Hydropower ‘Good Practice Guide’ Supplement to EA Hydropower manual Dr John Aldrick HO Water Resources Regulation manager
Jan 22, 2016
Hydropower ‘Good Practice Guide’Supplement to EA Hydropower manual
Dr John Aldrick
HO Water Resources Regulation manager
Environment Agency Policy on Hydropower
The slides showing hydrographs and flow duration curves were prepared to illustrate the impact a hydropower scheme may have on flows in the depleted reach. A range of different river types were used, as indicated in the title of each slide.
The hydrograph shows the gauged flow, without hydropower, the flow in the depleted reach with abstraction for hydropower, and the flow for hydropower (and other amenity purposes in the hydropower leat etc).The percentile flow values (Q50,Q95 values) used are for illustrative/investigation purposes.
This work has shown that there are further principles that can be drawn out and developed regarding the setting of hydropower abstraction/flows in the depleted reach. These will be developed further as part of the 'Good Practice Guidance'.
PRESENTATION CAVEATS
Environment Agency Policy on Hydropower
The Agency strongly supports the Government’s targets for the use of renewable energy. (10% - 2010, 20% - 2020)
BUT The Agency recognises both potential benefits &
environmental impacts of small-scale hydropower The Agency seeks to work constructively with the
hydropower industry to balance the benefits/impacts of hydropower
“We’re only borrowing the water, so what’s the big deal”
Agency regulatory regime
Strong legislative and environmental constraints which guide us
Range of matters to take into account e.g. water resources, fisheries, flood risk, water quality, navigation,
Water Resources permit Abstraction Licence/Impoundment licence/sec 158 agreement
Hydropower proposals test the Water Resources mandate to balance the needs of the developer and the environment
Abstraction Licence
Quantity that can be abstracted Max. Instantaneous, hourly, daily, annual
Residual flows in deprived reach measurement/control of abstraction & flows
Operating/control agreement Time limited licence (normally 12 years to CAMS Common End Date)
Fish Screening requirements Fish Pass requirements Derogation agreement ?- (quirk of legislation?)
Allows some further upstream abstraction
No abstraction charge if < 5Mw
Hydropower issues
Location environmental sensitivity
Volume/timing local impact
Residual flows deprived reaches flow measurement
Fisheries turbines screens fish-passes
Good Practice Guide
Appendix to Agency Hydropower Manual
To provide starting point for evaluating schemes
Checklist for criteria that may require EIA work Principles for setting Residual flow Flow measurement Screen/turbine relationship Principles of screen design
Hydropower Good Practice Guide
Being developed by EA/Hydropower Working Group Aims to :
provide Agency/developers with a consistent approach, common language and practical advice
clarify the Agency position and promote awareness But it won’t :
answer all your Hydropower development issues Agency Hydropower Manual(2003) available on website
Environmental site list audit
Red boxes need further work
Notes provide further guidance
Water Resources Conservation Chemical/physical
water quality Biological Water
quality Fisheries Flood Defence
tick box A Water Resources Checklist Note No.
YES NO
Is the scheme non-consumptive i.e. will 100% of any water abstracted be returned to the water course from which it was taken?
1
Is the scheme being built on existing infrastructure? 2
Will the turbine be placed directly within the weir / water course rather than in a separate channel?
3
Is there a flow-depleted channel? 4
Is there a flow-depleted weir? 4
Is it intended to increase the height of the impoundment? 8
Do surveys reveal any existing abstractions, including unlicensed ones, which will be derogated by the proposal? (1)
5
Is there an EA gauging station in the depleted reach or nearby that is likely to be affected by the scheme?
5
Will the developer accept a derogation consent within the proposed licence? 7
Checklist indicates factors that need to be considered
Deprived reach Flow
Flow to be left in deprived reach between intake and discharge - (how much?)
To meet fisheries, ecological, amenity, riparian, navigation needs
Dependant on environmental sensitivity May depend on the length of the deprived reach May vary with flow or season (eg migratory fish) Flow measurement or control Decisions impact on economics/viability of scheme
HydropowerLarge river Q50-Q95 Q50/Q95 2.01
Don hydropower
100
1000
10000
Oct
-89
Dec
-89
Feb
-90
Apr
-90
Jun-
90
Aug
-90
Oct
-90
Dec
-90
Feb
-91
Apr
-91
Jun-
91
Aug
-91
Oct
-91
Dec
-91
Feb
-92
Apr
-92
Jun-
92
Aug
-92
Oct
-92
Dec
-92
Feb
-93
Apr
-93
Jun-
93
Aug
-93
Oct
-93
Dec
-93
Feb
-94
Apr
-94
Jun-
94
Aug
-94
Date
Flo
w (
Ml/
d)
Long Term Natural
Qn50
Qn95
Hydro 1
Gen vol 1
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
0 10 20 30 40 50 60 70 80 90 100Flow Excedence %ile
Flo
w M
l/d
Long Term Natural
?
Hydro 1
Hydro 2
1.00 8808.610.00 2922.520.0 1762.130.0 1220.4
40.00 956.350.00 787.460.0 674.2
70.00 586.880.00 503.190.0 431.6
95.00 392.298.00 349.499.0 327.5
100.00 275.2
HydropowerLarge river Q50-Q100 Q50/Q95 2.01 141% more hydropower
Don hydropower
100
1000
10000
Oct
-89
Dec
-89
Feb
-90
Apr
-90
Jun-
90
Aug
-90
Oct
-90
Dec
-90
Feb
-91
Apr
-91
Jun-
91
Aug
-91
Oct
-91
Dec
-91
Feb
-92
Apr
-92
Jun-
92
Aug
-92
Oct
-92
Dec
-92
Feb
-93
Apr
-93
Jun-
93
Aug
-93
Oct
-93
Dec
-93
Feb
-94
Apr
-94
Jun-
94
Aug
-94
Date
Flo
w (
Ml/
d)
Long Term Natural
Qn50
Qn95
Hydro 1
Gen vol 1
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
0 10 20 30 40 50 60 70 80 90 100Flow Excedence %ile
Flo
w M
l/d
Long Term Natural
?
Hydro 1
Hydro 2
1.00 8808.610.00 2922.520.0 1762.130.0 1220.4
40.00 956.350.00 787.460.0 674.2
70.00 586.880.00 503.190.0 431.6
95.00 392.298.00 349.499.0 327.5
100.00 275.2
HydropowerSpaty river Q50-Q95 Q50/Q95 6.86116% more hydropower if Q100
Kilgram hydrograph
0
100
200
300
400
500
600
700
800
900
1000
Oct
-89
Oct
-90
Oct
-91
Oct
-92
Date
Flo
w (
Ml/
d)
Long Term Natural
Qn50
Qn95
Hydro 1 Q50 - Q951831590
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
0 10 20 30 40 50 60 70 80 90 100Flow Excedence %ile
Flo
w M
l/d
Long Term Natural
GES A2
Hydro 1
Hydro 2
Qn95
Qn50
1.00 10583.210.00 3603.220.0 2116.230.0 1407.2
40.00 957.050.00 657.160.0 471.7
70.00 316.480.00 200.690.0 127.1
95.00 95.898.00 70.699.0 55.7
100.00 33.4
HydropowerLarge Chalk river Q50-Q95 Q50/Q95 1.75
Chalk hydrograph
0
100
200
300
400
500
600
700
800
900
1000
Oct
-89
Dec
-89
Feb
-90
Apr
-90
Jun-
90
Aug
-90
Oct
-90
Dec
-90
Feb
-91
Apr
-91
Jun-
91
Aug
-91
Oct
-91
Dec
-91
Feb
-92
Apr
-92
Jun-
92
Aug
-92
Oct
-92
Dec
-92
Feb
-93
Apr
-93
Jun-
93
Aug
-93
Oct
-93
Dec
-93
Feb
-94
Apr
-94
Jun-
94
Aug
-94
Date
Flo
w (
Ml/
d)
Long Term Natural
Qn50
Qn95
Hydro 1 Q50 - Q95gen Q
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
0 10 20 30 40 50 60 70 80 90 100Flow Excedence %ile
Flo
w M
l/d
Long Term Natural
GES A2
Hydro 1
Hydro 2
Qn95
Qn50
1.00 1350.310.00 841.120.0 736.730.0 658.1
40.00 583.350.00 529.760.0 468.4
70.00 420.580.00 374.090.0 330.8
95.00 303.398.00 274.199.0 259.9
100.00 218.2
HydropowerLarge Chalk river Q50-Q100 Q50/Q95 1.75152% more hydropower
Chalk hydrograph
0
100
200
300
400
500
600
700
800
900
1000
Oct
-89
Dec
-89
Feb
-90
Apr
-90
Jun-
90
Aug
-90
Oct
-90
Dec
-90
Feb
-91
Apr
-91
Jun-
91
Aug
-91
Oct
-91
Dec
-91
Feb
-92
Apr
-92
Jun-
92
Aug
-92
Oct
-92
Dec
-92
Feb
-93
Apr
-93
Jun-
93
Aug
-93
Oct
-93
Dec
-93
Feb
-94
Apr
-94
Jun-
94
Aug
-94
Date
Flo
w (
Ml/
d)
Long Term Natural
Qn50
Qn95
Hydro 2Q50 - Q100genQ
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
0 10 20 30 40 50 60 70 80 90 100Flow Excedence %ile
Flo
w M
l/d
Long Term Natural
GES A2
Hydro 1
Hydro 2
Qn95
Qn50
1.00 1350.310.00 841.120.0 736.730.0 658.1
40.00 583.350.00 529.760.0 468.4
70.00 420.580.00 374.090.0 330.8
95.00 303.398.00 274.199.0 259.9
100.00 218.2
Hydropower50-50 flow split2/3rds of power
Hydropower Chalk hydrograph
0
10
20
30
40
50
Oct
-89
Dec
-89
Feb
-90
Apr
-90
Jun-
90
Aug
-90
Oct
-90
Dec
-90
Feb
-91
Apr
-91
Jun-
91
Aug
-91
Oct
-91
Dec
-91
Feb
-92
Apr
-92
Jun-
92
Aug
-92
Oct
-92
Dec
-92
Feb
-93
Apr
-93
Jun-
93
Aug
-93
Oct
-93
Dec
-93
Feb
-94
Apr
-94
Jun-
94
Aug
-94
Date
Flo
w (
Ml/d
)
Long TermNatural
Qn50
Qn95
Hydro 1 Q50 - Q95
gen Q
50%split
0
10
20
30
40
50
0 10 20 30 40 50 60 70 80 90 100Flow Excedence %ile
Flo
w M
l/d
Long Term Natural
GES A2
Hydro 1 Hydro 2Qn95Qn5050% split
1.00 53.610.00 32.720.0 24.830.0 19.7
40.00 15.650.00 12.760.0 10.5
70.00 8.880.00 7.590.0 6.3
95.00 5.598.00 4.899.0 4.4
100.00 3.3
Deprived reach Flow – principles?
Q90-95 default Hands Off Flow Q30/50 – HOF potentially available for hydropower Length of deprived reach 50/50 flow split?
Limited impact on flow variability 2/3rds of hydropower
Q50/Q95 < 3 (high baseflow) may have economic advantage of using Q100 if very short deprived reach
Fisheries
Turbines screens Migration spawning Habitats Directive
Turbines, screens, conservation
Conservation issues (HD, SSSI etc) impact on overall scheme
Fish friendliness of turbines Screen specification
Fish friendly turbines?
Crossflow Francis Kaplan Archimedean screw Waterwheel
Fish screens
Mostly physical wedge wire, mesh,bar
Fish screens are expensive
Recent R&D Mesh size flow velocities
Fish Screen - principles
Inlet velocity – ideally 0.25-0.3m/sec (at an angle to the flow) – leading to a
By-wash – to enable fish to escape Mesh size/turbine type
Tail race screens on salmonid rivers
1 3 6mm 16 25 50Crossflow Kaplan/ Screw/
Francis Waterwheel
10/ 12.5
Fish migration
Fish passes may involve retro-fit also likely to be costly New weirs Salmonid rivers first
Applicants should expect the Agency to:
Provide clear guidance on the licensing process Highlight key issues for environmental assessment Have an understanding of hydropower Provide information it has available Be consistent Provide timely responses, with explanations
Applicants should not expect the Agency to:
collect and analyse supporting data carry out the environmental assessment accept inadequate data or assessments give a binding view based on incomplete information design the scheme contravene its statutory duties
The Agency expects the applicants to:
to know their site, its environment and their objectives for the scheme (background)
consider and design their proposals carefully consider options/alternatives make early contact with the Agency and continue such
throughout the process appreciate the legislative and other constraints provide quality, focused environmental assessments provide appropriately detailed plans and drawings to
support any applications
Conclusions
Good Practice Guidance has not had final sign-off Will not answer all questions Provides ‘starting point’ for decision making Requires trialling/evaluation The Agency will move to National Permitting in 2008