WW All S 04 010 Rev. 1, Dec 2010 PETRONAS CARIGALI PRE-ACTIVITY SAFETY REVIEW (PASR) GUIDELINE PETRONAS CARIGALI SDN BHD
WW All S 04 010 Rev. 1, Dec 2010
Philosophy of Lifesaving Appliances for Offshore Installations
PETRONAS CARIGALI
PRE-ACTIVITY SAFETY REVIEW
(PASR) GUIDELINE
PETRONAS CARIGALI SDN BHD
Pre-Activity Safety Review WW ALL S 04 010 Main Table of Contents Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD Main Table of Contents
Page i
PRE-ACTIVITY SAFETY REVIEW
Main Table of Contents
Preliminary
Foreword
Distribution List
Amendment Summary
Preface
Glossary of Abbreviations and Acronyms
Reference Documents
Section 1 Introduction
Section 2 PASR Process
Section 3 Process-Related Activities
Appendices Appendix 1 Sample of Samarang Process-Related Activity Procedures
Appendix 2 Sample Checklist of Tembungo Integrated Shutdown Sequence
Appendix 3 Sample of Checklist of Tembungo Integrated Startup Sequence
Appendix 4 Sample of SMG-A Cooler Spading & Isolation List
Appendix 5 Sample of TBG Integrated Plan on Paper (iPOP)
Appendix 6 Sample of Pre-Shutdown Safety Review Checklist
Appendix 7 Sample of Pre-Startup Safety Review Checklist
Appendix 8 Full Pre-Startup Safety Review Checklist
Appendix 9 Sample of Appointment Letter for PASR Team Leader
Appendix 10 PASR Log
Appendix 11 PASR Phase 2 Form
Pre-Activity Safety Review WW ALL S 04 010 Preliminary Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD Preliminary
Page iii
DISTRIBUTION LIST
Copy No. Title Location
01 CEO DPS MD-KL
02
02
02
CEO XS MD-KL
03 XMAS XD - KL
04 XSK XD - KL
05 XSB XD - KL
06 XPM XD - KL
07 XINT XD - KL
08 XAFR XD - KL
09 XATL XD - KL
10 XSEAN XD - KL
11 XSEAS XD - KL
12 XMEA XD - KL
13 XTS XD - KL
14 XGO XD - KL
15 XBD XD - KL
16 XPL XD - KL
17 XHSE XD-KL
18 DGM DD - KL
19 DDR DD - KL
20 DFE DD - KL
21 DDW DD - KL
22 DPP DD - KL
23 DRMB DD - KL
24 DDP DD - KL
25 DHSE DD - KL
26 FIN MD - KL
27 CHSE MD - KL
28 HRM MD - KL
29 PED MD - KL
30 RM MD- KL
Pre-Activity Safety Review WW ALL S 04 010 Preliminary Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD Preliminary
Page iv
31 SCM-CAA MD – KL
32 SP MD – KL
33 TIM MD – KL
34 PI (CHO) MD – KL
35 MO MO
36 MO (HSE) MO
37 VO VO
38 VO (HSE) VO
39 INO INO
40 INO (HSE) INO
41 MAU MAU
42 MAU (HSE) MAU
43 UO UO
44 UO (HSE) UO
45 PAK PAK
46 PAK (HSE) PAK
47 TO TO
48 TO (HSE) TO
49 IRQ IRQ
50 IRQ (HSE) IRQ
51 PM (CHO) MD-KL
52 PMO PMO
53 PMO (HSE) PMO
54 SBO SBO
55 SBO (HSE) SBO
56 SKO SKO
57 SKO (HSE) SKO
Pre-Activity Safety Review WW ALL S 04 010 Preliminary Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD Preliminary
Page v
AMENDMENT SUMMARY
This sheet must be completed in detail at each revision once this document has been
approved.
Details must include revision number, description and indication of which pages and
paragraphs have been revised, date of revision approval, approvers title and signature.
Rev Description Date Approver Title Signature
1 Inclusion of PASR Phase 2 in Section 2 Dec 2010
Notes:
(1) Document Holders to update Amendment record as and when amendments/ new
revision are received.
(2) For description of amendment the Document Holder should indicate correction,
modification, updates or deletion issue.
(3) Document Holder to enter their company reference number, sign and date the
record entry.
(4) Where part amendments are issued, the relevant page(s) will be identified with a
lower case letter in the revision line in the header.
Pre-Activity Safety Review WW ALL S 04 010 Preliminary Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD Preliminary
Page vi
PREFACE
This Pre-Activity Safety Review (PASR) Guideline has been developed to ensure that all planned activities associated with process safety during drilling, facilities commissioning, production operations and maintenance, and facilities decommissioning are thoroughly reviewed prior to commencement to prevent adverse HSE consequences. The guideline is based on, or reference is made to relevant PETRONAS Technical Standards, and in line with PETRONAS Carigali’s HSEMS requirement. This document outlines the preparation requirement for process safety management to ensure the risks associated with the process have been reduced to ALARP level. This document only addresses process-related activities. It does not address the review requirement for non-process related activities. For non-process HSE critical activities, similar review/ risk assessment is required to ensure safe execution of activities. This manual shall be revised from time to time as required to ensure that any changes are documented and that any process safety related issues are correctly addressed. Any proposed amendment for continuous improvement from the users should be brought to the attention of Custodian by completing the standard revision request form. A copy of the standard revision request form is contained in PETRONAS Carigali Document Management Procedures (Document no. MY ALL A 05 002).
Pre-Activity Safety Review WW ALL S 04 010 Preliminary Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD Preliminary
Page vii
ABBREVIATIONS AND ACRONYMS
The abbreviations and acronyms used in this document shall have the following meaning:
ABV Actuated Ball Valve
AGV Actuated Gate Valve
ALARP As Low As Reasonably Practicable
ASD Assembly Shutdown
BC Battery Charger
BDV Blowdown Valve
CCR Central Control Room
COTP Crude Oil Transfer Pump
ESD Emergency Shutdown
FTHP Flow Tubing Head Pressure
GPA General Public Alarm
HAZOP Hazards Operability
HEMP Hazards and Effects Management Process
HHP High High Pressure
HP High Pressure
HSE Health, Safety and Environment
HSEMS Health, Safety and Environmental Management System
ICR Instrument Control Room
iPOCS Integrated Plant Operations Capabilities System
JHA Job Hazard Assessment
LCV Level Control Valve
LIC Level Indicating Controller
LOTO Lock-Out-Tag-Out
LP Low Pressure
LPS Low Pressure Switch
LSL Level Switch Low
Pre-Activity Safety Review WW ALL S 04 010 Preliminary Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD Preliminary
Page viii
MCB Motor Circuit Breaker
MOC Management of Change
MOD Module
MOL Main Oil Line
NSD Non-Shutdown
NTD Next Test Date
OIM Offshore Installation Manager
OPM Operations Procedure Manual
OS Operation Supervisor
PASR Pre-Activity Safety Review
PCSB PETRONAS Carigali Sdn Bhd
PCV Pressure Control Valve
PETRONAS Petroleum Nasional
PHA Process Hazard Assessment
PL Pipeline
PLC Programmable Logic Controller
PM Preventive Maintenance
PMCS Plant Monitoring Control System
PPP Pipeline Protection Panel
PRAP Process-Related Activity Procedures
PSD Process Shutdown
PSHL Pressure Switch High Low
PSL Pressure Switch Low
ROV Remote Operating Valve
RV Relief Valve
SCSSV Sub-Surface Safety Valve
SD Shutdown
SDS Shutdown Switch
SITHP Shut In Tubing Head Pressure
Pre-Activity Safety Review WW ALL S 04 010 Preliminary Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD Preliminary
Page ix
SOS Senior Operation Supervisor
SSV Surface Safety Valve
TMM Topside Maintenance Management
UPS Uninterrupted Power Supply
Pre-Activity Safety Review WW ALL S 04 010 Preliminary Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD Preliminary
Page x
REFERENCE DOCUMENTS
Doc. No. Title
PTS 60.0101 Health, Safety & Environment Management System Manual
PTS 60.0109 Production and Maintenance Guideline
PTS 60.0401 Hazards and Effects Management Process (HEMP)
PTS 60.2001 PETRONAS Group Guidelines for Permit to Work System
PTS 60.2201 Management of Change (MOC)
PTS 60.2203 Process Safety Information (PSI)
PTS 60.2204 Process Hazard Analysis (PHA)
PTS 60.2205 Operating Procedure (OP) Guideline
PTS 60.2208 Pre-Activity Safety Review (PASR) Guideline
WW ALL S 07 001 PCSB Health, Safety & Environment Management System Manual
Pre-Activity Safety Review WW ALL S 04 010 Introduction Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 1
Page 1
SECTION 1
INTRODUCTION
Contents Paragraph Page No.
1 INTRODUCTION 2
2 PURPOSE 2
3 SCOPE 3
Pre-Activity Safety Review WW ALL S 04 010 Introduction Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 1
Page 2
1 INTRODUCTION
This pre-activity safety review (PASR) guideline has been developed to provide guidelines to the PASR team, who are assigned by the facility owner to carry out safety review on the processes at the work site before commencement of planned process-related activities.
All personnel who are involved in PASR must ensure that they are familiar with the requirements and procedures contained in this guideline.
2 PURPOSE
This guideline establishes requirements to conduct a safety review of processes to ensure safe implementation of planned activities. The risks associated with the planned activities shall be thoroughly assessed and the readiness shall be properly reviewed before the commencement of the activities, so as to produce its intended benefits without adverse side effects. The objectives of this guideline are:
(1) Outline the requirements to carry out PASR.
(2) Define selection criteria, roles and responsibilities of PASR team members, to ensure the effectiveness of safety review through proper assessment of process-related risks associated of planned activities.
(3) Provide a coherent, systematic and as simple strategy as possible for all end users to ensure that all prior identified hazards and loss exposures associated with a planned activity’s implementation have been addressed to close-out before commencement of the planned activity.
(4) Ensure the development of detailed activity procedure/ checklists for the process-related activities.
Pre-Activity Safety Review WW ALL S 04 010 Introduction Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 1
Page 3
3 SCOPE
PASR is required for the following process safety related activities. It includes, but not limited to:
(1) All process-related changes i.e. equipment change,
operating parameter change, etc.
(2) Pre-commissioning and commissioning of production facilities and equipment;
(3) Planned shutdown of production facilities and equipment;
(4) Start-up of production facilities;
(5) Maintenance of equipment requiring process isolation;
(6) Simultaneous production and drilling operations;
(7) Simultaneous production and construction;
(8) Simultaneous production and major maintenance; and
(9) Decommissioning of production facilities and equipment.
Details criteria for each of the process-related activities that require PASR is further elaborated in Section 3 of this document. This guideline will be reviewed when any of the following occurs, but not limited to:
(1) Applicable regulations are introduced or revised.
(2) Further improvement required.
(3) Introduce new technology.
All changes made in the PASR guideline shall be approved by the approving authority. The complete guideline shall be distributed to all relevant parties.
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 1
SECTION 2
PASR PROCESS
Contents
Paragraph Page No.
1 PASR PROCESS FLOW 2
1.1 PASR Process Overview 2
1.2 Acceptance Criteria 7
1.3 Roles and Responsibilities 8
1.4 PASR Activities 9
1.5 PASR Reporting and Documentation 10
1.6 Outline of Process-Related Activities Procedure (PRAP) 11
1.7 PASR Log 12
1.8 Status Monitoring and Assurance 13
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 2
1 PASR PROCESS FLOW
1.1 PASR Process Overview
To ensure safe execution of the planned activities, PASR
shall be conducted prior to the implementation of the
activities. PASR is divided in two phases, i.e.
(1) Phase 1: Risk assessment on the planned activities using the most appropriate tools e.g. HAZID, HAZOP, SWIFT, etc.
(2) Phase 2: Review / verification exercise using appropriate checklist and / or procedures.
Phase 1
The hazards associated with the planned activities shall be
assessed in accordance to the following guidelines:
(1) Line manager (project manager, field manager, drilling manager) is responsible to identify the need for the conduct of PASR.
(2) Line manager to appoint a competent team leader and team members.
(3) Carry out PASR Phase 1 in accordance to this guideline. The review shall identify the required steps/ tasks in executing the process-related activity e.g. shutdown and/or start-up, as well as the required HSE controls to ensure risks associated with the process-related activities are ALARP.
(4) Depending on the nature and complexity of the process-related activity, the appropriate type of tool must be chosen. Example of tools to be used for PASR Phase 1 may include: (a) HAZOP / Mini HAZOP
(b) HAZID
(c) Bowtie
(d) Structured What-if Technique (SWIFT)
(e) Customizes Checklist
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 3
(5) In addition, where process-related activities requiring
the conduct of PASR Phase 1 is intended to be carried out simultaneously with another concurrent activities (e.g. concurrently with construction, maintenance, drilling, etc), the PASR Phase 1 assessment shall be extended to incorporate the risks attributed to the simultaneous activities. The sample assessment of concurrent maintenance activities for a planned shutdown is as illustrated in Appendix 5.
(6) Recommendations resulted from PASR Phase 1 to strengthen the control and recovery barriers shall be incorporated in the relevant documents i.e. the associated procedures.
(7) The deliverable of the PASR Phase 1 is a Process-Related Activity Procedures including checklists to ensure safe execution of the planned activity; for example Samarang-A Shutdown Procedures, Baronia-B Startup Procedures, Dulang-C Commissioning Procedures.
(8) This Process-Related Activity Procedures shall become part of the documentation as required per PETRONAS Integrated Plant Operations Capabilities System’s (iPOCS) Turn Around Management Guideline.
(9) Line manager to approve and implement the Process-Related Activity Procedure including relevant checklists, if any.
(10) All related documents must be kept for 7 years as per HSEMS requirement by the line department.
Phase 2 For ensuring all the identified control and recovery barriers are being implemented as well to confirm operational readiness to commence the planned activities, a review or verification exercise shall be conducted in accordance to the following guidelines: (1) Line manager to appoint a competent team leader
and team members for the verification exercise.
(2) Initiate PASR Phase 2 using PASR Form as shown in Appendix 11.
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 4
(3) In ensuring most of the relevant information has been
deliberated and assessed, a checklist can be used to guide the team as well to record the findings. Sample checklist for shutdown and start-up are as illustrated in Appendix 6 and Appendix 7 respectively.
(4) In addition, for new or modified facility-type review, the use of a standard commissioning checklist may usually suffice. The sample is as given in Appendix 8.
(5) The planned process-related activity shall not proceed if the results from the verification exercise are not acceptable by the Management and/or the project team. Alternative or corrective actions shall be identified and the subject shall be reviewed again until satisfactory. However, some portions of the planned activities could probably commence upon Management’s endorsement.
(6) Recommendations from the verification exercise shall be recorded and shall be closed prior commencement of the planned activities (subject to priority).
(7) All related documents must be kept for 7 years as per HSEMS requirement by the line department.
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 5
Figure 2.1: PASR Phase 1 Process Flowchart
No
Yes
Is the activity
Process-related?
Appoint PASR Team Leader and Members by
line manager.
Conduct PASR Phase 1 i.e. risk assessment
for the planned activity
Develop Process-Related Activity Procedures
including checklists
START
Is it a HSE critical
activity?
No Proceed with the
planned activity
Conduct risk assessment
review on the activity. *
Is the Process-Related
Activity Procedures
approved by
management?
Yes
No
Proceed with the planned
activity.
Yes
Implement all the required control and
recovery measures to ensure safe
execution of the planned activity
* In line with the respective governing guideline.
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 6
Figure 2.2: PASR Phase 2 Process Flowchart
START
Proceed with the planned activity.
Conduct PASR Phase 2 i.e. verification
exercise using appropriate checklist
Record PASR findings and follow up on
results
Are results from
PASR Phase 2
acceptable?
* Conditions to close the findings/ commencing the activity shall be in line with item 1.2
Appoint PASR Team Leader and Members
by line manager.
Do not proceed with the planned activity, identify
alternative/ corrective actions and review again
until satisfactory.
Note: Some portions of the planned activities
could probably commence upon Management’s
endorsement.
Yes
No
Close-out all findings from PASR
Phase 2 exercise*
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 7
1.2 Acceptance Criteria
Findings from PASR Phase 2 need to be prioritised based on the risk and practicality e.g. cost impact, prior execution of the planned process-related activities. For guidance in prioritising, PETRONAS Carigali Risk Assessment Matrix shall be used. The prioritisation of findings is essential in order to formally approve commencement of the process-related activity(ies), particularly in situations where PASR findings and action items are still outstanding. For situations where the planned process-related activity needs to commence prior closure of all the findings and action items, the execution shall be formally approved by appropriate level of authority based on the level of priority as outlined in the table below:
Level of Priority
Conditions to be met Approving Authority
High Activity shall not be allowed to proceed until they are rectified
-
Medium
Activity may proceed, subject to closure of findings/ action items within 2 weeks after commencement
Field Manager
Low
Activity may proceed, subject to closure of findings/ action items within 1 month after commencement
OIM
1.3 Roles and Responsibilities
Line Manager Line manager is the overall responsible person to organize, coordinate and execute the implementation of PASR in a safe and cost effective manner. The Line Manager shall also be responsible and accountable for the management and closure of all findings and actions items arising from PASR activities. PASR Team Leader PASR team leader is a competent operation personnel, who is appointed by Line Manager (e.g. Offshore Installation Manager). His duty is to carry out PASR
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 8
together with his team members prior to the execution of process-related activities. PASR members PASR team member is appointed by PASR team leader from among suitably competent personnel from various technical disciplines (e.g. operations, maintenance, reliability engineering, HSE, etc.) PASR Coordinator Each operating Region/ Division shall appoint PASR Coordinators to be responsible to administering PASR process. PASR Coordinator is a critical resource to ensure proper documentation of PASR activity, monitoring, adequacy of risk assessment and close-out documentation. These responsibilities are assigned to an individual within the functional group such as Field Engineer, and it is an addition to his/her normal duties. It is not separate position in the organization. The typical roles and responsibilities for PASR Coordinator as per followings: (1) Identify the process-related activities that require
PASR.
(2) Register the conduct of PASR in PASR Log.
(3) Coordinate PASR sessions both Phase 1 and Phase 2
(4) Maintain necessary information in PASR log, including tracking of action items and PASR closure.
All PASR reports, for both Open and Closed PASR, shall be kept for a period of seven (7) years.
1.4 PASR activities
Process-related activities that are stated in item 1.2 (e.g. major start-up, shutdown, simultaneous operations, commissioning, decommissioning, etc), shall be subject to a Pre-Activity Safety Review (PASR), both Phase 1 and Phase 2. PASR team will conduct the safety review as per following activities:
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 9
Phase 1 (1) Identify the sequence of tasks required to execute the
process-related activities (e.g. sequence of tasks to execute the plant shutdown/ startup).
(2) Identify hazards associated with these tasks and identify the required HSE controls to ensure risks associated with the process-related activities are ALARP; and incorporate the identified controls in the sequence of task execution.
(3) Document the sequence of tasks as well as the required HSE controls in Process-Related Activity Procedures including all relevant supporting documentation (e.g. risks assessment as carried out in item 2 above).
(4) Where required, all relevant documentation shall be developed e.g. spading list, drawing, etc.
(5) For guidance in developing the Process-Related Activity Procedures sample is attached.
Phase 2 (1) Using an appropriate checklist suitable for the
planned activity, a review or verification exercise shall be conducted in a team (note: the team could either be the same team of PASR Phase 1, or could be a different team).
(2) The checklist shall be developed mainly to verify the implementation of the control and recovery barriers as well as the operational readiness prior commencing the planned activity.
(3) The checklist shall be covering on below categories, but not limited to:
(a) Work planning.
(b) Isolations / normalisation of process lines.
(c) Fire and gas detection and protection systems.
(d) Utilities.
(e) Logistics.
(f) Equipment inspections and testing.
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 10
(g) Emergency response.
(h) etc.
The samples of checklist, depending on the type of planned activity, are as illustrated in Appendix 6, 7 and 8.
(4) The checklists shall serve as a basis for the PASR Phase 2 team to customise their own checklist, taking categories as applicable to the needs of the planned activities, as well as to cover other activities which may not be directly related to the planned activities, but may still deserve to be part of the review scope as they may have the potential to cause adverse HSE effects to the facility.
(5) As part of effective verification process, relevant documentations shall be referred to i.e. P&IDs, procedures, equipment inspection records, etc.
(6) Interview with affected personnel and site check shall also be conducted to confirm the findings.
1.5 PASR Reporting and Documentation
The PASR and Process-Related Activity Procedures shall be reviewed by relevant technical authority and approved by line manager. All HSE controls identified in the Process-Related Activity Procedures shall be implemented prior to the commencement of the activity. The execution of the process-related activities is to be carried out in accordance to the approved Process-Related Activity Procedures. Any deviation shall be managed in accordance to MOC procedure including the requirement to assess risks posed by the change. The Process-Related Activity Procedures including checklists shall be kept for 7 years.
1.6 Outline of Process-Related Activity Procedures (PRAP)
The deliverable of PASR activities would be the Process-Related Activity Procedures (PRAP) and the outline shall cover detail information of the process related activity, the
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 11
affected facilities, the required steps/ tasks in executing the process-related activity as well as the assessment of simultaneous maintenance activities. However, the outline of PRAP depends on the type of process-related activity, and is not limited to the list specified below (sample outline below is for planned shutdown): (1) Title Page. (2) Authorisation Page. (3) Shutdown Work Program
(a) Facilities affected during shutdown.
(b) Platform status.
(c) Operating Medium.
(d) Floating Resources.
(e) Alarms & Shutdown system.
(f) Shutdown HSE Plan.
(4) Shutdown Activities Workscope for each Facility.
(5) Shutdown Procedure.
(6) Flushing Procedure.
(7) Integrated Plan on Paper (iPOP).
(8) Leak Test and Purging Procedure.
(9) Start-up Procedure.
1.7 PASR Log In addition to Process-Related Activity Procedures (PRAP) and PASR Phase 2 report, PASR Coordinator for each Region and Division shall also maintain a master register of all PASRs initiated within PETRONAS Carigali Region and Division. This may be referred to as Pre-Activity Safety Review (PASR) Log. The PASR Log shall include, as a minimum for effective traceability, detailed information covering: (1) A coding or numbering system for each PASR.
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 12
(2) A name or title for each PASR; mainly indicating the process-related activity.
(3) A date recording the initiation/ execution and completion of each PASR.
(4) Notes or remarks to detail any changes to the initial logging of the PASR activity, status, etc.
(5) Reference to other process e.g. MOC.
Sample of PASR Log is as shown in Appendix 10.
1.8 Status Monitoring and Assurance
In order to help ensure that each Pre-Activity Safety Review system delivers its intended benefits suitably, adequately and effectively, an assurance system is established to serve as mechanisms and procedures to measure, monitor and provide assurance with respect to
performance of PASR implementation. Assurance on PASR should be conducted as part of the overall HSEMS Assurance activity at the facility (as per PTS 60.0102 and PTS 60.0301).
1.8.1 Status Monitoring
The objective of monitoring PASR implementation is to ensure: (1) Findings and action items are properly evaluated and
approved at appropriate levels.
(2) Implementation and close out of PASR are documented by a review of required records: (a) PASR Logs.
(b) Process-related Activity Procedure (PRAP).
(c) PASR Phase 2 checklist.
Pre-Activity Safety Review WW ALL S 04 010
PASR Process Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 2
Page 13
1.8.2 Action Tracking
A system shall be established to ensure that all action items are properly monitored and managed to completion. Action tracking as a minimum requires the establishment of a formal system and procedure for: (1) Tracking the status of, and following-up on, identified
corrective and preventive action items arising from PASR activities
(2) Tracking the status of, and following-up on, identified corrective and preventive action items arising from assurance activities and their respective assurance reports.
Pre-Activity Safety Review WW ALL S 04 010 Process-Related Activities Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 3
Page 1
SECTION 3
PROCESS-RELATED ACTIVITIES
Contents
Paragraph Page No.
1 PROCESS-RELATED ACTIVITIES 2
1.1 Process-related Changes 2
1.2 Planned shutdown 2
1.3 Unplanned shutdown 3
1.4 Startup situations 3
1.5 Facilities purging 5
Pre-Activity Safety Review WW ALL S 04 010 Process-Related Activities Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 3
Page 2
1 PROCESS-RELATED ACTIVITIES 1.1 Process-related Changes
As part of the Management of Change (MOC), any process-related change shall be subjected to PASR. In complying with MOC system requirements, risk assessments shall be conducted for all change proposals, using an appropriate type of review tool depending on the nature and complexity of the change. Therefore this is in compliance with PASR Phase 1 requirements. PASR Phase 2 shall also be conducted prior execution of the activities and action items shall be tracked to closure as part of PASR Management.
1.2 Planned shutdown
PASR is deemed necessary for major shutdown that fulfils any of below criteria to ensure all the HSE controls are in place, and risks are minimized to ALARP prior to startup:
(1) Shutdown duration is more than 24 hours.
(2) Change of equipment, operating parameters,
chemicals or anything that may affect the process or potential cause of loss of containment.
(3) Mothballing i.e. hazards contained in any equipment.
(4) Involving simultaneous operations i.e. SIPROD.
For shutdowns that do not meet any of the criteria above i.e. unit shutdown (USD), PASR may not be required, provided that the activity does not pose high risk and it is safeguarded by an updated operating procedure. In carrying out the PASR, in particular the development of the Process-Related Activities Procedures for a planned shutdown, the following process-related safeguards are to be considered: (1) Empty sump pile, sump caisson and sump tank.
(2) Perform vent line flushing, if applicable.
(3) Reduce intake and export.
(4) Close in flowing wells.
Pre-Activity Safety Review WW ALL S 04 010 Process-Related Activities Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 3
Page 3
(5) Bring down liquid level of vessels, gas compressors
separators to the lowest possible point.
(6) Ramp down all export compressors until idling speed.
(7) Start portable air compressor.
(8) Trigger ESD or initiate shutdown.
(9) Lock out GPA at CCR console.
(10) Perform ESD checklist on all ABV and BDV position as per logic.
(11) Isolation, depressurising, draining and water flushing the lines subject to maintenance or construction work including associated lines up to the first isolation points.
(12) Locking and tagging of isolation valves or spades as per shutdown spading list.
(13) Identify and install barriers for all live lines.
(14) Proceed with shutdown work.
1.3 Unplanned shutdown
PASR is deemed necessary for any unplanned shutdown to ensure all the HSE controls are in place, and risks minimised to ALARP prior to startup. Process-Related Activity Procedures are required for any unplanned shutdown (PSD and ESD) and it can be developed beforehand. The cause of the unplanned shutdown shall be investigated and rectified prior startup.
1.4 Startup situations PASR Phase 1 & 2 shall be conducted for 4 startup situations of offshore and onshore facilities, namely commissioning startup, startup after process shutdown (PSD), startup following emergency shutdown (ESD) with depressurisation, and startup following emergency shutdown (ESD) without depressurization. Additionally, PASR is deemed necessary for startup after shutdowns that fulfill any of the criteria as stated in item 3.2.
Pre-Activity Safety Review WW ALL S 04 010 Process-Related Activities Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 3
Page 4
1.4.1 Startup following PSD or ESD (with or without depressurization)
PASR Phase 1 & 2 shall be conducted and Process-Related Activity Procedures shall be developed for any startup following PSD or ESD (with or without depressurisation). The document shall be approved by the Offshore Installation Manager (OIM), with the cause of shutdown investigated and rectified. In certain circumstances, the required Process-Related Activity Procedures can be developed beforehand and incorporated into OPM.
1.4.2 Commissioning startup
Commissioning startup is associated with commissioning of new facilities.
The following requirements among others shall be fulfilled prior to start-up.
(1) All construction works shall be completed with appropriate handover certificates or reports signed off by the platform authority.
(2) All pipework have been hydrotested and drained.
(3) Ensure all positive isolations i.e. spades or blinds installed during the shutdown are removed.
(4) The instrumentation has been calibrated.
(5) All trips and relief valves are in the right setting as per start-up procedure.
(6) Facilities are purged with inert gas to prevent the possible build up of an explosive mixture in the system.
PASR Phase 1 & 2 shall be conducted and Process-Related Activity Procedures shall be developed and incorporate all the controls into Operating Procedures Manual (OPM) for the black startup of the facility.
Pre-Activity Safety Review WW ALL S 04 010 Process-Related Activities Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD SECTION 3
Page 5
1.5 Facilities purging
Purging is important especially for commissioning startup and startup after major maintenance shutdown.
Purging is required to remove the air (oxygen) presence inside the facilities which may possibly cause explosion. Purging shall start from the further upstream point, allowing the inert gas to sweep the air inside the facilities to the furthest possible downstream point. The following procedure should be used as a general guide for purging the facilities: (1) Open the purge connection preferably on the bottom
of the vessel or upstream of the facilities and the valves on top of the vessel or downstream of the facilities preferably the manual depressurisation valves.
(2) All the valves on the level gauges and level switches on vessels and any other instrumentation on vessels or facilities should be in open position during purging.
(3) Close all the drain valves on all vessels.
(4) Start injecting nitrogen into the system at the purge connection or upstream of the facilities. Nitrogen will displace the air in the vessel or facilities and the air together with nitrogen will be evacuated through the other end to the atmosphere or through the manual depressurisation line to the vent system.
(5) Pressurised the system with nitrogen and depressurised slowly to desired pressure as per site-specific purging procedure.
(6) Repeat the pressurisation and depressurisation cycle until the oxygen concentration in the system reduced to between 0% - 7%. Oxygen concentration shall be regularly checked at the purge outlet connection using portable oxygen analyzer.
(7) After purging operation completed, facilities shall be prepared for start-up.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page 1
APPENDIX 1
Contents
Appendix Page No.
1 Sample of Samarang Process-Related Activity Procedures A1-1
2 Sample Checklist of Tembungo Integrated Shutdown
Sequence
A2-1
3 Sample Checklist of Tembungo Integrated Startup
Sequence
A3-1
4 Sample of SMG-A Cooler Spading & Isolation list A4-1
5 Sample of TBG Integrated Plan on Paper (iPOP) A5-1
6 Sample of Pre-Shutdown Safety Review Checklist A6-1
7 Sample of Pre-Startup Safety Review Checklist A7-1
8 Full Pre-Startup Safety Review Checklist A8-1
9 Sample of Appointment Letter for PASR Team Leader A9-1
10 PASR Log A10-1
11 PASR Phase 2 Form A11-1
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-1
Appendix 1 Sample of Process-Related Activity Procedures
SAMARANG INTERGRATED SHUT DOWN AND STARTUP PROCEDURE
PLATFORM : SMG-A /SMP-A/SMDP-A /SMP-B/SMDP-B/ SMP-C /SMJT-D /SMJT-F /SMJT-G /SMJT-E/ SMR-A/ SMK-A
PLAN START : 14-09-2004 to 20-09-2004 Duration : 5 days
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-2
AUTHORISATION This guideline contains the arrangements and precautions required for shut down and start up by the ASSET Custodians to ensure the safe execution of the Samarang TMM project, riser repair, pipe line repair, valves change out, hot work activities etc.(refer to the scope of work) By the contractors with work boat assistance. During shut down and start up operation, all activities will be stop for operation to do depressurize or pressurize the systems and make isolations. It also to reduce potential extended time for depressurizes pipeline or vessels. The objective is to ensure all focal point are clear of their function and responsibility and ultimately are able to respond to an emergency in their capabilities and capacity during the period. In the event if there is conflicting statement or uncertainties between this shut down and start up procedure with existing documents and any changes during the actual implementations, the matter is to be revert to the OIM, SOS, OS and operation in charge.
Name Signature Date
Prepared by Yousof Bin Ahmad (Operation Tech)
Reviewed by Boneface Albanus (SOS-Samarang) M Anton Abdullah (SOS-Samarang)
John Masudal (OS-Samarang) Fairuze Yahya (OS-Samarang)
Endorsed by M Johari Amir (OIM-Samarang) A. Thamilrasu (OIM-Samarang)
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-3
TABLE OF CONTENTS Paragraph Page No
1 Introduction 4
2 Summary Scope of Work 5
3 Shut Down Guideline For SMG-A 7
4 Shut Down Guideline For SMP-A, SMJT-E & SMJT-G 8
5 Shut Down Guideline For SMP-B 10
6 Shut Down Guideline For SMP-C, SMJT-D & SMJT-F 11
7 Shut Down Guideline For SMR-A 12
8 JHA Attachment 13
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-4
1 INTRODUCTION 1.1. SIPCOM WORK PROGRAM
1.2. Platform : -
SM Central: SMQ-A, SMG-A, SMP-A, SMDP-A, SMJT-E, SMJT-G,SMV-AA, SMV-A & SMR-A SM Northern: SMP-B, SMDP-B SM Southern: SMP-C, SMJT-C, SMJT-D, SMJT-F Samarang Kecil
1.3 Platform Status : Shut down/Live during pre and post shut down activities.
1.4 Operating Medium: Instrument air (Central) & Instrument Gas.
1.5 Floating Resources : Rental Work Boat ( MV Sirocco)
1.6 Major Facilities : Facilities that will be maintained live during pre / post shut down job and total shut down during project.
1.7 Alarm and Shutdown System : Platform alarm and shutdown systems are to be functionally tested and accredited functional by OIM. Platform is ready operating using instrument air systems. On remote platform, alternative alarm will be provided by operation and all contraction crew must familiar with the alarm.
1.8 Safety Requirement and Precautions:
Normal hazardous area classification shall govern. The safety requirement and precautionary works shall be implemented as detail in this pre and post shut down procedure.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-5
2. SCOPE OF WORK
2.1 WORKSCOPE SUMMARY AS PER LOCATION
The summary of planned shutdown and pre shut down activities to be carried out for Samarang Platforms by contractors and operation as following:
2.1.1 SMQ-A/SMG-A (1) RV’s rectification by Wehaya (on passing isolation valves)
(2) PM & Punch list clearance for ASD and PMCS. (SD)
(3) LPS-4026 – replace corroded 1” tapping line. (SD)
(4) PCV-3151 & PCV-3152 valve replacement (NSD)
(5) PCV-3430 & PCV-3420 (NSD)
(6) LCV-3060 (NSD)
(7) PLC for SDS to be reset. (SD)
(8) BC3091 readjust voltage. Increase supply voltage. (SD)
(9) Hook-up connection for spare MCB (UPS1/2) - SUMANDAK field project.(SD)
(10) Vent stack obstruction light replace blown bulb and check lamp changer. (SD)
2.2.2 SMV-A (1) Marine lantern check (SD)
(2) NTD check by STS/2
2.2.3 SMP-A (1) PCV-201A replacement (SD)
(2) PCV-2000 replacement (SD)
(3) 3-way valve fuel gas replacement (SD)
(4) 2” condensate line from SMV-AA (SD)-DYG
(5) Header ball valve change out. (SD)
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-6
(6) PL-133 inspection & repair.(NSD) Allied Marine (7) PL-132 LP vents line. (NSD) Allied Marine
(8) Receiver door barrel from SMP-C replacement. (SD)
(9) RV’s rectification. (SD) Wehaya
2.2.4 SMDP-A (1) Replace kill knob stand.(SD)
(2) Install extra SR on kill knob line from SANCOP.(SD)
(3) 2” instrument air piping replacement.(SD)-DYG
(4) 1” instrument pipe change out on SR-2A, 2B & 3. (SD)
(5) 4” drain line to sump tank replacement.(SD)-DYG
(6) 4” Blown down line replacement. DYG
(7) Replace blown down valve underneath wellhead area.
(8) Repair corroded grating. DYG
(9) Blow down valve change out – OT
(10) RV’s rectification. (SD) Wehaya Service SD SR.
(11) Gas lift pipe and headers cut and replacement. (SD)
2.2.5 SMP-B (1) PL-139 sectional pipe replacement. (SD) Allied Marine
(2) Riser repair punch list : 10” R6- LP to SMG-A. (NSD) Corroshield
(3) Header ball valves replacement. SM-58L (HP valve), SM50L (All valves) (SD)
(4) 8” LP vent line check valves replacement. (SD)
2.2.6 SMDP-B (1) Header ball valves replacement. (SD) [Sm-60L – LP; 60S-HP; 53S-Test; 64L
– all valves and flow line; 58S-flowline. (2) Replace handrail on chemical tank required hot work. (SD) (3) 2” gas lift replacement. Alab-3 ; SM-51 & SM-65. (SD)
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-7
(4) Angle iron support for LCV-301.
2.2.7 SMV-B (1) Marine lantern inspection. (SD)
(2) Vent stack inspection by STS-2.(SD)
2.2.8 SMP-C (1) 8” vent line butterfly valve replacement.(SD)
(2) Install 1 ball valve for water sample on V-300.(SD)
2.2.9 SMJT-C (1) Replace 3/8” parted tubing from PSD-01. (SD)
(2) Service 2” Big Joe regulator for S-1 from HHP.(SD)
(3) Riser repair punch list ; LP ‘B’ to SMP-A. (SD) Corroshield
(4) Replace handrail sockets (Hotwork) SD
2.2.10 SMV-C (1) Marine lantern inspection. (SD)
(2) Vent stack inspection by STS-2.(SD)
2.2.11 SMJT-D (1) Remove 2 pieces check valves on incoming lines SMJT-F.(SD)
(2) Riser repair punch list. (SD) Corroshield
(3) Unblock S1 drain line.(NSD)
(4) 4” Drain ball valves on Receiver R-117 replacement.
(5) Replace 2” x 600# header ball valve for HHP – SD
2.2.12 SMJT-F (1) Remove 2 pieces check valves lines to SMJT-D.(SD)
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-8
(2) Unblock S1 drain line.(NSD)
(3) Replace 6” orifice box on main gas lift header (SD)
(4) Replace 2” x 600# header ball valve for HHP – SD
2.2.13 SMJT-G (1) Replace 6” orifice box on gas lift header.(SD)
(2) Replace 2” x 600# header ball valve for HHP - SD
3 Shut Down Guideline For SMG-A
Pre-shutdown task: 14/09/2004 @ 0800 hrs
(1) Run close and open drain pumps to empty the sump pile
(2) Run condensate pump to empty the free water knock out drum on SMV-AA. (task – replace condensate line)
Shut down Guideline: 3.1 Establish proper communication with LGAST, KNDP-A and SMP-A prior to
reduce export to LGAST.
3.2 Ram down HP and LP compressors.
3.3 Run standby diesel generator (G-3670) before shutting down gas turbine generator.
3.4 Bring down vessel level to minimum.
3.5 Wait for SMP-A to initiate ESD by pulling kill knob from SANCOP.
3.6 After ESD trigger, check for vessel pressure and level. If still have pressure trap inside, depressurize the vessel.
3.7 Check for common ABV, ROV, BDV and equipment trip as per logic.
All start-up sequence can be referred in the startup procedure manual
REMINDER!
NO HOT WORK IS ALLOWED DURING FLANGE BREAKING, DEPRESSURIZATION, DRAINING AND LINE FLUSHING.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-9
GAS TEST `TO BE CARRIED OUT PRIOR TO ANY OF THE HOT WORK. 4 Shut Down Guideline For SMP-A/SMDP-A/SMJT-G/SMJT-E
Pre-shutdown task:
(1) Run sump pumps to empty sump pile (SMP-A) and sump tank (SMDP-A) (task – Hot work on SMP-A and replace drain line, blow down line for sump tank at SMDP-A)
(2) Carry out vent line flushing on all line. (SV & HP)
Shutdown Guideline:
4.1 Establish proper communication with SMG-A, CCR, LCOT and KNDP-A prior to reduce intake and export.
4.2 By-pass ASD-01 prior to shut down the station. (for lowering level)
4.3 Ram down HHP compressor until no load or minimum speed.
4.4 Run standby diesel fire water pump.
4.5 Inform KNDP-A to shut down their station.
4.6 Close in flowing wells when the HHP static reach 500psig or minimum pressure. (Last well to close SM9L, 6L, 16S, 17L ; high water cut)
4.7 Bring the HP vessel (V-100A) level to minimum. (task replace PCV-201A)
4.8 The surge vessel (V-300A) level to minimum. (task replace 20” ball valve if valve arrive on time)
4.9 Monitor the pumps and if needed put one export pump on manual during lower down the surge vessel level. At minimum level, stop the pump manually to prevent cavitations.
4.10 Once minimum level is reached, initiate ESD by pulling kill knob at SANCOP module. Monitor the time delay for SANCOP’s kill knob to trigger ESD. If not triggered, instrument personnel to check and rectify the problem.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-10
4.11 After ESD triggered, ensure all rotating equipment are brought to stop and vessels fully depressurized.
4.12 Record all ABVs and BDVs position.
4.13 At SMDP-A, isolate :
(1) 6” main gas lift manual ball valve
(2) 2” individual line gas lift valve
(3) individual valves on the headers to wellheads
(4) gas lift valves on the wellhead
(5) master valves etc.(task – replace main and individual gas lift headers,
valves and piping)
4.14 At SMP-A, close all header ball valves, COTP on off mode, bring up the orifice plate to top position of the orifice box and put tagging of isolation.
4.15 Normalize ASD and PPP panel.
4.16 Proceed to do shutdown jobs.
4.17 SMJT-E and SMJT-G will shutdown when SMP-A ESD.
4.18 Personnel onboard SMJT-G and SMJT-E will carry out shutdown sequence. If the station does not ESD, pull kill knob and check shutdown sequence.
4.19 Close all valves on wellhead.
4.20 At SMJT-G, isolate :
(1) The main gas lift header
(2) Individual gas lift valve
(3) Gas lift valve on the wellhead. (task – replace 6” orifice box )
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-11
EQUIPMENT AND PROCESS LINE NEED FLUSHING AND DEPRESSURIZATION
1. Condensate line from SMV-AA to SMP-A – flush and depressurize
2. Drain line to sump tank SMDP-A – flush
3. Drip pan SMP-A – flush and washdown
4. Blow down line SMDP-A – flush
5. LP and Test headers – depressurize and drain
6. Instrument air line SMDP-A –depressurize
7. S-1 – depressurize
8. V-100 PCV-201 - depressurize
9. V-300A – drain (depending on 20” ball valve availability)
10. LP gas line to SMG-A PCV-2000 – depressurize
11. Main and individual gaslift header SMDP-A – depressurize and flush
12. Main gas lift header on SMJT-G - depressurize
All start-up sequence can be referred in the startup procedure manual.
REMINDER!
NO HOT WORK IS ALLOWED DURING FLANGE BREAKING, DEPRESSURIZATION, DRAINING AND LINE FLUSHING.
GAS TEST `TO BE CARRIED OUT PRIOR TO ANY OF THE HOT WORK.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-12
5. Shut Down Guideline For SMP-B/SMDP-B
Pre-shutdown task: (1) Run both sump pumps on SMP/SMDP-B to empty sump pile and tank.
(2) Carry out vent line flushing and rocking LP pipeline.
Shut down Guideline:
5.1 Establish proper communication with SMG-A, CCR, ICR and SMP-A prior do the vent line flushing, rocking and close in well.
5.2 Close in high crude producing wells and let high water cut wells flowing for 3 hours. (SM42S, 51L, 60S, 57S, 66S ; high water cut wells) (task- pipeline sectional cut under water PL-139)
5.3 Manually isolate the LP ABV to SMGA on the cellar deck for pipeline total depressurization. (Corroshield task)
5.4 Inform CCR and SMP-A prior shuting down the station. Pull kill knob.
5.5 Carry out ESD check on all ABV and BDV as per logic. All vessels depressurized.
5.6 Close all flow line valves, wing valves and all header valves SSV as per logic. (task – flow line change out)
5.7 Depressurize the HP, LP and test headers. If required, depressurize HHP header. (Task - ball valves header and flow line change out)
5.8 Normalize all ASD and PPP.
5.9 Proceed with shutdown jobs.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-13
EQUIPMENT AND PROCESS LINE NEED FLUSHING AND DEPRESSURIZATION
(1) HP, LP and Test headers at SMP-B & SMDP-B – depressurize and drain.
(2) Vent lines – depressurize on upstream.
(3) Main and individual gas lift header SMDP-B - depressurize
All start-up sequence can be referring in the manual startup procedure.
REMINDER!
NO HOT WORK IS ALLOWED DURING FLANGE BREAKING, DEPRESSURIZATION, DRAINING AND LINE FLUSHING.
GAS TEST `TO BE CARRIED OUT PRIOR TO ANY OF THE HOT WORK.
5. Shut Down Guideline For SMP-C/SMJT-C/SMJT-D/SMJT-F
Pre-shutdown task:
(1) Run both sump pumps on SMP/SMJT-C to empty sump pile.
(2) Carried out vent line flushing and rocking LP pipelines.
Shut down Guideline:
5.1 Establish proper communication with SMG-A, CCR, ICR and SMP-A prior carryingout vent line flushing, LP line rocking and ESD test. 5.2 By-pass ASD-001, PPP and manually isolate supply to ABV on LP gas
pipelines to SMP-A prior shuting down the station. (Corrosheild and DESB task)
5.3 Inform SMJT-F first to close in all following wells.
5.4 Allow SMJT-D to flow only high water producing wells for 1-2 hours. (31S,41S & 34L)
5.5 Monitor COTP’s pump and bring down the Surge vessel level to minimum.
5.6 Close all wells at SMJT-C wells except SM19S and 85S.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-14
5.7 Pull kill knob from SMJT-C boat landing. (to check functionality)
5.8 Check that LP pipeline to SMP-A is totally depressurized.
5.9 Carry out ESD check on all ABV and BDV position as per logic.
5.10 Isolate all flow line valves.
5.11 Normalize the isolation valves to ABV (LP gas to SMP-A) after depressurization.
5.12 Normalize all ASD and PPP.
5.13 Proceed with shut down job.
SMJT-F
1. Shut down station by pulling kill knob.
2. Close in all wells by isolating flow line valves.
3. Check ABV position, as per logic.
4. Normalize the kill knob.
SMJT-D
1. Close in wells except SM-31S, 41S & 34L. (high water cut)
2. Estimate the wells to flow for 1-2 hours.
3. Contact SMP-C before pulling kill knob after 1-2 hours
4. Check the station status after ESD.
5. Normalize the kill knob before leaving the station.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 1 Page A1-15
EQUIPMENT AND PROCESS LINE NEED FLUSHING AND DEPRESSURIZE 1. All LP gas pipeline to SMP-A – depressurize.
2. Vent lines – depressurize upstream.
3. LP pipeline from SMJT-D
REMINDER!
NO HOT WORK IS ALLOWED DURING FLANGE BREAKING, DEPRESSURIZATION, DRAINING AND LINE FLUSHING.
GAS TEST `TO BE CARRIED OUT PRIOR TO ANY OF THE HOT WORK.
Prepared by : Yousof Ahmad Reviewed by: .......................................... John Masudal Samarang Ops Supv .......................................... M Anton Abdullah Samarang Senior Ops Supv Aproved by: ........................................... Thamilarasu SK Samarang OIM ........................................... M Johari Amir Samarang OIM
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD Appendix 2 Page A2-1
APPENDIX 2
SAMPLE CHECKLIST OF TEMBUNGO INTEGRATED SHUTDOWN SEQUENCE
TBG Shutdown Sequence (Shutdown Driver: Vessel Cleaning)
23/01/09 @ 0700hrs (Friday)
Time Task Action Party Check
0700 TBG A/B team to empty sump caisson. TBG A/B (HM,MM, AF)
1530 Toolbox meeting with contractors. (Contractor to prepare and submit PTW for next day, checklist preparation) All
Distribute ESD,PASR checklist.
1700 Power Transfer @ TBG A (G-500 to G-510) TBG A Elect/Mech
Ensure C-520 and P-400 is on duty before power transfer. Switch back to C-510 and P-320 after power transfer.
TBG A Elect/Mech
2000 Start lowering down liquid level for LP & HP flare scrubber liquid. Night Shift (SL,NL)
Empty sump pumps MOD 2,Prod Deck Night Shift (SL,NL)
Bypass V-200 and V-150 LSL and PSL. Night Shift (SL,NL)
TBG A start to lower down V-200 and V-150 liquid level. Night Shift (SL,NL)
Set LIC 5% for V-200 and V-150 Night Shift (SL,NL)
Ensure V-200 and V-150 level reach to the lowest point. Night Shift (SL,NL)
2300 Team depart to TBG B TBG B (AF,AW,NM)
2330 Team ready at TBG B TBG B (AF,AW,NM)
Ensure all systems are ready for shutdown mode. TBG B (AF,AW,NM)
2350 Inform EW CCR on pre-shutdown tasks. Night Shift (SL)
Inform TBG B if everything is ready for ESD activation Night Shift (SL)
24/01/09 @ 0000hrs (Saturday)
Time Task Action Party Check
0000 To close in high liquid producing wells B8-L & B1-L. (to reduce trunkline pressure from TBG B to TBG A) TBG B (AF,AW,NM)
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD Appendix 2 Page A2-2
0010 Activate TBG B ESD by kill knob and inform TBG A TBG B (AF,AW,NM)
Go through ESD check list. TBG B (AF,AW,NM)
Manually close flow line and wing valve for all wells and start TBG B system depressurization. TBG B (AF,AW,NM)
Normalize S-315 gas scrubber by nitrogen to open up SDV-2501 and monitor trunkline pressure to 0 psi.
TBG B (AF,AW,NM)
After trunkline pressure reach the lowest point inform TBG A. TBG B (AF,AW,NM)
0015 CCR panelman to activate ESD by killknob before LSL-200 reach the setpoint. CCR (SL,IBT,HM)
Inform EW CCR on shutdown activation confirmation. CCR (SL)
Go through ESD check list. Night Shift (SL,NL)
0030 Manually close flow line and wing valve for all wells. Night Shift (SL,NL)
0040 Tour check at site to ensure all pressure and level reached the lowest point. Night Shift (SL,NL)
0100 Stop Mol Pump P-140 when V-150 level reach 0% on LIC reading. Night Shift (SL,NL)
Manually drain V-200 and V-290 to caisson Night Shift (SL,NL)
Pump up skimmer pile. Night Shift (SL,NL)
Line up SDV-155 and SDV-165 Night Shift (SL,NL)
Restart P-140 to reduce V-150 level. Night Shift (SL,NL)
Prepare for LOTO All
Wait for complete depressurization Process
0200 TBG B team depart back to TBG A TBG B (AF,AW,NM)
0400 Extinguish flare (purge with nitrogen) Night Shift (SL,NL)
0430 LOTO on P-120,P-130,P-140,P-100 and complete check on ALL isolations.
Elect/Process (NJT,SL)
0600 Toolbox meeting (PTW, checklist preparation) All
0615 Handover to shutdown project teams All
0730 Team depart to TBG B TBG B (AS,MM)
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 3
Page A3-1
APPENDIX 3
SAMPLE CHECKLIST OF TEMBUNGO INTEGRATED STARTUP SEQUENCE
TBG Start-Up Sequence
TBG A Start-Up Sequence
Time Task Action Party Check
Ensure all the purging for vessel have been done Process
Tour check to identify isolation, spading removal of all associated line (refer to checklist) Process
Inform EWPA before start up CCR
Perform the following system check : Process
a. Portable air compressor is online and supply enough pressure for instrumentation.
b. L-160 & R-170 total shutdown switch on bypass
c. Gas compressor on bypass
d. Wellhead control panel on bypass
e. SDV 155 & SDV 165 opened
f. SDV-200 & SDV-290 opened
g. Header valve to production separator opened
h. Ensure that all natural producing well’s choke beans are set to the lowest size
i. Ensure all AGV for flowing wells are in open position
j. Ensure the blowdown valve in close position
Inform TBG B operation to start up station (go through TBG B start up sequence) Process
Pressure up all hydraulic supply to ScSSV. Open the master valve and then the SSV Process
Open the wing valve very slowly until the SITHP gradually falls equal to the FTHP. Process
Start the MOL pump when V-150 level reach 40 to 50 %. Electrical
Start the chemical injection pump. Process
Monitor V-210 pressure and start up Gas Compressor.(Check the V-210 for fuel gas supply pressure before initiate)
Process/ Mechanical
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 3
Page A3-2
Return the flowing panel to normal operation mode : CCR
a. Acknowledge and reset annunciator panel.
b. L-160 & R-170 switch to normal.
c. Gas Compressor bypass on normal
d. Reset flow computer alarms
Ignite flare Process
Tour check again to ensure all normally open valve are in open position and all normally close valve is in close position. All
TBG B Start-Up Sequence
Time Task Action Party Check
Ensure all spades have been remove by following the checklist. Process
Plug-off SDV-315 exhaust port Process
Bypass 'ESD bypass' button Process
Pull all 'PSD bypass' button & 'PSHL bypass' button at the Autocon module Process
Inject nitrogen to open SDV-315 (instrument gas scrubber) Process
Inform TBG A before opening SDV-2501 (line to TBG A) Process
Open up 1 well to supply enough pressure to instrument gas scrubber. Process
O/up all wells one by one Process
Monitor station until stabilize Process
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 4
Page A4-1
APPENDIX 4
SAMPLE OF SMG-A COOLER SPADING AND ISOLATION LIST
SMG-A COOLER SPADING & ISOLATION LIST E-3095 & E-3105
ISOLATION
NO TAG &
DESCRIPTION ISOLATION
DONE DATE OPERATION TECHNICIAN
PROJECT ENGINEER
OPERATION SUPERVISOR REMARKS
1 E-3095 LUBE OIL COOLER’S INLET & OUTLET 4” FLANGES.
(2 UNITS)
20/08/03 Patrick Edwin M Anton
2 E-3105 - GAS COOLER INLET 6” FLANGES
(3 UNITS).
20/08/03 Patrick Edwin M Anton
3 E-3105 - GAS COOLER OUTLET 6” FLANGES
(3 UNITS).
20/08/03 Patrick Edwin M Anton
4 HOV-3094
SUCTION MANUAL VALVE CLOSED.
20/08/03 Patrick Edwin M Anton
5 HOV-3096
DISCHARGE MANUAL VALVE CLOSED
20/08/03 Patrick Edwin M Anton
6 PSV-3095
MANUAL VALVE
CLOSED
20/08/03 Patrick Edwin M Anton
7 GT-3095 L/OIL TO E-3095 MANUAL VALVE CLOSE
(NEAR GT-3095 SKID)
20/08/03 Patrick Edwin M Anton
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 4
Page A4-2
DE-ISOLATION
NO TAG &
DESCRIPTION
DE-ISOLATION
DONE DATE
OPERATION TECHNICIAN
PROJECT ENGINEER
OPERATION SUPERVISOR
REMARKS
1 E-3095 LUBE OIL COOLER’S INLET & OUTLET 4” FLANGES.
(2 UNITS)
27/08/03 Patrick Edwin Boneface
2 E-3105 - GAS COOLER INLET 6” FLANGES
(3 UNITS).
27/08/03 Patrick Edwin Boneface
3 E-3105 - GAS COOLER OUTLET 6” FLANGES
(3 UNITS).
27/08/03 Patrick Edwin Boneface
4 HOV-3094
SUCTION MANUAL VALVE CLOSED.
29/08/03 Patrick Edwin Boneface
5 HOV-3096
DISCHARGE MANUAL VALVE CLOSED
29/08/03 Patrick Edwin Boneface
6 PSV-3095
MANUAL VALVE
CLOSED
29/08/03 Patrick Edwin Boneface
7 GT-3095 L/OIL TO E-3095 MANUAL VALVE CLOSE (NEAR GT-3095 SKID)
29/09/03 Patrick Edwin Boneface
Prepared by, Acknowledgement By OIM :
_______________________ ___________________________
Patrick Pterus. M Johari Amir.
Operation Process/Instrument Tech. Platform Superintendent. Date : Date :
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 5
Page A5-1
APPENDIX 5
SAMPLE OF TBG INTEGRATED PLAN ON PAPER (iPOP)
V-290 PL Welltest By Pass Line Modification
ACTIVITIES Materials Resources Who’s responsible? Clashes w/ other activities
HSE Issues Correction Action Parties
/Mitigation
PRE – SHUTDOWN ACTIVITIES
Mob Project Materials 25% Tarmazi no no Tarmazi SV
Mob Manpower no yes 100% Tarmazi no no Tarmazi SV
Site Preparation yes yes Tarmazi yes no Tarmazi SV
Odd Bolting no yes Tarmazi yes hand finger injury gloves/ proper tchq Tarmazi SV
SHUTDOWN ACTIVITIES
USD V-290 no yes OPR yes, VC
SD Welltest System no yes E&I / Opr no no
Remove existing spool no yes Tarmazi no spillage, pressure trap canvas, bleed before remove
Tarmazi SV
Blind Off incoming/outgoing line yes yes Tarmazi no spillage Canvas Tarmazi SV
Modify existing line yes yes Tarmazi/Opr yes, Workover Rig Down
HC existance in spool Cleaning before HW Tarmazi SV
RT & HT yes yes RT team/ Tarmazi/Opr
All activities Radiation, High pressure Midnight, barricade, announcement
Tarmazi SV / OPR
Re-instate back line yes yes Tarmazi yes, VC congested area Tarmazi SV
Power up energize system no yes tarmazi no no Tarmazi SV / OPR
POST- SHUTDOWN ACTIVITIES
Touch-up painting yes yes tarmazi yes fume PPE Tamarzi
Flanges greasing yes yes tarmazi yes no
Install U-Bolt & neoprene sheet yes yes tarmazi yes figer injury gloves Tamarzi
Housekeeping no yes tarmazi yes no
Rig down Equipment no yes tarmazi & opr yes ergonomic, heavy lift proper technique Tamarzi/OPR
Demob no yes trmazi no no
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 6
Page A6-1
APPENDIX 6
Sample of Pre-Shutdown Safety Review Checklist
No Descriptions Findings Remarks
Yes No N/A
Work planning
1. Work permit is written and obtained prior to commencement of respective activity.
2. Work scope has been discussed and agreed on with operations, contract holder and contractors.
3. Number of personnel carry out respective work is planned and identified, including shift work.
4. No. of pax on platform is planned, closely monitored and comply to PCSB requirement.
5. Coordination meeting is conducted with involvement from all parties; shutdown plan is developed.
6. Weather condition is taken into account prior to commencement of work.
7. Materials/ parts required for shutdown activities are checked and available at site.
8. Inspection and calibration of equipments/ tools is completed (including tools brought in by contractors)
9. Tools and consumables list is available.
10. All portable equipments are inspected and certified prior to site placement.
11. Shutdown procedure (from shutdown to startup), workpack or site-specific procedure is prepared and approved by management.
12. MOC is raised and approved by TA for modification in process or equipment prior to commencement of activity.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 6
Page A6-2
13. Operating manual (OPM), Hazard and Effect Register (HER) and other relevant documents are available at site for quick reference
14. All trainings required for shutdown activities are completed (both PCSB staff and contractors).
15. All outstanding items have been cleared prior to commencement of activity; otherwise management approval must be granted in order to proceed with open items.
16. Site preparations activities have been completed as per shutdown plan, include:
- erection of scaffolding - utilities set-up - hot bolting(if any) - insulation removal - spade placement/marking (spading list) - temporary equipment inspection & certification - preparation of relevant barriers/ safety
signage etc.
17. Locks (LOTO) are available and adequate.
18. Barricades are available and adequate.
19. Safety officer is identified.
20. Identified area fenced for authorized personnel only.
21. Communications means (radio, GPA etc.) is available and functioning.
22. Pre-mobilization briefing has been conducted for all contractors and staff.
Hydrocarbon liquid
1. Area is free of hydrocarbon.
2. Fire blanket is available.
3. Draining/ bleeding route is checked.
4. Adjacent pipework is leak free.
5. Containers, sumps, pits are prepared/ empty.
Hydrocarbon gas
1. Gas detectors and fire detectors are available and functioning.
2. Gas testing equipment is available and functioning.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 6
Page A6-3
Non-hydrocarbon gas under pressure in pipework (test by N2)
1. N2 purging equipment and supply are available and adequate.
2. Warning signage on pressure testing is available and visible.
Bottled gas under pressure
1. Gas bottles are stored at safe area and properly secured with wire rope.
2. Gas bottles are equipped with flashback arresters and check valve.
3. Gas bottles are certified and color-coded.
Diesel
1. Integrity check on diesel tank is done.
2. Diesel tank is earthed.
3. Diesel is sufficient for shutdown duration.
Overhead/ lifting equipment
1. All lifting gears are checked and certified.
2. Actual weight of the load is confirmed.
3. Lifting plan is prepared and discussed with operations & contractors.
4. Load chart of the crane is correct.
5. Crane standing area is firmed and flat.
6. Integrity check is done (using crane inspection checklist).
7. No unnecessary activities in lifting area.
8. Fire extinguishers, fire hose, and firewatcher are ready.
9. All alarm and emergency system of the crane is checked and functioning.
10. Number of personnel in the lifting area is minimized; access is restricted.
11. Clear escape routes are available.
12. Lifting coordinator is identified.
13. Crane operator is trained and qualified.
14. Crane signaler is trained and qualified.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 6
Page A6-4
Equipments with rotating parts
1. Ensure sufficient clearance for machine operation.
2. Moving parts are properly covered with guards.
3. Appropriate tools are ready for machine operation.
4. Ensure air, water and steam hoses are properly secured.
5. Access is restricted to authorized personnel.
Pressure vessels/ tanks/ separators
1. Ensure sump pile, sump tank, sump caisson and drip pan are empty.
2. Ensure liquid level is at lowest possible level.
3. Draining/ bleeding route is checked.
4. Ensure no hot work in the bleeding area.
5. Area fenced for authorized personnel only, if required.
6. Wind direction is checked. Gas plume is checked and considered safe.
7. Gas detectors are available and functioning at the nearby working area.
8. Fire extinguishers, fire hose, firewatcher are ready.
9. Tanks, vessels or work pieces are properly earthed.
Mechanical isolation
1. Ensure that spades are in right location (refer to startup and shutdown procedure).
2. Spectacle blinds are turned to correct position (refer to startup and shutdown procedure).
3. Valve opening/ closing sequence for shutdown activities are part of shutdown procedure and communicated to relevant personnel.
4. Pipe specifications are as per designed (refer to P&ID).
Instrument settings
1. Pressure safety valve (PSV) or Relieve valve (RV) settings are as per designed (refer to P&ID).
2. Ensure all instruments settings are as per designed (refer to P&ID) :
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 6
Page A6-5
PAH/PAHH PAL/PALL LAH/LAHH LAL/LALL TAH/TAHH TAL/TALL
3. Ensure all gauges & transmitters are available as per P&ID and functioning : PG/PT TG/TT LG/LT FT, flowmeter
4. Fire detection and protection equipments are functioning.
Electrical isolation
1. Equipments/ tools are checked for electrical safety.
2. Locks (LOTO) and isolation tags are available and adequate.
3. Personnel are trained and qualified.
Confined space
1. Blower is available and functioning for sufficient ventilation.
2. BA sets/ oxygen feeder are available, adequate and functioning.
3. Fire extinguishers, fire hose, firewatcher are ready. Firewatcher is trained and qualified.
4. No. of personnel working in confined space is planned and trained (including shift work).
5. Portable gas detector is available and functioning.
6. Access and egress are prepared.
7. Sufficient lighting is prepared.
8. Dust mask is available.
9. Proper tools for collecting and cleaning the sludge are available.
10. Temporary de-contamination room is available, if required.
11. Sunshade is available.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 6
Page A6-6
12. Area is fenced and warning sign is installed.
Gamma rays closed source type - radiography
1. Source container is checked for integrity.
2. Area is fenced for authorized personnel only.
3. Dosimeters for radiographers are available and functioning.
4. Max. exposure of gamma ray at the edge of the fence is checked.
5. Proper lead shields are available.
6. Source recovery or emergency tools are available.
7. Warning sign is installed and visible.
8. Radiographers are physically fit and certified.
Arc, gas and electrical welding
1. Proper PPE is available (welding mask, leather gloves, etc).
2. Welding curtain is prepared.
3. Access is restricted.
4. Welders are trained and certified.
5. Welding equipment is available, functioning, and checked for electrical safety.
6. Welding cable is in good condition.
7. Equipments are properly earthed, as required.
8. For gas acetylene welding/ cutting, cylinder tanks must be segregated during welding activities and stored separately.
9. Fire extinguishers, fire hose, firewatcher are ready. Firewatcher is trained and qualified.
Person working at height
1. Safety harnesses are available.
2. Scaffolding is erected by trained & certified personnel, and inspected by certified inspector.
3. Barricade the area underneath the scaffold or platform.
4. Adequate means to transport tools and equipment.
Health check for PCSB staff and contractors
1. Ensure all personnel working onboard are physically
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 6
Page A6-7
fit to work.
2. Blood and urine test for personnel working on mercury.
3. Drug and alcohol test for personnel working onboard.
Emergency response
1. ERP document is available at site.
2. Staff is familiar with roles and responsibility of ERT and EMT.
3. Staff is familiar with escape routes.
4. Members of DCT are trained and familiar with fire fighting equipments.
5. Staff is familiar with alarm system and aware of the mustering point.
6. Staff is aware of the location of life saving equipments.
Additives
1. For long duration shutdown, ensure that sufficient amount of corrosion inhibitor and biocide are available for the injection to relevant pipelines, if required.
2. For facilities with waxy crude, ensure that sufficient amount of demulsifier is available for injection to relevant pipelines.
Storage area
1. Dedicated storage area for materials and scheduled waste.
2. Chemicals are segregated accordingly.
3. Copy of MSDS is available at storage area.
4. Ensure proper labeling is displayed.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 7
Page A7-1
APPENDIX 7
SAMPLE OF PRE-STARTUP SAFETY REVIEW CHECKLIST
No Descriptions Findings Remarks
Yes No N/A
Work planning
1. All work permits are signed off accordingly.
2. All construction works is completed and appropriate reports signed off by platform authority.
3. No. of pax on platform is planned, closely monitored and comply to PCSB requirement.
4. Coordination meeting is conducted with involvement from all parties; startup plan is developed.
5. Weather condition is taken into account prior to startup.
6. Used materials/ parts are properly segregated and disposed off.
7. Equipments/ tools are returned to store/ warehouse, or brought back by contractors.
8. Tools and consumables list is checked.
9. All portable equipments are checked and removed from site.
10. Startup procedure, workpack or site-specific procedure is prepared and approved by management.
11. Applicable MOC requirement is met.
12. PHA/HAZOP has been performed and recommendations have been resolved or implemented before startup.
13. Operating manual (OPM), Hazard and Effect Register (HER) and other relevant documents are available at site for quick reference
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 7
Page A7-2
14. All trainings required for operating the process are completed (both PCSB staff and contractors).
15. All outstanding items have been cleared prior to startup; otherwise management approval must be granted in order to proceed with open items.
16. Site clean-up have been completed as per startup plan, include:
- Dismantle of scaffolding - Removal of utilities - Insulation installed - removal of spade - removal of temporary equipment - removal of relevant barriers/ safety signage
etc.
17. Locks (LOTO) are checked and removed accordingly.
18. Barricades are removed after work completion.
19. Safety officer is on site.
20. Identified area fenced for authorized personnel are removed.
21. Communications means (radio, GPA etc.) is available and functioning.
22. Safety rules or signs, as needed, have been posted.
23. PPE required for new equipment or chemicals are available prior to startup.
24. Tool box meeting is conducted on daily basis to ensure work carried out in a safely manner.
Hydrocarbon liquid
1. Area is free of hydrocarbon.
2. Gas detectors and fire detectors are available as per P&ID.
3. Draining/ bleeding route is checked.
4. Adjacent pipework is leak free.
5. Equipment is installed as per design specification.
6. Hydro-testing, tightness, and pressure tests have been completed with satisfactory results.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 7
Page A7-3
7. Leak check is performed.
8. Process line is purged with inert or N2 gas.
9. Warning signage on pressure testing is removed.
10. Fire extinguishers and fire hose are available.
11. Fire blanket is available.
Hydrocarbon gas
1. Gas detectors and fire detectors are available as per P&ID.
2. Equipment is installed as per design specification.
3. Hydro-testing, tightness, and pressure tests have been completed with satisfactory results.
4. Gas testing is completed.
5. Process line is purged with inert or N2 gas.
6. Warning signage on pressure testing is removed.
7. Fire extinguishers and fire hose are available.
Bottled gas under pressure
1. Gas bottles are stored at safe area and properly secured with wire rope.
2. Gas bottles are equipped with flashback arresters and check valve.
3. Gas bottles are certified and color-coded.
Diesel
1. Integrity check on diesel tank is done.
2. Diesel tank is earthed.
3. Diesel is sufficient for startup and operation activities.
Overhead/ lifting equipment
1. All lifting gears are checked and certified.
2. Actual weight of the load is confirmed.
3. Lifting plan is prepared and discussed with operations & contractors.
4. Load chart of the crane is correct.
5. Crane standing area is firmed and flat.
6. Integrity check is done (using crane inspection checklist).
7. No unnecessary activities in lifting area.
8. Fire extinguishers, fire hose, and firewatcher are
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 7
Page A7-4
ready.
9. All alarm and emergency system of the crane is checked and functioning.
10. Number of personnel in the lifting area is minimized; access is restricted.
11. Clear escape routes are available.
12. Lifting coordinator is identified.
13. Crane operator is trained and qualified.
14. Crane signaler is trained and qualified.
Equipments with rotating parts
1. Ensure sufficient clearance for machine operation.
2. Moving parts are properly covered with guards.
3. Appropriate tools are ready for machine operation.
4. Ensure air, water and steam hoses are properly secured.
5. Critical rotating equipment has been “run-in” to test for operability.
6. Access is restricted to authorized personnel.
Pressure vessels/ tanks/ separators
1. Ensure the manhole is properly boxed-up, secured and all bolts are tighten up as required.
2. Ensure sump pile, sump tank, sump caisson and drip pan are empty.
3. Ensure purging operation is completed.
4. Draining/ bleeding route is checked.
5. Ensure all valves are open/ close as per operation startup manual. No sign of leak from the valve body or stem.
6. ABV is in good condition and operated as per logic. No instrument air or gas release from the vent port.
7. Upstream or downstream of the unit is checked and confirmed no leakage.
8. Wind direction is checked. Gas plume is checked and considered safe.
9. Fire extinguishers and fire hose are available.
10. Tanks and vessels are properly earthed.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 7
Page A7-5
Mechanical isolation
1. Ensure that spades are in right location (refer to startup procedure).
2. Spectacle blinds are turned to correct position (refer to startup procedure).
3. Valve opening/ closing sequence for startup are part of startup procedure and communicated to relevant personnel.
4. Ensure all valves are lined up for startup.
5. Ensure that positive isolations i.e. spades or blinds installed during the shutdown are removed.
6. Pipe specifications are as per designed (refer to P&ID).
Instrument settings
1. Pressure safety valve (PSV) or Relieve valve (RV) are in the right settings (refer to P&ID).
2. Ensure all instruments settings are as per designed (refer to P&ID) : PAH/PAHH PAL/PALL LAH/LAHH LAL/LALL TAH/TAHH TAL/TALL
3. Ensure all gauges & transmitters are available as per P&ID and functioning : PG/PT TG/TT LG/LT FT, flowmeter
4. Instruments, including analyzers have been calibrated, as required.
5. Safety systems, including fire fighting equipment, are in place and have been checked.
6. Control systems, including shutdowns, have been checked.
7. Fire detection and protection equipments are
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 7
Page A7-6
functioning.
Electrical isolation
1. Electrical equipments/ tools are checked and kept in safe place.
2. Locks (LOTO) and isolation tags have been removed.
3. De-isolation and energizing is performed by trained and qualified personnel.
Confined space
1. Gas testing is conducted regularly.
2. Vessel inspection and cleaning are completed.
3. Sludge is segregated, and properly disposed off.
4. Access and egress are prepared.
5. Fire extinguishers, fire hose, firewatcher are ready. Firewatcher is trained and qualified.
6. Temporary de-containmination room is safely removed, if any.
Emergency response
1. ERP document is available at site.
2. Staff is familiar with roles and responsibility of ERT and EMT.
3. Staff is familiar with escape routes.
4. Members of DCT are trained and familiar with fire fighting equipments.
5. Staff is familiar with alarm system and aware of the mustering point.
6. Staff is aware of the location of life saving equipments.
Storage area
1. Scheduled waste is stored properly in a dedicated area.
2. TENORM waste is stored properly in a dedicated area.
3. Chemicals are kept in drums and stored in a dedicated area.
Copy of MSDS is available at storage area.
5. Ensure proper labeling is displayed.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 7
Page A7-7
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-1
APPENDIX 8
PRE-STARTUP SAFETY REVIEW CHECKLIST
Questions Notes and Percentage Compliance Action (Before/After Start-up)
1. Contractor Safety
1.1 What construction work will still be
in progress at time of start-up?
1.2 Will any contractors be allowed to
carry on work during the "startup
period?
1.3 What percent mechanical
completion do you project before
start-up? How much work will have to
be done after start-up? e.g. insulation,
painting, other installation
2. Emergency Planning
2.1 Has a plant emergency procedures
been written and have ALL employees
been trained in the procedure?
2.2* Have all employees participated
in an emergency exercise under the
latest plant plan? When? Review any
significant deficiencies found and
corrective action taken since.
2.3* Is there adequate provision for
emergency egress from
buildings/structures?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-2
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
2.4 Will power failure produces a
hazardous condition? If so, what
protection is provided?
2.5* Are there any key isolating valves
which would need to be shut off in any
emergency situation? Local or remote
operated? Where are they located and
how are they identified?
2.6 What shift manning will be
provided for start-up?
2.7 Other
3. Operations
3.1* Have all new or revised operating
instructions and SOPs been completed?
Have they been reviewed with all
appropriate plant operators and staff?
Documented? Tested? Is the complete
operating manual up to date?
3.2 Are copies of all procedures and
manuals available in the Control
Room?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-3
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
3.3 Do procedures cover start-u p,
shutdown, emergency shutdown
(various conditions), and normal
operation? e.g. includes loss of utilities,
weather emergency, earthquakes etc.
3.4 Are there procedures covering any
applicable "peripheral" tasks e.g.
sampling, materials handling(drums),
transfers, equipment opening,
emptying dikes or spill containment.
3.5* Have the operator log sheets,
checklists and HSE checklists been
written?
3.6* Are process flow sheets P&IDs and
equipment specifications available in the
Control Room including utility and other
"vendor supplied" units.
3.7 What is the status of operating
discipline program? Have limits been
set all critical?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-4
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
4. Training
4.1 Review training program which
has been implemented. Is it
complete?
4.2 Who carried out the training?
4.3* How the training been documented
for individual operators? How their
understanding of the training been
tested?
4.4 What training has been done for
day supervisors, shift supervisors,
maintenance supervisors?
5. Government Regulations
5.1 What licenses, permits or
agreements are required by the sites?
Have they been obtained?
5.2 Are there any materials handled on
site that are covered by government
regulations? If so, what chemicals and
what are the requirements under the
government regulations?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-5
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
5.3 What other government
regulations pertain to the plant site for
safety or environmental or industrial
hygiene or health?
5.4 Is a system in place to be kept
informed of changes in government
requirements?
5.5 Do you have copies of the
existing regulations? Do people have
the necessary knowledge to comply
with these and our permit
requirements?
6. Guarding
6.1* Are all equipment guards
completed and in place? Have they been
included on inspection checklists?
Not observe as equipment, static & rotating, are being installed.
6.2 Are all platform guard-rails,
handrails, safety gates, kick plates
complete? Check for pinch points/sharp
edges/operation of gates?
Not observe as platforms, etc are being installed. Not included in pipework and vessels check list
To include checking of platform, guard rails etc in piping and vessel check list
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-6
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
7. Personal Protective Equipment (Respirators)
7.1 Are any respirators used for
routine, non-routine or emergency
situations? If so, what type?
7.2 Is there a formal method for
approval/selection of respirators?
Who is responsible?
7.3 Is there an inspection, cleaning
and maintenance and storage
program?
7.4 Is there a "beard" and eyeglass
policy for use with respirators?
7.5 Does a training program exist for
correct use and maintenance? What is
frequency? When was it done? By
whom?
7.6 What limitations are placed on
the use?
7.7 If cartridge masks are used, what
is the policy for changing them?
7.8 Who was responsible for setting
the policy?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-7
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
7.9 Was fit testing conducted prior to
allowing use? Qualitative? Quantitative?
How is it documented?
7.10 Is medical approval required for
use of respirators?
7.11 Are any employees restricted in
their use of respirator protection?
7.12 Are respirators assigned to
individuals?
7.13 If air supplied respirators are
used, what is the source of air? What
protection is in place to ensure that
breathing air is not contaminated?
7.14 Does the respirator program
include contractors? If not the same,
how does it differ?
Protective Equipment/Work Clothes
7.15 Are nuisance dust masks used? In
what service?
7.16 Are there any special uses of
masks on site? Is this special use
documented? E.g. odor control.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-8
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
7.17 Is protective equipment, such as
glasses, boots and hats provided and
required? What is provided?
7.18 Are work clothes provided? What
is the policy for replacement? Is it worn
off site?
7.19 Are work clothes, protective
equipment laundered? On site or off
site?
7.20 If laundered off site, has the
laundry been checked to ensure no
cross-contamination occurs and
informed of potential hazards?
7.21 Is there a written policy for
selection, use and limitations,
decontamination, maintenance and
storage of protection equipment?
7.22 Who is responsible for selection
of protective clothing? Is data
available to support the selection?
7.23 How is proper maintenance and
storage of protective equipment
assured?
7.24 How is protective equipment
decontaminated?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-9
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
7.25 Do job procedures and safety
permits specify protective equipment?
7.26 What is the contractor's program?
7.26 Have emergency needs been
identified?
General
7.27 Where are safety showers and
eye baths located? Has this been
reviewed with regard to potential
exposure points, e.g. tank dipping,
truck unloading, filter changes etc?
8. Reactive Chemicals
8.1 Does the project introduce any
increased/new potential for a Reactive
Chemicals incident?
8.2* Has a Reactive Chemicals review
been carried out? By whom?
8.3 Were there any recommendations
from the review? If so, what follow-up
action has been taken?
8.4 Has any new Reactive Chemicals
testing been required? Completed?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-10
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
8.5 Review controls aimed at
preventing use of incorrect raw
material/acceptance or wrong
material/transfer error.
8.6 Are there any materials or
construction which would present a
Reactive Chemicals hazard in contact
with any of the process materials? How
has the new equipment been screened
to avoid miss-matches of this type?
8.7 Have pumps been checked for
potential to operate "dead-headed"? If
potential exists, is protection needed/
provided?
8.8 Is there potential for energy input
from agitation to cause a Reactive
Chemicals incident? If so, what
protection is provided?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-11
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
8.9 Has waste handling been
reviewed for reactive chemical
concerns?
9. Electrical
9.1 Review electrical hazard
classifications. Have electric equipment
been installed to this or higher standard?
9.2* Review bonding and grounding of
equipment and structure. Has
bonding/grounding been tested? What
provisions are there for bonding when
loading to or from drums? Has
maintenance testing schedule been
revised to include the new grounding
systems?
9.3 Have all the alarms/interlocks/
relays been set and tested? Has a
program been set up for regular future
testing?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-12
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
9.4 Review lockout tagout procedures
to be used with the new electrical
equipment. What plant rules apply to
fuse changing?
9.5* Is one-line diagram up to date (as
built) and posted?
9.6 Have electrical drawings been
updated to "as built" status?
9.7 Have electric motors been
meggered, checked for rotation and
lubricated?
10 Instrumentation
10.1 Have limits been set for all
critical control parameters?
10.2* Have "critical instruments" been
identified? Review list and redundancy
provided. Have procedures for regular
testing of critical instruments been
defined and program for future testing
set up?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-13
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
10.3 Have electronic instruments
been reviewed for vulnerability to
lightning (induced voltage)?
10.4 Are all instruments and
emergency block valves fail safe?
10.5* Are controls/instruments for
"crash shutdown" suitably highlighted?
10.6 Does instrumentation and/or
computer have a non-interruptible
power supply?
10.7* Are logic diagrams available for
computer controlled systems and
interlock systems? Including vendor
supplied items.
10.8 Have all interlocks been
physically checked for correct
operation in all occurrences of
parameter deviation?
10.9* Are all instruments and on-line
analyzers working?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-14
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
11. Environmental Leak and
Spill
11.1* Review location of gas detectors.
Have procedures been established for
regular testing of detectors?
11.2* Review plant drainage and
location/control of dike drain valves.
11.3 What protection is provided
against overfilling of tanks during
transfer?
11.4 Are there written procedures
covering emergency action for all leaks
or spills?
11.5 Do you have a written program
for environmental management?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-15
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
11.6 Does this written program include
procedures for : -waste management -
spill control - spill containment -
prevention, detection and Containment
of accidental releases - on and off site
emergency response plan including
response capability - waste and
emission recording and reporting -
audit of site program and performance -
environmental reviews of new facility
design and process and design changes
for existing facilities - environmental
review for introduction of new chemicals
- system to demonstrate compliance
with regulations and guidelines -
employee and community training and
awareness program - energy
conservation
11.7 Are responsibilities and
procedures for waste management
defined?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-16
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
11.8 Are all treatment and disposal
options identified for wastes and
inventory records maintained?
11.9 Is there a system records of
treatment and disposal kept in
accordance with file retention?
11.10 Are all burnable wastes
incinerated?
11.11 Has your waste management
plan ensured that no liquid or
hazardous wastes being sent to
landfill?
11.12 Are wastes well segregated?
11.13 Have off site facilities been
audited and approved?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-17
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
11.14 What is the waste storage
system? - labeled with original label (if
used drums) defaced - good containers
compatible with material - spill
containment and leak detection -
segregated used empty drums
11.15 Does your reactive chemical
program cover wastes?
11.16 Has the transport company for
waste been audited and approved?
Monitoring Program
11.17 Do you have a formal
environmental training program for all
employees? Review records and
content.
11.18 Has a monitoring program been
established to meet PETRONAS and
permit requirements? What does it cover
(review) (including noise)?
11.19 Has a baseline study/EIA been
conducted? If so, what were the
recommended monitoring plans?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-18
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
Technology
11.20 Does the plant comply with all
requirements for Environmental
guidelines for operations? (Review self
checklist and highlight any
discrepancies?) Has "deviation"
approval been obtained from Area VP
for Operations e.g. pumps, vents?
11.21 Are any HLPCs of CFCs used on
site? If so, where?
Containment Drainage
11.22 Are there any below ground
tanks or piping other than clean water
(including gasoline, fuel oil)?
11.23 Are tank farms, storage Areas
(including drums), loading and
unloading areas paved and diked?
11.24 What materials and design
have been used to pave and dike
including pits, valves etc?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-19
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
11.25 Can spills be contained and
recovered? Small? Large?
11.26 Do procedures and equipment
exist for spill control, containment and
recovery? What is the procedure for
draining dikes, pits, sumps etc?
11.27 Has potential sources for leaks
been identified and consequences
examined e.g. pipe ways?
11.28 Would fire fighting water be
contained in the case of a fire? If not,
where would it go?
11.29 Can drains and sewers be
blocked in the case of a spill?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-20
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
11.30 Have wall and floor
penetrations through containment
been eliminated or properly sealed?
11.31 Have a number of joints been
minimized and sealed?
11.32 Are drainage systems adequate
to handle worse case flows?
11.33 Are storm water - and
potentially contaminated water
segregated?
12. Pressure Vessels and Pressure
Relief
12.1 Have all pressure vessels been
registered? Regulatory requirement?
12.2 Have baseline thickness
measurements been taken?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-21
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
12.3 Do all pressure vessels have
safety relief? Do any relief systems
have isolation valves?
12.4 Review conditions used as
design bases for relief capacity.
12.5* Review location of relief
outlets.
12.6 Do multiple relief devices
discharge to a single manifold? If so,
what procedures have been established
for protection of people on removal for
servicing?
12.7* Has piping been reviewed to
identify locations where lines could be
blocked if exposed to heat from the sun
or from heat tracing?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-22
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
12.8 What is the inspection-frequency
for pressure vessels and relief devices? -
External? Internal? What is the impact
of this on plant operations?
13. Equipment and Piping
13.1* Will the project add any new
glass devices, expansion joints or brittle
equipment? If so, do these have site
registration and authorization? Will the
project eliminate any such devices in
use previously?
13.2* Review any cross-connection
between utility lines and process lines
or equipment.
13.3* Has there been an audit of
construction for completion as per
specification and drawings? (e.g. civil,
structural, electrical etc)
13.4* Review accessibility of operating
valves.
13.5 Has all piping been hydro tested
and flushed?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-23
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
13.6 Has piping and equipment been
inspected where special materials are
called for? (e.g. stainless or alloy bolts,
spiral wound gaskets, special grease)
13.7* Has complete P&ID check been
done on entire plant? By whom? How
many times?
14. Computers General
14.1 What fire protection is provided?
What materials? e.g. Halo CO2
14.2 Are duplicates of key programs/
records stored in a secure location
external to the plant? E.g. in a fire
proof safe in the Engineering
Department.
14.3 What will happen in the event of a
general power failure? How will the
process be restarted? Does the
computer have the ability to detect loss
of power?
14.4 Is there adequate protection
against over voltage or shorts in
individual circuits?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-24
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
Process Control Computer
14.5 Who can modify the program?
How is this controlled? Who can make
adjustments to control limits?
14.6 Are alarms classified in priority
categories? Are critical alarms
programmed to repeat at intervals
until the problem cause is corrected?
14.7 What is the manual override
policy and procedures?
14.8* Is there sufficient clearance for
work space with the computer open
back and front?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-25
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
14.9 Do the operators know what to
do in the event of power failure,
computer failure or alarm conditions?
15. Risk Analysis
15.1* Review F&E Index and MPPD
data.
15.2 Review drainage layout. What
flow rate can be carried?
15.3 Has a Process Hazard Analysis
been carried out for the new plant?
e.g. HAZOPS
15.4 Have existing operational
processes and equipment, not included
in the scope of the new project, been
reviewed for operational compatibility?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-26
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
16. Fire Protection
16.1* Review location of fire
extinguishers.
16.2* Review testing of deluge systems.
(Deluge systems should have an
acceptance test which follows the
procedure given in a write-up on "Fire
Protection Hydraulics" DCPL S&LP
Manual. The optimum is for the P.A.
Safety Director to witness this test and
in that case it will be desirable to have
run the system prior to the test, to
locate and clear any blocked spray
nozzle. Acceptable alternate would be
to review the test results.)
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-27
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
17. Occupational Health
17.1 Does an industrial hygiene
manual exist? If so, what does it
contain?
17.2 Where are copies kept? Are they
readily available?
17.3 Does the IH manual contain all
required information?
17.4 Has a chemical and Physical Agent
Inventory been established for all job
categories? (Including raw materials,
intermediates, wastes products,
maintenance chemicals etc.)
17.5 Is health and safety information
available on all chemicals listed on
C&PAI (e.g. MSDS, TIME)? Are they
available at all times to employees?
17.6 Is information obtained from
non- PETRONAS suppliers adequate?
Who assesses this information?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-28
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
17.7 What is the smoking policy?
17.8 What show policy exists? What
facilities are available?
17.9 Are lockers provided for clothes
storage?
17.10 Where is food stored and eaten?
17.11 What are the facilities and
requirements for contractors for
showering, clothes, smoking and
eating?
17.12 Does the site hearing
conservation program comply with
PETRONAS Corporate Guidelines?
17.13 Were audiograms conducted on
new hires for baseline? By whom?
What is the frequency for undertaking
audiometric tests?
17.14 Are any areas expected to
exceed 90 dB? Are signs posted
requiring hearing protection?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-29
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
17.15 What type of protection is used
(plugs muffs etc.)? Has the protection
been checked to ensure adequate
protection?
17.16 Has training been provided in
potential hazards and correct use and
maintenance of plugs and/or muffs?
17.17 Are there plans to check noise
levels at start-up? How?
17.18 Has ventilation systems
(general, local) been checked to
ensure they meet design
requirements?
17.19* Are air intakes located away
from containment sources?
17.20 If there are multiple hoods on
a system, have they been fitted with
dampers to allow balancing? Has the
balancing been done?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-30
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
17.21 Have all potential exposure
sources been identified?
17.22 Has all the necessary training
been conducted?
17.23 (Review Records). Has the
training record been reviewed?
17.24 Are any radiation devices
installed monitoring?
17.25 Has a lighting survey been
carried out?
17.26 What monitoring plans do you
have for start-up? Post start-up?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-31
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
18. Quality Assurance
18.1 Has the quality assurance
program been reviewed in respect of
the new operation?
18.2 Are new raw material
specifications necessary?
18.3 Are new product specifications
necessary? Is it necessary to re-qualify
the plant?
18.4 Has there been preparation for
stringent quality checks on initial
production to monitor new product
composition differences?
19. Maintenance(Assets Protection)
19.1 Does the Maintenance Department
have equipment specs and maintenance
manuals? Have spare parts been
reviewed? Have equipment history files
been commenced?
List of commissioning spares and consumables are available. Only Few spares for vessels at GRT 2 available. Majority has not been delivered. Auditing for availability on site not done. Consumables eg lube oil and hot oil are not on site. Hot oil is expected to be on site 13 Aug 08. Asset register for CMMS for GRT 2 has not been done
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-32
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
19.2 Has a lubrication schedule been
developed and checklist updated? Not available
19.3 Has the PPM program been
established and reviewed? Not develop
19.4 Other issues
19.5 Maintenance update on issues
related to incident 2 Jan 03
19.6 Maintenance update on issues
related to incident on 18 Dec 02
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-33
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
20. Start-up Planning
20.1* Has a complete start-up plan
been prepared?
20.2 Have start-up teams been
established on a regular schedule?
(Supervisors, Tech Center help,
maintenance people, computer people)
20.3 Has line authority been
established in start-up teams?
20.4 Has a maximum daily working span
been set (12-14 hours)? For team
members?
20.5 Have food transportation
arrangements been made for the startup
team?
20.6 Have arrangements been made to
keep out unauthorized visitors?
20.7* Has all construction equipment
been cleared from the plant? Is the
plant housekeeping satisfactory? (All
sheds, welding machines, insulation
storage etc. gone?)
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-34
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
20.8 Will material accounting
procedures be ready for the start-up?
Have feed and product metering,
inventory checks been updated?
20.9 Are plant clerical procedures
organized?
20.10 Operation update on issues
related to incident on
20.11 Operation update on issues
related to incident on
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-35
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
21. Distribution/Transport
21.1 Has a Risk Analysis been
conducted for ALL materials? What was
the recommendation? Have they been
implemented?
21.2 Is a 24 hour emergency response
system in place? Does it follow the
Pacific Area guidelines? If not, what are
the discrepancies and why? What is the
procedure for Marine emergency? Who
has been trained? How has it been
publicized externally?
21.3 What training has been
conducted for the transport
company? Terminal Operator?
Warehouse Operator?
21.4 What discussion has been held
with the emergency responders? Are
they aware of our emergency response
system?
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-36
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
22. PIPING
22.1 Piping subject to thermal expansion
must be sufficiently flexible and supports
adequate to take this into account. Check
if expanding piping, incl. nozzles and
branches, is not installed near
obstructions, support beams etc. When
checking expansion possibility for piping,
take into account insulation, which may
not yet have been installed. (For thermal
expansion take 1 mm per meter length
per 100 C temperatures for C-steel. For
stainless steels take 3 mm/m/
1OOdegC.).
22.2 Check that support in pipe racks
is adequate; for small-bore piping at
least every 3 m.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-37
22.3 Avoid small-bore piping, where
possible. In existing units, remove, or at
least spade, redundant piping. Min. size
process piping size should be DN 40.
Small-bore piping, such as DN 20
sample lines, should be connected to
the process lines via DN 50 weld necks
and the distance between connection
and first block valve minimized.
Reference is made also to DEP 31
.38.01.11, paragraph 2.1 and 3.8. Small-
bore piping should be properly
supported where vibration may be
expected such as on pumps (e.g. PG
manifolds) and sample connections.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-38
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
22.4 Piping should be able to be flushed
and drained easily. For regular drainage,
possibility for drainage to COC (oily
sewer) should be nearby. Low points in
steam lines to be provided with steam
traps.
22.5 Check/avoid pockets in piping
where liquid could collect during normal
operation and/or where corrosion could
occur. This also applies to e.g. piping in
spray water systems for fire protection
(where non-drained water after use or
testing could corrode internal welds,
where galvanic protection may be
missing). Check also for dead ends.
Minimize or remove. Dead ends of
bypass lines should be self-draining,
where possible.
22.6 Check/avoid screwed connections,
particularly in LPG service or at
temperatures above auto-ignition.
22.7 Thermal relief valves are required in
LPG process piping, if over 500 l. can be
blocked in. Also required in piping
systems over 500 l. in storage areas and
transport lines, which will be regularly
blocked in during normal operation.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-39
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
22.8 Look for steam rings on
inaccessible piping and equipment
flanges of DN 150 and larger in
hydrogen services above 200°C. To be
considered also for general service
above auto-ignition temperature.
Manifold to be at a safe distance from
the steam rings, some 10 m.
Alternatively, fire walls should be
provided. See also item 24, with respect
to weep holes in steam rings.
22.9 if there is a heat exchanger in a
pump suction line, ensure that the
suction line is self-venting.
22.10 Hot steam lines are to be well-
insulated, where possible danger exists
of auto-ignition of leaking HC's on hot
piping.
22.11 At interconnection of vapor-, and
liquid lines consider the line-up with
regard to possible liquid back flow into
the vapor line, e g. during a compressor
trip.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-40
22.12 Look for pockets in vapour lines
where condensation may occur, in
particular waste gas lines to furnaces. In-
and outlet piping of relief valves and
valves in compressor anti-surge circuits
(kickback system) must be self-draining
away from valves and contain no
pockets. External heating been may be
applied on those pockets which cannot
be avoided.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-41
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up) 22.13 Check whether sampling points
are safe for personnel. Facilities should
be provided for minimum spillage during
sampling, i.e. closed loops or flushing to
slops. Provide sealed, e.g. DOPAK-type,
sample connections for fluids, which
present a health hazard (e.g. with over
5% v. benzene or high concentrations
of n-hexane). Apply 'Strakman'-type
sample valves in hot, viscous service,
instead of sample coolers.
22.14 Flanges should be placed such,
that especially in liquid service during
fire flame impingement on equipment
surfaces, e g. vessels, can be avoided.
Where critical, shielding could be
applied in existing units.
22.15 Vapour lines (incl. steam) should
branch off from the top of main lines.
Small-bore cooling water lines must
also emerge from the top of the main
header.
22.16 Check position of eccentric
reducers. Normally straight side on
bottom of horizontal lines except in
pump suction lines where vapour
pockets may cause cavitations in the
pump.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-42
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
22.17 Compressor suction lines should
be traced and slope toward knock-out
drum.
22.18 Tracing between isolation valves
of pumps and heat exchanger elements
should be avoided and flushing
connections (FOS/FOR) supplied
instead.
22.19 Where possible, avoid flanges in
LPG service, except where strictly
required for operational or maintenance
reasons.
22.20 Check that anchoring of piping
discharging to atmosphere can
withstand reaction forces.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-43
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
22.21 Check SB's in rigid piping systems,
where spades could not be placed; also
on equipment nozzles of DN 250 and
larger and in lines of equipment that can
be blocked in with the unit still in
operation. Spacers and spades should be
installed rather than SB's in HP service
(ANS class 900 and higher) below 0°C
and in lines outside the range of
S.38.011 (OEP 31.38.01.11 Para 12).
Spacer rings should also be considered in
hot HP service rather than SB's, for heat
transfer reasons. Spacer rings should be
installed rather than excessively sized
SB's. For sizes of DN 750 or larger, ring
spacers should be placed in the vertical
plane for (easier) handling. In high-
pressure service spades should not be
used at all, since they are generally too
thin.
22.22 In deciding on SB's vs.
conventional spading prior to
maintenance (e.g. pumps) in systems,
where the need for SB's is less clear,
the time required to do the entire
maintenance job should be weighed
against the time needed to turn a SB.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-44
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
22.23 Ensure SB's or spades can be
turned or placed, when required, i.e.
ensure proper isolation valves placed
with bleed valve to check if SB can be
turned or spade placed. Ensure also
SB's can be turned properly (no
obstructions).
22.24 Check whether weep holes, 6
mm. dia., are present, located directly
downstream header valves in snuffing
steam line manifolds to furnaces, in
steam rings manifolds for hot H2
flanges (see item 8) and in tailpipes of
atm. RV's.
22.25 Check that seal loops in piping are
correctly installed and that facilities are
provided to ensure that the seal is
permanently in place (such as
permanent small water flow to a water
seal, controlled by a restriction orifice in
a supply line to the loop, if there is no
normal water flow through the loop)
22.26 Hot lines under insulation should
not be painted.
22.27 Non-insulated hot lines should
have personnel protection, if accessible
from grade, stairs or walkways.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-45
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
22.28 Hot piping (>auto-ignition
temps.) should not be laid in culverts,
open to HC spillages.
22.29 Flanges should not be insulated
prior to start-up.
22.30 Check for possible failure of
stainless steel piping by zinc drips from
galvanized structures above piping,
during a fire.
22.31 Check need for fireproofing
critical pipe supports/hangers.
22.32 In fire zones, check fire-proofing
of hydraulic tubing to ROV's - see also
item C15. A min. fire resistance of 15
minutes is normally provided by
stainless steel tubing. Alternatively, C-
steel tubing could be wrapped with
ceramic/mineral fibre material or may
be run through fire-resistant conduits or
may be coated with intumescent paint.
22.33 Pipe racks should be avoided
directly above 'hot' pumps (in service at
or above auto-ignition temperature) or
above pumps in LPG service.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-46
22.34 Supports for valves and
associated piping around hot pumps
(see item 33 above) should be fire-
proofed supports, particularly for
larger-dia piping (i.e. 6" or more).
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-47
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
22.35 Tell-tale vents must be provided in
cold-insulation near (insulated) flanges
for tightness testing during start-up.
Also, if such flanges are used for
spading during shut-down, ensure that
insulation around the flanges is
removable.
22.36 Check insulated equipment for
possibility for rain ingress under the
insulation and for under-lagging
corrosion. Also valid for 'cold'
equipment in humid climates.
23 VALVES
23.1 Apply double valve isolation in
service of piping class ANS 900 and
higher. Inside double block valves of
e.g. pumps and compressors that can
be isolated from the high pressure,
double isolation of vents/drains is no
longer required. Bleed valves in HP
service in general should only be lined
up to flare or closed system.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-48
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up) 23.2 In HP service, ensure isolation
valves can be operated easily, if no
motor-assistance is provided (see item 3
below). Small-size equalization bypass
valves around larger isolation valves
should be provided for this purpose.
23.3 Motor-operated valves (MOV)
should be considered for large valves,
which require regular opening/closure.
This could be above e.g. DN 300 but in
high-pressure service MOV's may be
needed for smaller (e.g. DN 150) valves,
such as discharge isolation valves for
high-pressure pumps
23.4 Isolation valves in small-bore
sample systems should be as close as
possible to the off-take lines.
23.5 Drain valves on equipment and
piping must be capped or blinded if
they are not used during normal
operation.
23.6 For operational drain valves,
see items 25.8-9.
23.7 Check valves may be applied in
continuous drains to closed drain
systems, to prevent back-syphoning.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-49
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
23.8 Block valves on RV's should
preferably have horizontal spindles to
eliminate accidental valve closure due to
failed gate-spindle connection (modern
gate valves are more robust).
23.9 Block valves are not allowed in
waterlines to safety showers and eye
baths between header and
shower/bath.
23.10 Consider access to valves in
overhead pipe racks.
23.11 Long-stem valves are to be
applied in (possible) cold duty and
should be in vertical position, to
protect the gland and/or the bonnet
from sub-zero conditions.
23.12 Hand-wheels for operational
valves must be easily accessible and
not obstruct walkways.
23.13 For reduced-port valves, check
that piping is self-draining on both
sides of the valves.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-50
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
23.14 Valves which may be required in
an emergency should be operable from
grade level. Valves that need frequent
attention should be easily accessible.
23.15 Recheck fire resistance (at least
15 minutes) of remote-operated valves,
as per Code BS. 5146. Fire resistance is
also required for appendages, like limit
switches that might prevent the valve
from closing and for the energy supply
system. Air-operated valves are
vulnerable, unless the entire air supply
system is made fire-resistant. An
exception could be made for ROV's in
the suction of those pumps that would
need to be stopped during a fire, in
which case loss of air would cause the
ROV to close, which in turn trips the
pump. See also item B32 on fire-
resistance for hydraulic tubing to ROV's.
23.16 The fail-safe action of ROV's, if
any (double-acting actuators have no
fail-safe position), should be checked.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-51
23.17 It must be checked that the
hydraulic levers of ROV's can be
locked-shut during maintenance on e.g.
pumps. Check that pneumatically
operated ROVs can be opened at the
valve, as well as from a safe location
(see also 28.13).
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-52
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
23.18 Check valves should preferably be
in horizontal line sections and never in
vertical lines with down flow. In upward
vapour lines not recommended either if
liquid could collect on top of the flapper,
when the vapour flow is stopped.
23.19 Check that external flapper shafts
of check valves are properly secured, so
that no leakage to atmosphere can
occur (e.g. by external restraint bar). In
high-risk service use other type check
valve.
23.20 Ensure that check valves between
equipment and its relief valve are fire-
resistant, if they are in the fire zone.
23.21 Hot oil block valves should be
well accessible in view of fire risk.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-53
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
23.22 Locks on valves should be
minimized to those where valves cannot
be avoided but must remain open /
closed during normal operation. Seal
locks are allowed only on isolation of
thermal relief valves and where the
safety consequences of unauthorized
closure of a valve would not be very
pronounced.
23.23 Welded valves should have
flanged bonnets for maintenance.
23.24 Maintenance access to valves
must not be obstructed by all-welded
steam tracing.
23.25 Check whether lubricants are
allowed in valves in oxygen-enriched
air service.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-54
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
24 RELIEF VALVES (INCL.
ASSOCIATED PIPING/VALVES)
24.1 Check accessibility of relief- and
de-pressuring valves for maintenance
and inspection.
24.2 Relief valve piping and bypasses
must be self-draining, away from the
relief valves. Inlet piping should
preferably not contain long, say more
than 10 diameters, horizontal sections,
unless these are traced or at the very
least insulated.
24.3 Connections from relief valves are
made on top of the flare header. An
exception may be made for DN 25*25
thermal relief valves which do not need
to be self draining on both sides if the
lines become too long.
24.4 Check if heat tracing is provided to
avoid RV inlet plugging by freezing,
hydrate formation or sublimation.
Provide at least insulation on relatively
long horizontal line sections (longer than
say 10 diameters).
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-55
24.5 If relief valve size is determined by
fire, verify the type of insulation, which
was used in calculations. Please note
that PUF is as good as or better than
conventional insulation in providing fire-
resistance.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-56
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
24.6 Dedicated fire relief valves on
vessels should never be routed to
grade but tied into a closed relief
system.
24.7 In non-vacuum service the space
between a RD and a RV should have a
PA(H) to warn of leaking RD (pinhole).
In vacuum service a PG will suffice. As
an alternative to a PA/PG, the space
between RD and RV could have an
open vent line to flare but this system,
though safe, gives no warning of a
leaking RD.
24.8 Balanced-type RV's should have
open bonnets, venting freely to
atmosphere. Check that bonnet vent
holes are not plugged. These vents
should be tagged for hazardous
materials (e.g. for H2S) and vent holes
should then be provided with instrument
tubing that terminates well above the
RV platform.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-57
24.9 Three-way valves instead of
interlocked valves on relief valves plus
spares should not be allowed, if no
guarantee can be given on total
isolation of any one of the two
positions, needed for removal of a RV
for maintenance.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-58
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
24.10 Inlet block valves are only allowed
on single relief valves for fire relief only
and if spare relief valves or spare
positions are available. The block
valve(s) of the on-line RV('s) should be
LO. Outlet block valves on RV's and
spare positions should always be LO
(incl. the spare RV or spare position), in
order not to over-pressure the outlet
piping/nozzle in case of a leaking RV.
Check that spare relief valve connections
are open dummies, as per DEP.
24.11 On single relief valves, outlet
block valves (LO) are allowed as long as
there are no inlet block valves. An
exception is made for thermal
expansion valves on equipment that can
easily be isolated and taken out of
operation, like parallel heat exchanger
elements, spare filters or spare
reciprocating compressors. For types of
locks on valves, see section valves, item
23.22.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-59
24.12 With (inter)locking systems,
ensure proper access to these systems
and that interlocking can only be
achieved in the correct sequence. Check
interlock control system, if applicable
(e.g. keys).
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-60
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
24.13 Check presence of ‘tell-tale'
vents between isolation valves and
relief valves (always on inlet side and
on outlet to H25 flare or back to
process).
24.14 In refrigerated service, RD's may
have been placed parallel to RV's, with
30% higher set pressure, for protection
in case of icing (alt.: methanol injection
into RV inlet line).
24.15 Any equipment that directly
affects the capacity of a relief valve,
must be properly tagged in the field
This may include restriction orifices,
check valves and control valves plus
their bypasses. (These must also be
checked regularly). Isolation valves
with small holes drilled in the gates can
serve as thermal relief valves (e.g. in
Cooling Water service); these must
also be properly tagged in the field for
identification (and regular inspection).
24.16 A check valve in a relief route
must be checked to be fire-resistant, if
in the fire zone during fire relief.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-61
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
24.17 The open end of an RV tail pipe
for flammable HC's should be within the
action radius of fire extinguishing
equipment. If not, a snuffing steam
connection should be provided.
24.18 RV tail pipes to atmosphere
must have a 6 mm dia. weep hole at
the bottom, to drain collected water.
The tail pipe should preferably have
90-degree elbow to prevent rain
ingress (unless calculated reaction
forces prohibit such an elbow).
24.19 Check atm. tail pipes of relief
valves for adequate support against
reaction forces.
24.20 Common atm. vents for a
multitude of RV's should not be applied,
since during maintenance of one of the
RV's personnel may be exposed to
leakage/discharge from the other valves.
24.21 Silencers on atm. relief valves
must be of the non-fouling type.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-62
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
25 COLUMNS, VESSELS AND
TANKS.
25.1 Check position of drain nozzles.
These should be clear from areas where
heavy equipment such as forklift trucks
may work.
25.2 Drains and vents are to be
provided with valves and blinded or
capped normally.
25.3 Man-ways must be within reach of
hoisting equipment.
25.4 Check possibility for safe entry for
inspection and check availability of
adequate venting facilities (DN 150 or
more).
25.5 Instrument tappings and local
instruments, particularly level gauges,
must be readily accessible, also from
ladders.
25.6 Check if insulation for personnel
protection is provided. Check also
whether any specified fire insulation is
suitable material, hence a hard layer of
intumescent fire insulation material (and
not simple stainless steel sheeting that
covers ordinary insulation material)
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-63
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
25.7 Check if lines can follow vessel
expansion when heating up/cooling
down. Pay special attention to
supports on hot and cold structures.
Check free movement of platforms
25.8 Operational drains to
atmosphere should have two drain
valves, the downstream one being a
spring-loaded quarter-turn ball valve,
in sight of the level gauge and also in
sight of - but at a safe distance from -
the actual drain point. These drains
should be lined up to safe disposal
system by hard-piping or via
tundishes.
25.9 Drainage of liquid LPG
components should be via two
valves, one upstream block valve and
a globe valve, for control. The
distance between the valves should
be min. 600 mm. Thus, if the globe
valve accidentally freezes, the block
valve can still be closed. If freezing
through unattended drainage, even
for a very short time, would cause
severe problems in downstream
systems (e.g. fuel gas), then the
downstream valve should preferably
be a spring-loaded quarter-turn ball
valve.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-64
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
25.10 Liquid drainage should be done
with min. environmental impact, i.e. to
oily sewer. Those liquids that are
valuable or liquids with a potential
health hazard (e.g. liquids with >5%v
benzene or high concentrations of n-
hexane) should be drained to a closed
collection system, for recovery.
Connections between vessels and closed
drain systems should preferably be open
to atmosphere with sealed drain hubs.
This prevents syphoning flammable
materials back into the vessel. Check
valves may be used, but may not
prevent back-flow.
25.11 For drain lines with seal legs,
ensure that the syphon breaker line
vents to safe location, if gas can be
trapped or accidentally entrained with
the liquid.
25.12 Check if water trapped in
goosenecks can be displaced by
hydrocarbons, i.e. sufficient static head
on the inlet side of the gooseneck.
25.13 No flanges are allowed inside
vessel skirts.
25.14 Check that center-wings of pipes
passing through skirts can move freely.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-65
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
25.15 Check earthing/bonding.
25.16 Check line-up of emergency de-
pressuring facilities, of ROV's in suction
lines to pumps and of emergency pump-
out systems, where applicable. Check
also fire detection systems (double,
fuseable plastic tubing under air
pressure) and water spray systems on
vessels containing over 4m3 of LPG or
over 10 m3 of HC's above auto-ignition
temperature (generally >220°C).
25.17 Check site procedure for re-
pressuring of cold pressure vessels (e.g.
after de-pressuring LPG), if material is
not suitable for sub-zero °C
temperatures. (Re-pressuring only if
material has warmed up again to
ambient conditions).
25.18 Check presence of level alarm in
open pits for HC drain vessels, to warn
against excessive water collection (rain).
Check also presence of HC detector in
pit to warn against possible build-up of
flammable mixture in the non-ventilated
space. Check electrical equipment in pit
to be suitable for Area Classification
Class 1.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-66
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
25.19 If nitrogen is used to air-free LPG
storage vessels prior to filling, the utmost
care should be taken during filling, since
during initial filling, especially if carried
out slowly, evaporating LPG can cause
liquid phase temperatures to be well
below those normally assumed for LPG,
since the LPG vapour partial pressure is
then very low. Check procedures at site.
25.20 Tank vents and PV-valves should
be fitted with bird screens.
25.21 PV-valves on fixed-roof tanks
should be installed for more volatile
liquids (if floating-roof tanks are not
specified, such as for gasoline)
26 REACTORS
26.1 Check regeneration connections
are positively isolated from process.
26.2 Check area for suitability of
catalyst handling and safe location of
mobile air compressors, if applicable.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-67
26.3 If a Nitrogen blanket must be
provided on spent catalyst or catalyst
dust drums, ensure that the drum lids
are loose and cannot be clamped shut,
(check if specialized contractors are
used for inert operations/cat, handling)
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-68
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
27 HEAT EXCHANGERS
27.1 Check space for withdrawal of
tube bundles.
27.2 Check, whether piping on the
tube side of heat exchangers can be
removed easily (e.g. by spools) for
dismantling of the tube side for
cleaning or repair.
27.3 Check whether bundles can be
pulled and lowered safely from
platforms and stacked arrangements.
27.4 Check stacked heat exchangers
for the possibility of oil spills on hot
equipment underneath it, especially
during maintenance work.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-69
27.5 Check position/availability and
operability of SB's and the possibility
for draining/venting heat exch.
elements. Each stack of heat
exchangers should have one drain-
and one vent valve. min DN 40,
preferably DN 50, on shell- and tube
side piping. (For drainage to closed
systems see item 25.10).
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-70
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
27.6 Vertical floating head heat
exchangers must have drain valves at
the lowest points in the shells,
especially if hot oil is the medium and
at start-up water has been used for
flushing (also in LPG service on tube
side and steam on shell side, where
residual water could freeze upon de-
pressuring of LPG). For vertical floating
head heat exchangers a separate vent
may be located on the shell for
degassing, if this is not possible via
the vent on the piping.
27.7 Utility connections and drains
should be located correctly, i.e. short
distance from block valves, drains at
low points.
27.8 Check if thermal expansion valves
(TEV) are installed on the colder side, if
this can be blocked in. On LNG/Natural
Gas heat exchangers, a TEV is thus
required on the LNG (cold) side. Check
air cooler bundles for TEV's, if these can
be blocked in.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-71
27.9 Check location of air cooler
bundles, with respect to possible need
for fire protection. Not to be placed
above pumps in service for LPG or
above auto-ignition temperature.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-72
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
27.10 Check whether FOS/FOR
connections can be properly spaded.
27.11 Check earthing/bonding.
27.12 Check expansion possibility for
elements- sliding supports.
27.13 The body flanges of heat
exchangers should not be insulated,
when in H2 service or with varying
temperature load.
27.14 With insulated flanges, bolts
must be pre-tensioned, since on startup
they will get hot and therefore expand.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-73
27.15 Inaccessible flanges around, and
body flanges of, heat exchangers in H2
service above 200 °C. must be provided
with snuffing steam rings for dispersion
of leakage from the (non-insulated)
flanges. The bottom of the steam ring
should have a 6 mm dia. weep hole for
drainage of condensate. See also item
22.8.
27.16 Condensate may be drained via
steam traps; an upstream strainer is
then required and in addition the trap
must have a bypass. If discharging to a
condensate system, a full-size drain is
also required.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-74
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
27.17 Check personnel protection
measures on hot exchanger surfaces.
27.18 For leak detection of very light
HC's into open cooling water channels,
outlet piping of coolers may be provided
with T-pieces, from which light HC's are
vented to safe location. HC detectors
can then be placed in the area of the
vents.
28 PUMPS
28.1 Check if line-up of valves around the
pump is correct and that valves are
operable. See also items 23.1-23.3 on
large valves and valves in HP service.
28.2 Check if the pump can be handled
safely for maintenance. Pay special
attention to spading-off possibilities and
to adequate drainage possibilities for line
work, especially if product could spill onto
hot equipment and/or piping nearby. See
also item 28.8.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-75
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
28.3 Check for SB's on inside of pump
isolation valves (except if valve size
smaller than DN 50). Spades or SB's
also needed on pump vents/drains, if
connected to a common discharge
system (e.g. on pumps in vacuum
service). Need for spades or SB's to be
judged by time it takes to turn spades
vs. time needed to carry out a repair
job.
28.4 Check if facilities have been
provided for pump standby conditions,
notably bypasses around check valves.
Special check valves with holes in the
flappers (not encouraged but only
allowed for drainage of discharge
piping) should be clearly tagged for
regular inspection.
28.5 If there is a heat exchanger in a
pump suction line, ensure suction line is
self-venting.
28.6 Check position of eccentric
reducers. Normally straight side on
bottom of horizontal lines except in
pump suction lines where vapour
pockets may cause pump cavitation.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-76
28.7 Casing drains must be provided with
valves, except for LPG pumps, and
blinded/spaded). See item 25.10 on
connections to a closed drain system.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-77
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
28.8 Check if double-valve pump vents
(with two block valves and SB on pump
side of vent line) are provided for LPG or
lighter service (vent to flare), if suction
vessel operates under vacuum (vent to
suction vessel) or if venting is required
at start-up at/above auto-ignition
temperature (vent to closed suction
system) For the latter case, it may also
be acceptable to vent to atm. drain (via
hose connection) but only if cold flushing
oil can be supplied to the pump, cold
flushing oil is then bled from the pump
vent system to oily sewer. The pump
contents can then gradually be replaced
by the hot process fluid, once the vent is
closed again. However, hard-piped vent
systems to the suction system are
preferred. Pumps in high vapour pressure
liquid service should have vents between
check valves and discharge valves.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-78
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
28.9 No tracing between pump block
valves, but instead Flushing Oil
Supply/Return connections, with proper
spade positions. If in high-pour-point
service the piping between discharge
valve and check valve is not flushed, this
particular piping section should be as
short as possible (and possibly traced).
28.10 Pumps for LPG or materials
above auto-ignition temperature must
not have any screwed connections.
28.11 Pumps for LPG or materials above
auto-ignition temperature must be easily
accessible and (preferably) not installed
underneath pipe racks/air-coolers. See
also next item 12.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-79
28.12 Ensure that fire detection
systems (preferably double, fuseable
plastic tubing under air pressure) and,
where required, also water spray
systems are installed over LPG pumps,
over pumps in other HC service above
auto-ignition temperature (generally
over 220°C), over compressor seal oil
pumps and return sumps (see also item
1-10).
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-80
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
28.13 If an ROV is installed in the pump
suction, ensure that a remote switch for
closing the ROV is located at a safe
distance (15 m+), but with the pump
still visible. See also items 23.15-C17 on
ROV's.
28.14 For Y strainers over DN 100,
separate DN 20 drain valves on the
strainers are required. Check easy
access to strainers and easy
replacement of strainer elements.
28.15 Check if PG- and other small-
bore connections are well supported.
28.16 Check earthing/bonding.
28.17 Check motor EX ratings with
respect to Area Classification.
28.18 Check that no process flanges
are located inside noise covers around
pumps and compressors, which could
possibly result in the build-up of a
flammable mixture.
29 COMPRESSORS
29.1 Check if compressor suction lines
are traced and slope toward KO drum.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-81
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
29.2 Suction lines to compressors with
bottom inlets have pockets, which should
have operational drains (see also 25.8-
9), to check for, and drain, quickly any
liquid prior to (re) startup. The drain
system should either be piped to flare or
alternatively be hard-piped to a point at
grade/AOC (not into a 'closed' drain
system) in a safe (i.e. open, well-
ventilated) location, at a distance of 2-5
m. but still visible from the last of two
drain valves, with no valve but blinded
end flange only at the actual drain point.
Also valid for casing drains on
centrifugal compressors. Suction drains
on pulsation dampers should be lined up
to flare. Drains on discharge damper
could be lined up to flare or alternatively
hard-piped to grade, at 2-5 m. but still
visible from the drain valve; at drain
point no valve but blinded end flange.
29.3 Check if contaminated seal oil tank
has safe location vent with flame
arrestor and (permanent) N2 purge
connection on the tank. Check safe
location of distance piece vents. Sour
seal oil traps should have (locked) open
vents to flare.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-82
29.4 Check relief and remote-operated
valves.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-83
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
29.5 Check earthing/bonding.
29.6 Check motor EX ratings with
respect to Area Classification.
29.7 With respect to danger of reverse
rotation, distance between compressor
block valves should be as short as
possible, if pressure differential is high.
29.8 Check de-pressuring facilities for
compressors with dry gas seals.
Automatic (AFC) de-pressuring valves
should be installed, if it is impossible to
de-pressure manually from a safe
distance within a few minutes after seal
failure. Dry gas seal purge lines should
be lined up to flare.
29.9 Check if discharge valves for
compressors with dry gas seals are
closed automatically upon seal failure, if
reverse rotation could cause much
damage. Gas seals purges should be
lined-up to flare.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-84
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
29.10 Check presence of fire protection
facilities for vital compressors for which
no spare are available, such as recycle
gas compressors in Hydro-processing
Units. See also item 28.12 re. fire
protection seal-oil systems.
29.11 In case two electrical seal-oil
and/or lube-oil pumps are installed,
check whether at least one pump
motor is connected to a vital or
emergency power supply system.
30 FURNACES AND BOILERS
30.1 Check available space for tube
withdrawal and cleaning.
30.2 Pay special attention to safety of
fuel systems: - Heavy fuel and LBF
systems to be sufficiently segregated. -
Provisions to prevent liquid fuels from
entering steam and gas systems must be
adequate. - Special requirements for low
pressure/waste gas systems.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-85
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
30.3 Check that smothering steam
headers are at safe distance (10-15
m.) from the furnace. For individual
lines, coming off headers: - Weep holes
of 6 mm dia. should be provided
immediately downstream of the
isolation valves. - Branch off nozzles
position on top of mains. - Steam lines
to slope (no pockets) back to isolation
valves. - Sufficient steam traps and
drain points provided.
30.4 Check that fuel valves are within
hand reach when looking at the
burners through the observation
windows.
30.5 The emergency shutdown switch
must be at a safe location and fuel trip
valves must be in a non-vulnerable
position.
30.6 Check that trip valves in fuel
service are single-seated and dedicated
(TSO).
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-86
30.7 Trip valves must not have
bypasses or hand-wheels, which could
defeat the safeguarding function.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-87
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
30.8 Check possibilities to test TSO trip
valves.
30.9 Fuel-gas lines ex KO drum must
be traced and slope to KO drum.
30.10 Check mech. min. stops on fuel
control valves, if applicable.
30.11 Check that thermo-wells in
furnace outlet coils are not located too
close to the junction of the coils, since
otherwise a TW may give a false
indication of a coil flow (through
convection from other coil), whilst there
may not be any flow.
30.12 Non-return valves in outlet lines of
some Hydro-processing furnaces,
(minimize backflow upon tube rupture)
must be fire-resistant.
30.13 Check provisions for damper
failure (fail-safe, or min. stop).
30.14 Check purge/ignition timers of
automated ignition systems on
calculations/settings for their specific
actual conditions.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-88
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-89
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
30.15 Check that flame arrestors in
waste gas systems have been placed at
less than 60 pipe diameters from the
waste gas burner(s). No further block
valves are allowed downstream of a set
of parallel arrestors; a TA(H) should be
located just downstream of a flame
arrestor to warn against back-burning.
31 INSTRUMENTATION /CONTROL
VALVES
31.1 Check that, where needed,
emergency shutdown (ESD) or de-
pressuring (EDP) valves have a secure
instrument air supply, that they are in a
safe location and that they are fire-
resistant, incl. the secure instrument air
supply system, ref. DEP 32.45.10.1 0-
Gen. Check that EDP valves are
installed in the correct direction.
31.2 Emergency Shutdown (ESD) and
De-pressuring (EDP) valve stations
must be readily accessible for
maintenance and inspection.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-90
31.3 If for de-pressuring valves two
NDE solenoids are applied, per DEP
32.45 10.1 0-Gen, ensure that all other
specified electrical requirements on
cable routings and alarms on internal
solenoid circuits will be met. Check
cable routings.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-91
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
31.4 Check whether connections to
safeguarding instrumentation have
been steam-traced, where applicable.
31.5 Check installation details of critical
(instrument) back-flow protection
systems.
31.6 Check critical control/shutoff
valves for correct spring actions and
for possible lock-up systems and/or
minimum stops.
31.7 Trip valves must not be equipped
with bypasses or hand wheels, that
could override the trip action. ESD
valves may only have bypasses, if there
are other trip valves (without bypass)
further downstream.
31.8 Check testing frequency and
extent of instrument safeguarding
systems, incl. trip valves. Check if on-
line testing is possible for testing of
TSO trip valves in services, where
leakage of a TSO valve could cause a
potentially hazardous situation (e.g.
furnace fuel).
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-92
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
31.9 Level gauges in HP and LPG
service should be of a safe type,
preferably of the magnetic type. Level
glasses in class ANS 1500 service are
not allowed. Level gauges in LPG
service in a potential fire zone should
be of the magnetic type. In clean
service level glasses with excess flow
valves could possibly be applied as an
alternative, that could limit loss of
containment, should the glass break
when engulfed in a pool fire.
31.10 Wafer-type level connections and
control valves in potential pool fire areas
must be avoided. In some cases it may
be possible to fire-proof the bolting.
31.11 Ensure that visibility of a level
gauge from a drain point is not blocked
by the lighting facilities.
31.12 Level connections should be
drained to flare, if at all possible.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-93
31.13 Check that pneumatic remote-
operated valves can be opened at the
valve, as well as from a safe location
(see also 28.13).
31.14 Control valve stations should
have drains on both sides of the
control valve, if the valve is spring-to
close in corrosive or toxic service.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-94
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
31.15 Vent blocks for pressure gauges
and transmitter blocks should be fitted
with recessed vent valves, accessible
only by qualified personnel with a
special key.
31.16 Instrumentation should be
connected via proper instrument tubing
and not via screwed connections This
holds especially for those instrument
connections that are purged to keep the
instrument cool, since during purge
failure the Teflon sealing material may
melt.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-95
31.17 No 90 degree bends are allowed
in stainless steel instrument tubing
connected to the process (such as in
DP-cells), if H2S-induced stress
corrosion could occur.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-96
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
31.18 (Toxic) gas detectors (e.g. H2S
and HF) should be placed in 'strategic'
locations, either as a point or as area
detection system. For point detection:
within 2-4 m. from pump and
compressor seals, atm. vents and drains
and selected large control valves (e.g. in
high-H2S service), in less well-ventilated
areas. Not required for pumps with
double mech. seals and for compressors
with dry gas seals. The detectors should
be located at elevation 0.9-1.2 m. (not
lower, to avoid splashing by liquid or
rain).
31.19 Check location of gas detectors,
i.e. at floor level for heavier-than-air
gases and at high(er) level (i.e. near
ceiling in buildings, analyzer houses,
etc.) for light gases.
31.20 TP's (thermo-wells) should be
sealed with plastic caps/plugs to
prevent corrosion inside the well (TP's to
be part of regular inspection routines).
32 UTILITY SYSTEMS ( INCL. CONNECTIONS/PIPING)
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-97
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
32.1 Utility connections to be as per
standard arrangement; N2- and steam
connections should have check valves
and be spaded. Drain/vent connections
required for start-up steam supply
during warming-up. On vacuum
systems, the drain line must have a
check valve to minimize possible ingress
of air.
32.2 Check on presence of check valves
on drains in utility injection lines into a
vacuum system, if air ingress possible.
32.3 Small-bore cooling water lines
should be taken off the top of headers.
32.4 Nitrogen purge connections should
be hard-piped to systems that may
require frequent purging (e.g.
reciprocating compressors plus spares).
For non-regular connections a common
point (as per item 1 above) could be
installed from where dedicated N2-
hoses can be run to various purge
connections (with valve/blind).
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-98
32.5 Nitrogen should not be used as a
back-up system for Instrument Air.
Even if breathing air is not taken off the
IA system, (direct or via bottles) there is
always the danger that leaking
instruments/control valves in a poorly
ventilated space could cause an
asphyxiating atmosphere to develop.
Instrument air should not be used for
breathing air purposes.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-99
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up) 32.6 Relief valves on commercial
Nitrogen evaporators should never
relieve onto the supporting structure of
the evaporator, since this could
potentially cause brittle fracture of the
supports.
32.7 Drinking water must never be
connected to a process stream, other
than via a break tank or, e.g. in an
analyzer house, via taps. For
interconnections between drinking water
and industrial water, an alternative to a break system could be two check valves
with in between vent, provided there is
no danger of bacteriological
contamination.
32.8 Check that warm-up/start-up vents
on steam systems have silencers fitted.
32.9 Ensure that safety showers are
operable and in correct location.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-100
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
33 FLARE SYSTEMS AND ATM.
VENT SYSTEMS
Flare Systems:
33.1 This part (flare systems) includes
all relevant items from a 1993 Flare
Workshop, which resulted in a very
comprehensive check list, included in
this report (OP 99-30010) under separate tab: "Flare Reviews'.
33.2 Flare headers must not contain
pockets and must be sloping towards
the flare, with slope 1:200 in the plant
area and 1:500 in the off-plot area.
33.3 Eliminate low points in the flare
system, where possible. Any remaining
low points should be equipped with
preferably open line into KO vessel or
alternatively with an operational drain
the size of which should be DN 150 or
larger. If smaller or not free-draining,
there should be connections for purging
and clearing the line. Drain lines to be
winterized if applicable.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-101
33.4 Ensure that flare piping is well
supported and braced to handle liquid
slugs from liquid relief, particularly
near elbows and tees.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-102
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up) 33.5 Check on heat tracing or insulation
for dead parts of flare piping in colder
climates, since water will always collect.
33.6 Flare headers should not be routed
through high-risk areas, e.g. where a
pool fire could reach flare headers. In
existing units fire shielding could be
applied.
33.7 There should be no open drains,
vents, or instrumentation connections
on the flare piping, through which air
could be drawn in.
33.8 Spades and/or valves in flare lines are to be minimized and restricted to
plant isolation only. Valves to be locked-
open.
33.9 Check sterile area around flare
stack re. radiation heat load.
33.10 Check facilities for smokeless
combustion and specified vs. actual
max. noise level at max. smokeless
capacity at fence.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-103
33.11 Check that two pumps and high-
level alarms have been provided on Flare
KO vessels.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-104
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up) 33.12 Check that oil skimmed from seal
vessels can be routed properly to oily
sewer or direct to the oil compartment
of oil interceptors.
33.13 Check presence of video camera,
to monitor flame and smokeless
combustion.
Atm. Vent Systems:
33.14 Check the location of all atm.
vents, also with regard to installed
silencers. For personnel safety an atm.
vent should be at least 3 m. above the
highest platform in the neigh-bouring
area.
33.15 All atm. vents should have
facilities to prevent rain ingress.
Adequately-sized drain facilities to be
provided on silencers.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-105
33.16 For safe location vents fitted with
flame arrestors, check that the distance
from flame arrestor to vent outlet is no
longer than 60 pipe diameters; also that
the flame arrestor is accessible for
maintenance.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-106
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
34 ENVIRONMENTAL ASPECTS
(SUMMARY OF SECTIONS A-M)
34.1 Check possibilities for drainage into
oily sewer, incl. slopes and low points.
Spillages should not be allowed to
collect underneath equipment and
should thus be led away from
equipment.
34.2 Ensure hazardous/corrosive
liquids are contained in bunded areas
and that, where necessary, tiling has
been provided. Check also on proper
facilities for removal of such liquids.
34.3 Check site for personnel warning
signs on use of ear and eye protection.
All entries to areas with high-noise or
where toxic chemicals are handled,
should be clearly marked and/or fenced
off. Check that such areas are well away
from the plant fence.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-107
34.4 Check (correct) location of fire,
H2S and HC-gas detectors, beacons
and horns. They should be seen and
heard from all sections of the plant,
which are covered by these systems;
these sections should be well away
from the plant's fence (see also item
22).
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-108
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
34.5 Check for adequate equipment
protection facilities against exposure to
toxic materials, incl. fluids containing
over 20% v. benzene or n-hexane (e.g.
double seals, closed drains).
34.6 Check that operators, while
manipulating drain valves, can see the
emerging effluent as well as the level in
the vessel, that is being drained, whilst
keeping a safe distance in case of e.g.
drainage of H2S-containing liquids.
Provide tundishes if required.
Environmental aspects should not be
neglected (stench, etc.).
34.7 TV cameras should be considered
for a.o. remote monitoring of flares,
stacks and hazardous product handling
areas (e.g. TEL). This list is not all-
inclusive but for guidance only.
34.8 Check whether Waste Handling
Storage has good access, flooring and
roofing, suitable utility connections and
proper drainage to oily sewer.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-109
34.9 Piping should be able to be flushed
and drained easily. For regular drainage,
possibility for drainage to COC (oily
sewer) should be nearby.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-110
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
34.10 Check whether sampling points
are safe for personnel. Facilities should
be provided for mm. spillage during
sampling. i.e. closed loops or flush to
slops prior to sampling. Provide sealed,
e.g. DOPAK-type, sample connections for
fluids, which present a health hazard
(e.g. fluids with >5% v. benzene or rich
in n-hexane). Apply 'Strakman' type
sample valves in hot, viscous service,
instead of sample coolers.
34.11 Operational drains to atmosphere
should have two drain valves, the
downstream one being a spring-loaded
quarter-turn ball valve, in sight of the
level gauge and also in sight of - but at
a safe distance from -the actual drain
point. These drains should be lined up to
safe disposal system by hard-piping or
via tundishes.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-111
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
34.12 Liquid drainage from columns,
vessels, pumps, heat exchangers and
other equipment should be done with
min. environmental impact, i.e. to oily
sewer/COC. Those liquids that are
valuable or liquids with a potential
health hazard (e.g. liquids with >5%v.
benzene or rich in n-hexane) should be
drained to a closed collection system,
for recovery. Connections between
vessels and closed drain systems should
preferably be open to atmosphere with
sealed drain hubs. This prevents
syphoning flammable materials back
into the vessel Check valves may be
used, but may not prevent back-flow.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-112
34.13 Check area for suitability of
catalyst handling. If a Nitrogen blanket
must be provided on spent catalyst or
catalyst dust drums, ensure that the
drum lids are loose and cannot be
clamped shut. Ensure facilities allow for
min. dust emission. Check if specialized
contractors will be used for inert
operations/catalyst handling.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-113
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
34.14 For leak detection of very light
HC's into open cooling water channels,
outlet piping of coolers may be provided
with T-pieces, from which light HC's are
vented to safe location. HC detectors
can then be placed in the area of the
vents.
34.15 Check if contaminated seal oil
tanks for centrifugal compressors have
vent with flame arrestor and
(permanent) N2 purge connection on
the tank. Check safe location of
distance piece vents on reciprocating
compressors.
34.16 Check for proper operational
drains on pockets in large-bore suction
piping upstream of compressors, piped
to oily sewer, so that after a liquid
carry-over incident the line can be
drained quickly, prior to re-startup.
34.17 Check that compressor gas seals
purges are lined-up to flare.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-114
34.18 Check facilities for smokeless
combustion of flares and specified vs.
actual max. noise level at max.
smokeless capacity at fence.
34.19 Check that oil skimmed from water
seal vessels (e.g. in flare systems) can
be routed properly to oily sewer or direct
to the oil compartment of oil
interceptors.
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 8 Page A8-115
Pre-Startup Safety Review Checklist
Questions Notes and Percentage Compliance Action (Before/After Start-up)
34.20 Check presence of video camera,
installed to monitor smokeless
combustion ex flares and stacks and to
monitor flare flames.
34.21 Check the location of all atm.
vents, also with regard to installed
silencers. For personnel safety an atm.
vent should be at least 3 m. above the
highest platform in the neighbouring
area.
34.22 (Toxic) gas detectors (e.g. H2S
and HF) should be placed in 'strategic'
locations, either as a point or as area
detection system For point detection:
within 2-4 m. from pump and
compressor seals, atm. vents and drains
and selected large control valves (e.g. in
high H2S service), in less well-ventilated
areas. Not required for pumps with
double mech. seals and for compressors
with dry gas seals. The detectors should
be located at elevation 0.9-1.2 m. (not
lower, to avoid splashing by liquid or
rain).
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 9 Page A9-1
APPENDIX 9
SAMPLE OF APPOINTMENT LETTER FOR PASR TEAM LEADER
Pre-Activity Safety
Review
No.
Date
Name :
Job Title/ Indicator :
Activity :
Location :
You are hereby appointed as PASR TEAM LEADER to conduct PASR on the activity aforesaid to ensure planned activity is sufficiently reviewed before commencement.
Description of DUTY :
Identification of need for PASR
Register the planned activity with HSE department
Form a PASR Team for the planned activity
Conduct PASR at work site using appropriate checklist
Record findings and communicate with relevant parties
Implement preventive/ corrective action if any
Develop Process-Related Activities Procedure (PRAP)
Approval at a level appropriate for the risk (PCSB Risk Acceptance Criteria)
Close-out including communication to all involved parties
PASR data and reports to be submitted to HSE department for logging and filing
Issued and approved for and on behalf of PCSB Sabah Operations (SBO)
SIGNATURE :
NAME :
DESIGNATION :
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 10
Page A10-1
APPENDIX 10
PASR Log
Year No. PASR Number Location PASR Title PASR Phase 1
Date PASR Phase 1
Leader PASR Phase 2
Date PASR Phase 2
Leader Approval
Date
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 10
Page A10-2
PASR Number PASR Title Action Items Status of Action Items PASR Status Close-out Date Remarks
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 11
Page A11-1
APPENDIX 11
PASR PHASE 2 FORM
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 11
Page A11-2
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 11
Page A11-3
Pre-Activity Safety Review WW ALL S 04 010 Appendices Rev. 1, Dec 2010
PETRONAS CARIGALI SDN BHD APPENDIX 11
Page A11-4