1 Chapter 7: Monitoring and Controlling Projects Introduction to Project Management Introduction to Project Management Copyright 2005 2 Learning Objectives • List several tasks and outputs of project monitoring and controlling, and describe outputs common to all knowledge areas. • Discuss performing integration change control as part of project integration management and how to use earned value management. • Explain the importance of scope verification, scope control, and accepting deliverables. • Describe the schedule control process and schedule performance measurement tools, such as tracking Gantt charts. • Discuss tools and techniques to assist in cost control.
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
1
Chapter 7:Monitoring and Controlling
Projects
Introduction to Project Management
Introduction to Project Management Copyright 2005 2
Learning Objectives• List several tasks and outputs of project monitoring
and controlling, and describe outputs common to allknowledge areas.
• Discuss performing integration change control aspart of project integration management and how touse earned value management.
• Explain the importance of scope verification, scopecontrol, and accepting deliverables.
• Describe the schedule control process and scheduleperformance measurement tools, such as trackingGantt charts.
• Discuss tools and techniques to assist in costcontrol.
2
Introduction to Project Management Copyright 2005 3
Learning Objectives (continued)
• List the Seven Basic Tools of Quality, and provideexamples of how they assist in quality control.
• Explain the monitoring and controlling work done aspart of project human resource management to helpmanage project teams and stakeholders.
• Summarize methods for performance reporting andmanaging stakeholders as part of projectcommunications management.
• Describe the risk monitoring and controlling process.• Explain how to monitor and control projects though
good contract administration.
Introduction to Project Management Copyright 2005 4
Introduction
• Monitoring and controlling involves regularlymeasuring progress to ensure that the project is meetingits objectives and addressing current business needs.
• The project manager and other staff monitor progressagainst plans and take corrective action whennecessary.
3
Introduction to Project Management Copyright 2005 5
Table 7-1. Summary of Project ClosingOutputs
Introduction to Project Management Copyright 2005 6
Monitoring and Controlling Tasks forProject Integration Management
• Main tasks include:– Monitoring and controlling project work, which involves
collecting, measuring, and disseminating performanceinformation as well as assessing measurements andanalyzing trends to determine what processimprovements can be made.
– Performing integrated change control, which involvesidentifying, evaluating, and managing changesthroughout the project’s life cycle.
4
Introduction to Project Management Copyright 2005 7
Forecasting With Earned ValueManagement
• Earned value management (EVM) is a project performancemeasurement technique that integrates scope, time, and costdata.
• Given a baseline, project managers and their teams candetermine how well the project is meeting scope, time, and costgoals by entering actual information and then comparing it to thebaseline.
• The baseline information includes:– Scope data (WBS tasks)– Time data (start and finish estimates for each task)– Cost data (cost estimates for each task)
• Note that you can use earned value management at either adetailed or a summary level.
Introduction to Project Management Copyright 2005 8
Earned Value Terms
• The planned value (PV) is that portion of the approved totalcost estimate planned to be spent on an activity during a givenperiod.
• The actual cost (AC) is the total direct and indirect costsincurred in accomplishing work on an activity during a givenperiod.
• The earned value (EV) is an estimate of the value of thephysical work actually completed. It is based on the originalplanned costs for the activity and the rate at which the team iscompleting work on the activity to date.
• The rate of performance (RP) is the ratio of actual workcompleted to the percentage of work planned to have beencompleted at any given time.
5
Introduction to Project Management Copyright 2005 9
Table 7-2. Earned Value Calculations forOne Activity After One Week
Introduction to Project Management Copyright 2005 10
Table 7-3. Earned Value Formulas
6
Introduction to Project Management Copyright 2005 11
Interpreting Earned Value Numbers
• In general, negative numbers for cost and schedulevariance indicate problems in those areas.
• Negative numbers mean the project is costing morethan planned or taking longer than planned.
• Likewise, CPI and SPI less than one or less than 100percent indicate problems.
Introduction to Project Management Copyright 2005 12
Forecasting with Earned Value• The budget at completion (BAC), or the approved total budget
for the project, can be divided by the cost performance index tocalculate the estimate at completion (EAC), which is a forecastof how much the project will cost upon completion.
• Likewise, the approved time estimate for the project can bedivided by the schedule performance index to calculate when theproject will be completed.– CPI = $700,000/$750,000 = .933333– SPI = $700,000/$689,500 = 1.015228– EAC = $1000,000/.933333 = $1,071,429– New time estimate = 12 months/.933333 = 11.82 months
• Earned value, therefore, provides an excellent way to monitorproject performance and provide forecasts based on performanceto date.
7
Introduction to Project Management Copyright 2005 13
Figure 7-1. Sample Earned Value Chart
Introduction to Project Management Copyright 2005 14
Objectives of Integrated Change Control
• Influence the factors that cause changes to ensure thatchanges are beneficial.
• Determine that a change has occurred.• Manage actual changes as they occur.• Note: The project management plan provides the
baseline for identifying and controlling projectchanges.
8
Introduction to Project Management Copyright 2005 15
Monitoring and Controlling Tasks forProject Scope Management
• The main monitoring and controlling tasks performedas part of project scope management are scopeverification and scope control.
• Key outputs are deliverables that are accepted by thecustomer.
• It is difficult to create a good project scope statementand WBS; it is often even more difficult to verify theproject scope and minimize scope changes.
Introduction to Project Management Copyright 2005 16
Scope Creep
• Even when the project scope is fairly well defined,many projects suffer from scope creep— the tendencyfor project scope to grow bigger and bigger.
• There are many horror stories about projects failingdue to scope creep.
• Even for fairly simple projects, people have a tendencyto want more.
• How many people do you know, for example, who saidthey wanted a simple wedding or a basic new houseconstructed, only to end up with many more extras thanthey initially planned?
9
Introduction to Project Management Copyright 2005 17
Scope Verification
• Scope verification involves formal acceptance of thecompleted project scope by the project sponsor ordesignated stakeholders.
• Acceptance is often achieved through customerinspection and then sign-off on key deliverables.
• The project team must develop clear documentation ofthe project’s products and procedures, which theappropriate stakeholders can then evaluate for thedegree of project completion and their satisfaction withthe results.
Introduction to Project Management Copyright 2005 18
Table 7-4. Sample Deliverable Acceptance Form
10
Introduction to Project Management Copyright 2005 19
Scope Control
• You cannot control the scope of a project unless you have firstclearly defined the scope and set a scope verification process inplace.
• You also need to develop a process for soliciting and monitoringchanges to project scope; stakeholders should be encouraged tosuggest beneficial changes and discouraged from suggestingunnecessary changes.
• For example, Northwest Airlines built in a special function keyfor users to submit change requests for a new reservationsystem. The project manager assigned three full-timeprogrammers to handle changes. Users made over 11,000enhancement requests. Although they only implemented 38percent of the requested enhancements, these were the mostimportant, and users were very satisfied with the system andprocess.
Introduction to Project Management Copyright 2005 20
Monitoring and Controlling Tasks forProject Time Management
• The main monitoring and controlling task performed aspart of project time management is schedule control.
• Project managers often cite delivering projects on time(schedule control) as one of their biggest challenges,because schedule problems often cause more conflictthan other issues.
• During project initiation, priorities and procedures areoften most important, but as the project proceeds,especially during the middle and latter stages of theproject, schedule issues become the predominantsource of conflict.
11
Introduction to Project Management Copyright 2005 21
Why Schedules Cause Conflicts
• Time is the variable with the least amount offlexibility; time passes no matter what happens on aproject.
• Individual work styles and cultural differences mayalso cause schedule conflicts.– People who prefer the “P” vs. “J” in the MBTI profile
may not like having schedules and deadlines.– Different cultural views of time affect meeting schedules
and attitudes toward work.
Introduction to Project Management Copyright 2005 22
Media Snapshot
• Many articles were written before the opening ceremonies of the AthensGames predicting that the facilities would not be ready in time. “With just162 days to go to the opening of the Athens Olympics, the Greek capital isstill not ready for the expected onslaught....By now 22 of the 30 Olympicprojects were supposed to be finished. This week the Athens OlympicCommittee proudly announced 19 venues would be finished by the end ofnext month. That’s a long way off target.”*
• The Games did go well. There were, however, several last-minute changesand many extra hours worked in the last few months before the games began.Costs exceeded $12 billion— more than double the original budget.**
• Many project managers and team members would have been morecomfortable if the original plans had been followed, but Greek workers takepride in putting in major efforts near a deadline. The Greeks even made funof critics by having construction workers pretend to still be working as theceremonies began.
*Fran Kelly, “The World Today— Olympic Planning Schedule behind Time,” ABC Online (March 4, 2004).**Reuters, “Olympics Bill Reportedly Passes $12 Billion,” MSNBC.com (August 25, 2004).
12
Introduction to Project Management Copyright 2005 23
Schedule Control Goals and Outputs
• The goal of schedule control is to know the status ofthe schedule, influence the factors that cause schedulechanges, determine whether the schedule has changed,and manage changes when they occur.
• A key output of schedule control is performancemeasurements, which are provided by:– Earned value management– Indicators– Milestone completion– Worker morale and discipline– Performance review meetings and tracking Gantt charts
Introduction to Project Management Copyright 2005 24
Figure 7-2. Sample Schedule PerformanceMeasurement Using a Tracking Gantt Chart
13
Introduction to Project Management Copyright 2005 25
What Went Right?
• Canadian Imperial Bank of Commerce (CIBC) provides anexcellent example of successfully controlling the schedule for alarge information technology project in the banking industry.CIBC transformed 20,000 workstations in 1200 differentfinancial branches in just one year. It created a Web-based toolto enable large, geographically dispersed teams to accessinformation simultaneously. Each of the 1200 sites had 75milestones to track, including the baseline, latest plan, and actualfinish dates, resulting in 90,000 data points. According to JackNewhouse, the company’s director of application support,CIBC’s Web-based tracking tool “was a critical component tosuccess....Accurate, timely data was an invaluable managementtool.”*
*Tom Chauduri and David Schlotzhauer, “So Many Projects, So Little Time,” PM Network(October 2003): 58.
Introduction to Project Management Copyright 2005 26
No Surprises
• Top management hates surprises, so the projectmanager must be clear and honest in communicatingproject status.
• By no means should project managers create theillusion that the project is going fine when, in fact,serious problems have emerged.
14
Introduction to Project Management Copyright 2005 27
Monitoring and Controlling Tasks forProject Cost Management
• The main monitoring and controlling task performed as part ofproject cost management is cost control.
• Cost control includes monitoring cost performance, ensuring thatonly appropriate project changes are included in a revised costbaseline, and informing project stakeholders of authorizedchanges to the project that will affect costs.
• Outputs include project management plan updates, documentationof corrective actions, revised estimates for project completion,requested changes, and updates to organizational process assets,such as lessons-learned documents.
Introduction to Project Management Copyright 2005 28
What Went Wrong?
• Many people have heard about the problems with Boston’s Big Dig project.Newspapers and Web sites showed the many leaks in the eight- to ten-laneunderground expressway that took over 14 years and $14 billion to build. Didthe project overseers cut corners to save time and money?
• Representative Stephen F. Lynch believes the answer to that question is yes,and that at some point, pressure to get the project done distractedBechtel/Parsons Brinckerhoff from getting the project done right. ‘‘Under thepressure and scrutiny of a lot of people, they went back to look at areas wherethey could reduce cost in areas of material and time,” said Lynch, a SouthBoston Democrat, in the aftermath of the Big Dig congressional hearing hebrought to Boston on April 22, 2005. Pressure to finally speed up the costly,long-running project may explain why the new Artery tunnel is plagued byleaks. ‘‘As a casual observer, I am forced to conclude that the focus on thecost overrun and the schedule distracted attention from quality control issueson the Central Artery project,” declared George J. Tamaro in writtentestimony to the Congressional Committee on Government Reform.*
*Joan Vennochi, “Time, Money, and the Big Dig,” Boston Globe (April 26, 2005).
15
Introduction to Project Management Copyright 2005 29
Monitoring and Controlling for ProjectQuality Management
• The main project quality management task formonitoring and controlling is quality control.
• Key outputs include quality-control measurements,validated defect repair, and validated deliverables.
• The main outcomes of this process are acceptancedecisions, rework, and process adjustments.
Introduction to Project Management Copyright 2005 30
Sample Quality Control Measurements
• Cause-and-effect diagrams: Help you find the root cause ofquality problems.
• Control charts: Illustrate the results of a process over time.• Run charts: Display the history and pattern of variation of a
process over time.• Scatter diagrams: Show if there is a relationship between two
variables.• Histograms: Show a bar graph of a distribution of variables.• Pareto diagrams: Help you identify and prioritize problem areas.• Flowcharts: Display the logic and flow of processes that help
you analyze how problems occur and how processes can beimproved.
16
Introduction to Project Management Copyright 2005 31
Figure 7-3. Sample Cause-and Effect Diagram
Introduction to Project Management Copyright 2005 32
Figure 7-4. Sample Control Chart
17
Introduction to Project Management Copyright 2005 33
Figure 7-5. Sample Run Chart
Introduction to Project Management Copyright 2005 34
Figure 7-6. Sample Scatter Diagram
18
Introduction to Project Management Copyright 2005 35
Figure 7-7. Sample Histogram
Introduction to Project Management Copyright 2005 36
Figure 7-8. Sample Pareto Chart
19
Introduction to Project Management Copyright 2005 37
Figure 7-9. Sample Flowchart
Introduction to Project Management Copyright 2005 38
Monitoring and Controlling Tasks forProject Human Resource Management
• The main human resource management task performedas part of monitoring and controlling a project ismanaging the project team, which is no small task!
• Project managers must use their soft skills to find thebest way to motivate and manage each team member.
20
Introduction to Project Management Copyright 2005 39
Introduction to Project Management Copyright 2005 40
General Advice on Managing Teams
• Be patient and kind with your team. Assume the best aboutpeople; do not assume that your team members are lazy andcareless.
• Fix the problem instead of blaming people. Help people workout problems by focusing on behaviors.
• Establish regular, effective meetings. Focus on meeting projectobjectives and producing positive results.
• Allow time for teams to go through the basic team-buildingstages of forming, storming, norming, performing, andadjourning, as described in Chapter 6. Do not expect teams towork at the highest performance level from the start; moreover,not all teams will reach even the performing level.
21
Introduction to Project Management Copyright 2005 41
General Advice on Managing Teams(continued)
• Limit the size of work teams to three to seven membersto enhance communications.
• Plan some social activities to help project teammembers and other stakeholders become acquainted.Make the social events fun and not mandatory.
• Stress team identity. Create traditions that teammembers enjoy.
• Nurture team members and encourage them to helpeach other. Identify and provide training that will helpindividuals and the team as a whole become moreeffective.
• Acknowledge individual and group accomplishments.
Introduction to Project Management Copyright 2005 42
Advice for Virtual Teams
• Take the additional actions necessary to workwith virtual team members.
• If possible, have a face-to-face or phonemeeting at the start of a virtual project or whenintroducing a virtual team member.
• Screen people carefully to make sure they canwork effectively in a virtual environment.
• Clarify how virtual team members willcommunicate.
22
Introduction to Project Management Copyright 2005 43
Monitoring and Controlling Tasks forProject Communications Management
• The main communications management tasks includeperformance reporting and managing stakeholders.
• Key outputs include performance reports, forecasts,and resolved issues.
Introduction to Project Management Copyright 2005 44
Performance Reporting
• Performance reporting keeps stakeholders informedabout how resources are being used to achieve projectobjectives.– Status reports describe where the project stands at a
specific point in time.– Progress reports describe what the project team has
accomplished during a certain period.– Forecasts predict future project status and progress
based on past information and trends.
23
Introduction to Project Management Copyright 2005 45
Figure 7-10. The Shortest PerformanceReview Meeting Ever
Unlike the managers found in Dilbert cartoons, most senior managers do wantto review pertinent information at status review meetings and discuss problems,issues, and forecasts!
Introduction to Project Management Copyright 2005 46
Table 7-5. Sample Performance Report
24
Introduction to Project Management Copyright 2005 47
Managing Stakeholders
• Project managers must address how they will identifyand resolve issues with stakeholders.
• An issue is a matter under question or dispute thatcould impede project success.
• An issue log is a tool used to document and monitorthe resolution of project issues.
• It’s important to resolve issues as soon as possible sothat the project can proceed as planned.
Introduction to Project Management Copyright 2005 48
Table 7-6. Sample Issue Log
25
Introduction to Project Management Copyright 2005 49
Monitoring and Controlling Tasks forProject Risk Management
• Monitoring and controlling risks involves executing therisk management processes to respond to risk events,which are specific, uncertain events that may occur tothe detriment or enhancement of the project.
• Carrying out individual risk management plansinvolves monitoring risks based on defined milestonesand making decisions regarding risks and theirresponse strategies.
• Project teams sometimes use workarounds—unplanned responses to risk events— when they do nothave contingency plans in place.
Introduction to Project Management Copyright 2005 50
Outputs of Monitoring and ControllingRisks
• Requested changes• Recommended corrective and preventive actions• Updates to the risk register, project management plan,
or organizational process assets, such as lessonslearned information that might help future projects
26
Introduction to Project Management Copyright 2005 51
Sample Risk Register Updates
• Recall that the number one risk event in the riskregister for the Just-In-Time Training project was apoor survey response. Because the project was nowhalfway completed, the risk register would have tochange significantly.
• For example, senior management informed Kristin thatGlobal Construction, Inc. was growing faster thanexpected, and they thought the number of peopleneeding training would be higher than expected. Thisinformation resulted in the identification of several newrisks related to accommodating this growth in trainees.
Introduction to Project Management Copyright 2005 52
Monitoring and Controlling Tasks forProject Procurement Management
• Administering the contract, or contract administration,ensures that the seller’s performance meets contractualrequirements.
• The contractual relationship is a legal relationship and,as such, is subject to state and federal contract laws.
• It is very important that appropriate legal andcontracting professionals be involved in writing andadministering contracts.
• A key output of contract administration is contractdocumentation.
27
Introduction to Project Management Copyright 2005 53
Tools and Techniques for ContractAdministration
• Formal contract change-control systems• Buyer-conducted performance reviews• Inspections and audits• Performance reporting• Payment systems• Claims administration• Records management• Information technology to support contract administration
Introduction to Project Management Copyright 2005 54
Watch for Constructive Change Orders
• Constructive change orders are oral or written acts oromissions by someone with actual or apparent authority that canbe construed to have the same effect as a written change order.
• For example, if a project team member has met with a supplieror contractor on a weekly basis for three months to provideguidelines for performing work, he or she can be viewed as anapparent authority.
• If he or she tells the contractor to redo part of a report that hasalready been delivered and accepted by the project manager, thataction can be viewed as a constructive change order, and thecontractor can legally bill the buyer for the additional work.
28
Introduction to Project Management Copyright 2005 55
Suggestions on Administering Contracts
• Changes to any part of the project need to be reviewed,approved, and documented by the same people in the same waythat the original part of the plan was approved.
• Evaluation of any change should include an impact analysis.There must also be a baseline against which to compare andanalyze changes.
• Changes must be documented in writing. Project team membersshould document all important meetings and telephone calls.
• Project managers and their teams must stay closely involvedwith suppliers to make sure that their deliverables meet businessneeds and work in the organization’s environment.
• Have backup plans in case the procurement does not produce thedesired results.
Introduction to Project Management Copyright 2005 56
Chapter Summary• Monitoring and controlling involves regularly measuring
progress to ensure that the project is meeting its objectives andaddressing current business needs.
• Every knowledge area includes tasks and outputs to helpmonitor and control projects. Outputs common to all knowledgeareas include requested changes, recommended correctiveactions, and updates to applicable plans and processes.
• Monitoring and controlling outputs related to integrationmanagement also include forecasts. Earned value management isa project performance measurement technique that integratesscope, time, and cost data.
• Monitoring and controlling tasks related to scope managementinclude scope verification and scope change control. A uniqueoutput includes accepted deliverables.
29
Introduction to Project Management Copyright 2005 57
Chapter Summary (continued)
• Monitoring and controlling outputs related to time, cost, andquality management include schedule control, cost control, andquality control. Unique outputs include performancemeasurements, forecasted completion, and quality-controlmeasurements.
• Monitoring and controlling outputs related to communicationsmanagement include performance reports, forecasts, andresolved issues.
• Monitoring and controlling outputs related to risk managementinclude updating the risk register.
• Monitoring and controlling outputs related to procurementmanagement include contract documentation.