LVBC LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management
52

LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

Apr 02, 2015

Download

Documents

Vernon Parden
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

LVBC

The 3rd Lake Victoria Basin Donors’ conference

17th -18th June 2013

Mr. Mathias Chemonges

Climate Change, Environment &Natural Resource Management

Page 2: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Climate Change, Environment and Natural Resources

1. Reducing Emissions from Deforestation and Forest Degradation (REDD+) Programme for the Mt. Elgon Ecosystem

2. Intergrated Climate Change Adaptation and Mitigation Programme in Lake Victoria Basin

3. Regional Water Resources Management Project4. Mechanical removal of Water Hyacinth in Lake Victoria5. Kisat River Catchment Restoration Project (KRCRP)6. Nyungwe –Kibira Transboundary Conservation Programme7. Development of the state of the lake and Basin Report

PRESENTATION OUTLINE

Project Concept Notes

Background /Introduction

Page 3: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC MORPHOMETRIC DATA FOR LVB

• Million at beach level), Foreign exchange ~ US

$ 250 million• Major water transport

linkage for the landlocked Uganda,

Kagera

Page 4: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Country Lake Surface Area Catchment Area Lake Shoreline

Sq Km % Sq Km % Km %

Tanzania 33,756 49 79,570 44 1150 33

Uganda 31,001 45 28,857 15.9 1750 50

Kenya 4,113 6 38,913 21.5 550 17

Rwanda - 20,550 11.4 -

Burundi - 13,060 7.2 -

Total 68,870 180,950 3,450

THE LAKE AND THE BASIN

Page 5: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Four main types impacting the LVB:

Stresses within the lake – over-fishing, untreated liquid wastes, water hyacinth, over-abstraction

Stresses on littoral zones – construction and farming in shoreline, conversion of wetlands, poor solid wastes management

Stresses from the basin – land degradation, deforestation, inflow of water hyacinth, pollution from agro-chemicals, sediment loads, poor solid waste management

Stresses from outside the basin – nutrients (N and P) transported into the basin by air, climate change

Deteriorating water quality – caused by increased sedimentation, and pollution and eutrophication

Fluctuating lake levels – due to unsustainable LVB water management practices

Overexploitation of natural resources – caused by increased basin population and competition over natural resources

Resurgence of water hyacinth

Climate change

CHALLENGES: Environmental stresses in the Basin

Page 6: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

• Stresses within the lake

Stresses from the basin

Stresses on littoral zones

Stresses from outside the basin –

Environmental stress within the LVB

Page 7: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Environmental Stress in LVB

• Stresses within the lake – – e.g., over-fishing, oil spills, untreated

liquid wastes, water hyacinth, over-abstraction of water from the lake and its basin.

– Fish Frame-survey 2012 shows overfishing of through increase of illegal gillnet by 26% but mostly for 2 ½” and 3 ½”There was a serious increase in legal nets of size > 10 by 343% and the 10” by 156% compared to 2010 Survey.

– In 2005 average BOD in, 5000Kg day respectively in major cities

Littoral zones e.g., construction and farming in shoreline, conversion of wetlands, poor solid wastes management.estimated about 75% of Lake Victoria’s wetland area has been affected significantly by human activity

• Stresses from outside the basin nutrients (N

and P) transported into the basin by air, climate change. In 2005/6 estimated atmospheric depositions accounted for about 60% of the total Phosphorus and over 80% of the total N loading to the lake.

• Stresses from the basin– e.g., land degradation, deforestation,

inflow of water hyacinth, pollution from agro-chemicals, sediment loads, poor solid waste management.

– Water hyacinth coverage in 2010 Kenya 10,000ha and TZ=540ha.

– The deforestation rate is estimated to be 55,000 to 100,000 ha per year, based on habitat change from 1990-1995.

Page 8: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC UPSTREAM DEFORESTATION

INCREASING ENCROACHMENT OF LITTORAL WETLANDS FOR AGRICULTURE

INCREASING WATERSHED DEGRADATION DUE TO POOR LAND USE PRACTICES

Page 9: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Terminal at Mwanza South port left hanging

EUTROPHICATION

• Visibility decreased by about 75%. (Max readings at 70 m depth in Feb 2006 was ~5 m)

Chlorophyll

a (mg m

-3)

0

5

10

15

20

1965 2006

Secchi disc vis

ibility (m)

0

2

4

6

8

101965 2006

Depth of oxyclin

e (m)

0

20

40

601961 2006

Fish catch (t x

1000)

0

400

800

1200

1960s 2000s

Secchi depth (m)

0 65

TSS (mg/l)

EFFECTS OF LAKE LEVEL FLUCTUATIONS

Page 10: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC OPPORTUNITIES

Page 11: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

LVBC

REDD+ refers to Reducing Emissions from Deforestation and forest Degradation and also sustainable forest management, conservation and enhancement of forest carbon stocks.

A REDD+ program can encompass a range of activities within a designated area, e.g: tree planting, agroforestry, training & education, microfinance.

Governments – including Uganda & Kenya are developing national REDD+ strategies applying general UNFCCC guidelines and with donor support.

Carbon markets can help to finance sustainable land management activities for the benefit of communities, global and local environment.

Sub-national (project-based) initiatives can help increase national capacity, and provide additional resources to the national REDD+ program.

The LVBC would like to work with relevant partners to develop a trans-boundary, sub-national REDD+ initiative in the Mt. Elgon area.

Introduction to REDD+006 - REDD+ FOR MT. ELGON ECOSYSTEM PROJECT CONCEPT NOTE

Page 12: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

An international performance-based system is being developed for REDD+ under the UNFCCC.

Voluntary carbon market standards have methodologies that allow sub-national projects to receive carbon credits for REDD+ activities. These follow the same principles that non-forestry UNFCCC carbon credit projects.

Long-term the funding is likely to come from the private sector, through markets. Total value of carbon market in 2011 was over 176 Billion US dollars.

The Mt Elgon REDD+ initiative will seek to use voluntary carbon market funding for activities, AND will complement the national systems that are being developed.

REDD+ Contd..

Page 13: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

1. To create a framework for a trans-boundary sub-national REDD+ programme including shared methodology components, monitoring system, and harmonized governance mechanisms.

2. Implement at least 2 distinct REDD+ projects, one in Kenya and in Uganda, which can be a national REDD+ demonstration pilot for each country.

1. To define & agree on ecosystem boundary, map activities, and land use patterns.

2. To establish appropriate institutional infrastructure3. To assess potential benefits from, and negative impacts of,

REDD+ activities:4. To assist with the identification, implementation and

management of project activities by REDD+ proponents.5. To assist with the promotion and funding of the REDD+

projects.

REDD+ Project Objectives

Specific Objectives

Page 14: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Factory in Europe

The factory cannot reduce its emissionsIt buys 50 tCO2 per year from the forest project

Sale of 50 t CO2 each year

Payment for the Carbon Credits

Carbon Credit Project (e.g. from REDD initiative)

Produces: 150 tCO2 per yearReduction commitment:100 tCO2 per year

Theoretical example of how carbon markets work:

Carbon Markets: What are they?

Page 15: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

• Kenya developed its National Climate Change Response Strategy (NCCRS) in 2010, and other policy initiatives to tackle climate change issues have since been developed. REDD+ is an important component of Kenya’s strategy. Vision 2030 also enshrines relevant environmental goals, e.g. in protecting Kenya’s “Water Towers”.

• Kenya an Uganda is supported in national REDD+ strategy development from the World Bank and other donors. GoK intends to

develop sub-national pilots.• The National REDD+ initiative is with the Ministry of Water and

Environment in Uganda. • A number of consultations have already been carried out, lead by IUCN in

this region.

REDD+ in Kenya and Uganda (1/2)

Page 16: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

• Initiated in 2011 by MERECP, and finalized in 2012.• Mt Elgon is a critical, shared forest area and watershed for both

Kenya and Uganda and it is under threat.• Strong support from both Governments, input from NGOs (e.g.

IUCN), input from communities (workshops).• Discussions on the main drivers of forest cover change, existing

interventions and possible new interventions.• Strategy suggested phasing, local governance structures, benefit

sharing mechanisms, safeguards and next steps.

Overview of Mt. Elgon REDD+ Strategy

Page 17: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

PIN• “Pro

gram Idea Note” to summarize REDD+ initiative & raise funds

Fund-raise• Rais

e funds from donors, charities, private sector (e.g. carbon funds)

Preparation• Detai

led technical feasibility work, certification, manag’t structures etc.

Begin to

implement

April / May 2013 Ca. 12 – 18 months

June LVBC-donor meeting

Proposed Next Steps for REDD+ in Mt Elgon

Page 18: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Possible Governance – Mt. Elgon

Page 19: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Expected Deliverables of the Project1. Carbon credit project documentation: E.g. Project Idea Notes (PINs), Project

Design Documents (PDDs), verification, validation and registration documents for issuance of carbon credits (likely Verified Carbon Units under the Verified Carbon Standard and accreditation by Climate, Community and Biodiversity Standards)

2. Annual reports from the institutional framework that supports the trans-boundary REDD+ program

3. Project events and reports, e.g. disseminated Learning Reports and presentations at various international meetings as this is a first-of-kind initiative

Page 20: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Total budget US$ Million Total(Ca. 6 years,

rounded)Social interventions 1.265Governance interventions 2.800Environmental interventions 5.585Economic interventions 4.280Sub-total for interventions 13.93

Reference Level / Reference Emission Level (RL / REL) 0.59

Monitoring, Reporting and Verification (MRV ) 1.06Sub-total for RL/REL and MRV 1.65

Management framework 0.10Benefit sharing models 0.20Safeguard framework 0.20

Total: set up of institutional frameworks 0.50

Sub-total 16.08Management and administration cost @10% for 6 yrs 1.61

Grand total, 6 year budget 17.69

Total budget estimate for REDD+ strategy implementation

Page 21: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

LVBC

Programme Overall Objective

Enhance nature conservation and sustain people’s livelihoods in critical landscapes in the Lake Victoria Basin through ecosystem and community based climate change adaptation initiatives over the next five years.

Specific Objectives

1. To influence policy, legislation and institutional approaches to support climate change adaptation and mitigation

2. To reduce loss of biodiversity and ecological footprint in critical ecosystems

3. To promote sustainable management and utilization of water resources

4. To enhance capacity of stakeholders/ actors and groups to alleviate impacts of climate change

5. To promote livelihood options that lessen impacts of climate change

6. To enhance the knowledge base of the stakeholders / actors in the basin on climate change and adaptation

7. To integrate gender and HIVR&AIDS dimensions in the reduction of climate change impacts

007: Project concept note

INTEGRATED CLIMATE CHANGE ADAPTATION AND MITIGATION PROGRAMME IN THE LAKE VICTORIA BASIN-

PCN 7

Page 22: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

LVBC

a. Undertaking protection, management and restoration activities

b. Advocacy for public –private sector partnerships

c. Support for policy work, CSO strengthening, fuel efficient stoves

d. Policy interventions, Managing Climate Change Vulnerabilities ,Climate change adaptation and

e. Promoting community based natural resource management.

f. Education for Sustainable Development

Programme Strategies

Page 23: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

a. Improved policy, legislation and institutional approaches to climate change

b. Increased adaptive capacity to address the impacts of climate change

c. Enhanced capacity on climate change adaptation and mitigation

d. Reduction of forest habitat conversion to agriculture

e. Reduction of demand for fuel wood & charcoal from protected areas

f. Reduction of water pollution from farmland and other effluents

g. Reduction of illegal poaching, wildlife trade & human wildlife conflicts  

1. Protection, management and restoration

2. Community, livelihoods and resilience to climate change

3. Institutional, Legal and Policy Enhancement

4. Capacity Building5. Cross cutting Issues

(Gender, HIV & AIDS)6. Conservation Targets

Expected OutcomesProgramme components

Page 24: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Consolidated Budget

• Consolidated budget of Objectives 1-6 USD 5 Million

Page 25: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

OO8:Project concept notes summary

The region is among the poorest in the world with two of the countries being among the five poorest countries in the World.

dependent on rain fed agriculture, subsistence farming; low industrialization; poor infrastructure,

low levels of education attainment and skilled human resources, gender exclusion,

an average life expectancy of 50 and high population growth of 3% per annum.

The AIDS scourge, poor and inadequate education infrastructure and human capital flight worsen the situation..

• There are four main sources of environmental stresses adversely impacting the LVB ecosystem, as well as the region’s economy and livelihoods.

1. The effect of the above environmental stresses is the severe environmental degradation of the LVB ecosystem.

2. Increased sedimentation:3. Increased pollution and euthrophication:4. Wetlands destruction:.5. Forest degradation:  

REGIONAL WATER RESOURCES MANAGEMENT PROJECTS

Page 26: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Why IWRM Programme

1. LVEMP is finalising WRMP which will be based on IWRM2. Inadequate IWRM capacity to implement WRMP for the various

stakeholders 3. The project is aiming at providing IWRM capacity to key

stakeholders at various level

Page 27: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Goal, Objectives &Project components

The overall goal to which the project will contribute to is “Enhance the development and management of the LVB water resources in a sustainable manner by addressing water quality challenges through the promotion of the IWRM in the Region”

The objective of the project is “To address water quality challenges in the Lake Victoria Basin through the IWRM principle.

Proposed Componentsa. To address the water quality challenges in the Lake Victoriab. Promote public awareness and sensitisation campaigns on IWRM to

enhance stakeholder awareness and appreciation of Integrated Transboundary Water Resources Management.

c.  Capacity Building: d. Project Management and Coordination

Page 28: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Expected Deliverables of the Project1. Improved water quality and livelihood on the selected

interventions areas and towns; 2. Public becomes more aware on the IWRM and sensitisation

campaigns on IWRM to enhance stakeholder awareness and appreciation of Integrated Transboundary Water Resources Management conducted; and

3. Capacity built at all levels for Relevant Central, Local Government Agencies, NGOs and CBOs ;

4. Project managed and additional activities include field missions, RPSc meetings and various operational activities conducted. Consultants supervised and output delivered, LVBC field supervision report, annual audit reports, quarterly, and annual progress reports.

Page 29: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC ESTIMATED BUDGET BY COMPONETS

Component

Description Amount in USD

1 To address the water quality challenges in the Lake Victoria

1,200,000

Promote public awareness and sensitisation campaigns on IWRM to enhance stakeholder awareness and appreciation of Integrated Transboundary Water Resources Management.

400,000

2 Build Capacity of Relevant Central and Local Government Agencies in IWRM

1000000

3 Build Capacity and Contribute Toward the Operations of NGOs and CBOs Relevant to the Lake Victoria Basin

400000

4 Project Management and Coordination 300,000

Total 3,300,000

Page 30: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

LVBC

Water hyacinth Eichhornia crassipes (Mart) Solms is a perennial plant native to tropical America.

First noted in East Africa in the 1930s and in Lake Victoria in 1989- Uganda& Tanzania and in 1990 in Kenya

Officially recognized a noxious invasive weed in the late 1980’s In Uganda, weed control efforts began in 1993 by involving the local

communities. In 1995 Tanzania implemented an integrated noxious weed management

control (bioligical, manual &, quarantine regulations and s control of nutrient influxes )

In Kenya the weed coverage was at 17,200ha by 1998 (4Njoka and Kusewa, 2006).

Weed control involved biological methods using weevils and mites and a mechanical harvesting at peak infestation in 1998

mechanical removal supported by biological control and sustainable manual removal programmes are the most viable options

need for strong coordination of weed control programs by the lake basin governments.

Mechanical Removal and Management of Water Hyacinth in Lake Victoria

Page 31: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Pure mat of hyacinth

Mat invaded by I. aquatica and E,fluctuans

Mat invaded by hippo grassLate stages

INCREASING INFLOW OF WATER HYACINTH

Page 32: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Climax stage

Collapse

Debris at the lake bottom

1. To mechanically remove water hyacinth from hot spot areas to manageable levels.

2. To manage remnant populations of water hyacinth through sustainable control programmes.

WATER HYACINTH SUCCESSION

OBJECTIVES

Page 33: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Project Area The main project area is Lake Victoria ie major ports and bays in each of the three

East African countries.

Project implementation Approach The project will be implemented in the entire Lake Victoria and rivers focusing on areas

infested by water hyacinth. LVBC will coordinate (establishment of institutional frameworks, capacity building,

implementation processes). Implementation will involve relevant government departments, LVBC, private sector,

existing local communities and other stakeholders. Government agencies and other stakeholders will provide technical support and also

oversee implementation to ensure further sustainability of project.

Monitoring and Evaluation Monitoring and Evaluation (M&E) will form an integral part of the project planning and

implementation process. The process will adopt the following approach; Carry out at least one quarterly monitoring and evaluation exercise at the cluster levels Carry out at least two monitoring and evaluation exercises per year at the national level Prepare monitoring and evaluation reports A midterm evaluation will be undertaken after 2½ years

Project Area, Approach &M&E

Page 34: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Expected Deliverables of the Project

1. Water hyacinth menace reduced to the ecologically and socio-economically acceptable levels (80% of current water hyacinth removed).

2. Sustainable water hyacinth management regime established- regionally

3. Improved economies, environment and social life of communities within Partner States

Page 35: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Project Objectives Total budget (US$)

Objective 1: To Mechanically remove water hyacinth from hot spot areas to manageable levels.

3,722,664

Objective2: To manage remnant populations of water hyacinth through sustainable control programmes.

12,769,664

Project Coordination and M&E (10%)

1,276,966

GRAND TOTAL (USD) 14,046,630

Estimated Budget

Page 36: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

LVBC

010: project concept note summary

INTRODUCTION AND BACKGROUND The total harvestable fish biomass of between 700,000MT –

1,000,000mt (Mkumbo et al, 2005) Fishery industry employs over 2 million people. inter-state trade and tourism using existing ports like

Kisumu. Source of drinking water. In urban setups stream and river ecosystems are not

protected by buffer zones Malfunctioning sewerage facilities Consequently this has led to sedimentation and

eutrophication Carry out rehabilitation and restoration interventions in

catchments One such river is the Kisat River, located within the Kisumu

City. Kisat is a short river of about 4km, wholly within Kisumu City.

KISAT RIVER CATCHMENT RESTORATION PROJECT (KRCRP)

Page 37: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

LVBC

1. Rehabilitate the degraded areas within the Kisat river catchment

2. Develop and implement an integrated solid waste management system within the catchment

3. Reduce municipal and industrial effluent discharges into river Kisat

4. Establish and maintain environmental flows for the Kisat river

5. Develop and implement a Master Plan for economic utilization of riparian zone

Objectives

Page 38: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

At the end of the project period, it is expected that the following outputs will have been achieved:

1. Reduced pollution load discharge into Lake Victoria2. Improved solid and liquid waste management,

sanitation facilities and therefore water quality3. Well conserved riparian areas with rehabilitated

riverbanks providing increase potential for recreation and sustainable economic activities

4. Improved access to clean fresh water for industrial and domestic use for residents of Kisumu City

5. Enhanced public awareness on the environment

Expected Outputs

Page 39: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Project Area -The River Kisat Watershed, in Kisumu, Kenya.

Project design-• Phase one survey and delineation of the riparian zone of the river and mapping of

industries and pollution hot spots• Phase two of the project will focus on implementation of rehabilitation and

restoration interventions Project implementation Approach• integrated multi-sectoral approach to ensure sustainable solutions are put in place.• multiple stakeholders from the Government, Civil society, Private Sector,

development partners and communities Monitoring And Evaluation • a participatory approach and fitted into the larger LVBC framework. • LVBC will coordinate the tracking of day-to-day progress• A baseline will be generated at the start of the project period• Mid-term review and end term evaluation will also be inbuilt into the project design.

Project Area, Design, Approach and M&E

Page 40: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Expected Deliverables of the Project

1. Reduced pollution load discharge into Lake Victoria2. Improved solid and liquid waste management, sanitation

facilities and therefore water quality3. Well conserved riparian areas with rehabilitated riverbanks

providing increase potential for recreation and sustainable economic activities

4. Improved access to clean fresh water for industrial and domestic use for residents of Kisumu City

5. Enhanced public awareness on the environment

Page 41: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Project Objectives Total budget (US$)

Objective 1: To rehabilitate the degraded areas within the Kisat river catchment.

428,750

Objective 2: To develop and implement an integrated solid waste management plan within the catchment.

373,750

Objective 3: To reduce municipal and industrial effluent discharges into river Kisat: A. Cleaner production activities

622,500

Objective 3:A.Municipal waste, liquid waste and improved sanitation will be achieved by carrying out the following activities

242,500

Objective 4: To establish and maintain environmental flows for the Kisat river

345,000

Objective 5: To develop and implement a Master Plan for economic utilization of riparian zone

337,500

Project Coordination /management, communication, Monitoring and evaluation

795,000

Grand Total 3,145,000

Estimated Budget

Page 42: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

LVBC

a) The forestry resources component supports highly the communities ( foods, fruits, construction materials, pasture and spiritual)

b) High forest destruction in Kibira – Nyungwe forests in Rwanda, Burundi

c) The Rwanda 90,000 ha, Burindi Ruvubu National Park (50,000ha) and the Kibira National Park (40,000ha).

d) The quality of natural habitats, protected areas, wetlands and aquatic resources within trans- Overexploitation or invasion of other species alien to the area.

e) Need for concerted efforts from the EAC Partner Statesf) Currently efforts are fragmentedg) harmonization of institutions, policy, legal and systems and

procedures for effective TBNRM

011: Project concept note

PROMOTING NATURAL RESOURCES MANAGEMENT IN KIBIRA – NYUNGWE TRANS-BOUNDARY ECOSYSTEMS

Page 43: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

The E A is endowed with a variety of natural resources. Some of them are transboundary: Terrestrial Ecosystems Various categories:

– The Mountain Forest Ecosystems– The Eastern Arc Mountains– The Dry Mountain Forest Ecosystems– The Lowland Ecosystems– The Lowland Rain Forest Ecosystems

43

Among the above category of transbounndary terrestrial Ecosystems, we find the following:• Mt. Kilimanjaro (TZ/KE)- highest Mt in Africa;• Mt. Elgon (KE/UG);• The Eastern Arc Mountain Forests (Taita and• Pare Hills in KE/TZ);• Mara-Serengeti (KE/TZ) wildebeest migration;• Kajiado – Moduli dry lands (KE/TZ);• Albertine Rift Mountains

– Nyungwe- Kibira (Rw-Bu)– Volcano-Virunga Mountains-Mgahinga(DRC, Rw, Ug)

Trans-boundary Terrestrial Ecosystems

Shared Ecosystems in East Africa

Page 44: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

The Lake Victoria Basin-Africa’s largest lake (KE/UG/TZ); • Lake Tanganyika, “aquatic biodiversity hotspot”(TZ/BR/ZM/DRC) -2nd longest and 2nd deepest lake in the world found in the Albertine Rift;• Minziro-Sango Bay Swamp Forest (UG/TZ) along the shores of Lake Victoria;• Lake Malawi-TZ /Mozambique;• Lake Jipe and Chala (KE/TZ);

44

• High dependence by adjacent communities (proximity of the protected areas posing- fire, poaching, encroachment );

• inadequate institutional arrangements/structures,.

• The lack of formal institutional collaboration arrangements between two or more countries in the (human, infrastructure, funds, procedures, policies, and knowledge)

• un-harmonized immigration procedures; and lack of ecosystem approach competence and capacity for (TBNRM).

• joint management and joint monitoring and protection within the wildlife, forest, water and wetland Acts of the respective countries;

• differential application of user rights and responsibilities of stakeholders (e.g. local communities);

• no formal provision for intelligence information sharing by the protected areas institutions;

Shared Aquatic Ecosystems

TBE Management challenges

Page 45: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

1. Promote trans-boundary conservation, natural resources and participatory benefit sharing and co-management models of ecosystem and biodiversity conservation and management around protected areas;

2. Create opportunities for payment of ecosystem goods and services for improved livelihoods through equity and benefit sharing models/revolving funds;

3. Link livelihood improvement to climate change mitigation and adaptation in trans-boundary ecosystems;

4. Strengthen appropriate institutions in support of cooperation and collaboration in the management of trans-boundary ecosystems.

Objectives

Page 46: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Expected Deliverables of the Project

1. Mechanisms to promote, support and sustain trans-boundary collaboration established;

2. Capacity of implementing institutions build towards effective and participatory conservation of Nyungwe- Kibira ecosystem;

3. Communities empowered to participate in equitable resource governance

Page 47: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

Objectives

Description Amount USD

1 To promote trans-boundary conservation, natural resources and participatory benefit sharing and co-management models of ecosystem and biodiversity conservation and management around protected areas.

1,680,000

2 To create opportunities for PES for improved livelihoods through equity and benefit sharing models/revolving funds

750,000

3 To link livelihood improvement to climate change mitigation and adaptation in trans-boundary ecosystems

900,000

4 To Strengthen appropriate institutions in support of cooperation and collaboration in the management of trans-boundary ecosystems

500,000

5 Programme Management and coordination 1,384,000

TOTAL 5,214,000

Estimated Budget

Page 48: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

O12: project concept note summary

Development of state of the Lake Basin report

Page 49: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Project Goal ,Objective &Output

Goal _ to develop the State of the Lake Victoria basin report.specific objectives :a. Assess the environmental profile of the Lake Victoria basin, including the Lake Victoria and its

basin including a description of the global environment (different ecosystems), plus environmental governance in the Lake Victoria basin;

b. Assess the water resources of the Lake Victoria basin including analysis of the Lake Victoria and its basin water resources, quantity and quality, surface and ground water, hydrology and climatology;

c. Assess the socio-economic status of the Lake Victoria basin including poverty analysis, a demography analysis, urbanization, employment, people’s health, youth and economic growth;

d. Assess the water uses in the Lake Victoria basin; ande. Elaborate a scenario analysis – this includes a synthesis of the emerging issues presented

before and their trends.

Page 50: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC Deliverables

1. Status of physical chemical and biological characteristics of the Lake;2. Information on the status of human health and toxins 3. Status of natural resources, biodiversity and aquatic invasive species of the

Lake and its basin.4. The socio-economic status of the Lake and its catchment.5. Climate change and hydrology of Lake Victoria and the basin6. Emerging issues on Lake Victoria and the basin;7. Opportunities and challenges with respect to the sustainable management and

development of the Basin;8. Critical role that cooperation among stakeholders can play in optimizing the

benefits and bringing about equitable utilization of LVB common resources;9. Indicators for monitoring the health of LVB

Page 51: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC

  Component Outputs Specific activities/input Category

Unit Total Unit Cost (US $)

Total cost in US$

1 Consultancy Services to Conduct a State of the Lake Victoria and its Basin

1.1 Consultancy Fee ( Total man months as per the ToRs – 20 for 4 staff )

Consul Man Month

10 man months

for 4 staff

500 per day 400,000

    1.2 Reimbursable Consultants costs

Consul Lump sum

1 100000 100000

    1.3 Regional Technical working groups meetings to support review the reports

OC Lumpsum

1 60,000 60,000

    1.4 Regional Stakeholders' consultations and workshop to review and adopt the reports.

OC Lumpsum

1 100,000 100,000

    1.5: Operational costs (stationary etc) for amended policies, regulations and laws on natural resources.

OC MATERIALS

1 10,000 10,000

    1.6: Support national Task Force activities (4 staff members for each of the 5 Partner States)

OC No 5 50,000 250,000

Conducting one Joint monitoring mission in the Lake and Basin – hire a ship and vehicles- Costs for national and

regional staff

OC No lump sum

100000 100000

Printing and dissemination costs

100,000

Total budget     1,120,000

ESTIMATED BUDGET

Page 52: LVBC The 3 rd Lake Victoria Basin Donors’ conference 17 th -18 th June 2013 Mr. Mathias Chemonges Climate Change, Environment &Natural Resource Management.

LVBC