Vertical section Passive house detail 0.1.1 Date: 2009-07-01 Schematic view Design of plinth area with projecting facade insulation and perimeter insulation down to foundation interior plaster brickwork bonding ETICS Insulation Board ETICS Basecoat + Finishing Coat in system build-up ETICS Plinth Joint Profile ≥ 260 175 10 ETICS Window Joint Profile Fill with PUR Filler Foam without joints foundation wall protection foil ETICS Plinth and Underground Insulation Board, bonded with ETICS Multiflex ETICS Basecoat + Finishing Coat in system build-up double protection coat using ETICS Multiflex capillary-breaking, water draining layer, e.g. gravel existing water proofing* ≥ 220 300 *according to DIN 18195
18
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Passivhaus Detail

Vertical section

Passive house detail 0.1.1

Date: 2009-07-01 Schematic view

Design of plinth area with projecting facade insulation and perimeter insulation down to foundation

interior plaster

brickwork

bonding

ETICS Insulation Board

ETICS Basecoat + Finishing Coat in system build-up

ETICS Plinth Joint Profile

≥ 260 175 10

ETICS Window Joint Profile

Fill with PUR Filler Foam without joints

foundation wall protection foil

ETICS Plinth and Underground Insulation Board, bonded with ETICS Multiflex

ETICS Basecoat + Finishing Coat in system build-up

double protection coat using ETICS Multiflex

capillary-breaking, water draining layer, e.g. gravel

existing water proofing*

≥ 220

300

*according to DIN 18195

Page 2: Passivhaus Detail

Vertical section

Passive house detail 0.1.2

Date: 2009-07-01 Schematic view

Design of plinth connected to soil

bondinginterior plaster

brickwork

screed on isolation layer/steam barrier

thermal insulation

existing water proofing*

basement ceiling

existing water proofing*

unheated basement

≥ 260 175 10

200

250

50

200

ETICS Plinth and Underground Insulation Board, bonded with ETICS Multiflex

double protection coat using ETICS Multiflex

300

ETICS Insulation Board

insulation stone

mortar bed

foundation wall protection foil

ETICS Basecoat + Finishing Coat in system build-up

*according to DIN 18195

Page 3: Passivhaus Detail

Vertical section

Passive house detail 0.1.3

Date: 2009-07-01 Schematic view

Skirting design with connection to base plate

bondinginterior plaster

brickwork

screed on isolation layer/steam barrier

thermal insulation

insulation stonemortar bed

filletETICS Plinth and Underground Insulation Board,bonded with ETICS Multiflex

existing water proofing*existing water proofing*

base plate

compensation layer

drainage

≥ 260 175 10

200

250

50

300

double protection coat using ETICS Multiflex

foundation wall protection foil

ETICS Basecoat + Finishing Coat in system build-up

ETICS Insulation Board

*according to DIN 18195

Page 4: Passivhaus Detail

Vertical section

Passive house detail 0.2

Date: 2009-07-01 Schematic view

Connection to balcony exit sill

ETICS Sealing Tape

ETICS Sealing Tape

airtight window connection foil

supporting console

foundation wall protection foil

balcony exit sill

ETICS Basecoat + Finishing Coat in system build-up

double protection coat using ETICS Multiflex

ETICS Plinth and Underground Insulation Board, bonded with ETICS Multiflex ≥ 260 175

Page 5: Passivhaus Detail

Vertical section

Passive house detail

Date: 2009-07-01 Schematic view

0.3.1System connection to windows flush with facade

ETICS Window Sill

airtight window connection foil

bonding

ETICS Window Joint Profile, Special+

brickwork

interior plaster

≥ 260 175 10

≥30

ETICS Insulation Board

ETICS Basecoat + Finishing Coat in system build-up

Page 6: Passivhaus Detail

Horizontal section

Passive house detail

Date: 2009-07-01 Schematic view

0.3.2System connection to semi-attached windows

ETICS Window Sill

ETICS Insulation Board

bonding

ETICS Basecoat + Finishing Coat in system build-up

airtight window connection foil

ETICS Window Joint Profile, Special+

brickwork

interior plaster

≥ 260 175 10

≥ 3

0

Page 7: Passivhaus Detail

Horizontal section

Passive house detail

Date: 2009-07-01 Schematic view

0.3.3System connection to attached windows

ETICS Window Sill

bonding

airtight window connection foil

ETICS Window Joint Profile, Special+

brickwork

interior plaster

≥ 3

0

≥ 260 175 10

ETICS Basecoat + Finishing Coat in system build-up

ETICS Insulation Board

Page 8: Passivhaus Detail

Horizontal section

Passive house detail

Date: 2009-07-01 Schematic view

0.3.4Inclined reveal connection to attached windows

bonding

airtight window connection foil

ETICS Window Joint Profile, Special+

brickwork

interior plaster

≥ 3

0

≥ 260 175 10

ETICS Insulation Board

ETICS Basecoat + Finishing Coat in system build-up

Page 9: Passivhaus Detail

Vertical section

Passive house detail

Date: 2009-07-01 Schematic view

0.4.1System connection ETICS window sill to windows flush with facade

ETICS Sealing Tape

ETICS Sealing Tape

ETICS Wall Anchor

ETICS Insulation Board

airtight window connection foil

ETICS Window Sill

≥ 260 175 10

ETICS Basecoat + Finishing Coat in system build-up

Page 10: Passivhaus Detail

Vertical section

Passive house detail

Date: 2009-07-01 Schematic view

0.4.2System connection ETICS window sill to semi-attached windows

ETICS Sealing Tape

ETICS Sealing Tape

ETICS Wall Anchor

airtight window connection foil

assembly base

ETICS Window Sill

≥ 260 175 10

ETICS Insulation Board

ETICS Basecoat + Finishing Coat in system build-up

Page 11: Passivhaus Detail

Vertical section

Passive house detail

Date: 2009-07-01 Schematic view

0.4.3System connection ETICS window sill to attached windows

ETICS Wall Anchor

airtight window connection foil

assembly base

ETICS Window Sill

≥ 260 175 10

ETICS Insulation Board

ETICS Basecoat + Finishing Coat in system build-up

ETICS Sealing Tape

ETICS Sealing Tape

Page 12: Passivhaus Detail

Horizontal section

Passive house detail

Date: 2009-07-01 Schematic view

0.5.1Exterior corner

interior plaster

bonding

ETICS Basecoat + Finishing Coat in system build-up

ETICS Insulation Board

brickwork

≥ 260 175 10

≥ 2

6017

510

Page 13: Passivhaus Detail

Horizontal section

Passive house detail

Date: 2009-07-01 Schematic view

0.5.2Interior corner

interior plaster

bonding

ETICS Basecoat + Finishing Coat in system build-up

ETICS Insulation Board

brickwork

10 175 ≥ 260

1017

5≥

260

Page 14: Passivhaus Detail

Horizontal section

Passive house detail

Date: 2009-07-01 Schematic view

0.6.1Interior wall/exterior wall

bonding

≥ 260 175 10

interior plaster

brickwork

interior plaster

brickwork

1011

510

ETICS Insulation Board

ETICS Basecoat + Finishing Coat in system build-up

Page 15: Passivhaus Detail

Vertical section

Passive house detail

Date: 2009-07-01 Schematic view

0.6.2Intermediate floor/exterior wall

bonding

≥ 260 175 10

interior plaster

brickwork

interior plaster

brickwork

1020

020

50

ETICS Basecoat + Finishing Coat in system build-up

ETICS Insulation Board

Page 16: Passivhaus Detail

Vertical section

Passive house detail

Date: 2009-07-01 Schematic view

0.7.1Connection to attic

bonding

≥ 260 175 10

interior plaster

sheet metal flashing, ≥ 2 % inclination

brickwork

1020

035

050

ETICS Sealing Tape

ETICS Insulation Board

ETICS Basecoat + Finishing Coat in system build-up

bitumen seal, double

ETICS Sealing Tape

steam barrier/emergency seal

concrete ceiling

Page 17: Passivhaus Detail

Vertical section

Passive house detail

Date: 2009-07-01 Schematic view

0.7.2Upper system connection to pitched roof

chipboard 20 mm

bonding

≥ 260 175 10

3022

240

6012,5

interior plaster

brickwork

1020

020

50

intermediate rafter insulation

air seal

gypsum plasterboard

sub-rafter insulation with installation level

ETICS Basecoat + Finishing Coat in system build-up

ETICS Insulation board

embed air seal in plaster

ETICS Sealing Tape

Page 18: Passivhaus Detail

Vertical section

Passive house detail

Date: 2009-07-01 Schematic view

0.7.3Upper system connection to verge with verge tile

verge tile

bonding

≥ 260 175 10

12,5

5824

022

interior plaster

intermediate rafter insulation

air seal

gypsum plasterboard

sub-rafter insulation with installation level

brickwork

ETICS Sealing Tape

formwork

embed air seal in plaster

ETICS Insulation Board

ETICS Basecoat + Finishing Coat in system build-up