.77234.83Total Jam 1918.1910.14243.31Total Jam 2018.8010.52251.80Total Jam 2118.8210.98263.04Total Jam 2219.4111.36271.62Total Jam 2319.9911.72281.55Total Jam 2420.5812.10290.17Total Jam 2521.1712.58300.12

Jumlah Jam435.24254.359,037.88Jumlah Hari39.5723.12821.631 hari = 14 jam31.0918.17645.56 694.82

BILL NO. 2PURI INDAH FINANCIAL TOWERPT. ANTILOPE MADJU PURI INDAH

PEKERJAAN KONTRAK UTAMA STRUKTUR, ARSITEKTUR, PLUMBING & KOORDINASIDAFTAR RINCIAN PEKERJAANNOURAIAN PEKERJAANBOBOTJADWAL PELAKSANAAN PEKERJAAN (465 HARI KALENDER)KETSeptemberOktoberNopemberDesemberJanuariFebruariMaretAprilMeiJuniJuliAgustusSeptemberNopemberDesember

BILL NO. 1 - PEK. PERSIAPAN, PRASARANA DAN PENUNJANG 11.9%0.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0040.0%0.0%BILL NO. 2 - PEK. STRUKTUR 0.0%PEKERJAAN TANAH DAN SALURAN AIR0.0%GALIAN DAN URUGAN TANAH0.9%0.0040.0040.0%PEKERJAAN STRUKTUR BAJA & BETON0.0%SUBSTRUCTURE6.3%0.0160.0160.0160.0160.0%STP0.2%0.0010.0010.0010.0010.0%GWT & RWT0.1%0.0000.0000.0000.0000.0%STRUKTUR BANGUNAN ATAS 0.0%0.0%Basement 41.9%0.0190.0%Basement 31.9%0.0190.0%Basement 22.0%0.0200.0%Basement 11.9%0.0190.0%Lantai Ground2.1%0.0210.0%Lantai 21.6%0.0160.0%Lantai 31.6%0.0160.0%Lantai 41.4%0.0140.0%Lantai 51.3%0.0130.0%Additional L5 (sisi Utara)0.5%0.0050.0%Lantai Tipikal Low Rise L61.0%0.0100.0%Lantai Tipikal Low Rise L71.0%0.0100.0%Lantai Tipikal Low Rise L81.0%0.0100.0%Lantai Tipikal Low Rise L91.0%0.0100.0%Lantai Tipikal Low Rise L101.0%0.0100.0%Lantai Tipikal Low Rise L111.0%0.0100.0%Lantai Tipikal Low Rise L121.0%0.0100.0%Lantai 131.0%0.0100.0%Lantai 141.0%0.0100.0%Lantai 151.0%0.0100.0%Lantai Tipikal High Zone L161.0%0.0100.0%Lantai Tipikal High Zone L171.0%0.0100.0%Lantai Tipikal High Zone L181.0%0.0100.0%Lantai Tipikal High Zone L191.0%0.0100.0%Lantai Tipikal High Zone L201.0%0.0100.0%Lantai Tipikal High Zone L211.0%0.0100.0%Lantai Tipikal High Zone L221.0%0.0100.0%Lantai 231.0%0.0100.0%Lantai 241.0%0.0100.0%Lantai 251.0%0.0100.0%ATAP - PROVISIONAL0.7%0.0030.0030.0%ROOF CROWN0.4%0.0020.0020.0%ATAP R. PERTEMUAN L50.4%0.0010.0010.0010.0%KANOPI LOBI UTAMA0.3%0.0010.0010.0010.0%KANOPI LANTAI 40.2%0.0010.0010.0010.0%RAMP 0.4%0.0010.0010.0010.0010.0%DINDING PARAPET - PROVISIONAL0.2%0.0010.0010.0010.0010.0%PEKERJAAN LAIN-LAIN4.9%0.0050.0050.0050.0050.0050.0050.0050.0050.0050.0%0.0%0.0%BILL NO. 3 - PEK. FINISHING 0.0%0.0%PEKERJAAN DINDING BATA 4.2%0.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0%Pekerjaan plaster aci menggunakan semen instan sesuai gambar dan spesifikasi pada :1.1%0.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0%Pekerjaan skim caoting0.0%0.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0%Soffit Basement0.5%0.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0%Concrete Filling0.0%0.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0%PEKERJAAN PARTISI CORRIDOR3.5%0.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0%PEKERJAAN CT/HT1.0%0.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0%PEKERJAAN PLAFOND1.5%0.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0010.0%CURTAIN BOX2.7%0.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0%PEKERJAAN PEMASANGAN SANITAIR0.1%0.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0%PEKERJAAN LAIN-LAIN0.6%0.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0000.0%0.0%0.0%BILL NO. 4 - PEK. PLUMBING4.1%0.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0030.0%0.0%0.0%BILL NO. 5 - BWIC0.1%0.0000.0000.0000.0000.0000.0000.0000.0000.0%0.0%0.0%BILL NO. 6 - NOMINATED SUBCONTRACTORS, DIRECT CONTRACTORS AND SUPPLIERS 11.7%0.0130.0130.0130.0130.0130.0130.0130.0130.0130.0%0.0%0.0%BILL NO. 7 - PEK. TAMBAH KURANG/ADDENDUM5.9%0.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0020.0%

PROGRESS 0.40%1.07%2.74%2.31%2.31%2.31%2.51%2.51%2.61%2.50%4.39%4.86%3.86%4.13%4.83%5.11%6.12%6.08%5.66%5.66%4.67%4.54%4.54%3.43%2.29%1.76%1.71%1.71%1.71%1.70%PROGRESS KUMULATIF0.40%1.47%4.20%6.52%8.83%11.14%13.64%16.15%18.76%21.26%25.64%30.51%34.36%38.49%43.32%48.43%54.55%60.63%66.29%71.95%76.62%81.16%85.69%89.12%91.41%93.18%94.88%96.59%98.30%100.00%

SCEDULE

BILL NO. 3 - PEK. FINISHING PEKERJAAN DINDING BATA Tangga Kebakaran1,119,644,406.40General3,405,188,358.72Pekerjaan plaster aci menggunakan semen instan sesuai gambar dan spesifikasi pada :Tangga Kebakaran355,895,068.98General - dalam shaft tidak diplaster aci864,892,547.98Pekerjaan skim caotingSoffit Basement19,742m227,068.09534,378,233Concrete Filling1Pekerjaan plaster dengan concrete fill pada permukaan beton expose untuk siap cat1ItemexcludedPEKERJAAN PARTISI CORRIDOR3,711,562,648.36PEKERJAAN CT/HTPemasangan saj keramik HT/CT diatas screed dengan perekat instan ex. Mortar Utama atau setara dan diisi dengan nad grouting ex. Mortar Utama atau setara atau setara sesuai gambar dan spesifikasiBasement 449,881,392.23Basement 356,249,732.76Basement 2191,439,813.20Basement 124,557,267.45Ground Floor48,582,635.34Lantai 225,223,255.55Lantai 325,223,255.55Lantai 425,223,255.55Lantai 528,308,137.57Typical Low Rise (L6-L13)203,831,089.87L1428,308,137.57L1525,223,255.55Typical High Zone (L16-L22)205,516,682.80L2331,692,020.89L2428,607,138.87L2528,607,138.87Mechanical Roof9,597,346.96PEKERJAAN PLAFONDBasement B4-B3601,055,793.58Basement 224,508,623.34Basement 19,822,019.27Ground Floor115,749,579.43L2116,593,772.36L395,189,059.45L451,025,459.55L5-L15260,007,910.79L16-L25238,111,416.88Manhole43,030,267.79CURTAIN BOX2,882,198,067.58PEKERJAAN PEMASANGAN SANITAIRPemasangan saja (Material SBO) sanitary dan fitting termasuk sealant, adukan isian, coring, grouting dan perapihan kembali sesuai gambar dan spesifikasiB04 - B031,628,922.97B022,773,551.70B011,472,726.96Lantai Dasar - L517,982,283.38L6-L1532,246,652.80L16-L2532,246,652.80PEKERJAAN LAIN-LAIN252,547,500.00CORNER GUARD69,518,966.67CAR STOPPER52,872,040.46PENINGGIAN LANTAI & KANSTEEN237,950,870.23SECURITY TOWER - PROVISIONAL49,214,712.00

ALATSCHEDULE ALATPROYEK PURI INDAH FINANCIAL TOWERNo.NamaJumlahSTRUKTURFINISHINGSep-13Oct-13Nov-13Dec-13Jan-14Feb-14Mar-14Apr-14May-14Jun-14Jul-14Aug-14Sep-14Oct-14Nov-141Scaffolding2Tower Crane113Generator Set1114Placing Boom15Air Compressor116Water Pump77Welding Set108Concrete Mixer219Concrete Vibrator1010Bar Cutter311Bar Bender312Dump Truck4213Flat Bed Truck114Pick Up215Theodolith216Waterpass217Gerinda218Hand Bor319Mesin Potong Keramik220Mesin Potong Pipa3SCHEDULE TENAGA KERJANONAMASTRUKTURFINISHINGJUMLAHBULAN KE 1BULAN KE 2BULAN KE 3BULAN KE 4BULAN KE 5BULAN KE 6BULAN KE 7BULAN KE 8BULAN KE 9BULAN KE 10BULAN KE 11BULAN KE 12BULAN KE 13BULAN KE 14BULAN KE 151Manager Proyek11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.002Site manager11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.003Site Engineer11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.004Quality Control11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.005Quality Assurance11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.006Pengadaan Peralatan11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.007Keuangan11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.008Pelaksana K311.001.001.001.001.001.001.001.001.001.001.001.001.001.001.009Surveyor12.002.002.002.002.002.002.002.002.002.002.002.002.002.002.0010BBS12.002.002.002.002.002.002.002.002.002.0011PELAKSANA STRUKTUR32.002.002.002.002.002.002.002.002.002.0012PELAKSANA ARSITEK34.004.004.004.004.004.004.004.004.004.004.004.0013Drafter33.003.003.003.003.003.003.003.003.003.002.002.002.002.002.0014Koordinator Work pek. Finishing44.004.004.004.004.004.004.004.004.0015Keamanan44.004.004.004.004.004.004.004.004.004.004.004.004.004.004.00SCHEDULE SHOP DRAWINGNONAMASTRUKTURFINISHINGJUMLAHBULAN KE 1BULAN KE 2BULAN KE 3BULAN KE 4BULAN KE 5BULAN KE 6BULAN KE 7BULAN KE 8BULAN KE 9BULAN KE 10BULAN KE 11BULAN KE 12BULAN KE 13BULAN KE 14BULAN KE 151PENGAJUAN SHOP DRWSTRUKTURFINISHINGPLUMBINGSCHEDULE MATERIALPROYEK PURI INDAH FINANCIAL TOWERNo.NamaSTRUKTURFINISHINGBULAN KE 1BULAN KE 2BULAN KE 3BULAN KE 4BULAN KE 5BULAN KE 6BULAN KE 7BULAN KE 8BULAN KE 9BULAN KE 10BULAN KE 11BULAN KE 12BULAN KE 13BULAN KE 14BULAN KE 151BESI TULANGAN2BEKISTING3BETON4MATERIAL WATER PROOFING5BAJA6RAILING7BATA RINGAN8BATA MERAH9KERAMIK TILE10PLAFON11SANITAIR12MATERIAL PLUMBING

PERSONELDATA PERSONILNo.NamaTgl/Bln/Thn Lahir1231Ir Shafril Yinurullah7-Apr-702Ir Heri Triwinarto25-Jan-693Ir Endang Budiman6-Aug-694Jose Ricardo, ST5-Sep-695Sri Hidayat, ST6-Feb-786Ary Widodo S, ST22-Jul-817Budi Triatmoko, A.Md19-Sep-65

ALATSCHEDULE ALATPROYEK PURI INDAH FINANCIAL TOWERNo.NamaJumlahSTRUKTURFINISHINGSep-13Oct-13Nov-13Dec-13Jan-14Feb-14Mar-14Apr-14May-14Jun-14Jul-14Aug-14Sep-14Oct-14Nov-141Scaffolding2Tower Crane113Generator Set1114Placing Boom15Air Compressor116Water Pump77Welding Set108Concrete Mixer219Concrete Vibrator1010Bar Cutter311Bar Bender312Dump Truck4213Flat Bed Truck114Pick Up215Theodolith216Waterpass217Gerinda218Hand Bor319Mesin Potong Keramik220Mesin Potong Pipa3SCHEDULE TENAGA KERJANONAMASTRUKTURFINISHINGJUMLAHSep-13Oct-13Nov-13Dec-13Jan-14Feb-14Mar-14Apr-14May-14Jun-14Jul-14Aug-14Sep-14Oct-14Nov-141Manager Proyek11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.002Site manager11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.003Site Engineer11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.004Quality Control11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.005Quality Assurance11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.006Pengadaan Peralatan11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.007Keuangan11.001.001.001.001.001.001.001.001.001.001.001.001.001.001.008Pelaksana K311.001.001.001.001.001.001.001.001.001.001.001.001.001.001.009Surveyor12.002.002.002.002.002.002.002.002.002.002.002.002.002.002.0010BBS12.002.002.002.002.002.002.002.002.002.0011PELAKSANA STRUKTUR32.002.002.002.002.002.002.002.002.002.0012PELAKSANA ARSITEK34.004.004.004.004.004.004.004.004.004.004.004.0013Drafter33.003.003.003.003.003.003.003.003.003.002.002.002.002.002.0014Koordinator Work pek. Finishing44.004.004.004.004.004.004.004.004.0015Keamanan44.004.004.004.004.004.004.004.004.004.004.004.004.004.004.00SCHEDULE SHOP DRAWINGNONAMASTRUKTURFINISHINGJUMLAHBULAN KE 1BULAN KE 2BULAN KE 3BULAN KE 4BULAN KE 5BULAN KE 6BULAN KE 7BULAN KE 8BULAN KE 9BULAN KE 10BULAN KE 11BULAN KE 12BULAN KE 13BULAN KE 14BULAN KE 151PENGAJUAN SHOP DRWSTRUKTURFINISHINGPLUMBINGSCHEDULE MATERIALPROYEK PURI INDAH FINANCIAL TOWERNo.NamaSTRUKTURFINISHINGBULAN KE 1BULAN KE 2BULAN KE 3BULAN KE 4BULAN KE 5BULAN KE 6BULAN KE 7BULAN KE 8BULAN KE 9BULAN KE 10BULAN KE 11BULAN KE 12BULAN KE 13BULAN KE 14BULAN KE 151BESI TULANGAN2BEKISTING3BETON4MATERIAL WATER PROOFING5BAJA6RAILING7BATA RINGAN8BATA MERAH9KERAMIK TILE10PLAFON11SANITAIR12MATERIAL PLUMBING

PERSONELDATA PERSONILNo.NamaTgl/Bln/Thn Lahir1231Ir Shafril Yinurullah7-Apr-702Ir Heri Triwinarto25-Jan-693Ir Endang Budiman6-Aug-694Jose Ricardo, ST5-Sep-695Sri Hidayat, ST6-Feb-786Ary Widodo S, ST22-Jul-817Budi Triatmoko, A.Md19-Sep-65

Rekap SubkonSCHEDULE SUBKONTRAKTORPROYEK: PURI INDAH FINANCIAL TOWERPKP: 1053LOKASI: PURI KEMBANGAN, JAKARTA BARATKONTRAKTARGETAPPROVESTARTFINISHSCHEDULE PELAKSANAAN 2013SCHEDULE PELAKSANAAN 2014NOURAIAN PEKERJAANSatVolumeHarsatTotalKPTSANMATERIAL/MOB/PELAKSDURJULIAGUSTSEPTOKTNOVDESJANPEBMARAPRMEIJUNIJULIAGUSTSEPTUPPMTD/ GBRPELAKS(HARI)ABCDEF = D x ESUBKON PEK. PERSIAPAN1Pembersihan area site officels1.0017-Jul-1319-Jul-1321-Jul-1324-Jul-1332Pagar sementara area site officels1.0017-Jul-1319-Jul-1321-Jul-1328-Jul-1373Pembuatan direksi keetls1.0017-Jul-1322-Jul-1331-Jul-1330-Aug-13304Papan nama proyekls1.003-Sep-138-Sep-1317-Sep-1319-Sep-132SUBKON STRUKTUR & ARSITEKTURStruktur1Pek. Galian & urugan tanahls1.0018-Aug-1325-Aug-1317-Sep-131-Oct-13142Pek. Anti Rayapls1.0018-Aug-1325-Aug-1317-Sep-138-Oct-13213Pek. Pembesian ( upah )ls1.0019-Jul-1326-Jul-1317-Sep-1314-Jul-143004Pek. Bekestingls1.0019-Jul-1326-Jul-1317-Sep-1314-Jul-143005Pek. Betonls1.0019-Jul-1326-Jul-1317-Sep-1314-Jul-143006Pek. Atap & Kanopi rangka baja profills1.001-Apr-148-Apr-141-May-1429-Aug-141207Pek. Water proofing Integralls1.0018-Sep-1325-Sep-1318-Oct-1317-Dec-13608Pek. Water proofing membran & coatingls1.0018-Sep-1325-Sep-1318-Oct-1324-Aug-143109Pek. Floor Hardener & trowel finishls1.0018-Sep-1325-Sep-1318-Oct-1324-Aug-1431010Pek. Keramik & screels1.003-Nov-1310-Nov-133-Dec-139-Sep-1428011Pek. Grill Gutter, Grill Trap, Cat ladder, corner guardls1.0012-Nov-1319-Nov-1312-Dec-1312-Mar-149012Pek. Railling & Hand raillingls1.0027-Oct-133-Nov-1326-Nov-1323-Aug-1427013Pek. Separator beamls1.0029-May-145-Jun-1428-Jun-1427-Aug-146014Pek. Pas. Dinding dan plester aci + concrete fillls1.0022-Oct-1329-Oct-1321-Nov-1317-Sep-1430015Pek. Skim coatls1.0021-Nov-1328-Nov-1321-Dec-1321-Mar-149016Pek. Partisi & Plafond Gyps & WRls1.0029-Oct-135-Nov-1328-Nov-1324-Sep-1430017Pek. Pasang sanitair ( upah )ls1.0029-Mar-135-Apr-1328-Apr-1325-Sep-13150SUBKON MEKANIKAL & ELEKTRIKAL1PEKERJAAN PLAMBINGls1.0025-Aug-131-Sep-1324-Sep-1320-Aug-14330SUB TOTAL PEKERJAAN SUBKON PEK. M/E0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0TOTAL SUBKON0.00.00.00.00.00.00.00.00.00.00.00.00.00.00.0

Jakarta, 11 Juli 2013Dibuat oleh

( Budi Setiadi )Ka. Teknik

00000

Sheet1Q S H E P L A NNo PKP: 1053PURI INDAH TOWERHalaman: 1/1Revisi: 0Tanggal: 10 Juni 2013Dibuat: Budi SetiadiHOLD POINT & WITNESS POINTDisetujui: Sugeng SubagyoNO.URAIANTAHUN 2012TAHUN 2010SeptemberOktoberNovemberDesemberJanuariFebruariMaretAprilMeiJuniJuli-Joint SurveyRC =ORL =Site PlanRC =RL =Master ScheduleRC =RL =Mix Desain BetonRC =RL =Trial MixRC =RL =Besi BetonRC =RL =BekistingRC =RL =PengecoranRC =RL =CelconRC =RL =RaillingRC =RL =PlafondRC =RL =HomogenousRC =RL =KeramikRC =RL =PlumbingRC =RL =SanitaryRC =RL =Keterangan := Pengetesan= Persetujuan

STRUKTUR ORGQ U A L I T Y P L A NNo. PKP: 1053Halaman: 1/1Revisi: 0STRUKTUR ORGANISASITanggal: 10 Juni 2013Dibuat oleh: Budi SetiadiSTRUKTUR ORGANISASI PROYEKDisetujui Oleh: Sugeng SubagyoKEPALA DIVISI VPusatTri WibowoLapanganKEPALA PROYEKSugeng SubagyoKOORINATOR MUTUSAFETY OFFICERSugeng SubagyoSugeng SubagyoKEPALA TEKNIKKEPALA OPERASIGENERAL AFFAIRBudi SetiadiIwan CandraAgus PriyantoPlaning and MonitoringPELAKSANA 1ADM. KEUANGANSyamsuddinDESAIN DRAWINGPELAKSANA 2LOGISTIKQUANTITY SURVEYORPELAKSANA 3GUDANGQUALITY CONTROLSURVEYORKOORDINATORKEAMANANAgus MuhtaromHadiCOST CONTROLPELAKSANA ME TEMP DAN A2BPartono

PURI INDAH TOWER

STRUKTUR ORG (2)Q U A L I T Y P L A NNo. PKP: 1053Halaman: 1/1Revisi: 0STRUKTUR ORGANISASITanggal: 10 Juni 2013Dibuat oleh: Budi SetiadiDisetujui Oleh: Sugeng SubagyoKEPALA DIVISI VPusatTri WibowoLapanganKEPALA PROYEKSugeng SubagyoKOORINATOR MUTUSAFETY OFFICERSugeng SubagyoSugeng SubagyoKEPALA TEKNIKKEPALA OPERASIGENERAL AFFAIRBudi SetiadiIwan CandraAgus PriyantoPlaning & MonitoringPLKS. STRUKTURME PermanenKOORD. NSC, DC, DSADM. KEUANGANDisnaBudiyono (Koord.)Irwan (Koord.)SyamsudinHendroNur CahyoCost ControlAriesME TemporaryA2BLOGISTIKRudi WidiatmokoBakrieTriyono (Koord.)HendrySutisnaQuality ControlPLKS. FINISHINGSURVEYGUDANGLuthfiCahyadi (Koord.)NitaAgus MuhtaromQuantity SurveyorKEAMANANRini Tri PartiwiHadiTitoDRAFTER

PURI INDAH FINANCIAL TOWER