PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live
Dec 28, 2015
PPAAGGEE 22
DARLING HARBOUR LIVE
Entertainment Centre
Pyrmont/Ultimo
Powerhouse Museum
Exhibition Centre
Convention Centre
Tumbalong ParkChinatown
Darling Harbour
PAGE 14
ICC Hotel
DARLING HARBOUR LIVE
• Up to 900 room hotel• Equity and operation currently being finalised
PAGE 15
Glebe Island Expo
• Contracts and other documents being finalised• 25,000 m2 of exhibition space with a banquet facility• 1000 space car park• Event Ferry and Bus shuttle service
DARLING HARBOUR LIVE
PAGE 16
• Existing Convention, Exhibition Halls demolished first half of 2014
• Sydney Entertainment Centre (SEC) Car Park closes around end of January 2014 to allow demolition to commence
• Hoarding line around building / carpark perimeter• After demolition hoarding line is modified to reflect new
building form• End of 2015 structure of event buildings and Boulevard
substantially complete
DARLING HARBOUR LIVE
Preliminary Construction Staging
PAGE 17
• End of 2015 SEC closes and is demolished to allowcommencement of eastern side of Haymarket
• Beginning of 2016 Boulevard open and Tumbalong Park hoarded off.
• Tumbalong Park works completed in around 6 months• End of 2016 New Core Facility, western side of Haymarket and
Hotel opens• Completion of eastern side of Haymarket delivered
progressively with completion by early 2020’s.
DARLING HARBOUR LIVE
Preliminary Construction Staging (Cont)
PAGE 18
• Monorail closed end of June 2013• Demolition follows with Darling Harbour section planned to
be substantially complete by end of 2013• Convention Station and Paddy Market’s stations to be removed
by early 2014• Advice indicates extension of existing Ferry Service will be
difficultdue to access issues
• Ongoing discussions with Transport and City of Sydney on improved directional signage
• Ongoing discussions on shuttle bus to serve western edge and Convention Centre
• Glebe Island Event Day Ferry Service will stop at Darling Harbour
• Mid 2014 – opening of Inner west Light Rail extension and Light rail frequency increased to 6 per hour
• [2020] – opening of CBD and South East Light Rail – connectingDarling Harbour with Circular QuayDARLING HARBOUR LIVE
Transport
PAGE 19
Key Milestones
DARLING HARBOUR LIVE
ITEM DATE
Preferred Bidder announced 11 December 2012
Contract closed 22 March 2013
Exhibition of development applications for Core Facilities and the Haymarket
27 March 2013
Close of Exhibition period 10 May 2013
Exhibition of western area of Haymarket including commercial,residential and student housing
Early May 2013
Exhibition of Hotel development application June 2013
Construction of Glebe Island Expo commences June / July 2013
Closure of existing Convention & Exhibition facility 8 December 2013
Glebe Island Expo Opens December 2013
Demolition and construction of new facilities 2013 – 2016
Closure of Sydney Entertainment Centre End 2015
New facilities open End 2016