    Jaipur CMP

    Percent Share of public transit- buses: 31% (2009)

    Public Transit Improvement Strategy:

    Alternative Scenarios considered:

    1. Do Nothing2. Bus Fleet Augmentation

    3. Augment Jaipur Commuter/ Regional rail system

    4. Bus rapid transit system (BRTS)

    5. High capacity rail based systems (Monorail/ LRT/ Metro)

  • 7/28/2019 Justification of Questions

    2/10

    Jaipur CMP

    Bus Augmentation

    Existing fleet- 2200Minibuses 1900

    Concerns:

    1. Unregulated routes

    2. Poor quality of buses

    3. Safety problems

    Steps to implement:

    1. Rationalize, add routes

    2. Modern buses (2450 new)

    3. ITS application

    Commuter Rail/ Regional Rail

    Augmentation

    4 rail corridors at present: Jaipur- Phulera

    Jaipur- Chomu

    Jaipur- Dausa

    Jaipur- Shivdaspura

    Concerns:1. Inadequate capacity

    2. Less terminals

    3. No dedicated tracks

    Steps to implement:

    1. More terminals (1-2 KM)2. Dedicated lines

  • 7/28/2019 Justification of Questions

    3/10

    Jaipur CMP

    Bus Rapid Transit System:

    Studies done on the BRTS have

    identified the complete networkfor the city.

    Concerns:

    1. ROW

    2. Traffic flows

    3. Future growth centres

    NB: the authorities did not spend

    time on the route alignment,

    preferring to take the shortest

    distance between 2 points.

  • 7/28/2019 Justification of Questions

    4/10

    Jaipur CMP

    Higher Order Mass Transit System:

    Studies done on the BRTS have

    identified the complete network forthe city.

    Concerns:

    1. ROW

    2. Traffic flows

    3. Future growth centres

    NB: the authorities did not spend

    time on the route alignment,

    preferring to take the shortest

    distance between 2 points.

  • 7/28/2019 Justification of Questions

    5/10

  • 7/28/2019 Justification of Questions

    6/10

    Jaipur CMP

    Public Transit Improvement Plan: 2011-2031

    A ring and radial network has been envisaged for the study area. It is proposed that the

    mobility corridors will be developed as multi modal corridors

    2011 2016 2021 2031

  • 7/28/2019 Justification of Questions

    7/10

    The authorities had initially decided to implement light rail, but then they went ahead

    with the bus rapid transit system under JnNURM.

    Metro started undergoing construction before the BRT was completed.

    P L A N N E D R A P I D T R A N S I T S Y S T E M

    PHASE BRT METRO

    I- East- West Modifications

    to be approved

    9.2 KM

    II- North-

    South

    26 KM, 5 KM

    dedicated lane

    Yet to begin

    The system recommended by the CMP:

    The authorities, when preparing the mobility

    plan talked about mode integration of BRT, Metroand Mono rail with the network feeder system

    (personalized vehicles, autos, taxis) in a

    systematic manner.

    Source: Comprehensive Mobility Plan- Jaipur

  • 7/28/2019 Justification of Questions

    8/10

    BRT plan

    P L A N N E D R A P I D T R A N S I T S Y S T E M

    Metro plan

    Source: Comprehensive Mobility Plan- Jaipur

    Superimposing the 2 plans:

    Overlaps are seen between the blue

    and the green lines.

    Legend:

    Metro lines

    BRT lines

  • 7/28/2019 Justification of Questions

    9/10

    BRT kick started by the

    government under the

    JnNURM schemeChange in government

    results in Metro given

    prominence

    Work for both continuingsimultaneously

    Jaipur BRT: Feasibility study done by PDCOR Ltd.

    Only about 5 KM of BRT lane

    created.

    After disruptions and delays, BRT

    now has an open system, with the

    buses intermingling in the mixedtraffic.

    Infrastructure needed for the BRT is

    still not completed.

    Jaipur Metro: Feasibility study done by DMRC.

    Two routes of 12 and 23 KM have

    been proposed.

    Infrastructure construction is still

    ongoing.

    No idea if the Metro is supposed toact as feeder to the BRT, or the BRT

    is to be support for Metro

    j a i p u r B R T v / s M E T R O : p r e s e n t c o n d i t i o n

    Source: Comprehensive Mobility Plan- Jaipur

  • 7/28/2019 Justification of Questions

    10/10

    1. Why do cities decide on one thing, change their mind halfway through, and then go

    ahead with another thing with modifications to old ones? What lead to this change

    of mind?

    2. What will be the probable impact of these decisions on the mode? What will be the

    final outcome of the transit plan?

    Q U E S T I O N S :

    I N F E R E N C E S :

    1. A comprehensive alternative analysis of the city is missing.

    2. The timeline decided for transit infrastructure has not been followed.

    3. The BRTS corridors are incomplete.