EXISTING CONDITIONS SURVEYS. NYP BEST PRACTICES. Presentation to Approved A/E Vendors to NYP June 17, 2013. - PowerPoint PPT Presentation
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: NYP BEST PRACTICES

1

NYP BEST PRACTICESEXISTING CONDITIONS SURVEYS

Presentation to Approved A/E Vendors to NYPJune 17, 2013

Page 2: NYP BEST PRACTICES

2

We

Put P

atien

ts F

irst

“…as we know, there are known knowns; there are things we know we know. We also know there are known unknowns; that is to say we know there are some things we do not know. But, there are also unknown unknowns – the ones we don’t know…”

Donald Rumsfeld

Page 3: NYP BEST PRACTICES

3

We

Put P

atien

ts F

irst • Create an accurate basis for developing scope, cost, schedule and design,

• Identify non-compliant conditions

• Minimize unknown project conditions

• Minimize change orders

Page 4: NYP BEST PRACTICES

4

We

Put P

atien

ts F

irst

Scope: Existing Conditions Boundaries

1. Projects NOT requiring DOH approval Project limits, Adjacent spaces (6 sides) as they are impacted by the limits of the base project, Potential decanting spaces

2. Projects requiring DOH approval Project limits, Adjacent spaces (6 sides) as they are impacted by the limits of the base project, Potential decanting spaces, Life safety code compliance: project limits plus entire smoke/fire compartment and egress path to public way FGI Guidelines: project limits plus entire smoke/fire compartment.

Project limits

Smoke/fire compartment

Egress path to the public way

Page 5: NYP BEST PRACTICES

5

We

Put P

atien

ts F

irst

Deliverables

FEASIBILITY PHASE1. General for all trades

• Review existing documentation,• Walk the total site, adjacent areas and ancillary spaces impacted by the project,• Outline of assumptions.

2. Architecture• Field survey, measurement and verification of existing architectural conditions,• Identification of areas requiring replacement or remediation,• Assessment of scope of work required in areas outside the project limits that will support the project such as

decanting space, mechanical rooms, IT rooms, etc,• Identification of building envelop components requiring remediation,• Identification of code upgrades within the project limits, smoke/fire compartment and the egress path (as

applicable to each project)3. Infrastructure (MEP, FP, IT, AV, Structural)

• Assessment of existing equipment condition and systems capacity ,• Documentation of existing building systems,• Definition of spatial requirements for new equipment,• Identification of areas requiring replacement or remediation.

4. Furniture/Finishes/Equipment• Assessment and documentation of furniture and equipment scheduled for reuse.

5. Hazardous materials • Identify requirement for environmental surveys.

Page 6: NYP BEST PRACTICES

6

We

Put P

atien

ts F

irst

Design Document PhaseVerification of existing conditions as applicable to the development of the design.

Construction Document PhaseConditions assessments should be complete prior to this phase.

Construction Administration PhaseVerification of existing conditions that could not be accessed during the feasibility and design phases .

Concealed and Inaccessible Conditions• Assume the “worst case” based on prior experience and professional judgment and request unit pricing where

possible,• Provide an appropriate opportunity in the construction phase to assess and re-evaluate conditions concealed

during the documentation phases,

Page 7: NYP BEST PRACTICES

7

Roles + ResponsibilitiesOwner: New York Presbyterian Hospital 1. Facilities Design & Construction

a. Manage process,b. Set expectations,c. Obtain commitments,d. Verify that commitments have been met,e. Provide requested reference material with respect to our facility (to the extent available),f. Retain appropriate consultants

• Hazardous Materials Consultant: abatement scope/cost/schedule,• Contractor/CM: support conditions investigations,• Commissioning Agent: Liaise with Facility Operations to provide information relative to existing

infrastructure systems. 2. Regulatory Compliance/Life Safety :

a. Provide baseline life safety drawings, a list of deficiencies (PFI’s) and waivers for non-compliant spaces.3. NYP/IT, AV, Security, BioMed, Signage, Environmental Services, Safety, Food Service, and the like

a. Provide information regarding existing equipment (to the extent available).

Consultant Team4. Provide a list of required information,5. Develop a probe plan,6. Present document assumptions related to existing conditions,7. Identify inaccessible areas that will require surveying during prior to final shop drawings or construction,8. Create existing conditions documents in the form of drawings, narratives and reports.

Page 8: NYP BEST PRACTICES

8

We

Put P

atien

ts F

irst

The Take Away

1. Project Limits do not equal Limits of the Work,

2. Existing conditions must include decanting areas and 6-sides impacted by the project

3. Existing conditions must be fully documented during the Feasibility Phase of the project,

4. Appropriate allowances and strategies must be developed to mitigate the cost and design

impact of concealed conditions.