Page 1: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 1

DARLING HARBOUR LIVE

Darling Harbour Live

Page 2: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PPAAGGEE 22

DARLING HARBOUR LIVE

Entertainment Centre

Pyrmont/Ultimo

Powerhouse Museum

Exhibition Centre

Convention Centre

Tumbalong ParkChinatown

Darling Harbour

Page 3: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 3

DARLING HARBOUR LIVE

Page 4: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 4

DARLING HARBOUR LIVE

Page 5: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 5

DARLING HARBOUR LIVE

Page 6: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 6

DARLING HARBOUR LIVEICC Theatre

Page 7: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 7

DARLING HARBOUR LIVE

Page 8: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 8

DARLING HARBOUR LIVE

Page 9: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 9

DARLING HARBOUR LIVE

Page 10: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 10

DARLING HARBOUR LIVE

Page 11: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 11

DARLING HARBOUR LIVE

Page 12: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 12

DARLING HARBOUR LIVE

Page 13: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 13

DARLING HARBOUR LIVE

Page 14: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 14

ICC Hotel

DARLING HARBOUR LIVE

• Up to 900 room hotel• Equity and operation currently being finalised

Page 15: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 15

Glebe Island Expo

• Contracts and other documents being finalised• 25,000 m2 of exhibition space with a banquet facility• 1000 space car park• Event Ferry and Bus shuttle service

DARLING HARBOUR LIVE

Page 16: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 16

• Existing Convention, Exhibition Halls demolished first half of 2014

• Sydney Entertainment Centre (SEC) Car Park closes around end of January 2014 to allow demolition to commence

• Hoarding line around building / carpark perimeter• After demolition hoarding line is modified to reflect new

building form• End of 2015 structure of event buildings and Boulevard

substantially complete

DARLING HARBOUR LIVE

Preliminary Construction Staging

Page 17: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 17

• End of 2015 SEC closes and is demolished to allowcommencement of eastern side of Haymarket

• Beginning of 2016 Boulevard open and Tumbalong Park hoarded off.

• Tumbalong Park works completed in around 6 months• End of 2016 New Core Facility, western side of Haymarket and

Hotel opens• Completion of eastern side of Haymarket delivered

progressively with completion by early 2020’s.

DARLING HARBOUR LIVE

Preliminary Construction Staging (Cont)

Page 18: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 18

• Monorail closed end of June 2013• Demolition follows with Darling Harbour section planned to

be substantially complete by end of 2013• Convention Station and Paddy Market’s stations to be removed

by early 2014• Advice indicates extension of existing Ferry Service will be

difficultdue to access issues

• Ongoing discussions with Transport and City of Sydney on improved directional signage

• Ongoing discussions on shuttle bus to serve western edge and Convention Centre

• Glebe Island Event Day Ferry Service will stop at Darling Harbour

• Mid 2014 – opening of Inner west Light Rail extension and Light rail frequency increased to 6 per hour

• [2020] – opening of CBD and South East Light Rail – connectingDarling Harbour with Circular QuayDARLING HARBOUR LIVE

Transport

Page 19: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

PAGE 19

Key Milestones

DARLING HARBOUR LIVE

ITEM DATE

Preferred Bidder announced 11 December 2012

Contract closed 22 March 2013

Exhibition of development applications for Core Facilities and the Haymarket

27 March 2013

Close of Exhibition period 10 May 2013

Exhibition of western area of Haymarket including commercial,residential and student housing

Early May 2013

Exhibition of Hotel development application June 2013

Construction of Glebe Island Expo commences June / July 2013

Closure of existing Convention & Exhibition facility 8 December 2013

Glebe Island Expo Opens December 2013

Demolition and construction of new facilities 2013 – 2016

Closure of Sydney Entertainment Centre End 2015

New facilities open End 2016

Page 20: PAGE 1 DARLING HARBOUR LIVE Darling Harbour Live.

NSWGOVERNMENT