LBB & BUSBAR PROTECTION LBB & BUSBAR PROTECTION LBB & BUSBAR PROTECTION LBB & BUSBAR PROTECTION PREPARED BY PREPARED BY GOPALA KRISHNA PALEPU GOPALA KRISHNA PALEPU [email protected], [email protected], Mobile:9440336984 Mobile:9440336984
Nov 02, 2014
LBB & BUSBAR PROTECTIONLBB & BUSBAR PROTECTIONLBB & BUSBAR PROTECTIONLBB & BUSBAR PROTECTIONPREPARED BYPREPARED BY
GOPALA KRISHNA PALEPUGOPALA KRISHNA [email protected], [email protected],
Mobile:9440336984Mobile:9440336984
NOMINICLATURENOMINICLATURE
LBB : Local Breaker Backup Relay.
BFR : Breaker Failure Relay.BFR : Breaker Failure Relay.
CBF : Circuit Breaker Failure Relay.
ANSI Code : 50Z or 50BF.
This is Current Operated Relay.
BASICS OF LBB/BFR PROTECTIONLOCALLOCAL BREAKERBREAKER BACKUPBACKUP PROTECTIONPROTECTION
A PROTECTION WHICH IS DESIGNED TO CLEAR A SYSTEMFAULTY BY INITIATING TRIPPING OTHER CIRCUIT BREAKER(S) INTHE CASE OF FAILURE TO TRIP OF THE APPROPRIATE CIRCUITBREAKER.
IN MODERN NETWORKS THE CRITICAL FAULT CLEARINGTIME MAY BE LESS THAN 200ms. HENCE, IF THE FAULT IS NOTTIME MAY BE LESS THAN 200ms. HENCE, IF THE FAULT IS NOTCLEARED DUE TO FAILURE OF THE PRIMARY PROTECTIVE RELAYSOR THEIR ASSOCIATED CIRCUIT BREAKER, A FAST ACTING BACK-UP PROTECTIVE RELAY MUST CLEAR THE FAULT.
THERE ARE TWO BASIC FORMS.
REMOTE BACK-UP.
LOCAL BACK-UP.
REMOTEREMOTE BACKBACK--UPUPPROVIDES BACK-UP PROTECTION FOR THE BOTH THEPROVIDES BACK-UP PROTECTION FOR THE BOTH THE
RELAYS (MAIN-1 & MAIN-2) AND BREAKERS AT REMOTESUBSTATION.
LOCALLOCAL BACKBACK--UPUPLOCAL BACK-UP PROTECTION CAN BE DEVIDED INTO TWOCATAGORIES.RELAY BACK-UPBREAKER BACK-UP
RELAY BACKRELAY BACK--UPUP
DUPLICATE PRIMARY PROTECTION. i.e ONE IS NON SWITCHED
DISTANCE PROTECTION AND ANOTHER IS SWITCHED DISTANCE
SCHEME OR OTHER WISE BOTH SCHEMES CHARECTERSTICS ARE
DIFFERENT (QUADRALATERAL, MHO CIRCULAR, TAMOTO & OPTICAL )
OR DIFFERENT MANUFACTURERS(ABB, ALSTOM, SIEMENS, EASUN
REYROLL, SEL, GE, NXT PHASE OR BASLER) OR DIFFERENT METHODS (i.e
ELECTROMECHANICAL, STATIC, NUMERICAL{MICROPROCESSOR &DSP}).ELECTROMECHANICAL, STATIC, NUMERICAL{MICROPROCESSOR &DSP}).
IF MAIN-1 & MAIN-2 ARE NUMERICAL RELAYS BOTH SHOULD BE
SEPARATE CHARECTERESTICS AND SEPARATE MODELS AND ALL
FEATURES SHOULD BE AVAILABLE IN BOTH SCHEMES AND BOTH
RELAYS SHOULD BE 100% REDENDENCY IN ALL ASPECTS.
TO INCREASE THE SECURITY, THE CIRCUIT BREAKER HAS TWO
TRIP COILS, ONE IS CONNECTED TO MAIN-1 PROTECTION AND ANOTHER
IS CONNECTED TO MAIN-2 PROTECTION.
BREAKER BACKBREAKER BACK--UPUP
BECAUSE OF THE HIGH COST OF HIGH VOLTAGE CIRCUIT
BREAKERS, IT IS NOT FEASIBLE TO DUPLICATE THEM.
IN CASE OF A BREAKER FAILURE THE OTHER CIRCUIT BREAKERS
CONNECTED TO THE SAME BUS AS THE FAULTED BREAKER MUST THERE
FORE BE TRIPPED.
LBB/BFR FLOW CHART
MAIN PROTECTIONOPERATED
YESTRIP MAIN
BREAKER
FAULT CLEARED
YESRESET
BREAKER FAILURE
SCHEME
YES INITIATEBFR
WAIT FOR FAULT
CLEARENCE
AND
NO
TRIPBACK-UP/Adjacent
BREAKERS
The Breaker Failure Protection (LBB/BFR) can operate single-stage/two-stage.
RETRIP
stage.When used as single-stage protection, the Bus trip command is given tothe adjacent Circuit Breakers if the protected feeder Breaker fails.When used as two-stage protection, the first stage can be used torepeat the trip command to the relevant feeder Breaker, normally on adifferent trip coil, if the initial trip command from the feeder protectionis not successful. The second stage will result in a Bus trip to theadjacent Breakers, if the command of the first stage is not successful.
LBB/BFR TIME CO-ORDINATION CHART
FAULT OCCURS
NORMAL
NORMAL CLEARING TIME
NORMAL
CLEARING
BREAKER
INTURUPTING TIME
PROTECTIVE RELAY
FOR EX: DISTANCE RELAY
BREAKER FAILURE RELAY START
MARGIN
RESETTING TIME OF THE
CURRENT MEASURING UNITS
SET TIME OF THE TIME MEASURING UNIT TRIPPING
RELAY
TIME
BACK-UP BREAKER
INTERUPTING TIME
MARGIN
~30ms ~60ms <12ms
INOPERATIVE
BREAKER
BREAKER FAILURE RELAY START
TOTAL CLEARING TIME OF THE BREAKER FAILURE RELAY
MAXIMUM FAULT CLEARING TIME BEFORE SYSTEM INSTABILITY
LBB/BFR LOGIC
PHASE L1
PHASE L2/E
PHASE L3
CURRENT INPUTS
~
|||
A/DCONVERTER
&I > ISET
I > ISET
PHASE CURRENT SET POINT
&> 1
LED
(PHASE START)
ALARM RELAY
(PHASE START)
ALARM RELAY|||EARTH CURRENT SET POINT
CIRCUIT BREAKER FAILURE INITIATE
BINARY INPUT
OUT PUT OF DISTANCE RELAY ORSHORT CIRCUIT CURRENT RELAY
TIMING/OUTPUT STAGE
TIME STAGE T1
& LED
TRIP T1 RELAY
LED
(EARTH START)
ALARM RELAY
(EARTH START)
0 1
0 1
TIME STAGE T2
TIME STAGE T2SWITCHED OFF
&
&
&
O
> 1
LEDCB FAILURE
INITIATE
LED
TRIP T2RELAY
ALARM T1
RELAY
LED
CBIP Guidelines on ProtectionLBB/ BFR PROTECTION COMMENTSLBB/ BFR PROTECTION COMMENTS
In the event of any CB fails to trip on receipt ofcommand from Protection relays, all CBs connected to
GENERALGENERAL
command from Protection relays, all CBs connected tothe Bus section to which the faulty circuit Breaker isconnected are required to be tripped with minimumpossibly delay through LBB Protection.
This Protection also Provides coverage for faultsbetween CB and CT which are not cleared by otherprotections.protections.
CBIP Guidelines on ProtectionRECOMMENDATIONS FOR LBB/BFR PROTECTIONRECOMMENDATIONS FOR LBB/BFR PROTECTION
i) In all new 400KV and 220KV Substations as well asGenerating Stations Switch Yard, it must beprovided for each Circuit Breaker.provided for each Circuit Breaker.
ii) For existing Switch Yards, it is considered a must at400KV level and also 220KV Switch Yards havingmultiple feed.
iii) In case of radially fed 220KV Substations, Provisioniii) In case of radially fed 220KV Substations, Provisionof LBB Protection is desirable but not essential.
CBIP Guidelines on ProtectionLBB/BFR REQUIREMENTSLBB/BFR REQUIREMENTS
i) Have Short Operation and Drop off times.
ii) Have 3 Phase Current elements with facility forPhase wise initiation.
iii)have current setting range such that these can be setminimum 200mA for Line and 50mA for generators(for 1A CT for secondary).
iv) Have one common associated timer with adjustablesetting.
REQUIREMENTS OF CIRCUIT BREAKERSREQUIREMENTS OF CIRCUIT BREAKERSREQUIREMENTS OF CIRCUIT BREAKERSREQUIREMENTS OF CIRCUIT BREAKERS
� Operating Time
� Breaking Capacity
� Stuck Breaker Probability
� Operating Sequence / Duty cycle
CBIP Guidelines on ProtectionLBB/BFR OPERATIONLBB/BFR OPERATION
� The Breaker Failure Protection (LBB/BFR) canoperate single-stage/two-stage.
�When used as single-stage protection, the Bus trip�When used as single-stage protection, the Bus tripcommand is given to the adjacent Circuit Breakers ifthe protected feeder Breaker fails.
�When used as two-stage protection, the first stagecan be used to repeat the trip command to therelevant feeder Breaker, normally on a different tripcoil, if the initial trip command from the feedercoil, if the initial trip command from the feederprotection is not successful. The second stage willresult in a Bus trip to the adjacent Breakers, if thecommand of the first stage is not successful. (This isMore recommended)
CBIP Guidelines on ProtectionLBB/BFR SPECIAL COMMENTSLBB/BFR SPECIAL COMMENTS
(i) The relay is separate for each breaker and is to beconnected in the secondary circuit of the CTsassociated with that particular breaker.
(ii)For line breakers, direct tripping of remote endbreaker(s) should be arranged on operation of LBBprotection.
For transformer breakers, direct tripping ofbreaker(s) on the other side of the transformershould be arranged on operation of LBB protectionshould be arranged on operation of LBB protection
(iii) For lines employing single phase auto reclosing,the LBB relays should be started on a single phasebasis from the trip relays.
CBIP Guidelines on ProtectionLBB/BFR SPECIAL COMMENTSLBB/BFR SPECIAL COMMENTS
(iv) The CT sec core may be separate core, if available.
Other wise it shall be Clubbed (in series) with Main-1
or Main-2 protection.
(v)It is considered a good practice to have DC circuits ofGr.A and Gr. B protections and relay independent.
(vi) LBB cannot operate without proper initiation. It isgood practice to provide redundant trip output andbreaker fail input where other forms of redundancydoes not exist.does not exist.
(vii) Separation should be maintained betweenprotective relay and CB trip coil DC circuit so thatshort circuit or blown fuse in the CB circuit will notprevent the protective relay from energizing the LBBscheme.
CBIP Guidelines on ProtectionLBB/BFR SPECIAL COMMENTSLBB/BFR SPECIAL COMMENTS
(viii) In addition to other fault sensing relays the LBBrelay should be initiated by Bus bar protection, sincefailure of CB to clear a bus fault would result in theloss of entire station if BFP relay is not initiatedloss of entire station if BFP relay is not initiated
(ix) Tripping logic of the bus bar protection schemeshall be used for LBB protection also.
(x) For breaker-fail relaying for low energy faults likebuchholz operation, special considerations may haveto be given to ensure proper scheme operation byto be given to ensure proper scheme operation byusing C.B. contact logic in addition to currentdetectors.
CBIP Guidelines on ProtectionLBB/BFR SETTING CRITERIALBB/BFR SETTING CRITERIA
(i) Current level detectors should be set as sensitive asthe main protections
A general setting of 0.2 A is commonly practiced forLines and Transformers
(ii) Timer setting should be set considering breakerinterrupting time, current detector reset time and amargin. Generally a timer setting of 200 ms has beenfound to be adequate.found to be adequate.
LBB/BFR connections during STATIC RelaysLBB/BFR connections during STATIC Relays
CT CORE-5: Main-1 Distance Relay & Fault Locator are inseries.
CT CORE-4: Main-2 / Backup Relay, LBB/BFR & DisturbanceRecorder are in series.
CORE-5
IN CASE OF LINE
1-5
2C
B
FAULTFAULTLOCALOCA--TORTOR
21 L1 /21 L1 /87 L187 L1
forforLineLine
P2
P1
CORE-4
IN CASE OF LINE
LineLine
LBBLBBBFRBFR
21 L2 /21 L2 /87 L287 L2ForForLineLine
DISTDISTRECREC
P1
P2
P1
LBB/BFR connections during NUMERICAL RelaysLBB/BFR connections during NUMERICAL Relays
1. Fault Locator is inbuilt feature in both Distance Schemes.2. Disturbance Recorder is also inbuilt feature in both Distance
Schemes.3. Most of the Utilities are not accepting the LBB is Inbuilt feature of
Main-1 or Main-2/ BU Protection. But Accepting Inbuilt feature ofBUSBAR Protection.BUSBAR Protection.
CORE-5
P2
1-5
2C
B
21 L1 /21 L1 /
87 L187 L1CORE-5
CORE-4
P1
P2
P1
forfor
LineLine
LBBLBBBFRBFR
21 L2 /21 L2 /
87 L287 L2
ForFor
LineLine
NEXT DEVELOPMENTNEXT DEVELOPMENT 1. LBB is now Part of BUSBARProtection Relay, ForDistributed Architecture orCentralised Architecture.
2. In case of DistributedArchitecture, CT connections,Binary Input & Output
CORE-5
21 L1 OR
87 L1
1-5
2C
B
P2
P1 Binary Input & OutputConnections are up to BAY /Peripheral Unit and BU/PU toBUSBAR is Fiber Optic Link
3. In case of CentralisedArchitecture I, V, BI & BO toCentral Unit.
CORE-4
CORE-2
C
E
ABB Network Partner AG REL531
21 L2 OR
87 L2
50 Z + 87BBLBB IS INBUILTCENTRALISED
P1
P2
P1
P2
CORE-1 FIBEROPTIC
OR
C
E
50Z +87BBCENTRAL UNITLBB IS INBUILT
BUSBAR
ABB Network Partner AG
CENTRALISED
BUSBAR
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
ABB Network Partner AG REL 316*4
C
E
BU/PU
P1
P2
P1
NEXT DEVELOPMENTNEXT DEVELOPMENT
1. ABB is developed the New Concept i.e2. CT connections are up to Main-1 Protection & Main-1 to Bay Unit and
BAY UNIT to BUSBAR is Fiber Optic Link. (Numerical DistributedArchitecture) and
3. Similarly for Main-2 Protection.4. The CB and Isolator Status Given to Bay Unit.4. The CB and Isolator Status Given to Bay Unit.
CORE-5
21 L1 / 87L1
FO FO
BAY UNIT CENTRAL UNIT
1-5
2C
B
P2
P1
CORE-4
21 L2 / 87L2
FO FO
BAY UNIT CENTRAL UNIT
P2
P1
CORE-1
NEXT DEVELOPMENT FOR REDUNDANT BUSBAR PROTECTION FOR DISTRIBUTED OR CENTRALISED ARCHITECTURENEXT DEVELOPMENT FOR REDUNDANT BUSBAR PROTECTION FOR DISTRIBUTED OR CENTRALISED ARCHITECTURE
1-5
2C
B
P2
CORE-1
CORE-2
OROR
P1
P2
P1
P2
CORE-2 FIBEROPTIC
CORE-1
C
E
50Z +87BBCENTRAL UNITLBB IS INBUILT
BUSBAR
ABB Network Partner AG
BU/PU
FIBEROPTIC
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
ABB Network Partner AG REL 316*4
C
E
P2
P1
P2
P1
RECENT DEVELOPMENTRECENT DEVELOPMENT
1. New Relay Introduced i.e Breaker Management Relay.2. In this LBB (50Z) + A/R (79) + Check Syn (25)+ O/C&E/F
(67/51/50) are Inbuilt features.3. This is connected to Centralised Unit Through Fiber Optic or CT
Connections are in Series to BUSBAR.
CORE-2P2
P1
BMR
FO
1-5
2C
B
CORE-1P2
P1
BMR
FO
INITIATION TO LBB / BFRINITIATION TO LBB / BFR
1. 21L1 & 21L2 Operation will operate 1-Ph Trip Relays (186-R,Y,B & 286-R,Y,B). These Relays will
energise the trip coils of the Circuit Breaker and initiate the LBB Relay.
2. 87T1 & 87T2 & Other Relays will operate Master Trip Relays / High Speed Trip Relays (86Gr-A,
86Gr-B). These Relays will energise the trip coils of the Circuit Breaker and initiate the LBB Relay.
3. BUSBAR Relays will operate Master Trip Relays / High Speed Trip Relays (96-BB). These Relays will
energise the trip coils of the Circuit Breaker and initiate the LBB Relay.
4. Incase of Transfer Bus System or Bypass Isolator System initiation of LBB is selection of Normal /4. Incase of Transfer Bus System or Bypass Isolator System initiation of LBB is selection of Normal /
Transfer switch Position.
LBB / BFR Tripping LogicLBB / BFR Tripping Logic
When LBB Operated following Output Operations will Taken Place.� To Main-1 Disturbance Recorder.
� To Main-2 Disturbance Recorder..
� To 86 Gr-A Bi-Stable relay.
� To 86 Gr-B Bi-Stable relay.� To 86 Gr-B Bi-Stable relay.
� To 87BUSBAR Output Relays ( 96BB1 and/or 96BB2).
� Direct Trip Ch-1 to Other end.
� Direct Trip Ch-2 to Other end.
� To Annunciation.
� To SER / RTU.
� Incase of ONE & HALF CB System, Central/ Tie LBB Having Duplicate Tripping Logics for
2 sides of Main Bays.
MAIN-1 (21L1) PROTECTION OPERATED
21 MAIN-1
TO LBBTO TC-1
+VE -VE
R PHASE
186 R1
186 R2
TO LBBTO TC-1
TO TC-2
TO LBBTO TC-1
TO TC-2
TO TC-1
TO TC-2
TO TC-1
TO TC-2
Y PHASE
186 Y1
186 Y2
BINARY OUTPUT
TO TC-2
TO LBBTO TC-1
TO TC-2TO TC-1
TO TC-2
B PHASE
186 B1
186 B2
MAIN-2 (21L2) PROTECTION OPERATED
21 MAIN-2
TO LBBTO TC-1
+VE -VE
R PHASE
286 R1
286 R2
TO LBBTO TC-1
TO TC-2
TO LBBTO TC-1
TO TC-2
TO TC-1
TO TC-2
TO TC-1
TO TC-2
Y PHASE
286 Y1
286 Y2
BINARY OUTPUT
TO TC-2
TO LBBTO TC-1
TO TC-2TO TC-1
TO TC-2
B PHASE
286 B1
286 B2
86 GA (MASTER TRIP RELAY) OPERATION
21L1:MAIN-1
+VE
-VERESET
OPERATED
PB
TO ANN
OPERATED
TO CL I/L
TO LBB
TO TC-1
TO SER
OTHER PROTECTIONS
87T1:MAIN-1
TO TC-2
TO M1 DR
TO M2 DR
86 GA MASTER TRIP RELAY
86 GB (MASTER TRIP RELAY) OPERATION
21L2:MAIN-2
+VE
-VERESET
OPERATED
PB
TO ANN
OPERATED
TO CL I/L
TO LBB
TO TC-1
TO SER
OTHER PROTECTIONS
87T2:MAIN-2
TO TC-2
TO M1 DR
TO M2 DR
86 GB MASTER TRIP RELAY
96 BB (MASTER TRIP RELAY) OPERATION
87 BUSBAR
TO D/T-1
+VE
-VERESET
OPERATED
PB
FO
R S
ING
LE
BU
S S
YS
TE
M,
ON
E &
HA
LF
CB
SY
ST
EM
,D
OU
BL
E C
B &
DO
UB
LE
BU
S S
YS
TE
M
& R
ING
MA
IN B
US
SY
TE
M
TO D/T-1
TO CL I/L
TO LBB
TO TC-1
TO D/T-2
TO ANNUN
TO SER
FROM LBB
FO
R S
ING
LE
BU
S S
YS
TE
M,
ON
E &
HA
LF
CB
SY
ST
EM
,D
OU
BL
E C
B &
DO
UB
LE
BU
S S
YS
TE
M
& R
ING
MA
IN B
US
SY
TE
M
TO TC-2
TO M1 DR
TO M2 DR
96 BB MASTER TRIP RELAY
FO
R S
ING
LE
BU
S S
YS
TE
M,
ON
E &
HA
LF
CB
SY
ST
EM
,D
OU
BL
E C
B &
DO
UB
LE
BU
S S
YS
TE
M
& R
ING
MA
IN B
US
SY
TE
M
LBB Operation & Output(SINGLE BUS / DOUBLE BUS / QUAD BUS SYSTEM)
INITIATION
186 R186 Y
186 B 50X
LBB / BFR
TIMER
186 B
286 R286 Y
286 B
86 GR-A
86 GR-B
96 BB
+VE
TO D/T CH-1
TO D/T CH-2
TO ANNUN
TO MAIN1 DR
TO MAIN2 DR
TO SERTO 86 GR-A
-VE50X
TO 86 GR-A
TO 86 GR-B
TO BUSBAR
TO 96 BB
LBB Operation & Output(TRANSFER BUS / BYPASS ISO SYSTEM)
INITIATIONINITIATION
186 R186 Y
186 B 50X
LBB / BFR
TIMER
186 B
286 R
286 Y
286 B
86 GR-A
86 GR-B
96 BB
+VE
TO D/T CH-1
TO D/T CH-2
TO ANNUN
TO MAIN1 DR
TO MAIN2 DR
TO SERTO 86 GR-A
-VE50X
+VE
N TN T..
TO 86 GR-A
TO 86 GR-B
TO BUSBAR
+VE . In case of Feeder bay / Transformer Bay
+VE
N TN T.In case of Transfer Bay for Transfer Bus System initiation to that LBB
In case of Bus Coupler Bay for Bypass ISO System initiation to that LBB+VE
N TN T.
LBB Operation & Output(ONE&HALF CB SYSTEM)
INITIATIONINITIATION
186 R186 Y
186 B +VE -VE50X1
LBB / BFR
TIMER
186 B
286 R286 Y
286 B
86 GR-A
86 GR-B
96 BB
+VE
TO D/T CH-1
TO D/T CH-2
TO ANNUN
TO MAIN1 DR
TO MAIN2 DR
TO SERTO 86 GR-A
-VE
TO D/T CH-1
TO D/T CH-2
-VE50X2
TO 86 GR-B
TO BUSBAR
TO D/T CH-2
TO ANNUN
TO MAIN1 DR
TO MAIN2 DR
TO SERTO 86 GR-A
TO 86 GR-B
TO BUSBAR
IN THIS 2 NOS TRIPPING AUXILIARY RELAYSPROVIDED FOR MAIN CB & TIE CB.IN CASE OF TIE LBB, ONE FOR BUS-1 MAIN
CB & OTHER FOR BUS-2 MAIN CB.
LBB/BFR PROTECTION
2-52CB 3-52CBBUS-1 BUS-2
LINE1 AT/F-1
1-52CB
50Z 50Z
� LBB/BFR IS LOCAL BREAKER BACKUP PROTECTION/ BREAKER FAILURE RELAY.� 1No LBB RELAY IS PROVIDED FOR EACH BREAKER.� LBB IS CURRENT OPERATED RELAY.� LBB RELAY IS ENERGISED WHEN MASTER TRIP RELAY(86-A OR/AND 86-B OR/AND 96)
OPERATES OR SINGLE PHASE TRIP RELAYS OPERATES AND GIVEN SIGNAL TO BREAKER FOR TRIP.
50ZT
BREAKER FOR TRIP. � LBB RELAY TIME DELAY IS PROVIDED.� LBB RELAY OPERATES WHEN THE BREAKER IS UNDER TROUBLE/ FAILS TO OPERATE. � AFTER ENERGISED THE LBB RELAY AND TIME DELAY COMPLETES, EVEN CURRENT IS
THERE THIS THINKS BREAKER FAIL TO OPERATE AND GIVEN SIGNAL AS PER SCHEME DESCRIBED NEXT PRESENTATION.
� NEW CONCEPT: Normally the CT connections for LBB/BFR relay is in series with Main-2 Protection.In case of Numerical Distributed LBB/BFR and Centralized Bus-Bar System, the CT connections forBus-Bar are terminated at LBB/BFR and Centralized Bus-Bar is interconnected by Fiber-Optic cable.
1-52 CB LBB/BFR OPERATION
86
86
--AA
BB
ABBABBREL521REL521MAINMAIN--11
ABBABB
86
86
--AA
BB
86
86
--BB
ABBABBREL316REL316MAINMAIN--22
86
86
--BB
BUSBAR-1
PROTECTION (96-BB )
OPTD
AND BUSBAR-1
ISOLATED
DIRECT TRIP 1&2
VIA CARRIER TO
OTHER END
50Z
TO 96-ZT TRIP RELAY
OF TIE CB(2-52CB)
BUS-1 BUS-2
1-52CB 3-52CB2-52CB
TC-1 TC-2
ISOLATED
TC-1TC-2
Breaker Failure Relay of the Main Circuit Breaker Trips the 1. Connected Bus Bar Protection, 2. Tie Circuit Breaker 96/50Z Relay &
3. Remote End Circuit Breaker through Carrier Tripping.
2-52 CB LBB/BFR OPERATION
ABBABBREL521REL521MAINMAIN--11
86
86
--AA
ABBABBRET521RET521MAINMAIN--11
ABBABBREL316REL316MAINMAIN--22 8
68
6--BB
ABBABBRET316RET316MAINMAIN--22
TO 96-BB TRIP RELAY
OF LINE CB(1-52CB)
DIRECT TRIP 1&2
VIA CARRIER
TO OTHER END
TO 96-BB TRIP RELAY
OF AT/F(ICT) CB (3-52CB)
INTER TRIP TO
LVCB & TBCCB
50ZT
BUS-1 BUS-2
1-52CB 3-52CB2-52CB
TC-1 TC-2
OF LINE CB(1-52CB) OF AT/F(ICT) CB (3-52CB)
Breaker Failure Relay of the Tie Circuit Breaker Trips the 1. Both Sides Main Circuit Breakers and 2. Remote End Circuit Breakers through carrier Tripping
( In case of Transformer, LV Circuit Breaker)
3-52 CB LBB/BFR OPERATION
86
86
--AA
BB
ABBABBRET521RET521MAINMAIN--11
ABBABB
86
86
--AA
BB
86
86
--BB
ABBABBRET316RET316MAINMAIN--22
86
86
--BB
BUSBAR-2 (96 BB)
PROTECTION OPTD
AND BUSBAR-2
ISOLATED
INTER TRIP TO
LV CB & TBC CB
50Z
TO 96-ZT TRIP RELAY
OF TIE CB(2-52CB)
BUS-1 BUS-2
1-52CB 3-52CB2-52CB
TC-1 TC-2 TC-1TC-2
ISOLATED
Breaker Failure Relay of the Main Circuit Breaker Trips the 1. Connected Bus Bar Protection 2. Tie Circuit Breaker 96/50Z Relay &
3. Remote End Circuit Breaker ( In case of ICT, LV CB)
DISTRIBUTED LBB & NUMERICAL CENTRALISED BUS BAR PROTECTION
BUS-1
1-5
2
4-5
2
7-5
2
10
-52
13
-52
OR OR
(REB 500) ABB (7 SS 52) SIEMENS (MICOM P740) AREVA
12
-52
45
-52
78
-52
10
11
-52
13
14
-52
BUS-2
3-5
2
6-5
2
9-5
2
12
-52
15
-52
OR OR
LBB/BFR PROTECTION
1-52CB 2-52CBBUS-1 BUS-2
LINE1
50Z 50Z
� THE ABOVE SYSTEM IS DOUBLE BUS AND DOUBLE BREAKER SYSTEM.
� THE ABOVE CONFIGUARATION IS UTILISED IN 765KV SYSTEM.
� IN THIS SYSTEM EACH CIRCUIT BREAKER HAVING SEPARATE LBB.
� BREAKER FAILURE RELAY OF THE 1-52 CIRCUIT BREAKER TRIPS THE
CONNECTED BUS, 2-52 CIRCUIT BREAKER, AND REMOTE END CIRCUIT
BREAKER.
� SIMILARLY BREAKER FAILURE RELAY OF THE 2-52 CIRCUIT BREAKER
TRIPS THE CONNECTED BUS, 1-52 CIRCUIT BREAKER, AND REMOTE END
CIRCUIT BREAKER.
� INCASE OF TRANSFORMER THE REMOTE END BREAKER MEANS IV
CIRCUIT BREAKER.
DISTRIBUTED LBB & NUMERICAL CENTRALISED BUS BAR PROTECTION
BUS-1
1-5
2
3-5
2
5-5
2
-52
-52
OR
(REB 500) ABB (7 SS 52) SIEMENS
1 3 5 7-
9-
BUS-2
2-5
2
4-5
2
6-5
2
8-5
2
10
-52
OR
NEED/NECESSICITYNEED/NECESSICITY
� BUSBAR Protection is provided for high speed sensitive
clearance of BUSBAR faults by tripping all the Circuit
Breakers connected to faulty bus.
� A BUSBAR Protection is a Protection to protect BUSBARs at� A BUSBAR Protection is a Protection to protect BUSBARs at
Short-Circuits and Earth-faults. In the “childhood” of electricity
no separate Protection was used for the BUSBARs. Nearby
line protection were used as back-up for BUSBAR Protection.
� In its absence fault clearance takes place in zone-II of
Distance Relay by remote end tripping.
� With increasing Short-Circuit Power in the network separate
BUSBAR Protections have to be installed to limit the damage
at primary faults. A delayed tripping for BUSBAR faults can
also lead to instability in nearby generators and total system
collapse.
NEED/NECESSICITYNEED/NECESSICITY
� The earliest form of BUS Protection was that provided by
the relays of circuits (i.e. Lines , Transformers, Reactors &
Capacitor Banks) over which current was supplied to a
BUS. In other words the BUS was included within the back-
up zone of these relays. This method was relatively slowup zone of these relays. This method was relatively slow
speed, and loads tapped from the lines would be interrupted
unnecessarily, but it was otherwise effective. Some
preferred this method to one in which the inadvertent
operation of a single relay would trip all the connections to
the BUS.
� This Means Slow And Unselective Tripping And Wide
Spread Black Out.
EFFECT OF DELAYED CLEARENCEEFFECT OF DELAYED CLEARENCE
� Greater damage at fault point.
� Indirect shock to connected equipments like shafts of Generatorand windings of Transformer.
PRINCIPLE OF OPERATIONPRINCIPLE OF OPERATION
� The Principle of Operation of Bus bar protection is Kirchoff’s
Current Law. i.e. Sum of the Currents Entering in to the Node isCurrent Law. i.e. Sum of the Currents Entering in to the Node isequal to Sum of the Currents Leaving the node. Here Node Means
BUSBAR.
CAUSES OF BUS ZONE FAULTSCAUSES OF BUS ZONE FAULTS
� Deterioration of Insulating Material.
� Flashover of insulators due to lightning or
System Over Voltages.System Over Voltages.
� Wrong application of /or failure to remove
temporary earth connections.
� Short circuits caused by birds, monkeys,
vermin and the like.vermin and the like.
� Short circuits caused by construction
machinery.
BASICS OF BUS BAR PROTECTIONBASIC THEORY
EXTERNAL FAULT
KIRCHOFF’s CURENT LAW STATES THAT THE SUM OF THE CURRENTS ENTERING A GIVEN NODE MUST BE EQUAL TO THE CURRENTS LEAVING THAT NODE
INTERNAL FAULTIF
I6
I4
I2
I5
I3
I1
I6
I4
I2
I5
I3
I1
IF
IF
IF= I6= I1+I2+I3+I4+I5 IF= I1+I2+I3+I4+I5+I6
RECOMMENDATIONSRECOMMENDATIONS
� Must have as short tripping time as possible.
� Must be able to detect internal faults.
� Must be absolutely stable at external faults. External faults are
much more common than internal faults. The magnitude ofmuch more common than internal faults. The magnitude of
external faults can be equal to the stations maximum breaking
capacity, while the function currents can go down to
approximately 2% of the same. The stability factor there fore
needs to be at least 50 times i.e. 20. CT-saturation at external
faults must not lead to mal-operation of the BUSBAR
Protection.
� Must be able to detect and trip only the faulty part of the
BUSBAR system.
� Must be secure against mal-operation due to auxiliary contact
failure, human mistakes and faults in the secondary circuits
etc.
TYPES OF BUSBAR PROTECTION SCHEMESTYPES OF BUSBAR PROTECTION SCHEMES
�� HIGHHIGH IMPEDENCEIMPEDENCE BUSBARBUSBAR PROTECTIONPROTECTION:
High Impedance Differential Protection has traditionally been provided by
Electromechanical Relays and associated stabilising resistances connected
across the Current Transformer secondary bus wires of the Protected zone,
i.e. the Measuring Circuit comprises a High impedance stabilising Resistori.e. the Measuring Circuit comprises a High impedance stabilising Resistor
(Metrosil) connected across the circulating current arrangement of all the
CT’s in parallel. The resulting Scheme is economical, simple in concept and
easily extendable to cover additional circuits. It has an added advantage that
low fault current settings can be achieved whilst retaining through fault
stability. Application of this type of scheme can however sometimes be
limited by the need for CTs on each circuit to be of the same ratio and by the
knee point voltage required to achieve fast operating times. The Value ofknee point voltage required to achieve fast operating times. The Value of
Stabilising Resistor chosen such that the voltage drop across the relay circuit
is insufficient to operate the relay for faults outside the protection zone.
The High-impedance protection scheme, on the other hand, is a good
Solution for single BUSBAR arrangements, 1 ½ breaker systems or ring
BUSBARS, providing that appropriate dedicated CT cores are available For
this use alone.
TYPES OF BUSBAR PROTECTION SCHEMESTYPES OF BUSBAR PROTECTION SCHEMES
�� MEDIUM/MODERATE IMPEDENCE BUSBAR PROTNMEDIUM/MODERATE IMPEDENCE BUSBAR PROTN:
This is effectively combination of the normal plain
circulating current High-Impedance and Stabilised
percentage biased differential scheme. This relay actspercentage biased differential scheme. This relay acts
as Medium Impedance Protection during internal faults
& but Low Impedance Protection during load and
external faults.
Although heavy through fault currents may produce a
different current that exceeds the differential pick-up
setting, stabilizing current prevents tripping. Thesetting, stabilizing current prevents tripping. The
requirements made on the primary CT’s are
subsequently less stringent than for a simple High-
Impedance Scheme.
LOW IMPEDANCE PROTECTIONLOW IMPEDANCE PROTECTION
�� PHASEPHASE COMPARISIONCOMPARISION BUSBARBUSBAR PROTECTIONPROTECTION:
This operates on the principle that any BUSBAR fault will becharacterised by all current flows towards the protected BUSBARS
and phase coincidence and is checked for positive and negativehalf cycles. In addition the non coincidence is used for as ahalf cycles. In addition the non coincidence is used for as ablocking signal.
However under low fault level conditions, it is possible for someload flow to continue. To prevent this from stabilising the
Protection, a fault load current of Highest rated outgoing circuit isnormally selected i.e. pick-up level is set above the load current.
The differential current can also be included in the phaseThe differential current can also be included in the phasecomparison , there by further improving stability.
The Main advantage of this scheme is that, it is not necessary forthe current transformers on each circuit to be equal ratio. Also thecurrent transformers may be lower output than those required for
High-Impedance Schemes.
LOW IMPEDANCE BUSBAR PROTECTIONLOW IMPEDANCE BUSBAR PROTECTION
�� PERCENTAGEPERCENTAGE BIASEDBIASED DIFFERENTIALDIFFERENTIAL PROTECTIONPROTECTION:
This Protection is known as current comparison with current
restraint, biased or percentage differential relaying. The operatingcurrent is the Phasor sum of all feeder currents and the restraintcurrent is the arithmetic sum. A trip command is given when
operating current is greater than its pickup level and the stabilisingoperating current is greater than its pickup level and the stabilisingfactor the ratio of operating current to restraint current.
in case of CTs ratios differ, the currents have to be balanced byusing interposing CTs (Aux ratio matching CTs). In this load bias
take care for any matching errors.
where as High-Impedance protection the scheme is inherentlystable during CT saturation, in this scheme special measures muststable during CT saturation, in this scheme special measures mustbe taken to ensure the protection remains stable during CT
saturation. In this scheme check feature can be included.
This type incorporates a stabilising resistor to ensure through fault
stability at high fault levels. This can limit the minimum size ofcurrent transformer that will be required to ensure high speed
performance.
VOLTAGE DIFFERENTIAL RELAY WITH LINEAR COUPLERSVOLTAGE DIFFERENTIAL RELAY WITH LINEAR COUPLERS
The problem of CT saturation is eliminated at its source by air-core CTscalled linear couplers. These CTs are like bushing CTs but they have noiron in their core, and the number of secondary turns is much greater.The secondary-excitation characteristic of these CTs is a straight linehaving a slope of about 5 volts per 1000 ampere-turns.
Contrasted with conventional CTs, linear couplers may be operatedContrasted with conventional CTs, linear couplers may be operatedwithout damage with their secondaries open-circuited. In fact, verylittle current can be drawn from the secondary, because so much of theprimary magneto-motive force is consumed in magnetizing the core.
The linear couplers are connected in a series of all CTs & to Voltage-Differential circuit. For normal load or external-fault conditions, the sumof the voltages induced in the secondaries is zero, except for the verysmall effects of manufacturing tolerances, and there is practically nosmall effects of manufacturing tolerances, and there is practically notendency for current to flow in the Differential Relay.
When a BUS fault occurs, the Voltages of the CTs in all the sourcecircuits add to cause current to flow through all the secondaries and thecoil of the Differential Relay. The Differential Relay, necessarily requiringvery little energy to operate, will provide high-speed Protection for arelatively small net voltage in the Differential Circuit.
SUMMATION CTs METHOD SUMMATION CTs METHOD
In practical application of the schemes, Summation CurrentTransformers (one per main set of CTs) are normally used. Thesesummation CTs have a tapped primary to which the three phasesof the Main CTs are connected, the secondary of the summationCTs providing single-phase output.CTs providing single-phase output.
The Advantages of summation CTs are.
1. Single Relay is used for all three phases.
2. A Definite bias is available for all types external faults.
3. Lead burden on Main CTs is less, provided these CTs arelocated Judiciously.
4. Secondary Cabling is reduced.
5. Aux switch requirement in Double BUSBAR arrangement is5. Aux switch requirement in Double BUSBAR arrangement isreduced.
TheThe MainMain DrawbacksDrawbacks areare
1. The setting for Various types of faults is different, needingcareful analysis.
2. Bias effect is less for Phase faults than for Earth faults.
NUMERICAL BUSBAR PROTECTIONNUMERICAL BUSBAR PROTECTION
� In this two Models of BUSBAR Protections are offered.
1. Centralised Architecture.
2. Distributed Architecture.
� The following are the advantages in this Numerical BUSBAR Protection
1. LBB, EFP and other Protections are inbuilt feature.
2. Ratio Matching Transformers are not required. They can be2. Ratio Matching Transformers are not required. They can beprogrammable.
3. Isolator selection is required and these are to be wired to Bay unit as abinary input & selection relays are not required for zone segregation.
4. One Unit is sufficient, for any no of Zones of BUSBAR Protection.
5. In Distributed Architecture Communication between Bay Unit to CentralUnit is Fiber Optic connection.
6. Check Zone feature like Over-all Differential Protection & Over CurrentStarter Protection is in built function. Recently rate of fall of VoltageStarter Protection is in built function. Recently rate of fall of Voltagefunction also inbuilt function.
7. Current comparison, CT supervision, CT open circuit & CT SaturationDetection is also inbuilt feature.
8. Disturbance Recorder and Event Recorders are inbuilt feature.
9. Distributed Architecture is more convenient, it can be accommodated inrespective Bay C&R Panels and very easy for expansion.
Traditionally Two Distinctive ArchitecturesTraditionally Two Distinctive Architectures((CENTRALISED & DECENTRALISEDCENTRALISED & DECENTRALISED))
52 52 52
Distributed Bus Protection
52 52 52
Centralized Bus Protection
52
DAU
52
DAU
52
DAU
CU
52 52 52
CU
• Fits better new installations
• Perceived less reliable
• Slower
CU
copper
fiber
copper
• Fits better retrofit installations
• Perceived more reliable
• Potentially faster
DIFFERENCE BETWEEN BUSBAR SCHEMES
DETAILS HIGH IMPEDENCE BUSBAR PROTECTIONPERCENTAGE BIASED LOW
IMPEDENCE BUS BAR PROTECTION
PRINCIPLE
THE CURRENTS ENTERING AND LEAVING THE BUSBAR ARECOMPARED CONTINUOSLY. IT INVOLVES CHOOSING OFIMPEDENCE HIGH ENOUGH STABLISE THE RELAY FORHEAVY EXTERNAL FAULTS. THIS IS CIRCULATING CURRENTPRINCIPLE.
IT HAS DIFFERENTIAL AND BIAS SETTING. THERESULTANT BIAS IS PROPOTIONAL TO ARITHMATICSUM OF ALL CURRENTS, WHEREAS THE OPERATINGCURRENT IS VECTOR SUM OF ALL CIRCUITCURRENTS.
IT REQUIRES ALL IDENTICAL CT RATIO’s & TURNS RATIO.LOW RESISTANCE OF SECONDARY WINDING. Class X for
IT CAN WORK WITH CTs OF UNEQUAL RATIOS ALSO.FREE OF ANY NEED OF MATCHED CT
CTs
LOW RESISTANCE OF SECONDARY WINDING. Class X forall CT Cores.MINIMUM KNEE POINT VOLTAGE OF 300-500V.LOWMAGNETISING CURRENT (FEW MILLIAMPS).
FREE OF ANY NEED OF MATCHED CTCHARACTERESTIC OR RATIOs LOW LEAKAGEREACTANCE OR RESISTANCE. OTHER PROTECTIVERELAYS CAN BE INCLUDED IN THE SAME CIRCUIT.
BURDEN
IMPOSES COMPARATIVELY HIGH BURDEN ON CTs.AUXILIARY CTs REDUCE THE PERFORMANCE OF THESCHEME
IMPOSES LESS BURDEN ON CTs. AUXILIARY CTsHAVE NO EFFECT ON PERFORMANCE OF SCHEME.
CT
SATURATION
OPERATION OF SCHEME EVEN WHEN CTs GET SATURATEDDURING INTERNAL FAULTS.
OPERATION OF SCHEME EVEN WHEN CTs GETSATURATED DURING INTERNAL FAULTS. INSENSITIVETO CT SATURATION.
UTILISATION
IT IS GOOD SOLUTION FOR SINGLE BUSBARARRANGEMENTS, ONE & HALF BREAKER SYSTEMS OR RINGBUSBAR SYSTEMS.
MOST SUITABLE FOR DOUBLE AND MULTIPLE BUSBARSYSTEMS ( WITH OR WITHOUT TRANSFER BUS).
OPERATING
TIME
BASIC OPERATING TIME EXCLUDING RELAY TIME IS 15 – 20mS.
DETECTS FAULTS WITH IN 1 –2 mS AND INITIATESTRIPPINGWITH IN 5-7 mS.
STABILITY INABILITY TO COPE WITH INCREASING FAULT CURRENT. STABLE FOR INFINITE FAULT LEVEL.
PERFORMAN
CE
HIGHLY SENSITIVE FOR INTERNAL FAULTS AND COMPLETELYSTABLE FOR EXTERNAL FAULTS.
HIGHLY SENSITIVE FOR INTERNAL FAULTS ANDCOMPLETELY STABLE FOR EXTERNAL FAULTS.
ADDITIONAL
PROTECTION
THIS RELAY REQUIRES CHECK ZONE FEATURE. THE TRIPCOMMAND IS ONLY GIVEN WHEN BOTH ADISCRIMINATING & CHECK ZONE SYSTEM OPERATES.
THIS RELAY HAS IN BUILT CHECK ZONE FEATURE (NOSEPARATE CHECKZONE FEATURE) i.e. OVERCURRENT STARTING RELAY PROVIDED.
CHECK ZONE FEATURECHECK ZONE FEATURE
Mal-operation of BUSBAR Protection can resultin wide spread system failure. It is thereforeconsidered judicious to monitor its operation bysome form of check relay.some form of check relay.
In case of High Impedance Relay the settingcalculations is quite high and some times lowsettings can be adopted. In this factor of safetyis more. This may be possibility for mal-is more. This may be possibility for mal-operation from design point of view. Theprovision of a check feature is therefore purely ameasure against mal-operation caused byexternal agencies.
CHECK ZONE FEATURECHECK ZONE FEATURE
TheThe idealideal checkcheck featurefeature shouldshould possesposses thethe followingfollowing characteristicscharacteristics::
1. Check feature should be provided by a Relay which is physically differentfrom the Main Relay.
2. It should pick-up for all types of faults that the Main Protection is capable ofdetecting.detecting.
3. The check feature should be at least as fast if not faster than MainProtection for given type of fault.
4. The source which feeds the Check Relay should be Physically Differentfrom what feeds the Main Protection.
5. The Check feature should operate only for faults within the Main Zone/Zonesof Protection and not for external faults.of Protection and not for external faults.
6. A separate cores of CTs for Check Relay is added with the ratios same asfor the Main Relay.
7. Check Relay can be connected irrespective of CT isolator selection in caseof Double Bus, Triple Bus & Quad Bus for all circuits, this is called overallCheck zone and in case Single Bus and 1-1/2 CB system same as MainRelay.
TRIPPING LOGICTRIPPING LOGIC
The TRIP command is only given when both a discriminating/Main Zone and Check-Zone system Operates.
To Zone-1 Trip Relays
+ve
Check zone Relay output
Main zone-1 Relay output
To Zone-2 Trip Relays
Main zone-2 Relay output
TRIPPING LOGICTRIPPING LOGIC
incase of Single Bus System and One and Half Breaker system the output ofMain Relay and Check Relay is transferring to Main Tripping Relays & checkTripping Relays respectively. The outputs of these Tripping Relays are
parallel for Tripping and series incase of interlocks.87 BB1
96 BB1
+ve FromDC Source-1
Main zoneRelay output
To Circuit BreakerClosing interlockTrip Coil R-PhTrip Coil Y-PhTrip Coil B-Ph
-ve FromDC Source-1
Check zone Relay output
+ve FromDC Source-2
87 BB2
96 BB2
-ve FromDC Source-2
CBIP Guidelines on ProtectionSPECIAL COMMENTSSPECIAL COMMENTS
i) DC Supply for Bus Bar protection shall be independentfrom feeder.
ii) Faults between CB & CT shall be cleared from one side byopening of CB on Bus Bar Protection Operation.opening of CB on Bus Bar Protection Operation.
iii) However clearing of Fault from other side shall be throughBreaker Failure Protection.
iv) 3–ph trip relays shall be provided for each CB which shallalso initiate LBB/BFR Protection.
v) in case of existing SS where CTs are different ratios, biasedtype Differential Protection/ Numerical Bus Bar Protectionis recommended.is recommended.
vi) Length of secondary leads should be kept as minimum aspossible.
vii)Where lead runs are excessive, an increase in wire size oruse of parallel conductors are meant to reduce leadresistance.
CBIP Guidelines on ProtectionREQUIREMENTSREQUIREMENTS
i. It shall be 3-ph type and operate selectively for each bus bar section.
ii. It shall operate on Differential Principle and provide independent zonesof protection for each bus.
iii. It shall provide zone indication.
iv. It shall be stable for through fault conditions up to maximum 40KA faultiv. It shall be stable for through fault conditions up to maximum 40KA faultlevel.
v. For applications where BUS Differential Protection sensitivity has to beset below load current, as may be a case with use of concretestructures, it is recommended that a separate check zone is provided,other wise separate check zone is not essential. Check zone, if provided,shall be of High Impedance type.
vi. It shall incorporate continuous supervision for CT secondary against anypossible open circuits. In case of detection of open circuiting of CTsecondary, after a time delay, the effected zone of protection shall bepossible open circuits. In case of detection of open circuiting of CTsecondary, after a time delay, the effected zone of protection shall berendered inoperative and alarm initiated.
vii. It shall be include DC supply supervision.
viii. Include adequate number of high speed tripping relays.
ix. whenever CT switching is involved the scheme shall include necessaryCT switching relays and have provision for CT switching incompletealarm.
x. It shall be include IN/OUT switching facility for each zone.
CBIP Guidelines on Protection
� C.T wire supervision relays should be set with a sensitivity suchthat they can detect C.T secondary open circuit even in case ofleast loaded feeder.
� BUSBAR Differential Protection should have overall sensitivity
SETTING CRITERIASETTING CRITERIA
� BUSBAR Differential Protection should have overall sensitivityabove heaviest loaded feeder current unless a separate checkzone has been provided.
� In case where faults currents are expected to be low, theprotection should be sensitive enough to take care of suchexpected low fault current.
� In case of voltage operated High Impedance type Protection, thevoltage setting should be above expected voltage developedvoltage setting should be above expected voltage developedacross the relay during maximum through fault currentcondition.
� In case of current operated relays for stability under throughfault condition, external resistance is to be set such that voltagedeveloped across relay and resistance combination is below thevoltage required for forcing required relay operating current.
HIGH IMPEDENCE BUSBAR PROTECTION
87BBM2
52 CIRCUIT
96 BBM2 : BUSBAR MAIN2 TRIPPING RELAY
52 CIRCUIT BREAKERTRIP COIL
- VEA varistor is normally applied
87BBM1
+ VE96 BBM1 : BUSBAR
MAIN1 TRIPPING RELAY
A varistor is normally applied
across the relay input terminals
to limit the voltage to a value
safely below the insulation
voltage of the secondary circuits
LOW IMPEDENCE BUSBAR PROTECTION
+VE
OV
ER
C
UR
RE
NT
RESTRAINTCOIL
OV
ER
CU
RR
EN
T
ST
AR
TE
R R
EL
AY
S
.
OV
ER
C
UR
RE
NT
CO
ILO
PE
RA
TIN
GC
OIL
96 BUS BAR
TRIPPING
RELAY
OV
ER
CU
RR
EN
T
ST
AR
TE
R R
EL
AY
S
Id
Is
52
CIR
CU
IT
BR
EA
KE
RT
RIP
CO
IL
-VE
OP
ER
AT
ING
VOLTAGE-DIFFERENTIAL BUSBAR
PROTECTION
Vd
VO
LTA
GE
OP
ER
AT
ED
V
OLTA
GE
OP
ER
AT
ED
DIF
FE
RE
NT
IAL R
EL
AY
DIF
FE
RE
NT
IAL R
EL
AY
VO
LTA
GE
OP
ER
AT
ED
V
OLTA
GE
OP
ER
AT
ED
DIF
FE
RE
NT
IAL R
EL
AY
DIF
FE
RE
NT
IAL R
EL
AY
SUMMATION CT METHOD
3 3 3 3 3 3 3 3 3 3 3 3
UUUUUUUUU
3 3 3UUUUUUUUU UUUUUUUUU
3 3 3UUUUUUUUU3 3 3
UUUUUUUUU
UU UU UUU
UU3 3 3
UUUUUUUUU
UU UU UUU
UU
SUMMATION METHOD DIFFERENTIAL RELAY SUMMATION METHOD DIFFERENTIAL RELAY –– 87BB87BB
UUUUUUUUU UUUUUUUUU UUUUUUUUU UU UUUUUUUUU UU
METHOD - 1 METHOD - 2
DOUBLE BUS- HIGH IMPEDENCEBUS-1
BUS-2
U
UU
UU
UU UU UU
87 B
BC
UU UU UU
87 B
BM
-2
BUS-2
UU
UU
87 B
BM
87 B
BM
-1
ISOLATORSELECTION
ISOLATORSELECTION
ISOLATORSELECTION
ISOLATORSELECTION
DOUBLE BUS- LOW IMPEDENCEBUS-1
BUS-2
U
U
UU UU UU UU
87 B
BM
-2
UU
UU
87 B
BM
87 B
BM
-1ISOLATORSELECTION
ISOLATORSELECTION
ISOLATORSELECTION
ISOLATORSELECTION
LOW IMPEDANCE RELAY HAVING INBUILT CHECK FEATURE
DOUBLE BUS- NUMERICAL CENTRALISEDBUS-1
BUS-2
U
U
UU UU UU UU
UU
UUCENTRALISED NUMERICAL BUSBAR HAVING NUMERICAL ALGORITHAM FORISOLATOR SELECTION, ZONE SELECTION, OVER ALL DIFFERENTAIL PROTECTION ASCHECK ZONE, OVER CURRENT STARTER AS CHECK ZONE, CT SUPERVISION, CT
OPEN CIRCUIT & CT SATURATION ETC FEATURES ARE INBUILT.
87 CENTRALISED NUMERICAL BUSBAR PROTECTION RELAY
DOUBLE BUS- NUMERICAL DISTRIBUTEDBUS-1
BUS-2UU UU UU UU
BUS-2
BAY BAY BAY BAY
UU
87 DISTRIBUTED NUMERICAL BUSBAR PROTECTION RELAY
BAY
UNIT
LBB
BAY
UNIT
LBB
BAY
UNIT
LBB
BAY
UNIT
LBB
FO FO FO FO
BAY
UNIT
LBB
FO
DOUBLE BUS- DUPLICATE PROTECTIONBUS-1
BUS-2UU UU UU UU
BAY
UNIT
LBB
BAY
UNIT
LBB
BAY
UNIT
LBB
BAY
UNIT
LBB
BAY
UNIT
LBBUU
87 DISTRIBUTED
NUMERICAL BUSBAR PROTECTION RELAY
LBB LBB LBB LBB
87 DISTRIBUTED
NUMERICAL BUSBAR PROTECTION RELAY
LBB
DOUBLE BUS- DUPLICATE PROTECTIONBUS-1
BUS-2
UUU
UU UU UU UU
BAY
UNIT
LBB
BAY
UNIT
LBB
BAY
UNIT
LBB
UU UU UU UU
BAY
UNIT
LBB
BAY
UNIT
LBB
BAY
UNIT
LBB
BAY
UNIT
LBB
BAY
UNIT
LBB
BAY
UNIT
LBBUU
UU
BAY
UNIT
LBB
87 DISTRIBUTED
NUMERICAL BUSBAR PROTECTION RELAY
LBB LBB LBB
87 DISTRIBUTED
NUMERICAL BUSBAR PROTECTION RELAY
LBBLBB LBB LBB LBB LBBLBB
DOUBLE BUS- DUPLICATE PROTECTIONBUS-1
BUS-2
UUUU
UUUU
MAIN2PROT
MAIN1PROT
UU
UU
MAIN1PROT
MAIN2PROT
UU
UU
MAIN1PROT
MAIN2PROT
UU
UU
MAIN1PROT
MAIN2PROT
UU
BAY UNIT
BAY UNIT
BAY UNIT
BAY UNIT
BAY UNIT
BAY UNIT
BAY UNIT
BAY UNIT
87 DISTRIBUTED
NUMERICAL BUSBAR PROTECTION RELAY
87 DISTRIBUTED
NUMERICAL BUSBAR PROTECTION RELAY
BAY UNIT
BAY UNIT
DOUBLE BUS WITH TB- HIGH IMPEDENCEBUS-1
BUS-2
U
UU
UU UU UU UU
UUUU
UU
87BB
UU87BB
CHECK
UU UU UU UU
UU
UU
87BBBUS2
87BBBUS3
87BBBUS1
89A
89B
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
DOUBLE BUS WITH TB- LOW IMPEDENCEBUS-1
BUS-2
U
UU
UU UU UU UU
UUUU
UU
87BB
UU
87BBBUS2
87BBBUS3
87BBBUS1
89A
89B
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
DOUBLE BUS WITH TB- NUMERIC(1)BUS-1
BUS-2
U
UU
UU UU UU UU
UUUU
UUUU
89A
89B
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
89A
89B
89C
ISOLATORSELECTION
DOUBLE BUS WITH TB- NUMERIC(2)BUS-1
BUS-2
U
UU
UU UU UU UU
UUUU
UUUU
89A
89B
89C
89A
89B
89C
89A
89B
89A
89B
89C
89A
89B
89C
87 BB DISTRIBUTED NUMERICAL BUSBAR
PROTECTION
BAYUNIT
BAYUNIT
BAYUNIT
BAYUNIT
BAYUNIT
BAYUNIT
BAYUNIT
BAYUNIT
DOUBLE BUS WITH TB- NUMERIC(3)BUS-1
BUS-2
U
UU
UU UU UU UU
UUUU
UUUU
89A
89B
89C
89A
89B
89C
89A
89B
89A
89B
89C
89A
89B
89C
87 BB NUMERICAL CENTRALISED BUSBAR
PROTECTION
ONE AND HALF CB SYSTEM – HIGH IMPEDANCE
87BB187BB1--MAIN1 BB1 PROTECTIONMAIN1 BB1 PROTECTION
BUS-1
52
52
52
-52
-52
-52
-52
87BB187BB1--MAIN2 BB1 PROTECTIONMAIN2 BB1 PROTECTION1
-52
2-5
2
1-CT
3-CT
4-5
25
-52
4-CT
6-CT
7-5
28
-52
7-CT
9-CT
10
-11
-52
10-CT
12-CT
13
-1
4-5
2
13-CT
15-CT
16
-1
7-5
2
16-CT
18-CT
19
-2
0-5
2
19-CT
21-CT
UU
UU
UU
UU
UU
UU
UUUUUU
UU
UU
UU
UU
UUUU UU UU UU UU UU UU
BUS-2
3-5
2
3-CT
6-5
2
6-CT
9-5
2
9-CT
12
-52
12-CT
15
-52
15-CT
18
-52
18-CT
21
-52
21-CT
87BB287BB2--MAIN1 BB2 PROTECTIONMAIN1 BB2 PROTECTION 87BB287BB2--MAIN2 BB2 PROTECTIONMAIN2 BB2 PROTECTION
UU UU UU UU UU UU UU
ONE AND HALF CB SYSTEM – LOW IMPEDANCE
87 87 –– BB1 BUS BARBB1 BUS BAR--1 PROTECTION1 PROTECTION
BUS-1
52
-52
-52
-52
-52
52
52
1-C
T
7-5
28
-52
7-C
TC
T
10
-11
-52
10
-CT
CT
13
-1
4-5
2
13
-CT
CT
16
-1
7-5
2
16
-CT
CT
19
-2
0-5
2
19
-CT
CT
CT
2-5
21
-52
4-5
25
-52
4-C
TC
T
87 87 –– BB2 BUS BARBB2 BUS BAR--2 PROTECTION2 PROTECTION
BUS-2
9-5
2
9-C
T
12
-52
12
-CT
15
-52
15
- CT
18
-52
18
-CT
21
-52
21
-CT
3-C
T
3-5
2
6-5
2
6-C
T
DISTRIBUTED LBB & NUMERICAL CENTRALISED BUS BAR PROTECTION
BUS-1
1-5
2
4-5
2
7-5
2
10
-52
13
-52
OR OR
(REB 500) ABB (7 SS 52) SIEMENS (MICOM P740) AREVA
12
-52
45
-52
78
-52
10
11
-52
13
14
-52
BUS-2
3-5
2
6-5
2
9-5
2
12
-52
15
-52
OR OR
LATEST DEVELOPMENT IN NUMERICAL DISTRIBUTED BUS BAR PROTECTION
ABBABB SIEMENSSIEMENS AREVAAREVA
BUSBAR
PROTECTION
CENTRAL UNIT
ABB Network Partner AG
c
E
1
2
3
4
9
10
11
12
ABB Network Partner AG REL 316*4
BAY UNIT
LINE
PROTECTION
TRANSFORMER
21 L1 21 L2 21 L1 21 L2 21 L1 21 L2
C
E
ABB Network Partner AG REL531
ABB Network Partner AG REL531
5
6
7
8
13
14
15
16
C
E
PROTECTION
DESCRIPTION
1. IN THIS NO SEPARATE CORE IS REQUIRED FOR EITHER BUSBAR PROTECTION OR LBB / BFR.
2. CENTRALISED BUSBAR IS CONNECTED FROM BAY UNIT OR LBB OR BFR THROUGH FIBRE OPTIC.
3. BAY UNIT / BFR / LBB IS CONNECTED FROM MAIN-1 & MAIN-2 OF LINE PROTECTION OR MAIN &
BACKUP PROTECTION OF TRANSFORMER THROUGH FIBRE OPTIC FOR REDUNDANCY TO BAY UNIT.
4. THE CURRENT DATA IS TRANSFERED TO BAY UNIT TO BUSBAR CENTRAL UNIT FROM LINE /
TRANSFORMER PROTECTIONS FOR NUMIRICAL ALGORITHAM OF LBB & BUSBAR CENTRAL UNIT AND
IT WILL OPERATE FOR INTERNAL FAULTS AND DOES NOT OPERATE FOR THROUGH / EXTERNAL
FAULTS.
87 T1 87 T2 87 T1 87 T2 87 T1 87 T2
C
E
NUMERICAL BUSBAR SCHEME INCL LBB/BFR/CBF
(DECENTRALISED & CENTRALISED ARCHITECTURE)
BU /PUBU /PU
(REB 500) ABB
DECENTRALISED CONCEPTDECENTRALISED CONCEPT CENTRALISED CONCEPTCENTRALISED CONCEPT
FOFO
BU / PUBU / PU
(7 SS 52) SIEMENS
FOFO
(REB 670) ABB
(487B) SEL
OROROROR
BU / PUBU / PU
(MICOM P743) AREVA
LBB INBUILT FEATURELBB INBUILT FEATUREBU / PU TO BUSBARBU / PU TO BUSBAR
DIGITAL COMMUNICATIONDIGITAL COMMUNICATION
FOFO
(MICOM P746) AREVA
LBB INBUILT FEATURELBB INBUILT FEATURE
NUMERICAL BUSBAR SCHEME INCL LBB/BFR/CBF
(DECENTRALISED CONCEPT- DUPLICATE )
BU / PUBU / PU
(REB 500) ABB
DECENTRALISED CONCEPTDECENTRALISED CONCEPT
FOFO(REB 500) ABB
DECENTRALISED CONCEPTDECENTRALISED CONCEPT
BU / PUBU / PU
FOFO
BU / PUBU / PU
OR
OR
(7 SS 52) SIEMENSFOFO
OR
OR
(7 SS 52) SIEMENS
BU / PUBU / PU
BU / PUBU / PU
FOFO
BU / PUBU / PU
OR
(MICOM P743) AREVA
BU / PU TO BUSBARBU / PU TO BUSBARDIGITAL COMMUNICATIONDIGITAL COMMUNICATION
FOFO
OR
(MICOM P743) AREVA
BU / PU TO BUSBARBU / PU TO BUSBARDIGITAL COMMUNICATIONDIGITAL COMMUNICATION
BU / PUBU / PU
FOFO
LBB INBUILT FEATURELBB INBUILT FEATURE LBB INBUILT FEATURELBB INBUILT FEATURE
NUMERICAL BUSBAR SCHEME INCL LBB/BFR/CBF
(CENTRALISED CONCEPT - DUPLICATE)
CENTRALISED CONCEPTCENTRALISED CONCEPT CENTRALISED CONCEPTCENTRALISED CONCEPT
(REB 670) ABB
(487B) SEL
(REB 670) ABB
(487B) SEL
LBB INBUILT FEATURELBB INBUILT FEATURE LBB INBUILT FEATURELBB INBUILT FEATURE
(MICOM P746) AREVA
(MICOM P746) AREVA
PROTECTION OF RING BUS SYSTEM
UU UU
87
BB
2
87 BB3FEEDER4 FEEDER3
UU
UU8
7 B
B2
87
BB
4
UU
UU
UU UU
FEEDER187 BB1
FEEDER2
87
BB
4
BUS BAR PROTECTION
INITIATE ALL CBs TRIP UNITS CONNECTED TO THIS BUS AND OPERATE.
TO TRIP COIL-1 CONCERNED BAY CB
TO TRIP COIL-2 CONCERNED BAY CB
TO CLOSE CIRCUIT INTERLOCK OF CONCERN CB
DIRECT TRIP SEND CHANNEL-1 TO OTHER END
DIRECT TRIP SEND CHANNEL-2 TO OTHER END
BU
SB
US
--1
1
TO EVENT RECORDER ( SOE/ SCADA )
TO DISTURBANCE RECORDER OF MAIN-1
INITIATE ALARM (ANNUNCIATION COME)
TO LBB/BFR INITIATION
TO DISTURBANCE RECORDER OF MAIN-2
FROM LBB/BFR TO BUS BAR TRIPPING
INITIATE ALL CBs TRIP UNITS CONNECTED TO THIS BUS AND OPERATE.
TO TRIP COIL-1 CONCERNED BAY CB
TO TRIP COIL-2 CONCERNED BAY CB
BU
SB
US
TO EVENT RECORDER ( SOE/ SCADA )
TO DISTURBANCE RECORDER OF MAIN-1
TO TRIP COIL-2 CONCERNED BAY CB
TO CLOSE CIRCUIT INTERLOCK OF CONCERN CB
DIRECT TRIP SEND CHANNEL-1 TO OTHER END
DIRECT TRIP SEND CHANNEL-2 TO OTHER END
INITIATE ALARM (ANNUNCIATION COME)
TO LBB/BFR INITIATION
TO DISTURBANCE RECORDER OF MAIN-2
FROM LBB/BFR TO BUS BAR TRIPPINGBU
SB
US
--2
2
87 BUSBAR PROTECTION TRIPPING SCHEME87 BUSBAR PROTECTION TRIPPING SCHEME
HIGH SPEEDHIGH SPEED
TRIP RELAYTRIP RELAY
(96BB) FOR (96BB) FOR
BAY1BAY1
HIGH SPEEDHIGH SPEED
TRIP RELAYTRIP RELAY
(96BB) FOR (96BB) FOR
BAY2BAY2
BAY1 CR PANELBAY1 CR PANEL
TRIP FROM 50 LBB
TO START 50 LBB
BAY2 CB PANELBAY2 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
FO
R S
ING
LE
BU
S S
YS
TE
MBAY2BAY2
HIGH SPEEDHIGH SPEED
TRIP RELAYTRIP RELAY
(96 BB) FOR (96 BB) FOR
BAY3BAY3
HIGH SPEEDHIGH SPEED
TRIP RELAYTRIP RELAY
(96 BB) FOR (96 BB) FOR
BAY4BAY4
TO START 50 LBB
BAY3 CB PANELBAY3 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
BAY4 CB PANELBAY4 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
87 BUSBAR
FO
R S
ING
LE
BU
S S
YS
TE
M
HIGH SPEEDHIGH SPEED
TRIP RELAYTRIP RELAY
(96BB)FOR (96BB)FOR
BAY5BAY5
HIGH SPEEDHIGH SPEED
TRIP RELAYTRIP RELAY
(96 BB) FOR (96 BB) FOR
BAY6BAY6
TO START 50 LBB
BAY5 CB PANELBAY5 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
BAY6 CB PANELBAY6 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
+VE BUSBAR PANEL
FO
R S
ING
LE
BU
S S
YS
TE
M
96 BB (MASTER TRIP RELAY) OPERATION96 BB (MASTER TRIP RELAY) OPERATION
87 BUSBAR
TO D/T-1
+VE
-VERESET
OPERATED
PB
FO
R S
ING
LE
BU
S S
YS
TE
M,
ON
E &
HA
LF
CB
SY
ST
EM
,D
OU
BL
E C
B &
DO
UB
LE
BU
S S
YS
TE
M
& R
ING
MA
IN B
US
SY
TE
M
TO D/T-1
TO CL I/L
TO LBB
TO TC-1
TO D/T-2
TO ANNUN
TO SER
FROM LBB
FO
R S
ING
LE
BU
S S
YS
TE
M,
ON
E &
HA
LF
CB
SY
ST
EM
,D
OU
BL
E C
B &
DO
UB
LE
BU
S S
YS
TE
M
& R
ING
MA
IN B
US
SY
TE
M
TO TC-2
TO M1 DR
TO M2 DR
96 BB MASTER TRIP RELAY
FO
R S
ING
LE
BU
S S
YS
TE
M,
ON
E &
HA
LF
CB
SY
ST
EM
,D
OU
BL
E C
B &
DO
UB
LE
BU
S S
YS
TE
M
& R
ING
MA
IN B
US
SY
TE
M
96 BB (MASTER TRIP RELAY) OPERATION96 BB (MASTER TRIP RELAY) OPERATION
TO D/T-1
+VE
-VERESET
OPERATED
PB
FO
R S
INL
E B
US
AN
D T
RA
NS
FE
R B
US
SY
ST
EM
FO
R D
OU
BL
E B
US
SY
ST
EM
FO
R D
OU
BL
E B
US
& B
YP
AS
S I
SO
SY
ST
EM
DO
UB
LE
BU
S &
TR
AN
SF
ER
BU
S S
YS
TE
M
TR
IPP
LE
BU
S &
TR
AN
SF
ER
BU
S S
YS
TE
M &
(DO
UB
LE
BU
S W
ITH
CB
SE
CT
ION
AL
ISE
R)
BUSBARRELAYS
ISOLATORSELECTION
87 A 89 A
87 B 89 B TO D/T-1
TO CL I/L
TO LBB
TO TC-1
TO D/T-2
TO ANNUN
TO SER
IF BUS-1 IS OPERATED THE FEEDERS CONNECTED TO BUS BAR-1WILL BE OPTD BASED ON
FO
R S
INL
E B
US
AN
D T
RA
NS
FE
R B
US
SY
ST
EM
FO
R D
OU
BL
E B
US
SY
ST
EM
FO
R D
OU
BL
E B
US
& B
YP
AS
S I
SO
SY
ST
EM
DO
UB
LE
BU
S &
TR
AN
SF
ER
BU
S S
YS
TE
MT
RIP
PL
E B
US
SY
TE
MT
RIP
PL
E B
US
& T
RA
NS
FE
R B
US
SY
ST
EM
&
QU
AD
BU
S S
YT
EM
(DO
UB
LE
BU
S W
ITH
CB
SE
CT
ION
AL
ISE
R)
FROM LBB
87 B 89 B
87 C 89 C
TO TC-2
TO M1 DR
TO M2 DR
96 BB MASTER TRIP RELAY
BAR-1WILL BE OPTD BASED ON
THE ISOLATOR SELECTION. SIMILARLY FOR BUS-2 & BUS-3 & FOR ANY NO OF BUSES, EXCEPT 1.ONE AND HALF CB SYSTEM,2.DOUBLE CB SYSTEM & 3.RING BUS SYTEM. FO
R S
INL
E B
US
AN
D T
RA
NS
FE
R B
US
SY
ST
EM
FO
R D
OU
BL
E B
US
SY
ST
EM
FO
R D
OU
BL
E B
US
& B
YP
AS
S I
SO
SY
ST
EM
DO
UB
LE
BU
S &
TR
AN
SF
ER
BU
S S
YS
TE
MT
RIP
PL
E B
US
SY
TE
MT
RIP
PL
E B
US
& T
RA
NS
FE
R B
US
SY
ST
EM
&
QU
AD
BU
S S
YT
EM
(DO
UB
LE
BU
S W
ITH
CB
SE
CT
ION
AL
ISE
R)
87BB87BB--1 BUSBAR PROTECTION TRIPPING SCHEME1 BUSBAR PROTECTION TRIPPING SCHEME
HIGH SPEED
TRIP RELAY
(96BB) FOR
BAY1
HIGH SPEED
TRIP RELAY
(96BB) FOR
BAY4
BAY1 CB PANELBAY1 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
BAY4 CB PANELBAY4 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
FO
R O
NE
& H
AL
F C
IRC
UIT
BR
EA
KE
R S
YS
TE
M
BAY4
HIGH SPEED
TRIP RELAY
(96 BB) FOR
BAY7
HIGH SPEED
TRIP RELAY
(96 BB) FOR
BAY10
TO START 50 LBB
BAY7 CB PANELBAY7 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
BAY10 CB PANELBAY10 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
87 BUSBAR
FO
R O
NE
& H
AL
F C
IRC
UIT
BR
EA
KE
R S
YS
TE
M
87 BB-1
HIGH SPEED
TRIP RELAY
(96BB)FOR
BAY13
HIGH SPEED
TRIP RELAY
(96 BB) FOR
BAY16
TO START 50 LBB
BAY13 CB PANELBAY13 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
BAY16 CB PANELBAY16 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
+VE BUSBAR PANEL
FO
R O
NE
& H
AL
F C
IRC
UIT
BR
EA
KE
R S
YS
TE
M
87BB87BB--2 BUSBAR PROTECTION TRIPPING SCHEME2 BUSBAR PROTECTION TRIPPING SCHEME
HIGH SPEED
TRIP RELAY
(96BB) FOR
BAY3
HIGH SPEED
TRIP RELAY
(96BB) FOR
BAY6
BAY3 CB PANELBAY3 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
BAY6 CB PANELBAY6 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
FO
R O
NE
& H
AL
F C
IRC
UIT
BR
EA
KE
R S
YS
TE
M
BAY6
HIGH SPEED
TRIP RELAY
(96 BB) FOR
BAY9
HIGH SPEED
TRIP RELAY
(96 BB) FOR
BAY12
TO START 50 LBB
BAY9 CB PANELBAY9 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
BAY12 CB PANELBAY12 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
87 BUSBAR
FO
R O
NE
& H
AL
F C
IRC
UIT
BR
EA
KE
R S
YS
TE
M
87 BB-2
HIGH SPEED
TRIP RELAY
(96BB)FOR
BAY15
HIGH SPEED
TRIP RELAY
(96 BB) FOR
BAY18
TO START 50 LBB
BAY15 CB PANELBAY15 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
BAY18 CB PANELBAY18 CB PANEL
TRIP FROM 50 LBB
TO START 50 LBB
+VE BUSBAR PANEL
FO
R O
NE
& H
AL
F C
IRC
UIT
BR
EA
KE
R S
YS
TE
M
UTILISATION RECOMMENDATIONSUTILISATION RECOMMENDATIONS
� BUSBAR protection must be provided in all new 400kVand 220kV Substations as well as Generating StationSwitchyards.
� For existing Substations, provision of BUSBAR Protectionis must & considered at 400kV level and at 220kV level.is must & considered at 400kV level and at 220kV level.
� In case of radially fed 220kV Substations, having morethan one bus it is desirable to have BUSBAR Protection,but it is an Option.
� Redundant / Duplicate Busbar Protection to be providedFor Substations of High strategic importance i.e. 765KVor 400KV Systems.or 400KV Systems.
� Dedicated Protections invariably employ separate DCcircuits and CT cores. They send trip impulses toseparate trip coils and use separate isolator positionauxiliary contacts. Cross tripping of both trip coils is alsodone.
DISTRIBUTED ARCHITECTURE DISTRIBUTED ARCHITECTURE (CONNECTION DIAGARAM)(CONNECTION DIAGARAM)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
ABB Network Partner AG REL 316*4
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
ABB Network Partner AG REL 316*4
BAYUNIT
BAYUNIT
BAYUNIT
BAYUNIT
PERIPHERALUNITS
BAYUNIT
BAYUNIT
C
E
ABB Network Partner AG
ABB Network Partner AG REL 316*4 ABB Network Partner AG REL 316*4
C
E
C
E
CE
NT
RA
LU
NIT
S
CE
NT
RA
LU
NIT
S
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
C
E
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
C
E
BAYUNIT
BAYUNIT
BAYUNIT
BAYUNIT
PERIPHERALUNITS
BAYUNIT
BAYUNIT
STAR CONNECTION TOPOLOGYSTAR CONNECTION TOPOLOGY
TOSHIBA Bay unit is accepting 2Bays in one. So One Bay unit is for one Dia or 2 Adjacent Bays
DISTRIBUTED ARCHITECTURE DISTRIBUTED ARCHITECTURE (CONNECTION DIAGARAM)(CONNECTION DIAGARAM)
Tx
Rx
Tx
Tx
Rx
Tx
Tx
Rx
Tx
Tx
Rx
Tx
RxRx Rx Rx
Tx
Rx
Tx
Tx
Rx
Tx
Tx
Rx
Tx
Tx
Rx
TxTx
Rx
Tx
Rx
Tx
Rx
Tx
Rx
REDUNDANT RING TOPOLOGYREDUNDANT RING TOPOLOGY
FUNCTIONS OF DISTRIBUTED BUSBAR BAY UNIT BAY UNIT
FUNCTIONS & PROTECTIONSFUNCTIONS & PROTECTIONS
CENTRAL UNIT CENTRAL UNIT
FUNCTIONS & PROTECTIONSFUNCTIONS & PROTECTIONS
1. Breaker Failure Protection (LBB)
2. End Fault Protection (EFP)
3. Over Current Protection (OC)
1. Breaker Failure Protection (LBB)
2. Neutral Current Detection (Io)
3. Disturbance Recorder (DR)3. Over Current Protection (OC)
4. Pole Discrepancy Protection (PD)
5. Under Voltage Protection (U)
6. Disturbance Recorder (DR)
7. Event Recorder (ER)
8. Fault Recorder (FR)
9. Alarms
3. Disturbance Recorder (DR)
4. Event Recorder (ER)
5. Fault Recorder (FR)
6. Alarms
7. Programmable LEDs
8. Communication to BU
(Owner Based Protocol)9. Alarms
10. Programmable LEDs
11. Human Machine Interface (HMI)
12. Measurements
13. Communication to CU (Owner Based Protocol)
9. Communication to SAS
(IEC 61850 Protocol)
10. Check Zone Busbar
11. Remote HMI
12. Measurements
13. Test Generator
BENEFITS OF DISTRIBUTED BUSBAR 1. Improved Functionality – Optional
Functions.
2. Less Space Required – Aux relays
not required for Isolator selection.
3. We can save the 96 Relay – Thiscan be possible to configure in Bay
11. On Line Alarms.
12. On Line Event Lists.
13. Ethernet Connection (TCP/IP).
14. Connection to SAS/SCS.
15. Disturbance Recorder Transfer.can be possible to configure in Bay
Unit.
4. Easily Expandable.
5. Reduced Copper Wiring – Savingof cable 60%.
6. Software CT matching.
7. Reduced no of Spare parts – Aux
15. Disturbance Recorder Transfer.
16. Data Archiving (Disturbance / Events).
17. Access to Remote Disturbance
data.
18. Disturbance Analysis.
19. Synchronous System events.
20. Remote Support.7. Reduced no of Spare parts – Aux
CTs and CT switching Relays.
8. Easy changeable parameters at
site.
9. Continuous self Supervision.
10. Less Cost for Maintenance.
20. Remote Support.
21. Signal Simulation.
22. Upgrading functionality.
23. Measurement in BU & CU.
TYPES OF BUSBAR PROTECTION RELAYSDISTRIBUTED ARCHITECTURE CENTRALISED ARCHITECTURE
MAKE MODEL BAY UNIT CENTRAL UNIT MAKE MODEL CENTRAL UNIT
ABBREB
500ABB
REB
670C
ABB Network Partner AG
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
ABB Network Partner AG REL 316*4
C
500 670
AREVAMICOM
P 741/3AREVA
MICOM
P 746
SIEMENSSIPROTEC
7 SS 52GE
UR
B 90
EE
B 90
ANDRITZDRS
BBSEL
SEL
487 B
HITACHIGRB
100
ERL
PHASE
B-PRO
4000
RECOMMENDATIONS FOR 400KVRECOMMENDATIONS FOR 400KV
� In Case of Centralised Architecture BUSBAR
Protection, Stand alone LBB is preferable.
� In Case of Distributed Architecture BUSBAR
Protection, LBB is configured in Bay Unit,Protection, LBB is configured in Bay Unit,
BUSBAR Protection is configured in Central
Unit and tripping Logic is to be duplicated i.e.
one tripping Logic Through FO and another
through Hardwiring.
� In case of Redundant or Duplicate BUSBAR� In case of Redundant or Duplicate BUSBAR
Protection Distributed Architecture need not
require redundant/ Duplicate trip logic. The
Tripping Logic from CU to BU is FO and BU to
Master trip Relay & Trip Coil.
MODIFICATIONS REQUIRED IN DISTRIBUTED BUSBAR MODIFICATIONS REQUIRED IN DISTRIBUTED BUSBAR
� The Connection between BU & CU Redundant
communication.
� Bay Unit can communicate to Dual/ Twin CUs in
Star Topology.
� The Connection between BU & CU Redundant and
one is Star Topology communication and another is
Redundant Ring Topology Communication.
� Always Preferable Fail Safe Mode.
� When ever FO Communication Problem, CU is giving
Alarm and BB is blocked (out of service). This can beAlarm and BB is blocked (out of service). This can be
modified. The value before failure has to be taken
and BB is to be in service. Now a days all Relays are
61850 Communication, when failure, the Analog data
from Main Relays and Digital Data from BCU and
tripping can be extend through BCU / Main Relays.