Building the Future Current Activities this Week: Site/Playing field: Grading site on the East side of building to be ongoing. Pouring of the truck dock entrance on the east side to be ongoing. Grading of the plaza area is ongoing. Underground drainage and irrigation at the playing field is ongoing. Plaza storm line installation has begun. Concrete Flatwork: Area 1-Suite and Press level tub intermediate stairs are complete. Area 3-Topping slab at cauldron club to be completed. Area 1- SOG work at SW toilet entry to be completed. Masonry : Block installation at NW transformer area to be ongoing. Block installation at Terrace Bar is ongoing. Sealing and final wash of block on the East side to be ongoing. Stone: Area 1-Stone installation in area H to be ongoing. Steel : Installation of stone support steel at Stadium Suite is ongoing. Installation of dock overhead doors to be complete. Installation of wind columns/screen wall support at stair #1 to be completed. Installation of Bar/counter top support steel to be ongoing. To: David Ficklin - OnGoal Rory O’Connor – OnGoal Lee Turner – OnGoal Andy Heitmann – Turner Dave Dudzik - Turner Brandon Valdez-Turner From: Nick Durand Office: Kansas City Date: 3.9.2011 Re: Sporting Kansas City Project Update – Week of 3.9.2011 Installation of field drainage and irrigation lines is ongoing. Plaza utility work has begun.
6

LIVESTRONG Sporting Park Construction Update (3/9/11)

Dec 01, 2014

Download

Sports

SportingKC

LIVESTRONG Sporting Park is the $200 million, state-of-the-art stadium home to Sporting Kansas City of Major League Soccer. It will open June 9, 2011.
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: LIVESTRONG Sporting Park Construction Update (3/9/11)

Building the Future

Current Activities this Week:

Site/Playing field:

Grading site on the East side of building to be ongoing.

Pouring of the truck dock entrance on the east side to be

ongoing.

Grading of the plaza area is ongoing.

Underground drainage and irrigation at the playing field

is ongoing.

Plaza storm line installation has begun.

Concrete Flatwork:

Area 1-Suite and Press level tub intermediate stairs are

complete.

Area 3-Topping slab at cauldron club to be completed.

Area 1- SOG work at SW toilet entry to be completed.

Masonry:

Block installation at NW transformer area to be ongoing.

Block installation at Terrace Bar is ongoing.

Sealing and final wash of block on the East side to

be ongoing.

Stone:

Area 1-Stone installation in area H to be ongoing.

Steel:

Installation of stone support steel at Stadium Suite is

ongoing.

Installation of dock overhead doors to be complete.

Installation of wind columns/screen wall support at stair

#1 to be completed.

Installation of Bar/counter top support steel to be

ongoing.

To: David Ficklin - OnGoal

Rory O’Connor – OnGoal

Lee Turner – OnGoal

Andy Heitmann – Turner

Dave Dudzik - Turner

Brandon Valdez-Turner

From: Nick Durand

Office: Kansas City

Date: 3.9.2011

Re: Sporting Kansas City

Project Update – Week of

3.9.2011

Installation of field drainage and irrigation

lines is ongoing.

Plaza utility work has begun.

Page 2: LIVESTRONG Sporting Park Construction Update (3/9/11)

Building the Future

Roofing and Sheet metal:

Area 1-Alucobond metal panel installation at Suite and

Press level on field side is near complete.

Alucobond metal panel and subgirt installation is

ongoing at Concourse buildings.

Drilling anchors for exterior fins is near complete.

Area 3- Concourse building roofing in the NE is complete.

Gutter shrouds at canopy gutter are ongoing.

Canopy deck flashing installation is ongoing.

Coping cap installation at concourse buildings to be ongoing.

Area 3-Alucobond metal panel installation along East side

of building is ongoing.

Polycarbonate:

Area 1-Polycarbonate installation is ongoing.

Area 2-Polycarbonate installation is ongoing.

Metal Stud Framing/Drywall/Ceilings:

Area 1- Drywall installation is complete.

Area 3-Drywall installation and finishing is near complete.

DAFS installation is ongoing at exterior soffits.

Stud framing for North screenwall/ metal panels is near complete.

Drywall installation in concessions/retail areas is

complete.

FRP installation in Concessions is complete.

Ceiling grid installation is ongoing on all levels.

Glass:

Area 1-installation of aluminum door frames is ongoing.

Installation of storefronts at Main Concourse retail

buildings is ongoing.

Installation of Press level Solar innovation sliders is

ongoing.

Area 1- installation of interior storefronts is ongoing.

Area 3-Curtian wall at Cauldron Club installation to begin.

Stone installation in area H is ongoing.

Cauldron Club topping slab is near complete.

Page 3: LIVESTRONG Sporting Park Construction Update (3/9/11)

Building the Future

MEP:

Ductwork installation is ongoing on the East side field level.

Plumbing rough in is ongoing on the East side field level.

NW transformer is now set and primary cables have been

pulled and is awaiting BPU to be energized.

Installation of permanent lights and speakers in soffits is

ongoing.

Fixtures and devices are being installed in the West

tower and termination of branch circuits is ongoing.

Area 1-installation of toilet fixtures on Suite and Field level

is ongoing.

Broadcast cable pulls from loading dock to the Video

Production room is ongoing.

Tie -in of canopy gutters to downspouts is ongoing.

North scoreboard structure installation is complete and

module Installation to begin.

Ad Panel installation on the South scoreboard is complete.

Initial burn in of the SW sport lights has begun.

Elevators:

F1 elevator installation is near completion.

P2 & P3 elevator installation is ongoing.

P4 & P5 elevator installation is ongoing.

P1 installation to begin.

Painting:

Area 1-Painting at Field level is near complete.

Area 1-Painting in Main Concourse buildings is near

complete.

Area 1-Painting on Press and Suite level is near complete.

Area 1-Painting of the Main Concourse west tower is ongoing.

Sealing of exposed concrete floors is ongoing.

Resinous flooring at field level is near complete.

Resinous flooring is ongoing in the concessions.

Painting of stair structure and walls is ongoing.

Tile/Carpet:

Tile installation at Press level Suites to be ongoing.

Tile installation in club areas at Suite and Press levels is ongoing.

Tile in restrooms at all levels is near complete.

Carpet installation to be ongoing on Suite and Mezzanine levels.

Painting of the Main Concourse Club.

Installation of metal panels on East side.

Page 4: LIVESTRONG Sporting Park Construction Update (3/9/11)

Building the Future

Food Service:

Installation of all counters and kitchen equipment at

Mezz level, Suite level, and Press level to be ongoing.

Cooler installation in concessions and cauldron club is complete.

Exhaust hood installation in cauldron club is ongoing.

Concession stand back counters and MEP equipment

Installation to begin.

Projected Activities occurring next Week:

Concrete Flatwork:

Cauldron Club topping slab installation to be complete.

Plaza site concrete to begin.

Stone/masonry:

Block installation at NW transformer area to be complete.

Block installation at Terrace Bar to be complete.

Stone installation in area H to be ongoing.

Steel:

Installation of stone support steel at Stadium Suite to be

complete.

Installation of dock overhead doors to be complete.

Installation of screen wall support at stair #1 to be complete.

Roofing and Sheet metal:

Canopy gutter shroud installation to be ongoing.

Installation of metal panels at concessions to be ongoing.

Installation of coping cap at concourse roof to be ongoing.

Installation of East side metal panels to be ongoing.

Installation of metal panels at North Main Concourse to

begin.

Metal Stud Framing/drywall soffits:

DAFS installation to be ongoing at exterior soffits.

Ceiling grid installation to be ongoing on all levels.

Drywall installation to be complete at all levels.

Installation of tile at Field Club.

Installation of kitchen equipment at Mezz.

level.

Page 5: LIVESTRONG Sporting Park Construction Update (3/9/11)

Building the Future

Glass:

Area 1-Aluminum door frame installation to be ongoing.

Installation of storefronts at Main Concourse buildings

to be ongoing.

Installation of Solar innovation sliders at back of suites on

Press level to be ongoing.

MEP:

NW transformer to be energized.

Installation of North Scoreboard to be ongoing.

Preliminary hydrostatic testing of the fire sprinkler

lines to begin.

All startup of the RTU’s to begin.

Relocation of North traffic signal fiber to begin.

Paint:

Area 1-Painting of the Suite and Press level areas to

be near complete.

Painting of the Main Concourse buildings to be complete.

Painting at Field level to be ongoing.

Sealing of concrete floors to be ongoing.

Resinous flooring to be complete at all levels.

Playing Field:

Installation of underground drainage and irrigation lines

to be ongoing.

Additional Photos:

Hollow metal door installation is ongoing.

Installation of Ad panels at South scoreboard.

Carpet installation at Suite level Suites.

Page 6: LIVESTRONG Sporting Park Construction Update (3/9/11)

Building the Future

Ceiling grid installation at Main Concourse Club.

Kawneer sliders at Press level Suites.

Toilet partition installation has begun.

Millwork installation at Field Club.