© 2016 IBM Corporation Maximo Scheduler Solution Overview Michigan & Chicago Maximo Users Group Hosted by Herman Miller September 8, 2016
14

Maximo scheduler

Mar 20, 2017

Download

Software

Sun W. Kim
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Maximo scheduler

© 2016 IBM Corporation

Maximo Scheduler Solution Overview

Michigan & Chicago Maximo Users Group

Hosted by Herman Miller

September 8, 2016

Page 2: Maximo scheduler

Please Note:

• IBM’s statements regarding its plans, directions, and intent are subject to change or

withdrawal without notice at IBM’s sole discretion.

• Information regarding potential future products is intended to outline our general product direction and it should not be relied on in making a purchasing decision.

• The information mentioned regarding potential future products is not a commitment, promise, or legal obligation to deliver any material, code or functionality. Information about potential future products may not be incorporated into any contract.

• The development, release, and timing of any future features or functionality described for our products remains at our sole discretion.

• Performance is based on measurements and projections using standard IBM benchmarks in a controlled environment. The actual throughput or performance that any user will experience will vary depending upon many factors, including considerations such as the amount of multiprogramming in the user’s job stream, the I/O configuration, the storage configuration, and the workload processed. Therefore, no assurance can be given that an individual user will achieve results similar to those stated here.

1

Page 3: Maximo scheduler

Maximo Scheduler

7.6.3

Maximo Asset Mgmt

7.6.0.5

Maximo Scheduler

iLog

DOC Required only for

Optimization

• Add-on product to Maximo

EAM, code embedded in

core Maximo therefore a

single install

• Requires a separate

license purchase

• Includes integration

adapter and optimization

engine and models

• Optional: clients may choose

not to use the optimization

capability and can skip the

DOC installation during the

install process

DOC Server

Scheduler – embedded in Maximo

• 7.6.0.5 fix pack level 2

Page 4: Maximo scheduler

New Graphical Technology!

3

• No dependency on Java applet / JRE

• Significant usability enhancements

Page 5: Maximo scheduler

4 Role Based Applications

1) Graphical Scheduling

2) Graphical Assignment

3) Graphical Assignment – Repair Facilities

4) Graphical Crew Management

Also includes the Everyplace mobile templates to support the Field

Technicians and the Supervisor

4

Page 6: Maximo scheduler

5

Roles We Accommodate in Managing Work

Page 7: Maximo scheduler

Maximo Scheduler Pedigree

Work Orders in a Gantt View Labor Load/Avail. Critical Path Methodology PM Forecasts (7.1.1)

Work Orders in a Gantt View Labor Load/Avail. Critical Path Methodology PM Forecasts Graphical Assignment Dispatching Schedule Compliance Crews Asset, Location, Tools & Item Availability

Work Orders in a Gantt View Labor Load/Avail. Critical Path Methodology PM Forecasts Asset, Location, Tools & Item

Avail. Graphical Assignment Dispatching Schedule Compliance Crews Optimization / Automation Scenario Management Compliance Dashboards Graphical Crew Management

Long Term Planning Manual Long, Mid and

Short Term Planning Automated Long, Mid and

Short Term Planning

6

Page 8: Maximo scheduler

New capabilities built on a new technical foundation • Repair Facility Capacity

Planning • Repair Facility Graphical

Assignment Core Maximo PM costing • Includes Nested Job

Plans “Scheduler” application name change • New name: “Graphical

Scheduling”

Usability enhancements • Improved Gantt tools

and navigation

New Asset/Location scheduling capabilities built on a new technical foundation • Work Orders and PM

forecasts viewed by asset/location hierarchy

Multi-tenancy support Usability enhancements • Improved Gantt tools and

navigation

Port existing applications to the new technical foundation • Graphical Scheduling • Graphical Assignment

• Dispatch • Graphical Crew Management

Usability enhancements • Multi-column sort, search, and

filtering • Multi-craft/skill display • Undo / Redo • Expand / Collapse • Much more….

Addressing RFEs during these releases

7

Scheduler 7.6.x Delivery Timeline

Page 9: Maximo scheduler

Advanced use cases being requested by clients

• Ability to schedule customer appointments • Match customer's location and requirements with technician's skills and availability to schedule a service

appointment

• Model a complex project plan using real world interdependencies of tasks • A plant turnaround requires many dependent actions to shutdown the location, perform project work, and re-

start the location to bring it back to an operational stage

• Ensure resources with the right qualifications are assigned to work with special requirements • Supervisors need to ensure that technicians have valid certifications to do the work

• How do the current traffic conditions effect work in progress? • Incorporate real-time traffic conditions to better route technicians to their work locations

• Handle larger volumes of data • Many Maximo clients require the ability to manage a heavy volume of work orders be it for shutdowns,

turnarounds, outages, or for dispatching field technicians

Page 10: Maximo scheduler

Appointment scheduling

• Make customer appointments within a schedule window

• Customer notifications – cancel / reschedule

Managing large projects

• Dependencies across work orders and tasks

• Highlight critical path, backward pass, % complete

Weather integration

• Incorporate weather data into planning/scheduling and dispatching

• Weather alerts / notifications

Dynamic dispatching

• Auto refresh, re-optimization based on real-time progress

• Incorporate real-time traffic conditions

Introducing – Scheduler Plus!

Advanced work management solution, built on top of Maximo Scheduler

The information on the new product is intended to outline our general product direction and it should not be relied on in making a purchasing decision. The information on the new product is for informational purposes only and may not be incorporated into any contract. The information on the new product is not a commitment, promise, or legal obligation to deliver any material, code or

functionality. The development, release, and timing of any features or functionality described for our products remains at our sole discretion. . 9

Page 11: Maximo scheduler

Scheduler Plus – also embedded in Maximo

Maximo Asset Mgmt

Maximo Scheduler

iLog

DOC

Required for

Optimization

Maximo Scheduler

Maximo Scheduler

Plus

• Advanced scheduling

solution

• Add-on product to

Maximo Scheduler,

code embedded in

core Maximo therefore

still a single install

• On-prem and via SaaS

• Requires a separate

license purchase

• Includes the

optimization models

10

Page 12: Maximo scheduler

Maximo Scheduler and Scheduler Plus – Roadmap

Notice: IBM’s statements regarding its plans, directions, and intent are subject to change or withdrawal at IBM’s sole discretion. Information regarding potential future

products is intended to outline our general product direction and it should not be relied on in making a purchasing decision. The information mentioned regarding potential

future products is not a commitment, promise, or legal obligation to deliver any material, code or functionality. Information about potential future products may not be

incorporated into any contract. The development, release, and timing of any future features or functionality described for our products remains at our sole discretion.

Weather − Configurable weather views − Enabled in Graphical Scheduling and

Graphical Assignment Appointment Scheduling

- Make customer appointments within a schedule window, see tech availability, incorporate weather

- Cancel, reschedule appointments Network dependencies (Phase 1)

- Link across WOs and tasks

Weather impact on Assets − Weather overlay on maintenance/operational

windows Weather impact on Job Plans

− Adding weather requirements to conditional job plans

− Variable length condition (ex: weather impacted) − Go or No Go criteria − Applying conditional job plan tasks to existing

WOs Network dependencies (Phase 2)

- Backward pass - Highlight critical path - Introduce % complete

Excel Export Enhance status color to include synonyms

Qualifications at WO & Task Level - Manual and Optimization

Weekly and Monthly planning buckets

Performance

Dynamic Dispatching − Auto refresh for improved tracking of

progress − Re-optimization based on real-time

progress, including emergent work − Real-time road conditions and traffic − Continuous weather updates and

weather event notifications − Everyplace template updates - weather

Weather based assignments

− Manual clearing of decks − Optimization – reschedule planned

and emergency

Enhanced resource availability − WO outside schedule, shifts/breaks

PM display − Constraint window − Compare PM scenarios − Emergency template (ex. Weather

event activity) Performance

Scheduler Scheduler Plus

Page 14: Maximo scheduler

Questions

13

SOLUTION DEMO