November November 2009 2009 THE HASHEMITE KINGDOM OF JORDAN MINISTRY OF PUBLIC WORKS AND HOUSING THE HASHEMITE KINGDOM OF JORDAN MINISTRY OF PUBLIC WORKS AND HOUSING BRIDGES MIDDLE EAST 2009
101

Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Sep 13, 2014

Download

Business

The region’s only event dedicated to designing, planning and delivering sustainable bridges
Following the phenomenal success of IQPC’s global Bridges series, including two regional summits, we are delighted to announce the third Bridges Middle East summit will take place under the patronage of Abu Dhabi Municipality and the official support of Ministry of Public Works, Kuwait on 24-27 October 2010 in Abu Dhabi. www.bridgesme.com
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

November November

20092009

THE HASHEMITE KINGDOM OF JORDAN

MINISTRY OF PUBLIC WORKS AND HOUSING

THE HASHEMITE KINGDOM OF JORDAN

MINISTRY OF PUBLIC WORKS AND HOUSING

BRIDGES MIDDLE EAST 2009

Page 2: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abdoun Bridge-Amman

Page 3: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

The Strategic Vision

The Strategic vision of the Ministry of Public Works and

Housing concerning Bridge construction and maintenance in

Jordan can be summarized as follows: • Achieving economic, feasible, durable and safe design and construction through the

use of latest available international techniques in the design and construction

• Planning and applying a sustainable program of roads and bridges maintenance, repair

and rehabilitation

• Applying an environmental friendly design and construction methodology

• Ensuring a successful and sustainable system of project management, construction

monitoring, and quality enhancement

• Implementing a continuous and well elaborate program of training and technology

transfer

Page 4: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

The Strategic Vision

• Master Planning: A planned system of Bridge rehabilitation and

maintenance is the main objective where it depends on the Strategic

need and priorities, the current condition and the social /economic and

environmental impacts. Analytical assessment are carried out

culminating in optimal strategies to be implemented under conditions of

budget restraint

• Inventory and condition surveys are carried out, recorded and entered

into national database systems.

• Socio-Economic and Environmental assessment are carried out with the

objective of ensuring the proper and best usage of in-country capacity

• Bridges construction, rehabilitation and maintenance strategies are

appraised and prioritised using Multi Criteria Analysis

• Prioritised activities are effectively applied and managed.

Page 5: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

The Strategic Vision

• Environmental Impact: The overall objective of the Strategic Environmental

Assessment is to demonstrate the effective

integration and implementation of Bridge planning policies and programs under a

given regulatory and administrative procedures.

• “Construction Environment Management Guidelines “are applied to ensure minimum

adverse impacts and effective mitigation measures.

Page 6: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Major Bridge Projects In Jordan

Page 7: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor-Bridges

Main Features:

• Environment Friendly Design

• Provision of Safety Features such as noise barrier and side fencing

• Relieving major traffic from city centre and helping in reducing

congestion and pollution

• Serving the local communities by providing links to local

developments.

• Minimizing disturbance to local community by adopting optimized

alignment and design best fit with the local features and

constraints.

• Provision of landscaping to make the road and bridges Aesthetic

and in harmony with the surrounding

• Below are samples of Amman Development Corridor Bridges:

Page 8: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan
Page 9: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor-Viaduct 2

• Bridge Description:

Location : Viaduct 2, Amman Development corridor – Section 3 –

Zarqa Through Link

Type: Post tension Pre-cast Girder Beams and steel beams

Length: 310 m.

Width: 34.7 m to 49.47 m

Span length,: 36 m post tension concrete beams, 50 m steel beams

No. of Spans: 8

Height of piers: 20 m

Type of foundation: Pile foundation

Construction cost: 8.9 M JD

Designed By: Dar Al-Handasah Consultants

Main Contractor: Group Five in Cooperation with MID Contracting

Completion date: 2010

Page 10: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor-Viaduct 2

•Sequence Of Work (19)

Special environmental and safety features of the bridge:

The provision of sound barrier to mitigate noise, and long steel beams to span over existing roads and minimize disturbance to local traffic circulation

Page 11: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor-Viaduct 2

General Plan -Profile

Page 12: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor-Viaduct 2

Page 13: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Viaduct 2 Pictures

Substructure Pier Construction

Page 14: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Viaduct 2 Pictures

Superstructure Construction

Page 15: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Viaduct 2 Pictures

Superstructure Construction

Page 16: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Viaduct 2 Pictures

Superstructure Construction

Page 17: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- OP 11

Page 18: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- OP 11

• Bridge Description:

Location : Amman Development corridor – Section 3 – Overpass

11

Type: Post tension – cast in situ Voided Slab

Length: 72.4 m,

Width: 10m

longest Span length: 35.5 m

No. of Spans: 3

Height of piers: 10 m

Type of foundation: Concrete piles

• Construction cost: 0.9 M JD

• Designed By: Dar Al-Handasah Consultants

• Contractor : Group Five in Cooperation with MID Contracting

• Completion date: 2010

Page 19: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- OP 11

Special environmental and safety feature of the bridge:

Provision of special safety barrier and fencing for added environmental protection as the bridge is passing through environmental sensitive area that required added safety measures

Page 20: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- OP 11

Page 21: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- OP 11

Bridge at Completion

Noise Barrier

Page 22: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- OP 11

Substructure & Superstructure

Page 23: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- OP 11

Superstructure Construction

Page 24: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- OP 8

Page 25: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- OP 8

• Bridge Description:

Location : Amman Development corridor – Section 2 –

OP 8 over Madounah Road

Type: Post tension – cast in situ Voided Slab

Length: 78 m,

Width: 13m

Longest Span length: 56 m

No. of Spans: 3

Height of piers: 9 m

Type of foundation: Concrete footing

Construction cost: 1.5 M JD

Designed By: Dar Al-Handasah Consultants

Main Contractor: China Chongqing International Corp. in

Cooperation with United Massar

Completion date: 2010

Page 26: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- OP 8

Page 27: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- OP 8

Page 28: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- Viaduct 1

Page 29: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- Viaduct 1

• Bridge Description:

Location : Amman Development corridor – Section 2 – OP 8

over Madounah Road

Type: Post tension – cast in situ Box Girder & precast beams

• Length, 235 m,

Width 13m

longest Span length: 57 m

No. of Spans: 6

Height of piers: 17 m

Type of foundation: Concrete footing

• Construction cost: 2.1 M JD

• Designed By: Dar Al-Handasah Consultants

• Constructed By: China Chnogqing International Corp in cooperation

with United Massar

• Completion date: 2010

Page 30: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- Viaduct 1

Page 31: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- Viaduct 1

Page 32: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- Viaduct 1

Precast Girder Cast- in situ

Page 33: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- Viaduct 1

Bridge at Completion

Page 34: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- Airport

Interchange Bridges

Page 35: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- Airport

Interchange Bridges

• Bridges Description:

Location : Amman Development corridor – Section 1 –

Airport Interchange

Type: Post tension – cast in situ Box Girder

Length: 160 m, (one bridge)

Width : 13m

longest Span length: 48 m

No. of Spans: 5

Height of piers: 10 m

Type of foundation: Concrete piles

Designed By: Dar Al Handasah Consultants

Main Contractor: Copri Construction Enterprises Est

Bridge Subcontractor: Marwan Al Kurdi & Partners Co. Ltd.

Completion date: 2011

Page 36: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- Airport

Interchange Bridges

Special environmental and safety features of the Interchange and bridges:

The provision of environmental friendly design including fulllandscaping compatible with the surrounding and to ensure the least intrusion .

Page 37: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Amman Development Corridor- Airport

Interchange Bridges

Page 38: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abdoun Bridge-Amman

Page 39: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abdoun Bridge-Amman

Special environmental and safety features

This bridge spans over major wadi in Amman and links the two sides of the

city with an aesthetically pleasing , economic and with minimum land

acquisition requirement. This bridge has minimized the travel time and

distance within Amman and provided a very attractive feature that is

environmentally acceptable and socially desired

Length:420 n, longest span length: 132 m

Width: 27 m

Designed by: Dar Al-Handasah Consultants

Completion time: 2007

Page 40: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abdoun Bridge-Amman

Page 41: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abdoun Bridge-Amman

Page 42: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abdoun Bridge-Amman

Precast Segment Installation

Page 43: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abdoun Bridge-Amman

Bridge at completion

Page 44: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abu Alasal Bridge / Parkway

Page 45: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abu Alasal Bridge / Parkway

• Bridge Description:

Location : Maeen – Dead Sea

Type: Post tension – Precast Girder – AASHTO Type

Length: 91.2 m,

Width: 12.8m

longest Span length: 30 m

No. of Spans: 3

Height of piers: 26 m

Type of foundation: Shallow Foundation.

Construction cost: 2.4 M JD.

Designed By: Pacific Consultant International & Yamasita

Consultants Sekki Inc. & Consolidated Consultant.

Main Contractor: Condotte

Bridgework Subcontractor: Marwan A. Al-Kurdi & Part. Co. Ltd.

Completion date: 2005.

Page 46: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abu Alasal Bridge / Parkway

Page 47: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abu Alasal Bridge / Parkway

Page 48: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abu Alasal Bridge / Parkway

Page 49: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abu Alasal Bridge / Parkway

Precast Girder Installation & Substructure

Page 50: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abu Alasal Bridge / Parkway

Bridge During

Construction

Page 51: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abu Alasal Bridge / Parkway

Substructure Works

Page 52: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Abu Alasal Bridge / Parkway

Precast Girder Installation using Launching Girder

Page 53: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Himara Bridge / Parkway

Page 54: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Himara Bridge / Parkway

• Bridge Description:

Location : Maeen- Dead Sea

Type: Post tension – Precast Girder

Length: 100 m,

Width : 12.8m

longest Span length: 32m

No. of Spans: 3

Height of piers: 32 m.

Type of foundation: Shallow Foundation.

Construction cost: 2.5 M JD.

Designed By: Pacific Consultant International & Yamasita

Consultants Sekki Inc. & Consolidated Consultant

Main Contractor: Condotte

Bridge Subcontractor: Marwan A. Al-Kurdi & Part. Co. Ltd.

Completion date: 2005.

Page 55: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Himara Bridge / Parkway

Page 56: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Himara Bridge / Parkway

Page 57: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Himara Bridge / Parkway

Page 58: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Bridge Construction

Page 59: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Himara Bridge / Parkway

Precast Girder Installation

Page 60: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Himara Bridge / Parkway

Deck Slab Works

Page 61: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Himara Bridge / Parkway

Page 62: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

King Hussein Bridge

Page 63: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

King Hussein Bridge

• Bridge Description:Location : Dead Sea – Jordan RiverType: Extra Dose Bridge

Length: 120 m, Width: 1.8m longest Span length: 52 m No. of Spans: 3Height of piers: 21 mType of foundation: Deep Foundation (Cast in-situ Piles) .

Construction cost: 4.5 M JD.

Designer : Nippon Koie

Main Contractor : Sumitomo

Bridge Subcontractor: Marwan A. Al-Kurdi & Part. Co. Ltd.

Completion Date : 2001

Page 64: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

King Hussein Bridge

Page 65: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

King Hussein Bridge

Page 66: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

King Hussein Bridge

Piling Works

Scaffolding Works

Page 67: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

King Hussein Bridge

Post – Tensioning Works

Page 68: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

King Hussein Bridge

Bridge at Completion

Page 69: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

King Hussein Bridge

Bridge at Completion

Page 70: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Mukharis Bridges/Dead Sea

Page 71: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Mukharis Bridges

• Bridge Description:Location : Dead Sea Type: Post tension – Precast Girder – AASHTO TYPE IV

Length: 100 m.Width: 12.8m .longest Span length, 33 m No. of Spans: 3Height of piers: 11 m.Type of foundation: Shallow Foundation.

Construction cost: 3.5 M JD.

Designer : Engicon

Bridge Works By : Marwan A. Al-Kurdi & Part. Co. Ltd.

Completion Date : 2004

Page 72: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Mukharis Bridges

Page 73: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Mukharis Bridges

Substructure Works (Piers)

Page 74: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Mukharis Bridges

Bridge During Construction – Superstructure

Page 75: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Mukharis Bridges

Bridge After Completion

Page 76: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Mukharis Bridges

Mukharis Bridges

Page 77: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Zarka Interchange Bridge

Page 78: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Zarka Interchange Bridge

Bridge Description:

Location : Zarqa Highway – Zarqa

Type: Post tension – Solid Slab

Length: 82.4 m,

Width: 10.6m

longest Span length: 42.4 m

No. of Spans: 2

Height of piers: 8 mType of foundation: Shallow FoundationConstruction cost: 2.1 M JD.

Designed By: Engicon and Trois

Main Contractor: Marwan A. Al-Kurdi & Part. Co. Ltd.

Completion date: 2008

Page 79: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Zarka Interchange Bridge

Page 80: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Zarka Interchange Bridge

Page 81: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Zarka Interchange Bridge

Superstructure Works - Scaffolding

Page 82: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Zarka Interchange Bridge

Superstructure Works - Scaffolding

Page 83: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Zarka Interchange Bridge

Concrete Operation

Page 84: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Zarka Interchange Bridge

Post Tensioning Operation

Page 85: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Zarka Interchange Bridge

Zarka Interchange Bridge

Page 86: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Karak Bridge

Page 87: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Karak Entrance Bridge

• Bridge Description:

Location : Karak Entrance- KarakType: Post tension – Precast Girder AASHOTO type IV

Length: 177 m.Width: 20 m.longest Span length: 36 m. No. of Spans: 2Height of piers: 42 m.Type of foundation: Shallow Foundation

Estimated Cost: 8.2 M JD

Designed By: Engicon & Lotti

Main Contractor: Marwan A. Al-Kurdi & Part. Co. Ltd.

Completion date: 2010 ( Expected)

Page 88: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Karak Bridge

Page 89: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Karak Bridge

Page 90: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Karak Bridge

Page 91: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Karak Bridge

Substructure Works

Page 92: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Karak Bridge

Preparation for Cap Beam

Page 93: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Karak Bridge

Substructure Works

Page 94: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Baqa'a Camp Entrances

Page 95: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Baqa'a Camp Entrances

Bridge Description:

Location: Baqa'a camp

Type: Post Tension (Girder)

Length: 230 m

Width: 21 m

Girder Length: 33.40 m, No. of Spans: 7

Date of Completion: 15/11/2009

Construction Cost: 15 Million JD

Designer: Engicon

Contractor: United Enterprises Company

Page 96: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Baqa'a Camp Entrances

Bridge Special Features

• The objective of the bridge is to serve the local community of Baqa’a and the surrounding areas, spanning over the existing roads and bypassing all the local circulating traffic. It reduces congestion, enhances safety reduces noise and minimizes accidents.

• Concrete barriers of 1.26 m height was provided to separate the bridge from the adjacent service roads to mitigate noise and enhance safety.

Page 97: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Baqa'a Camp Entrances

Page 98: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Baqa'a Camp Entrances

Page 99: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Baqa'a Camp Entrances

Page 100: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

THANK YOU

Page 101: Past Bridges Middle East Presentation from Ministry of Public Works and Housing Jordan

Index Page

• Stratgic Vision

• Abdoun Bridge

• Amman ring Road

• Kin Hussein Bridge

• Mukharis Bridge

• Parkway Bridges

• Zarqa Bridge

• Baq’a Bridge

• Karak Bridge