-
EPT 432 Production Management Laboratory Module
Page 1 of 12
A) Graphical Approaches
A manufacturer of roofing supplies has developed monthly
forecasts for family of
products. Data for 6 moth period January to June are presented
in Table below, The firm
would like to begin development of an aggregate plan.
Month Expected
Demand
Production
Days
January 900 22
February 700 18
March 800 21
April 1200 21
May 1500 22
June 1100 20
Solution:
Average requirement = Total expected demand = 6200 = 50 units /
day
Number of production days 124
There is a few plan can be made:-
-
EPT 432 Production Management Laboratory Module
Page 2 of 12
1st plan is to maintain a constant workforce through out the
whole year.
2nd
strategy is to maintain a constant workforce at level necessary
to meet the lowest
demand and to meet all the balance demand and
subcontracting.
Both plan 1 and 2 have a level production, so its called level
strategies.
3rd
plan is to hire and layoff workers as needed to produce exact
monthly requirements a chase strategy.
Table below provides cost information necessary for analyzing
these three alternatives:
Inventory carrying cost $5 per unit / month
Subcontracting cost per unit $10 / unit
Average per rate $5 / hour ($40 / day)
Overtime per rate $7 / hour (above 8 hours /
day)
Labor hours to produce a unit 1.6 hours per unit
Cost of increasing daily production rate
(hiring and training)
$ 300 / unit
Cost of decreasing daily production rate
(layoffs)
$ 600 / unit
(i) Plan 1 - A constant workforce
Assume that 50 units are produced per day and that we have a
constant workforce, no
overtime or idle time, no safety stock, and no subcontractors.
The firm accumulates
inventory during the slack period of demand, January through
March and depletes it
during the higher demand warm season, April through June. Assume
beginning inventory
= 0 and planned ending inventory = 0
Solution:
(1) Find the production for 50 units/ day
-
EPT 432 Production Management Laboratory Module
Page 3 of 12
(2) Find the monthly inventory change
(3) Ending inventory
-
EPT 432 Production Management Laboratory Module
Page 4 of 12
Total units of inventory = 1850 units
(4) Find the total of man needed to produce 50 units / day
1 man who worker for 8 hours can produce 5 units. To produce 50
units a days, we need
10 men.
-
EPT 432 Production Management Laboratory Module
Page 5 of 12
(5) Find the total cost for the above figure
Inventory carrying = (1850 units in inventory x $5 per unit) =
$9250
Regular time labor = (10 workers x $40 per day x 124 days) =
$49600
Other cost (overtime, hiring, layoffs, subcontracting) =0 Total
cost = $58,850
*Note the significant cost of carrying the inventory
(ii) Plan 2 Subcontractors and constant workforce
Although constant workforce is maintained, it is set low enough
to meet demand only in
March, the lowest demand per day month. To produce 38 units per
day in house, 7.6
workers are needed. (You can think of this as 7 full time
workers and 1 part timer). All
other demand is met by subcontracting. Subcontracting is thus
required in every other
month. No inventory holding costs are incurred in plan 2.
Solution:
-
EPT 432 Production Management Laboratory Module
Page 6 of 12
Because 6200 units are required during the aggregate plan
period, we must compute how
many can be made by the firm and how must be subcontracted:
(1) Find the in house and subcontract total production
(1) In-House production = 38 units per day x 124 production days
= 4,712 units
(2) Subcontract units = 6,200 4,712 = 1,488 units
(2) Find the total cost for regular time labor and
subcontractor
Regular time labor = (7.6 workers x $40 per day x 124 days) =
$37,696.00
Subcontracting = (1,488 units x $10 per unit) = $ 14,880.00
Total cost = $52,576.00
* Note the lower cost of regular labor but the added
subcontracting cost
-
EPT 432 Production Management Laboratory Module
Page 7 of 12
(iii) Plan 3 Hiring and Firing
This plan involves varying the workforce size by hiring and
firing as necessary. The
production rate will equal the demand, and there is no change in
production from the
previous month, December
Solution:
Below show the calculations and total cost plan 3. Recall that
it costs $600 per unit
produced to reduce production from the previous months daily
level and $300 per unit change to increase the daily rate of
production hiring.
Thus, the total cost, including production, hiring, and layoffs
for plan 3 is $68, 200
* Note the substantial cost associated with changing (both
increasing and decreasing) the
production levels.
-
EPT 432 Production Management Laboratory Module
Page 8 of 12
(iv) Final step in graphical method
The final step in the graphical method is to compare the costs
of each proposed plan and
to select the approach with the least total cost. A summary
analysis is provided below.
We can see that plan 2 has the lowest cost, it is the best of
the 3 options.
-
EPT 432 Production Management Laboratory Module
Page 9 of 12
B) Mathematical Approaches
The transportation method of linear programming is not a
trial-and-error method like
graphing but is rather produces an optimal plan for minimizing
costs. Example below
shows the supply consists of on hand inventory and units
produced by regular time,
overtime and subcontracting.
Farnsworth Tire Co. would like to develop an aggregate plan via
the transportation
method. Data that relate to production, demand, capacity and
cost at its West Virginia
Plant are shown in the table below:-
Sales Period
March April May
Demand Capacity: 800 1000 750
Regular 700 700 700
Overtime 50 50 50
Subcontracting 150 150 130
Beginning Inventory 100 tires
Costs
Regular time $40 per tire
Overtime $50 per tire
Subcontract $70 per tire
Carrying cost $2 per tire per month
-
EPT 432 Production Management Laboratory Module
Page 10 of 12
Illustration below showed the structure the transportation table
and initial feasible
solution. However, the transportation method is flexible when
costs are linear but does
not work when costs are non-linear.
The total cost for the initial solution is $105,900.
-
EPT 432 Production Management Laboratory Module
Page 11 of 12
EXERCISE
1. The president of Hill Enterprise, Terri Hill, projects the
firms aggregate demand
requirements over the next 8 months as follows:
January 1400 May 2200
February 1600 June 2200
March 1800 July 1800
April 1800 August 1400
Her operations manager is considering a new plan, which begins
in January with 200
units on hand and ends with zero inventories. Stock out cost of
lost sales in $100 per
unit. Inventory holding cost is $20 per unit per month. Ignore
any idle time costs. The
plan is called plan A.
Plan a: Vary the workforce level to execute a chase strategy by
producing the quantity demand in the prior month. The December
demand and rate of production
are both 1,600 units per month. The cost of hiring additional
workers is $5000 per
100 units. The cost laying off workers is $7500 per 100 units.
Evaluate the plan.
2. Haifa Instruments, an Israeli producer of portable kidney
dialysis units and other medical products, develops a 4 months
aggregate plan. Demand and capacity in
units are forecasts as follows:
Capacity
Source Month 1 Month 2 Month 3 Month 4
Labor
Regular time 235 255 290 300
Overtime 20 24 26 24
Subcontract 12 15 15 17
Demand 255 294 321 301
The cost of producing each dialysis units is $985 on regular
time, $1319 on overtime and
$1500 on a subcontract. Inventory carrying cost is $100 per unit
per month. There is to be
no beginning or ending inventory in stock and backorders are not
permitted. Set up a
production plan that minimizes cost using the transportation
method.
-
EPT 432 Production Management Laboratory Module
Page 12 of 12
LAB 2
AGGREGATE PLANNING
Lab Result
SCHOOL / PROGRAMME OF :___________________________
DATE OF LABORATORY :___________________________
GROUP MEMBERS NAME : (Reminder: Do not accept your group member
to sign if his/her contribution is not satisfy)
1)_______________________________signature:__________
2)_______________________________signature:___________
3)_______________________________signature:__________
Marks: