  • WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI

    PERMIT TO WORK

    PROCEDURE

    PETRONAS CARIGALI SDN BHD

  • Permit To Work Procedure Main Table of Contents

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD MAIN TABLE OF CONTENTS Page i

    PERMIT TO WORK PROCEDURE

    Main Table of Contents

    Preliminary Foreword

    Distribution List

    Amendment Summary

    Abbreviations and Acronyms

    Referenced Documents

    Section 1 Introduction

    Section 2 Roles and Responsibilities

    Section 3 Permit to Work Application Process

    Section 4 Certificates

    Section 5 Work and Activities Management

    Section 6 Training

    Section 7 Inspection & Auditing

    Appendices Appendix 1 Sample of Appointment Letter

    Appendix 2 PTW and Certificates

    Appendix 3 Steps for Filling-up PTW and Certificates

    Appendix 4 Template for PTW Logbook

    Appendix 5 PTW Sample Assessment Questions

    Appendix 6 PTW Daily Audit Checklist

    Appendix 7 PTW Weekly/Quarterly Audit Checklist

    Appendix 8 PTW 6-Monthly Audit Checklist

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page ii

    FOREWORD

    Authority for Rev. 4 issue

    Issue Approval

    Document Custodian

    The following person has been assigned as the document custodian:

    Name Haslina Bt Abdullah

    Reference Indicator Head

    Position Head, Operations Integrity

    Proprietary Information

    This document contains proprietary information belonging to

    PETRONAS Carigali Sdn Bhd and must not be wholly or partially reproduced nor

    disclosed without prior permission from PETRONAS Carigali Sdn Bhd.

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page iv

    DISTRIBUTION LIST

    Copy No. Title Location

    01 President, PCSB and CEO PDP MD – KL

    02 Vice President PETRONAS and CEO PEX PEX – KL

    03 DGM DD – KL

    04 DR DD – KL

    05 DRD (HSE) DD – KL

    06 DFE DD – KL

    07 DPP DD – KL

    08 DRMB DD – KL

    09 P&E DD – KL

    10 DHSE DD – KL

    11 FIN MD – KL

    12 EPHSE MD – KL

    13 HRM MD – KL

    14 PED MD – KL

    15 PED (HSE) MD – KL

    16 SCM MD – KL

    17 CAA MD – KL

    18 SP MD – KL

    19 TIM MD – KL

    20 PM (CHO) MD – KL

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page iv

    21 PD PMO

    22 PSE PMO

    23 SD SBO

    24 SSE SBO

    25 BD SKO

    26 BSE SKO

    27 PI (CHO) MD – KL

    28 MO MO

    29 MO (HSE) MO

    30 VO VO

    31 VO (HSE) VO

    32 INO INO

    33 INO (HSE) INO

    34 UO (HSE) UO

    35 TO TO

    36 TO (HSE) TO

    37 IRQ IRQ

    38 IRQ (HSE) IRQ

    39 XMAS PEX – KL

    40 XSK PEX – KL

    41 XSB PEX – KL

    42 XPM PEX – KL

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page iv

    43 XINT PEX – KL

    44 XAFR PEX – KL

    45 XATL PEX – KL

    46 XSEAN PEX – KL

    47 XSEAS PEX – KL

    48 XMEA PEX – KL

    49 BIE

    SKO

    50 BIE6

    SKO

    51 BRM

    SKO

    52 BTA

    SKO

    53 BWI

    SKO

    54 IO Iraq

    55 OE KL

    56 PDP KL

    57 PI KL

    58 PIE PMO

    59 PIE6 PMO

    60 PM KL

    61 PRM PMO

    62 PTA PMO

    63 PWI PMO

    64 SIE SBO

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page iv

    65 SIE6 SBO

    66 SRM SBO

    67 STA SBO

    68 SWI SBO

    69 XTS PEX – KL

    70 XGO PEX – KL

    71 XGP PEX – KL

    72 XGM PEX – KL

    73 XBD PEX – KL

    74 XPL PEX – KL

    75 XHSE PEX – KL

    76 XHR PEX – KL

    Note to All Copy Holders: Should you are transferred to other OPU, or should it be impractical for you following your move to a new position, please return this manual to the Custodian. The Custodian will make arrangement for re-distribution.

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page v

    AMENDMENT SUMMARY

    The Permit to Work Procedure shall be revised every three (3) years or earlier should there is change in relevant regulation, PETRONAS Technical Standard and/or findings arising from assurance exercise and incident investigations. This sheet must be completed in detail at each revision once this document has been approved. Details must include revision number, description and indication of which pages and paragraphs have been revised, date of revision approval, approvers title and signature.

    Rev Description Date Approver Title Signature

    2 Inclusion of: 1. PTS 60.2001

    PETRONAS Group Guidelines for Permit to Work System

    2. PTS 60.2102 Recommendation of Electrical Safety (Standard)

    3. PTS 60.2212 Bypassing of SCE

    4. PTS 60.2117 Energy Isolation Standard

    Sep 2011 Head HSE Division

    Saifuddin Shah B Sowkkatali

    3

    Inclusion of: 1. Requirement of Hot

    Work in Hazardous Zone

    2. Roles and Responsibilities of Contractors Management and Individual Working Under the PTW

    3. Improvement to permits and certificates

    4. Diving of Certificate

    Dec 2012 Head HSE Division

    Saifuddin Shah B

    Sowkkatali

    4 Minor amendment to the permits and certificates

    July 2013 Head

    HSE Operations

    Hamadi B Tani

    Notes: (1) Document Holders to update Amendment Record as and when amendments/new

    revisions are received.

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page v

    (2) For description of amendment the Document Holder should indicate correction,

    modification, update or deletion issue. (3) Document Holder to enter their company reference number, sign and date the

    record of entry. (4) Where part amendments are issued, the relevant page(s) will be identified with a

    lower case letter in the revision status line in the header.

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page vi

    ABBREVIATIONS AND ACRONYMS

    The abbreviations and acronyms used in this document shall have the following meaning: Applicant/RA

    The person who applies for the PTW e.g. the foreman/ supervisor responsible for planning and execution of the work. The Permit Applicant can also be the Receiving Authority (RA). The Permit Applicant shall be responsible for the following:

    discusses work with Work Leader (WL) and Authorised Supervisor (AS)

    specifies location and work description

    specifies tools and equipment

    specifies known hazards and hazardous activities

    Appointed Person (AP)

    The person trained for certain duties (e.g. isolation/de-isolation of electrical equipment, synchronising, etc.) and has sufficient technical knowledge and experience to enable him to avoid danger.

    Approving Authority (AA)

    The person who is responsible for approving the PTW and shall ensure all precautions are specified and controls in place. He carries the overall responsibility for the facility and all work carried out. His responsibilities among others includes:

    assign Authorised Gas Tester (AGT) and other required competent persons

    approves/revalidates PTW

    receives PTW handback

    specifies controls/precautions for safe work

    specifies other Certificates

    Areas of the facilities assigned to the Approving Authority (AA) shall be clearly defined to ensure clear boundary of authority is set covering all areas of the facilities. There shall be no overlap between Approving Authority (AA). Where a PTW is required to cover work in more than one area it shall be approved by all the respective Approving Authority (AA).

    The Approving Authority can be an Offshore/Onshore Installation Manager, Terminal Superintendent, Warehouse Manager or any person authorized by PETRONAS Carigali.

    Approving Authority Representative (AAR)

    The person authorised by the Approving Authority (AA) to carry out safety precautions prescribed in the PTW/Certificates prior to commencement of work.

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page vii

    Authorised Competent Person (ACP)

    The person registered with Energy Commission or equivalent local authority and authorised by Management. He has sufficient technical knowledge and experience to enable him to avoid danger and who can have authority delegated to him, according to his knowledge and experience to carry out operations in power systems and work on electrical equipment. He has the authority to issue and cancel Electrical Isolation Certificate and Limit of Electrical Access on Electrical Equipment/System.

    Authorised Supervisor (AS)

    Supervisor authorised by PETRONAS Carigali Management to endorse PTW. The Authorised Supervisor shall be a Production Supervisor or Operation Supervisor. In the event the Production Supervisor or Operation Supervisor is not on site, the Maintenance Supervisor or any person authorised by the Approving Authority can take the role of the Authorised Supervisor.

    Authorised Gas Tester (AGT)

    A person who is trained and qualified to carry out gas testing. The AGT should attend training provided by PETRONAS Carigali recognised training organisation. For countries that impose legal requirements on AGT, such requirements shall be complied with e.g. in Malaysia, the AGT for confined space entry shall meet requirements set by Department of Occupational Safety and Health (DOSH) Malaysia Code of Practice.

    Certificate Written and signed statement that specified checks or tests have been carried out by an authorized person and that conditions are acceptable. Certificates do not replaced the PTW but are complementary.

    Hot Work

    Hot work is any work where heat is used and generated. Example of hot work are :

    Welding, flame cutting, grinding, grit/sandblasting, etc (positive ignition sources)

    any work which may generate incentive sparks or other sources of ignition e.g. taking of photograph using camera with flash, use of non-intrinsically safe equipment, including opening of junction boxes etc (potential ignition sources).

    Cold Work Any work other than hot work defined above.

    Example of cold work:

    Erect/dismantle of scaffolding

    Housekeeping etc.

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page viii

    Confined Space An enclosed or partially enclosed space that is at atmospheric pressure during occupancy and is not intended or designed primarily as a place of work, and is liable at any time to have an atmosphere which contains potentially harmful levels of contaminants; have an oxygen deficiency or excess; or cause engulfment; and could have restricted means for entry and exit.

    Display Board A board which displays all active work permits at an installation/facility. It is normally located in the main operations control room.

    Gas Testing

    Gas testing is done to check a workplace, prior to the commencement and during work activities for the level of oxygen, flammable and toxic gases. This is to alert personnel involved should the environment become dangerous.

    Hazard Assessment

    An evaluation of the potential hazards, their severity and likelihood associated with any work activity.

    Isolation A physical barrier between a source of energy and a place of work.

    Job Hazard Analysis (JHA) Job Hazard Analysis (JHA) is the application of the hazards and effects management process at the task level, identifying and assessing the hazards of each element of the task and defining appropriate controls and recovery measures.

    Override/Bypass The temporary bypass of a safety device, to allow certain work to proceed without causing an unnecessary process shutdown or fire alarm (e.g.) fire detectors overridden during welding operations.

    Personal Protective Equipment (PPE)

    Equipment, clothing or devices used to protect employees from potential hazards that are or may become present during a job task.

    Potential Hazard An event, circumstances or condition, if not controlled, has the potential to harm personnel, environment, asset or reputation.

    Precautionary Measures Preventative and contingency steps taken to ensure a work site safe and to prepare for emergencies.

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page ix

    Radiation Protection Officer/Supervisor (RPO/RPS)

    The Radiation Protection Supervisor/Radiation Protection Officer (RPS/RPO) is a person with the technical competency and approved by Atomic Energy Licensing Board to supervise the implementation of the radiation protection programme including all the appropriate radiation protection regulations, measures and procedures.

    Toolbox Talk

    A safety briefing carried out by the Work Leader (WL) highlighting to all those directly or indirectly involved in the work of the potential hazards associated with the work and the precautions to be taken throughout the execution of the work. Carried out before work begins, preferably at the worksite.

    Validity The period of time (as defined) during which an approved document such as the PTW, Certificate and other documents in this PTW system is valid for its intended purpose.

    Work Leader (WL)

    The person who leads or carries out the work:

    confirms conditions of PTW and agreement by signing

    explains Job Hazard Analysis (JHA) content and PTW conditions to workers

    supervises and is at site at all times

    ensures no deviation to PTW conditions

    returns PTW to Receiving Authority (RA)

    ensure all the safety precautions prescribed in the PTW/Certificates are carried out prior to commencement of work

    Work Crew

    A group of people working together led by the Work Leader (WL).

    PTW Written and signed statement by an authorized person for work to be carried out under stated precautions.

  • Permit To Work Procedure Preliminary

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD PRELIMINARY Page x

    REFERENCED DOCUMENTS

    Doc. No. Title JKKP DP(S) 127/379/3-1 Industry Code of Practice for Safe Working in a

    Confined Space PTS 18.5101 PETRONAS Group Guidelines for Permit to Work

    System PTS 18.5205 Electrical Safety Rules PTS 18.5226 Guideline Bypassing of Safety Critical Equipment PTS 18.5219 Energy Isolation Standard PTS 18.5218 Excavation WW ALL S 05 003 PETRONAS Carigali Confined Space Entry Procedure WW ALL S 04 018 PETRONAS Carigali Energy Isolation Guideline WW ALL S 04 019 PETRONAS Carigali Bypass of SCE Equipment

    Guideline WW ALL S 04 012 PETRONAS Carigali Job Hazard Analysis Guideline

  • Permit To Work Procedure Introduction

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 1 Page 1

    SECTION 1

    INTRODUCTION

    Contents

    Paragraph Page No.

    1 INTRODUCTION 2

    1.1 Purpose 2

    1.2 Scope 2

    1.3 Permit to Work Requirement 2

    1.4 Hot work in Non-Hydrocarbon Facilities 5

    1.5 Hot Work in Hazardous Area 5

  • Permit To Work Procedure Introduction

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 1 Page 2

    1 INTRODUCTION

    1.1 Purpose

    This Procedure defines PETRONAS Carigali Permit to Work (PTW) system and the process of obtaining work permits including the requirements of obtaining Certificates where required.

    1.2 Scope

    The requirements defined in this procedure shall be applicable for all hazardous activities carried out at all work locations throughout PETRONAS Carigali global operations, including Contractors and Sub-Contractors engaged for work on Company facilities. Hazardous are activities that have been identified by the Hazards and Effects Management Process as vital to ensure asset integrity, prevent incidents, and/or mitigate adverse HSE effects. Examples of hazardous activities are pigging, production sampling, wireline activities, blasting, welding, etc.

    1.3 Permit to Work Requirement

    (1) The purpose of PTW system is to ensure that risks associated with work activities are managed to a level that is as low as reasonably practicable (ALARP). The PTW is a written document authorizing persons to carry out the work concerned, warning them of possible hazards and spelling out precautions needed for the job to be done safely.

    (2) Listed below is the criteria for the application of PTW

    system:

    (a) For work carried out on PETRONAS Carigali facilities, PETRONAS Carigali PTW System shall be used;

    (b) For work carried out on Contractor’s facilities,

    Contractor’s PTW may be used subject to PETRONAS Carigali review and acceptability. When Contractor PTW system is used, PETRONAS Carigali representatives (e.g. OIM, Terminal Manager, CSR, Drilling Supervisor) shall be included as part of the signatory parties for acknowledgement.

  • Permit To Work Procedure Introduction

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 1 Page 3

    (3) For workover/infill drilling work carried out on the rig

    floor, where Contractor’s PTW is applied, a photocopy of the Contractor’s PTW shall be provided to the OIM for reference.

    (4) As a general principle, PTW shall be applied for all

    activities which may harmfully affect the personnel, environment, asset or reputation carried out on PETRONAS Carigali facilities. The examples of work that requires PTW among others are as follows:

    (a) Hot Work: Any activities or equipment which

    may have the potential to generate incentive sparks or other sources of ignition such as welding, flame cutting, grinding, grit/sandblasting, taking of photograph using camera with flash, use of non-intrinsically safe equipment, including opening of junction boxes etc. (potential ignition sources). Refer to sub-section 1.5 for details of hot work requirement in hazardous area;

    (b) Cold Work: Any activities or equipment which

    does not have the potential to generate sparks such as erecting/dismantling of scaffolding, cold cutting, etc;

    (c) Work in confined space i.e. Any enclosed or

    partially enclosed space, either above or below ground or deck level, where entry is possible and where accumulation of dust or gases which are flammable or hazardous to health;

    Examples of confined space are:

    (i) Process vessels and related equipment

    (vessel tower skirt and flare stacks), boilers;

    (ii) Cooling tower, pipe, storage tanks, other

    tanks including pontoon in floating roof tanks;

    (iii) Spaces located below ground or deck

    level, such as drain pits, sewage pits and associated tunnels, ducts, trenches, wells, shafts, cellars, vaults and unventilated rooms which may be considered confined space under specific circumstances;

    (iv) The cargo, ballast or void space onboard

    ship; and

  • Permit To Work Procedure Introduction

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 1 Page 4

    (v) The support columns/legs/pontoons of

    fixed or mobile off-shore installations.

    (d) Excavation work of the ground in excess of 150mm (brownfield);

    (e) Mechanical lifting activities involving pedestal,

    mobile and gantry crane. Lifting using gantry crane in workshop may be carried out without a PTW;

    (f) Radiation work involving the handling of

    radioactive materials such as radiography works, working in or on equipment containing radioisotopes and removing or servicing radioisotopes;

    (g) Closure of any road that may affect the passage

    of emergency response vehicles; (h) Electrical works in close proximity to live

    conductors/equipment/apparatus,or testing of live voltage conductors;

    (i) Diving activities e.g. inspection and

    maintenance of subsurface structures, decommissioning of facilities, etc.;

    (j) Work with bypass of safety critical equipment

    that may jeopardise reliability of process control;

    (k) Work requiring energy isolation e.g. physical, electrical or radiation; and

    (l) Vehicle entry into PETRONAS Carigali

    production facilities. (5) For work which requires Certificates, the Work Permit

    shall be supplemented with the required Certificates.

    (6) In cases of doubt as to whether a work activity requires a PTW, the PTW requirement shall be complied with if deemed necessary by the Approving Authority.

  • Permit To Work Procedure Introduction

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 1 Page 5

    1.4 Hot work in Non-Hydrocarbon Facilities

    (1) Non-hydrocarbon facilities are facilities that do not process, store or operate hydrocarbon or any flammable materials in its facilities. Examples of non-hydrocarbon facilities are supply base, office, base camp, fabrication yard, etc.

    (2) For hot work at non-HC facilities, the work may be carried out without conducting gas test in view that there is no expected presence of HC in the area.

    (3) However, other controls and recovery measures in

    making safe the activity shall still be implemented.

    1.5 Hot Work in Hazardous Area

    (1) Hazardous area are defined as below (based on IP

    Model Code of Safe Practice Part 15): Zone 0: Hazardous area in which a

    flammable atmosphere is continuously present or present for a long period

    Zone 1: Hazardous area in which a flammable atmosphere is likely to occur in normal operation.

    Zone 2: Hazardous area in which a flammable atmosphere is not likely to occur in normal operation and if it occurs will exist only for a short period.

    Non- classified/ hazardous area

    Area where flammable vapours, liquids or gas do not or are not expected to exist

    Hierarchy of Hot Work Management

    (1) Where possible, hot work should not be carried out in hazardous area.

    (2) However, if the hot work is unavoidable, the next preference is to shutdown, depressurise and render hydrocarbon-free. This is to minimize the potential source of fuel that may be ignited by the spark produced from the hot work activities.

  • Permit To Work Procedure Introduction

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 1 Page 6

    (3) The requirements for carrying out hot work in hazardous area are as follows:

    Zone Limitations

    Zone 0 No hot work on live facility shall be allowed, unless the facility is shutdown, depressurise and render hydrocarbon-free.

    Zone 1 For open flame hot work e.g. oxy cutting, grinding, etc., the facility shall be shutdown, depressurise and render hydrocarbon-free prior proceeding with hot work.

    For blasting, the activity shall only proceed after conversion of instrument gas to instrument air, flanges are wrapped and the area is barricaded

    Note: For blasting on process piping where the remaining wall thickness is less than the corrosion allowance, the piping/equipment shall be shutdown prior blasting.

    Non-open flame/non-blasting hot work e.g. use of portable hand-held non-intrinsically safe (non-Ex) equipment in Zone 1 area may proceed with implementation of other control and recovery barriers

    Zone 2 Open flame hot work on live facility shall only proceed with use of Pressurised Habitat

    For blasting, the activity may only proceed after conversion of instrument gas to instrument air, flanges are wrapped and the area is barricaded Note: For blasting on process piping where the remaining wall thickness is less than the corrosion allowance, the piping/equipment shall be shutdown prior blasting.

    Non-open flame/non-blasting hot work e.g. use of portable hand-held and mobile non-intrinsically safe (non-Ex) equipment e.g. mobile genset, mobile air-compressor, etc. in Zone 2 area may proceed with implementation of other control and recovery barriers.

  • Permit To Work Procedure Introduction

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 1 Page 7

    Non-classified/ hazardous/ safe area

    Hot work may be allowed with the conduct of gas testing and implementation of other required control and recovery barriers identified in risk assessment

    (4) Additionally, a rigorous risk assessment shall also be

    conducted for all hot work activities to identify any other control and recovery barriers to ensure the risks associated with the work is minimised to ALARP.

    (5) Regular gas testing at site shall be carried out for any

    hot work activity.

    Note: Gas test at start of shift or activity only is not

    acceptable. AGT has the authority to withdraw a PTW if condition is deem unsafe.

    (6) For facilities equipped with fixed gas detectors, the

    gas detectors shall not be bypassed during the hot work activities.

    (7) For hot work inside confined space, in addition to the

    hot work requirement, the confined space entry requirement (e.g. medical declaration, CSE training, etc) shall be fully complied with.

    (8) The process to allow the hot work activities to be

    conducted on ‘live’ facility is summarized as Figure 1 and 2 below.

    (9) For hot work in confined space, the conduct of the

    work shall comply with WW ALL S 05 004 PETRONAS Carigali Confined Space Procedure.

  • Permit To Work Procedure Introduction

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 1 Page 8

    Need to conduct hot work on ‘live’

    facility in Zone 1

    Open-flame hot

    work?Blasting (grit/ganite)?

    Process piping/

    equipment?

    Corrosion > corrosion

    allowance?

    Non-open flame/Non-blasting

    Convert instrument gas to

    instrument air, wrap flanges

    and barricade the area

    Shutdown and blowdown

    Conduct activity risk

    assessment

    Implement control/recovery

    barriers

    Proceed with Hot Work

    End

    Start

    No No

    No

    No

    Yes

    Yes

    Yes

    Yes

    Figure 1: Decision tree for hot work activities in Zone 1

  • Permit To Work Procedure Introduction

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 1 Page 9

    Start

    Need to conduct hot

    work on ‘live’ facility in

    Zone 2

    Open-flame hot

    work?

    Blasting (Grit/

    ganite)?Non-open flame/Non-blasting

    Conduct risk

    assessment and

    Implement Pressurised

    Habitat

    Process piping/

    equipment?

    Corrosion >

    corrosion

    allowance?

    Convert Instrument gas to

    Instrument air, wrap flanges and

    barricade the area

    Shutdown and Blowdown

    Conduct activity risk assessment

    Implement control/ recovery

    barriers

    Proceed with hot work

    End

    NoNo

    Yes Yes

    Yes

    Yes

    No

    No

    Figure 2: Decision tree for hot work activities in Zone 2

  • Permit To Work Procedure Roles and Responsibilities

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 2 Page 1

    SECTION 2

    ROLES AND RESPONSIBILITIES

    Content

    Paragraph Page No.

    1 ROLES AND RESPONSIBILITIES 2

    1.1 Permit Signatories 2

    1.2 Contractors Management 7

    1.3 Other Competent Personnel 7

    1.4 Roles and Responsibilities at Remote Facilities 8

  • Permit To Work Procedure Roles and Responsibilities

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 2 Page 2

    1 ROLES AND RESPONSIBILITIES

    The following are the key roles and their responsibilities in PTW. Personnel who are assigned to these roles as per the PTW Signatory Matrix below shall have completed the required training and passed the required assessment. PTW Signatory Matrix Signatories Personnel

    Approving Authority (AA) Offshore/Onshore Installation Manager (OIM)

    Authorised Supervisor (AS) Operations Supervisor/Maintenance Supervisor/Senior Technician/Technician

    Approving Authority Representative

    Senior Technician/Technician

    Applicant/Receiving Authority Competent PETRONAS Carigali/Contractors’ Personnel

    Work Leader Competent PETRONAS Carigali/Contractors’ Personnel

    To ensure there is no conflict of roles, there must be a minimum of two distinct responsibility. The person who applies for the permit shall not be the same person as the one who shall approve this permit.

    1.1 Permit Signatories

    Applicant/Receiving Authority (RA)

    Applicant/Receiving Authority shall be the person who will be directly involved with the work. He/she shall be responsible in the execution, planning and supervising of the work. The Applicant/Receiving Authority (RA) shall be responsible for:

    (1) Describing in detail on the work activity, including the

    tools and equipment to be used, number of workers involved, equipment/location of the work;

    (2) Completing a JHA specifying hazards and precautions to be taken;

    (3) Preparation of worksite, ensuring implementation of

    all identified control and recovery barriers;

    (4) Job is thoroughly discussed with the Authorised Supervisor (AS) and/or Approving Authority (AA);

  • Permit To Work Procedure Roles and Responsibilities

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 2 Page 3

    (5) The PTW top copy is displayed at the work site and

    the workers briefed on the PTW including any potential hazards and the precautions taken or to be taken;

    (6) The precautions shall be complied throughout the work activity;

    (7) The workers shall be made to understand that if circumstances change, work shall stop and advice sought;

    (8) Ensure that the scope of work in each PTW is limited to a single job;

    (9) Ensure that the workers stay within the work limitations as defined in the PTW; and

    (10) On completion or suspension of the work, the site is kept in a safe condition and the AS and/or AA shall be duly informed.

    An Applicant/Receiving Authority may be Company or Contractor personnel. He/she shall have completed a three days PETRONAS Carigali PTW Certification Training including passing the required PTW assessment. The Applicant/Receiving

    Authority shall be formally appointed through issuance of

    appointment letter or approved list of Applicant/Receiving

    Authority signed by Contract Holder or OIM.

    Note: To prevent an RA from applying too many work permits, either for himself or on behalf of other work teams, the RA should discuss the number of permit allowed to be applied with the Approving Authority.

    Work Leader (WL)

    The Work Leader (WL) is responsible for planning and supervising the safe execution of the work. The Work Leader may also be the Applicant/Receiving Authority (RA). The WL shall:-

    (1) Confirm the site conditions is safe for work execution

    as required by the PTW and certificates and agree by signing;

    (2) Brief the workers on JHA and PTW requirements;

    (3) Supervise the work and remain at the work site at all

  • Permit To Work Procedure Roles and Responsibilities

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 2 Page 4

    times;

    (4) Ensure that the scope of work in each PTW is limited to a single job;

    (5) Conduct joint site inspection at the work site with the

    AAR prior to approval of the PTW;

    (6) Ensure there is no deviation from any condition as defined in the PTW. The WL may take on the additional responsibilities as an RA when deemed necessary; and

    (7) Return the PTW to RA upon completion of work.

    A Work Leader (WL) shall have completed a three days PETRONAS Carigali PTW Certification Training including passing the required PTW assessment. The Work Leader shall be formally appointed through issuance of appointment letter or approved list of Work Leader signed

    by Contract Holder or OIM. Note 1: Preferably WL is the RA for the work. But in the absence of WL, anybody who is involve with the work and has completed the PTW Certification Training should be the RA. Note 2: To prevent ineffective work supervision, the WL should discuss the number of work to be supervised with the Approving Authority.

    Approving Authority Representative (AAR)

    The Approving Authority Representative (AAR), who will be appointed among the authorised AAR by the Authorised Supervisor (AS), is responsible for the roles and responsibilities assigned by AA which may include one or more of the followings:

    (1) All hazards associated with the job are identified and

    risks have been reduced to as low as reasonably practicable;

    (2) The authorized work does not endanger other ongoing operations in the facility;

    (3) Physically mark/barricade and place tag on the

    items/equipment to be worked onsite;

    (4) Other permits/work activities that may interact are cross-referenced;

  • Permit To Work Procedure Roles and Responsibilities

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 2 Page 5

    (5) Verify implementation of all control stated in all supporting certificates and ensure that the certificates as well as relevant documents are attached and made known to all concerned parties;

    (6) All the required equipment and PPE are adequate for

    completion of work safely;

    (7) Effective communication to ensure that the work site is inspected before work begins, suspended and on completion;

    (8) Effective handover for outstanding work after each

    shift/crew change; and

    (9) The list of authorised PTW signatories is regularly updated.

    AAR shall have completed a three days PETRONAS Carigali PTW Certification Training including passing the required PTW assessment. The Approving Authority Representative (AAR) shall be formally appointed through issuance of appointment letter or approved list of AAR

    signed by the OIM.

    Authorised Supervisor (AS) The person assigned as Authorised Supervisor (to be appointed by AA e.g. Production Supervisor, Maintenance Supervisor, CSR, etc.) shall ensure all precautions are specified, controls in place, and work is performed in a safe and efficient manner. The AS may also be the AA upon approval from respective management. Before endorsing the PTW, the AS shall verify and ensure the following:-

    (1) All hazards associated with the job are identified and

    risks have been reduced to as low as reasonably practicable;

    (2) The authorized work does not endanger other

    ongoing operations in the facility; (3) Verify that all work preparation such as energy

    isolation/ lockout-tagout have been completed and the applicable certificates have been approved;

    (4) Other permits/work activities that may interact are

    cross-referenced;

  • Permit To Work Procedure Roles and Responsibilities

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 2 Page 6

    (5) Endorse all supporting certificates and ensure that

    the certificates as well as relevant documents are attached and made known to all concerned parties;

    (6) All the required equipment and PPE are adequate for

    completion of work safely; (7) Appoint AAR from among the Authorised AAR for the

    work to be responsible in physically verifying the worksite preparations;

    (8) Effective communication to ensure that the work

    site is inspected before work begins, suspended and on completion;

    (9) Effective handover for outstanding work after each

    shift/crew change; and

    (10) The list of authorised PTW signatories is regularly updated.

    AS shall have completed a three days PETRONAS Carigali PTW Certification Training including passing the required PTW assessment. The AS shall be formally appointed through issuance of appointment letter signed by the PETRONAS Carigali Management e.g. Head of Country/Region.

    Approving Authority (AA)

    The person responsible for approving the work permit, shall ensure all precautions are specified, controls in place, and work is performed in a safe and efficient manner.

    Before approving the Permit to Work, this person shall verify and ensure the following:-

    (1) All hazards associated with the job are identified and

    risks have been reduced to as low as reasonably practicable;

    (2) The authorized work does not endanger other ongoing operations in the facility;

    (3) The Approving Authority Representative (AAR),

    delegated by AA, is competent and aware of the conditions as stated in the Permit/Certificate and to implement precautions prior to start of work;

    (4) Other permits/work activities that may interact are

    cross-referenced;

  • Permit To Work Procedure Roles and Responsibilities

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 2 Page 7

    (5) Approve all supporting certificates and documents

    are attached and made known to all concerned parties;

    (6) All the required equipment and PPE are adequate for

    completion of work safely;

    (7) Communicate personally with the Applicant/RA on the contents and requirements of the PTW prior to hand-over of the permit and work execution;

    (8) Effective communication to ensure that the work site

    is inspected before work begins, suspended and on completion;

    (9) Effective handover for outstanding work after each

    shift/crew change; and

    (10) The list of authorised PTW signatories is regularly updated.

    AA shall have completed a three days PETRONAS Carigali PTW Certification Training including passing the required PTW assessment. The AA shall be formally appointed through issuance of appointment letter signed by the PETRONAS Carigali Management e.g. Head of Country/Region.

    Refer to Appendix 1 for sample of the appointment letter.

    1.2 Contractors Management

    Contractor’s Management shall ensure all their employees:

    (1) Have undergone PETRONAS Carigali PTW awareness training and/or PETRONAS Carigai Certification Training (for signatories only);

    (2) Understands PETRONAS Carigali PTW system; and

    (3) Are qualified and competent to execute the respective duties as per contract requirement.

    1.3 Individuals Working Under the Permit/Certificates

    Individuals working under the permit/certificate, including contractors shall ensure that:

    (1) They have received PTW awareness training/instruction and have a good understanding of

  • Permit To Work Procedure Roles and Responsibilities

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 2 Page 8

    the PTW system;

    (2) They do not start any work requiring a permit/certificate until it has been properly authorised and issued;

    (3) They have received a briefing from the Work Leader (WL) on the particular task and understand the hazards and the precautions including those stipulated on Job Hazard Analysis (JHA) to ensure safe execution of the activities;

    (4) Full compliance to the instructions/conditions specified in the permit/certificate;

    (5) If in doubt, or if circumstances change, they shall stop work and consult their Work Leader (WL);

    (6) When the work is stopped, make safe the site and the equipment; and

    (7) The worksite is restored to its normal condition upon completion of work.

    1.4 Roles and Responsibilities at Remote Facilities

    When on a remote facility, the Approving Authority may delegate his roles and responsibilities to an Authorised Supervisor/AAR. The Authorised Supervisor may also delegate his roles and responsibilities to an AAR. The Applicant/Receiving Authority and the Approving Authority/Authorised Supervisor/Approving Authority Representative shall not be the same person.

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 1

    SECTION 3

    PERMIT TO WORK APPLICATION

    Content

    Paragraph Page No.

    1 PERMIT TO WORK APPLICATION PROCESS 2

    1.1 PTW Application And Site Preparation 2

    1.2 PTW Application and Site Preparation for Cold Work 5

    1.3 Work Execution 7

    1.4 Work Completion 8

    1.5 Permit to Work Validity 13

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 2

    1 PERMIT TO WORK APPLICATION

    (1) Application of permit via PTW system is required for

    all hazardous activities which may have the potential to cause harm to personnel, environment, asset or reputation.

    (2) PETRONAS Carigali PTW System utilises two permit forms (A3) for both cold work and hot work.

    (3) During permit application, the mandatory sections to

    be filled for both cold and hot work are Section 1-7 of the permit. Additionally, it is also mandatory to fill in Handback Section of the permit upon completion of work.

    (4) For hot work, the additional sections that are

    mandatory to be filled are Type of Hot Work Allowed and Hot Work Precautions in Section 1 and Section 3 of Hot Work Permit.

    (5) The extension of cold work, Section 9 of the cold work

    permit shall be filled in where it requires authorisation and approval from WL, AAR, AS and AA.

    (6) For extension of wireline operations activities, Section

    8 of the cold work permit shall be filled in where it requires daily endorsement from WL, AS and AA.

    Template for permit form is shown in Appendix 2 and detail steps-by-steps instruction to fill in the permit is mentioned in Appendix 3.

    1.1 PTW Application and Site Preparation for Hot Work

    (1) The Applicant/RA fills in Section 1 to 4 of the PTW with the details of the hot work to be done, specifying the exact location and the tools to be used. Additionally, the Applicant/RA shall identify type of hot work and additional precautions for the hot work activities in Section 1 and 3 respectively.

    (2) The Applicant/RA shall also attach together with the PTW the required certificates, JHA and other documents related to the work. In addition, it is also expected for the Applicant/RA to identify the hazards, precautions and Personal Protective Equipment (PPE) with respect to the work.

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 3

    (3) The Applicant/RA shall then discuss on the work with

    the Work Leader (WL) and Authorised Supervisor (AS) to ensure the correct work scope as well as determination of hazards, precautions and PPE. In addition, the hazardous area classification shall also be confirmed by the AS to ensure the correct precautions are in place.

    Note: For work that is conducted by Contractors where the Company Site Representative (CSR) is at site (e.g. drilling, diving, construction, etc.), the Applicant/RA shall discuss the work scope, hazards and control/recovery barriers required for the work with the CSR prior meeting the AS.

    (4) The AS shall also verify that the JHA is communicated

    to all personnel involved in the work during the toolbox meeting. The AS shall then approve the JHA.

    (5) Additionally, where required, the AS shall propose additional precautions in minimizing the risk associated with the work to ALARP. If the nature of the work requires gas testing, i.e. hot work on hydrocarbon facilities, AS shall organise the gas tests to be carried out by an Authorized Gas Tester (AGT).

    (6) For hot work and work in confined space, the AS shall determine the frequency of gas testing in the designated column of the Hot Work Precautions, Confined Space Certificate and Gas Test Form.

    (7) The AS will verify the submission of certificates and identify the need for other certificates. The certificates number shall be recorded in Section 5 of the PTW form.

    (8) After site preparation is completed, joint site visit shall

    be carried out before commencement of work by the AAR, together with Applicant/RA and/or WL. Upon agreement by the AAR on the site preparation, the AAR and RA/WL shall indicate confirmation by signing in Section 6 of the PTW form and submit the Hot Work Permit to the Approving Authority (AA).

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 4

    (9) For work that needs to be communicated to other parties, the AA shall identify the relevant parties in Section 7 of the Hot Work Permit. The Applicant/RA shall then obtain the initial from the parties identified by Approving Authority (AA).

    (10) For work that is conducted by Contractors where the

    Company Site Representative (CSR) is at site (e.g. drilling, construction, etc.), the CSR shall be one of the mandatory parties to be informed of the work. He/she shall indicate acknowledgement by signing in Section 7 of the Hot Work Permit.

    (11) After all the actions are completed, Section 7 of the

    Hot Work Permit shall be signed by RA to indicate acceptance of the PTW requirement. The form shall then signed by AS for endorsement prior approval from AA.

    (12) For work conducted on remote facilities, the

    AAR/AS/AA may be the same person as the roles and responsibilities may be delegated to the most senior person on the facility.

    Note: The Permit Applicant and the Approving Authority/Authorised Supervisor/Approving Authority Representative shall not be the same person.

    (13) For unplanned hot work on remote facilities, the

    endorsement and approval for the work shall be given by the AAR who assumed the functions of AS and AA. However, the work shall first be communicated to the AS and AA at main installations prior AAR endorsing and approving the permit.

    (14) Among the information that needs to be communicated

    are:

    (a) Details of the hot work that needs to be carried out, including any special work instructions;

    (b) Required precautions and PPE for the work; and

    (c) Additional certificates or documents required for the work

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 5

    1.2 PTW Application and Site Preparation for Cold Work

    (1) The Applicant/RA fills in Section 1 to 4 of the Cold Work Permit with the details of the work to be done, specifying the exact location and the tools to be used. The Applicant/RA shall also attach together with the PTW the required certificates, JHA and other documents related to the work. In addition, it is also expected for the Applicant/RA to identify the hazards, precautions and Personal Protective Equipment (PPE) with respect to the work.

    (2) The Applicant/RA shall then discuss on the work with the Work Leader (WL) and Authorised Supervisor (AS) to ensure the correct work scope as well as determination of hazards, precautions and PPE. In addition, the hazardous area classification shall also be confirmed by the AS to ensure the correct precautions are in place.

    Note: For work that is conducted by Contractors where the Company Site Representative (CSR) is at site (e.g. drilling, diving, construction, etc.), the Applicant/RA shall discuss the work scope, hazards and control/recovery barriers required for the work with the CSR prior meeting the AS.

    (3) The AS shall also verify that the JHA is communicated

    to all personnel involved in the work during the toolbox meeting. The AS shall then approve the JHA.

    (4) Additionally, where required, the AS shall propose

    additional precautions in minimizing the risk associated with the work to ALARP.

    (5) For cold work in confined space, the AS shall determine the frequency of gas testing in the designated column of the required precautions (of the Cold Work Permit), Confined Space Certificate and Gas Test Form.

    (6) The AS will verify the submission of certificates and identify the need for other certificates. The certificates number shall be recorded in Section 5 of the Cold Work Permit.

    (7) After site preparation is completed, joint site visit shall

    be carried out before commencement of work by the AAR, together with Applicant/RA and/or WL. Upon agreement by the AAR on the site preparation, the AAR and RA/WL shall indicate confirmation by signing

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 6

    in Section 6 of the PTW form and submit the Cold Work Permit to the Approving Authority (AA).

    (8) For work that needs to be communicated to other parties, the AA shall identify the relevant parties in Section 7 of the Cold Work Permit. The Applicant/RA shall then obtain the initial from the parties identified by Approving Authority (AA).

    (9) For work that is conducted by Contractors where the

    Company Site Representative (CSR) is at site (e.g. drilling, construction, etc.), the CSR shall be one of the mandatory parties to be informed of the work. He/she shall indicate acknowledgement by signing in Section 7 of the Cold Work Permit.

    (10) After all the actions are completed, Section 7 of the

    Cold Work Permit shall be signed by RA to indicate acceptance of the PTW requirement. The form shall then be signed by AS for endorsement prior approval from AA.

    (11) For work conducted on remote facilities, the

    AAR/AS/AA may be the same person as the roles and responsibilities may be delegated to the most senior person on the facility.

    Note: The Permit Applicant and the Approving Authority/Authorised Supervisor/Approving Authority Representative shall not be the same person.

    (12) For unplanned cold work on remote facilities, the

    endorsement and approval for the work shall be given by the AAR who assumed the functions of AS and AA. However, the work shall first be communicated to the AS and AA at main installations prior AAR endorsing and approving the permit.

    (13) Among the information that needs to be communicated

    are:

    (a) Details of the cold work that needs to be carried out, including any special work instructions;

    (b) Required precautions and PPE for the work; and

    (c) Additional certificates or documents required for the work.

    1.3 Work Execution

    (1) The Applicant/RA and/or WL shall brief all workers on

    the hazards and conditions of PTW before work

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 7

    commences. He shall also verify that the precautions are continuously implemented by those involved with the work and shall regularly check the work site to identify and correct any deviation to the PTW requirements.

    (2) The top copy and any attached certificates are displayed at the work site by the WL and shall be available for inspection at any time. The second copy will be retained in the control room of the facility and the third copy is retained by the Applicant/RA.

    (3) Process or operational conditions may change, so it is essential that the AS and/or AAR shall regularly check the work site to ensure that all precautions are maintained. In cases where additional gas test is required, the AS and/or AAR shall instruct for the gas test to be conducted and recorded in the Gas Test Form.

    (4) The AA or AS or AAR shall stop the work at any time

    if the conditions or work is deemed as unsafe. The PTW shall be suspended until the conditions are made safe. However, in the event where the conditions remain unsafe, the PTW shall be closed.

    (5) For extension of wireline operation, Section 8 of the

    Cold Work permit shall be filled. Thereafter, the WL, AS and AA shall sign daily to indicate agreement of the work extension. The conditions of work extension shall comply with the requirements specified in sub-section 1.5.

    (6) For extension of cold work, Section 9 of the Cold Work permit shall be filled. The duration of the required extension shall be specified in this section. Thereafter, the WL, AAR, AS and AA shall sign to indicate agreement of the work extension. The conditions of work extension shall comply with the requirements specified in sub-section 1.5.

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 8

    1.4 Work Completion

    (1) Upon work completion, the WL shall sign in Section 8 of the Hot Work Permit and Section 10 of the Cold Work Permit to indicate that work has completed and the site has been restored to its normal condition.

    (2) The AAR shall then verify the worksite and sign-off the permit if the condition is satisfactory.

    (3) The Applicant/RA, AS and AA shall then sign-off the

    permit to indicate agreement on the work completion and permit handback (closure).

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 9

    Start

    Need to conduct work that requires PTW.

    Attach the relevant certificate to the PTW

    Applicant/RA shall discuss with WL and AS on the workscope, hazards, precautions and

    PPE required for the work

    AS will verity the submission of certificates and record the certificates number in Section 5

    of PTW

    Need other certificates?

    Applicant to raise the required certificate and get it endorsed by the appropriate parties

    AAR and Applicant/RA/WL conduct joint site visit

    AAR and WL shall indicate confirmation in Section 6 of PTW form

    AA to identify other parties where PTW needs to be communicated in Section 7 of PTW

    form

    Applicant/RA to obtain initials from the identified parties

    Yes

    No

    Applicant fills in Section 1-4 of PTW form

    Note: For work requiring gas test, AS shall determine the gas test

    frequency

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 10

    * Work Execution

    Brief all workers on the hazards and conditions

    RA / WL to ensure continuous implementation of precautions at site

    WL to ensure respective copies shall resides at respective location

    AS and/or AAR to check the worksite regularly

    Safe work

    condition?

    Stop Work and suspend PTW

    Implement additional control to make safe the work condition

    Re-evaluate work condition

    Safe work condition?Resume Work

    End Work

    Work Completion

    ** Work Completion

    WL to sign Section 8 upon work completion

    AAR verify the worksite

    Worksite restored to normal condition?

    Applicant/RA to

    restore the

    worksite to

    satisfactory

    Applicant/RA, AS and AA signed off at Section 8 to close PTW

    End

    Yes

    No

    Yes

    No

    No

    Yes

    Note: Refer to **

    Figure 3: PTW Process Flow for Hot Work Permit

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 11

    Start

    Need to conduct work that requires PTW.

    Attach the relevant certificate to the PTW

    Applicant/RA shall discuss with WL and AS on the workscope, hazards, precautions and

    PPE required for the work

    AS will verity the submission of certificates and record the certificates number in Section 5

    of PTW

    Need other certificates?

    Applicant to raise the required certificate and get it endorsed by the appropriate

    parties

    AAR and Applicant/RA/WL conduct joint site visit

    AAR and WL shall indicate confirmation in section 6 in PTW form

    AA to identify other parties where PTW needs to be communicated in Section 7 of PTW

    form

    Applicant/RA to obtain initials from the identified parties

    Yes

    No

    Applicant fills in Section 1-4 of PTW form

    Note: For work requiring gas test, AS shall determine the gas test

    frequency

    Work Execution

    Note: Refer to *

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 12

    * Work Execution

    Brief all workers on the hazards and conditions

    RA / WL to ensure continuous implementation of precautions at site

    WL to ensure respective copies shall resides at respective location

    AS and/or AAR to check the worksite regularly

    Safe work

    condition?

    Stop Work and suspend PTW

    Implement additional control to make safe the work condition

    Re-evaluate work condition

    Safe work condition?Resume Work

    End Work

    ** Work Completion

    WL to sign Section 10 upon work completion

    AAR verify the worksite

    Worksite restored to normal condition?

    Applicant/RA to

    restore the

    worksite to

    satisfactory

    Applicant/RA, AS and AA signed off at Section 10 to close PTW

    End

    No

    Yes

    No

    No

    Yes

    Work

    Completed?

    **Work Completion

    For work requires

    extension:

    Fill in Section 8

    (for cold work)

    or section 9 (for

    Non-Rig Coil

    Tubing &

    wireline

    Operation.

    Note: Refer

    to **

    Yes

    No

    Yes

    Figure 4: PTW Process Flow for Cold Work Permit

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 14

    1.5 Permit to Work Validity

    (1) The PTW is valid when:-

    (a) Work is conducted during the period for which it is issued or a maximum of one shift (i.e.) 8 - 12 hours;

    (b) Equipment remains the same; (c) Work activity remains the same; (d) Crew/workers remain the same; (e) Work site conditions remain the same; and (f) Required signatures are in place.

    (2) However, exceptions of the PTW validity may be

    allowed for two conditions stated below: (a) Extension of PTW of a cold work (in Section 8 of

    Cold Work Permit) should be allowed provided that work is conducted by the same crew (shift extension). It shall be revalidated to verify the conditions of the worksite remains the same and all the controls are still in place. The allowable extension of the cold work shall not exceed 4 hours; and

    (b) Extension for wireline operations may be

    allowed for up to seven (7) days, provided that requirement below are satisfied:

    (i) On suspension of work on daily basis, the

    well shall be made safe by making the SCSSV and SSV in operation mode;

    (ii) Single control panel shall be switched to

    Wellhead Control Panel (WHCP);

    (iii) Tools shall be retrieved from the well; and

    (iv) The operation is performed by the same crew on the same well.

    Daily endorsement shall be recorded in Section 8 of the Cold Work Permit.

  • Permit To Work Procedure Permit to Work Application

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 3 Page 15

    Note: A PTW may require several certificates before it may be validated.

    (3) In the event where there is change in AAR or AS or

    AA during the work extension, the new AAR or AS or AA shall indicate their agreement for the work extension in Section 9 (for cold work) or Section 8 (for wireline operations).

    (4) Should an Emergency Shutdown (ESD) or General

    Platform Alarm (GPA) activated, all work shall stop immediately and the PTW shall be suspended. The work sites shall be secured and made safe and all personnel shall proceed to their designated muster stations.

    (5) In the case of false alarm or emergency drill, the work

    may resume after revalidation of PTW and the condition remains the same.

    (6) However, in the event of confirmed emergency, all

    PTW and associated certificates shall be cancelled and re-applied prior to resume work as worksite condition has changed.

    (7) During equipment test run, all PTW for cold work and

    wireline operations shall be suspended until completion of test run/troubleshooting. Meanwhile, all PTW for hot work shall be closed and re-apply to resume the work.

  • Permit To Work Procedure Certificates

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 4 Page 1

    SECTION 4

    CERTIFICATES

    Content

    Paragraph Page No.

    1 CERTIFICATES 2

    1.1 General Certificate Application Process 4

    1.2 Gas Test Form 6

    1.3 Confined Space Entry Certificate 7

    1.4 Electrical Isolation Certificate 7

    1.5 Limit of Electrical Access Certificate 7

    1.6 Physical Isolation Certificate 8

    1.7 Lifting Certificate 8

    1.8 Safety System Bypass/Override Certificate 9

    1.9 Excavation Certificate 10

    1.10 Radiation Certificate 10

    1.11 Road Obstruction/Closure Certificate 11

    1.12 Vehicle Entry Certificate 11

    1.13 Diving Certificate 11

  • Permit To Work Procedure Certificates

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 4 Page 2

    1 CERTIFICATES

    (1) Certificates shall be required to be attached together with PTW as part of PTW approval in providing the assurance to the AA that the work is safe to be conducted.

    (2) The required certificates shall be completed and endorsed by the Subject Matter Expert (SME) of the activities in confirming that all precautions are in place prior PTW application.

    (3) PETRONAS Carigali PTW system has twelve (12) certificates. Each is intended for a specific purpose, as the name implies, and each has a coloured border of diagonal stripes.

    (4) The twelve certificates are:-

    (a) Gas Test Form;

    (b) Confined Space Entry Certificate;

    (c) Electrical Isolation Certificate (EIC);

    (d) Limit of Electrical Access Certificate (LoEA);

    (e) Physical Isolation Certificate (PIC);

    (f) Lifting Certificate;

    (g) Safety System Bypass/Override Certificate (SSBOC);

    (h) Excavation Certificate;

    (i) Radiation Certificate;

    (j) Road Obstruction/Closure Certificate;

    (k) Vehicle Entry Certificate; and

    (l) Diving Certificate.

  • Permit To Work Procedure Certificates

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 4 Page 3

    (5) In most cases, the certificates are normally associated with the work and dependent to the PTW. However, there are certificates that may be standalone due to some reasons as elaborated below:

    Certificate Reason for Standalone

    Safety System Bypass/Override Certificate (SSBOC)

    The certificate may remains active after the completion of work e.g. may be due to spare parts unavailability, which requires the bypass of SCE equipment to be extended.

    Physical Isolation Certificate

    The certificate may remains active if work is yet to complete and the energy needs to remain isolated. However, the PTW needs to be closed as the PTW validity shall not exceed 16 hours.

    Electrical Isolation Certificate

    Radiation Certificate

    Excavation Certificate

    The certificate may remains active if work is yet to complete and the work area may remains excavated, barricaded and warning signs posted to prevent inadvertent access to the area. If the excavation area requires road closure, the road shall remains closed. However, the PTW needs to be closed as the PTW validity shall not exceed 16 hours.

    Road Obstruction Certificate

    The certificate may remains active if the work which involved road closure e.g. excavation, radiography test, etc., is yet to complete. However, the PTW needs to be closed as the PTW validity shall not exceed 16 hours.

    (6) In cases where the work needs the application of more than one certificates, all the required certificates shall be filled up and attached together with the PTW.

    Refer to Appendix 2 for all templates of certificates.

    Where requirement to have competent personnel in

    the conduct of the work by Contractor, the requirement shall be specified in the contract.

  • Permit To Work Procedure Certificates

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 4 Page 4

    1.1 Certificate Application Process

    (1) In general, the process for certificate shall be following the steps below: (a) Applicant/RA to fill in general information and

    work description; (b) SME for the activity (e.g. Entry Supervisor for

    CSE, Diving Supervisor for diving, Crane Operator for lifting, etc.) will assure on the precautions required and the implementation of all the precautions. For non-specialised work that does not require specific SME, the WL will provide the assurance;

    (c) The SME will then declare that the checks have

    been conducted and sign the certificate; (d) The AAR will then conduct site verification and

    declare that the precautions have been implemented;

    (e) The AS will endorse that the activity is safe to

    proceed; (f) The AA will approve and provide certificate

    validation; and (g) Upon completion of work, the SME will confirm

    that the work is completed and the AA will provide confirmation that he is aware that the work is complete and worksite maybe returned to normal operations.

    (2) The certificate applications is summarised in the process flow below:

  • Permit To Work Procedure Certificates

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 4 Page 5

    Figure 1: General Process Flow for Certificate Application

    Start

    Applicant / RA fills in information and work description in the relevant

    certificate.

    Specialised

    work?

    WL will verify implementation of all

    precaution and sign the certificate.

    SME for the activity will verify implementation of all precautions, and

    sign the certificate.

    AAR conduct site verification and provide confirmation by signing the

    certificate.

    AS will endorse that the activity is safe by signing the certificate.

    AA will provide approval and indicate certificate validation.

    No

    Yes

  • Permit To Work Procedure Certificates

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 4 Page 6

    1.2 Gas Test Form

    (1) Gas Test Form shall be filled and attached to respective PTW which requires gas testing i.e. hot work and work in confined space.

    (2) The Authorized Gas Tester (AGT) shall be the person responsible to carry out gas testing as well as filling in the Gas Test Form. He/she shall be certified, competent and authorized to conduct the gas testing. The training and competency requirement is deliberated in Section 6 of this document.

    (3) The gas testing shall be conducted as part of site preparation to qualify that the work place is safe and the PTW may be approved for work to commence.

    (4) Additionally, the gas testing shall be carried out on regular basis as per interval stated in the PTW. All gas test results shall be recorded in the Gas Test Form.

    (5) During work execution, should the AGT found that the gas level is beyond the acceptable level during the periodic gas testing, the AGT shall decide to either suspend or stop the work.

    (6) The acceptable parameters for gas testing are tabulated as below:

    HHowever, for work in confined space, the gas test requirement shall meet the confined space entry conditions as stated in WW ALL S 05 004 PETRONAS Carigali Confined Space Procedure.

    No. Gas type Acceptable parameters

    1 Oxygen (without BA) 20% to 20.9%

    2 LEL Less than 10%

    3 H2S Less than or equal to 5 ppm

  • Permit To Work Procedure Certificates

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 4 Page 7

    1.3 Confined Space Entry (CSE) Certificate

    (1) Confined Space Entry (CSE) Certificate shall be filled and attached to the PTW for all work in confined space.

    (2) The Entry Supervisor shall be the person to declare that all precautions required for the work in confined space has been implemented.

    (3) Where the host country/ legal required certified, competent and authorized AGT, those requirement shall be complied with. For example, in Malaysia, any work in confined space requires the AGT to attend training for authorised gas tester and entry supervisor where the AGT shall be certified based on the test conducted after the training.

    (4) The detail requirements of work in confined space is defined in WW ALL S 05 004 PETRONAS Carigali Confined Space Procedure.

    1.4 Electrical Isolation Certificate

    (1) The Electrical Isolation Certificate shall be filled for work on electrical equipment, and confirms that an appointed and authorized competent person has electrically isolated the equipment to be worked on and has taken suitable precautions to prevent accidental reconnection.

    (2) The detail requirements of the Electrical Isolation Certificate are defined in the WW ALL S 04 018 PETRONAS Carigali Energy Isolation Guideline.

    1.5 Limit of Electrical Access Certificate

    (1) The Limit of Electrical Access Certificate shall be filled for Testing of Live Voltage conductors or work in close proximity to live conductors/equipment/ apparatus.

    (2) The ACP/AP shall be the person to declare that all

    precautions required for the work near the live conductors/equipment/apparatus have been implemented.

  • Permit To Work Procedure Certificates

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 4 Page 8

    1.6 Physical Isolation Certificate

    (1) The Physical Isolation Certificate shall be filled for work on process lines and equipment to confirm that the energy is positively isolated and free from liquid, gas and other hazardous material. In addition, the certificate confirms that the precautions are implemented to ensure the energy remains isolated.

    (2) The detail requirements of the Physical Isolation Certificate are defined in the WW ALL S 04 018 PETRONAS Carigali Energy Isolation Guideline.

    1.7 Lifting Certificate

    (1) The Lifting Certificate shall be filled and attached to the PTW whenever any of the following conditions exist but not limited to:-

    (a) Lifting over unprotected process equipment or

    wellheads;

    (b) Lifting dangerous goods;

    (c) Lifting exceeding 8 tonnes;

    (d) Lifting inside confined spaces;

    (e) Lifting with sling not made of wire rope;

    (f) Lifting with greater than four leg;

    (g) Multiple crane lifts;

    (h) Failure to fully illuminate load;

    (i) Failure to fully illuminate path of load;

    (j) When removing or installing well head hatch

    cover/grating; and

    (k) When a safety device is bypassed.

  • Permit To Work Procedure Certificates

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 4 Page 9

    (2) The lifting checklist shall be filled by the Crane

    Operator for critical lifting which meets below criteria:

    (a) The percent of capacity between 86% - 100% of the load chart; or,

    (b) Multiple cranes are used for lifting; or,

    (c) Any other criteria classified as critical lifting as per PTS 18.5206: Lifting (previous PTS no. 60.2103).

    (3) For lifting activities, the AAR should be the person

    who has attended Rigging and Slinging Training e.g. deck foremen, area operator etc.

    (4) Besides Lifting Certificate, the additional

    documentation to supplement the PTW are:

    (a) Lifting Plan (for critical lifting); and

    (b) JHA. 1.8 Safety System Bypass/Override Certificate

    (1) The Safety System Bypass/Override Certificate shall

    be filled for any bypass/override/isolation/defeating of

    SCE equipment. The act of disabling any of the SCE equipment may increase the risk to people, environment, asset and reputation due to inability of the affected system to function automatically in the event of an emergency during continued operations.

    (2) The bypass/override/isolation/defeating of SCE

    equpment shall be managed via two certificates i.e.:

    (a) Bypass/override/isolation/defeating of SCE equipment due to Planned Preventive Maintenance; and

    (b) Bypass/override/isolation/defeating of SCE equipment due to faulty/prolong bypass.

    (3) The permission for bypass/override/isolation/

    defeating SCE equipment shall be based on the Safety Integrity Level (SIL) of the SCE equipment or the level of risk posed due to bypassing of the SCE equipment.

  • Permit To Work Procedure Certificates

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 4 Page 10

    (4) The detail requirements of the Safety System

    Bypass/Override Certificate are defined in the WW

    ALL S 04 019 PETRONAS Carigali Bypass of SCE

    Equipment Guideline. 1.9 Excavation Certificate

    (1) The Excavation Certificate shall be filled for all excavation work deeper than 150mm.This certificate confirms that a competent person has checked the worksite of a planned excavation and studied layout drawings to ensure that the proposed excavation can be made without damage to existing buried facilities such as pipelines, drains and electric cables.

    (2) The information and validity of the Excavation

    Certificate shall be in line with the excavation plan.

    (3) Besides Excavation Certificate, the additional documentation to supplement the PTW are listed as below, depending on the depth of the excavation:

    (a) Excavation Plan;

    (b) JHA; and

    (c) Work site layout drawings.

    (4) The detail requirements for excavation work is

    defined in the WW ALL S 04 035 PETRONAS

    Carigali Excavation Safety Guideline. 1.10 Radiation Certificate

    (1) The Radiation Certificate shall be filled for handling

    and isolating of equipment containing ionising radiation source.

    (2) For handling of radiation source, the certificate shall

    be attached to the PTW as part of its application and approval.

    (3) For isolating of equipment containing ionising

    radiation source, the certificate may be standalone.

    (4) The RPO/RPS shall be the person to declare that all precautions required for the work involving ionising radiation source have been implemented.

  • Permit To Work Procedure Certificates

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 4 Page 11

    (5) The detail requirements for isolating the equipment containing ionising radiation source are defined in the

    WW ALL S 04 018 PETRONAS Carigali Energy

    Isolation Guideline.

    1.11 Road Obstruction/Closure Certificate

    (1) The Road Obstruction/Closure Certificate shall be filled whenever the closure of any road may affect or obstruct the emergency/escape route.

    (2) The plot plan to indicate the road closure as well as

    the alternative route shall be attached to the certificate.

    1.12 Vehicle Entry Certificate

    (1) The Vehicle Entry Certificate shall be filled for control of entry of non-company vehicle into the process areas.

    (2) One permit is valid for more than one certificate and

    each certificate is valid for one vehicle. 1.13 Diving Certificate

    (1) The Diving Certificate shall be filled for any work

    requiring diving activities e.g. pipeline inspection and maintenance, installation of subsurface structures, decommissioning, etc.

    (2) The Diving Supervisor shall be the person to declare

    that all precautions required for the diving work have been implemented.

    (3) Besides Diving Certificate, the additional

    documentation to supplement the PTW are:

    (a) Diving Plan; and

    (b) JHA

    (4) For diving work within 500m radius of the platform, the relevant OIM shall be the AA of the PTW. However, for diving work outside 500m radius of the platform, the CSR should be the AA of the PTW.

  • Permit To Work Procedure Work and Activities Management

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 5 Page 1

    SECTION 5

    WORK AND ACTIVITIES MANAGEMENT

    Content

    Paragraph Page No.

    1 WORK AND ACTIVITIES MANAGEMENT 2

    1.1 Preparation 2

    1.2 Co-ordination 2

    1.3 Planning 2

    1.4 Isolation 2

    1.5 Communication 3

    1.6 Display Board 3

    1.7 Cross Referencing 3

    1.8 PTW/Certificates Site Log Book 3

    1.9 Tracking 4

    1.10 Distribution 4

    1.11 Toolbox Meetings 5

  • Permit To Work Procedure Work and Activities Management

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 5 Page 2

    1 WORK AND ACTIVITIES MANAGEMENT

    1.1 Preparation

    It is important to ensure that work activities, requiring a PTW, are planned and coordinated in order to avoid risks that may occur in simultaneous activities.

    1.2 Co-ordination

    This co-ordination is best achieved by having one person, usually the AA, to control the issue and return of all PTW.

    1.3 Planning

    Proper planning of work, requiring a PTW, shall take place to ensure the following:

    (1) Approval for the work is obtained;

    (2) All personnel are aware of the safety precautions and

    ensure no interaction with other work activities; and

    (3) Sufficient time is available to identify all potential hazards, implement precautions and worksite preparation.

    It is therefore important that no work permit shall be issued unless adequate time is given for the identification of hazards and effects, precautions and control measures.

    1.4 Isolation

    An essential component of any safe system of work is the method and integrity of the isolation procedure. The isolation principle shall be adopted, prior to carrying out maintenance or repair, shall be determined by a number of factors, such as potential for pressure, dangerous substances, moving machinery and other hazards. Reference shall be made to WW ALL S 04 018 PETRONAS Carigali Energy Isolation Procedure.

  • Permit To Work Procedure Work and Activities Management

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 5 Page 3

    1.5 PTW Communication

    PTW communication shall be carried out using the most understandable language. Effective communication shall include:

    (1) A clear description and the scope of the work to be

    carried out;

    (2) Those affected by the work activity, whether directly or indirectly, are well informed on the potential hazards, precautions and controls; and

    (3) All affected are well informed on the proactive

    actions in the event of an emergency.

    1.6 Display Board

    Each installation shall use a display board for the permit in managing daily activities onboard the facilities which may cause additional hazards if those activities are carried out simultaneously. It is usually located in the main operations control room or at a central location on a remote facility.

    1.7 Cross Referencing

    In managing simultaneous activities, besides referring to the display board, the AS & AA shall also make a reference to the related permits and its associated documents to ensure that each activity does not introduce additional hazards to each other.

    1.8 PTW/Certificates Site Log Book

    (1) After the PTW and its associated certificates are approved, the details shall be recorded in a log book. A dedicated log book for a facility shall be maintained.

    (2) The required information to be recorded include,

    amongst others:

    (a) PTW number;

    (b) Certificates number;

    (c) Date of PTW application;

    (d) Summary of work description;

  • Permit To Work Procedure Work and Activities Management

    WW ALL S 05 002 Rev. 4a, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 5 Page 4

    (e) Name of Applicant/RA (including the name of his/her department/company);

    (f) Location of work;

    (g) Equipment name and tag number;

    (h) Date and time of PTW closure;

    (i) Status of certificates; and

    (j) Date of certificate closure.

    (3) The retention period of expired permit, certificate and all other relevant documents is at least one (1) year.

    (4) The permit, certificate and all relevant documents

    related to any incident shall be kept throughout the duration of the plants/facilities lifecycle.

    (5) In cases where the local authority imposed a more stringent requirement on record keeping, this requirement shall be fully complied with.

    Refer to Appendix 4 for template PTW logbook.

    1.9 Tracking

    (1) All PTW, including the associated certificates shall be tracked to closure.

    (2) For standalone certificates, the certificates shall be tracked to closure via the PTW logbook to ensure requirements for revalidation is fully complied with.

    1.10 Distribution

    Copies of the permit and certificates shall be distributed as follows:

    (1) The Top Copy, which has all the required signatures,

    to be displayed at the work site whenever work is underway;

    (2) The 2nd. Copy, to be displayed on the display board at the Permit Issue Point when work is in progress; and

    (3) The 3rd Copy to be held by the Applicant/RA.

  • Permit To Work Procedure Work and Activities Management

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 5 Page 5

    1.11 Toolbox Meetings

    Toolbox meetings or short briefings shall be given by either the Applicant/RA or the WL to all personnel who are involved in the work. It shall be conducted whenever PTW is applied and approved. For the same work that will continue for a few days where the crew may change, a new PTW shall be applied and therefore toolbox meeting shall be carried out. During the toolbox meeting, the plan for the activity is explained, individual responsibilities identified, procedures reviewed and hazards discussed.

  • Permit To Work Procedure Training

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 6 Page 1

    SECTION 6

    TRAINING

    Content

    Paragraph Page No.

    1 TRAINING 2

    1.1 Training and Competence 2

    1.2 Training Criteria 2

  • Permit To Work Procedure Training

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 6 Page 2

    1 TRAINING 1.1 Training and Competence

    (1) PTW Awareness training is mandatory for all PETRONAS Carigali and Contractors personnel working under the permit. The awareness training may be carried out by personnel who are familiar and have full understanding on PCSB PTW system i.e. PTW Trainer, PTW signatory parties, HSE personnel, etc.

    (2) For PTW signatory parties, the PTW Certification training is mandatory to be attended. In addition, the written examination shall be carried out after the training to assess the competency level of the personnel to authorised as signatories in the PTW system. The certification training shall be carried out by a certified trainer that met the criteria as mentioned in sub-section 1.2 of this section.

    (3) For competency assessment, the PTW signatory

    parties shall passed 85% of the PTW certification assessment.

    (4) The validity of the training shall be three (3) years.

    (5) For work requiring certificates, the responsible

    Subject Matter Experts (SME) may not be required to attend the certification training. However, if the SME are part of the PTW signatories, the SME shall attend the PTW Certification training.

    (6) The minimum training requirements for different

    parties in PTW system are:

    PTW Awareness Training (1 day)

    PTW Certification Training (including JHA and Confined

    Space) (3 days)

    Refresher Training (3 days)

    Permit Applicant √ √

    Approving Authority (AA) √ √

    Authorised Supervisor (AS) √ √

    Approving Authority Representative (AAR)

    √ √

  • Permit To Work Procedure Training

    WW ALL S 05 002 Rev. 4, July 2013

    PETRONAS CARIGALI SDN BHD SECTION 6 Page 2

    Receiving Authority (RA) √ √

    Work Leader (WL) √ √

    Authorised Gas Tester (AGT)