METODE KONSTRUKSIPEMINDAHAN TANAH MEKANIS

Oleh Kelompok 6:

Wildan Yoga Pratama I1114082Yopi Saparudin I1114083Yosethyaji Arif Setiawan I1114084Yudi Risdiyanto I1114085

Page 2: Perencanaan parkir jts

1. VOLUME TANAH

Luas Lahan 475 m2

Volume Galian 807,5 m3 (BM)

Dalam galian 1,7 m

Page 3: Perencanaan parkir jts

Volume tanah keadaan Bank (BM), volume tanah keadaan Loose (LM), volume stripping dan Volume dipadatkan (CM)

Volume Bank ( BM ) = 807,5 m3

Volume Loose ( LM ) = Koef. volume Loose x Volume Bank

= 1.2 x 807.5

= 969 m3

Volume Stripping = Luas Lahan x Tebal Stripping

= 475 m2 x 0,3 m

= 142,5 m3 (BM)

= 142,5 x 1,2 = 171 m3 (LM)

Volume Compact (CM) = Koef. volume Compact x (BM – Volume stripping)

= 0.8 x ( 807,5 – 142,5 )

= 532 m3

Page 4: Perencanaan parkir jts

2. ALAT KERJA

BULLDOZER KOMATSU D31P-20

Untuk stripping Lapisan

permukaan tanah

Page 5: Perencanaan parkir jts

EXCAVATOR BACKHOE KOMATSU PC100

Untuk malaksanakan pekerjaan

galian tanah dan loading ke dumptruck

Page 6: Perencanaan parkir jts

DUMP TRUCK HINO DUTRO 130 HD 6,8 PS

Untuk mengangkut tanah hasil

galian menuju lembah teknik untuk

dipadatkan

Page 7: Perencanaan parkir jts

TANDEM ROLLER KOMATSU S6D102E

Untuk melaksanakan pekerjaan

pemadatan tanah

Page 8: Perencanaan parkir jts

3. METODE KERJA

a. Clearing & Stripping

Page 9: Perencanaan parkir jts

b. Pekerjaan Galian

Page 10: Perencanaan parkir jts

c. Pekerjaan Pemadatan

Page 11: Perencanaan parkir jts

4. STRIPPING

Produktifitas alat dihitung dengan cara berikut.

Efisiensi kerja = 85% (50 menit per jam)

Fixed time = 0,15 menit

Tebal stripping = 0,3 m

Jarak gusur = 15 m

Volume tanah = 142,5 m3

Volume lepas = 1,25 × 142,5

= 178,125 m3

Load factor = Vb/Vl

= 142,5 /178,125

= 0,8 (swell 20%)

Kapasitas pisau = 2,875 × 0,3

= 0,863 m3

Kapasitas (bank) = 0,863 × 0,8

= 0,69 m3

Waktu maju =

=

= 0,20 menit

Waktu mundur =

=

= 0,15 menit

= 0,5 menit

Total cycle time (CT)= fixed time + waktu maju + waktu mundur

= 0,15 + 0,2 + 0,15

= 0,5 menit

Total produktifitas =

=

= 55,2 m3/jam

Page 12: Perencanaan parkir jts

Pekerjaan pembersihan dilakukan dengan alat jenis bulldozer buatan Komatsu D31P-20 dengan produktivitas 55,2 m3/jam. Perkiraan kebutuhan alat dan waktu dihitung dengan cara berikut.

Volume stripping = 142,5 m3

Produktivitas = 55,2 m3/jam

Jumlah alat = 1 buah

Waktu pekerjaan =

=

= 2,58 jam

Page 13: Perencanaan parkir jts

5. CUTING & LOADING

Produktifitas alat dihitung dengan cara berikut.

Efisiensi kerja = 85% (50 menit per jam)

Fill factor = 100 % (tanah loose)

Kapasitas bucket = 0,55 m3

Waktu menggali (t1) = 5 detik

Waktu wing (t2) = 7 detik (90º)

Waktu membuang (t3) = 5 detik (truk)

Total cycle time (CT)= t1 + 2t2 + t3

= 5 + (2 × 7) + 5

= 24 detik

= 0,4 menit

Total produktifitas =

=

= 83,33 m3/jam

Page 14: Perencanaan parkir jts

Setelah pekerjaan pembersihan maka dilanjutkan pekerjaan galian dengan alat excavator buatan buatan Komatsu tipe PC100 yang langsung ditujukan ke alat angkut dengan produktivitas alat sebesar 83,33 m3/jam Perkiraan kebutuhan dan waktu dihitung dengan cara berikut.

Volume galian = 807,5 m3

Produktivitas = 83,33 m3/jam

Jumlah alat = 1 buah

Waktu pekerjaan =

=

= 9,69 jam

Page 15: Perencanaan parkir jts

6. TRANSPORTING

Produktifitas alat dihitung dengan cara berikut.

Efisiensi kerja = 85% (50 menit per jam)

Fill factor = 100 % (tanah loose)

Jarak angkut = 400 m

Kapasitas bucket = 7 m3

Kapasitas berat = kapasitas bucket(bank) × konversi tanah

= (7 / 1,25) × 1,6

= 8960 kg = 8,96 ton

Berat total = berat dump truck

+ berat angkut

= 2355 + 8960

= 11315 kg = 11,315 ton

 Tahanan gelinding = 60 lb/ton

Tahanan kelandaian = 2% x 20 lb/ton = -40 lb/ton

Tahanan total = 20 lb/ton

Rimpull yang diperlukan= 20 lb/ton x 11,315 ton = 226,3 lb

Pada waktu mengangakat beban kecepatan maksimum truck

hanya bisa mencapai 32,7

Page 16: Perencanaan parkir jts

Tahanan gelinding = 60 lb/ton

Tahanan kelandaian = 2% x 20 lb/ton

= 40 lb/ton

Tahanan total = 100 lb/ton

Berat kosong truck = 2,57 ton

Rimpull yang diperlukan = 100 lb/ton x 2,355 ton

= 235,5 lb

Pada waktu mengangakat beban kecepatan maksimum truck

hanya bisa mencapai 32,7 m

Cycle time

Loading = = 0,188 jam

Mengangkut = = 0,00856 jam

Kembali = = 0,00856 jam

Fixed time 2 menit = 0,033 jam

Membuang dan mengatur posisi 1 menit = 0,0165 jam

Total cycle time = 0,2053 jam = 13 menit

Jumlah trip / jam = 60/13 = 4,6 trip ~ 4 trip

Produksi alat angkut = jumlah trip × kapasitas alat angkut

= 4 × 7

= 28 m3/jam

Page 17: Perencanaan parkir jts

Manajemen faktor dan medan kerja baik = 0,85 (baik)

Total produktifitas = Efisiensi kerja × FM × produktifitas

= 0,85 × 0,85 × 28

= 20,23 m3/jam

Keperluan alat =

=

= 4,1 ≈ 4 buah

Page 18: Perencanaan parkir jts

Pekerjaan pengangkutan dilakukan dengan alat jenis DUMP TRUCK Hino type Dutro dengan produktivitas alat sebesar 20,33 m3/jam. Pekerjaan pengangkutan dihitung dengan cara berikut.

Volume pemuatan = 969 m3 (loose)

Produktivitas = 20,33 m3/jam

Jumlah alat = 4 buah

Waktu pekerjaan =

=

= 11,91 jam

Page 19: Perencanaan parkir jts

7. COMPACTING

Volume tanah compact (disyaratkan) = 532 m3

Luas Lembah Teknik = 34 m x 25 m = 850 m2

Ditetapkan tebal tanah = 60 cm; 3 layer tanah @ 20 cm

Didapat volume tanah compact = 850 m2 x 0,6 m = 510 m3

Pemadatan tanah menggunakan alat Tandem Roller Komatsu tipe S6D102E berat 22266.7 lb

Lebar efektif compactor = 213 cm

Jumlah pass yang diperlukan = 10 kali

Kecepatan operasi = 5  km/h

Kondisi manajemen baik dan kondisi medan baik

Produksi compactor / jam = = 798,75 m2/lapis/jam

Page 20: Perencanaan parkir jts

Waktu pemadatan = = 1,064 jam/lapis

Lapis tanah = 4 lapis

Waktu total pemadatan = 1,064 x 4 = 4,256 jam

Waktu pengerjaan = 4,25 / 8 = 0,53 hari ~ 1 hari

Page 21: Perencanaan parkir jts

8. ESTIMASI BIAYA

No Nama Alat Jumlah Waktu Kerja (jam) Harga Sewa Per Jam Total 1 Bulldozer 1 2,58 IDR 130.000,00 IDR 335.400,002 Excavator 1 9,69 IDR 190.000,00 IDR 1.841.100,003 Dump Truck 4 11,91 IDR 68.750,00 IDR 3.275.250,004 Tandem Roller 1 8 IDR 14.000,00 IDR 112.000,00

5.563.750,00IDR

No Nama Jumlah Waktu Kerja (jam) Harga Sewa Per Jam Total 1 Op. Dump Truck 4 11,91 12.500,00IDR 595.500,00IDR 3 Op.Bulldozer 1 2,58 13.750,00IDR 35.475,00IDR

630.975,00IDR

No Nama Bahan Jumlah Waktu Kerja (jam) Harga Bahan Total 1 Solar Dump Truck 4 11,91 110.000,00IDR 5.240.400,00IDR 2 Solar bulldozer 1 2,58 95.200,00IDR 245.616,00IDR

No Nama Kegiatan Satuan Jumlah Harga Total 1 Mobilisasi Alat ls 1 3.000.000,00IDR 3.000.000,00IDR

8.486.016,00IDR 14.680.741,00IDR

1.468.075,00IDR 16.148.816,00IDR

SEWA ALAT

TotalTENAGA KERJA

TotalBAHAN

Total

MOBILITAS

Total Biaya PelaksanaanJasa10%TOTAL