Top Banner
UNFCCC/CCNUCC CDM Executive Board Page 1 PROJECT DESIGN DOCUMENT FORM FOR CDM PROJECT ACTIVITIES (F-CDM-PDD) Version 04.1 PROJECT DESIGN DOCUMENT (PDD) Title of the project activity Lican Hydroelectric Plant Version number of the PDD 01 Completion date of the PDD 16/06/2012 Project participant(s) Empresa Eléctrica Lican S.A. Host Party(ies) Chile Sectoral scope and selected methodology(ies) Sectoral Scope N°1: Energy industries (renewable - / non-renewable sources). - Renewable Energy, Run-of-River Hydropower. Methodology: AM0026 “Baseline Methodology for zero-emissions grid- connected electricity generation from renewable sources in Chile or in countries with merit order based dispatch grid” (version 3), together with the “Tool to calculate the emission factor for an electricity system” (version 2.2.1) and the “Tool for the demonstration and assessment of additionality” (version 6.0.0) Estimated amount of annual average GHG emission reductions 56,427 tCO 2 e per year
63

Lican- PDD

Aug 08, 2018

Download

Documents

Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 1/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 1 

PROJECT DESIGN DOCUMENT FORM

FOR CDM PROJECT ACTIVITIES (F-CDM-PDD)

Version 04.1

PROJECT DESIGN DOCUMENT (PDD)

Title of the project activity Lican Hydroelectric Plant

Version number of the PDD 01

Completion date of the PDD 16/06/2012

Project participant(s) Empresa Eléctrica Lican S.A.

Host Party(ies) Chile

Sectoral scope and selected methodology(ies) Sectoral Scope N°1: Energy industries

(renewable - / non-renewable sources). -

Renewable Energy, Run-of-River Hydropower.

Methodology: AM0026 “Baseline

Methodology for zero-emissions grid-

connected electricity generation from

renewable sources in Chile or in countries

with merit order based dispatch grid”

(version 3), together with the “Tool to

calculate the emission factor for an electricity

system” (version 2.2.1) and the “Tool for the

demonstration and assessment of additionality”(version 6.0.0)

Estimated amount of annual average GHG

emission reductions

56,427 tCO2e per year

Page 2: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 2/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 2 

SECTION A. Description of project activity

A.1. Purpose and general description of project activity

The Lican Hydroelectric Plant, or hereafter the Project, consists of the construction and operation of a

Run-Of-River hydropower plant of 18.18 MW of installed capacity and near 92.101 GWh of average

annual generation, resulting in 57.83% plant factor.

The Lican Hydroelectric Plant will operate with two horizontal Francis Turbines, each one connected

directly to their respective synchronous generators. Both generators will connect to a power transformer 

elevating the voltage from 13.2 KV to 66 kV in the Lican substation. The Project electric generation will

 be supplied to the Central Interconnected Grid (Sistema Interconectado Central in Spanish, hereafter 

SIC) by a single-circuit 66 kV transmission line, connecting the Project to the existing Pilmaiquén

substation at 20.9 km west from the Lican substation. Total Project Investment costs have been estimated

in USD 44.7 million.

The baseline scenario for the Lican Hydroelectric Plant is the continuing operation of the existing and

future power plants, without the Lican Hydroelectric Plant electricity generation, to meet the actual

electricity demand. In the Project scenario the same electricity demand is met with the Lican

Hydroelectric Plant generation displacing the generation from existing power plants and future power 

developments (see further details in section B.4). The aim of the Lican Hydroelectric Plant is to generate

electricity from renewable hydrological resources that will directly reduce greenhouse gas emissions

 produced by fossil fuel based power plants. With its average annual generation, the Project will reduce

near 56,427 tons of CO2e per year.

The Lican project was initially approved by the Environmental Impact Assessment process in 23/12/2004

through the  Resolución Exenta  N° 862, COREMA X Región de los Lagos, and modified through  Resolución Exenta N° 0 dated in 16/01/2006, Resolución Exenta N° 267 dated in 25/04/2006,  Resolución

 Exenta N° 767 dated in 17/11/2006 and Resolución Exenta N° 0051 dated in 14/04/2007.

Lican Hydroelectric Plant was initially developed by Inversiones Candelaria Ltda. Then, the Project and

all its related assets were transferred to Empresa Eléctrica Lican S.A. (ELISA)1, who will be in charge of 

the plant development, construction and operation.

The prupose of the Lican Hydroelectric Plant is to generate electricity contributing to the sustainable

development in Chile through:

  Use of local renewable energy resources (small hydro) to displace fossil fuel based power generation in the SIC.

  Reduction of GHG emissions, specifically CO2e

  Increased commercial activity through clean and renewable source of power.

1ELISA shareholders are: 45% owned by Inversiones Corporativas Lican Ltda. and 55% owned by Iberdrola

Energía Chile Ltda. (IBERENER). Inversiones Corporativas Lican Ltda. belongs to the Fernandez-Goycoolea

family, a group with investments in different areas both in Chile and abroad (salmon farms, forestry, construction,

real estate, agriculture, flower production and exports to Europe and U.S.A.). IBERENER, is a subsidiary of theSpanish multinational power company IBERDROLA S.A. whose purpose is undertaking investments in the Chilean

electricity sector.

Page 3: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 3/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 3 

  Permanent and temporary employment generation in the XIV region where the project is located,

improving economic benefits to the surrounding communities which have a high rate of 

unemployment and poverty.

  Training of local people, in techniques and occupations related to the construction and operation

of a hydroelectric power plant.

A.2. Location of project activity

A.2.1. Host Party(ies)

Chile

A.2.2. Region/State/Province etc.

XIV Region of Los Ríos (formerly X Region of Los Lagos).

A.2.3. City/Town/Community etc.

Ranco Province, Río Bueno Commune.

A.2.4. Physical/Geographical location

Lican Hydroelectric Plant is located in the XIV Región de los Ríos, Chile, at about 65 km east from

Osorno city and 45 km west of the Chilean-Argentinean border.

The Project’s intake is placed in the Lican River, and the Powerhouse facilities are placed in the Lican

Farm.

The water restoration takes place through a tailrace channel, delivering and restoring the waters to their 

 previous course in the Lican River.

The project coordinates are:

 Table A.1: Project Coordinates

(Geographic Coordinate System, WGS84, Zone 19, Southern Hemisphere)

Latitude Longitude Intake 40° 34' 39.5" S 72° 18' 52.092" WPower house 40° 36' 52.7" S 72° 23' 58.2" W

Page 4: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 4/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 4 

Figure A.1: Geographic position

Lican Hydroelectric Plant

Puyehue Lake

Osorno

 

Figure A.2: Satellite view of the project

Pilmaiquén

SubstationProject

Powerhouse

Project

Intake

Lican River

Transmission LIne

Puyehue Lake

 

A.3. Technologies and/or measures

Electric power generation will be accomplished through well-proven technologies. The project considers

the construction of: a water intake in the Lican River with 8 m3/s design flow, a pressure penstock with

238.2 meter head, a daily peak hour reservoir of 102,000 m3, a power house with two sets of horizontal

axis Francis turbines of 8.554 MW each connected to their correspondent power generators of 9.090

MW each, a 13.2 to 66 KV power transformer of 18 MVA capacity and 20.9 km of a single circuit 66 kV

transmission line, which connects the project to the SIC grid through the existing Pilmaiquén substation.

Average annual energy production of the Project is estimated in 92.101 GWh, obtained through a 48

hydrologic statistical average from years 1959 to 2006, resulting in 57.83% plant factor.

The net electricity delivered to the grid will be monitored continuously on by electric meters on site. The

design of the energy monitoring system of the Project is presented detail in section B.7.3

The development of the Project will help to stimulate the development of Non Conventional Renewable

Energy (ERNC) industry in Chile and will contribute to transfer technology and know-how to the country

on small renewable zero-emissions developments.

Page 5: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 5/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 5 

 Table A.2: Project Details Summary

PHYSICAL INFRASTRUCTURE POWER PLANT

  2 horizontal Francis Turbines of 8.554 MW

each

  2 power generator of 9.090 MW each

  Design flow: 8 m3/s

  A daily peak hour reservoir of 102,000 m3

area

  238.2 m head

  1 power transformer of 18/22.5 MVA

(ONAN/ONAF) to 66 KV

  66 KV power substation

  20.9 km, 66 KV transmission line

  57.83% plant factor 

  Capacity: 18.18 MW

  Average Net Generation: 92.101 GWh/year.

  Located 65 km east from Osorno city

  Construction time: 25 months

  Estimated cost: USD 44.7 million

Figure A.3: Project Site Schematic Diagram

3

~

Turbine1

Mechanical Axis

Forebay

AdductionChannel, 8.55km,

And 8m3/s design flow

Intake

LicánRiver

3~

LicánRiver

Generator1

9.09 MW

Generator2

9.09 MWTurbine2

3~

Tailrace

13.2KV

Bus bar

Power

Transformer

13.2/66 kV

18/22.5 MVA 66 KV

Bus bar

Circuit

Braker

Powerhouse Substation

Electricity

tothe

grid

Daily peakhour

Reservoirof 

102,000 m3

     S    p     i      l      l    w    a    y

 

A.4. Parties and project participants

 Table A.3: Project Participants

Party involved

(host) indicates a host Party

Private and/or public

entity(ies) project participants

(as applicable)

Indicate if the Party involved

wishes to be considered as

project participant (Yes/No)

Chile (host) Empresa Eléctrica Lican S.A. No

A.5. Public funding of project activity

 No public funding is involved in the project activity. The fund used to financing is not diversion of 

ODA.

Page 6: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 6/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 6 

SECTION B. Application of selected approved baseline and monitoring methodology

B.1. Reference of methodology

AM0026: “Baseline Methodology for zero-emissions grid-connected electricity generation from

renewable sources in Chile or in countries with merit order based dispatch grid” (version 3), together 

with the “Tool to calculate the emission factor for an electricity system” (version 2.2.1) and the “Tool for 

the demonstration and assessment of additionality” (version 6.0.0)

B.2. Applicability of methodology

The project activity is a grid connected run-of-river hydropower project, connected within the

interconnected grids of the republic of Chile. The proposed methodology AM0026 (version 3) has been

specifically tailored for the Chilean Power sector, where the project meets every condition stated in the

approved methodology.

As stated by AM0026 (version 3), the applicability of this methodology requires the following conditions

to be met:

Condition N°1) Projects that are renewable electricity generation projects of the following types:

  Run-of-river hydro power plants and hydro electric power projects with existing reservoirs where

the volume of the reservoir is not increased;

(a)  New hydro electric power projects with reservoirs having power densities (installed power 

generation capacity divided by the surface area at the full reservoir level) greater than 4

W/m2 

  Wind sources;

(b)  Solar sources;(c)  Geothermal sources;

(d)  Wave and tidal sources.

  Applicability: The proposed Project Activity fulfills letter (a) of the previous

conditions, where it is a new hydro electric power plant having a reservoir power

density of 178.23 W/m2

(18,180,000 W / 102,000 m2), which is greater than 4 W/m

2.

Condition N°2) Projects that are connected to the interconnected grids of the Republic of Chile and

Projects that fulfils all the legal obligations under the Chilean Electricity Regulation; or Proposed

projects implemented in countries other than Chile provided the country has a regulatory

framework for electricity generation and dispatch that meets the following conditions:(a)  An identifiable independent identity is responsible for optimal operation of the system based

on the principle of lowest marginal costs.

(b)  The data for merit order based on marginal costs is publicly made available by the authority

responsible for operation of the system.

(c)  The data on specific fuel consumption for each generation source in the system is publicly

available.

(d)  It is possible with the information available, to ensure that power plants dispatched for other 

considerations (e.g. safety conditions, grid stability, transmission constraints, and other 

electrical reasons) are not identified as marginal plants

  Applicability: The proposed Project Activity is connected to the Central

Interconnected Grid of the Republic of Chile, fulfilling all legal obligations underthe Chilean Electricity Regulations.

Page 7: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 7/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 7 

  Condition N°3) The methodology is not applicable to: 

The proposed CDM project activities that involve switching from fossil fuels to renewable energy

at the site of the project activity, andif the baseline is the continued use of fossil fuels at the site.

  Applicability: The proposed Project Activity does not involve switching from fossil

fuels to renewable energy at the site of the project activity and the baseline is not

the continued use of fossil fuels at the site.

B.3. Project boundary

The methodology only claims emissions reductions from the substitution of power generation due to the

implementation of a CDM activity in one of the grids. Only CO2 derived from the combustion of thethermal plants is accounted. The sources and types of GHG included are listed in the following table.

 Table B.1: GHG Emission Sources

Source GHGs Included? Justification/Explanation

   B  a  s  e   l   i  n  e

  s  c  e  n  a  r   i  o SIC grid

thermal

dispatch

CO2 YesMain emission source due to thermal power plant

dispatch on the grid

CH4 No

 N2O No

   P  r  o   j  e  c   t

  s  c  e  n  a  r   i  o SIC grid

thermal

dispatch

CO2 No

CH4 No

 N2O No

Chile has four different grids and there are no interconnections between them. Therefore, each grid

defines the geographical and system boundaries for proposed projects located within it (see map in

Figure B.1 below). According to the National Energy Commission (Comisión Nacional de Energía or CNE (www.cne.cl), the Northern Interconnected Grid (SING) compromises the regions I to II and

accounts 23%t of the total capacity. The SIC, where the Lican Hydroelectric Plant is immersed,

compromises the regions III to X and accounts 76% of the total capacity. The Aysen and Magallanes

grids are located in the XI and XII regions, respectively, and account about 1% of the nation total

capacity.

The generation mix capacity of the SIC comprises of 45% hydroelectric generation, 17% diesel, 11%

coal, and the remainder from natural gas, wind and cogeneration.

Page 8: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 8/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 8 

Figure B.1: Project Boundary

Chile Electric Grids Sistema Interconectado Central – SIC

Santiago

III

I

II

IV

V

VIVII

X

VIII

IX

XI

XII

SistemaInterconectado del

Norte Grande

SING

Sistema

Interconectado

Central

SIC

Sistema de

Aysén

Sistema de

Magallanes

The electricity generated by the proposed Project will be transmitted to Central Interconnected System

grid (Sistema Interconectado Central or SIC). The spatial scope of the project boundary also covers all

 power plants physically connected to this grid.

At present there are no electricity imports or exports of the SIC grid to other national or international

grids. However, future system expansion may include interconnection to the SING grid or Argentina grid

(SADI).

Figure B.2: Flow Diagram

Project

Activity

CDEC-SICand other

official

Databases

Net hourly Electricity

To the Grid

Project Boundary

ProjectEmission

Reductions

Estimation

M

Other SIC

power plants

Project Site Energy

Measurement Equipment

SIC thermal

power plants

Specific Fuel Consumption

and Net Electricity

To the Grid

Net hourly Electricity

To the Grid

 

Page 9: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 9/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 9 

B.4. Establishment and description of baseline scenario

  Identification of the Baseline Scenario

In a centrally planned system the baseline scenario can be determined on the basis of the least cost

expansion and operation of the electric grid as defined by the planning authority. In Chile there is no

central planning for expansion of power facilities. However, the CNE prepares an indicative expansion

 plan, which is used to calculating system energy and power node prices. This calculation is based on the

most plausible scenario for least cost capacity additions on the grid. However, sector investments come

from private investors who are free to choose the projects they want to develop and base their decisions

regarding investments and operation of plants on their own perception of the market, where the CNE

node price determination is a key factor.

Consequently, the baseline for the purpose of estimating emission reductions prior to their actual

generation, should be determined as the most likely scenario of capacity additions and generation private

investors and plant operators would choose on the basis of demand projections, node and spot prices,investment costs, available technology for capacity expansions and expected price of fuels. Thus, the

 baseline scenario consists of the current power plants in the relevant system grid for the Lican

Hydroelectric Plant boundary (which is the SIC grid) plus the projected capacity expansion and including

the generation pattern in the SIC as it occurs in the absence of the generation of this CDM Project.

  Description of the identified Baseline Scenario

The baseline scenario for the Lican Hydroelectric Plant is the continuing operation of the existing and

future power plants, without the Lican Hydroelectric Plant electricity generation, to meet the actual

electricity demand. In the Project scenario the same electricity demand is met with the Lican

Hydroelectric Plant generation dispatched in the base load displacing the generation from existing power  plants and future power developments. Because the Project uses renewable sources to produce electricity,

there are no additional emissions from the Project Activity and the emissions reductions is a result of the

displaced generation from the SIC grid.

B.5. Demonstration of additionality

  How the anthropogenic GHG emissions are to be reduced

The Project Activity is a grid connected run-of-river hydropower project. It does not involve switching

from fossil fuels and the grid’s geography and system boundaries are explicit and characteristics are

readily available through CNE and CDEC-SIC information systems.

The Project Activity will reduce emissions by displacing electric energy generated from fuel-based

 power plants. The electric energy generated by the Project is produced using renewable energy with zero

emission to the atmosphere associated with its operation.

  Key steps of the Project development and CDM prior consideration

CDM has been considered at an early stage of the project feasibility analysis. The feasibility report of the

 project showed that carbon credits sales are a relevant part of the project finance and essential to the

 project implementation. The following schedule shows some of the relevant milestones of the project

development:

Page 10: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 10/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 10 

o  June 2004: Inversiones Candelaria Ltda. submits the project for environmental qualification

 process.

o  23/12/2004: Inversiones Candelaria Ltda. obtains the environmental approval of Lican Project,

through  Resolución Exenta N° 862, Comisión Regional del Medio Ambiente - X Región de los Lagos.

o  From 10/08/2005 to 14/04/2007: Inversiones Candelaria Ltda. obtains environmental approval

for various changes of the original project design, through:  Resolución Exenta N° 0 dated on

16/01/2006,  Resolución Exenta N° 267 dated in 25/04/2006, Resolución Exenta N° 767 dated in

17/11/2006 and Resolución Exenta N° 0051 dated in 14/04/2007 .

o  27/04/2006: Inversiones Candelaria Ltda. obtains the Letter of Approval from the Chilean DNA

(CONAMA) through letter D.E. N°061196.

o  29/10/2007: Signature of the agreement between Inversiones Candelaria Ltda. and IBERENER 

S.A. where Inversiones Candelaria Ltda. committed to transfer all permits, studies, engineering

and lands related to the Lican Hydroelectric Plant project to Empresa Eléctrica Lican S.A.

(ELISA)o  May 2008: ELISA invites various DOEs to execute the Validation of the Lican Hydroelectric

Plant. After some delays in the process, the CDM validation was finally awarded to Bureau

Veritas on 28/11/2008.

o  13/10/2008. ELISA instructs ICAFAL to proceed with the main construction contract for the

 project civil works.

o  30/10/2008: ELISA signs the main electromechanical equipment contract with Andritz Hydro

s.r.l Unipersonale / Indar S.A.

o  16/02/2010: The Chilean DNA confirms the Letter of Approval of the Lican Hydroelectric Plant,

authorizing the change of ownership of the project from Inversiones Candelaria Ltda. to Empresa

Eléctrica Lican S.A. through letter D.E. N°100552 dated on 16/02/2010.

o  14/03/2011: After several delays from the DOE (Bureau Veritas) to perform the project

validation, ELISA resolves to terminate the validation agreement with BV and requests BV tounpublish the Project from UNFCCC website.

o  June 2011: Lican Hydroelectric Project is commissioned and starts generating electricity to the

SIC grid

o  April 2012: ELISA instructs DNV to proceed with the Project validation.

Following the above key steps. the project start date to be considered for the Lican Hydroelectric Plant

 project is 13/10/2008, being this date the date when the purchase order of the main civil works were

engaged with ICAFAL.

  Additionality Assessment

The following steps are used to demonstrate Lican Hydroelectric Plant additionality. These steps are

 based on the latest “Tool for the demonstration and assessment of additionality” (version 6.0.0).

Step 1) Identification of alternatives to the project activity, based on the Chilean national authority

indicative expansion plan; this step shows that Lican Hydroelectric Plant is not the only alternative for 

the expansion of the system and nor the least cost alternative, which are combined cycle natural gas or 

diesel fired power plants, coal and hydro dams (non run-of-river). Step 2) Investment Analysis is

developed. This analysis is done through a Benchmark Analysis (Option III), showing that the Project is

not financially attractive. Step 3) Barrier Analysis has been omitted from the analysis. Finally, Step 4)

With a common practice analysis, other projects similar to Lican Hydroelectric Plant were searched for,

showing that there are no similar activities observed in the SIC, with the exception of those projects that

have been submitted under, or are seeking, carbon finance under the CDM.

Page 11: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 11/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 11 

  Step 1. Identification of alternatives to the project activity consistent with current laws andregulation.

The CNE establishes for every node price report the optimal expansion plan of the SIC, and uses it tocalculate the regulated prices (Node Prices). The expansion plan consists of successive iterations of 

comparing different options of the system expansion that minimizes the net present cost of the energy

supply, which includes the sum of the net present value of investments, operation and maintenance,

and shortage cost for a period of ten years (see the Formula below). Therefore, the model picks the

technologies and projects that minimize the objective formula, assuring the minimum economic cost

for the expansion and operation of the system. The investor uses the expansion plan as reference to

take the investment decision, so the construction plan is a clear view of the investment conditions of 

the system.

lue ResidualVaostsVariablesC  MantCostsOp Investment  Min &  

Following the previous rationale, the alternatives to the proposed Project activity are:

a. The proposed Project Activity implemented, not undertaken as a CDM project

As it is supported later in this section, this alternative is not realistic for the project developer,

since it is not economically attractive without CDM revenues.

 b. Continuation of the current baseline for Chile, being this the implementation of fossil fuel power 

 plants

The projected tendency in Chile is generally towards the continuation of large scalenonrenewable sources, as described in the step 4) common practice analysis.

  Step 2. Investment analysis (Sub-step 2b Option II I . Benchmark analysis)

The Investment Analysis shall demonstrate that the Project Activity is economically or financially

less attractive than other alternatives without additional revenues from the sale of emission

reductions.

Sub-step 2a) Determine the appropriate analysis method 

Since the proposed project will earn revenues from not only ER sales but also electricity sales, the

simple cost analysis method is not appropriate. Instead, Benchmark analysis (Option III) will be

applied.

Sub-step 2b) Option III. Apply Benchmark Analysis

The financial indicator for this analysis is the IRR, which is the most commonly used parameter to

determine the investment decisions. According to the Chilean electric law (DFL 4/2006), the official

rate of return for electric projects is 10%, used to determine Node Prices, transmission line and

distribution investments. Based on this benchmark, calculation and comparison of financial indicator 

are carried out in sub-step 2c.

Page 12: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 12/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 12 

It should be noted that the IRR Benchmark is a conservative rate, applicable to the Chilean power 

sector where most of the projects investments come from large companies that benefit from scale

economies.

Sub-step 2c) Calculation and comparison of financial indicator.

Calculation and comparison of the financial indicator of the Project is implemented according to the

Guidance on Assessment of Investment Analysis (version 5). According to the feasibility study of the

Project, the parameters needed for calculation of key indicators are the following:

 Table B.2: Lican Hydroelectric Plant Valuation Parameters

Firm capacity 7.2 MW

Energy production (1) 92.101 GWh / year 

Contract and Spot sales 50% at Node Price and 50% at Spot

Total Investment USD 44.7 million

Operation Life 30 years

Income Tax 17%

Debt rate 5.24%

Avg. Node Energy Price (2) 68.13 USD/MWh

Avg. Spot Energy Price (2) 71.06 USD/MWh

Capacity Price 87.73 USD/KW-year 

Emission Factor 650 tCO2e/GWh

CERs Price 18 USD/CER 

O&M costs USD 0.675 million / year 

Transmission toll USD 1.200 million / year 

Administrative costs USD 0.582 million / year 

Source: Eléctrica Lican S.A. according to the Lican Hydroelectric Plant Feasibility Study

(1) Based on 48 years statistical average (1959 to 2006), resulting in 57.83% plant factor (2) Average over 30 years of plant operation. As shown in the feasibility study and confirmed in

the CNE Node Price Report, system prices tend to decrease in the mid and long term, because

of the construction of new coal, natural gas and hydro power plants, thus reducing the more

expensive operation of oil power in the SIC.

In accordance with the Benchmark Analysis, if the financial indicators of the Project, such as the

Project IRR, are lower than the benchmark, the Project is not considered to be financially attractive.

 Table B.3: Financial Indicator Comparison

IRR Over Assets NPV in USD x 1000(10% discount rate)

Project with ER Income 10.33% 1,132

Project without ER Income 8.33% -5,647

Table B.3 shows the Project IRR of the Project with and without the sales of emission reductions

(ERs). Without the sales of ERs the Project IRR is 8.33 percent, which is lower than the financial

 benchmark. Thus the Project is not considered to be financially attractive.

However, taking into account the additional revenues from ERs sales, the project IRR is increased to

10.33 percent, which is slightly higher than the financial benchmark. Therefore the CDM revenues

enable the project to overcome the investment barrier and the additionality of the Project is

demonstrated.

Page 13: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 13/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 13 

Sub-step 2d) Sensitivity analysis

The sensitivity analysis shall show whether the conclusion regarding the financial attractiveness is

robust to reasonable variations in the critical assumptions. For the Project, four parameters whereselected as sensitive factors to check out the financial attractiveness, plus a fifth parameter to see the

ER sales impact on the Lican Hydroelectric Plant: 1) Total investment cost. 2) Hydrological impact

during the first two years of operation. 3) Energy Node Prices during the first two years of operation.

4) O&M Costs. and 5) ER Sales

The results of sensitive analysis are shown in Table B.4 and Figure B.3 below.

 Table B.4: Sensitivity Analysis

Sensitive variable LOW HIGHTo

Benchmark 

Investment costs +10%  – 10%  – 13.3%

IRR over assets 7.29% 9.55% 10.0%

Hydrology variations Humid Dry (see comment)

IRR over assets 7.31% 8.28% -

Energy Node price  – 10% +10% +23.9%

IRR over assets  7.60% 9.03% 10.0%

O&M Costs +10%   – 10%   – 100%

IRR over assets  8.17% 8.48% 9.84%

Figure B.3: IRR Over Assets Sensitivity Analysis

7,29%

7,31%

7,60%

8,17%

8,33%

9,55%

8,28%

9,03%

8,48%

10,33%

6% 7% 8% 9% 10% 11% 12%

Investment costs +10% / -10%

Hydrology Humid/Dry

Node price -10% / +10%

O&M Costs +10% / -10%

ER sales (up to 3x7 years)

IRR Over Assets Sensitivity

 

The IRR of the Project varies in different degrees in accordance with the fluctuation of the selected 4

 parameters within the range of +7.29% to +9.55% if ER sales are not considered.

  Analysis over Node Price Variations:

Energy Node Prices sensitivity for the first five years of operation shows that an increase by 10 percent results in an increase of the Project IRR by 9.03%, still positioning the Project IRR under 

Page 14: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 14/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 14 

the financial Benchmark. To stay over the Benchmark it would be required an increase over the

energy node prices of 23.9%. Below this level, the Project IRR would remain under the

 benchmark. It should be noted that Node Prices reflect a long term average of the system

operation, considering most plausible capacity additions, available technologies and fuel prices.Taking into account that diesel fuel plants are gradually been replaced by lower cost plants such

as coal, liquefied natural gas plants and hydroelectric plants, it is unlikely to expect un increase

on long term system prices.

  Analysis over Hydrology Variations:

Hydrology variations do have impact in the IRR, however the effects are mostly negative and

keeps the IRR below the Benchmark. Since it is unlikely that a hydropower project would face an

extreme hydrological scenario for many years, the sensitivity analysis for hydrology variations

only considers the first three years of operation facing a Dry or Humid condition. These first

three years have the largest impact in the project Net Present Value and IRR, and show a realisticscenario over hydrology variations impacts. For the remaining years of this analysis, the project

is expected to produce an average generation output (92.101 GWh/year). The Humid condition

 produces 108.7 GWh of energy generation and a Dry condition produces 69.9 GWh of energy

generation (See Figure B.4 below). It is important to note that hydrological scenarios not only

affect the project generation output but it is also inversely correlated with system spot prices,

where low spot prices appear in Humid conditions (near 31 USD/MWh, based on system variable

costs where low-cost coal technology results in the relevant dispatching unit) and high spot

 prices appear in Dry conditions (near 132 USD/MWh, based on system variable costs, where

closed cycle diesel power units are dispatched to cover the system demand). As it is shown in the

Table B.4 above, the Humid condition presents a more negative result compared to the average

case. The Dry scenario, does not present a significant variation, where the lower generation is

compensated by higher spot prices revenues. Still, both conditions, Dry and Humid, remain under 

the Benchmark of 10% IRR.

Figure B.4 : Lican Hydroelectric Plant Monthly Projected Generation

0

2

4

6

8

10

12

14

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    G    W

    h

Average (92.1 GWh)Dry (69.9 GWh)Humid (108.7 GWh)

 Source: ELISA. estimate based on hydrological data for 48 years (1959 to 2006).

Since the Benchmark cannot be reached on any of the extreme conditions, a simplified example

can show the unlikelihood of reaching the Benchmark: For the Dry scenario, it would be required

a price increase of 215% of the system spot prices (224 USD/MWh as average for the first three

Page 15: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 15/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 15 

years of operation in dry conditions). In the Humid scenario, it would be required an increase of 

near 79% in the average system spot prices to reach the 10% IRR Benchmark (127.4 USD/MWh

as average price for the first three years of operation in humid conditions). In each case, such

increase in the system prices are not likely to occur considering the CNE Node Price reportApril-2007, which estimates a relatively stable result for the projected spot prices for the next 10

years of the system operation, with an average of near 71.06 USD/MWh.

  Analysis over O&M Costs Variations:

Compared with the total investment, the annual O&M costs have a relative small impact on the

IRR and can be regarded as an insensitive factor. Even completely neglecting these costs, the

 project IRR results in 9.84%, which is still below the Benchmark.

  Analysis over Investment Costs Variations:

The investment costs have a relevant impact in the IRR. If the investment costs are increased by

10%, this results in a decrease of the project IRR by 7.29%. In the opposite scenario, if the

investment costs are decreased by 10%, results in an increase of the project IRR by 9.55%, but in

 both cases, the IRR remains under the Benchmark of 10% IRR.

It’s highly unlikely that the investment costs can decrease more than 10%. The development of 

the engineering of Lican Hydroelectric Plant is in the final stage, where all the basic engineering,

electromechanical equipment is already defined and the contracts are already closed, thus the

 budget could not suffer great variations, except for possible contingencies as problems with soil

mechanics or other unexpected difficulties that would only increase the investment costs instead

of decreasing them.

Through the previous sensitivity analysis, it is clearly shown the relevance of the ER sales in the success

of the Project. The additional revenues change substantially the IRR of the project, positioning the

Project IRR over the Benchmark, thus evidencing the impact of these revenues on the investment

decision, as shown in Table B.3 and Figure B.3.

  Step 3. Barrier Analysis

This section has been omitted as per the latest “Tool for the demonstration and assessment of 

additionality” version 6.0.0., step 1.

  Step 4. Common practice analysis.

o  Sub-step 4a Analyze other activities similar to the proposed activity:

Even with the actual Node Price scenario, where monomic price levels are over 80

USD/MWh, thermal generation alternatives are still the minimum cost option for capacity

additions, as indicated by CNE in its node Price and construction plan published in April

2007 (see Table B.6).

Page 16: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 16/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 16 

By the other hand, analyzing other activities that are currently in operation in the SIC and

that are similar to the Project, it is shown that all of them have considered the support of 

CDM incomes.

For this analysis, it has been considered all the operational run-of-river projects in the SIC,

in the capacity range similar to Lican Hydroelectric Plant, which have an installed capacity

 between 9 to 28 MW commissioned since 19972

in the SIC grid. The projects that meet the

 previously restrictions are shown in Table B.5.

 Table B.5: Similar Run of River Project in the SIC Operating since 1997

ProjectStarting

Date

Installed

Capacity

[MW]

Owner & Developer CDM Status

Puntilla 1997 22 Electrica Puntilla S.A. Not CDM

Lircay 2009 19 Hidromaule S.A.Registered Project id

2417

Ojos de Agua 2008 9 Endesa Eco S.A.Registered Project id

0937

Guayacán 2011 12 Energía Coyanco S.A.Registered Project id

3830

Coya 2008 10.8 Pacific Hydro Chile S.A. Not CDM

Florida1909-

199927 Pacific Hydro Chile S.A. Not CDM

Chiburgo 2007 19 Colbún S.A. Not CDM

Source: CNEs Energy Electricity Statistics

CDM Registered projects listed in the table above can be found in the CDM databases. The

following exception are:

  Puntilla hydroelectric project corresponds to a previously existing project developed

 between 1926 (unit N°1 4.5 MW) and 1942 (unit N°2 9.5 MW), originally owned by

Compañía Manufacturera de Papeles y Cartones S.A. (CMPC), an important paper 

manufacturing company in Chile. In 1997, after a bidding process, CMPC transfers

its generating assets to Eléctrica Puntilla S.A. In 2006 Electric Puntilla S.A.

implements Unit N°3 after a energy efficiency improvement, resulting in total

capacity installed of 22 MW. Since this capacity addition of Unit N°3 did not

require other important civil works, it is not comparable to Lican Hydroelectric

Plant project.

  Coya 10.8 MW project corresponds to the implementation of unit N°5 of the

 previously existing Coya project, that was commissioned in 1911. Unit N°5 was

commissioned in 2008 after an efficiency improvement of the plant. Since this

capacity addition of Unit N°5 did not require other important civil works, it is not

comparable to Lican Hydroelectric Plant.

2During this time frame, the Chilean electric sector experienced dramatic changes due to natural gas fuel shortages.

Since 1996 and until 2004 the Chilean sector development was highly influenced by the very low prices of naturalgas delivered from Argentina. Combined cycle natural gas plants where the evident least cost expansion alternative,

with an important impact on average system energy costs that were bellow 40 USD/MWh.

Page 17: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 17/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 17 

  Florida power plant has been in operation since 1909. The latest capacity results

from the installation of 2.2 MW in 1999 and 1.8 MW in 2003.

  Chiburgo 19 MW project utilizes the existing discharge system of Colbun 478 MW

reservoir power plant that originally delivered irrigation waters to Canal Maule Sur 

through a dissipation valve. Colbun is the second largest electric player in the

Chilean market, with near 2,400 MW of installed capacity. Chiburgo project

replaced the existing dissipation valve with hydroelectric turbines, requiring limited

additional civil works and benefiting from the existing Colbun’s substation and

 power line for grid interconnection. Thus Chiburgo faces very different conditions

and could not be considered as common practice in the system due to its particular 

characteristics.

o  Sub-step 4b. Discuss similar options that are occurring:

The effective CNE Node Price Report at the time the project was considered as an

investment option is April 2007 report, and thus, the one that affected the investment

decision. The following Table B.6 shows the Construction plan from that report

(www.cne.cl).

 Table B.6: CNE Construction Plan for the SIC

Month Year Project NameCapacity

in MW

October 2007 San Isidro II Open Cycle Diesel 240

April 2007 Quilleco Hydroelectric Plant 70

June 2007 Chiburgo Hydroelectric Plant 19.4

September 2007 Canela Wind Farm 18.15

August 2007 Hornitos Hydroelectric Plant 55

October 2007 Palmucho Hydroelectric Plant 32

March 2008 San Isidro II Combined Cycle Diesel 358

April 2008 Ojos de Agua Hydroelectric Plant 9

October 2008 La Higuera Hydroelectric Plant 155

March 2009 San Isidro II Combined Cycle LNG 358

April 2009 San Isidro II Combined Cycle LNG additional fire 377

October 2009 Guacolda III coal power plant 135

January 2010 Nueva Ventanas coal power plant 242

Source: Node Price Report April 2007 www.cne.cl 

As shown above, the least cost alternative for the construction plan of the SIC are thermal

 power plants (Coal, Diesel and Natural Gas). The rest of the projects in the construction plan

are renewable energy CDM projects in development, additional to the baseline. The CDM

status of these projects is shown in Table B.7 below:

Page 18: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 18/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 18 

 Table B.7: Projects Considered Additional Undergoing CDM Registration Process

Project Name

Capacity (MW)

as in CNENode Price

Report

Technology CDM status

Hornitos

Hydroelectric Plant55 Run-Of-River 

CDM Project id 1374,

Registration date:

09/07/2008

Quilleco

Hydroelectric Plant70 Run-Of-River 

CDM Project id 1265,

Registration date:

09/07/2008

Chiburgo

Hydroelectric Plant19.4 Run-Of-River Not CDM

Palmucho

Hydroelectric Plant 32 Run-Of-River Not CDM

Canela Wind Farm 18.15 Wind

CDM Project id 1958,

Registration date:

03/04/2009

La Higuera

Hydroelectric Plant155 Run-Of-River 

CDM Project id 0248,

Registration date:

20/03/2006

Ojos de Agua

Hydroelectric Plant9 Run-Of-River 

CDM Project id 0937,

Registration date:

19/04/2007

Source: http://cdm.unfccc.int/Projects/projsearch.html 

Following the above evidence, there are no similar activities observed in the SIC being carried

at the Project start date, with the exception of those projects that have been submitted under, or 

are seeking, carbon finance under the CDM, thus they are considered additional to the baseline,

with the exception of Palmucho Hydroelectric Project.

Palmucho project faces particular characteristics since it has been conceived to utilize the

ecological water flow discharge from the existing Ralco 570 MW reservoir power plant,

requiring limited additional civil works and benefiting from the existing Ralco’s substation and

 power line for grid interconnection. Also, Palmucho is being developed by the largest electric

 player in the Chilean market  –  ENDESA - who owns and operates near 4,300 MW of 

hydrothermal installed capacity in the Central Interconnected System. Thus Palmucho faces

very different conditions and could not be considered as common practice in the system due to

its particular characteristics.

Most comparable development occurring in the SIC at the project start date is the case of Lircay

19 MW Run-Of-River project, developed by Hidromaule S.A. This project considers an

investment of USD 29.5 million according to information provided by the project developer in

the approved PDD (cdm.unfccc.int). Despite it has a lower unitary investment cost than Lican

Hydroelectric Plant, this project has demonstrated its additionality obtaining additional finance

for its development.

Since all above steps are satisfied, the additionality of the proposed CDM Project Activity is fulfilled,according to the “Tool for the demonstration and assessment of additionality” (version 6.0.0).

Page 19: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 19/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 19 

B.6. Emission reductions

B.6.1. Explanation of methodological choices

Project emission reductions are calculated as a Combined Margin emission factor (CM), consisting of the

weighted average of an Operating Margin (OM) and a Build Margin (BM), following AM0026 (version

3) approved methodology.

The OM emission factor from the project activity will depend on the actual generation data from the SIC.

The dispatch data, to be provided ex-post by the Economic Dispatch Center (CDEC-SIC), will

conclusively indicate the type of generation displaced by the addition of Lican Hydroelectric Plant in the

generation mix in the SIC. The monitoring and verification plan for the Project utilizes the data provided

 by CDEC-SIC and other official data.

The BM emission factor will be determined as option (i) in AM0026 (version 3), i.e., following the BM

emission factor estimation process described in the: “Tool to calculate the emission factor for an

electricity system” (version 2.2.1), which is calculated on an ex-post basis as the generation-weighted

average emission factor (tCO2/MWh) of all the power units during the most recent year for which power 

generation data is available.

B.6.2. Data and parameters fixed ex ante

Data / Parameter wBM 

Unit %

Description Weight for Build Margin emission factor Source of data Proposed value

Value(s) applied 50%

Choice of data

or

Measurement methods

and procedures

Default recommended value

Purpose of data Calculation of baseline emissions

Additional comment

Data / Parameter wOM Unit %

Description Weight for Operating Margin emission factor 

Source of data Proposed value

Value(s) applied 50%

Choice of data

or

Measurement methods

and procedures

Default recommended value

Purpose of data Calculation of baseline emissions

Additional comment

Page 20: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 20/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 20 

B.6.3. Ex ante calculation of emission reductions

AM0026 (version 3) calculates ex-post the emission factor for the Operating Margin by observing actual

dispatch data, the generation from the power plants and the merit order. The OM emission factor isdetermined by the generation that would be dispatched in the absence of this CDM Project.

Step 1) The Emission Factor of the Operating Margin  – OM

EF

1

,

1

,,

yOM,

 H 

h

h j

 H 

h

h jh j

Generation

n xGeneratio EF 

:AM0026 (version 3) formula (8) 

Where,

 EF  j,h .................Operating margin Emission factor for proposed CDM project ‘ j’ for hour ‘h’, expressed

in tCO2/MWh

Generation j,h ....Generation of  proposed CDM project ‘ j’ during hour ‘h’, expressed in MWh 

h .......................Total number of hours of the year ‘y’ 

Sample calculation (year 2010, see Appendix 4:) 

EFOM,y=2010 = 55,182.5 tCO2e / 92,101 MWh = 599.33 tCO2e/GWh

The emission factor for the proposed CDM project ‘ j’, in a system with ‘N’ CDM projects, for a hour ‘h’is based on identification of the marginal plant(s) that would be operated to meet the electricity supplied

 by the proposed CDM project ‘ j’. The identification of marginal plant(s) displaced by proposed CDM

 project ‘ j’ is based on the “first- built first served” principle. “Date of built” is defined as the date when

the plant begins the dispatch of energy to the grid.

The emission factor for any hour ‘h’  for a CDM project ‘ j’ in system is estimated as the weighted

average of emission factor of the identified marginal plant(s) that would have supplied electricity to the

grid in absence of the ‘ jth’ CDM plant. The emission factor is estimated as follows: 

),(/*),(EF

1

h j, i j Dd i j D M 

i

i : AM0026 (version 3) formula (9)

Where,

 D(j,i) ...........Energy displacement of the marginal plant ‘i’ due to the proposed CDM project ‘ j’,expressed in MWh

d i .................Emission factor of the marginal plant ‘i’, expressed in tCO2/MWh.

 M ................M is the total number of marginal plants that would be dispatched if the system is operated

without the N CDM projects.

Sample calculation (year 2010):

EF j=1,h=8754 = 6.98 MWh * 750.4 tCO2e/GWh / 6.98 MWh = 750.4 tCO2e/GWh

Page 21: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 21/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 21 

Energy displacement of the marginal plant ‘i’  due to the proposed CDM project ‘ j’, is calculated as

follows:

 N 

 jk 

ii

i

 j ik  D B Al  j DC  MIN i j D1

1

1

),(;),(),( : AM0026 (version 3) formula (11) 

Where,

 Ai ..............Maximum energy generation of the marginal plant ‘i’ expressed in MWh/h (equivalent to

 plant capacity in MW)

 Bi .............. Actual Energy generation of the CDM marginal plant ‘i’ expressed in MWh/h 

Cj ............... Energy generation of the CDM project ‘  j’ expressed in MWh/h

 N  .............. Total number of CDM projects in the system M  ............... Total number of additional marginal plants that should be dispatched if the system is

operated without the N CDM projects

Where:

D( j,0) = 0 and D( N+1 , i) = 0

D( j,i) = 0 for all i<m , s.t. 

 N 

 jk 

m

i

ii C  B A11

 

D( j,i) = 0 for all i>m , s.t.  j

 N 

 jk 

m

i

ii C C  B A 1

*

1

 

Sample calculation (year 2010, h=8754, applicable for the displacement of energy over Quellon 2 diesel

 power plant) (values in MWh):

D(j=1,i=1) = Min { 6.98 – 0; (10 – 0.7) – 0) } = Min { 6.98 ; 9.30 } = 6.98 MWh

di , the emission factor for displaced marginal plant, is estimated as follows:

Oxid*CEF*SFCd iiOM,i i : AM0026 (version 3) formula (12) 

Where,

SFC i  ........... Is the specific fuel consumption of  ithmarginal power plant, expressed as (ton of fuel or 

TJ/MWh.

CEF OM,i, ..... is the CO2 emission factor of fuel used in ithmarginal power plant, expressed as tCO2/ (ton

of fuel or TJ)

Oxid i  .......... is fraction of carbon in fuel, used in ith marginal plant, oxidized during combustion.

Sample calculation (year 2010, h=8754, applicable for Quellon 2 diesel power plant):

di=1 = 0.2219 Kg-fuel/MWh x (10,900 Kcal/Kg-fuel x 7,400 KgCO2e/TJ x 4,1868 x 10-9 TJ/Kcal) x 1

di=1 = 0.2219 Kg-fuel/MWh x 3.3816 tCO2e/Kg-fuel x 1di=1  = 750.4 tCO2e/GWh

Page 22: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 22/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 22 

The marginal plant(s) are those power plants listed in the top of the grid system dispatch order during

hour ‘h’ needed to meet the electricity demand at the hour ‘ h’ without the generation of CDM project(s).

If no thermal power plants are needed to meet the demand without the CDM projects, then the emission

factor of the marginal plant is zero.

The generation of Lican Hydroelectric Plant is obtained from the metering system which follows a

national standard NCh 2542, which states 0.2% error allowance on a KWh base. Hourly energy data

obtained from the metering system is submitted to CDEC-SIC every two hours as for all other generating

units of the system. Periodic calibration (every two years) will be conducted through independent

certified entities.

The Semi-annual Node Price Report, CDEC-SIC databases and the IPCC Good Practice Guidance

 provide all the information to calculate the emission factors for all the power plants within the Chilean

grids, including future plants projected in the expansion plan. Node Price Reports inform about the

specific fuel consumption for every thermal power plant, which are used together with the carbon contentof the different fuels as reported by the IPCC.

Step 2. Calculation of the Build Margin – BM

As described in AM0026 (version 3), Option i), the emission factor for the Build Margin for the first

crediting period can be calculated annually ex-post , following Option 2 for Build Margin Calculation as

indicated in the “Tool to calculate the emission factor for an electricity system” (version 2.2.1).

According the chosen option above, the build margin emission factor for the first crediting period can be

calculated annually, based on the set of power units that comprises the larger annual generation of the

following two options:

  the most recent 20% of capacity added to the grid in, ex-post ; or 

  The set of five power units that have been built most recently

Taking in consideration the options above, the build margin is calculated as follows:

m

i

 ym

m

 ym EL ym

 y BM  grid 

 EG

 EF  EG

 EF 

1

,

1

,,,

,, : actually am-tool-07 (version 2.2.1) formula (12) 

Where,

 EF  grid,BM ,y .... Build margin CO2 emission factor in year y (tCO2/MWh)

m................. Power units included in the build margin

 EF  EL, m ,y ...... CO2 emission factor of power unit min year y(tCO2/MWh)

 EGm,y ........... Net quantity of electricity generated and delivered to the grid by power for the min year y 

(MWh.)

 y ..................Most recent historical year for which power generation data is available

Sample calculation (year 2010, see Appendix 4:):

EFgrid,BM ,y=2010 = 5,433,966 tCO2e / 9,480.3MWh = 573.18 tCO2e/GWh

Page 23: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 23/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 23 

 ym

 yiCO yi

i

 ymi

 ym EL EG

 EF  NCV  FC 

 EF ,

,,2,,,

,,

** : actually am-tool-07 (version 2.2.1) formula (2) 

Where,

 EF  EL,m,y, .......CO2 emission factor of power unit m in year y (tCO2/MWh) 

 FC i,m,y.......... Amount of fossil fuel type i consumed by power unit min year y(Mass or volume unit).

 NCV i,y ......... Net calorific value (energy content) of fossil fuel type i in year y (GJ/mass or volume unit).

 EF CO2,i,y ....... CO2 emission factor of fossil fuel type i in year y(tCO2/GJ)

 EGm,y ........... Net quantity of electricity generated and delivered to the grid by power unit min year  y 

(MWh)

m................. Power units included in the build margin

i................... All fossil fuel types combusted in power unit min year y 

 y .................. Most recent historical year for which power generation data is available

Note: Since FCi,m,yis not directly available through CDEC-SIC data and only one fuel type is used per 

 power plant in the system, then the above formula can be been computed with following equivalent

formula:

 ymCO ym ym

 ym

 yiCO yi

i

 ymi

 ym EL EF  NCV SFC  EG

 EF  NCV  FC 

 EF  ,,2,,

,

,,2,,,

,, **

**

 

:replacement of am-tool-07 formula (2) 

Where,

SFC m,y…….. Is the specific fuel consumption of the power unit min the year yexpressed as ton of fuel or 

TJ/MWh.

 NCV m,y……. Net calorific value (energy content) of fossil fuel used by power plant min year y(GJ/mass

or volume unit).

 EF CO2,m,y….. CO2 emission factor of fossil fuel used by power plant min year y(tCO2/GJ)

Sample calculation (year 2010, applicable for Candelaria 1 GNL power plant):

EFEL,m=1,y=2010 = 0.314 dam3-fuel/MWh x (9,341 Kcal/m

3-fuel x 4.1868 TJ/Kcal) x 54,300 KgCO2/TJ

EFEL,m=1,y=2010  = 666.81 tCO2e/GWh

When no data is available for calculating EFEL,m,y a conservative value shall be applied considering either 

a null EF EL,m,yor Option A2 of the “Tool to calculate the emission factor for an electricity system”, which

establishes the following formula to estimate the plant emission factor:

 ym

 ymCO

 ym

 yimCO

 ym EL

 EF  EF  EF 

,

,,2

,

,,,2

,,

6.3*6.3*

   : actually am-tool-07 (version 2.2.1) formula (3)

Where,

 EF CO2,m,y….. Average CO2

emission factor of used in power unit min year y(tCO2/GJ)

m…………. Power units included in the build margin

Page 24: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 24/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 24 

 ym,  ………Average net energy conversion efficiency of power unit min year y(ratio)

i ………….. All fossil fuel types combusted in power unit min year y

 y …………. Most recent historical year for which power generation data is available

Sample calculation (year 2010, applicable for Curauma 2 MW diesel power plant):

EFEL,m=124,y=2010 = 72,600 x 3.6 / 39.5% = 661.67 tCO2e/GWh

For the second crediting period, the Build Margin emission factor ( EF  grid, BM,y ) shall be updated based on

the most recent information available on units already built at the time of submission of the request for 

renewal of the crediting period. For the third crediting period to be submitted, the Build Margin emission

factor calculated for the second crediting period shall be used.

Step 3. Project Emission Reductions

According to AM0026 (version 3), the combined emission factor for the proposed Project Activity, is

calculated with the weighted average for both the Operating Margin (OM) and the Build Margin (BM) as

follows:

EF*EF*EF yBM,grid,,y BM  yOM OM  ww : AM0026 (version 3) formula (7) 

Where,

 EF OM,y ......... Emission factor for operating margin power generation sources, in tCO2/MWh

wOM =0.5 ..... Weight for operating margin emission factor.

 EF  grid,BM,y ..... Emission factor for build margin power generation sources, in tCO2/MWh

w BM =0.5...... Weight for build margin emission factor.

Sample calculation (year 2010, see Appendix 4:):

EF y=2010 = 599.33 tCO2e/GWh x 0.5 573.18 tCO2e/GWh x 0.5 = 586.25 tCO2e/GWh

The baseline emissions for the Project are calculated as follows:

Generation*EFBE yyy : AM0026 (version 3) formula (6) 

Where,

 EF  y...................Baseline emission factor, in tCO2/MWh

Generation y ..... Electricity generated by the proposed CDM Project in year y(in MWh).

Sample calculation (year 2010, see Appendix 4:):

BEy=2010 = 92,101 MWh x 586.25 tCO2e/GWh = 53,995 tCO2e

Finally, the Project mainly reduces CO2 emissions through substitution of power generation supplied by

the existing generation sources connected to the grid and likely future additions to the grid. The emissionreduction (ERy) by the project activity during year y is equal to the Baseline Emissions. Since the Lican

Page 25: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 25/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 25 

Hydroelectric Plant consists of a hydro power plant, there are no Project Emissions (PEy). Additionally,

as per AM0026 (version 3), no leakage has been identified for this project activity. The emission

reduction can be expressed as follows:

 y y y y y BE  L PE  BE  ER : AM0026 (version 3) formula (2) 

Sample calculation (year 2010, see Appendix 4:):

ERy=2010 = 53,995 tCO2e – 0 – 0 = 53,995 tCO2e

The Baseline emission calculation requires an overwhelming amount of data, considering all hourly

dispatch and weekly merit order data. All detailed system data can be freely obtained from CDEC-SIC’s

web page at www.cdec-sic.cl. Also, node price reports, used to calculate thermal plant emission factors,

can be obtained from national’s authority energy commission CNE at www.cne.cl. 

The calculation of the baseline emissions will be provided ex-post with real data according the approved

methodology; hence, the data used in this PDD for the calculation of the current baseline for registration

is only for estimation purposes based on historical data that will not necessary reflect actual system

conditions. The detailed data required to calculate the EFOM,y and EFgrid,BM,y  will be provided ex-post  

(refer to section B.6.1 for further details).

For estimation purposes within this PDD, the information of CDEC-SIC real dispatch data from 2007 to

2010 has been used together with a simulated dispatch of the Lican Hydroelectric Plant. The following

tables show the estimation results of emission factor of each year and the average emission factor of the

 period:

 Table B.8: Ex-ante Combined Emission Factors Estimation

YEAR EFOM,y 

tCO2e/GWhEFGrid,BM,y

tCO2e/GWhEF y

tCO2e/GWh

2007 892.45 468.22 680.34

2008 793.30 427.36 610.33

2009 791.29 356.16 573.72

2010 599.33 573.18 586.25

Average 769.09 456.23 612.66

Source: Preliminary estimations based on CDEC-SIC data and IPCC Guidelines. See Appendix 4: for 

further details

The following table provides information and data used to determine baseline emissions

Page 26: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 26/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 26 

 Table B.9: Summarized Data to Calculate the Baseline Emissions

Variable Value Data source

EFgrid, BM,y (tCO2e/GWh) 456.23

Estimated using an average of CDEC-SIC

real dispatch data from 2007 to 2010 and

latest IPCC Guidelines following the latest

Tool to calculate the emission factor for an

electricity system, actually (version 2.2.1)

formula (12) 

EFOM, y (tCO2e/GWh) 769.09

Estimated using an average of ex-post data

of SIC dispatch (2007 to 2010) and latest

IPCC Guidelines following AM0026

(version 3) formula (8) 

EF y(tCO2e/GWh) 612.66Combined Margin result following

AM0026 (version 3) formula (7) 

EGy (GWh/year) 92.101 Average net project generationBEy=ERy (tCO2e/year) ≈ 56,427 

Calculated following AM0026 (version 3)

formula (6) and (2) 

B.6.4. Summary of ex ante estimates of emission reductions

For estimation purposes, the following table summarizes the emissions reductions of the first seven years

of operation and the expected emissions reductions.

 Table B.10: Estimation of Emission Reductions for the First Crediting Periods

YearBaseline

emissions

(t CO2e)

Projectemissions

(t CO2e)

Leakage

(t CO2e)

Emissionreductions

(t CO2e)

2012 (from

01/10/2012)14,107 0 0 14,107

2013 56,427 0 0 56,427

2014 56,427 0 0 56,427

2015 56,427 0 0 56,427

2016 56,427 0 0 56,427

2017 56,427 0 0 56,427

2018 56,427 0 0 56,4272019 (until

30/09/2019)42,320 0 0 42,320

Total 394,989  0 0 394,989 

Total number of 

crediting years7

Annual

average over the

crediting period

56,427 0 0 56,427

Page 27: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 27/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 27 

B.7. Monitoring plan

B.7.1. Data and parameters to be monitored

Data / Parameter Generationy (or Generation j,h) 

Unit Energy in MWh

Description Energy Generation of the Project for each hour h

Source of data On-site metering system (same data submitted to CDEC-SIC)

Value(s) applied 92,101 MWh

Measurement methods

and procedures

For the project activity energy meters, verification procedures shall be

applied based on redundant energy meters.

Monitoring frequency Hourly

QA/QC procedures Meter shall have a maximum error of 0.2% according to NCh 2542 officialstandard, and will be calibrated every two years through independent

certified entities (see Appendix 5: App 5.4.2) 

Metering data is sent regularly to CDEC-SIC where a balance is made for 

energy transactions between power generators. This data results in receipts

of sales that represent a double check for the generation of the Project

Activity.

Purpose of data Calculation of baseline emissions

Additional comment The total energy of the period Generationy, equivalent to the sum of all

Generation j,h shall be crosschecked with actual energy invoices

Data / Parameter EF y

Unit tCO2e/MWh

Description CO2e Emission factor of the displaced energy from the grid

Source of data Latest IPCC Guidelines, CDEC-SIC databases and CNE official reports

Calculated based on AM0026 (version 3) formula (7) 

Value(s) applied 0.61266 tCO2e/MWh

Measurement methods

and proceduresCalculation based on official data and AM0026 procedures.

Monitoring frequency Annually

QA/QC procedures Automatic calculation procedure through a revised worksheet

Purpose of data Calculation of baseline emissionsAdditional comment

Page 28: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 28/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 28 

Data / Parameter EFOM,y 

Unit tCO2e/MWh

Description Operating Margin Emission Factor Source of data Latest IPCC Guidelines, CDEC-SIC databases and CNE official reports.

Calculated based on AM0026 (version 3) formula (8) using CDEC-SIC

data

Value(s) applied 0.76909 tCO2e/MWh

Measurement methods

and proceduresCalculated using CDEC-SIC databases and AM0026 procedures.

Monitoring frequency Annually

QA/QC procedures Automatic calculation procedure through a revised worksheet. Calculation

should be done after CDEC-SIC energy balance to ensure data validity

Purpose of data Calculation of baseline emissions

Additional comment

Data / Parameter EF j,h

Unit tCO2e/MWh

Description Operating margin Emission factor for proposed CDM project j for hour h 

Source of data Latest IPCC Guidelines, CDEC-SIC databases and CNE official reports

Calculated based on AM0026 (version 3) formula (9) 

Value(s) applied Average estimation is 0.76909 tCO2e/MWh (EFOM,y)

Measurement methods

and procedures

Calculated from CDEC-SIC dispatch data and AM0026 procedures.

Monitoring frequency Hourly

QA/QC procedures Automatic calculation procedure through a revised worksheet. Calculation

should be done after CDEC-SIC energy balance to ensure data validity

Purpose of data Calculation of baseline emissions

Additional comment

Page 29: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 29/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 29 

Data / Parameter D(j,i) 

Unit Energy in MWh

Description Energy displacement of the marginal plant i due to the proposed CDM project j 

Source of data Calculated based on AM0026 (version 3) formula (11) using CDEC-SIC

dispatch data

Value(s) applied Displaced energy is calculated for each system unit. Total energy

displacement for the proposed Project Activity is equivalent to project

generation (60.75 GWh per year)

Measurement methods

and proceduresCalculated from CDEC-SIC dispatch data and AM0026 procedures.

Monitoring frequency Hourly

QA/QC procedures Automatic calculation procedure through a revised worksheet. Calculation

should be done after CDEC-SIC energy balance to ensure data validity

Purpose of data Calculation of baseline emissions

Additional comment

Data / Parameter di

Unit tCO2e/MWh

Description Emission factor of the marginal plant i,

Source of data IPCC manual and CNE node price report

Calculated based on AM0026 (version 3) formula (12)  based on official

data whenever available

Value(s) applied Average for Coal powered units = 1.29 tCO2e per MWh

Average for diesel powered units = 0.81 tCO2 per MWh

Average for natural gas powered units = 0.55 tCO2 per MWh

Measurement methods

and procedures

Calculation based on official data and the latest IPCC manual and official

data from CNE´s Node Price Report.

Monitoring frequency Hourly

QA/QC procedures Calculation based on official data. Verification procedure shall be applied

 based on historical data per fuel type.

Purpose of data Calculation of baseline emissions

Additional comment

Page 30: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 30/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 30 

Data / Parameter SFCi

Unit Fuel intensity in Ton/MWh or TJ/MWh

Description Specific fuel consumption of it

marginal power plant Source of data CNE official reports and CDEC-SIC databases

Value(s) applied Average for Coal powered units = 0.547 tons per MWh

Average for diesel powered units = 0.291 m3 per MWh

Average for natural gas powered units = 0.227 m3

per MWh

Measurement methods

and procedures

Calculation based on official data. Verification procedure shall be applied

 based on historical data per fuel type.

Monitoring frequency Annually

QA/QC procedures Data is obtained from official reports. Historic comparison of each unit can

 provide data validation for existing and new units in the system.

Purpose of data Calculation of baseline emissions

Additional comment

Data / Parameter M 

Unit  Number 

Description  Number of marginal plants that would be dispatched if the system is

operated without the N CDM projects. 

Source of data CDEC-SIC data

Value(s) applied Several results per hour base

Measurement methods

and proceduresCalculated from CDEC-SIC databases and AM0026 procedures.

Monitoring frequency Hourly

QA/QC procedures Electronic worksheet shall be implemented to deliver automatic

calculations through revised worksheet

Purpose of data Calculation of baseline emissions

Additional comment

Page 31: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 31/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 31 

Data / Parameter N 

Unit  Number 

Description List of CDM plants in the system Source of data CDEC-SIC and UNFCCC registered projects for the SIC grid

Value(s) applied  N=1

For estimation purposes, only one CDM unit was considered. According to

AM026 methodology, the identification of marginal plant(s) displaced by

CDM projects is based on the “first- built first served” principle. Assuming

only one CDM unit in the system is equivalent to assume that the proposed

 project is the last CDM project of the system.

Actual number of CDM units will be determined according to the official

information from UNFCCC project registry and CDEC-SIC actual dispatchMeasurement methods

and proceduresDetermined from CDEC-SIC databases

Monitoring frequency Annually

QA/QC procedures Data is obtained from official reports.

Purpose of data Calculation of baseline emissions

Additional comment

Data / Parameter C j

Unit MWh

Description Energy generation of CDM project j Source of data CDEC-SIC dispatch data

Value(s) applied Since N = 1, as describes in the previous table, all CDM energy considered

for estimation purposes is equivalent to 92.101 GWh per year.

Measurement methods

and proceduresCalculated from CDEC-SIC dispatch data and AM0026 procedures.

Monitoring frequency Hourly

QA/QC procedures Automatic calculation procedure through a revised worksheet. Calculation

should be done after CDEC-SIC energy balance to ensure data validity

Purpose of data

Additional comment

Page 32: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 32/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 32 

Data / Parameter Ai

Unit MW

Description Maximum energy generation of the marginal  plant i at hour h Source of data CDEC-SIC

Value(s) applied Several system units are considered in the estimation. Official CDEC-SIC

dispatch data was used

Measurement methods

and proceduresDetermined from CDEC-SIC official data

Monitoring frequency Hourly

QA/QC procedures Data is obtained from CDEC-SIC official data

Purpose of data Calculation of baseline emissions

Additional comment

Data / Parameter Bi

Unit MWh

Description Energy generation of the marginal plant i during hour h 

Source of data CDEC-SIC

Value(s) applied Several system units are considered in the estimation.

Measurement methods

and proceduresDetermined from CDEC-SIC databases.

Monitoring frequency Hourly

QA/QC procedures Data is obtained from official CDEC-SIC databases.

Purpose of data Calculation of baseline emissions

Additional comment

Data / Parameter EF grid,BM,y

Unit tCO2e/MWh

Description Build Margin CO2 Emission Factor of the grid for the year y 

Source of data Calculated based on the latest Tool to calculate the emission factor for an

electricity system, actually (version 2.2.1) formula (12). based on official

data, CNE node price report, the latest IPCC Guidelines and CDEC-SIC

databases

Value(s) applied 0.45623 tCO2e/MWhMeasurement methods

and procedures

Calculated using CDEC-SIC databases and the latest “Tool to calculate the

emission factor for an electricity system” procedures

Monitoring frequency Annually

QA/QC procedures Automatic calculation through a revised worksheet using CDEC-SIC and

official databases and CNE Node Price report values.

Purpose of data Calculation of baseline emissions

Additional comment

Page 33: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 33/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 33 

Data / Parameter EFEL,m,y

Unit tCO2e/MWh

Description CO2 Emission Factor of power unit min year y Source of data Calculated based on the latest Tool to calculate the emission factor for an

electricity system, actually (version 2.2.1). Based on the latest IPCC

Guidelines, CNE official reports and CDEC-SIC databases

Value(s) applied Average estimation is 0.45623 tCO2e/MWh (EFgrid,BM,y)

Measurement methods

and procedures

Calculated from CDEC-SIC databases and the latest Tool to calculate the

emission factor for an electricity system procedures.

Monitoring frequency Annually

QA/QC procedures Official data and latest IPCC Guidelines are used

Purpose of data Calculation of baseline emissions

Additional comment

Data / Parameter EGm,y

Unit MWh

Description  Net quantity of electricity generated and delivered to the grid by power 

unit min year y 

Source of data CDEC-SIC dispatch databases

Value(s) applied Several system units are considered in the estimation.

Measurement methods

and proceduresDetermined from CDEC-SIC dispatch databases

Monitoring frequency AnnuallyQA/QC procedures Automatic calculation through a revised worksheet using CDEC-SIC data

Purpose of data Calculation of baseline emissions

Additional comment

Data / Parameter Plant name

Unit Text

Description Identification of power sources

Source of data CDEC-SIC databases

Value(s) applied Several system units are considered in the estimation.

Measurement methodsand procedures

Determined from CDEC-SIC databases, as new power plants are availablein the system

Monitoring frequency Annually

QA/QC procedures Based on CDEC-SIC identification names. A revised worksheet is used to

 properly identify each plant name on the system.

Purpose of data Calculation of baseline emissions

Additional comment

Page 34: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 34/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 34 

Data / Parameter CEFOM, i

Unit tCO2 per ton of fuel or TJ

Description CO2 emission factor of fuel used in the it

marginal power plant of theOperating Margin cohort

Source of data IPCC Guidelines

Value(s) applied Coal powered units = 94.6 tCO2e per TJ

Diesel powered units = 74.1 tCO2 per TJ

 Natural gas powered units = 56.1 tCO2 per TJ

Measurement methods

and proceduresDetermined from IPCC guidelines following AM0026 procedures

Monitoring frequency As required following the latest IPCC guidelines updates

QA/QC procedures IPCC recommended data is used

Purpose of data Calculation of baseline emissions

Additional comment

Data / Parameter Oxidi

Unit %

Description Fraction of fuel oxidized on combustion

Source of data Latest IPCC default values

Value(s) applied Average for Coal powered units = 100%

Average for diesel powered units = 100%

Average for natural gas powered units = 100%

Measurement methods

and proceduresDetermined from IPCC guidelines following AM0026 procedures

Monitoring frequency As required following the latest IPCC guidelines updates

QA/QC procedures IPCC recommended data is used

Purpose of data Calculation of baseline emissions

Additional comment

Data / Parameter SFCm,y

Unit Mass or volume per MWh (Ton/MWh or TJ/MWh)

Description Specific fuel consumption of the power unit m in the year y of the Build

Margin

Source of data CNE node price report, CDEC-SIC databases and/or other official sources

Value(s) applied Several system units are considered in the estimation.

Measurement methods

and proceduresDetermined from CNE node price reports and CDEC-SIC databases.

Monitoring frequency Annually

QA/QC procedures Automatic calculation through a revised worksheet

Purpose of data Calculation of baseline emissions

Additional comment In replacement of FCi,m,y following explanation in section B.6.3 step 2)

( replacement-am-07 formula 2)

Page 35: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 35/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 35 

Data / Parameter NCVm,y

Unit Energy per mass or volume unit

Description  Net calorific value (energy content) of fossil fuel of power  plant  m in year y 

Source of data Latest CNE official data for national energy inventory

Value(s) applied Average for Coal powered units = 7,000 Kcal per Kg

Average for diesel powered units = 10,900 Kcal per Kg

Average for gas powered units = 9,341 Kcal per m3

Measurement methods

and proceduresDetermined from CNE official data for national energy inventory

Monitoring frequency Annually

QA/QC procedures Official data is used

Purpose of data Calculation of baseline emissions

Additional comment In replacement of NCVi,y following explanation in section B.6.3 step 2)

(replacement-am-07 formula 2)

Data / Parameter EFCO2,m,y 

Unit tCO2 per GJ

Description CO2 emission factor of fossil fuel used by power plant min year y 

Source of data Latest IPCC Guidelines (2006) values at the lower limit of the uncertainty

at a 95% confidence interval following the “Tool to calculate the emission

factor for an electricity system”

Value(s) applied

Several units are considered in the estimation.

Measurement methods

and proceduresDetermined from IPCC guidelines

Monitoring frequency As required following the latest IPCC guidelines updates

QA/QC procedures IPCC recommended data is used

Purpose of data Calculation of baseline emissions

Additional comment In replacement of EFCO2,i,y and EFCO2,m,i,y following explanation in section

B.6.3 step 2) (replacement-am-07 formula 2 and am-07 formula 3)

Page 36: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 36/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 36 

Data / Parameter ym,   

Unit ratio

Description Average net energy conversion efficiency of power unit min year y 

Source of data Latest “Tool to calculate the emission factor for an electricity system”, 

Annex 1.

Value(s) applied

 Not Applicable

Measurement methods

and proceduresDetermined according to AM0026 procedures

Monitoring frequency As required following the latest updates of the “Tool to calculate the

emission factor for an electricity system” QA/QC procedures Official data is used

Purpose of data Calculation of baseline emissions

Additional comment

B.7.2. Sampling plan

 Not applicable

B.7.3. Other elements of monitoring plan

The monitoring methodology determines the baseline emissions by observing the actual power dispatchdata from CDEC-SIC and the official expansion plan provided by CNE.

Please refer to section B.6.3 for formulae reference

The monitoring methodology involves the monitoring of the following:

The monitoring methodology involves the monitoring of the following:

  Fuel Specific Consumption for every power plant: Semi-annual CNE Node Price Report and/or 

other official sources

  Calorific Content of every Fuel: CNE National Energy Balance

  Fuel Carbon Content: IPCC Guidelines

  Combustion Efficiency: IPCC Guidelines

All data monitored and required for verification and issuance are to be kept for two years after the end of 

the crediting period or the last issuance of CERs for this project activity, whichever occurs later.

The marginal plant(s) are identified using the merit order and the official marginal price for that hour.

Page 37: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 37/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 37 

1-. Project Activity Metering system diagram

Figure B.5 : Lican Hydroelectric Plant Energy Metering System Diagram

3

~

Power

TransformerPower

Unit 1

High Voltage

Meetering

Device

Class 0.2

Control Room

High Voltage Line

Energy Measurement

Meetering

Server

Operator

Screen

Meetering System Ethernet

Mid Voltage Line

Energy Measurement

Mid Voltage

Meetering

DevicesThis device measures the

Project net energy and is

used for sending data to

CDEC-SIC.

This device is the relevant

measurement equipment

for EFy calculations

3

~

Power

Unit 2

Energy to

The grid

 

2- Data Processing for ER calculation

  Step 1. Calculation of Operating Margin Emission Factors

The next diagram shows the complete process for calculating the operating margin emission factor for 

the Lican Hydroelectric Plant:

Page 38: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 38/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 38 

 Net hourly Generation output from the Project Activity and all other units in the system

(MWh)

Analysis of hourly dispatch from all units of the SIC to determine

Marginal Plant(s) not dispatched (or displaced) due to dispatch of all existing CDM projects

(CDEC-SIC hourly data)

Calculation of emission factor of all operational units of the system

(CNE report and latest IPCC Guidelines following AM0026 procedures)

(tonnes CO2e/MWh)

Determination of the marginal plants and energy being displaced due to the operation of the CDM

Project Activity following the “first-built first-served” principle3

stated on AM0026

(MWh and tonnes CO2e/MWh)

Determination of EFOM,y of each CDM project as the weighted average emission factor of the Marginal

Plant(s) not dispatched (or displaced) by each CDM Project Activity

(tonnes CO2e/MWh)

  Step 2 – Calculation of the Build Margin

Following AM0026 (version 3) option i), the Build Margin emission factor is calculated using the “Tool

to calculate the emission factor for an electricity System” (version 2.2.1).

Please refer to formulae stated in section B.6 (Tool to calculate the emission factor for an electricitysystem, (version 2.2.1) formulas (13), (2) and (3)).

The next diagram shows the complete process for calculating and assigning the Build Margin emission

factor:

3 The “first-built first-served” principle implies that the “last” plant existing in the grid, that would have been

dispatched to meet the electricity requirement fulfilled by all the CDM projects in the grid is considered to be

displaced due to introduction of the First CDM project built in the system. Similarly the first marginal plant isconsidered to be displaced by the CDM plant built last. Note that all CDM projects (even projects adopting other 

methodologies) must be considered

Page 39: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 39/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 39 

SIC Dispatch of all power units of the system

(MWh)

Determination of set of mplants considered in the Build Margin following the “Tool to

calculate the emission factor for an electricity system” 

(MWh)

Calculation of emission factor of the set of mplants considered in the Build Margin

(CNE reports, latest IPCC guidelines and CDEC-SIC databases)

(tonnes CO2e/MWh)

Determination of EFgrid,BM,y as the weighted average emission factor of the dispatched plants and their 

individual emission factor 

(tonnes CO2e/MWh)

  Step 3 – Calculation of the Baseline Emissions Reductions

According to AM0026 methodology, the Combined Margin emission factor (CM) of the Project is

calculated as the weighted average of the Operating Margin (OM) and the Build Margin (BM).

Please refer to formulae stated in section B.6.3 (AM0026 (version 3) formula (2), (6) and (7))

Calculation of Combined Margin Emission factor of EFgrid,BM,y and EFOM,y 

(tonnes CO2e/MWh)

Energy generation of the Project Activity

(from CDEC-SIC or metering data)

(MWh)

Calculation of Baseline Emissions

(tonnes CO2e)

Discount any leakage or project activity emissions, if any

(No leakage emission was identified for Lican Hydroelectric Plant, and project emissions are null)

(tonnes CO2e)

Page 40: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 40/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 40 

3-. Operational and Management structure

In order to secure a correct emission reduction calculation, the project developer will implement and

maintain a proper management structure as follows:

Figure B.6 : Management Structure for Empresa Eléctrica Lican S.A.

General

Manager

Plant

Manager

Operation

Chief 

Administrative

Manager

Environmental

Chief  

Empresa Eléctrica Lican S.A. will designate competent managers who will be in charge of and

accountable for the generation of ERs including monitoring, record keeping, computation of ERs, audits

and verification.

An General Manager will be in charge of the company commercial activities, through a Plant Manager and an Administrative Manager. The Plant Manager will be in charge of all plant production and

maintenance activities through the Operation Chief. An Environmental Chief will be in charge of 

developing and operating the project in accordance with all environmental obligations relative to the

 project activity.

 Nevertheless, the current management structure may vary on time, as it is usual on any management

scheme, but it shall maintain all relevant tasks required to ensure proper operation and monitoring

according to this PDD.

Page 41: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 41/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 41 

SECTION C. Duration and crediting period

C.1. Duration of project activity

C.1.1. Start date of project activity

The Project Start Date is 13/10/2008. This is the date of the civil work contract with ICAFAL.

C.1.2. Expected operational lifetime of project activity

The operational lifetime of Lican Hydroelectric Plant is estimated over 40 years.

C.2. Crediting period of project activity

C.2.1. Type of crediting period

The crediting period will be renewable. This will be the first crediting period.

C.2.2. Start date of crediting period

01/10/2012 or the day after the project has been registered, whichever the latest

C.2.3. Length of crediting period

Seven (7) years

Page 42: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 42/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 42 

SECTION D. Environmental impacts

D.1. Analysis of environmental impacts

Following article 10, letter c) of the Environmental Law Nº19,300 (Ley sobre Bases Generales del Medio

Ambiente), and article 3, letter c) of its Regulation (Supreme Decree N°95 of 2001, Reglamento del

Sistema de Evaluación de Impacto Ambiental - RSEIA), all energy generation projects having more than

3 MW of installed capacity, must meet the terms of Environmental Impact Evaluation System (SEIA).

Further, section II, article 8 of the Environmental Law 19,300 indicates that this kind of projects will not

 be able to be executed or modified if they do not have the subsequent approval of the Environmental

Qualification Resolution (R.C.A. in Spanish). According this, Lican Hydroelectric Plant was submitted

to the SEIA through an Environmental Impact Assessment (EIA in Spanish).

The Lican project was initially approved by the Environmental Impact Assessment process in 23/12/2004

through the Resolución Exenta N° 862, COREMA X Región de los Lagos, and modified throughResolución Exenta N° 0 dated in 16/01/2006, Resolución Exenta N° 267 dated in 25/04/2006,

Resolución Exenta N° 767 dated in 17/11/2006 and Resolución Exenta N° 0051 dated in 14/04/2007.

According to Chilean legal dispositions, the environmental qualification process discusses a wide range

of environmental impacts related to physical, biotic, social and economic impacts during the plant’s

construction, operation and end of the project operation, such as: land use, air quality, noise emissions,

solid emissions, liquid emissions, native forestry effects, among other effects. It identifies the risk or 

contingency zones and the type of risk associated to them. It also discusses a number of corrective

measures and establishes an environmental management plan to deal with the identified impacts. This

 plan addresses the significant and medium impacts providing measures for their mitigation, restoration or 

compensation. In general terms, the RCA certifies that:

  The project accomplishes with all the environmental requirements, and the environmental laws,

including all the requirements stated in the sectorial environmental permits and authorizations.

There is a minimum ecological flow to be considered for this project activity of 750 liters per second,

according to Resolución D.G.A. Nº 660 dated on 20/11/2003. This flow will be granted through the intake

design, where the intake will be placed with a 40 cm difference from the river bed, allowing the delivery

of the ecological flow to de river before the acquisition of waters in the intake channel.

D.2. Environmental impact assessment

As mentioned above, no relevant impacts where detected for the Project

All objections were assessed and officially cleared up by COREMA in a meticulous way. Specific

measures are considered for soil, natural watercourses, transport, risk and emergency control, specially

fire and spills.

Lican Hydroelectric Plant does not entail any physical construction such as dams and dikes, or cause

reservoir-like impoundments, with the exception of the daily reservoir of 102,000 m3

considered in the

Project design, having a reservoir power density of 178.23 W/m2 (18,180,000 W / 102,000 m2), which is

greater than 4 W/m2.

Page 43: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 43/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 43 

SECTION E. Local stakeholder consultation

E.1. Solicitation of comments from local stakeholders

Lican Hydroelectric Plant SEIA project file can be publicly accessed through SEA website at

www.sea.gob.cl  containing all project details and the Official Environmental Qualification.

Link:

http://seia.sea.gob.cl/expediente/expedientesEvaluacion.php?modo=ficha&id_expediente=968098 

In compliance with the Chilean Environmental Law 19,300 and the SEIA procedures, the project’s EIA

collected opinions and information from all relevant authorities and local stakeholders in consideration to

their legal relation to possible impacts of the project. These comments were received along the

environmental qualification process and its later modifications between 17/08/2005 and 06/12/2005

Local Authorities:

The local authorities that presented comments to the project are the following:

  CONADI

  CONAF, X Región de Los Lagos

  Dirección de Obras Hidráulicas, X Región de Los Lagos

  Dirección General de Aguas Puerto Montt, X Región

  Ilustre Municipalidad de Río Bueno

  SEREMI de Agricultura, X Región de Los Lagos

  SEREMI de Salud, Región de Los Lagos

  SEREMI de Vivienda y Urbanismo, X Región de Los Lagos  Sernapesca, X Región de Los Lagos

  Sernatur, X Región de Los Lagos

  Servicio Agrícola y Ganadero, X Región de Los Lagos

  Consejo de Monumentos Nacionales

  Subsecretaría de Pesca

  Sernageomin

  Servicio de Salud de Valdivia

Local Community:

Also individuals and local communities were consulted during de EIA process, as it is a requirement of 

article 29 of law 19,300.

E.2. Summary of comments received

Comments received relate mainly to the following aspects: flora and fauna impacts, land use and

treatments, hydrological resources, debris management, level improvement, rubble movement,

 biodiversity, landscape intervention, land ownership, eventual project intervention with surrounding

communities, access roads maintenance, effects on energy tariff for local communities, transmission line

impacts, water resource impacts, etc.

Details of each of the comments received are detailed in the each of the qualification resolutions and theSEIA process at CONAMA’s web site:

Page 44: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 44/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 44 

http://seia.sea.gob.cl/expediente/expedientesEvaluacion.php?modo=ficha&id_expediente=968098 

E.3. Report on consideration of comments received

Comments, observations and questions received from above mentioned authorities were answered by the

 project developer during the SEIA process. The answers are compiled in the approval resolutions:

 Resolución Exenta N° 862, COREMA X Región de los Lagos, Resolución Exenta N° 0 dated in

16/01/2006, Resolución Exenta N° 267 dated in 25/04/2006, Resolución Exenta N° 767 dated in

17/11/2006 and Resolución Exenta N° 0051 dated in 14/04/2007 .

Besides from the above comments, no major issues were raised that could be related to the environmental

or CDM aspects of the project. All comments and questions were duly taken into account by the project

developer for the construction and operation of the project

Page 45: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 45/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 45 

SECTION F. Approval and authorization

Host party Letter of Approval of the Lican Hydroelectric Plant has been obtained on 27/04/2006. On

30/04/2009 a new Letter of Approval was granted confirming Empresa Eléctrica Lican S.A. as the project proponent in replacement of Inversiones Candelaria Ltda.

There are no other Parties involved in the Project Activity, thus no there are no letters of approvals

available at the time of submitting this PDD for valitadion.

- - - - -

Page 46: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 46/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 46 

Appendix 1: Contact information of project participants

Organization name Empresa Eléctrica Lican S.A. 

Street/P.O. Box Av. Vitacura 2771 of. 501 – Las Condes

Building Helvecia

City Santiago de Chile

State/Region Región Metropolitana

Postcode 7550134

Country Chile

Telephone 56-2-592-51-00

Fax 56-2-588-88-85

E-mail [email protected] Website

Contact person

Title General Manager 

Salutation Mr.

Last name Pérez

Middle name Rodrigo

First name Marcelo

Department

Mobile

Direct fax 56-2-592-51-00

Direct tel. 56-2-588-88-85

Personal e-mail

Page 47: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 47/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 47 

Appendix 2: Affirmation regarding public funding

There is no public funding in the projects. The fund used to financing is not diversion of 

ODA

Page 48: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 48/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 48 

Appendix 3: Applicability of selected methodology

 No further background information on the applicability of the selected methodology.

Page 49: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 49/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 49 

Appendix 4: Further background information on ex ante calculation of emission reductions

 Table App4.1 – Ex-ante EFOM,y results according to AM0026

YEAR Sum Generation j,h 

(1)

[in MWh]

Sum { EF j,h x Generation j,h }

(2)

[in tCO2e]

EFOM,y

(2) / (1) x 1000

[in tCO2e/GWh]

2007 92,101 82,195.6 892.45

2008 92,101 73,064.0 793.30

2009 92,101 72,878.5 791.29

2010 92,101 55,198.5 599.33

 Table App4.2 – Ex-ante EF grid, BM, y results according to the “  Tool to calculate the emission factor for an electricity

system”  

YEAR Sum EGm,y 

(1)

[in MWh]

Sum { EF EL,m,y x EGm,y }

(2)

[in tCO2e]

EFgrid, BM, y

(2) / (1) x 1000

[in tCO2e/GWh]

2007 9,482.9 4,440,093.6 468.22

2008 8,725.3 3,728,797.7 427.36

2009 8,112.7 2,889,394.9 356.16

2010 9,480.3 5,433,966.0 573.18

 Table App4.3 – Ex-Ante EF y results according to AM0026

YEAR EFOM,y

(1)

[in tCO2e/GWh]

wOM

(2)

EFgrid, BM, y(3)

[in tCO2e/GWh]

WBM

(4)

EFy(1) x (2) + (3) x (4)

[in tCO2e/GWh]

2007 892.45 0.5 468.22 0.5 680.34

2008 793.30 0.5 427.36 0.5 610.33

2009 791.29 0.5 356.16 0.5 573.72

2010 599.33 0.5 573.18 0.5 586.25

Average 769.09 456.23 612.66

 Table App4.4 – Ex-ante Baseline Emissions displaced by the Project

YEAR 

Sum Generation j,h or Generationy 

(1)

[in MWh]

EF y

(2)[in tCO2e/GWh]

BE y

(1) x (2)[in tCO2e]

2007 92,101 680.34 62,660

2008 92,101 610.33 56,212

2009 92,101 573.72 52,840

2010 92,101 586.25 53,995

Average 92,101 612.66 56,427

Further details in estimating ex-ante emission reductions can be obtained in the ex-ante estimation

worksheets

Page 50: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 50/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 50 

Appendix 5: Further background information on monitoring plan

MONITORING AND VERIFICATION PROTOCOL (MVP)

App 5.1  Purpose of The MVP ................................................................................................................... 50 App 5.2  Concepts and Principle Assumptions .......................................................................................... 51 App 5.3  Operational and Monitoring Obligations ..................................................................................... 53 App 5.4  Project Workbook ........................................................................................................................ 53 App 5.5  Project Activity Sustainable Development MVP ........................................................................ 59 App 5.6  Management and Operational Systems MVP .............................................................................. 60 App 5.7  Auditing and Verification Procedures ......................................................................................... 61 

App 5.1  Purpose of The MVP

In the context of the Clean Development Mechanism (CDM) of the Kyoto Protocol, monitoring describes

the systematic surveillance of a project's performance by measuring and recording performance-related

indicators relevant to the project or activity. Verification is the periodic auditing of monitoring results,

the assessment of achieved emission reductions (ER) and of the project's continued conformance with allrelevant project criteria.

This Monitoring and Verification Protocol (MVP) defines a standard against which the project

 performance in terms of its greenhouse gas (GHG) reductions and conformance with all relevant Clean

Development Mechanism (sustainable development) criteria will be monitored and verified. As such, the

MVP, after its validation, will be an integral part of the contractual agreement between the Project

Sponsor, the Project Operator and the ERs Buyer(s). The MVP builds on the baseline scenario identified

in the Baseline Study and is fully consistent with the Baseline Study.

The MVP is a working document that identifies the key project performance indicators and sets out the

 procedures for tracking, monitoring, calculating and verifying the impacts of the project, in particular 

with respect to the project’s ERs. The MVP must therefore be used throughout the life of the project.Specifically, the MVP provides the requirements and instructions for:

  Establishing and maintaining the appropriate monitoring system including spreadsheets for the

calculation of ERs.

  Checking whether the project meets key sustainable development indicators;

  Implementing the necessary measurement and management operations;

  Preparing for the requirements of independent, third party verification and audits.

The MVP can be updated and adjusted to meet operational requirements, provided such modifications

are approved by the Verifier during the process of initial or periodic verification. In particular, any shifts

in the applicable baseline that are identified by following this MVP may lead to such amendments, whichmay be mandated by the Verifier.

Page 51: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 51/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 51 

App 5.2  Concepts and Principle Assumptions

App 5.2.1 

The Lican Hydroelectric Plant ActivityThe Lican Hydroelectric Plant (the Project Activity), consists of a run-of-river power plant with a total

installed of 18.18 MW that utilizes the waters of Lican river. The project developer and operator (the

Project Operator) is Empresa Eléctrica Lican S.A.

Being this a CDM activity, Lican Hydroelectric Plant must meet the requirements of the Kyoto Protocol

Art. 12 for CDM projects. The methodology for carrying this out and the monitoring and verification

 protocol for establishing the emission reduction are provided in this document.

App 5.2.2  Emission reductions from the Project Activity

As indicated in the Baseline Study, the actual emission reduction to be credited from the project will

depend on the actual dispatch data for the SIC provided by the Economic Dispatch Center (CDEC).

App 5.2.3  Geographic and System Boundaries for the MVP

The Baseline Study defines the project boundary to correspond to the SIC Grid for the purpose of 

identifying potential emissions and leakage during the projects lifetime.

The Baseline Study has not found leakage to be a problem for the project as the project is a closed

system. Therefore the MVP does not correct the calculated ERs to account for leakage.

App 5.2.4  Time Boundary and Baseline Review Protocol

The Baseline Study has opted for a 7-year renewable baseline (for a total crediting period of 21 years) for 

which the project is likely to generate ERs in compliance with the CDM.

App 5.2.5  Calculating Emission Reductions

The emission reduction calculation results from the displacement of electricity produced mainly by coal,

diesel and other pollutant sources in the SIC, due to the clean energy dispatch of the Project Activity in

the system. The outline of the method to calculate the emission reduction is as follows:

Page 52: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 52/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 52 

  Key Steps for Estimating Operating Margin Emission Factor

 Net hourly Generation output from Lican Hydroelectric Plant and all other units in the system(MWh)

Analysis of hourly dispatch from all units of the SIC to determine

Marginal Plant(s) not dispatched (or displaced) due to dispatch of all existing CDM projects

(CDEC-SIC hourly data)

Calculation of emission factor of all operational units of the system

(CNE report and latest IPCC Guidelines following AM0026 procedures)

(tonnes CO2e/MWh)

Determination of the marginal plants and energy being displaced due to the operation of the CDM

Project Activity following the “first-built first-served” principle4

stated on AM0026

(MWh and tonnes CO2e/MWh)

Determination of EFOM,y of each CDM project as the weighted average emission factor of the Marginal

Plant(s) not dispatched (or displaced) by each CDM Project Activity

(tonnes CO2e/MWh)

  Key Steps for Estimating Build Margin Emission Factor

SIC Dispatch of all power units of the system

(MWh)

Determination of set of m plants considered in the Build Margin following the “Tool to

calculate the emission factor for an electricity system” 

(MWh)

Calculation of emission factor of the set of m plants considered in the Build Margin

(CNE reports, latest IPCC guidelines and CDEC-SIC databases)

(tonnes CO2e/MWh)

Determination of EFgrid,BM,y as the weighted average emission factor of the dispatched plants and their 

individual emission factor 

(tonnes CO2e/MWh)

4 The “first-built first-served” principle implies that the “last” plant existing in the grid, that would have been

dispatched to meet the electricity requirement fulfilled by all the CDM projects in the grid is considered to be

displaced due to introduction of the First CDM project built in the system. Similarly the first marginal plant isconsidered to be displaced by the CDM plant built last. Note that all CDM projects (even projects adopting other 

methodologies) must be considered

Page 53: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 53/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 53 

  Key Steps for Estimating Baseline Emissions

Calculation of Combined Margin Emission factor of EFgrid,BM,y and EFOM,y 

(tonnes CO2e/MWh)

Energy generation of the Project Activity

(from CDEC-SIC or metering data)

(MWh)

Calculation of Baseline Emissions of the Project

(tonnes CO2e)

Discount any leakage or project activity emissions, if any

(No leakage emission was identified for Lican Hydroelectric Plant, and project emissions are null)

(tonnes CO2e)

App 5.3  Operational and Monitoring Obligations

App 5.3.1  Operational Obligations

The operational obligations of the Project Activity operator are to ensure that all reasonable steps are

taken to maximize the generation of the project facility and, thereby, maximize the GHG emissions

reduction. This is in the interest of the operator anyway.

App 5.3.2 

Data Requirements and Project DatabaseThe data required for the MVP is in line with the kind of information collected by an electricity utility.

The data used in this MVP will be collected by the project operator and comes from the following

sources:

  The hourly generation of the project is obtained from the metering system of the plant, which is

submitted every two hours to CDEC-SIC.

  The actual dispatch of all units in the system and dispatch priority list of the power units is

collected from the CDEC-SIC website (www.cdec-sic.cl) 

  Data of Emission factors of the thermal units in the system is collected from CNE reports, latest

IPCC guidelines and CDEC-SIC databases

App 5.4  Project Workbook 

App 5.4.1  Main Data

The project MVP consists of the following three workbooks:

  MVP workbook for the Operating Margin calculation

  MVP workbook for the Build Margin calculation

  MVP workbook for the ERs calculation of the CDM project

In the MVP workbooks for the Operating Margin and Build Margin calculations its used respectively the

following data:

Page 54: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 54/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 54 

  Generation and other data collected from CDEC-SIC: Data from electricity generation of all

units of the system from Load Economic Dispatch Center (CDEC-SIC).

  Tonnes of CO2e (tCO2) Emission Factors: Emission Factor of thermal units of the system,

calculated every six months form the CNE official node price reports.

  Emission Displacement: Calculation of the Operating Margin and the Build Margin.

Determination of emission displacement due to the operation of the project.

The calculations resulted from these workbooks its used in the MVP workbook for the ERs calculation to

calculate the ERs of the CDM project.

The following sections describe how is calculated ERs.

App 5.4.2  Energy Generation of The CDM Project

The hourly net generation of the Project Activity is obtained from the metering system of the power  plant. This information is submitted to CDEC-SIC every two hours, as all other plants of the SIC. With

this data, CDEC-SIC provides an hourly report of the system dispatch.

Day 1 2 3 .. 24

1 Energy Generation (MWh)

2 Energy Generation (MWh)

3 Energy Generation (MWh)

Energy Generation (MWh)

31 Energy Generation (MWh)

Hour 

 

The electronic metering system of the Project Activity must have precision class of 0.2%, according the

 NCh 2542 / 2001, which is the general standard in the electric system in Chile for all power generating

units. This meter will be placed at the high voltage bus. The metering register the instantaneous sum of 

the power of the generators, which is integrated in 15 minutes intervals. The data from the meter will be

collected by the Project Operator, and is then transmitted every two hours to the CDEC-SIC

electronically.

Every meter in the system, including the Project Activity meters, are equipment that fulfill highly

reliability and quality standards. Actually, there is no official indication or regulations that require a

 periodic calibration of metering equipment, however they will be calibrated every two years by

independent and accredited third parties that will certify the meters fulfill the precision requirements.

The calibration procedure consists in comparing the measuring system with a higher precision referencemeter. A calibration report is then issued for each meter.

App 5.4.3  Energy Generation Data of All Generating Units of the System

  Actual Dispatch in the CDEC-SIC

For every hour of the monitoring period, the actual dispatch of the SIC is obtained from the CDEC-SIC.

This information can be retrieved through a web access or a dedicated connection that works as a file

server. A sample data is shown below.

Page 55: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 55/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 55 

DATE

Type V.COSTPLANT POWER Hr01 Hr02 Hr… Hr23 Hr24 TOT

Reservoir ANTUCO 300 171 235 … 181 171 5,113

MACHICURA 90 19 19 … 60 60 881

RANGUE 467 463 463…

461 461 11,117

SANIGNACIO 37 … … … 20 20 168

RALCO 570 570 570 … 570 570 14

… … … … … … …

1.512 1.534 … 2.602 2.224 48,005

Run-of-River ABANICO 136 45 45 … 44 43 1

 ACONCAGUA 72.9 28 28 … 28 28 692

 ALFALFAL 160 56 53 … 57 57 1

CAPULLO 10.7 12 12 … 11 12 280

CDM CHACABUCO 26 19 18 … 17 17 421

CDM QUILLECO 70 40 40 … 40 40 960

CDM OTHER … … … … … … …

CDM PROVIDENCIA 12.75 12.75 12.75 … 12.75 12.75 306

803 787 … 833 18.850

Thermal 0 ACONSTITUCION 20 16 15 … 15 15 354

0 CONSTITUCION 8,7 7 7 … 7 6 146

0 HORCONES TG 12,1 18 17…

16 16 4050 LAJA 8,7 3 4 … 8 6 124

0 LICANTEN 13 2 2 … … … 17

0 P.VALDIVIA 70 … … … … … …

0 PETRPOWER 48,6 68 68 … 68 68 1.634

2,4 ARAUCO 101,3 31 32 … 31 31 761

9,9 CHOLGUAN 15 12 12 … 10 11 276

12,5 NUEVA RENCA 379 186 67 … 367 332 6.463

16,6 NEHUENCO 2 380 379 379 … … … 4.603

16,7 NEHUENCO 2 352 351 336 … 354 356 8.262

17,3 CENTRAL SAN 370 305 167 … 352 353 7.269

20,4 GUACOLDA 1 152 … … … … … …

20,4 GUACOLDA 2 152 150 150 … 15,1 152 3.610

21,3 TALTAL 1 120 97 80 … 116 117 2.435

21,3 TALTAL 2 120 … … … … … …

27,4 VENTANAS2 212 … … … … … …

29,4 BOCAMINATV 125 … … … … … …

… … … … … … … … …

1.626 1.336…

1.511 1.465 36.432

3.940 3.657 … 4.946 4.496 103.287Total

DD-MM-YYYY

 Total of Reservoir

 Total of Run-of-River

 Total Thermal

   Dispatch Priority List

For every week the CDEC-SIC state the dispatch priority list of the power units in the SIC according to

their marginal operation cost. That information is also available from CDEC-SIC and a sample is

reproduced below.

PriorityVariable Cost

USD/MWhUnit

1 0 ACONSTITUCION Arauco

2 0 CONSTITUCION Gener  

3 0 HORCONES TG

4 0 LAJA5 0 LICANTEN

6 0 P.VALDIVIA

7 0 PETROPOWER

8 2,4 ARAUCO

9 9,9 CHOLGUAN

10 12,5 NUEVA RENCA

11 16,6 NEHUENCO 2

12 16,7 NEHUENCO

13 17,3 CENTRAL SAN ISIDRO

14 20,4 GUACOLDA 1

15 20,4 GUACOLDA 2

16 21,3 TALTAL 1

17 21,3 TALTAL 2

18 27,4 VENTANAS2

19 29,4 BOCAMINATV

… … …  

Page 56: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 56/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 56 

  The “Marginal Power Unit in the SIC”

From the data issued by the CDEC-SIC on the hourly marginal power unit, it is possible to determine the

marginal power plant and the next marginal plants in the priority dispatch order list that would bedispatch in the system if no CDM project activities were present in the system.

Every thermal plant has its own tCO2/GWh conversion factor according to its specific consumption and

type of fuel. The emission factors can be calculated using CNE node price report, CDEC-SIC databases

and IPCC manual.

plantsdate of 

commissioning

plant

capacity

(net)

fuel type

plant CO2

emission factor 

(1) x (2) x (3) x (4)

x (5)

unit unit_id comm MW ft.name [tCO2e/GWh]

 Arauco 2 01-01-1996 30,10 biomass 0,00

Cholguán 3 01-01-2003 13,00 biomass 0,00

Constitución Arauco 4 01-01-1996 8,00 biomass 0,00

Horcones TG gas 5 01-01-2004 24,30 natural gas 920,38

Licantén 6 01-01-2004 4,00 biomass 0,00

Pedro de Valdivia 7 01-01-2004 61,00 biomass 0,00

 Antilhue TG 9 10-11-2005 100,60 diesel 778,32

Canutillar 10 01-01-1990 171,60 reservoir 0,00

Candelaria 1 gas 11 16-05-2005 135,32 natural gas 688,92

Candelaria 2 gas 12 01-05-2005 135,32 natural gas 688,92

Colbún 13 01-01-1985 476,80 reservoir 0,00

Machicura 14 01-01-1985 95,76 reservoir 0,00

Nehuenco 9b gas 15 01-01-2002 101,95 natural gas 689,84

Nehuenco 9B diesel 16 01-01-2002 101,95 diesel 928,87

Nehuenco 1 gas 17 01-01-1998 373,56 natural gas 432,22

Nuehuenco 2 gas 18 01-01-2003 382,49 natural gas 397,12

Nehuenco 1 diesel 19 01-01-2004 373,56 diesel 539,71

Rucue 20 01-01-1998 177,70 run-of-river 0,00San Ignacio 21 01-01-1996 36,90 run-of-river 0,00

Constitución Gener 22 01-01-1995 10,06 biomass 0,00

Laja 23 01-01-1995 11,70 biomass 0,00

Nueva Renca gas 24 01-01-1997 370,88 natural gas 424,20

Nueva Renca diesel 25 01-01-2004 370,88 diesel 578,26

 Abanico 26 01-01-1948 128,60 run-of-river 0,00

 Antuco 29 01-01-1981 323,20 run-of-river 0,00

Bocamina TV 31 01-01-1970 119,38 coal 1.053,55

Campanario 1 gas 35 21-03-2007 54,44 natural gas 644,45

Campanario 1 diesel 36 21-03-2007 54,44 diesel 831,88

Candelaria 1 diesel 37 16-05-2005 135,32 diesel 914,67

Candelaria 2 diesel 38 01-05-2005 135,32 diesel 914,67

Cipreses 43 01-01-1955 99,70 reservoir 0,00  

Page 57: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 57/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 57 

  The “Theoretical Dispatch without CDM Projects” and the Emission Displacement 

Without the Project Activity and other CDM projects, the marginal dispatched plant should increment its

generation to supply the system demand in each hour. Since the generation from the marginal plant haslimited capacity, and it´s increment may not be sufficient to meet the system demand, a next power unit

must be dispatched in the economic merit order priority to supply the required energy. And if there is still

not sufficient energy with the next marginal plant, then other unit(s) must be dispatched following the

same order. In order to determine the Project Activity’s energy and emission displacement, i t must be

taken into account all other CDM units of the system. The following table presents an example how the

dispatch should change and the energy displacement that CDM projects will produce in the system.

H1 H2 … H23 H24

CDM N°1 (CHACABUQUITO) Energy in MWh C1 19,0 18,0 … 17,0 17,0

Capacity in MW 26,0 26,0 … 26,0 26,0

CDM N°2 (QUILLECO) Energy in MWh C2 40,0 40,0 … 40,0 40,0

Capacity in MW 70,0 70,0 … 70,0 70,0

CDM N°N-1 (---) Energy in MWh C3 25,0 30,0 … 30,0 30,0

Capacity in MW 55,0 55,0 … 55,0 55,0

CDM N°N (PROJECT ACTIVITY) Energy in MWh C4 10,0 10,0 … 19,0 19,0

Capacity in MW 19,4 19,4 … 19,4 19,4

Marginal Plant 1 Energy MWh B1 97,0 80,0 … 116,0 117,0

Plan Name TALTAL1 TALTAL1 … TALTAL1 TALTAL1

Capacity MW A1 120,0 120,0 … 120,0 120,0

E. Factor TCO2/GWh d1 641,0 641,0 … 641,0 641,0

Marginal Plant 2 Energy MWh B2 - - … - -

Plan Name TALTAL2 TALTAL2 … TALTAL2 TALTAL2

Capacity MW A2 120,0 120,0 … 120,0 120,0

E. Factor TCO2/GWh d2 641,0 641,0 … 641,0 641,0

Marginal Plant 3 Energy MWh B3 - - … - -

Plan Name VENT2 VENT2 … VENT2 VENT2

Capacity MW A3 212,0 212,0 … 120,0 120,0

E. Factor TCO2/GWh d3 1.025,0 1.025,0 … 1.025,0 1.025,0  

If other CDM projects are implemented in the system then, for each hour, the emission displacement

should meet the formulae stated on AM0026 (version 3).

  Emission Displacement for Operating Margin

The emission factor form the Operating Margin can be estimated following formulas indicated en

AM0026 (version 3). The following table presents an illustrated example to calculate the emission

displacement of the Operating Margin.

Page 58: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 58/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 58 

MDL N°1 (CHACABUQUITO)

MWh Displacement

Marginal Plant 1 min(C1, (A1-B1) - D21-D31-D41) = D11 - - … - -

Marginal Plant 2 min(C1-D11; (A2-B2) - D22-D32-D42) = D12 19,0 18,0…

17,0 17,0Marginal Plant 3 C1-D11-D12; (A3-B3) - D23-D33-D43) = D13 - - … - -

TCO2 Displacement

d1*D11+d2*D12+d3*D13 = ER1 12,2 11,5 … 10,9 10,9

MDL N°2 (QUILLECO)

MWh Displacement

Marginal Plant 1 min(C2, (A1-B1) - D31-D41) = D21 - - … - -

Marginal Plant 2 min(C2-D21; (A2-B2) - D32-D42) = D22 40,0 40,0 40,0 40,0

Marginal Plant 3 min(C2-D21-D22; (A3-B3) - D33-D43) = D23 - - … - -

TCO2 Displacement

d1*D21+d2*D22+d3*D23 = ER2 25,6 25,6 … 25,6 25,6

MDL N°N-1 (---)

MWh Displacement

Marginal Plant 1 min(C3;(A1-B1) - D41) = D31 13,0 30,0…

- -Marginal Plant 2 min(C3-D31; (A2-B2) - D42) = D32 12,0 - 30,0 30,0

Marginal Plant 3 min(C3-D31-D32; (A3-B3) - D43) = D33 - - … - -

TCO2 Displacement

d1*D31+d2*D32+d3*D33 = ER3 16,0 19,2 … 19,2 19,2

MDL N°N (PROJECT ACTIVITY)

MWh Displacement

Marginal Plant 1 min(C4;(A1-B1) - 0) = D41 10,0 10,0 … 4,0 3,0

Marginal Plant 2 min(C4-D41; (A2-B2) - 0) = D42 - - 15,0 16,0

Marginal Plant 3 min(C4-D41-D42; (A3-B3) - 0) = D43 - - … - -

TCO2 Displacement

d1*D41+d2*D42+d3*D43 = ER4 6,4 6,4 … 12,2 12,2  

  The Build Margin Calculation Worksheet

For the first crediting period, the Build Margin emission factor EFgrid,BM,y, must be updated annually ex

 post  for the year in which actual project generation and associated emissions reductions occur,

accounting energy and emission from the power plants capacity additions in the electricity system that

comprise 20% of the system generation (in MWh), or the set of five power units that have been built

most recently, it will depend on which method has the larger annual generation. The following table

 presents an illustrated example of how the Build Margin Emission Factor for the Project is calculated for 

a given year 

Page 59: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 59/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 59 

COMM DATE Plant Name Type EF Energy

OTHERS 3.853.386

1970 BOCAMINATV Thermal 925 300.051

1973 EL TORO Reservoir 0 1.693.974

1977 HUASCOTG Thermal 1002,9 29.0641977 VENTANAS1 Thermal 1071 413.467

1977 VENTANAS2 Thermal 1024,96 1.050.510

1981 ANTUCO RoR 0 1.662.081

1981 ARAUCO Thermal 0 156.044

1985 COLBUN Reservoir 0 2.021.022

1985 CONSTITUCION Gener Thermal 982 50.265

1985 CURILLINQUE RoR 0 627.902

1985 DIEGO DE ALMAGRO Thermal 1071 6.236

1985 MACHICURA RoR 0 453.530

1990 CANUTILLAR Reservoir 0 1.094.674

1991 PEHUENCHE Reservoir 0 2.567.234

1993 ACONCAGUA RoR 0 371.391

1993 CONSTITUCION Arauc Thermal 0 132.388

1993 ALFALFAL RoR 0 840.860

1995 CAPULLO RoR 0 74.237

1995 GUACOLDA 2 Thermal 893,697 2.468.970

1995 LAJA Thermal 0 39.483

1996 PANGUE Reservoir 0 1.675.343

1996 SAN IGNACIO RoR 0 182.344

1997 LOMA ALTA RoR 0 276.888

1997 NUEVA RENCA Thermal 396 2.275.586

1997 PUNTILLA RoR 0 118.339

1998 QUELTEHUES RoR 0 357.697

1998 RUCUE RoR 0 1.091.127

1998 CENTRAL SAN ISIDRO Thermal 424,012 2.705.618

1998 NEHUENCO Thermal 396,115 1.847.504

1998 PETROPOWER Thermal 879 526.035

2000 MAMPIL RoR 0 173.898

2000 PEUCHEN RoR 0 261.831

2000 TALTAL 1 Thermal 641 624.403

2000 TALTAL 2 Thermal 641 364.208

2002 NEHUE.9B Thermal 604 106.395

2003 CHOLGUAN Thermal 0 93.3472003 NEHUENCO 2 Thermal 411,691 1.996.332

2003 SAN FRANCISCO M. Thermal 982 9.380

2004 ANTILHUE TG (*) Thermal 0 160

2004 ANTILHUE TG Thermal 820 710

2004 HORCONES TG (*) Thermal 0 12.023

2004 HORCONES TG Thermal 944 56

2004 ITATA Thermal 0 319

2004 LICANTEN Thermal 0 21.412

2004 P.VALDIVIA Thermal 0 153.204

2004 RALCO Reservoir 0 1.332.259

Total SIC Energy Generation of 2004 MWh 36.113.187

Latest 20% of Capacity additions Generation MWh 7.523.475

Total Emiission of latest 20% TCO2e 2.723.889

EF_BM TCO2/GW 362

(*) Commisioning tests  

App 5.5  Project Activity Sustainable Development MVP

App 5.5.1  Monitoring Sustainable Development

The MVP compares the project’s actual environmental and development performance as measured by the

indicators below with the set target values and determine whether the targets have been reached. The

following local environmental benefits have been identified from the Lican Hydroelectric Plant (see

Lican Hydroelectric Plant EIA from SEA’s official website www.sea.gob.cl for more details).

  The project will contribute with clean renewable energy for the SIC Grid of Chile, displacing

thermal generation

Page 60: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 60/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 60 

The direct social and development impact of the project are as follows (see Lican Hydroelectric Plant

DIA from SEA’s official website www.sea.gob.cl for more details).

  Job creation during the construction period and also during the operation

  Economic activity during the construction period and also during all of its lifetime.

App 5.5.2  Monitoring, Recording and Reporting

For project operator shall monitor and record the environmental, social and developmental impacts

identified for the Project.

App 5.6  Management and Operational Systems MVP

App 5.6.1  Allocation of Project Management Responsibilities

The management and operation of the project, related to CDM activities, is part of the Project Operator’sresponsibilities. Ensuring the environmental credibility of the project through accurate and systematic

monitoring of the project’s implementation and operation for the purpose of achieving trustworthy ERs is

the key responsibility and accountability of the sponsor as far as this MVP is concerned.

App 5.6.2  Management and Operational Systems

  Data handling

The establishment of a transparent system for the collection, computation and storage of data, including

adequate record keeping and data monitoring systems. The Project Operator shall develop and implement

a protocol that provides for these critical functions and processes, which must be fit for independentauditing.

  Quality assurance

The Project Operator must designate a competent manager who will be in charge of and accountable for 

the generation of ERs including monitoring, record keeping, computation of ERs, audits and verification.

He or she will officially sign-off on all GHG Emission worksheets. Proper management processes and

systems records must be kept by the Project Operator, as the auditors will request copies of such records

to judge compliance with the required management systems.

  Reporting

The Project Operator will report regularly to the ERs Buyer(s) as well as to Chilean authorities as

required by them.

  Training:

It is the responsibility of the Project Operator to ensure that the required capacity and internal training is

made available to its operational staff to enable them to undertake the tasks required by this MVP. Initial

staff training must be provided before the project starts operating and generating ERs.

Page 61: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 61/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 61 

App 5.7  Auditing and Verification Procedures

App 5.7.1 

Audit and Verification RegimeThe Project Activity must be submitted to third party validation and verification, which is conducted by

independent firms specialized in environmental auditing services (auditors, validators, verifiers,

certifiers). The verification system for the Project Activity consists of these four activities:

  Validation of project design

The Project Activity must undergo a CDM validation of the project’s design, baseline and MVP against

CDM requirements and modalities. Validated MVP for a project must be followed by the Project

Operator.

  Verification of the Project

The Project Activity will a periodic verification process for the acceptance of emission reductions

delivered by it. To prevent conflicts of interest, verification must not be conducted by the same firm and

individuals that have provided validation services for the project.

The purpose of the periodic verification process is threefold:

  Ensure that the project has been implemented as planned, that the monitoring system is in place

and that the project is ready to generate and record GHG emission reductions.

  Approve adjustments and amendments to the MVP that may have become necessary during the

detailed design and construction of the project.

  Assist complying obligations and clear the way for project commissioning and generation of high

quality ERs.

  Periodic verification of emission reductions

The Project Activity must undergo periodic audits and verification of emission reductions. This is a

CDM requirement and the basis for issuance of Certified Emission Reductions (CERs). Verification must

 be arranged and conducted at annual or longer intervals as appropriate for the Project Developer.

Verification concludes with a formal verification report. The report may include a statement that may

allow the renewal of the project’s crediting period in line with applicable CDM rules and modalities.

The purpose of periodic audits and verification is to confirm that:

  The project has achieved the ERs for the verification period in compliance with the methodology

laid down in this PDD.

  The claimed ERs are real and additional to any that would have occurred in the baseline scenario

as interpreted and developed in the Baseline Study and this MVP.

  The operation of the project continues to be in compliance with all Kyoto Protocol, host country

requirements and modalities for CDM projects, and the ERs buyer(s).

  The project maintains a high quality monitoring systems consistent with the MVP.

Page 62: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 62/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 62 

  Certification of emission reductions

After a successfully completed verification process and the related verification report provide the basis

for the issuance by the UNFCCC. The issuance certificate is a legally binding statement which confirmsthe (successful) verification report’s conclusion that Project has achieved the stated quantity of ERs in

compliance with all relevant criteria and requirements.

  Auditing Criteria and Needs

Verification includes an audit of the project’s output information and data and management systems on

the basis of the following established criteria: Completeness; accuracy; coverage and risk management

controls.

The auditor will produce an audit report and verification report, which summarizes the audit findings.

The draft verification report will state the number of ERs achieved by the project and will point to areasof possible non-compliance if warranted. The report will also include conclusions on data quality, the

 projects monitoring and management and operational system, and other areas where corrective action

may be required to come into compliance, improve performance or mitigate risks.

Page 63: Lican- PDD

8/23/2019 Lican- PDD

http://slidepdf.com/reader/full/lican-pdd 63/63

UNFCCC/CCNUCC 

CDM  – Executive Board  Page 63 

Appendix 6: Summary of post registration changes

 Not Applicable

- - - - -