PMP ® Sample Questions PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.
12
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: PMP Exam Sample Questions

PMP® Sample Questions

PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the

development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every

attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam.

However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially

published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or

expressed by OSP International LLC.

Page 2: PMP Exam Sample Questions

This presentation will showcase free sample

PMP® questions that will help and guide

you in studying for your PMP® exam

Find more free sample questions when you visit

www.free-pm-exam-questions.com and

free.pm-exam-simulator.com

Page 3: PMP Exam Sample Questions

1. Your pharmaceutical drug manufacturing project is running late and you

have deadlines to meet on your project. You want to replace some of the

inefficient human resources with more talented human resources to finish

the project on time. What risk response strategy is being followed in this

context?

A. Share

B. Accept

C. Transfer

D. Mitigate

Hint: You are trying to reduce the likelihood of the risk occurrence.

Sample PMP® Exam Question

Page 4: PMP Exam Sample Questions

The correct answer is D

Explanation: This is an example of risk mitigation. By replacing

the human resources you are reducing the probability of the

risk.

Answer and Explanation

Page 5: PMP Exam Sample Questions

2. You are performing the Plan Risk Responses process for your manufacturing project

and encounter a critical risk that may have a high impact on the project completion. All

of the following are valid responses to this new risk except?

A. Allocating Contingency Reserves

B. Developing Fallback Options

C. Conducting Bidder Conferences

D. Reviewing Risks Driven by Strategies

Hint: A fallback plan is used when a primary response plan proves to be inadequate.

Sample PMP® Exam Question

Page 6: PMP Exam Sample Questions

The correct answer is C

Explanation: Conducting bidder conferences is not a

strategy used in Risk Management. All other answer

choices are valid risk responses.

Answer and Explanation

Page 7: PMP Exam Sample Questions

3. Which of the following Enterprise Environmental Factors does not influence the

Estimate Activity Durations process?

A. Duration Estimating Databases

B. Project Management Information Systems

C. Productivity Metrics

D. Published Commercial Information

Hint: All of the given choices are valid Enterprise Environmental Factors but which one of them

is not relevant to the Estimate Activity Durations process?

Sample PMP® Exam Question

Page 8: PMP Exam Sample Questions

The correct answer is B

Explanation: All of the given choices are valid Enterprise

Environmental Factors. However, the Project

Management Information System will not influence the

Estimate Activity Durations process. We do use project

management software for scheduling (Scheduling Tools)

during the Estimate Activity Durations process but we

do not use the Project Management Information System.

Conceptually, these two software applications are

different and perform different functions. However, you

can find a software application that performs both of

these functions, e.g. Microsoft Project. For the actual

PMP Exam you must remember that these two software

applications are different and perform different

functions, i.e. one is for reporting and one is for

scheduling.

Answer and Explanation

Page 9: PMP Exam Sample Questions

4. You are managing a hardware design project in India with locally trained engineers

but your client is based in the U.S. You are unable to meet your client face-to-face

and you cannot talk to your client on the phone because of the different time zones.

Instructions are sent via email but there is a communications breakdown and your

team fails to understand the messages. What is causing this issue?

A. Poor message encoding

B. Poor message decoding

C. Noise

D. Medium

Hint: You are faced with a language problem between native and non-native English speakers.

Sample PMP® Exam Question

Page 10: PMP Exam Sample Questions

The correct answer is C

Explanation: This is an example of noise. The PMBOK Guide

defines noise as "Anything that interferes with the

transmission and understanding of the message (e.g. distance,

unfamiliar technology, or lack of background information)".

In this case the "noise" is the fact that your team members

who are local to India do not speak English as well as your

customer. This interferes with the understanding of the

message.

Answer and Explanation

Page 11: PMP Exam Sample Questions

5. You are working at a steel manufacturing company as a project manager. There is a

department called Welding and Fabrication in your company. You are getting ready to

put together your project team and you want to see a hierarchical representation of

how many welders are working for your company in the Welding and Fabrication

Department. Which of the following illustrates this information?

A. Work Breakdown Structure

B. Organizational Breakdown Structure

C. RACI Chart

D. Resource Breakdown Structure

Hint: A welder is a resource. The project manager wants to see all welding resources in a

hierarchical format.

Sample PMP® Exam Question

Page 12: PMP Exam Sample Questions

The correct answer is D

Explanation: A Resource Breakdown Structure is a hierarchical

structure of resources broken down by resource category and

resource type.

Answer and Explanation