Back to overview2 Place , Date
OverviewOverview
1. Programme Structure
2. Development
3. Application
4. Assessment
5. Decision
Back to overview3 Place , Date
1. Programme Structure1. Programme Structure
INTERREG IIIC versus INTERREG IVC
321 MEUR ERDF
Cofinancing up to 75%/85%
One programme:
1 Managing Authority (Région Nord-Pas de Calais), 1 Audit Authority, 1 Certifying Authority
1 JTS in Lille and 4 Information Points in Rostock, Katowice (with support from Vienna), Valencia and Lille
Focus on Lisbon and Gothenburg Agendas
2 Types of Interventions
315 MEUR ERDF
Cofinancing up to 50% (up to 75% for Objective 1 Regions)
Four programmes: 4 Managing, 4 Audit and 4 Paying Authorities
4 JTS
All themes of regional and local public activities
3 Types of Operations
INTERREG IVCINTERREG IIIC
Back to overview4 Place , Date
INTERREG IVC – Management structures
1. Programme structure
Back to overview5 Place , Date
Information points• Rostock (IBSH), Germany:
Denmark, Estonia, Finland, Germany, Latvia, Lithuania, Sweden, Norway;
• Katowice (MRD), Poland, with support from the City of Vienna: Austria, Czech Republic, Hungary, Poland, Slovak Republic, Slovenia, Bulgaria, Romania;
• Valencia (GV), Spain: Cyprus, Greece, Italy, Malta, Portugal, Spain
• Lille (RNPC), France: Belgium, France, Ireland, Luxembourg, Netherlands, United Kingdom, Switzerland
1. Programme structure
Back to overview6 Place , Date
2. Development2. Development
Tools provided by the JTS and the Information Points (IPs)
• Website www.interreg4c.net
• Events
• Consultations
• Application Pack
• Project idea database
• Brochures, leaflets and articles in relevant media
Back to overview7 Place , Date
3. Application3. Application
Application Pack
• Programme Manual
• Application Form
• Activities Timeplan
• Co-financing Statement
Back to overview8 Place , Date
3. Application3. Application
Programme Manual
• Programme information
• Project development
• Application & selection
• Project implementation
• Project closure
Back to overview9 Place , Date
3. Application3. Application
Application Form
• General instruction
• Checklist
• Project summary
• Detailed project description
• Components
• Budget
• Partnership
Back to overview10 Place , Date
3. Application3. Application
Activities Timeplan
Back to overview11 Place , Date
3. Application3. Application
Co-financing Statement
Back to overview12 Place , Date
3. Application3. Application
Time table:
• 21 September 2007: Opening of first call
• 15 January 2008: Deadline for submission of
applications first call
• June 2008 (provisional) Opening of second call
• October 2008 (provisional) Deadline for submission of
applications second call
Back to overview13 Place , Date
4. Assessment4. Assessment
Assessment of applications
• Eligibility Check
• Quality Check
Back to overview14 Place , Date
4. Assessment4. Assessment
Eligibility Check (by JTS)
• Application Form submitted in due time
• Application is complete
• Application is fully and properly filled
• All Co-financing Statements are correctly filled and printed
• Partnership from a min of three countries, from which at least two partners must be from EU Member States and financed by the INTERREG IVC programme
• Mini-programmes: max of eight partners
Back to overview15 Place , Date
4. Assessment4. Assessment
Quality Check (by JTS and external experts)
1) Relevance of the proposal
2) Coherence of the proposal
3) Quality of results
4) Quality of management
5) Quality of partnership
6) Budget and finance
• Content related
• Implementation related
Back to overview16 Place , Date
4. Assessment4. Assessment
Scoring system
• Not eligible (Information to MC and Lead Applicant)
• Eligible
0 Knock out (objective of the project can not be fulfilled)
1 Very poor2 Poor3 Adequate4 Good5 Excellent
• Eligibility Check
• Quality Check
Back to overview17 Place , Date
4. Assessment4. Assessment
Time table (provisional):
• By end Feb 2008: Eligibility Check
• By end May 2008: Quality Check
Back to overview18 Place , Date
5. Decision5. Decision
MC decision based on recommendation of JTS
Back to overview19 Place , Date
5. Decision5. Decision
MC decision
• Two-thirds majority of Member States present needed
• Majority must include votes of countries having a Partner on its territory.
Back to overview20 Place , Date
5. Decision5. Decision
MC decision
• Approval without condition
• Approval with conditions
• Rejection
Back to overview21 Place , Date
5. Decision5. Decision
Time table (provisional):
• By end June 2008 Decision MC