NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 DATED 4/29/2011 Ladies/Gentlemen: Attached please find an addendum on the above captioned project. Included in the attachment is an adendum notification which details the changes and the respective proposal pages which were added and/ or changed. Except for new bid insert pages, it is unnecessary to return any of the pages attached. Bid insert pages must be returned with the bid proposal submitted to the Department, unless your firm is submitting a bid using a computer print out. The computer print out must be changed to reflect the new bid item information. Contractors and material suppliers, etc. who have previously been furnished informational proposals are not being furnished a copy of the addendum. If you have a subcontractor on the above project, please advise them of this addendum. Acknowledgment of this addendum is not requested if your company has been issued a proposal stamped “This Proposal Issued for Informational Purposes.” You are required to acknowledge receipt of this addendum on the Addendum Acknowledgement form contained in your bid proposal by placing a mark in the box next to the respective addendum. Failure to Acknowledge receipt of this addendum in your bid proposal will result in your bid not being read. 04/99 Control 0180-03-035, ETC. Project STP 1102(113), ETC. Highway SH 35 County ARANSAS
58

NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Feb 03, 2018

Download

Documents

lemien
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

NOTIFICATION OF ADDENDUM

ADDENDUM NO. 2

DATED 4/29/2011

Ladies/Gentlemen:

Attached please find an addendum on the above captioned project. Included in the attachment is an adendum notification which details the changes and the respective proposal pages which were added and/or changed.

Except for new bid insert pages, it is unnecessary to return any of the pages attached.

Bid insert pages must be returned with the bid proposal submitted to the Department, unless your firm is submitting a bid using a computer print out. The computer print out must be changed to reflect the new bid item information.

Contractors and material suppliers, etc. who have previously been furnished informational proposals are not being furnished a copy of the addendum. If you have a subcontractor on the above project, please advise them of this addendum. Acknowledgment of this addendum is not requested if your company has been issued a proposal stamped “This Proposal Issued for Informational Purposes.”

You are required to acknowledge receipt of this addendum on the Addendum Acknowledgement form contained in your bid proposal by placing a mark in the box next to the respective addendum.

Failure to Acknowledge receipt of this addendum in your bid proposal will result in your bid not being read.

04/99

Control 0180-03-035, ETC.Project STP 1102(113), ETC.Highway SH 35County ARANSAS

Page 2: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

1-2

SUBJECT: PLANS AND PROPOSAL ADDENDUMS PROJECT: STP 1102(113) CONTROL: 0180-03-035 COUNTY: ARANSAS LETTING: 05/04/2011 REFERENCE NO: 0426

PROPOSAL ADDENDUMS ------------------ _ PROPOSAL COVER X BID INSERTS (SH. NO.: 3-16,7-16, and 15-16 ) X GENERAL NOTES (SH. NO.: D,E,F,L-O,Q AND X (PLAN SHEETS 8A,8B,8E, 8F,8G, AND 8K) D-Z SHIFTED ) X SPEC LIST (SH. NO.: 3-5 AND 4-5 ) X SPECIAL PROVISIONS: ADDED: 440-004 DELETED: X SPECIAL SPECIFICATIONS: ADDED: 4586, 4576 DELETED: X OTHER: PLN SHTS 3,8A-8L,9,9A-9C,160-162,205,206,225,233,249, 250,252,255-257,259-261,263-265,267,268,269,339,354,361,& 464A DESCRIPTION OF ABOVE CHANGES (INCLUDING PLANS SHEET CHANGES) BID INSERTS SHEET 3-16 - DELETED ITEMS 409 2020 AND 409 2022 ADDED ITEM 409 2016 CHANGED QUANTITY FOR ITEM 409 2018 SHEET 7-16 - CHANGED QUANTITY FOR ITEM 502 2001 SHEET 15-16 - ADDED ITEMS 4586 2001, AND 4586 2002 CHANGED QUANTITY FOR ITEMS 4574 2001 AND 4574 2002 GENERAL NOTES SHEET D - ADDED NOTE "FOR THE PURPOSES OF SATISFYING REQUIREMENTS SET FORTH BY THE U.S. ARMY CORPS OF ENGINEERS PERMIT NO...." SHEET E - DELETED NOTES FOR ITEM 6 CHANGED WORKING DAYS FROM "CALENDAR DAY" TO "FIVE-DAY WORKWEEK" SHEET F - ITEM 8 DELETED NOTES ALLOWING NIGHTTIME WORK SHEET L - ITEM 409 ADDED NOTE "JETTING PILING TO REACH PENETRATION WILL NOT BE ALLOWED" ITEM 421 CHANGED PARAGRAPH INDICATED TO FURNISH TEST MOLDS FOR CYLINDRICAL CONCRETE "AS REQUIRED IN ASTM C31" SHEET M - ITEM 422 - ADDED NOTE DISALLOWING PERMANENT METAL DECK FORMS SHEET N- ITEM 440 ADDED NOTES INDICATED CONCERNING REINFORCING STEEL IN DESCRIPTION OF ABOVE CHANGES (CONTINUED) (INCLUDING PLANS SHEET CHANGES)

Page 3: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

2-2

BRIDGE GIRDERS AND PILING. SHEET O - ITEM 496 ADDED NOTE "REMOVAL OF THE EXISTING BRIDGE BY BLASTING WILL NOT BE PERMITTED." SHEET P - ITEM 500 ADDED NOTES CONCERNING WHAT THE CONTRACTOR SHOULD DO IN CASE OF A HURRICANE WATCH OR HURRICANE WARNING SHEET V - ITEM 4574 ADDED ALL NOTES FOR THIS ITEM SHEETS D-Z - SHIFTED DUE TO CHANGES MENTIONED ABOVE SPECIFICATION LIST SHEET 3-5 - THERE WERE NO CHANGES TO THIS SHEET. SP 440-004 WAS UPDATED SHEET 4-5 - ADDED SPECIAL SPECIFICATION 4586 SPECIAL SPECIFICATION 4576 WAS UPDATED PLAN SHEETS SHEET 3 - ADDED SHEET 464A TO INDEX OF SHEETS SHEET 9 - DELETED ITEMS 409 2020 AND 409 2022 ADDED ITEM 409 2016 CHANGED QUANTITY FOR ITEM 409 2018 SHEET 9A - CHANGED QUANTITY FOR ITEM 502 2001 SHEET 9B - CHANGED QUANTITY FOR ITEMS 4574 2001 AND 4574 2002 SHEET 9C - ADDED ITEMS 4586 2001,AND 4586 2002 SHEETS 160-162 - MADE MINOR DRAFTING CORRECTIONS SHEETS 205 AND 206 - REVISED MAX PILE LENGTHS AND TIP ELEVATIONS SHEET 225 - REVISED TIP ELEVATIONS SHEET 233 - CHANGED QUANTITY FOR 24" SQ CONCRETE PILING ADDED TABLE OF QUANTITIES FOR SS 4586 CHANGED NOTE 4 TO ITEM 421 SHEET 249 - ADDED NOTE 7 FOR SPLICES. SHEET 250 - ADJUSTED REINFORCING STEEL LENGTH AND QUANTITY SHEET 252 - ADDED NOTE 6 FOR SPLICES SHEET 255 - ADDED NOTE 9 FOR SPLICES SHEET 256 - ADDED NOTE 10 FOR SPLICES SHEET 257 - ADJUSTED REINFORCING STEEL LENGTH AND QUANTITY SHEET 259 - ADDED NOTE 8 FOR SPLICES SHEET 260 - ADDED NOTE 9 FOR SPLICES SHEET 261 - ADJUSTED REINFORCING STEEL LENGTH AND QUANTITY SHEET 263 - ADDED NOTE 12 FOR SPLICES SHEET 264 - ADDED NOTE 13 FOR SPLICES SHEET 265 - ADJUSTED REINFORCING STEEL LENGTH AND QUANTITY SHEET 267 - ADDED NOTE 11 FOR SPLICES SHEET 268 - ADDED NOTE 12 FOR SPLICES SHEET 269 - ADJUSTED REINFORCING STEEL LENGTH AND QUANTITY SHEET 339 - CHANGED CYLINDER PILE WEIGHT TO 974 PLF SHEETS 354 AND 361 - CHANGED THE LABELS FROM "STANDARD PENETRATION TEST" TO "TEXAS CONE PENETROMETER" SHEET 464A - ADDED THIS SHEET

Page 4: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

1-16

PROPOSAL SHEET PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

100 2002 002 PREPARING ROWDOLLARS

and CENTS

STA 83.800 1

104 2001 REMOVING CONC (PAV)

DOLLARSand CENTS

SY 738.000 2

104 2010 REMOVING CONC (RIPRAP)

DOLLARSand CENTS

CY 268.000 3

104 2040 REMOVING CONC (PAVERS)

DOLLARSand CENTS

SY 3,820.000 4

106 2001 OBLITERATING ABANDONED ROADDOLLARS

and CENTS

STA 35.760 5

110 2001 EXCAVATION (ROADWAY)DOLLARS

and CENTS

CY 2,663.000 6

110 2003 EXCAVATION (SPECIAL)DOLLARS

and CENTS

CY 23,038.000 7

132 2006 EMBANKMENT (FINAL)(DENS CONT)(TY C)

DOLLARSand CENTS

CY 16,547.000 8

134 2001 BACKFILL (TY A)

DOLLARSand CENTS

STA 65.200 9

158 2007 SPEC EXCAV WORK (UNDERWATER)

DOLLARSand CENTS

CY 1,600.000 10

162 2002 BLOCK SODDINGDOLLARS

and CENTS

SY 24,872.000 11

Page 5: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

2-16

164 2033 004 DRILL SEEDING (PERM) (RURAL) (SANDY)DOLLARS

and CENTS

SY 13,774.000 12

166 2002 001 FERTILIZER

DOLLARSand CENTS

TON .570 13

168 2001 VEGETATIVE WATERING

DOLLARSand CENTS

MG 624.500 14

247 2056 033 FL BS (CMP IN PLC)(TY D GR 4)(FNAL POS)

DOLLARSand CENTS

CY 5,802.000 15

275 2001 002 CEMENTDOLLARS

and CENTS

TON 218.000 16

275 2011 002 CEMENT TREAT(EXIST MATL)(8")DOLLARS

and CENTS

SY 17,276.000 17

310 2019 PRIME COAT (MC-30 OR SS-1)DOLLARS

and CENTS

GAL 3,279.000 18

316 2402 016 ASPH (AC-5, AC-10, CRS-2, OR HFRS-2)

DOLLARSand CENTS

GAL 6,220.000 19

316 2590 016 AGGR(TY PB GR 4 OR TY PB GR 4S)SAC-B

DOLLARSand CENTS

CY 188.000 20

341 2064 024 D-GR HMA(QCQA) TY-C SAC-B PG76-22

DOLLARSand CENTS

TON 4,780.000 21

341 2136 024 D-GR HMA(QCQA) TY-D SAC-B PG76-22DOLLARS

and CENTS

TON 16.000 22

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 6: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

3-16

341 2243 024 D-GR HMA(QCQA) TY-B SAC-B PG76-22DOLLARS

and CENTS

TON 2,861.000 23

354 2048 PLANE ASPH CONC PAV (3")

DOLLARSand CENTS

SY 898.000 24

354 2084 PLANE ASPH CONC PAV (3" TO 6")

DOLLARSand CENTS

SY 25,093.000 25

400 2005 CEM STABIL BKFL

DOLLARSand CENTS

CY 323.000 26

400 2006 CUT & RESTORING PAVDOLLARS

and CENTS

SY 82.000 27

409 2016 PRESTR CONC PIL (18 IN SQ)(HPC)DOLLARS

and CENTS

LF 320.000 28

409 2018 PRESTR CONC PIL (24 IN SQ)(HPC)DOLLARS

and CENTS

LF 27,844.000 29

416 2029 001 DRILL SHAFT (RDWY ILL POLE) (30 IN)

DOLLARSand CENTS

LF 124.000 30

420 2006 002 CL C CONC (RAIL FOUNDATION)

DOLLARSand CENTS

CY 13.100 31

420 2033 002 CL S CONC (APPR SLAB)

DOLLARSand CENTS

CY 125.100 32

420 2041 002 CL C CONC (ABUT)(HPC)DOLLARS

and CENTS

CY 88.800 33

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 7: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

4-16

420 2042 002 CL C CONC (BENT)(HPC)DOLLARS

and CENTS

CY 6,939.200 34

420 2123 002 CL C CONC (FOOTING) (HPC)

DOLLARSand CENTS

CY 2,467.200 35

420 2216 002 CL S CONC (SUPPORT SLAB)

DOLLARSand CENTS

CY 24.000 36

420 2258 002 CL F CONC (BENT)(HPC)

DOLLARSand CENTS

CY 4,741.600 37

422 2003 REINF CONC SLAB (HPC)(CL S)DOLLARS

and CENTS

SF 880,800.000 38

423 2005 RETAINING WALL (TEMP WALL)DOLLARS

and CENTS

SF 4,690.000 39

423 2014 RET WALL (SPREAD FOOTING)(SPL)DOLLARS

and CENTS

SF 5,982.000 40

425 2068 001 PRESTR CONC GIRDER (TX54)

DOLLARSand CENTS

LF 129,785.950 41

425 2070 001 PRESTR CONC GIRDER (TX70)

DOLLARSand CENTS

LF 1,794.000 42

428 2002 001 CONC SURF TREAT (CLASS II)

DOLLARSand CENTS

SY 93,177.000 43

432 2002 RIPRAP (CONC)(5 IN)DOLLARS

and CENTS

CY 228.000 44

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 8: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

5-16

432 2040 RIPRAP (MOW STRIP)(5 IN)DOLLARS

and CENTS

CY 32.200 45

432 2048 RIPRAP (CONC)(FLUME)

DOLLARSand CENTS

CY 5.700 46

432 2066 RIPRAP (CONC)(CL B)

DOLLARSand CENTS

CY 10.400 47

432 2072 RIPRAP (CONC)(CL B)(RR8&RR9)

DOLLARSand CENTS

CY 37.400 48

442 2048 016 STRUCTURAL STEEL(MISC NON-BRIDGE)DOLLARS

and CENTS

LB 6,034.000 49

442 2052 016 STR STL (ROLLED BEAM)(HP 12X54)DOLLARS

and CENTS

LB 100,700.000 50

442 2053 016 STR STL (ROLLED BEAM)(WT 8X20)DOLLARS

and CENTS

LB 9,000.000 51

450 2161 001 RAIL (TY T223)

DOLLARSand CENTS

LF 22,665.000 52

454 2001 SEALED EXPANSION JOINT (4 IN)(SEJ-A)

DOLLARSand CENTS

LF 2,560.000 53

464 2003 003 RC PIPE (CL III)(18 IN)

DOLLARSand CENTS

LF 371.000 54

464 2005 003 RC PIPE (CL III)(24 IN)DOLLARS

and CENTS

LF 48.000 55

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 9: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

6-16

465 2005 001 MANH (COMPL)(TY M)DOLLARS

and CENTS

EA 1.000 56

467 2222 SET (TY II)(18 IN)(RCP)(4:1)(C)

DOLLARSand CENTS

EA 1.000 57

467 2224 SET (TY II)(24 IN)(RCP)(4:1)(C)

DOLLARSand CENTS

EA 2.000 58

467 2236 SET (TY II)(24 IN)(RCP)(6:1)(C)

DOLLARSand CENTS

EA 1.000 59

467 2285 SET (TY II)(15 IN)(RCP)(6:1)(P)DOLLARS

and CENTS

EA 2.000 60

467 2286 SET (TY II)(18 IN)(RCP)(6:1)(P)DOLLARS

and CENTS

EA 8.000 61

474 2005 SLOT DRAIN (GAL STL)(18 IN)DOLLARS

and CENTS

LF 20.000 62

474 2006 SLOT DRAIN OUTFALL (GAL STL)(18 IN)

DOLLARSand CENTS

LF 4.000 63

480 2001 CLEAN EXIST CULVS

DOLLARSand CENTS

EA 1.000 64

496 2004 REMOV STR (SET)

DOLLARSand CENTS

EA 2.000 65

496 2007 REMOV STR (PIPE)DOLLARS

and CENTS

LF 240.000 66

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 10: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

7-16

496 2012 REMOV STR (BRIDGE 1000 FT OR GREATER)DOLLARS

and CENTS

EA 1.000 67

496 2082 REMOVE STRUCTURES (FENDER)

DOLLARSand CENTS

EA 1.000 68

500 2001 005 MOBILIZATION

DOLLARSand CENTS

LS 1.000 69

502 2001 055 BARRICADES, SIGNS AND TRAFFIC HAN-

DLINGDOLLARS

and CENTS

MO 42.000 70

502 2047 055 OFF-DUTY POLICE OFFICER

DOLLARSand CENTS

HR 80.000 71

506 2017 011 CONSTRUCTION EXITS (INSTALL) (TY 2)

DOLLARSand CENTS

SY 156.000 72

506 2019 011 CONSTRUCTION EXITS (REMOVE)

DOLLARSand CENTS

SY 156.000 73

508 2002 CONSTRUCTING DETOURSDOLLARS

and CENTS

SY 4,788.000 74

512 2004 002 PORT CTB (FUR & INST)(SNGL SLP)(TY 1)DOLLARS

and CENTS

LF 12,720.000 75

512 2022 002 PORT CTB (MOVE)(SNGL SLP) (TY 1)DOLLARS

and CENTS

LF 4,200.000 76

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 11: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

8-16

512 2040 002 PORT CTB (REMOVE)(SNGL SLP) (TY 1)DOLLARS

and CENTS

LF 12,720.000 77

514 2004 002 PERM CONC TRF BARR (SGL SLP)(TY 1)(42")

DOLLARSand CENTS

LF 10,655.000 78

514 2022 002 PERM CONC TRF BARR (SGL SLP)(TY 4)(42")

DOLLARSand CENTS

LF 510.000 79

530 2008 DRIVEWAYS (ACP)

DOLLARSand CENTS

EA 2.000 80

530 2011 DRIVEWAYS (ACP)DOLLARS

and CENTS

SY 1,240.000 81

530 2017 TURNOUTS (ACP)DOLLARS

and CENTS

SY 1,020.000 82

540 2011 023 MTL BEAM GD FEN TRANS (THRIE-BEAM)DOLLARS

and CENTS

EA 4.000 83

542 2001 REMOVING METAL BEAM GUARD FENCE

DOLLARSand CENTS

LF 1,475.000 84

544 2003 001 GUARDRAIL END TREATMENT (REMOVE)

DOLLARSand CENTS

EA 3.000 85

544 2005 001 GDRAIL END TRT(INST)(WOOD POST)(TY II)

DOLLARSand CENTS

EA 1.000 86

545 2049 CRASH CUSH ATTEN (INSTL)(WORK ZONE)DOLLARS

and CENTS

EA 8.000 87

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 12: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

9-16

545 2050 CRASH CUSH ATTEN(MOV&RESET)(WORK ZONE)

DOLLARSand CENTS

EA 1.000 88

545 2051 CRASH CUSH ATTEN (REMOVE)(WORK ZONE)

DOLLARSand CENTS

EA 9.000 89

545 2058 CRASH CUSH ATTEN (INSTL) (N)

DOLLARSand CENTS

EA 4.000 90

545 2059 CRASH CUSH ATTEN (MOVE & RESET) (N)

DOLLARSand CENTS

EA 6.000 91

545 2060 CRASH CUSH ATTEN (REMOVE) (N)DOLLARS

and CENTS

EA 1.000 92

610 2025 010 INS RD IL AM (TY SA) 40T-8 (.25 KW)SDOLLARS

and CENTS

EA 8.000 93

610 2042 010 INS RD IL AM (TY SA) 50T-8 (.4 KW)SDOLLARS

and CENTS

EA 6.000 94

610 2045 010 INS RD IL AM (TY SP) 38S-8-8 (.25 KW)S

DOLLARSand CENTS

EA 18.000 95

610 2072 010 REMOVE RDWY ILL ASSEM

DOLLARSand CENTS

EA 1.000 96

617 2004 001 TEMP RD IL (RD IL ASM)

DOLLARSand CENTS

EA 2.000 97

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 13: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

10-16

618 2018 CONDT (PVC) (SCHD 40) ( 2")DOLLARS

and CENTS

LF 28,650.000 98

618 2019 CONDT (PVC) (SCHD 40) (2") (BORE)

DOLLARSand CENTS

LF 385.000 99

618 2022 CONDT (PVC) (SCHD 40) (3")

DOLLARSand CENTS

LF 10.000 100

620 2003 001 ELEC CONDR (NO. 2) BARE

DOLLARSand CENTS

LF 5,140.000 101

620 2004 001 ELEC CONDR (NO. 2) INSULATEDDOLLARS

and CENTS

LF 20,560.000 102

620 2011 001 ELEC CONDR (NO. 8) BAREDOLLARS

and CENTS

LF 3,075.000 103

620 2012 001 ELEC CONDR (NO. 8) INSULATEDDOLLARS

and CENTS

LF 6,810.000 104

624 2008 014 GROUND BOX TY A (122311) W/APRON

DOLLARSand CENTS

EA 6.000 105

628 2158 001 REMOVE ELECTRICAL SERVICES

DOLLARSand CENTS

EA 1.000 106

628 2177 001 ELC SRV TY A 240/480 100 (NS)SS(E)GC(O)

DOLLARSand CENTS

EA 1.000 107

628 2220 001 ELC SRV TY A 240/480 100 (NS)SS(E)GC(U)DOLLARS

and CENTS

EA 1.000 108

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 14: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

11-16

636 2001 014 ALUMINUM SIGNS (TY A)DOLLARS

and CENTS

SF 27.000 109

644 2022 INS SM RD SN SUP&AM TY S80(1) SA(P)

DOLLARSand CENTS

EA 33.000 110

644 2025 INS SM RD SN SUP&AM TY S80(1) SA(T)

DOLLARSand CENTS

EA 13.000 111

644 2026 INS SM RD SN SUP&AM TY S80(1)SA(T-2EXT)

DOLLARSand CENTS

EA 4.000 112

644 2042 INS SM RD SN SUP&AM TY S80(2) SA(P)DOLLARS

and CENTS

EA 1.000 113

644 2058 RELOCATE SM RD SN SUP & AM TY S80DOLLARS

and CENTS

EA 64.000 114

644 2060 REMOVE SM RD SN SUP & AMDOLLARS

and CENTS

EA 64.000 115

644 2063 INS SM RD SN SUP&AM (RAIL MOUNT)

DOLLARSand CENTS

EA 5.000 116

658 2240 006 INSTL DEL ASSM (D-SW)SZ 1(FLX)GF2

DOLLARSand CENTS

EA 2.000 117

658 2258 006 INSTL DEL ASSM (D-SW)SZ (TYC)CTB

DOLLARSand CENTS

EA 227.000 118

658 2278 006 INSTL DEL ASSM (D-SY)SZ (TYC)CTB(BI)DOLLARS

and CENTS

EA 112.000 119

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 15: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

12-16

658 2316 006 INSTL OM ASSM (OM-2Z)(FLX)GNDDOLLARS

and CENTS

EA 5.000 120

662 2001 WK ZN PAV MRK NON-REMOV (W) 4" (BRK)

DOLLARSand CENTS

LF 169.000 121

662 2012 WK ZN PAV MRK NON-REMOV (W) 8" (SLD)

DOLLARSand CENTS

LF 1,993.000 122

662 2032 WK ZN PAV MRK NON-REMOV (Y) 4" (SLD)

DOLLARSand CENTS

LF 9,952.000 123

662 2052 WK ZN PAV MRK REMOV (REFL) TY I-CDOLLARS

and CENTS

EA 2,185.000 124

662 2054 WK ZN PAV MRK REMOV (REFL) TY II-A-ADOLLARS

and CENTS

EA 2,220.000 125

662 2060 WK ZN PAV MRK REMOV (TRAF BTN) TY WDOLLARS

and CENTS

EA 6,556.000 126

662 2062 WK ZN PAV MRK REMOV (TRAF BTN) TY Y

DOLLARSand CENTS

EA 6,660.000 127

662 2070 WK ZN PAV MRK REMOV (W) 6" (LNDP)

DOLLARSand CENTS

LF 60.000 128

662 2079 WK ZN PAV MRK REMOV (W) 24" (SLD)

DOLLARSand CENTS

LF 36.000 129

662 2104 WK ZN PAV MRK REMOV (Y) 12" (SLD)DOLLARS

and CENTS

LF 240.000 130

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 16: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

13-16

662 2113 WK ZN PAV MRK SHT TERM (TAB) TY WDOLLARS

and CENTS

EA 1,483.000 131

662 2115 WK ZN PAV MRK SHT TERM (TAB) TY Y-2

DOLLARSand CENTS

EA 2,165.000 132

666 2035 REFL PAV MRK TY I (W) 8" (SLD)(090MIL)

DOLLARSand CENTS

LF 5,315.000 133

668 2100 PREFAB PAV MRK TY C (W) ( 8") (LNDP)

DOLLARSand CENTS

LF 136.000 134

668 2105 PREFAB PAV MRK TY C (W) (24") (SLD)DOLLARS

and CENTS

LF 48.000 135

668 2106 PREFAB PAV MRK TY C (W) (ARROW)DOLLARS

and CENTS

EA 13.000 136

668 2116 PREFAB PAV MRK TY C (W) (WORD)DOLLARS

and CENTS

EA 13.000 137

668 2128 PREFAB PAV MRK TY C (Y) (24") (SLD)

DOLLARSand CENTS

LF 3,272.000 138

672 2012 034 REFL PAV MRKR TY I-C

DOLLARSand CENTS

EA 557.000 139

672 2015 034 REFL PAV MRKR TY II-A-A

DOLLARSand CENTS

EA 918.000 140

677 2001 ELIM EXT PAV MRK & MRKS ( 4")DOLLARS

and CENTS

LF 32,098.000 141

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 17: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

14-16

677 2003 ELIM EXT PAV MRK & MRKS ( 8")DOLLARS

and CENTS

LF 6,471.000 142

677 2007 ELIM EXT PAV MRK & MRKS (24")

DOLLARSand CENTS

LF 909.000 143

682 2025 001 VEH SIG SEC (12 IN) LED (YEL)

DOLLARSand CENTS

EA 4.000 144

682 2027 001 VEH SIG SEC (12 IN) LED (RED)

DOLLARSand CENTS

EA 2.000 145

685 2003 025 REMOVE RDSD FLASH BEACON ASSEMBLYDOLLARS

and CENTS

EA 3.000 146

685 2004 025 INSTL RDSD FLSH BEACON ASSM(SOLAR PWRD)

DOLLARSand CENTS

EA 3.000 147

730 2002 FULL-WIDTH MOWING

DOLLARSand CENTS

AC 7.990 148

4574 2001 PRESTRESSED CONCRETE PILING (54 IN CYL)

DOLLARSand CENTS

LF 49,149.000 149

4574 2002 PRESTRESSED CONCRETE PILING (66 IN

CYL)DOLLARS

and CENTS

LF 1,442.000 150

4575 2001 UHMW-PE FENDER PADS (2 1/4 IN)DOLLARS

and CENTS

SF 1,900.000 151

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 18: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

15-16

4576 2001 STEEL PIPE PILING (24 IN DIA X 1/2 IN)DOLLARS

and CENTS

LF 4,000.000 152

4580 2001 CONSTRUCTION ACCESS

DOLLARSand CENTS

LS 1.000 153

4586 2001 DYNAMIC PILE MONITORING

DOLLARSand CENTS

EA 34.000 154

4586 2002 DYNAMIC ANALYSIS

DOLLARSand CENTS

EA 34.000 155

5049 2002 BIODGRD EROSION CONTROL LOGS (18" DIA)

DOLLARSand CENTS

LF 7,156.000 156

5049 2003 BIODGRD EROSION CONTROL LOGS (12"

DIA)DOLLARS

and CENTS

LF 2,349.000 157

5261 2001 GEOGRID REINFORCEMENT (TY I)DOLLARS

and CENTS

SY 17,960.000 158

5430 2001 FLOATING TURBIDITY BARRIER

DOLLARSand CENTS

LF 3,600.000 159

6473 2001 001 MULTIPOLYMER PAV MRK (W)(4")(SLD)

DOLLARSand CENTS

LF 22,020.000 160

6473 2002 001 MULTIPOLYMER PAV MRK (W)(4")(BRK)

DOLLARSand CENTS

LF 4,816.000 161

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 19: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

16-16

6473 2007 001 MULTIPOLYMER PAV MRK (W)(8")(SLD)DOLLARS

and CENTS

LF 330.000 162

6473 2011 001 MULTIPOLYMER PAV MRK (Y)(4")(SLD)

DOLLARSand CENTS

LF 22,020.000 163

6473 2025 001 MULTIPOLYMER PAV MRK (W)(ARROW)

DOLLARSand CENTS

EA 1.000 164

6473 2026 001 MULTIPOLYMER PAV MRK (W)(WORD)

DOLLARSand CENTS

EA 1.000 165

6834 2001 PORTABLE CHANGEABLE MESSAGE SIGNDOLLARS

and CENTS

DAY 800.000 166

8251 2002 005 RE PM W/RET REQ TY I(W)4"(BRK)(090MIL)DOLLARS

and CENTS

LF 645.000 167

8251 2005 005 RE PM W/RET REQ TY I(W)4"(SLD)(090MIL)DOLLARS

and CENTS

LF 12,659.000 168

8251 2014 005 RE PM W/RET REQ TY I(Y)4"(BRK)(090MIL)

DOLLARSand CENTS

LF 58.000 169

8251 2017 005 RE PM W/RET REQ TY I(Y)4"(SLD)(090MIL)

DOLLARSand CENTS

LF 18,409.000 170

8705 2001 SOLAR-POWERED NAVIGATIONAL LIGHT-

ING SYSDOLLARS

and CENTS

LS 1.000 171

PROPOSAL SHEETPROJECT STP 1102(113) , ETC. TxDOTCOUNTY ARANSAS FORM 234-B I-61-5M

ALT

ITEM-CODE

UNIT BID PRICE ONLY.WRITTEN IN WORDS UNIT

APPROXQUANTITIES

DEPTUSE

ONLYITEM

NODESCCODE

S.P.NO.

Page 20: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 GENERAL NOTES: General Notes Find, for your information and convenience, tools such as forms, software, materials, and various other information provided by the Department at http://www.dot.state.tx.us/business/. Please note that these tools are updated periodically and your attention is directed to the latest edition. In the event of a called evacuation, emergencies, impending adverse weather or as directed, do not perform any work without written authorization. The District reserves the right to suspend all work in support of evacuations or emergencies occurring from other parts of the state. Any work performed, other than work directed by the Department, is unauthorized work in accordance with Item 5. Sweep, clean and remove any construction waste, surplus materials or debris from the roadway and right of way at the end of each day unless otherwise approved. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. The asphalt season for the placement of asphalt surface courses is March 15 to November 15 unless otherwise approved. Cut existing pavement using a saw or other approved method to ensure a neat transverse and/or longitudinal line to assure a smooth tie-in with new pavement. Cut to a minimum depth of the final lift thickness. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. Promptly pick up and properly dispose of paper and other materials used for pavement joints. Stencil the National Bridge Inventory (NBI) number on each bridge and bridge class culvert. Use 3” letters or numbers. Use stain and color as approved. Paint will not be permitted. Locate the NBI number on the outside beam immediately adjacent to the abutment on the downstream end, on the outside headwall upper right-hand corner, or as directed. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. All pavement markings shall be in accordance with the latest edition of Texas MUTCD.

This project will have a US Coast Guard Bridge Permit. The following requirements apply:

1. Do not deviate from the approved plans without approval from the Commander, Eighth Coast Guard District.

General Notes Sheet A

Page 21: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35

2. Obtain approval from the USCG District Commander prior to implementation of construction of false-work, cofferdams or other obstructions.

3. Conduct all work in a manner that does not impede navigation or impair the depths of the channel.

4. Notify the USCG District Commander of any and all events affecting navigation during construction in a timely manner.

5. Promptly clear the channel of all obstructions due to construction as deemed necessary by the USCG District Commander.

6. Remove in their entirety, all parts of the Fender System not utilized in the completed system, for the bridge across the Copano Bay, mile 0.0, west of Harvey Lock. The waterway shall be cleared to the satisfaction of the USCG District Commander.

Notify the USCG District Commander three (3) weeks prior to beginning work. Submit a construction plan for approval, containing a description of the equipment, such as barges and tugs that may occupy the waterway, and how they may affect navigation, and a detailed work schedule.

Operate all water-going vessels, barges, etc. in accordance with USCG regulations. The U.S. Corps of Engineers Notice to Proceed permit number for this project is SWG-2010-00887. TxDOT will not issue a Notice to Proceed until the USCG Bridge Permit is issued. TxDOT will ensure that the Contractor complies with all conditions of the USCG Bridge Permit.. Do not initiate activities in a project specific location (PSL) associated with a U.S. Army Corps of Engineers (USACE) permit area that have not been previously evaluated by the USACE as part of the permit review of this project. Such activities include, but are not limited to, haul roads, equipment staging areas, borrow and disposal sites. Associated defined here means materials are delivered to or from the PSL. The permit area includes all waters of the U.S. or associated wetlands affected by activities associated with this project. Special restrictions may be required for such work. Be responsible for any and all consultations with the USACE regarding ALL activities, including project specific locations (PSL) not YET evaluated by the USACE. Provide the department with a copy of all consultations or approvals from the USACE prior to initiating activities. Proceed with activities in PSLs that do not affect a USACE permit area if the USACE determines that the PSL is non-jurisdictional or that the USACE granted proper clearance for the jurisdictional areas or as part of the permit review of this project, the USACE previously evaluated the PSL. Take sole responsibility for documenting any determinations that activities do not affect a USACE permit area. Maintain copies of determinations for review by the department or any regulatory agency.

General Notes Sheet B

Page 22: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 Document and coordinate with the USACE, if required, prior to any excavation hauled from or embankment hauled into a USACE permit area by either (1) or (2) below.

(1) Restricted Use of Materials for the Previously Evaluated Permit Areas. Document both the project specific location (PSL) and their authorization. Maintain copies for review by the department or any regulatory agency. When an area within the project limits has been evaluated by the USACE as part of the permit process for this project:

a. Suitable excavation of required material in the areas shown on the plans and cross sections as specified in Item 110 is used for permanent or temporary fill (Item 132, Embankment) within a USACE permit area;

b. Suitable embankment (Item 132) from within the USACE permit area is used as fill within a USACE evaluated area; and,

c. Unsuitable excavation or excess excavation [“Waste”] (Item 110) that is disposed of at a location approved by the Engineer within a USACE evaluated area.

(2) Contractor Materials from Areas Other than Previously Evaluated Areas. Provide the department with a copy of all USACE coordination or approvals prior to initiating any activities for an area within the project limits that has not been evaluated by the USACE or for any off right of way locations used for the following, but not limited to, haul roads, equipment staging areas, borrow and disposal sites:

a. Item 132, Embankment, used for temporary or permanent fill within a USACE permit area; and,

b. Unsuitable excavation or excess excavation [“Waste”] (Item 110, Excavation) that is disposed of outside a USACE evaluated area.

This project requires permits with environmental resource agencies. There is a high probability of encountering environmentally sensitive areas on Contractor designated project specific locations (PSL) for this project (haul roads, equipment staging areas, borrow pits, disposal sites, field offices, storage areas, parking areas, etc.). Listings of regulatory agencies the Contractor may need to contact for this project are provided herein. Environmental issues and PSL coordination requirements will be addressed in permits. The locations of the underground utility installations are unknown. Confirm the location of any installations which may exist. Assume full responsibility of the notification to the utility involved in case of conflict or damage and be responsible for damage that occurs due to negligence. This work is subsidiary to the various bid items of the contract. Assume ownership for all designated waste material and dispose of it at a place off of the right of way, as approved by the Engineer.

General Notes Sheet C

Page 23: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 For the purposes of satisfying requirements set forth by the U.S. Army Corps of Engineers Permit No. SWG-2010-00887 the contractor performing work on behalf of TxDOT will be referred to as the permittee. As part of the requirements under SWG-2010-00887, the permittee shall collect and relocate oyster reef permanently impacted during bridge pile construction. TxDOT has estimated approximately 1,660 cubic yards of oyster reef material will be relocated as a result of the bridge pile construction. The permittee will be required to clean the collected oyster reef material of sediment and debris prior to the material relocation. The permittee shall relocate collected oyster reef material to a previously approved oyster reef restoration site in Copano Bay authorized under the Harte Research Institute permit SWG-2010-00246. The permittee will coordinate all efforts with TxDOT during collection and relocation to ensure requirements under Permit SWG-2010-00887 are completed. The permittee shall not deposit collected oyster reef material until the permittee has received GPS coordinates (latitude/longitude) from TxDOT. Based on data from NMFS and the Harte Research Institute, the relocation site is within three miles from the current bridge location in varying depths of water from two to four feet. The relocated oyster reef will be placed to construct a 3-dimensional reef complex with high vertical relief to enhance habitat and protect an eroding shoreline while minimizing sedimentation. Because complex reef structures provide habitat for numerous fish and invertebrate species, the permittee will construct the reef as a series of reef ridges where “hills and valleys” are required design parameters. The permittee shall use silt curtains during construction around oyster reefs to minimize sedimentation in the surrounding water column. ITEM 2 It is recommended that prospective bidders examine the specified work locations with the Engineer to view the nature of the work, the need for close coordination with the various utilities, traffic control considerations, and other factors influencing the prosecution of the work. ITEM 5 Field verify all dimensions and notify Engineer prior to initiating any work. Verify the locations of utilities, underground or overhead, shown within the limits of the right-of-way. Adhere to OSHA Standards when working within the vicinity of overhead power lines. Coordinate with the utility companies and notify the Engineer of any possible conflicts. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. Notify the Engineer immediately of utility conflicts in accordance with Item 5.5.B. Refer to Item 4.3 for consideration of differing site conditions. Prospective bidders may borrow reproducible earthwork cross-sections from the Area Engineer's office for making copies with a minimum twenty-four (24) hour notice. The responsibility for the construction surveying on this contract will be in accordance with Item 5.6.A, “Method A”.

General Notes Sheet D

Page 24: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 Provide safe access to the construction work areas, including vessel transportation (if necessary) to and from the mainland as requested by the Engineer, for the Engineer and inspector to observe and inspect the work. Provide platform or work barge to allow inspection of works at bents in Copano Bay. ITEM 7 The work performed for Item 7.7, “Public Safety and Convenience” will not be measured or paid for directly, but will be subsidiary to pertinent Items. When working at street, farm-to-market, state highway, and county road intersections, schedule work to minimize intersection closures. During nonworking hours, all public road intersections will be open to the traveling public. The total disturbed area for this project is 8 acres. The disturbed area in this project, all project locations in the Contract, and Contractor project specific locations (PSLs), within 1 mile of the project limits, for the Contract will further establish the authorization requirements for storm water discharges. The Department will obtain an authorization to discharge storm water from the Texas Commission on Environmental Quality (TCEQ) for the construction activities shown on the plans. The Contractor is to obtain any required authorization from the TCEQ for any Contractor PSLs for construction support activities on or off ROW. When the total area disturbed for all projects in the Contract and PSLs within 1 mile of the project limits exceeds 5 acres, provide a copy of the Contractor NOI for PSLs on the ROW to the Engineer. Establish uniform perennial vegetative coverage with a density of at least 70% of the native background vegetative cover to achieve final stabilization. Comply with the Texas Aggregate Quarry and Pit Safety Act for waste areas or material source areas resulting from this project. ITEM 8 Prepare the progress schedule using the Critical Path Method (CPM). Submit (2) two 11” x 17” hard copies and an electronic file of the original or updated progress schedule. Submit the original progress schedule seven (7) days before the Preconstruction Conference. Submit an updated progress schedule as directed to show proposed major changes, changes affecting compliance with the contract requirements, or changes affecting the critical path/controlling item of work. Working days will be computed and charged in accordance with Article 8.3.A.1, “Five-Day Workweek”.

General Notes Sheet E

Page 25: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 Work above traffic is not allowed. Lane closures are not permitted Monday through Friday before 8 AM or after 5 PM unless approved. For this project, the earliest start work date will be November 14, 2011. ITEM 9 Submit the approved forms to request compensation for material-on-hand (MOH) at least three (3) working days prior to the end of the month. Include any requests from subcontractors, suppliers, or fabricators. ITEM 100 Coordinate all right of way preparation activities with the project’s Storm Water Pollution Prevention Plan (SWP3) and Environmental Permit Issues, and Commitments Sheet (EPIC) or as approved. Prepare the right of way from STA 435+00(A) to STA 446+80(A), STA 556+90(A) to STA 564+60.16(A) = STA 1+30.59 (A) and STA 1+30.59(A) to STA 4+70.43(A). Remove and dispose of all obstructions shown and not specifically shown in the plans. Prune trees and shrubs as directed. Use accepted pruning practices in accordance with Item 192 and as defined by the National Arborist Association. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. ITEM 110 For earth cuts, manipulate and compact subgrade in accordance with Item 132.3.D.2, “Compaction Methods, Density Control”. ITEM 132 Use embankment material with a plasticity index (PI) ranging from 10 to 40. Blend or treat approved materials to achieve the desired PI and pulverize the material so that 100% passes the 3 inch sieve. Retest materials as borrow sources change or when the material changes significantly. Notify the Engineer of the proposed material sources and of changes to material sources. The Engineer may sample and test project materials at any time before compaction

General Notes Sheet F

Page 26: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 throughout the duration of the project to assure specification compliance. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. Obtain approval to incorporate existing salvaged asphaltic surface and flexible base materials in the surface layer. If approved, incorporate existing materials no larger than 2 inches in the surface layer. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. The estimated quantities for embankments adjacent to culverts and bridges were calculated using the average-end-area method. ITEM 134 Backfill pavement edges with reclaimable asphalt material (R.A.P.). Use backfill material with a plasticity index (PI) ranging from 15 to 35. Notify the Engineer of the proposed material sources and of changes to material sources. The Engineer may sample and test project materials at any time before compaction throughout the duration of the project to assure specification compliance. Windrow the existing topsoil and grass along the edge of the grading operations or as directed. After grading operations are completed, spread the topsoil and grass uniformly on all slopes and ditch lines. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. Manipulate and compact backfill material in accordance with Item 132.3.D.1, “Ordinary Compaction”. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. ITEM 162 Furnish and place Bermuda block sod. ITEM 164 Restore and seed areas not shown in the plans disturbed by the Contractor’s operations. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items.

General Notes Sheet G

Page 27: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 Notify the Engineer of the unavailability of any seed mix. Make changes to the seed mix as approved. Use a tacking agent of 50% SS-1 and 50% water and apply the agent at a rate of 0.10 gal/sy or as directed. A biodegradable tacking agent may be used in lieu of the SS-1 tacking agent in accordance with the manufacturer’s recommendations when approved. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. ITEM 166 Fertilize all areas of the project to be seeded or sodded. Furnish and apply fertilizer with analysis of 16-8-8 at a rate of 375 bulk pounds per acre. ITEM 168 Distribute water to only those areas shown in the plans or as directed. Excessive overspray will not be permitted. Water all areas of the project to be seeded or sodded every two (2) days for 90 days or as directed. Apply water in a manner to ensure adequate moisture but not to erode the soil in-place. During periods of adequate moisture, mechanical watering may not be required as approved. Upon final stabilization, the Engineer may require to continue watering as specified for a period not to exceed 30 days. The Basis of Estimate below establishes the approximate quantity of water required to complete the 90-day watering cycle:

Water Required to Complete the 90-day Watering Cycle Rate

(inch / week) Water

(Gal / Acre / Month) Area

(Acre) Total Gallons

(Gal / Acre / 3 Months)0.25 26,000 1 78,000

ITEM 247 The Engineer may accept material during stockpile operations, from completed stockpiles, or windrows. The Engineer will select any of these locations or any combination thereof with the provision that at least one out of ten consecutive samples will be taken at the project site.

General Notes Sheet H

Page 28: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 When requested, stake with blue tops, at 100-foot intervals, the lines and grade shown in the plans. Conform to the following flexible base (TY D GR 4) requirements: Table 1. Material Requirements

Percent Retained on each Sieve Soil Constants Wet Ball 2” 1-1/4” 7/8” 1/2" #4 #40 LL Max PI Max PI Min Mill Max 0 -- -- 20-60 40-75 60-85 -- 10 -- *45

*The maximum increase in material passing the No. 40 sieve is not to exceed 20.

For Table 1, “Material Requirements” there is no minimum plasticity index (PI) required for TY D, GR 4 material. Type D material consists of crushed stone produced and graded from oversize quarried aggregate that originates from a single, naturally occurring source. For this project Test Method Tex-117-E shall conform to the following minimum compressive strength requirements:

Lateral Pressure Triaxial Strength

15 psi 175 psi

If the contractor elects to use crushed concrete, it shall be stabilized with 3% cement by weight. This cement will not be paid for directly but will be considered subsidiary. ITEM 275 Cement and/or asphalt stabilized base may be encountered in the existing pavement structure. Pulverize or scarify the existing material after shaping so that 100% passes a 2-1/2 inch sieve. Use a mechanical mixer to mix the cement with the existing base material. Prime flexible base by applying a bituminous material at the rates of application shown for Item 310, “Prime Coat”.

General Notes Sheet I

Page 29: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 ITEM 302 Provide aggregates with a minimum surface aggregate classification (SAC) of “B” unless otherwise shown. The SAC for sources on the Department’s Aggregate Quality Monitoring Program (AQMP) is listed in the Department’s Bituminous Rated Source Quality Catalogue (BRSQC). SAC requirements apply to aggregates used on all final roadway surfaces, including shoulders. Precoated aggregate Type PB consists of crushed slag, crushed stone, or limestone rock asphalt (LRA). When using asphalt emulsion, use a precoat material for the aggregates as approved. ITEM 310 Use MC-30 or SS-1 at a rate of 0.20 gallons per square yard or as directed. Use SS-1 at the rate of 0.20 gallons per square yard per inch or as directed. Use a mixture of 10% SS-1 and 90% water and work the mixture into the top 2 inches of the flexible base surface. The water will not be measured or paid for directly, but will be subsidiary to pertinent Items. ITEM 316 Clean aggregates showing signs of excessive dust from the stockpile or while handling during construction. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. Do not place surface treatment on exposed concrete structures unless directed. Furnish a distributor equipped with a hand hose in working condition. Material rates shown are for estimating purposes only. Adjust actual rates based on the material used, the existing condition and type of roadway surface, and as approved. When using asphalt emulsion, a minimum 24-hour curing period is required before placing any subsequent asphalt courses. Stockpiling of aggregates may begin after the execution of the Authorization to Begin Work or issuance of the work order. Remove vegetation and blade pavement edges prior to surfacing operations. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items.

General Notes Sheet J

Page 30: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 Broom and clean sealed sections of roadway and all adjacent paved surfaces, including the gutter line, of any surplus aggregate before opening to traffic or as directed. ITEM 320 Provide the type of windrow pick-up equipment for approval prior to beginning paving operations. Use of motor grader will not be permitted unless approved. ITEM 341 Provide aggregates with a minimum surface aggregate classification (SAC) of “B” unless otherwise shown. SAC requirements apply to aggregates used on all final roadway surfaces, including shoulders. As per special provision 341-024, use of Contractor-owned RAP including HMA plant waste will be permitted. Department-owned RAP generated through required work on the Contract is available for the Contractor’s use. Any RAP remaining from the contract is to remain with the Contractor. Use crushed gravel screenings with or in lieu of stone screenings. Use a cut-off chute when placing hot-mix asphalt on narrow width locations unless approved. The laboratory-molded density for this project will be 97% in accordance with test method TEX-207-F for the Types B, C and D HMAC. Construct longitudinal joints with a joint maker providing a maximum one (1) inch vertical edge (1/2 inch desirable) with an adjacent 6:1 taper. Construct the outside edge with a 6:1 taper or backfill within the same day. ITEM 400 Compact each layer to meet the density and consolidation of the adjacent undisturbed material.

General Notes Sheet K

Page 31: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 Use cement-stabilized backfill for culvert and storm drains located beneath the pavement structure. ITEM 409 Use Class “H” (HPC). All pilings shall be sulfate resistant and include 3 gals/cy of calcium nitrite corrosion inhibitor. Jetting piling to reach plan penetration will not be allowed. ITEM 420 Set a Department-furnished brass disk on all bridge abutments and culvert headwalls as directed. The work performed will not be measured or paid directly, but will be subsidiary to pertinent Items. Promptly apply an ordinary surface finish to all concrete surfaces once meeting curing requirements. Mass concrete will be a plans quantity item. Place longitudinal construction joints at the lane line for bridge approach slabs. These construction joints will be subsidiary to Item 420. ITEM 421 Provide strength-testing equipment in accordance with the Contract controlling test(s). Furnish curing facilities adequately sized for this project as approved. Furnish test molds for cylindrical concrete specimens as required in ASTM C31. No air entrainment in concrete is required. Use Class C (HPC) on the following concrete elements: (1) Bridge bents (2) Bridge abutments (3) Bridge footings Use Class S (HPC) on the following concrete element: (1) Bridge slab Use Class H (HPC) on the following concrete element: (1) Bridge beams

General Notes Sheet L

Page 32: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 Provide sulfate-resistant concrete for the following concrete elements: (1)Bridge footings Include 2 gals/cy of concrete of calcium nitrite corrosion inhibitor in the beams. ITEM 422 Permanent metal deck forms (PMDF) are not allowed. ITEM 423 Furnish and install pipe underdrains for all retaining walls. Include the details and manufacturer, the limits and dimensions, the outfall location, and all details necessary to incorporate the underdrain system in the working drawings. The work performed for the underdrain system within the limits of the retaining wall will not be measured or paid for directly, but will be subsidiary to pertinent Items. Place the select and embankment backfill to the same elevation where possible. Do not exceed a 2 feet difference in elevation at any time. ITEM 427 Provide a rub finish for Surface Area II unless otherwise directed. ITEM 432 Saw cut the existing riprap to ensure a neat transverse and/or longitudinal line to assure a smooth tie-in with new riprap. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. Use Cap Option C for the joint between the face of the abutment and riprap as shown on the standard sheet “Concrete Riprap (CRR)". Reinforce concrete riprap with 4 x 4 – W2.9 x W2.9 welded wire fabric or with No. 3 reinforcing bars spaced at a maximum of 12 inch in each direction.

General Notes Sheet M

Page 33: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 ITEM 440 All reinforcing steel in the bridge girders and Prestressed Concrete Panels shall be plain. All reinforcing steel in the bridge deck and bridge rail shall be epoxy coated. All reinforcing steel in the piling shall be plain. All other reinforcing steel in the bridge substructure shall be epoxy coated or stainless, as specified in the Plans. ITEM 464 The work performed for concrete collars will not be measured or paid for directly, but will be subsidiary to pertinent Items. Use cold-applied, plastic asphalt sewer joint compound for all joints. Provide sandproof tape for all pipe placed in cohesionless backfill material as approved, or provide gaskets that conform to Item 464.2.I.3. ITEM 465 The work performed for concrete collars will not be measured or paid for directly, but will be subsidiary to pertinent Items. Shape and route floor inverts passing through the manhole or inlet with Class "B" concrete. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. Precast tops will not be permitted unless approved. ITEM 467 Place safety end treatments with a uniform slope. Reinforce concrete riprap with 4 x 4 – W2.9 x W2.9 welded wire fabric or with No. 3 reinforcing bars spaced at a maximum of 12 inch in each direction. The work performed for concrete collars will not be measured or paid for directly, but will be subsidiary to pertinent Items. The use of precast Type II safety end treatments with integrally cast riprap aprons is allowed as approved. All safety end treatments shall include riprap to the dimensions shown on PSET-RR. This riprap shall be subsidiary to Item 467.

General Notes Sheet N

Page 34: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 ITEM 496 The structure(s) to be removed have surface coatings which may contain hazardous materials. Provide for the safety and health of employees and abide by all OSHA Standards and Regulations. Removal of the existing bridge by blasting will not be permitted. Coordinate and identify the locations where the structure(s) will be cut at least 30 days prior to the demolition of the structure(s). If the surface coatings contain hazardous materials, the Department will arrange by separate Contract for the removal of a 4 inch wide strip around bearing attachments, at the anchor bolts, and as approved. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. Notify the Engineer no later than 20 calendar days prior to the demolition of the structure(s) for coordination with the Texas Department of State Health Services. Provide for approval a method of removal to prevent any materials from falling into water or traffic. The method used and work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. Disassemble, deliver and neatly stack all salvageable materials, except metal rail elements, at 1401 FM 3036 Rockport, TX 78382. All metal rail elements are to be salvaged and stockpiled at the East Nueces Maintenance Yard located at 844 S. Padre Island Dr. Corpus Christi, TX 78406. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. The bridge to be removed has asbestos containing materials (ACM) as indicated in the Plans. The Department will arrange for a separate contract to collect and dispose of the noted ACM. The asbestos removal contract will run concurrently with this contract and close coordination will be required. Follow the specific demolition requirements below during demolition of the existing structure: ACM Removal Site: Designate or provide a separate site for temporary storage of concrete elements with ACM. The site should be on land and should be adequately fenced with a locking gate. Store all concrete elements containing ACM at this site until the ACM have been removed. Store the concrete elements in a manner that leaves the ACM accessible for removal. This site will be used by the Department’s asbestos contractor for asbestos removal. Provide all cranes or other equipment necessary to move the concrete elements within this site. The asbestos contractor will not be required to relocate any elements.

General Notes Sheet O

Page 35: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 Railing: Notify the department at least four weeks before beginning railing removal. Remove the aluminum portion of the railing by unbolting it from the concrete parapet. Do not disturb or handle the Transite (containing asbestos) pads under the railing posts. The Department will arrange for collection and disposal of these pads. Span/Bent Removal: The roofing felt between the spans and the top of the bent cap at the expansion bents contains asbestos as indicated. A list of the expansion bents is included in the plans. Lift the spans from the expansion bents in a manner that minimizes disturbance to the roofing felt. If any roofing felt stays attached to the span sections, transport them to the ACM Removal Site. If any of the felt stays on the bent caps, carefully remove the cap from its supports and transport the entire cap to the ACM Removal Site. If pieces of the felt fall into the water or on the ground during demolition operations, carefully collect them and transport them to the ACM Removal Site. Notify the Department when concrete elements have been placed in the ACM Removal Site. Piling/Column Removal: Cut or break piling/columns as required by other Items but avoid disturbing the mastic. Transport piling or column sections with mastic on them to the ACM Removal Site. Not all of the piling or columns have the mastic. Final Disposal: The Department will notify you when the ACM have been removed. ACM removal may be done incrementally or all at once depending on the space available at the removal site. Once the ACM have been removed, dispose of the remaining concrete elements as necessary. ITEM 500 "Materials on Hand" payments are not considered when determining partial payments. If a Hurricane Watch is issued for this area, begin removing all rigging including cables, scaffolding and secure all materials and equipment to locations agreeable to both parties. The contractor will not be allowed to mark-up any costs associated with these efforts but will be compensated at an “at cost” basis. If a Hurricane Warning is issued for this area, remove all rigging including cables, scaffolding and equipment. Secure all barges and cranes to an area that is agreeable to both parties. The contractor will not be allowed to mark-up any costs associated with these efforts but will be compensated at an “at cost” basis. ITEM 502 Furnish additional barricades, signs, and traffic handling as directed. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items.

General Notes Sheet P

Page 36: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 Traffic control for daytime lane closures shall be in accordance with applicable BC and TCP standard sheets. When advanced warning flashing arrow panels are specified, furnish one (1) standby unit in good condition at the job site for immediate use. The Contractor’s Responsible Person (CRP) or his representative(s) shall be located within one hour of traveling time to the project site. The Contractor shall notify the Engineer in writing of the name, physical address, and telephone number of this employee or these employees. The Engineer shall furnish this information to local law enforcement officials. Maintain traffic control devices by taking corrective action as soon as possible. Complete corrective action within 48 hours of written notification regardless of the day of the week involved unless otherwise directed. Provide a positive means of communication between flaggers unless otherwise approved. Attach stop/slow paddle to a staff with a minimum length of 6 feet to the bottom of the sign. The use of a pilot vehicle in conjunction with flaggers will be permitted. If used, provide positive and unrestricted communication between the driver of the pilot vehicle and the flaggers. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. ITEM 504 Apply for and secure permits necessary for the buildings, and pay all utility meter deposits and service bills. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. Provide 2 sets of keys for all facilities, which include the field office and/or laboratory. Maintain all mechanical, electrical and plumbing facilities at all times. Provide one (1) Type C Structure (Field Office). This field office shall be for TxDOT use only and shall be a separate structure from the Contractor’s facilities. Furnish and install adequate equipment, outlets, lighting, air conditioning, heating and ventilation as approved. Arrange and install outlets as directed with no less than 1 outlet per wall. Portable toilets will not be allowed.

General Notes Sheet Q

Page 37: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 Provide 2 standard size office desk, 4 office chairs, 1 drafting table(s), 1 drafting stool, 2 bookcases, and 2 filing cabinets as approved. Provide solar screens, blinds, or shades. Provide janitorial services as needed. Provide 1 phone line and 2 phones. Submit a copy of the monthly phone bill for review to monitor phone usage. A cell phone will not be allowed unless approved. Provide a paper copier and facsimile. Provide one (1) Type D Structure (Asphalt Mix Control Laboratory). This laboratory shall be for TxDOT use only and shall be a separate structure from the Contractor’s facilities. Furnish and install adequate equipment, outlets, lighting, air conditioning, heating and ventilation as approved. Arrange and install outlets as directed with no less than 1 outlet per wall. Portable toilets will not be allowed. Provide 1 standard size office desk, 2 office chairs, 1 drafting table(s), 1 drafting stool, 1 bookcase, and 1 filing cabinet as approved. Provide solar screens, blinds, or shades. Provide janitorial services as needed. Provide 1 phone line and 1 phone. Submit a copy of the monthly phone bill for review to monitor phone usage. A cell phone will not be allowed unless approved. Provide a paper copier and facsimile. Provide hot water or a hot water dispenser capable of generating one (1) gallon of water at 140 degrees Fahrenheit with acceptable water pressure. Use support blocks for stability and tied down portable structures according to applicable zoning requirements or as directed. Provide Safety Equipment as follows: (1) ONE EYE WASH STATION (2) ONE FIRE EXTINGUISHER (3) ONE FIRST AID KIT Provide doors with a minimum width of 36 inches and 80 inches in height. Secure all exterior openings with bars. Provide electrical service for the asphalt content by Ignition Method.

General Notes Sheet R

Page 38: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 ITEM 506 Designate in writing a Contractor Responsible Person (CRP) for implementing, maintaining, and reviewing environmental requirements. ITEM 512 Use a Type R joint when using Type 2 precast concrete traffic barriers. ITEM 530 Replace existing driveways not shown on the plans when directed. The work performed will be measured or paid for by Item 530, “Driveways”. If conditions warrant, driveway locations, widths, or lengths may be adjusted as directed. ITEM 540 Complete each location during the working day. No exposed bridge rail or guard fence ends will be permitted at the end of the working day or unattended during the working day. Mixing of wood post types and shapes will not be permitted at the same location. ITEM 542 Disassemble, deliver and neatly stack salvageable materials at 1401 FM 3036 Rockport, TX 78382. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. ITEM 544 Drill an 18-inch pilot hole for post embedment. The method of placing steel tubes in drilled holes is not permitted.

General Notes Sheet S

Page 39: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 ITEM 585 Use Surface Test Type B and Pay Adjustment Schedule 1 to evaluate ride quality of the travel lanes in accordance with Item 585, "Ride Quality for Pavement Surfaces." Use latest version of approved Ride Quality Software. For QC Testing, provide inertial profiler results the same working day after paving. For QA Testing, provide the Engineer the opportunity to witness the testing. Provide a seat for the Engineer in the test vehicle or arrange for the Engineer to follow the test vehicle if requested. ITEM 610 For instructions on submitting shop drawings electronically go to TxDOT home page, Business with TxDOT, Bridge information, Shop drawings. File is titled: Guide to Electronic Shop Drawing Submittal. ITEM 618 Seal all conduits terminating in ground boxes and pole foundations with a sealant made of polyurethane or equivalent that will cure in the presence of moisture. Ensure sealant is suitable for sealing ends with electrical conductor extending past the ends of the conduit. Inject the sealant a minimum of 3 inches and a maximum of 5 inches into the conduit. Provide rigid metal conduit (RMC) elbows for all underground conduit bends of 45 degrees or more, including bends into ground boxes. Provide a polyvinyl chloride conduit (PVC) elbow in lieu of a RMC elbow for conduit 1 inch or larger. Ensure the elbow is the same schedule rating as the conduit to which it is connected. Bond the RMC to the grounding conductor with grounding type bushings when the RMC is exposed or extends into the ground box. Provide a flat, high tensile strength polyester fiber pull tape in each conduit to pull conductors. Provide polymer concrete junction boxes for concrete traffic barrier. Do not use cast iron junction boxes in concrete traffic barriers and single slope traffic barriers. Use polymer concrete junction boxes instead of the cast iron junction boxes shown on standard sheets CTBI (3), CTBI (4), AND SSCB (4). Mount the junction boxes flush (+ 0”, - ½”) with concrete surface of concrete barrier. The work will not be measured or paid for directly, but will be subsidiary to pertinent Items.

General Notes Sheet T

Page 40: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 Provide wide sweep conduit elbows. Jacking of conduit will not be permitted. ITEM 620 Bond grounding conductors that share the same conduit, junction box, ground box, or structure together at every accessible point. For both transformer and shoe-base type illumination poles, provide double-pole breakaway fuse holder as shown on the Texas Department of Transportation (TxDOT) materials producers list. Category is “Roadway Illumination and Electrical Supplies”. Fuse holder is shown on list under Items 610 & 620. Provide 10 amp time delay fuses ITEM 636 Disassemble, deliver and neatly stack salvageable materials at 1401 FM 3036 Rockport, TX 78382. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. ITEM 644 Use crash worthy supports as shown on the BC sheets, the CWZTCD, or as directed for signs relocated using temporary supports. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. Disassemble, deliver and neatly stack salvageable materials at 1401 FM 3036 Rockport, TX 78382. The work performed will not be measured or paid for directly, but will be subsidiary to pertinent Items. All set screws shall be galvanized. ITEM 662 Use temporary flexible-reflective roadway marker tabs at the beginning and end of no passing zones as shown on the TCP (7-1)-98 for seal coats and WZ(STPM)-03 for hot mix overlays.

General Notes Sheet U

Page 41: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 ITEM 677 Eliminate all conflicting pavement markings as work progresses or as directed. Use Method A for asphaltic pavements. Use a PB Grade 4 aggregate at an application rate of 1 cy/120 sy and asphalt AC-5, AC-10, CRS-2 or HFRS-2 at a application rate of 0.39 Gal/sy. ITEM 685 Provide solar powered flasher controller assemblies capable of a 24-hr flash with dual indications. The work to connect the flasher assemblies to the signal heads will not be measured or paid for directly, but will be subsidiary to pertinent Items. Provide single-pole breakaway disconnects. Use Bussman HEBW, Littlefuse LEB, Ferraz-Shawmut FEB, or equal on ungrounded conductors and grounded conductors. Ensure the disconnects have a white colored marking and a permanently installed solid neutral. ITEM 687 Provide single-pole breakaway disconnects. Use Bussman HEBW, Littlefuse LEB, Ferraz-Shawmut FEB, or equal on ungrounded conductors and grounded conductors. Ensure the disconnects have a white colored marking and a permanently installed solid neutral. ITEM 730 Provide full-width mowing for a period of 6 full width cycles or as directed. ITEM 4574 Jetting sheet piling to reach plan penetration will not be allowed. The use of pilot holes in water will not be allowed. A prototype anchor assembly of each type of size required for the sheet pile placement shall be reviewed by the engineer for approval prior to fabrication of the anchor assemblies required for piling on the project. ITEM 4580 The Contractor will develop an emergency plan in case of a material spill (i.e. fuel, hydraulic, etc.) on the temporary access platform. This plan will address both emergency measures to be taken immediately by the Contractor, as well as the names and phone numbers of applicable

General Notes Sheet V

Page 42: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 regulatory agencies to be contacted. The Contractor's emergency plan will include at least two outboard boats and 400 ft of floating boom that will be maintained and available onsite for emergency deployment. The Contractor will be required to train personnel in the implementation of the emergency plan. During any operations over water, adequate personnel must be on hand who are trained and capable of implementing the emergency plan. ITEM 5049 Biodegradable erosion control logs will be checked and cleared of debris or sediment (as well as maintenance) by the Contractor at least once a week. Biodegradable erosion control logs will also be checked and cleared of any debris or sediment after a ½” rain event or more. These tasks will be considered subsidiary to Item 5049 “Biodegradable Erosion Control Logs”. ITEM 5261 During the installation of the geogrid mats, the Contractor will not allow the traveling public to travel directly over the geogrid. A minimum flexible base thickness of 6 inches will be placed over geogrid prior to opening the mat to construction traffic. The Contractor will provide adequate storage for the geogrid and will plan the installation of the geogrid so as to limit exposure to ultraviolet degradation. The manufacturer’s recommendations will control, unless otherwise directed by the Engineer. Type I geogrid will be used. When using a multi-layer type of geogrid, longitudinally cut portions of a roll must be held together by at least two rows of longitudinal stitching to insure proper layer alignment during installation and maintain integrity of the cut portion ITEM 6834 Furnish the portable changeable message signs displaying the correct message at least seven (7) days prior to beginning work or as directed. The Contractor's Responsible Person (CRP) will maintain full control of messages at all times. The Engineer will provide the sign message text to use at each sign. A minimum of two (2) PCMS will be required. However, additional units may be necessary depending on the work in progress. Standby time will not be measured or paid for directly, but will be subsidiary to pertinent Items.

General Notes Sheet W

Page 43: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35 ITEM 8251 Establish and mark the location of existing standard pavement markings including but not limited to the edge lines, transitions, gore areas, etc. Place pavement markings no later than 14 calendar days after the placement of the surface. When inclement weather prohibits placement of the markings, the 14 day period may be extended until weather permits proper application.

General Notes Sheet X

Page 44: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35

***********************SPECIFICATION DATA************************* UNIT WEIGHT ESTIMATES EXISTING SUBGRADE ---------------------------------------------------------------------------- 105 LBS/CF ITEM 247 – FL BS (CMP IN PLC)(TY D GR 4) (FNAL POS)------------------------------- 136 LBS/CF ITEM 341 – (3”) D-GR HMA (QCQA) TY C SAC-B PG 76-22 ------------------------------ 330 LBS/SY ITEM 341 – (11”) D-GR HMA (QCQA) TY B SAC-B PG 76-22 ---------------------------- 1210 LBS/SY ITEM 341 – (2”) D-GR HMA (QCQA) TY C SAC-B PG 76-22 ------------------------------ 220 LBS/SY ITEM 341 – (1”) D-GR HMA (QCQA) TY D SAC-B PG 76-22 ----------------------------- 110 LBS/SY COMPACTION REQUIREMENTS FOR BASE COURSE ITEM 132 – EMBANKMENT (FINAL)(DENS CONT)(TY C) PLASTICITY INDEX ------------------------------------------------------------------------------- 40 MAX PLASTICITY INDEX ------------------------------------------------------------------------------- 10 MIN DENSITY --------------------------------------------------------------------------------------------- AS SHOWN ON TABLE 2 OF ITEM 132 LIFTS -------------------------------------------------------------------------------------------------- ALL ITEM 134 – BACKFILL (TY A OR B) PLASTICITY INDEX ------------------------------------------------------------------------------- 40 MAX PLASTICITY INDEX ------------------------------------------------------------------------------- 10 MIN DENSITY ----------------------------------------------------------------------------------------- ORDINARY COMPACTION ITEM 247 – FL BS (CMP IN PLC)(TY D GR 4)(FNAL POS) DENSITY ---------------------------------------------------------------------------------------------- 100% MIN LIFTS -------------------------------------------------------------------------------------------------- ALL ITEM 275- CEMENT TRT (EXIST. MATL)(8”) DENSITY ---------------------------------------------------------------------------------------------- 95% MIN LIFTS -------------------------------------------------------------------------------------------------- ALL ITEM 166 FERTILIZER @ 375 LBS PER ACRE-------------------------------------------0.57 TONS ITEM 168 VEGETATIVE WATERING @ 26,000 GAL/ACRE/MONTH--------------624.5 MG SURFACE TREATMENT DATA ONE COURSE UNDERSEAL ASPHALT, TYPE ------------------------------------ AC-5, AC-10, CRS-2, HFRS-2 AVERAGE ASPHALT RATE (GAL/SY) ---------0.39 AGGREGATE RATE (CY/SY) ---------------------1/85 AGGREGATE TYPE -------------------------------- PB AGGREGATE GRADE------------------------------ 4 SAC B OR 4S SAC B ROLLING (FLAT WHL) (HR/SY) ---------------- 1:100 ROLLING (LT PNEU) (HR/SY) ------------------- 1:2500

General Notes Sheet Y

Page 45: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

Project Number: Sheet County: ARANSAS Control: 0180-03-035, ETC. Highway: SH 35

General Notes Sheet Z

PRIME COAT ASPHALT, TYPE-------------------------------------------MC-30 OR SS-1 AVERAGE ASPHALT RATE (GAL/SY)---------------0.20 ************************BASIS OF ESTIMATE************************** CSJ:0180-03-035 RATE OF ITEM DESCRIPTION BASIS APPLICATION QUANTITY. ITEM 247 FL BS (CMP IN PLC) (TY D GR 4) (12”) 3,203 SY 0.33 (CY/SY) 1,057 CY ITEM 275 CEMENT 3,247 SY 0.0126 TONS/SY 41 TONS ITEM 275 CEMENT TRT (EXIST MATL)(8”) 3,247 SY ITEM 310 PRIME COAT (MC-30 OR SS-1) 3,095 SY 0.20 (GAL/SY) 619 GAL ITEM 316 ASPH (AC-5, AC-10, CRS-2, HFRS-2) 3,021 SY 0.39 (GAL/SY) 1,178 GAL ITEM 316 AGGR (TY-PB GR-4 OR 4S SAC-B) 3,021 SY 1/85 (CY/SY) 36 CY ITEM 341 ASPH CONC PAV TY B (3”) 2,982 SY 0.165 (TONS/SY) 492 TONS ITEM 341 ASPH CONC PAV TY C (2”) 2,945 SY 0.110 (TONS/SY) 324 TONS ITEM 5261 GEOGRID REINFORCEMENT TY 1 3,247 SY -- 3,247 SY CSJ:0180-04-083 RATE OF ITEM DESCRIPTION BASIS APPLICATION QUANTITY. ITEM 247 FL BS (CMP IN PLC) (TY D GR 4) (12”) 14,379 SY 0.33 (CY/SY) 4,745 CY ITEM 275 CEMENT 14,029 SY 0.0126 TONS/SY 177 TONS ITEM 275 CEMENT TRT (EXIST MATL)(8”) 14,029 SY ITEM 310 PRIME COAT (MC-30 OR SS-1) 13,300 SY 0.20 (GAL/SY) 2,660 GAL ITEM 316 ASPH (AC-5, AC-10, CRS-2, HFRS-2) 12,928 SY 0.39 (GAL/SY) 5,042 GAL ITEM 316 AGGR (TY-PB GR-4 OR 4S SAC-B) 12,928 SY 1/85 (CY/SY) 152 CY ITEM 341 ASPH CONC PAV TY B (3”) 14,357 SY 0.165 (TONS/SY) 2,369 TONS ITEM 341 ASPH CONC PAV TY C (2”) 13,000 SY 0.110 (TONS/SY) 1,430 TONS ITEM 423 RETAINING WALL 5,982 SF -- 5,982 SF ITEM 5261 GEOGRID REINFORCEMENT TY 1 14,713 SY -- 14,713 SY ITEM 6834 PORT. CHANGE. MESS. SIGNS -- 736 DAYS

Page 46: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

1-5

CONTROL : 0180-03-035, ETC PROJECT : STP 1102(113), ETC HIGHWAY : SH 35 COUNTY : ARANSAS TEXAS DEPARTMENT OF TRANSPORTATION

GOVERNING SPECIFICATIONS AND SPECIAL PROVISIONS ALL SPECIFICATIONS AND SPECIAL PROVISIONS APPLICABLE TO THIS PROJECT ARE IDENTIFIED AS FOLLOWS: STANDARD SPECIFICATIONS: ADOPTED BY THE TEXAS DEPARTMENT OF ------------------------ TRANSPORTATION JUNE 1, 2004. STANDARD SPECIFICATIONS ARE INCORPORATED INTO THE CONTRACT BY REFERENCE. ITEMS 1 TO 9 INCL., GENERAL REQUIREMENTS AND COVENANTS ITEM 100 PREPARING RIGHT OF WAY ITEM 104 REMOVING CONCRETE ITEM 106 OBLITERATING ABANDONED ROAD ITEM 110 EXCAVATION (132) ITEM 132 EMBANKMENT (100)(204)(210)(216)(400) ITEM 134 BACKFILLING PAVEMENT EDGES (166)(168) ITEM 158 SPECIALIZED EXCAVATION WORK (132) ITEM 162 SODDING FOR EROSION CONTROL (166)(168) ITEM 164 SEEDING FOR EROSION CONTROL (162)(166)(168) ITEM 166 FERTILIZER ITEM 168 VEGETATIVE WATERING ITEM 247 FLEXIBLE BASE (105)(204)(210)(216)(520) ITEM 275 CEMENT TREATMENT (ROAD-MIXED) (132)(204)(210)(216)(300) (310)(520) ITEM 310 PRIME COAT (300)(316) ITEM 316 SURFACE TREATMENTS (210)(300)(302) ITEM 341 DENSE-GRADED HOT-MIX ASPHALT (QC/QA) (210)(300)(301)(320) (520)(585) ITEM 354 PLANING AND TEXTURING PAVEMENT ITEM 400 EXCAVATION AND BACKFILL FOR STRUCTURES (132)(401)(420) (421) ITEM 409 PRESTRESSED CONCRETE PILING (404)(420)(421)(424)(425) (426)(440)(780) ITEM 416 DRILLED SHAFT FOUNDATIONS (420)(421)(440)(448) ITEM 420 CONCRETE STRUCTURES (400)(404)(421)(426)(427)(438)(440) (441)(448) ITEM 422 REINFORCED CONCRETE SLAB (420)(421)(424)(426)(430)(440) ITEM 423 RETAINING WALLS (110)(132)(400)(420)(421)(424)(440)(445) (458)(556)

Page 47: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

2-5

ITEM 425 PRECAST PRESTRESSED CONCRETE STRUCTURAL MEMBERS (420) (421)(424)(426)(427)(434)(440)(442) ITEM 428 CONCRETE SURFACE TREATMENT (427) ITEM 432 RIPRAP (247)(420)(421)(427)(440) ITEM 442 METAL FOR STRUCTURES (441)(445)(446)(447)(448)(449) ITEM 450 RAILING (420)(421)(424)(440)(441)(442)(445)(446)(448) (540) ITEM 454 BRIDGE EXPANSION JOINTS (442) ITEM 464 REINFORCED CONCRETE PIPE (400)(476) ITEM 465 MANHOLES AND INLETS (400)(420)(421)(440)(471) ITEM 467 SAFETY END TREATMENT (400)(420)(421)(432)(440)(445)(464) ITEM 474 SLOTTED DRAIN (400)(445) ITEM 480 CLEANING EXISTING CULVERTS ITEM 496 REMOVING STRUCTURES (430) ITEM 500 MOBILIZATION ITEM 502 BARRICADES, SIGNS, AND TRAFFIC HANDLING ITEM 506 TEMPORARY EROSION, SEDIMENTATION, AND ENVIRONMENTAL CONTROLS (432)(556) ITEM 508 CONSTRUCTING DETOURS ITEM 512 PORTABLE CONCRETE TRAFFIC BARRIER (420)(421)(424)(440) (442) ITEM 514 PERMANENT CONCRETE TRAFFIC BARRIER (400)(416)(420)(421) (424)(440)(442)(448) ITEM 530 INTERSECTIONS, DRIVEWAYS, AND TURNOUTS (247)(275)(316) (330)(340)(421)(440) ITEM 540 METAL BEAM GUARD FENCE (421)(441)(445)(529)(542)(544) ITEM 542 REMOVING METAL BEAM GUARD FENCE ITEM 544 GUARDRAIL END TREATMENTS ITEM 545 CRASH CUSHION ATTENUATORS (421) ITEM 610 ROADWAY ILLUMINATION ASSEMBLIES (421)(441)(442)(445)(446) (449)(616)(620) ITEM 617 TEMPORARY ROADWAY ILLUMINATION (416)(610)(613)(614)(618) (620)(621)(622)(624)(627)(628) ITEM 618 CONDUIT (400)(445)(476)(622) ITEM 620 ELECTRICAL CONDUCTORS ITEM 624 GROUND BOXES (420)(421)(432)(440)(618)(620) ITEM 628 ELECTRICAL SERVICES (441)(445)(449)(618)(620)(627)(656) ITEM 636 ALUMINUM SIGNS (643) ITEM 644 SMALL ROADSIDE SIGN SUPPORTS AND ASSEMBLIES (421)(440) (441)(442)(445)(636)(643)(656) ITEM 658 DELINEATOR AND OBJECT MARKER ASSEMBLIES (445) ITEM 662 WORK ZONE PAVEMENT MARKINGS (666)(668)(672)(677) ITEM 666 REFLECTORIZED PAVEMENT MARKINGS (316)(318)(662)(677)(678) ITEM 668 PREFABRICATED PAVEMENT MARKINGS ITEM 672 RAISED PAVEMENT MARKERS (677)(678) ITEM 677 ELIMINATING EXISTING PAVEMENT MARKINGS AND MARKERS (300) (302)(316) ITEM 682 VEHICLE AND PEDESTRIAN SIGNAL HEADS ITEM 685 ROADSIDE FLASHING BEACON ASSEMBLIES (441)(442)(445)(449) (656)(687) ITEM 730 ROADSIDE MOWING SPECIAL PROVISIONS: SPECIAL PROVISIONS WILL GOVERN AND TAKE

Page 48: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

3-5

------------------ PRECEDENCE OVER THE SPECIFICATIONS ENUMERATED HEREON WHEREVER IN CONFLICT THEREWITH. REQUIRED CONTRACT PROVISIONS, FEDERAL-AID CONSTRUCTION CONTRACTS (FORM FHWA 1273, MARCH, 1994) WAGE RATES SPECIAL PROVISION "PARTNERING" (000---002) SPECIAL PROVISION "NOTICE TO ALL BIDDERS" (000---003) SPECIAL PROVISION "NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY" (000---004) SPECIAL PROVISION "STANDARD FEDERAL EQUAL EMPLOYMENT OPPORTUNITY CONSTRUCTION CONTRACT SPECIFICATIONS" (000---006) SPECIAL PROVISION "CERTIFICATION OF NONDISCRIMINATION IN EMPLOYMENT" (000---009) SPECIAL PROVISION "DEPARTMENT DIVISION MAILING AND PHYSICAL ADDRESS" (000---011) SPECIAL PROVISION "NOTICE OF CHANGES TO U.S. DEPARTMENT OF LABOR REQUIRED PAYROLL INFORMATION" (000--1483) SPECIAL PROVISION "SCHEDULE OF LIQUIDATED DAMAGES" (000--1493) SPECIAL PROVISION "IMPORTANT NOTICE TO CONTRACTORS" (000--2139) SPECIAL PROVISION "ON-THE-JOB TRAINING PROGRAM" (000--1676) SPECIAL PROVISION "DISADVANTAGED BUSINESS ENTERPRISE IN FEDERAL AID CONTRACTS" (000--1966) SPECIAL PROVISION TO ITEM 1 (001---015) SPECIAL PROVISION TO ITEM 2 (002---017) SPECIAL PROVISION TO ITEM 3 (003---033) SPECIAL PROVISION TO ITEM 4 (004---017) SPECIAL PROVISION TO ITEM 5 (005---004) SPECIAL PROVISION TO ITEM 6 (006---030) SPECIAL PROVISION TO ITEM 7 (007---806) SPECIAL PROVISIONS TO ITEM 8 (008---063)(008---086)(008---119) SPECIAL PROVISIONS TO ITEM 9 (009---009)(009---015) SPECIAL PROVISION TO ITEM 100 (100---002) SPECIAL PROVISION TO ITEM 161 (161---006) SPECIAL PROVISION TO ITEM 164 (164---004) SPECIAL PROVISION TO ITEM 166 (166---001) SPECIAL PROVISION TO ITEM 247 (247---033) SPECIAL PROVISION TO ITEM 275 (275---002) SPECIAL PROVISION TO ITEM 300 (300---032) SPECIAL PROVISION TO ITEM 302 (302---010) SPECIAL PROVISION TO ITEM 316 (316---016) SPECIAL PROVISION TO ITEM 318 (318---010) SPECIAL PROVISION TO ITEM 330 (330---001) SPECIAL PROVISION TO ITEM 340 (340---003) SPECIAL PROVISION TO ITEM 341 (341---024) SPECIAL PROVISION TO ITEM 416 (416---001) SPECIAL PROVISION TO ITEM 420 (420---002) SPECIAL PROVISION TO ITEM 421 (421---035) SPECIAL PROVISION TO ITEM 424 (424---002) SPECIAL PROVISION TO ITEM 425 (425---001) SPECIAL PROVISION TO ITEM 428 (428---001) SPECIAL PROVISION TO ITEM 434 (434---003) SPECIAL PROVISIONS TO ITEM 440 (440---003)(440---004)

Page 49: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

4-5

SPECIAL PROVISION TO ITEM 441 (441---006) SPECIAL PROVISION TO ITEM 442 (442---016) SPECIAL PROVISION TO ITEM 447 (447---002) SPECIAL PROVISION TO ITEM 448 (448---002) SPECIAL PROVISION TO ITEM 450 (450---001) SPECIAL PROVISION TO ITEM 464 (464---003) SPECIAL PROVISION TO ITEM 465 (465---001) SPECIAL PROVISION TO ITEM 500 (500---005) SPECIAL PROVISION TO ITEM 502 (502---055) SPECIAL PROVISION TO ITEM 506 (506---011) SPECIAL PROVISION TO ITEM 512 (512---002) SPECIAL PROVISION TO ITEM 514 (514---002) SPECIAL PROVISION TO ITEM 540 (540---023) SPECIAL PROVISION TO ITEM 544 (544---001) SPECIAL PROVISION TO ITEM 610 (610---010) SPECIAL PROVISION TO ITEM 613 (613---002) SPECIAL PROVISION TO ITEM 617 (617---001) SPECIAL PROVISION TO ITEM 620 (620---001) SPECIAL PROVISION TO ITEM 624 (624---014) SPECIAL PROVISION TO ITEM 628 (628---001) SPECIAL PROVISION TO ITEM 636 (636---014) SPECIAL PROVISION TO ITEM 643 (643---001) SPECIAL PROVISION TO ITEM 658 (658---006) SPECIAL PROVISION TO ITEM 672 (672---034) SPECIAL PROVISION TO ITEM 682 (682---001) SPECIAL PROVISION TO ITEM 685 (685---025) SPECIAL PROVISION TO ITEM 687 (687---004) SPECIAL PROVISION TO SPECIAL SPECIFICATION ITEM 6473 (6473--001) SPECIAL PROVISION TO SPECIAL SPECIFICATION ITEM 8251 (8251--005) SPECIAL SPECIFICATIONS: ---------------------- ITEM 4574 CONCRETE CYLINDER PILING ITEM 4575 UHMW-PE FENDER PADS ITEM 4576 STEEL PIPE PILING ITEM 4580 CONSTRUCTION ACCESS ITEM 4586 DYNAMIC MONITORING AND ANALYSIS OF DRIVEN PILING ITEM 5049 BIODEGRADEABLE EROSION CONTROL LOGS (161)(506) ITEM 5261 GEOGRID BASE REINFORCEMENT ITEM 5430 FLOATING TURBIDITY BARRIER ITEM 6473 MULTIPOLYMER PAVEMENT MARKING S (MPM) (677)(678)(8094) ITEM 6834 PORTABLE CHANGEABLE MESSAGE SIGN ITEM 8094 MOBILE RETROREFLECTIVITY DATA COLLECTION FOR PAVEMENT MARKINGS ITEM 8251 REFLECTORIZED PAVEMENT MARKINGS WITH RETROREFLECTIVE REQUIREMENTS (316)(318)(502)(677)(678)(8094) ITEM 8705 SOLAR-POWERED NAVIGATIONAL LIGHTING SYSTEM GENERAL: THE ABOVE-LISTED SPECIFICATION ITEMS ARE THOSE UNDER WHICH ------- PAYMENT IS TO BE MADE. THESE, TOGETHER WITH SUCH OTHER PERTINENT ITEMS, IF ANY, AS MAY BE REFERRED TO IN THE ABOVE-

Page 50: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

5-5

LISTED SPECIFICATION ITEMS, AND INCLUDING THE SPECIAL PROVISIONS LISTED ABOVE, CONSTITUTE THE COMPLETE SPECIFI- CATIONS FOR THIS PROJECT.

Page 51: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

2004 Specifications CSJ 0180-03-035, Etc.

SPECIAL PROVISION

440---004

Reinforcing Steel

For this project, Item 440, “Reinforcing Steel” of the Standard Specifications, is hereby amended with respect to the clauses cited below, and no other clauses or requirements of this Item are waived or changed hereby.

Article 440.2 Materials, Section A. Approved Mills is supplemented by the following:

Contact the Construction Division with the name and location of the producing mill for stainless steel reinforcement at least 4 weeks prior to ordering any material.

Article 440.2. Materials, Section D. Weldable Reinforcing Steel is supplemented by the following:

Do not weld stainless reinforcing steel without permission from the Engineer. If welding is required, provide stainless steel reinforcing suitable for welding and submit welding procedures and electrodes to the Engineer for approval.

Article 440.2. Materials, Section G. Mechanical Couplers is voided and replaced by the following: When mechanical splices in reinforcing steel bars are shown on the plans, use couplers of the type specified in DMS-4510, “Mechanical Couplers for Reinforcing Steel,” Article 4510.5.A, “General Requirements.” Furnish only couplers produced by a manufacturer pre-qualified in accordance with DMS-4510. Do not use sleeve-wedge type couplers on coated reinforcing. Sample and test couplers for use on individual projects in accordance with DMS-4510. Furnish couplers only at locations shown on the plans. Furnish couplers for stainless reinforcing steel with the same alloy designation as the reinforcing steel. Article 440.2. Materials is supplemented by the following:

H. Fibers. When allowed by the plans, supply fibers at the minimum dosage listed on the Material Producer List maintained by the Materials and Pavements Section of the Construction Division. When shown on the plans, use fibers that do not corrode due to carbonation of concrete or the use of deicing salts.

1-2 440---004 04-11

Page 52: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

2-2 440---004 04-11

I. Stainless Steel. When stainless reinforcing steel is required in the plans, provide deformed steel bars of the types listed below and conforming to ASTM A 955, Gr. 60 or higher.

UNS Designation S31653 S31803 S24100 S32304

AISI Type 316LN 2205 XM-28 2304

Article 440.3.Construction, Section A. Bending is supplemented by the following:

Bend stainless reinforcing steel in accordance with ASTM A955.

Article 440.3.Construction, Section C. Storage is supplemented by the following:

Do not allow stainless steel reinforcement to be in direct contact with uncoated steel reinforcement, nor with galvanized reinforcement. This does not apply to stainless steel wires and ties. Store stainless steel bar reinforcement separately, off the ground on wooden supports.

Article 440.3. Construction, Section D. Splices. The fifth bullet is voided and replaced by the following:

For box culvert extensions with less than 1 ft. of fill, lap the existing longitudinal bars with the new bars as shown in Table 5. For extensions with more than 1 ft. of fill, lap at least 1 ft. 0 in.

Article 440.3. Construction, is supplemented by the following: G. Handling and Placing Stainless Steel Reinforcing. Handle, cut, and place stainless steel bar reinforcement using tools that are not used on carbon steel. Do not use carbon steel tools, chains, slings, etc. when handling stainless steel. Use only nylon or polypropylene slings. Cut stainless steel using shears, saws, abrasive cutoff wheels, or torches. Remove any thermal oxidation using pickling paste. Do not field bend stainless steel without approval. Use 16 gauge fully annealed stainless steel tie wire conforming to the material properties listed in 440.2.I. “Stainless Steel”. Support all stainless steel on solid plastic, stainless steel, or epoxy coated steel chairs. Do not use uncoated carbon steel chairs in contact with stainless steel.

Page 53: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

2004 Specifications CSJ 0180-03-035

SPECIAL SPECIFICATION

4586 Dynamic Monitoring and Analysis of Driven Piling

11.. DDeessccrriippttiioonn.. This item consists of (1) conducting the dynamic pile monitoring during initial pile driving and during pile restrikes and (2) the services of a dynamic testing consultant to provide dynamic analyses using Case Pile Wave Analysis Program (CAPWAP) and Wave Equation analyses programs. The CAPWAP and Wave Equation analyses shall be performed for the purpose of obtaining ultimate pile bearing capacity, pile stresses, pile integrity, and pile driving system efficiency. The Contractor shall supply all material, equipment, and labor to perform the dynamic monitoring. The Contractor shall obtain the dynamic measurements with the Pile Driving Analyzer (PDA) of monitor piles and furnish the necessary dynamic data to the dynamic testing consultant. 22.. EEqquuiippmmeenntt.

A. The Pile Driving Analyzer (PDA) shall be capable of four channels of strain data acquisition and four channels of acceleration data acquisition. The PDA shall conform to the requirement of ASTM D-4945.

B. To prepare the pile for sensor attachment, a drill of sufficient power, operated by either a

DC battery or a generator, shall be furnished. A hammer drill is required for preparation of concrete piles.

3. SSccooppee ooff WWoorrkk. The Contractor shall furnish equipment, materials, and labor necessary for conducting dynamic pile monitoring and contacting dynamic testing consultant for providing the CAPWAP and Wave Equation analyses.

A. Dynamic Pile Monitoring. This work consists of obtaining dynamic measurements with the Pile Driving Analyzer (PDA) of monitor piles during initial pile driving and during pile restrikes. Dynamic monitoring involves attaching at least two strain transducers and two accelerometers to the 24 inch square pile, and at least four strain transducers and four accelerometers to the 54 and 66 inch cylindrical pile near the pile head during initial driving and during restrike testing. A cable or wireless transmission connects the sensors near the pile head with the Pile Driving Analyzer located a safe distance from the pile, but not more than 330 ft from the pile. The cost of equipment mobilization or any delays due to dynamic pile monitoring shall be subsidiary to pertinent bid items. When dynamic monitoring is specified, the piles shall be lengthened by a distance of 2.5 times the pile diameter to allow access to the top of the pile at the end-of-driving. The additional length on the piles to be monitored is included in the total pile lengths shown in the plans.

1-3 4586 04-11

Page 54: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

During pile driving operations the pile driving stresses induced by the Contractor's hammer shall be monitored with the pile driving analyzer to ensure that the pile is not being damaged. When necessary, the Contractor shall reduce the driving energy transmitted to the pile.

Pile Restrike. Pile restrikes for monitor piles may be performed in accordance with the time intervals specified below unless otherwise shown in the plans. Monitor piles with dynamic monitoring shall have a 1-day restrike after the initial pile installation with the Pile Driving Analyzer monitoring the driving.

Field Report. Within one day of dynamic pile monitoring, the Contractor shall prepare a hand written daily field report summarizing the dynamic monitoring results. As a minimum, the daily reports shall include the calculated driving stresses, transferred energy, and estimated pile capacity at the time of testing. Daily field reports shall be transmitted to the Engineer.

B. Dynamic Analysis. The Contractor shall secure the Dynamic Testing Consultant (DTC)

to perform either a Case Pile Wave Analysis Program (CAPWAP) analysis or a Wave Equation analysis or a combination of both, for each occurrence of dynamic monitoring. The minimum requirement of the DTC shall be a Master Level PDA tester as certified by the Foundation QA. The Contractor shall furnish the necessary dynamic data obtained from the dynamic monitoring to the consultant who shall use the results from the CAPWAP data to assess pile installation stresses and integrity, as well as to predict the pile’s static bearing capacity and resistance distribution. This information will be used to verify the Pile Driving Analyzer’s Case pile capacity assumptions and to determine the distribution of soil static resistance, quakes, and damping factors required for the wave equation analysis. The dynamic testing consultant shall use the CAPWAP results to establish the relationship between stroke, energy, and blow count in the wave equation. The dynamic testing consultant shall submit two copies of the results to the Department’s Geotechnical Section within 1 week of receiving the data unless otherwise directed by the Engineer. Additional production piles may be monitored if deemed necessary by the Engineer. The cost of additional analyses shall be at the contract unit price for dynamic analysis unless it is determined that the monitoring is necessary because of Contractor error.

44.. MMeeaassuurreemmeenntt..

A. Dynamic Pile Monitoring. The number of dynamic monitoring to be paid for will be the number of dynamic monitoring occurrences on monitor piles ordered and completed. Dynamic monitoring during initial pile driving shall be considered as a single monitoring occurrence. Additionally, monitoring during pile restrike shall be considered as a separate monitoring occurrence. Dynamic monitoring occurrences that are necessary because of Contractor error shall not be measured for payment. Quantities of dynamic pile monitoring and dynamic analysis will be shown on the plans.

2-3 4586 04-11

Page 55: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

3-3 4586 04-11

B. Dynamic Analysis. The number of dynamic analysis to be paid for will be the number of dynamic analysis occurrences on test piles or monitor piles. Dynamic analysis occurrences that are necessary because of Contractor error shall not be measured for payment.

55.. PPaayymmeenntt..

A. Dynamic Pile Monitoring. Payment for dynamic monitoring will be made at the unit price per each.

B. Dynamic Analysis. Payment of the dynamic analysis (CAPWAP or Wave Equation)

performed by the dynamic testing consultant will be paid for at the contract unit price for each occurrence of dynamic monitoring.

Page 56: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

2004 Specifications CSJ 0180-03-035, ETC.

SPECIAL SPECIFICATION

4576

Steel Pipe Piling

1. Description. Furnishing of steel pipe piling in place, fabricated, reinforced, and filled with concrete must be in accordance with these specifications and plans, of the type and size shown on the plans, and in the locations as required by the plans.

Furnish the length of piling as indicated on the plans or authorized by the Engineer.

2. General. All materials and construction methods must conform to the requirements of this Item, and to the pertinent requirements of the following Items:

Item 404, “Driving Piling”

Item 407, “Steel Piling”

Item 416, “Drilled Shaft Foundations”

Item 420, “Concrete Structures”

Item 421, “Hydraulic Cement Concrete”

Item 440, “Reinforcing Steel”

Item 441, “Steel Structures”

Item 442, “Metal for Structures”

Item 446, “Cleaning and Painting Steel”

Item 448, “Structural Field Welding”

3. Material. Metal for the steel pipe pile must conform to ASTM A588, ASTM A572 Grade 50, or ASTM A1008 Grade 50, Class 2 . Hydrostatic testing of pipe is not required.

For concrete placement in pipe pile, supply Class “SS” concrete with a Coarse Aggregate Grade 4, 5 or 6.

4. Coating. Shop apply protective coating on pipe piling and structural steel elements as specified in Item 407.2 Materials, Paragraph 5

5. Storing and Handling. Store and handle steel pipe piling to prevent damage to the piling and coating system. Place the stored piling on blocking to prevent contact with the ground. Keep piling clean and fully drained at all times. Use a sufficient amount of blocking to prevent deflection in the stored piling. Utilize fabric slings or other methods as approved by the Engineer to handle the steel pipe pile.

1-2 4576 04-11

Page 57: NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 …ftp.dot.state.tx.us/pub/txdot-info/cmd/cserve/addendum/local/a... · NOTIFICATION OF ADDENDUM ADDENDUM NO. 2 ... adendum notification which

2-2 4576 04-11

6. Construction. The length of a steel pipe pile may be built up in sections prior to the driving operation. The minimum length of a section measured between splices shall be 25 feet. Splices must be made with complete penetration groove welds in accordance with Item 448, “Structural Field Welding,” for structural steel construction. Weld the sections together in a manner that will fully develop the section of pile and also form a water-tight joint. The Contractor is advised that accurate alignment of pile splice is critical and misalignment between sections should not be more than 1:200.

The Contractor must provide equipment and facilities necessary for the proper inspection of the piling. Any damaged, improperly driven, or otherwise defective piling will be evaluated by the Engineer and be removed and replaced if deemed necessary.

At the completion of driving, remove all soil from the pile by augering and high pressure washing, or other methods approved by the Engineer. Capture all soil and water removed from the inside of the pile and properly disposed of the material. No discharge of these materials into the surrounding water will be allowed.

Provide reinforcing steel in the piling as indicated on the plans. Care shall be taken to hold the reinforcement to true position in the pipe when placing concrete. Use concrete blocks or other suitable devices to prevent the displacement of the reinforcing steel.

Continuously place concrete in a single operation. If the interior of the pile is dry, concrete can be allowed to free fall an unlimited distance if it does not strike the reinforcing cage or sides of the hole during placement. When free fall is used, provide a hopper with a minimum 3-ft.-long drop tube at the top of the shaft to direct concrete vertically down the center of the shaft. Do not use a shovel or other means to simply deflect the concrete discharge from the truck. If the interior of the pile contains standing water, place concrete with a pump or tremie in accordance with the “Underwater Placement” provisions of Item 416, “Drilled Shaft Foundations”.

7. Measurement. Steel pipe piling will be measured by the foot of acceptable piling in place after all cut-offs and builds-ups have been made. Cut-offs and build-ups will not be measured for payment.

If the Contractor elects to drive piling deeper than required to meet the specified penetration requirements, no measurement will be made on the portion below the elevation at which penetration was first obtained.

8. Payment. The work performed and materials furnished in accordance with this Item and measured as provided under "Measurement" will be paid for at the unit price bid for "Steel Pipe Piling", of the specified size.

No payments will be made for cut-offs and build-ups.

The unit price bid will be full compensation for furnishing and driving the steel pipe pile, including alignment holes, pilot holes, and jetting, placing reinforcing steel, concrete and anchor plate, and for all materials, tools, labor, equipment and incidentals necessary to complete the work.