How to Apply For Electricity Connection This handbook is published by SP PowerGrid Ltd in collaboration with SP Services Ltd Aug 2010 Procedures and requirements highlighted in this handbook are correct at the time of printing. Any changes that may arise will be reflected in the next edition. ISBN: 981-04-6932-3
129
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: How to Apply

How to Apply For Electricity Connection

This handbook is published by SP PowerGrid Ltd in collaboration with SP Services Ltd

Aug 2010 Procedures and requirements highlighted in this handbook are correct at the time of printing. Any changes that may arise will be reflected in the next edition.

ISBN: 981-04-6932-3

Page 2: How to Apply

Important Contact Numbers Tel No Fax NoSP SERVICES LTDGeneral Enquiry on Application 68238287 68238289For Connection to Transmission System 68238340

Consumer Connection Agreement

Contracts Section 68238282 68238289

Testing and Turn-on AppointmentSupply Application Section 68238287 68238289Installation Section 63092612 63092614

Opening of Utilities Accounts

Enquiry 1800-2222333 68238229 SP POWERGRID LTD

Endorsement of Substation Drawings 68238555 68238564• East zone 68238556 68238564• West zone

Installation of Meters

Deputy Director (Meter) 62777000 62777008Enquiry 62777005

1

Page 3: How to Apply

Table of Contents

1. GENERAL INFORMATION ................................................................................... 6 ....................................................................................................... 6 1.1 INTRODUCTION

....................................... 6 1.2 CONNECTION VOLTAGES AND SUPPLY FREQUENCY

............................................................................. 7 1.3 SUBMISSION OF APPLICATION

.............................................................................. 7 1.4 PROVISION OF A SUBSTATION

... 8 1.5 DOMESTIC PREMISES AND LOAD REQUIREMENT NOT EXCEEDING 45KVA

...................................................................................................................... 8 1.6 METER

............................................... 9 1.7 TARIFFS FOR NON-CONTESTABLE CUSTOMERS

..... 9 1.8 PAYMENT FOR ELECTRICITY CHARGES BY CONTESTABLE CUSTOMERS

1.9 OPENING ACCOUNT AND PAYMENT OF SECURITY DEPOSIT FOR USE OF

SYSTEM (UOS) CHARGES ...................................................................................... 9 1.10 ................................................................................. 9 TERMINATION OF ACCOUNT

1.11 . 9 DISCONNECTION OF SERVICE CABLES UPON TERMINATION OF ACCOUNT

2. APPLICATION FOR LOAD CONNECTION ........................................................ 11 .............................................................................. 11 2.1 DISTRIBUTION CONNECTION

............................................................................ 14 2.2 TRANSMISSION CONNECTION

3. TRANSMISSION CHARGES............................................................................... 16 3.1 CONSUMER CONNECTION AGREEMENT........................................................... 15

3.2 USE OF SYSTEM (UOS) CHARGES...................................................................... 16

2

Page 4: How to Apply

........................................................ 22 4. ENERGISATION AND TURN-ON PROCEDURES

4.1 PREMISES WHERE ELECTRICAL INSTALLATIONS ARE PREVIOUSLY

INSPECTED AND ENERGISED ............................................................................. 22 4.2 PREMISES WITH DIRECT CONNECTION FROM SPPA’S TRANSMISSION

SYSTEM.................................................................................................................. 23 ............................................................................... 25 4.3 BOOKING AN APPOINTMENT

4.4 PREMISES WITH INDIRECT CONNECTION (I.E. PREMISES IN A MULTI-

METERED DEVELOPMENT).................................................................................. 27 ....................... 28 4.5 MODIFICATION TO AN EXISTING ELECTRICAL INSTALLATION

................... 29 4.6 LICENCE TO USE OR OPERATE AN ELECTRICAL INSTALLATION

4.7 CERTIFICATES AND STATEMENTS FOR FIRST ENERGISATION OF SERVICE

CONNECTION ........................................................................................................ 29 .......................... 30 4.8 LEAD-TIME FOR APPLICATION FOR SERVICE CONNECTION

.... 32 4.9 NOTES TO BE READ IN CONJUNCTION WITH APPLICATION PROCEDURE

5. CUSTOMER'S INSTALLATION .......................................................................... 36 ............ 36 5.1 REQUIREMENTS FOR HT AND LT CONNECTION (22KV AND BELOW)

........................... 38 5.2 REQUIREMENTS FOR EHT CONNECTION (230KV AND 66KV)

5.3 INFORMATION ON SPPA NETWORK EARTHING SYSTEM (230KV, 66KV AND

22KV)....................................................................................................................... 39

6. METERING REQUIREMENTS ............................................................................ 40 .................................................................................................................. 40 6.1 GENERAL

........................................................................................... 41 6.2 LOCATION OF METER

6.3 METER/SERVICE BOARD SPECIFICATIONS (SINGLE-PHASE AND 3-PHASE

SERVICES, NOT EXCEEDING 100A PER PHASE) ............................................... 43 6.4 WIRING, LAYOUT OF METERS, MCBS, ETC IN CENTRALISED METER ROOMS,

METER COMPARTMENTS/RISER DUCTS/CUPBOARDS ................................... 43 ........................................................................ 43 6.5 SUBMISSION OF LAYOUT PLANS

6.6 METERS FOR 3-PHASE LOW TENSION CONNECTION (EXCEEDING 100A PER

PHASE) ................................................................................................................... 43 ......................................... 45 6.7 HIGH TENSION / EXTRA-HIGH TENSION METERING

................................................................ 46 6.8 TESTING OF METERING CTS AND VTS

................................................................................ 47 6.9 METERING REQUIREMENTS

6.10 .............................................................................. 48 CONTESTABLE CUSTOMERS

3

Page 5: How to Apply

7 Appendices 49 1 Application Form For Connection To SPPA Transmission System 50 2 Consultation Form For Connection To SPPA Transmission System 52 3 Form CS/3 – Letter Of Consent From The Landlord/Management Corporation 53 4 Form CS/3H – Letter Of Consent From The Housing & Development Board 54 5 Request To Handover Substation 55 6 Application For The Supply Of Water, Electricity And/Or Gas 56 7 Application For Interbank GIRO 57 8 Form CS/5 – Application For Inspection Of Electrical Installation 58 9 Types And Layout Of Substation 60 10 Submission Of Substation Site And Design Plans 61 11 6.6kV/LT Substation (4 drawings) 62 12 22kV/LT Substation (5 drawings) 66 13 Heavy Aluminium Louvred Door For Electric Substation (6 drawings) 71 14 Gate Details (2 drawings) 77 15 Checklist For Substation Building Plan Submission 79 16 Substation Layout Requirements To Be Incorporated In The Architectural Plans 80 17 General Requirements For EHT Substation (66kV And 230kV Only) 82 18 • Protection Requirements For Customer’s 22kV and 6.6kV

Main Incoming Switchgear 83 • Protection Requirements For Customer’s LT Main Incoming Switchgear 84 • Type 1: Customer 66kV Feeder Connection (Without Embedded Generation Plant) 85 • Type 2: Customer 66kV Feeder Connection

(With Embedded Generation Plant) 86 • Type 3: Customer 66 kV Feeder Transformer Connection 87 • Type 4: Customer 230kV Feeder Connection 88 • Type 5: Customer 230kV Feeder Transformer Connection 89

19 Application For De-Energisation/Re-Energisation (ADRE) 90 20 Statement For De-Energisation And Re-Energisation (SDRE) 91 21 Certificate Of Readiness For The Energisation Of Service Connection 92 22.1 Form CS/6 – Request For Installation Of Electricity kWh Meter For New Supply

Under Direct Supply From SPPA (Contestable Customer) 94 22.2 Form CS/7 – Request For Installation Of Electricity kWh Meter

(For Load Exceeding 45 kVA) Under Multi-Metered Building Scheme 95 23 Application For Appointment For Energisation Of Service Connection By Fax 96 24 • Technical Requirements For Service Cable And Meter Compartment

For Landed Houses 97 • Standard Meter Compartments At Gate Pillar 98

25 Standard Meter Board 99 26 Standard Size For Single-Phase Meter Board 100 27 Standard Size For Three-Phase Meter Board 101 28 CT Meter Panel For Low Tension Supply 102 29 Methods Of Sealing Meter Panels 103 30 Enclosure For Low Tension Metering Current Transformers 104 31 HT Metering Kiosk Requirements (For 1 or 2 Feeders) 105 32 HT Metering Kiosk Requirements (For 3 or 4 Feeders) 106 33 HT Metering Panel Requirements (For 1 or 2 Feeders) 108 34 Voltage Ratio, Sequence And Phase Angle Tests Report 109 35 Basis For The Service Connection Charge 110

4

Page 6: How to Apply

36 Standard Service Connection Cables 111 37 Certificate Of Compliance 112 38 Statement Of Turn-On Of Electricity 113 39 Requirements For Exempt Generation Facility not Exceeding 1MW 114 39A Capped Capacity Scheme 40 List Of Standards • IEC Standards 115 • British Standards 118 • Singapore Standards 119 • Other Standards 119 41 Form CS/12 – Application for Electrical Installation Inspection (up to 45kVA) 120 42 Application for Contestibility Status 121 43 Application to Open a MSS Account 122 44 Completion Certificate For Modification of Small Electrical Installation 123 45 Form E – Certificate of Fitness of Residential Unit 124

5

Page 7: How to Apply

2. General Information

1.1 INTRODUCTION

1.1.1 SP Services Ltd (SPSL), SP PowerAssets Ltd (SPPA) and SP PowerGrid Ltd (SPPG) are subsidiaries of Singapore Power Ltd. SPSL provides support services for the electricity market. It receives requests for electricity service connection; offers terms and conditions of service connection; arranges for service connection energisation/turn-on; and collects transmission charges, security deposits and charges for other services on behalf of SPPA. SPSL also bills customers for consumption. SPPA is the Transmission Licensee and owner of the transmission and distribution network. SPPG, the managing agent for and on behalf of SPPA, develops, operates and maintains the transmission and distribution facilities.

1.1.2 The supply of electricity and electrical installation practices are governed by the Electricity Act and its subsidiary legislation.

1.2 CONNECTION VOLTAGES AND SUPPLY FREQUENCY

1.2.1 In Singapore, the customers’ load installations are connected at the following voltages:

1.2.1.1 Transmission voltage of 66kV and 230kV

1.2.1.2 Distribution voltage consist of 230V, 400V, 6.6kV, 22kV (may vary within ± 6%)

The supply voltages are classified in the following categories:

1.2.1.3 Low Tension (LT) refers to 230V,single-phase and 400V, 3-phase

1.2.1.4 High Tension (HT) refers to 22kV and 6.6kV

1.2.1.5 Extra-High Tension (EHT) refers to 66kV 1.2.1.6 Ultra-High Tension (UHT) refers to 230kV

6

Page 8: How to Apply

1.2.2 The following connection schemes are provided, according to customers’ load requirements:

1.2.2.6 230V, 50 Hz, single-phase, up to a maximum of 23kVA, 100A

1.2.2.7 400V, 50 Hz, 3-phase, 4-wire.

1.2.2.8 22kV, 50 Hz, 3-phase, 3-wire for a Contracted Capacity of:

1.2.2.8.1 between 1,700 kW and 12,750kW for 2 HT 22kV services

1.2.2.8.2 between 12,751kW and 25,500kW for 4 HT 22kV services.

1.2.2.9 66kV, 50 Hz, 3-phase, 3-wire for connection with minimum Contracted Capacity of 25,500 kW.

1.2.2.10 230kV, 50 Hz, 3-phase, 3-wire for connection with minimum Contracted Capacity of 85,000 kW.

1.2.3 Where the customer requires a connection voltage and/or frequencies that differ

from those specified above, the customer is required to provide, install and maintain the necessary transformation equipment.

1.3 SUBMISSION OF APPLICATION

SPSL serves as a one-stop customer service centre. It receives all application forms on behalf of SPPA, and responds to all applications made by the Licensed Electrical Worker (LEW), who acts as the customer’s agent for connection to the transmission system. Customers applying for their installations to be connected to SPPA’s transmission system must submit their applications through their LEWs. Every application must be accompanied by all supporting documentation requested by SPSL. A copy of the Application Form is shown in Appendix 1.

For a development in the conception/planning stage, the customer is advised to seek consultation regarding SPPA’s requirements, such as the provision of a substation, for load connection. The Consultation Form (Appendix 2) must be submitted directly to SPPG by the customer’s LEW.

1.4 PROVISION OF A SUBSTATION

1.4.1 Direct service connection from SPPA's LT network to the customer’s installation is available for a small load requirement not exceeding 280kVA (400A). However, the provision of a direct service connection is dependent on the available network capacity in the vicinity. If there is insufficient capacity, the customer is required to provide a substation for the connection.

7

Page 9: How to Apply

1.4.2 For a larger load requirement exceeding 280kVA (400A), the customer has to provide a substation for SPPA to install necessary equipment to cater for the load.

1.5 DOMESTIC PREMISES AND LOAD REQUIREMENT NOT EXCEEDING 45kVA

1.5.1 For premises where the electricity meter has already been installed by SPPA and no extension or rewiring work is required, electricity service connection will be turned-on on the next working day from the date of the opening of an account with SPSL.

1.5.2 For premises where there is no electricity meter or where extension or rewiring work is required, the customer has to engage a LEW and submit an application for load connection (See Section 2).

1.6 METER All meters required for measuring a customer’s electricity consumption and demand (where applicable) are provided and maintained by SPPA. The customer provides meter boards, compartments, kiosks, etc as SPPA may require for the installation of its metering equipment.

1.6.1 Master- And Sub-Metering

A “Master-meter” is a meter measuring the consumption for all units and common areas in a building or cluster of buildings, which are used or occupied by multiple consumers. A “Sub-meter” is a meter measuring the consumption for a unit in a building or cluster of buildings used or occupied by multiple consumers, whose electricity is taken through a Master-meter. A master and sub-metering scheme is applicable for multi-tenanted premises. Under this scheme, the electricity supply is metered at the intake point and each tenant’s supply is also separately metered and billed under the appropriate tariff. The owner/developer/landlord shall be billed for the difference in the consumption between that metered at the intake point and the summated consumption of the tenants. Where the owner/developer/landlord takes supply at high tension and is responsible for stepping down the supply to 230V/400V for distribution to tenants, then a rebate of 2½% on the summated consumption of the tenants will be granted.

1.6.1.1 Multi-Metered Premises

The following are categories of multi-metered premises:

1.6.1.1.1 Residential premises which have landlord and tenant supply connections

1.6.1.1.2 Commercial complexes which have landlord and tenant supply connections

8

Page 10: How to Apply

1.6.1.1.3 Multi-storey factories or industrial complexes which have landlord and tenant supply connections

1.6.1.1.4 All multi-metered premises fall under the Master- and Sub-metering scheme with the exception of HDB residential premises.

1.7 TARIFFS FOR NON-CONTESTABLE CUSTOMERS

1.7.1 Tariffs are currently charged for low tension, high tension and extra-high tension electricity consumption.

1.7.2 Tariffs are subject to change and are published by SPSL from time to time. Online information on the latest electricity tariffs is available at www.spservices.com.sg.

1.8 PAYMENT FOR ELECTRICITY CHARGES BY CONTESTABLE CUSTOMERS Contestable customer pays to SPSL or authorised retailers, charges for electricity consumption as ascertained by meters, and transmission charges and other fixed charges as determined by SPSL. Payment for electricity charges must be made on or before the due date specified in the bill.

1.9 OPENING ACCOUNT AND PAYMENT OF SECURITY DEPOSIT FOR USE OF SYSTEM (UOS) CHARGES The customer must open an account and place a security deposit for UOS charges with SPSL upon application for energisation of service connection.

1.10 TERMINATION OF ACCOUNT

Non-contestable customers must give 4 business days' notice and contestable customers must give 12 business days’ notice to terminate an account. Such notices must be in writing to SPSL.

1.11 DISCONNECTION OF SERVICE CABLES UPON TERMINATION OF ACCOUNT Disconnection work involves the de-energisation and removal of service cables and equipment. The following are indicative lead times for the work:

9

Page 11: How to Apply

1.11.1 After the disconnection of LT, the lead-time is about 5 business days for the removal of LT service cables where road-opening work is not involved. Where road opening work is involved, a lead-time of 1 month is required.

1.11.2 After the disconnection of 6.6KV and 22KV where removal of service cables and equipment are involved, the lead-time is about 1 month.

1.11.3 For disconnection of 66kV and 230kV service cables, the service cable and equipment are de-energised within 10 business days, subject to the approval of the Power System Operator (PSO). The subsequent removal of service cables and equipment will depend on the operational requirement and approval of the PSO.

10

Page 12: How to Apply

Application For Load Connection

2.1 DISTRIBUTION CONNECTION

2.1.1 Introduction Each premises can have only one customer’s intake connection point. For modification of connection (such as upgrading of the load requirement) to existing premises, the customer is required to amalgamate the existing service connection into one intake.

2.1.2 Consultation For a development in the initial planning stage, the customer is advised to seek consultation with SPPG to ascertain SPPA‘s requirements for a new or modified connection to the transmission system. The LEW is required to submit the Consultation Form (Appendix 2), together with a site/location plan to SPPG. After receipt of the submission for consultation, SPPG will send a reply stating the approved load and other technical requirements, such as the provision of substation requirements necessary for the load connection to the transmission system.

2.1.3 Application

The Application Form (Appendix 1) together with a copy of the site/location plan, must be submitted to SPSL by the LEW for new or modified connections of new or existing premises to the transmission system.

2.1.3.1 Processing of Application Generally, SPSL responds to applications within 10 business days.

11

Page 13: How to Apply

The responses are made according to the following customer categories:

2.1.3.1.1 Contestable Customer

- A Consumer Connection Agreement, containing the service connection charge payable, the offer letter and the standard terms and conditions with respect to the distribution service connection.

- If a substation is required, a letter stipulating the requirements will be forwarded to the customer, and an Agreement offered after the substation plans are endorsed.

2.1.3.1.2 Non-Contestable Customer

- A Quotation, containing service connection charge payable and the conditions of service with respect to the distribution service connection

- If a substation is required, a letter stipulating the requirements will be forwarded to the customer. A Supply Agreement including the service connection charge payable and the terms & conditions with respect to the distribution service connection, is offered after the substation plans are endorsed.

2.1.3.2 Commencement of Work

- SPPG commences work only when the Agreement has been signed and received by SPSL, together with payment of service connection charges.

2.1.4 Type of Premises

2.1.4.1 Multi-Metered Premises

2.1.4.1.1 A multi-metered premises is one where the landlord/MCST (i.e. a master-metered consumer or directly connected consumer) receives bulk intake service connection from SPPA, and transforms/reticulates the supply to all the tenants (i.e. sub-metered consumers) within the premises. Any application for new or modified connection (including upgrading) for the bulk intake to the multi-metered premises must be made by the landlord through its LEW.

A master-metered consumer means a consumer that is responsible for the

common usage of a master-metered installation, which is connected to the transmission system.

A master-metered installation means an installation in which supply is received by a master-metered consumer and sub-metered consumers A sub-metered consumer means a consumer, other than a master-metered consumer, that receives supply in a master-metered installation via the electrical system owned by a master-metered consumer.

2.1.4.1.2 The landlord/MSCT or HDB, in the case of HDB premises, must ensure that the total applied load requirement for service connections to the multi-metered premises meet the total existing and future load requirements for all tenants. All

12

Page 14: How to Apply

tenants applying for any upgrading of load must do so through their master-metered consumer. In this regard, the master-metered consumer must approve the load of all tenants within the premises.

2.1.4.1.3 If the landlord’s existing approved load is insufficient to cater for the tenants’ load requirement, the landlord, as a master-metered consumer, must submit an application to SPSL for modification (upgrading) of service connection to the existing premises. In this case, the existing service cables are amalgamated with the new intake. Hence, there will not be separate direct connections to the tenants of such premises.

2.1.4.2 Premises in Private Housing, Industrial Estates, Commercial Developments Requiring Provision of Low Tension (LT) Distribution Network

2.1.4.2.1 For connection to premises where several parcels of land are to be sold or leased individually, one or more substations must be provided by the developer. Where the individual parcels of land are to be sold prior to development of these substations, details of the substation requirements and approved load must be included in the sales agreement by the future land parcel’s owner or lessee.

2.1.4.2.2 The developer must provide the development’s total load requirement and include the breakdown of the individual premises’ load requirement (as specified in the sales agreement) and the communal load requirement, if applicable.

2.1.4.2.3 In the case of landed housing estate development, the LEW must liaise with National Parks Board for the siting of overground distribution boxes on turfed areas. SPPA will provide and install the LT distribution network and service connection cables for the development.

2.1.4.3 Premises Involving Temporary Connection With Provision Of Substation

2.1.4.3.1 Special terms and conditions apply in such cases for temporary connection to construction worksites and other temporary premises. The term granted for temporary connection is usually 24 months.

2.1.4.3.2 Where there is a need for the provision of a temporary substation, the customer must provide the site and construct the structure of the substation according to the requirements of SPPA.

2.1.4.3.3 There will be a need to install the necessary cables and equipment to facilitate the temporary connection to the distribution network. The customer pays outright costs for the cables and a monthly hiring charge for the use of the equipment (including the cost of insuring the equipment) during the term for temporary connection.

13

Page 15: How to Apply

2.1.5 Provision of Substation

2.1.5.1 When an application for load connection necessitates the provision of a substation (See Appendices 9 and 10), a site must be provided and a substation constructed by the customer at its own cost.

2.1.5.2 The customer can either choose his substation to be a dedicated or non-dedicated

one (See Appendix 35). If the customer opts for a dedicated substation, he has to inform SPPG when he applies for connection. Otherwise, it shall be assumed that the substation would be non-dedicated.

2.1.5.3 The customer is advised to site the substation at an inconspicuous location, away

from the main entrance of the development and major public roads. The customer is also encouraged to harmonise, blend and integrate the substation with its development.

2.1.5.4 SPPG’s officers and vehicles will have full and unrestricted access to the

substation.

2.1.6 Service Connection Cables

Generally, SPPA supply, install and maintain customer service cable. However, if the customer intake point is at different level to the substation building, or service cable to be installed in cable tray/ladder, the customer shall supply, install and maintain the service cable. In the event that customer supplies the service cable, the customer’s LEW shall ensure that the service cable complied with SPPA cable specification, and submit cable sample and specification to Distribution Engineering Section for approval prior to procurement. The general type of cables for service connection is shown in Appendix 36.

2.2 TRANSMISSION CONNECTION

2.2.1 Consultation

2.2.1.1 A customer may choose to seek preliminary comments from SPPG via the connection consultation process before submitting a formal application. This practice is encouraged as incorporating SPPA’s requirements in a developer’s preliminary proposal would expedite the application process at a later stage.

2.2.1.2 To initiate the connection consultation process, the customer has to submit the Consultation Form (Appendix 2) through an LEW to SPPG.

2.2.2 Application

The following are steps in the application for service connection:

2.2.2.1 The customer submits the Application Form (Appendix 1) through an LEW to SPSL.

14

Page 16: How to Apply

2.2.2.2 A connection proposal, duly endorsed by the PSO, is given to the customer. It outlines the connection scheme, connection voltage, connection equipment and facilities required of the customer and the estimated connection charges. SPPG endeavors to respond to the customer, through SPSL, within 60 business days and 100 business days for 66kV connections and 230kV connections respectively.

2.2.2.3 Where the application requires the provision of an EHT substation, the customer must adhere to the general requirements attached in Appendix 17.

2.2.2.4 Once customer acknowledges acceptance of SPPG’s connection proposal, SPPG proceeds to execute the Consumer Connection Agreement through SPSL. The Agreement contains an Offer Letter, the standard terms and conditions associated with the connection and an estimation of the connection charges

2.2.3 Lead-Time for Application of Transmission Connection

2.2.3.1 The timely provision of electricity supply to a development involves the joint efforts of SPSL, SPPG, and the customer and their agents, such as the LEW. While SPSL and SPPG will make every effort to engineer and implement the connection scheme, it is at the same time essential for the new customers and their agents to co-operate via timely submission of applications and plans, timely acceptance of the terms and conditions of connection and compliance with the necessary SPPA or Transmission Code requirements.

2.2.3.2 As a guide for the customer and their agents, the normal lead-times for the events leading to the energisation of 66kV service connections are listed in the box below. The actual time-lead to energisation may vary for each connection, depending on the actual service cable length and the progress of intermediate events leading to completion of service connection works. Customers will be informed accordingly either at the point of application or at any time a review is required. For 230kV service connections, the customer will be informed of the lead-time only at the point of application.

NORMAL LEAD TIME FOR ENERGISATION OF 66kV SERVICE CONNECTION

New 66kV Connection from New 66kV Substation

Provided by Connection Applicant

New 66kV Connection from SPPA’s Existing

SubstationEvents

From day of execution of Consumer Connection Agreement to energisation of service connection

*21 months 26 months

Notes: * The Customer is required to handover the substation 8 months prior to target date of energisation of service connection.

15

Page 17: How to Apply

2. Transmission Charges

3.1 CONSUMER CONNECTION AGREEMENT

3.1.1 All customers are required to enter into a Consumer Connection Agreement with SPPA and to pay Use of System (UOS) charges. Customers having a direct connection to the transmission system must also pay a service connection charge. For non-contestable customers, the Connection Agreement is part of the Supply Agreement.

3.1.2 The Consumer Connection Agreement for customers taking HT supply at 6.6 kV/22 kV, EHT supply at 66 kV or UHT supply at 230 kV and above will, inter alia, state the Contracted Capacity, which is deemed to be the requirement for a period of five years. Customers cannot reduce their Contracted Capacity until the expiration of the 5-year period or additional 5-year period. Furthermore, a customer who terminates the supply agreement during the 5-year period or additional 5-year period will be required to pay SPPA through SPSL/Retailer, the Contracted Capacity Charge for the unexpired portion of the 5-year period.

3.1.3 UOS charges are payments for the use of the transmission services. The UOS charges are paid for electricity consumption at each metered intake supply point in accordance with the voltage at which a customer receives the electricity supply. The UOS charges are subject to annual review and the revised UOS charges will be published by SPPA.

3.1.4 In the case of HT and EHT supply to multi-metered premises, the landlord has to enter into a Connection Agreement for the network capacity required for his own load only, i.e. supply for common services, etc.

16

Page 18: How to Apply

3.1.5 The UOS Charges are applicable for the following categories of supplies :

• Low Tension (LT) Supplies (400V/230V)

Supply to Low Tension-Small Consumer Supply to Low Tension-Large Consumer

• High Tension (HT) Supplies (22kV and 6.6kV)

Supply to High Tension-Small Consumer, whose Contracted Capacity is less than 1,700 kW per month at each metered intake supply point.

Supply to High Tension-Large Consumer, whose Contracted Capacity is at least 1,700 kW per month at each metered intake supply point.

• Extra-High Tension (EHT) Supplies (66kV)

Supply to Extra-High Tension Consumer

Ultra-High Tension (UHT) Supplies (230kV and above)•

Supply to Ultra-High Tension Consumer • Temporary Supplies

Temporary Supplies apply only to LT and HT supplies for temporary civil engineering and building construction sites.

3.2 USE OF SYSTEM (UOS) CHARGES 3.2.1 Low Tension Small Customer

LT supplies (in kWh) to all non-contestable LT consumers are metered on a

monthly basis. A flat per kWh UOS rate is levied at each metered intake supply point.

3.2.2 Low Tension Large Customer

The large industrial and commercial LT consumers, who are contestable and have time-of-day metering, come under this category. LT Supplies to these contestable consumers are metered on energy (kWh) on a half-hourly time-of-day basis. The respective per kWh charges shall be levied at a “Peak” and an “Off-peak” period for the energy supplied at each metered intake supply point.

3.2.2.1 Peak Period Charge

The Peak Period Charge payable shall be the monthly charge based on the energy (in kWh) supplied to an installation during the peak period, 7.00 am to 11.00 pm, in that month.

17

Page 19: How to Apply

3.2.2.2 Off-Peak Period Charge

The Off-Peak Period Charge payable shall be the monthly charge based on the energy (in kWh) supplied to an installation during the off-peak period, 11.00 pm to 7.00 am, in that month.

3.2.3 High Tension, Extra-High Tension and Ultra-High Tension Supplies

For HT (i.e. HT Small and HT Large), EHT and UHT Supplies, UOS Charges shall be levied at each metered intake supply point as follows : a. Contracted Capacity Charge; b. Peak Period Charge; c. Off-peak Period Charge; d. Reactive Power Charge; e. Uncontracted Capacity Charge, and f. Uncontracted Standby Capacity Charge (applicable to consumers with

embedded generation who opt to cap their power demand drawn from the network).

3.2.3.1 Contracted Capacity Charge 3.2.3.1.1 The Contracted Capacity Charge is a monthly charge payable in any month for

the Contracted Capacity at each metered intake supply point of a consumer. The Contracted Capacity of a consumer's installation shall be the supply capacity (in kW), which is requested for that metered intake supply point. For the avoidance of doubt, and without prejudice to paragraph 3.2.3.1.3 herein, the consumer shall not be allowed to reduce the declared Contracted Capacity upon the signing of the Consumer Connection Agreement / Supply Agreement, notwithstanding the fact that the energisation of the new supply has still not taken place.

3.2.3.1.2 For a new supply, the Contracted Capacity shall be deemed to be the consumer's

requirement for a binding period of 5 years from the target date or the commissioning date for SPPA’s plant and equipment, except for the service cable, whichever is later. For new HT, EHT and UHT supplies, the minimum Contracted Capacity for each metered intake supply point shall be as follows :

HT with 1 or 2 feeders 1,700 kW, HT with 3 or more feeders 12,750 kW, EHT 25,500 kW, UHT 85,000 kW.

For new supplies, a request may be made for intermediate steps before the full

Contracted Capacity is implemented during the first year of the 5-year binding period. The first step shall be at least one quarter (¼) of the consumer’s requested full Contracted Capacity at each metered intake supply point.

3.2.3.1.3 After the initial 5-year period, the consumer may, by giving one month's notice in

writing, reduce his Contracted Capacity at each metered intake supply point subject to the following minimum values :

18

Page 20: How to Apply

HT with 1 or 2 feeders 850 kW, HT with 3 or more feeders 6,375 kW, EHT 12,750 kW, UHT 42,500 kW.

Any such reduction in Contracted Capacity shall be deemed to be the consumer’s requirements for one year commencing from the first day of the billing cycle that follows after the end of the notice period and the consumer shall not be entitled to make any further reduction in the Contracted Capacity within one year following any such reduction. Market Support Services Licensee will inform the consumer of the date of their billing cycle.

3.2.3.1.4 Upward revision of the Contracted Capacity may be allowed during the validity of the binding period of 5 years or 1 year of the Contracted Capacity. The revised Contracted Capacity shall in such cases commence from the first day in which it is effective and shall apply for the remainder of the initial 5-year period or for a minimum period of 1 year, whichever is the greater, provided SPPA is not required to install new or additional equipment. Downward revision during such binding periods will not be allowed.

3.2.3.1.5 A consumer whose revised contracted capacity requires SPPA to install new or

additional equipment shall be considered as receiving a new supply with a new 5-year binding period.

3.2.3.1.6 For a new development with landlord and tenants, the supply capacity required

by the landlord himself must meet the minimum values set out in paras 3.2.3.1.2 to 3.2.3.1.5 above in order for the landlord to qualify for HT, EHT or UHT supplies.

3.2.3.1.7 For those HT, EHT or UHT consumers whose Contracted Capacity are below the

minimum values specified above before the implementation of these rates, they may request to increase (but not decrease) their Contracted Capacity in the manner as described above.

3.2.3.2 Peak Period Charge

The Peak Period Charge payable shall be the monthly charge based on the energy (in kWh) supplied to an installation during the peak period, 7.00 am to 11.00 pm, in that month.

3.2.3.3 Off-Peak Period Charge

The Off-Peak Period Charge payable shall be the monthly charge based on the energy (in kWh) supplied to an installation during the off-peak period, 11.00 pm to 7.00 am, in that month.

3.2.3.4 Reactive Power Charge

The Reactive Power Charge is a monthly charge payable in any month for the installation's excess kVArh consumption. The excess kVArh shall be the

19

Page 21: How to Apply

difference by which the installation's kVArh consumption drawn from the network in that month is greater than 62% of its kWh consumption drawn from the network in the same month.

3.2.3.5 Uncontracted Capacity Charge 3.2.3.5.1 The Uncontracted Capacity Charge is a monthly charge payable in any month for

the Uncontracted Capacity utilised. The Uncontracted Capacity is the capacity in kW by which the maximum demand in kW (measured by the half-hour integration meter) exceeds the Contracted Capacity at that metered intake supply point.

3.2.3.5.2 The Uncontracted Capacity Charge shall apply to the following HT, EHT and UHT

consumers :

a. Normal consumers without embedded generation; b. Consumers with embedded generation whose monthly maximum

demand in kW is the maximum summated demand in kW in the month, determined by summating the kW demand drawn from the network and the kW output from embedded generation (i.e. Summation Scheme); and

c. Consumers with embedded generation who opt to cap their power

demand in kW drawn from the network in the event that the maximum demand in kW (measured by the half-hour integration meter) exceeds the Contracted Capacity at that metered intake supply point (i.e. Capped Capacity Scheme or Extended Capped Capacity Scheme). The Uncontracted Capacity for these consumers shall be limited to 20% of the Contracted Capacity.

3.2.3.6 Uncontracted Standby Capacity Charge 3.2.3.6.1 The Uncontracted Standby Capacity Charge is a monthly charge payable in any

month for the Uncontracted Standby Capacity utilised. The Uncontracted Standby Capacity Charge shall apply to those HT, EHT and UHT consumers with embedded generation who opt for the Capped Capacity Scheme or Extended Capped Capacity Scheme.

3.2.3.6.2 For Capped Capacity Scheme, the Uncontracted Standby Capacity Charge

applies in the event the demand in kW drawn from the network (measured by the power meter) exceeds 120% of the Contracted Capacity at that metered intake supply point for a duration of more than 10 seconds continuously.

3.2.3.6.3 For Extended Capped Capacity Scheme, the Uncontracted Standby Capacity

Charge applies in the event :

• the demand in kW drawn from the network exceeds 120% and up to 200% of the Contracted Capacity at that metered intake supply point for a duration of more than 100 seconds continuously; or

20

Page 22: How to Apply

• the demand in kW drawn from the network exceeds 200% of the Contracted Capacity at that metered intake supply point for a duration of more than 10 seconds continuously.

3.2.3.6.4 For the avoidance of doubt, in the event Uncontracted Standby Capacity Charge applies in accordance with Clauses 3.2.3.6.2 and 3.2.3.6.3 above, Uncontracted Capacity Charge shall also be applicable for the Contracted Capacity portion which is 20% above the customer’s declared Contracted Capacity.

3.2.4 TEMPORARY SUPPLIES

3.2.4.1 Temporary Supplies apply only to LT and HT supplies for temporary civil engineering and building construction sites. The UOS charges applicable for the LT and HT temporary supplies shall be the same as those used for LT and HT supplies respectively.

3.2.4.2 For temporary supplies at HT, the Contracted Capacity shall apply for a minimum

binding period of 1 year up to a maximum of 2 years. Upward revision of the Contracted Capacity may be allowed during the validity of the binding period of the Contracted Capacity. The revised Contracted Capacity shall in such cases apply for a minimum period of 1 year, provided SPPA is not required to install new or additional equipment. Downward revision during such binding period will not be allowed. A consumer whose revised Contracted Capacity requires SPPA to install new or additional equipment, shall be considered as receiving a new temporary supply. The term granted for temporary connection is 2 years.

21

Page 23: How to Apply

Energisation and 2.

Turn-on Procedures

The term ‘energise’, in the case of a customer’s installation that is directly connected to the transmission system, refers to the closing of a circuit breaker or other isolating device that is owned and controlled by SPPA. “Energisation”, “de-energisation” and “re-energisation” and all grammatical variations of the term shall be interpreted accordingly.

Arrangements need to be made with SPSL for energisation of the service connection and turn-on of a customer’s electrical installation. This is taken care of by the LEW. The following are arrangements needed by type of premises:

4.1 PREMISES WHERE ELECTRICAL INSTALLATIONS ARE PREVIOUSLY INSPECTED AND ENERGISED

4.1.1 NON-DOMESTIC PREMISES (LOAD REQUIREMENT NOT EXCEEDING 45kVA), AND DOMESTIC PREMISES WHERE ELECTRICAL INSTALLATIONS ARE PROVIDED AND PRE-INSPECTED OR PREVIOUSLY INSPECTED AND ENERGISED

4.1.1.1 This category includes all new HDB apartments and dwelling units in some private residential developments where electrical installations are provided and inspected in advance. It also includes non-domestic premises (supply capacity not exceeding 45kVA) and domestic premises where the existing electrical installations and service connections are intact and only the supply is required to be re-energised.

4.1.1.2 The customer has to open an account with SPSL for electricity service connection (See 4.9.2).

4.1.1.3 The customer is given an appointment for turn-on of service connection. This appointment date is normally the next working day from the date the account is opened. For electrical safety reasons, the customer or his representative must be present at the premises for the turn-on of electricity service connection.

22

Page 24: How to Apply

4.1.2 NON-DOMESTIC PREMISES (LOAD REQUIREMENT EXCEEDING 45kVA) WHERE ELECTRICAL INSTALLATIONS ARE PREVIOUSLY INSPECTED AND ENERGISED

4.1.2.1 This category includes non-domestic premises (supply capacity exceeding 45kVA)

where the existing electrical installations, meters and service connections are intact and only the supply is required to be re-energised.

4.1.2.2 The customer has to open an account with SPSL for electricity service connection

(See 4.9.2). 4.1.2.3 The customer has to apply for a licence from Energy Market Authority (EMA) to

use or operate the electrical installation through an appropriate class of licensed electrical worker.

4.1.2.4 Upon submission of the licence, the customer is given an appointment for turn-on

of service connection. This appointment date is normally the next working day from the date of receiving the licence. The licensed electrical worker must be present at the premises to issue a Certificate of Compliance (COC) to SPSL during the turn-on of electricity service connection.

4.2 PREMISES WITH DIRECT CONNECTION FROM SPPA’S TRANSMISSION SYSTEM

4.2.1 Domestic Premises (all load requirements)

4.2.1.1 The customer opens an account with SPSL, if an account has not already been opened (See 4.9.2).

4.2.1.2 Upon completion of the electrical installation and receipt of notification from SPPG on energisation/readiness of the service connection, the LEW books an appointment with SPSL for inspection and turn-on of the customer’s installation. For load below 45kVA, this is done by submitting Form CS/5 (Appendix 8) – Application For Inspection of Electrical Installation and the Certificate of Compliance (COC) (See 4.7.1) to Supply Application of SPSL. If the Application is done through facsimile, Form CS/12 (Appendix 41) – Application for Electrical Installation Inspection (up to 45kVA) is required. For load above 45kVA, this is done by submitting the Inland Revenue Authority of Singapore (IRAS) letter stating the official addresses, COC, Form E (Appendix 45) – Certificate of Fitness of Residential Unit and the as-build Single Line Drawing (SLD) to Installation Section of SPSL.

4.2.1.3 The electrical installation is connected to SPPA’s transmission system on the scheduled turn-on date if the electrical installation is safe to receive electricity supply. The LEW must be present during inspection of the electrical installation by SPSL. For electrical safety reasons, the customer or his representative must also be present at the premises for the turn-on of electricity service connection. A ‘PASS’ Inspection Report is issued by SPSL on-site upon successful turn-on of the customer’s installation.

23

Page 25: How to Apply

4.2.2 Non-Domestic Premises

4.2.2.1 Load Requirement Not Exceeding 45kVA

4.2.2.1.1 The customer opens an account with SPSL, if this has not already been done (See 4.9.2).

4.2.2.1.2 Upon completion of the electrical installation and receipt of notification from SPPG on energisation of the service connection, the LEW books an appointment with SPSL for inspection and turn-on of the electrical installation. This is done by submitting Form CS/5 (Appendix 8) – Application For Inspection of Electrical Installation and the COC form (See 4.7.1) to Supply Application of SPSL. If the Application is done through facsimile, Form CS/12 (Appendix 41) – Application for Electrical Installation Inspection (up to 45kVA) is required.

4.2.2.1.3 The electrical installation is connected to SPPA’s transmission system on the scheduled turn-on date if the electrical installation is safe to receive electricity supply. The LEW must be present during inspection of the electrical installation by SPSL. For electrical safety reasons, the customer or his representative must also be present at the premises for the turn-on of electricity service connection. A ‘PASS’ Inspection Report for the customer’s installation is issued by SPSL on-site upon successful turn-on.

4.2.2.2 Load Requirement Exceeding 45kVA

4.2.2.2.1 The customer submits an application for an account (See 4.9.2), to SPSL if this has not already been done, and applies for a licence from Energy Market Authority (EMA) to use or operate an electrical installation.

4.2.2.2.2 Upon completion of the electrical installation and receipt of notification from SPPG on the readiness of service connection, the LEW must inspect and test the electrical installation before booking an appointment with SPSL’s Installation Branch for the installation of meter and energisation of service connection by SPPG. This is done by submitting a letter of confirming the readiness of the service connection and the COC form (See 4.7.1). Alternatively, the LEW can submit the Application for Appointment for Energisation of the Service Connection By Fax (Appendix 23).

4.2.2.2.3 The LEW requesting for energisation of supply line has to arrange for the LEW responsible for the operation of the electrical installation and the customer (or his representative) to be present during the energisation.

4.2.2.2.4 The electrical installation is connected to SPPA’s transmission system on the scheduled energisation date if the electrical installation is safe to receive electricity supply. The LEW must issue a Certificate of Readiness (COR) form (See 4.7.2) to SPPG at site, prior to energisation of the service connection.

4.2.2.2.5 Upon successful energisation of service connection to the customer’s installation from SPPA’s direct connection, all parties are to acknowledge on the Statement of Turn-On of Electricity (See 4.7.3).

24

Page 26: How to Apply

4.3 BOOKING AN APPOINTMENT

4.3.3 Before booking an energisation and turn-on appointment, the LEW must ensure the following:

4.3.3.1 Metering requirements, where applicable, have been submitted and formal clearance has been given by SPPG’s Meter Section. All necessary meters have been installed.

4.3.3.2 The customer’s main incoming switchgear, protection system and earthing system have been successfully tested by an LEW. The HT metering panel has been provided, and testing of the metering current transformers/voltage transformers have been carried out and meters installed by Meter Section.

4.3.3.3 The service cables to the installation are ready to be energised.

4.3.3.4 A utilities account has been opened, an Agreement has been signed, and a security deposit for UOS has been paid by the customer.

4.3.3.5 A licence to use or operate the electrical installation, where applicable, has been obtained from EMA.

4.3.3.6 For service connection at a system voltage level of 66kV and above, the final clearance for the EHT switching procedure must be obtained from the PSO prior to the confirmation of the first energisation date.

Notes: (1) The EHT switching procedure must be jointly prepared and endorsed by the

LEW, who is authorised to perform EHT switching (at customer’s installation), and SPPG’s Project Engineer.

(2) For 66kV and above, the LEW must submit the COC form to SPPG’s Project

Engineer.

25

Page 27: How to Apply

4.3.4 Making An Appointment for Energisation Of Service Connection Direct From SPPA’s Transmission System:

4.3.4.1 Load Requirement Not Exceeding 45kVA To make an appointment to turn-on electricity supply, the LEW shall submit Form CS/5 (Appendix 8) – Application For Inspection of Electrical Installation on behalf of the customer, and a copy of the Certificate of Compliance (COC) to request for an inspection and turn-on to the premises. The LEW is encouraged to submit application via: Fax to: 68238289 Mail to: Customer Services

Supply Application Section 111 Somerset Rd, #01-10 Singapore Power Building Singapore 238164

Or drop the application into our drop-in box located in our Customer Service Centre at the above address.

4.3.4.2 Load Requirement Exceeding 45kVA Up To 22kV Supply Voltage An appointment for energisation of electricity service connection of load requirements greater than 45kVA and up to 22kV supply voltage can be made as follows: To make an appointment in person to energise the service connection, the LEW or his representative submits the letter confirming the readiness of service connection and the COC to SPSL’s Installation Section at 7th storey, St. James District Office, Keppel Road. Alternatively, the LEW can submit the Application for Appointment for Energisation of the Service Connection together with COC Form by Fax (Appendix 23) to Installation Section. The original copy of the COC Form must be submitted to SPPG on the scheduled energisation date.

4.3.4.3 A lead-time of 14 business days is required for the LEW to request for the energisation of SPPA’s service connection and turn-on of the customer’s installation.

4.3.4.4 Energisation of service connection involves several parties. An officer at SPSL’s Installation Section co-ordinates with SPPG for the energisation of the service connection for supply taken directly from SPPA’s transmission system.

26

Page 28: How to Apply

4.3.5 Submission Of Application For New EHT And HT Consumers Who Wish To Be Contestable At Time Of Turn-On

4.3.5.1 The consumer must subscribe and install one dedicated telephone line per metering point (adjacent to meter panel) to be used for the purpose of remote metering.

4.3.5.2 The LEW shall submit a copy of the duly completed Form CS/6 (Appendix 22.1) - Request from Contestable Customer for Installation of Electricity kWh Meter with the active dedicated telephone line number clearly stated to SPSL for the installation of TOD Meter.

4.3.5.3 The LEW shall proceed to liaise directly with Meter Section of SP PowerGrid to have the TOD meter installed.

4.3.5.4 Upon completion of the installation of the TOD meter and telephone line, the consumer shall submit a copy of the duly completed Application for Contestability Status (Appendix 42) and Application to open a MSS Account (Appendix 43) to Client Relations Branch of SPSL at 111 Somerset Road, #06-05 or via fax: 6823-6800 at least 12 business days prior to your arrangement for the turn-on appointment.

4.3.5.5 If the customer chooses to purchase electricity from a Retailer with effect from the turn-on date, the Retailer must submit a transfer request to SPSL at least 1 business day before the turn-on date.

4.3.5.6 Otherwise, SPSL will arrange to buy electricity for the customer from the wholesale electricity market and the customer will be charged for the electricity consumption at prevailing wholesale spot prices. In this case, a security deposit to SPSL is required.

4.3.5.7 The LEW shall proceed to apply to EMA for EI Licence.

4.3.5.8 The LEW shall submit a copy of COC, EI Licence, IRAS’s Letter stating official address and book an appointment for energisation of service connection at Installation Section of SPSL at St James District Office (for HT Supply) or at Transmission Projects III Section of SP PowerGrid @ Kallang Bahru District Office (for EHT Supply).

4.4 PREMISES WITH INDIRECT CONNECTION (I.E. PREMISES IN A MULTI-METERED DEVELOPMENT)

4.4.1 Load Requirement Not Exceeding 45kVA

4.4.1.1 The customer opens an account with SPSL (See 4.9.2) if this has not already done.

4.4.1.2 The customer submits an Application for Inspection of Electrical Installation (Appendix 8) to SPSL through the LEW together with a Letter of Consent from the

27

Page 29: How to Apply

Landlord/Management Corporation or HDB (Appendices 3 and 4). The LEW can also book an appointment for inspection of the electrical installation at the time of submission of the application and, in the meantime, proceed to carry out the wiring/extension work. The procedure of booking an appointment is as in 4.3.4.1 above.

4.4.1.3 The LEW is responsible for arranging the energisation of the service connection with the relevant party responsible where connection is taken via the landlord’s switchboard - such as in HDB, JTC or other private multi-metered buildings.

4.4.1.4 Service connection will be turned-on on the scheduled inspection date if the electrical installation is safe to receive electricity supply. The LEW must be present during the inspection. A ‘PASS’ Inspection Report for the customer‘s installation will be issued on-site by SPSL upon successful turn-on. The LEW must issue a Statement of Turn-On of Electricity and this must be acknowledged by the relevant parties.

4.4.2 Load Requirement Exceeding 45kVA (Multi-Metered Building Scheme)

4.4.2.1 When the premises is ready for installation of meters, the customer shall proceed to open a utilities account with payment of security deposit to SPSL.

4.4.2.2 The LEW shall proceed to apply to EMA for EI Licence before the electricity supply is turned on.

4.4.2.3 The LEW shall submit Form CS/3 (Appendix 3) or Form CS/3H (Appendix 4), Form CS/7 (Appendix 22.2) - Request for Installation of Electricity kWh Meter (for Load Exceeding 45kVA) and a copy of COC and EI Licence to SP Services declaring the account activation date (which is the proposed turn-on date).

4.4.2.4 The LEW shall proceed to liaise with Meter Section of SP PowerGrid to install meters.

4.4.2.5 For HT Supply, the consumer is required to sign an agreement with SP PowerGrid before SP Services can process the application for installation of TOD meter.

4.4.2.6 The LEW shall be responsible for arranging the energisation of the service connection with the relevant party where the connection is taken via landlord’s switchboard such as HDB, JTC or private multi-tenanted buildings.

4.4.2.7 Landlord’s LEW shall issue the Statement of Turn-On of Electricity (SOTO) upon successful turn-on.

4.5 MODIFICATION TO AN EXISTING ELECTRICAL INSTALLATION

4.5.1 Modification work (e.g. extension, rewiring, shifting of meter) carried out to an existing electrical installation where a licence to use or operate is not required, must be inspected by SPSL before the new/modified portion of the wiring can be used.

28

Page 30: How to Apply

4.5.2 The LEW must submit an application for inspection (Form CS/5, Appendix 8) by SPSL for the modified electrical installation.

4.5.3 Submission Of Completion Certificate For Modification of Small Electrical Installation (Exempted From Licensing)

4.5.3.1 The LEW shall submit to SPSL the duly completed Form CS/5 (Appendix 8), together with Form CS/3 (Appendix 3) or Form CS/3H (Appendix 4) and the Completion Certificate for Modification of Electrical Installation (Appendix 44) on behalf of the customer. (Note: First-time inspection is free-of-charge and Form CS/3 or Form CS/3H is not required for HDB residential premises)

4.5.3.2 SPSL conducts spot-checks for those system-selected applications.

4.5.3.3 For those applications not selected, acknowledgement letters will be sent to both the customer and the LEW.

4.5.3.4 If the inspection is “Failed”, the LEW will have to come to SPSL with a copy of the “Failed” letter to arrange for a re-inspection. A re-inspection fee is payable.

4.5.3.5 If the inspection is “Passed”, acknowledgement letter will be sent to both the customer and the LEW.

4.6 LICENCE TO USE OR OPERATE AN ELECTRICAL INSTALLATION

4.6.1 For service connection to non-domestic premises, residential buildings and condominiums with an approved load greater than 45kVA, and temporary connection for building construction and engineering work, irrespective of connection load, the customer must obtain a licence from EMA to use or operate the electrical installation.

4.6.2 It must be noted that SPPG cannot energise the service connection until such a licence is issued to the customer.

4.7 CERTIFICATES AND STATEMENTS FOR FIRST ENERGISATION OF SERVICE CONNECTION

4.7.1 Certificate of Compliance (COC)

4.7.1.1 The LEW must ensure that the electrical installation complies with the requirements of the Electricity Regulations, Singapore Standards CP5, relevant technical requirements and all other applicable standards. This compliance must be made in the COC form (Appendix 37). The COC form must be submitted to SPPG through SPSL when requesting for an energisation appointment.

29

Page 31: How to Apply

4.7.2 Certificate of Readiness (COR)

4.7.2.1 The LEW has to certify the readiness of the installation. This certification must be made in the COR form (Appendix 21). The LEW must hand over the COR form to SPPG’s Project Officer on the actual date of first energisation.

4.7.3 Statement of Turn-On of Electricity

4.7.3.1 Immediately after the successful first energisation of the service connection, SPPG will issue a Statement of Turn-On of Electricity (Appendix 38). All parties are to acknowledge by signing the form. The completed form will be given to all parties and a copy forwarded to SPSL.

4.8 LEAD-TIME FOR APPLICATION FOR SERVICE CONNECTION

4.8.1 The timely provision of electricity supply to a development involves the joint efforts of SPSL, SPPG, and the customer and his agents, such as the LEW. While SPSL and SPPG will make every effort to engineer and implement the connection scheme, it is at the same time essential for the new customers and their agents to play their part such as the early submission of applications and plans, the acceptance of terms and conditions of connection including making the necessary payments and the compliance of the necessary SPPA or Transmission Code requirements.

4.8.2 As a guide for the customer and his agents, the normal lead-times for the various events are listed on the following page. Depending on the progress and completion time of precedent events, the actual completion dates of events leading to the energisation of the service connection may need to be reviewed and adjusted.

30

Page 32: How to Apply

NORMAL LEAD TIME FOR ENERGISATION OF SERVICE CONNECTION UP TO 22KV

Installation with existing Service Connection Not Exceeding 45kVA or Domestic Premises

Non-domestic Installation with Existing Service Connection Exceeding 45kVA

New Connection from SPPA's Low Tension Mains

New Connection from New Substation

Pre-inspected Installation or Reconnection

Inspection Required

Submission of application to SPSL

NA 14 days* 4 weeks 3 months 6 months

Submission of substation plans to SPPG

NA NA NA NA 5½ months

Acceptance of Agreement§

4 days 14 days 14 days 7 weeks** 11 weeks*

Handover of substation to SPPG+

NA NA NA NA 10 weeks*

Opening of account with SPSL

4 days 14 days 14 days 14 days 11 weeks

Arrangements to inspect customer's installation (not exceeding 45kVA) by SPSL

NA 10 days NA NA NA

Application to EMA for licence to use or operate an electrical installation

NA NA 10 days 10 days 10 days

Request for energisation of service connection

NA NA 14 days 14 days 14 days

* These are critical events. Failure to adhere to the schedule may result in delay in the turn-on of supply.

§ Implementation of connection work shall only be effected upon the payment of service connection charge and execution of the Connection Agreement by the customer.

** For connection by underground cable, SPPG will have to seek road opening approval from the relevant authorities before cable work can commence. The approval process usually takes about 3 weeks. Depending on the length of cable to be installed, supply will normally be available 4 to 6 weeks from the date customer's premises is ready to receive the service cable.

+ Energisation of service connection will normally take place within 10 weeks of handing over of substation. This lead-time may vary from case to case, depending on the customer’s schedule.

31

Page 33: How to Apply

4.9 NOTES TO BE READ IN CONJUNCTION WITH APPLICATION PROCEDURE

4.9.1 Licensed Electrical Worker

4.9.1.1 There are three classes of LEW, namely Licensed Electrician, Licensed Electrical technician and Licensed Electrical Engineer. Licensed electrical workers of various class are licensed to design, install, repair, maintain, operate, inspect and test an electrical or supply installation in accordance with the condition stated below: Electrical Workers Approved Load of Installation Voltage

Electrician Not exceeding 45kVA Not exceeding 1,000VElectrical Technician Design: Not exceeding 150kVA Not exceeding 1,000V

Install: Not exceeding 500kVAElectrical Engineer No limit Subject to licence conditions

4.9.1.2 The customer should appoint an LEW appropriate to the capacity and voltage of the proposed installation, and inform SPSL immediately of any change of LEW during the course of the project.

4.9.2 Opening An Account

4.9.2.1 Before supply to an installation can be turned on, the customer must open an account with SPSL. An application to open an account for electricity supply can be made either personally, through the post or Internet. A sample of the Application(s) for the Supply of Water, Electricity and /or Gas and GIRO forms to be completed are shown in Appendix 6 and Appendix 7 respectively.

4.9.2.2 Application in person can be made at SPSL's Customer Services Centre, Upper First Storey, 111 Somerset Road #01-10, Singapore Power Building; or at SPSL's Application counter at Woodlands Civic Centre #02-06, 900 South Woodlands Drive, Singapore 730900. Applications through the post should be addressed to:

Deputy Director (Customer Services) SP Services Ltd P O Box 341 Orchard Post Office Singapore 912312

4.9.2.3 The following documents must be shown at the time of application in person:

4.9.2.3.1 Identity Card/Passport of owner/tenant/authorised signatory*

4.9.2.3.2 Copy of Business/ Company Registration Certificate*

4.9.2.3.3 Documentary proof of occupation of premises, e.g. rent receipt or sales letter from HDB confirming the purchase of the premises

4.9.2.3.4 Bank account book to effect GIRO deduction from the account

32

Page 34: How to Apply

*applicable for account in company's/organisation's name.

4.9.2.4 For applications submitted through the post, copies of the above-mentioned documents must be enclosed.

4.9.2.5 An initial deposit is payable on opening an account. Customers may call the Customer Enquiry Auto-Link (U-Link) at 1800-7380038 to enquire about the opening and closing of accounts.

4.9.2.6 For domestic premises, the deposits are as follows:

Type of Premises Deposit GIRO Non-GIRO

CustomersCustomersHDB 1/ 2 rooms S$ 40 S$ 60HDB 3/ 4/ 5 rooms S$ 70 S$ 100HDB Executive/ HUDC/ Terrace S$ 100 S$ 150Private Apts/ Semi-Detached/ Condo S$ 150 S$ 250Bungalow/ Penthouse/ Townhouse S$ 250 S$ 400

4.9.2.7 The deposit for non-domestic premises varies according to the electricity load required, the estimated water consumption, the floor area and type of operations. For enquiry on the amount of deposit required, customers can call 1800-2222333.

4.9.3 Handover Of Completed Substation

4.9.3.1 The handover of substation to SPPG for installation of equipment is a key event, which determines the earliest date when supply can be made available.

4.9.3.2 One week prior to the intended handover of the substation, the LEW must submit a Request to Handover Substation form (Appendix 5) to Deputy Director (Customer Projects - East / West / Distribution Projects), SPPG. Before this is done, the LEW must ensure that the customer/developer has accepted the terms and conditions of connection, including the payment of necessary charges.

4.9.3.3 It must be emphasised that SPPG will take over the substation only when it is completed in accordance with plans and specifications approved by SPPG and the relevant authority. It is particularly important that the access to the substation must be clear and passable for transportation of heavy equipment.

33

Page 35: How to Apply

4.9.3.4 Floor frames are needed for some types of switchgear. Prior to the final rendering of the switchroom floor, the LEW is to notify the project engineer-in-charge to make arrangements for the floor frame to be installed, if it is necessary.

4.9.3.5 Requirements on handover of a completed transmission substation are given in General Requirements for EHT Substation (Appendix 17).

4.9.4 Installation Of Current Transformer Operated Meters

4.9.4.1 On the day the LEW arranges with SPSL for a date for energisation of the service connection, he should also bring the letter of appointment for energisation of the service connection to Meter Section to arrange for the installation of meters. On the appointed day of meter installation, the LEW or his representative must be present to provide a 230V 13A single-phase supply for testing of the meters.

4.9.5 Procedure For Application For Licence To Use Or Operate An Electrical Installation

4.9.5.1 General

4.9.5.1.1 Under The Electricity Act, electrical installations in non-domestic premises, residential buildings and condominiums with an approved load greater than 45kVA are required to be licensed. In addition, certain premises classified as engaging in dangerous trades, are also required to be licensed even though they may have approved electrical loads not exceeding 45kVA.

4.9.5.1.2 Customer is required to appoint an appropriate class of licensed electrical worker to take charge of his electrical installation and submit application for Electrical Installation licence through his appointed licensed electrical worker via EMA website at www.ema.gov.sg. The validity of the licence is for a period of 12 calendar months.

4.9.5.2 Conditions For The Issue Of The Licence

4.9.5.2.1 Conditions for the issue of the electrical installation licences are governed by EMA.

4.9.5.2.2 The minimum grade of LEW required to take charge of the electrical or supply installation is determined by the total approved load. The grades of Electrical Workers and their authorisation conferred under the respective EMA licences are shown in the table in paragraph 4.9.1.1.

34

Page 36: How to Apply

4.9.6 Procedure For De-Energisation / Disconnection Of Service Cables

4.9.6.1 De-Energisation Of Service Cable For Maintenance Purpose

4.9.6.1.1 The LEW who needs to de-energise an existing service cable for the purpose of maintenance or upgrading of the customer’s installation must submit the ADRE form to SPPG 7 business days in advance (Appendix 19). For Contestable Customers, an advance notice of 14 business days is required.

4.9.6.1.2 The SDRE form (Appendix 20) must be used to ensure that the service cable is safely isolated after de-energisation and fit to be energised before re-energisation. Both SPPG’s officer in-charge and the LEW must duly complete and sign Part I and Part II of the form after de-energisation and before re-energisation of the service cable respectively. For Contestable Customers, the LEW must duly complete and sign Part III of the SDRE form.

35

Page 37: How to Apply

2. Customer's Installation Requirements

5.1 REQUIREMENTS FOR HT AND LT CONNECTION (22kV AND BELOW)

5.1.1 Short-Time Withstand Current Ratings of Switchgear

5.1.1.1 For electrical installations taking electricity supply directly from SPPA’s network, the customer’s main supply incoming switchgear must comply with the following short-time withstand current ratings:

5.1.1.1.1 For supply at 22kV - 25kA for 3 sec

5.1.1.1.2 For supply at 6.6kV - 20kA for 3 sec

5.1.1.1.3 For supply at low tension, a) Single-Phase 230V

- 6kA for supply capacity up to 15kVA - 9kA for supply capacity more than 15kVA and up to 23kVA

b) 3-Phase 400V

- 9kA for supply capacity up to 75kVA - 25kA, 3 sec for supply capacity more than 75kVA and up to 180kVA - 36kA, 3 sec for supply capacity more than 180kVA.

Note: The 3-second duration is not applicable to switchgear incorporating direct

acting tripping devices.

5.1.1.2 For electrical installations taking electricity supply from the landlord’s or management corporation’s electrical installations, the LEW in-charge must ensure that the customer’s main supply incoming switchgear is capable of withstanding the prospective short-circuit current at the connection point.

36

Page 38: How to Apply

5.1.2 Protection Requirements

5.1.2.1 Typical schemes and the protection requirements for customer’s HT and LT main incoming switchgear taking electricity supplies from SPPA’s system are shown in Appendix 18. It must comply in general to conditions as set out in the Transmission Code, Section 6.3 and Appendix F3.

5.1.2.2 For electrical installations taking electricity supply from the landlord’s or management corporation’s electrical installations, advice on protection requirements must be sought from the LEW responsible for the respective licensed electrical installation.

5.1.2.3 Protection Requirement For 22kV Customer Connection The main protection for the 22kV customer connection must be pilot wire differential protection. The current transformers of ratio 500/5 must be of Class X and the CT secondary star-point must be towards the protected line. The standard overcurrent/earth fault setting for the incomer is shown in Appendix 18.

5.1.2.3.1 To effect fast fault clearence, the 22KV cable terminations and metering CTs/VTs

installed at the incomers must be included in the 'Protected Zone' of the cable's Unit Protection, as shown in Appendix 18.

The LEW of the customer installation is responsible for:

5.1.2.3.2 proper specification, setting / commissioning of the protection system at the customer incomers, and

5.1.2.3.3 ensuring that the 22kV circuits within the customer installation are equipped with unit protection for fast fault clearance, inclusive of fault at cable terminations.

5.1.2.4 Protection Requirement For LT Supply Connection The customer’s incoming circuit breaker shall be set according to the approved load. For approved load exceeding 300A, external overcurrent relays of IDMTL or DTL characteristics and earth fault protection (DTL) must be provided at the incoming switchgear. The current transformer must be of Class 5P10, 15VA or better. Details are shown in Appendix 18.

5.1.2.5 Every low tension electrical installation of supply capacity exceeding 75kVA must be provided with short-circuit protection in the form of direct acting trip element at the incoming switchgear as follows: Approved Load Direct Acting Trip SettingAbove 1500A Up to 4500A400A< Approved Load < 1500A Up to 3200A260A < Approved Load < 400A Up to 2400A200A < Approved Load < 260A Up to 2000A200A and below Up to 1200A

Alternatively, a backup HRC fuse may be used in place of direct acting trip.

37

Page 39: How to Apply

5.2 REQUIREMENTS FOR EHT CONNECTION (230kV and 66kV)

5.2.1 Short-Time Withstand Current Ratings Of Switchgear

For electrical installations taking electricity supply directly from SPPA’s network, the customer’s main supply incoming switchgear must comply with the following short-time withstand current ratings:

5.2.1.1 For 230kV Switchgear - 63kA (1 sec)

5.2.1.2 For 66kV Switchgear - 40kA (3 sec)

5.2.2 Protection Requirement For 66kV and 230kV Customer Connection

5.2.2.1 General

5.2.2.1.1 The protection system for the connections has to comply in general to the conditions as set out in the Transmission Code.

5.2.2.1.2 All circuits connected to SPPA’s transmission network, inclusive of busbars for 230kV and above, must be provided with unit protection for fast fault clearance.

5.2.2.1.3 Engineering details and protection settings will be discussed with the customer during the project implementation.

5.2.2.1.4 The relays used for a unit protection scheme, and the characteristics of its associated current transformers should be matched. For reason of obsolescence or availability, the type of protection relays, signaling equipment and the protection schemes is subject to review and confirmation during the consultation period.

5.2.2.1.5 Wherever applicable, protection signaling equipment is to be provided for tele-protection function and for end-to-end transfer of intertrip and interlock signals.

5.2.2.1.6 Generally, the star-point of the current transformer secondary circuit must be towards the protected object / zone.

5.2.2.1.7 Generally, the location of the current transformers for the circuit and that of the installation’s busbar protection system for 230kV and above must be overlapped across the circuit breaker to eliminate protection blind zone.

5.2.2.1.8 Current transformers supplied for unit protection must be rated in accordance with IEC 60044 Part 1 & 6, BS 3938. They must be adequately dimensioned and of an accuracy class meeting the specified relay’s requirement. The characteristic of the current transformers installed at both ends of the connected circuit must be closely matched with each other to ensure stability.

38

Page 40: How to Apply

5.2.2.1.9 The LEW of the customer's installation is responsible for the proper specification, setting/commissioning of the protection system at the customer 230KV or 66KV incomers.

5.2.2.2 The proposed settings for the backup protection for the 66KV customer incomer must generally be as follows:

PROPOSED RELAY SETTING FOR 66kV CUSTOMER INCOMER

Protection Relay General Setting

Over Current Protection (IDMTL) CT Ratio SettingFeeder Circuit (1000/5) 150% 0.15

(800/5) 200% 0.15Feeder Transformer Circuit (1000/5) 100% 0.20 Hi-Set: 27A

(800/5) 125% 0.16 Hi-Set: 34A(for 75MVA transformer)Earth Fault Protection (IDMTL) Feeder Circuit (1000/5) 10% 0.10

(800/5) 15% 0.10Feeder Transformer Circuit N/A(for 75MVA transformer)

Notes: - The coordinated setting for the backup protection is applicable to the standard protection scheme proposed for a feeder or feeder-transformer type customer connection and is applicable to radial feed connection only. (Refer to Appendix 18)

- The overcurrent and earth fault setting are subjected to periodic review by SPPG.

5.3 INFORMATION ON SPPA NETWORK EARTHING SYSTEM (230KV, 66kV and 22kV)

5.3.1 Where customer is connected directly to SPPA’s network, customer shall note the following earthing system at each voltage level.

5.3.1.1 230kV

Solidly earthed system. 5.3.1.2 66kV Resistive earthed system with neutral ground resistor (NGR) of 19.5 ohms. 5.3.1.3 22kV Resistive earthed system with neutral ground resistor (NGR) of 6.5 ohms. 5.3.2 Customer shall ensure that all equipment including CTs, VTs, and protection

systems connected to SPPA network meet the technical specification required for the respective earthing system in accordance with the relevant standards.

39

Page 41: How to Apply

2. Metering Requirements

6.1 General

6.1.1 All metering requirements must comply with EMA’s Metering Code. SPPG will determine the location where the supply line terminates in the premises, based on ease of accessibility to SPSL and SPPG personnel.

6.1.2 The developer or customer bears the cost of providing and maintaining the meter boards, miniature circuit breakers (MCBs), isolators and wiring for installation of meters. The meters are supplied and maintained by SPPA.

6.1.3 Meters can be mounted on any of the following types of meter boards:

6.1.3.1 Teak board or any hardwood board chemically treated against attacks by termites. Plywood should not be used. The meter board must be at least 20mm thick and rigidly fixed with a minimum of 4 fixing screws.

6.1.3.2 Metal panel with nylon inserts accurately positioned to accommodate the meter.

6.1.3.3 Glass reinforced polyester base fitted with nylon inserts accurately positioned to accommodate the meter.

If item 6.1.3.2 or 6.1.3.3 is provided, SPPG’s Meter Section has to be consulted on the locations of the nylon inserts.

6.1.4 The LEW must ensure that all metering requirements are complied with, and submit, at the planning stage, all relevant drawings on meter locations, meter board size, meter rooms, meter compartments/riser ducts/ cupboard, etc to Meter Section for approval. Sample units of each approved type of meter compartment / riser duct / cupboard and meter board must be provided for final inspection and approval by Meter Section before meters are installed.

6.1.5 If the doors of centralised meter rooms, meter gate posts, meter compartments/ riser ducts/ cupboards, etc are to be locked, they must be fitted with locksets which can be opened with one of the following master keys:

40

Page 42: How to Apply

6.1.5.4 Abloy master key code reference MK 911047

6.1.5.5 Chubb (Union) master key code reference G1HBG

6.1.5.6 Yale master key code reference MK48

The doors of meter rooms/compartments must be able to be opened from the inside without the need to use a key or other devices/tools.

6.1.6 All access doors to meter rooms/compartments/riser ducts/cupboards, etc must have a clear access opening of at least 600mm (width). The doors must be fitted with doorknobs or handles.

6.1.7 Security access systems installed in any premises must not impede access by SPSL and SPPG personnel.

6.2 LOCATION OF METER

6.2.1 General

6.2.1.1 The service board accommodating SPPA's service MCBs and meters must be located near the termination of the service line. The meter/service position must be easily accessible at all times to SPSL and SPPG personnel for maintenance and reading of meters.

6.2.1.2 Meters must be installed in a safe location where they will not be damaged or be a cause of danger to personnel (viz, in a clean and dry location, not exposed to weather, mechanical damage, vibrations, extremes of temperature or dampness).

6.2.1.3 The height of the meter on the meter board must be between 1.0m and 1.8m above ground level, and the depth of the compartment for installation of meters must be between 200mm and 300mm. It is advisable that the service board is housed in an approved box of non-combustible high-impact material to give added protection to the metering equipment and safety.

6.2.2 Grouping of Meters

Meters must be installed outside each tenant unit for ease of meter reading, maintenance, etc. Where this is not possible for practical reasons, meters may be grouped together in easily accessible centralised meter rooms or meter compartments/riser ducts/cupboards in multi-metered premises (e.g., residential, office, shopping or industrial high-rise building/complex).

41

Page 43: How to Apply

6.2.3 Meters in Meter Compartments / Riser Ducts / Cupboards

6.2.3.1 Meters are to be grouped on the same floor as the tenant units.

6.2.3.2 There may be more than one group metering location on each floor.

6.2.3.3 There must be adequate lighting in the group meter location to facilitate meter installation/maintenance and meter reading.

6.2.3.4 Meter boards in meter compartments/riser ducts/cupboards must be such that meters can be mounted facing the doors.

6.2.3.5 All meter compartments/riser ducts/cupboards where meters are installed are to be clearly and permanently labeled. Tenant unit numbers on permanent labels must be fixed adjacent to their respective meters.

6.2.3.6 Meter compartments/riser ducts/cupboards housing the meters must have clear glass windows provided on the doors, if these are locked, for ease of meter reading. The window for each meter must not be less than 200mm (W) x 300mm (H) x 6mm (thickness) and must be correctly positioned in front of where the meter is to be installed. Plastic windows and UV resistant polycarbonates are not acceptable. Full glass doors are not acceptable.

6.2.4 Meters in Centralised Meter Rooms

6.2.4.1 The height of the meter board or panel must be such that meters can be mounted with the highest row not exceeding 1.8m above floor level and the lowest row not less than 1m above floor level.

6.2.4.2 There must be standing space of at least 700mm in front of the meter panel. However, if the meters are mounted on a free-standing panel, a clearance of 700mm all round the panel is required.

6.2.4.3 The meter board or panel must be rigidly and vertically mounted. The doors of the panel must be hinged.

6.2.4.4 The meter room must not be used as a storeroom.

6.2.5 Meters Installed in Landed Properties

6.2.5.1 The meters and service cables must be installed in a weatherproof compartment located at the gate pillar or perimeter wall. For supply capacity up to 100A 3–phase, the technical requirements for this compartment are as given in Appendix 24. For supply capacity greater than 100A 3-phase where a CT-operated meter will be installed, the LEW has to submit the technical requirements to Meter Section for approval.

426.2.5.2 If there is no gate pillar or fencing around the perimeter of the landed properties,

Page 44: How to Apply

meters must be installed inside a weatherproof meter box/compartment and easily accessible to SPSL and SPPG personnel. Meters must not be installed inside the house.

6.3 METER/SERVICE BOARD SPECIFICATIONS (SINGLE-PHASE AND 3-PHASE SERVICES, NOT EXCEEDING 100A PER PHASE)

The meter/service board for SPPA's service MCBs and meters must be as specified in Section 6.1.3 and in accordance with the drawings in Appendices 25, 26 and 27.

6.4 WIRING, LAYOUT OF METERS, MCBs, ETC IN CENTRALISED METER ROOMS, METER COMPARTMENTS/RISER DUCTS/CUPBOARDS

6.4.1 All wiring leading in and out of the group meter location must comply with SS CP5. The landlord's wiring must be segregated from the tenant's wiring.

6.4.2 Meters are to be mounted together with their associated service MCBs / neutral connectors such that each meter can be visually identified with its associated service MCBs. Each meter position must be clearly labeled according to the tenant unit number. There should be a space of 70mm between vertically mounted meters.

6.4.3 Meters are to be mounted in neat vertical columns and/or horizontal rows.

6.4.4 Service MCBs shall be sealable. MCBs must be clearly labeled according to the tenant units served. The labeling must also correspond to the labels used for the meters.

6.4.5 All wiring on the meter boards from service MCBs / neutral connectors to the meters and from the meters to the customer's main switches must be neatly run on the surface - horizontally and/or vertically.

6.5 SUBMISSION OF LAYOUT PLANS The layout of the meter rooms, meter compartments/riser ducts/cupboards together with the meter board drawings and plans of the units served, must be submitted at the planning stage by the LEW for approval by Meter Section.

6.6 METERS FOR 3-PHASE LOW TENSION CONNECTION (EXCEEDING 100A PER PHASE)

6.6.1 Meters for connections exceeding 100A per phase are operated from metering current transformers and are to be fixed on a pre-wired metering panel on the customer’s main switchboard. However, where the length of the connecting leads are not excessive, the pre-wired metering panel may, with the prior approval of Meter Section, be wall-mounted away from the main switchboard or in a separate meter room. The pre-wired metering panel with Meter Section approved type test block, 6A (10kA) MCB, pilot lights and metering cables to the busbars and the three metering current transformers, must be provided by the customer. Drawings

43

Page 45: How to Apply

of the pre-wired meter panel can be obtained from Meter Section at St James District Office, Telok Blangah Road.

6.6.2 Meter Panel Compartment Specifications

6.6.2.1 Meter panels must be of mild steel of at least 1.6mm thickness or other materials subject to approval by Meter Section

6.6.2.2 The panels must be detachable and of a size given in Appendix 28.

6.6.2.3 The compartments must have a minimum depth of 100mm between cover and base.

6.6.2.4 There must be openings with appropriate bushing for the meter wires.

6.6.2.5 The cover must have at least 3 hinges and be able to swing and open out at least 90o.

6.6.2.6 Facilities for sealing must be provided. Methods of sealing are illustrated in the drawings in Appendix 29.

6.6.3 Meter Installation Requirements

6.6.3.1 The switchboard must be complete and securely mounted in its final position before meters can be installed.

6.6.3.2 The top of the meter panel must not exceed 2.0m from the ground.

6.6.3.3 A 50mm x 50mm trunking of metal or other approved material between the switchboard and the meter panel must be provided to house the meter cables if the latter is installed away from the customer’s main switchboard.

6.6.3.4 A 6.0mm tap-hole plus screw/washer on each busbar must be provided to facilitate connection of the voltage cables to the meter voltage coils.

6.6.3.5 If the meter panel is away from the customer’s main switchboard, sealable 30A HRC fuse for each phase and a sealable 3-pole ganged MCB of 6A 10kA rating must be provided on the front of the switchboard panel near the metering CT enclosure for the protection of the meter voltage wiring. The MCB must be appropriately labeled.

6.6.3.6 Mounting of metering current transformers must be as follows: - Current transformers must be mounted on jumpers for easy installation. - Bakelite clamps must be provided to secure the meter current transformers

in position. - Adequate insulation between the metering current transformers and the

busbar must be provided.

44

- The metering current transformers and meter voltage tap off points must be installed after the incoming connection main protection current transformers.

Page 46: How to Apply

6.6.3.7 Enclosure A rigid enclosure of mild steel plate of thickness not less than 1.6mm must be provided solely for housing the metering current transformers and voltage tap off points. The enclosures must have facilities for sealing. A typical construction of the enclosure is shown in Appendix 30.

6.7 HIGH TENSION / EXTRA-HIGH TENSION METERING

6.7.1 General Requirements

6.7.1.1 The customer is required to provide, install and maintain, at his own expense, current transformers, voltage transformers, a pre-wired metering panel with test blocks, MCBs, pilot lamps and accessories, at his receiving HT switchboard. These must meet SPPA’s requirements. Drawings of the pre-wired metering panel can be obtained from Meter Section at St James District Office, Telok Blangah Road.

6.7.1.2 All metering current and voltage transformers must be used solely for SPPA's revenue metering equipment. No other apparatus of the customer is permitted to be connected to such metering current and voltage transformers. However, a voltmeter may be allowed to be connected via a 100 mA fuse (sealable) subject to approval by Meter Section.

6.7.1.3 The customer must also provide a metering kiosk to be located close to where the metering current and voltage transformers are installed, such that the route length of the cables from the current and voltage transformers to the metering kiosk does not exceed 20m. Where this cannot be complied with because of site constraints, the LEW must consult Meter Section concerning the type and size of cables to be provided and installed by the customer.

6.7.1.4 The requirements for the kiosk are given in Appendices 31 and 32. The access to the metering kiosk must be from outside the HT switchroom and fitted with any one of SPPA's approved master lock series as specified in Section 6.1.5.

6.7.1.5 The customer must provide an appropriate metering panel of a size given in Appendix 33 and install a 50mm x 50mm trunking of metal or other approved material between the customer’s HT switchboard and the metering panel together with the required type and size of cables.

6.7.1.6 Facilities for sealing connections of all metering wire termination at the customer's HT switchboard must be provided.

6.7.1.7 A schematic and wiring diagram of the customer’s switchboard must be supplied to facilitate installation of the meters.

6.7.2 Specifications For Metering Current Transformers

6.7.2.1 The customer will provide two metering current transformers of 30VA burden for 66kV connection or 15VA burden for connection at 6.6kV or 22kV. These must be of accuracy class 0.5 complying with SS 318 or IEC 60044-1.

45

Page 47: How to Apply

6.7.2.2 The current transformers are to be installed on the red and blue phases at the cable end for each of his receiving switchboard. The current transformer ratio will be determined by SPPG based on the customer’s load requirement. For connection at 230kV, the LEW will liaise with Meter Section on metering requirements.

6.7.2.3 The rated short-time current rating must not be less than 63kA 1 second, 40kA 3 seconds, 25kA 3 seconds and 20kA 3 seconds for connection at 230kV, 66kV, 22kV and 6.6kV respectively.

6.7.3 Specifications for Voltage Transformers

6.7.3.1 For each of the customer’s receiving switchboard, one of the following voltage transformers must be provided:

6.7.3.1.1 One unit 3-phase 66kV/110V, 22kV/110V or 6.6kV/110V voltage transformer of 100VA burden per phase, connected star-star with the yellow phase terminal of the secondary winding earthed, or

6.7.3.1.2 Three units single phase, 66kV 110V or 22kV 110V or 6.6kV 110V

3 3 3 3 3 3

Voltage transformers of 100VA burden per phase, connected star-star with the yellow phase terminal of the secondary winding earthed.

6.7.3.1.3 Voltage transformers must be of accuracy class 1.0 complying with BS3941 or IEC 60186.

6.7.3.1.4 The secondary wiring of the voltage transformer must terminate in a sealable MCB incorporated in the switchgear panel. The MCB must be rated at 6A, 110V, 50Hz with breaking capacity not less than 10kA and the terminals of the MCB must be able to accept cables of cross section up to 6mm2.

6.7.3.1.5 The voltage transformers must be fused and adequate stock of spare high-voltage fuses must be kept by the customer.

6.8 TESTING OF METERING CTs AND VTs

6.8.1 All metering current transformers and voltage transformers together with their manufacturers' test certificates must be submitted for testing and approval by Meter Section at least 2 weeks before connection is required. Voltage transformers at 66kV and 230kV are exempted from testing and only the manufacturer’s test certificates have to be submitted.

6.8.2 The metering VTs, after re-installation onto customer’s switchgear, have to be

tested and phase out, and a test report as per Appendix 34 have to be submitted to Meter Section for approval before installation of meters.

46

Page 48: How to Apply

6.9 METERING REQUIREMENTS

6.9.1 Low Tension Customer

6.9.1.1 Single Customer - More Than 75kVA

6.9.1.1.1 The customer will provide three metering current transformers (CTs) of 5VA burden and accuracy class 0.5 complying with SS 318 or IEC 60044-1 and the pre-wired metering panels on the customer’s intake switchboard. The pre-wired metering panel must be fitted with SPPA approved type test block, MCB and pilot lights and connected with metering cables to the CTs and busbars. The CTs together with their manufacturer’s test certificates must be submitted for testing and approval at least 2 weeks before connection is required.

6.9.1.1.2 A request for appointment to fix meters should be made only after the LEW has arranged with SPSL for a date to energise the service connection.

6.9.1.1.3 Meter Section will arrange to install the meters upon production of the energisation appointment letter issued by SPSL and requires at least 4 business days before the energisation of service connection date.

6.9.1.2 Multi-Metered Buildings

6.9.1.2.1 Submission of floor plans of building showing the locations of metering kiosks, meter room, meter compartments/riser ducts/cupboards.

6.9.1.2.2 Submission of dimensioned metering layout showing the plan, front and side elevations of the meter boards/rooms/compartments/riser ducts/cupboards, etc.

6.9.1.2.3 Arrangements for sample units of each approved type of meter compartment/riser duct/cupboard and meter board to be inspected and approved by Meter Section before meters are installed.

6.9.1.3 Landed Housing Development

6.9.1.3.1 Submission of site plans of building showing the locations of meter compartments at gate pillars.

6.9.1.3.2 Submission of dimensioned metering layout showing the plan, front and side elevations of the meter compartments in the gate pillars.

6.9.1.3.3 Arrangement for sample units of each approved type of meter compartment and meter board to be inspected and approved by Meter Section before meters are installed.

6.9.2 High Tension / Extra-High Tension Customer

47

6.9.2.1 The revenue metering equipment will be installed at the customers’ end of the service connection. The customer will provide a suitable metering kiosk at his intake station, and metering CTs and VTs for each of his receiving

Page 49: How to Apply

switchboard. The metering CTs ratio will be based on declared demand as shown in Section 6.9.2.4.

6.9.2.2 The customer will provide and maintain at its own cost, a fixed telephone line to the metering kiosk to be used exclusively for the purpose of remote meter reading. This telephone line must be terminated in a standard telephone socket at the metering kiosk. Provision of this telephone line must be made before installation of meters.

6.9.2.3 If the customer is unable to provide the fixed telephone line due to site constraint, a GSM line can be considered subject to approval by Meter Section.

6.9.2.4 Based on the contracted capacity stated in the application form, the customer is required to provide the correct metering CTs as follows:

Contracted Capacity CT Ratio MW

48

0.0-0.8 50/25/50.81-1.7 100/50/5

22kV Service Connection

1.71-2.5 150/75/52.51-3.2 200/100/53.21-5.0 300/150/55.01-6.6 400/200/5

6.61-10.0 500/300/50.0-5.0 100/50/5

5.01-10.0 200/100/566kV Service Connection

10.01-20.0 400/200/520.01-30.0 500/300/530.01-40.0 800/400/540.01-80.0 1000/500/5

6.10 CONTESTABLE CUSTOMERS

6.10.1 Eligibility The eligibility of contestable customers is determined by EMA.

Additional Requirements For Contestable Customers 6.10.2 A contestable customer must provide and maintain at its own cost a fixed telephone line to be used exclusively for the purpose of remote meter reading. The LEW must liaise with Meter Section for the location and termination of this telephone line.

Page 50: How to Apply

49

Appendices

Page 51: How to Apply

13/11/08

APPLICATION FORM For official use only FOR CONNECTION TO THE

TRANSMISSION SYSTEM Application Number :

Date Received : To : SP Services Ltd 111 Somerset Road #01-10 Singapore 238164

PART 1 APPLICANT’S DETAILS All connections with Distributed Generation (e.g. PV system) are required to submit this application. I request you to provide/upgrade the load connection service to my premises as given in Part 2 by my Licensed Electrical Worker undertaking the project

Name of Company/Applicant * : ______________________________________________ ROC/NRIC No. : __________________ Name of Authorised Person & Designation * : ___________________________________________________________________ Forwarding Address: __________________________________________________ Postal Code: Singapore ______________

Tel: _________________ Fax: __________________ Mobile Phone: ___________________ Pager: __________________

Email: _________________________ Signature of Applicant: _______________________________ Date: _______________

PART 2 INSTALLATION DETAILS (To be completed by LEW)

Project Description: _______________________________________________________________________________________ Site Address: ________________________________________________________ Postal Code Singapore ______________ Utility Account No. (existing): _____________________________ Existing Approved Load: _____________________ kVA/kW * Any previous Consultation? Yes / No* If Yes, please provide Consultation No.: _____________________

TYPE OF CONNECTION (Please tick the appropriate boxes)

New Connection Temporary Connection Replacement of switchboard (no load upgrading) [ same / different switchroom * ]

New Connection with Distributed Generation (Please specify): ____________________________________________________________

Existing Connection with Distributed Generation (Please specify): __________________________________________________________

Upgrading the existing connection point Change of intake connection point (involving new switchroom) Re-energise existing connection

Others (Please specify) : ____________________________________________________________________________________________

TYPE OF DEVELOPMENT (Please tick the appropriate boxes)

Industrial Commercial Residential Renewable Energy

Others (Please specify) : __________________________________________________________________________________ Type of Business Activity (Brief Description) : _________________________________________ Voltage Dip Sensitive? Yes / No *

LOAD REQUIREMENT (One intake connection point per premises) Total load requirement (to include existing load, if any)

30A/60A/100A* 30A/60A/100A* __________ kVA at 400V three-phase 230V single-phase 400V three-phase

22kV 66kV/230kV* (min. 1,700kW for 2 HV services, min. 12,751kW for 4 HV services) (min. 25.5MW for 66kV, min. 85MW for 230kV) SINGLE USER PREMISES (HIGH TENSION / EXTRA HIGH TENSION)

Total Contracted Capacity of ________________ kW at ____________________ kV via __________ service cable(s). Initial Contracted Capacity of ______________ kW (shall not be less than ¼ of the Contracted Capacity) for _________ months

(not exceeding 12 months)

Page 52: How to Apply

13/11/08

MULTI-TENANTED / MULTI-TENANTED MASTER-SUB PREMISES (HIGH TENSION / EXTRA HIGH TENSION)

Total Contracted Capacity of ________________ kW at ____________________ kV via __________ service cable(s). Landlord’s Contracted Capacity (minimum 1,700kW) : ______________________ kW Initial Landlord’s Contracted Capacity: ______________ kW (shall not be less than ¼ of the Landlord’s Contracted Capacity) for _________ months (not exceeding 12 months)

Target date of Energisation : ________/_________/___________ Estimated ultimate load : ___________________ kVA/kW*

(Please refer to expected lead time in handbook. For service costing job, supply will normally be available 4 to 6 weeks from the date customer switchboard/meterboard and cable entry pipes of your premises is ready to receive the service cable. For major work where substation is involved, you shall handover the substation building 10 weeks before the target date of energisation.)

TYPE OF PREMISES (Please tick the appropriate box)

Single user premises Multi-tenanted premises Multi-tenanted Master-sub premises

Estimated Landlord Load __________ kVA/kW* For multi-tenanted installation with the exception of HDB residential installation, the metering scheme shall be designed as Master/Sub-metering scheme.

TYPE OF METERING SCHEME Please specify the metering scheme: Master / Normal* (For master metering scheme, the common services load must be at least 10% of the total load for the premises.)

Any change in metering scheme? Yes / No*. If yes, please specify _________________________________________________

TO BE COMPLETED FOR INSTALLATION EXCEEDING 45kVA

Total Land Area: ___________________________ m2 Gross Floor Area: ______________________________ m2

PLANS AND DETAILS (Mandatory)

2 copies of Architect’s site and location plan Substation Land Ownership: SLA / URA / HDB / JTC / Private / Others*, please specify: _____________________ 2 copies of plan showing proposed customer’s intake connection point and the existing intake point (if applicable) Details of the type, floor area & designed load of individual premises for multi-metered premises 1 copy of Fault Level Report (distributed generation and applicants with large motors only)

PART 3 LEW DETAILS

I confirm that the above information is correct and agree to advise SP Services should there be subsequent changes.

Name of Authorised LEW: ______________________________________ License Number:______________________________ Registered Forwarding Address: ______________________________________________________________________________

______________________________________________________________________ Postal Code: Singapore ______________

Tel: _________________ Fax: __________________ Mobile Phone: ___________________ Pager: __________________

Email: ___________________________________________________________________________________________________

Signature of Authorised LEW: _____________________________________________________ Date: _____________________

PART 4 QUALIFIED ELECTRICAL CONTRACTOR (QEC) DETAILS (if applicable) Name of Authorised QEC: ______________________________________ License Number:______________________________ * Delete where not applicable

Page 53: How to Apply

■ Appendix 2 CONSULTATION FORM For official use only FOR CONNECTION TO THE

TRANSMISSION SYSTEM Consultation Number. :

Date Received :

To : SP PowerGrid Ltd 111 Somerset Road #08-05 Singapore Power Building Singapore 238164

CONSULTATION DETAILS Sub-metered consumers (tenants) are not eligible for this application. All tenants in multi-metered premises are required to obtain supply from their landlord/MCST or HDB for HDB premises.

Reference to the consultation, I hereby enclose one copy of site & location plans including proposed customer’s intake connection point Drawing No. ____________________________________________________________ for your advice on connection requirements.

SITE DETAILS

Connection Applicant/Developer* : _____________________________________________________________________________ Project Description : _____________________________________________________________________________ Site Location – Lot & Mk No : _____________________________________________________________________________

Street Name : __________________________________________________________ Blk/Unit No :_______________________

LOAD REQUIREMENT (One intake connection point per premises)

New Connection Upgrading the existing service cable Temporary Connection

Change of intake connection point Other Services (Please specify):________________________________________

Type of Premises : Industrial/Commercial/Residential/Others*_________________________Gross Floor Area(m2): _____________ Type of Business Activity (for non-residential premise only) : _______________________________ Voltage Sensitive? Yes / No * Existing Utility A/C No.(if any) : ________________________________ Existing Approved Load (kVA) : ________________________________ at 230V/400V/22kV/66kV/230kV* Load Requirement (kVA) : ____________________________________ at 230V/400V/22kV/66kV/230kV*

Target date of Energisation :__________/___________/__________ Previous consultation No. (if any) : _________________

Additional information : ______________________________________________________________________________________

______________________________________________________________________________________

LEW DETAILS I confirm that the above information is correct and agree to advise SP PowerGrid should there be subsequent changes.

Name of Authorised LEW : _____________________________________ Licence Number:_______________________________ Company Forwarding Address :________________________________________________________________________________

___________________________________________________________ Postal Code : Singapore __________________________ Tel : ______________________ Fax : __________________ Mobile Phone : _____________________ Pager : _______________

Email : ___________________________________________________________________________________________________

Signature of Authorised LEW ______________________________________________________ Date ______________________ * Delete where not applicable

52

Page 54: How to Apply

■ Appendix 3 Form CS/3

Letter of Consent from the Landlord/Management Corporation To: SP Services Ltd 111 Somerset Road #06-05 Singapore Power Building Singapore 238164 ELECTRICITY SUPPLY TO :______________________________________________________________________ (Full Address of the Customer)

FOR :________________________________________________________________________________________ (Name of Customer)

TOTAL LOAD ALLOWED FOR: _______________________________ AT ___________________________ VOLTS

_____________________________________________________________________________________________ PART I 1. I have checked the loading of the electrical installation of the abovementioned building/complex and hereby

confirm that the abovementioned load requirement can be catered for from the rising/horizontal mains system/main switchboard of the building/complex, and the total approved load to the entire building/complex will not be exceeded.

2. I have no objection for the abovementioned load to be connected to the rising/horizontal mains system/main

switchboard of the building/complex. 3. The Electrical Installation Licence No. of the building/complex is ______________________. 4. The electrical installation of the building/complex from which this load is to be connected is Unmetered (i.e. without Master Account) Metered under Master Account No. ________________________. 5. I will check to ensure that the abovementioned installation is compatible with the electrical installation of the

building/complex. _____________________________________ Date: ______________ Signature of Licensed Electrical Worker Licence No: _____/___________ Tel No: __________________ Name: ______________________________________ Address: _____________________________________________________________________S (______________) _____________________________________________________________________________________________ PART II I hereby give consent for the abovementioned customer to tap electricity supply of a capacity indicated above from the rising/horizontal mains system/main switchboard of the building/complex. ___________________________________ Date: ________________ Signature of authorised person __________________________________________ ________________________ Name Designation Official Stamp of the landlord/developer/management corporation

53

Page 55: How to Apply

■ Appendix 4 FORM CS/3H

Letter of Consent from Housing & Development Board To: SP Services Ltd 111 Somerset Road #06-05 Singapore Power Building Singapore 238164 ELECTRICITY SUPPLY TO :______________________________________________________________________ (Full Address of the Customer) FOR : ________________________________________________________________________________________ (Name of Customer) TOTAL LOAD ALLOWED FOR: ________________________________ AT _________________________ VOLTS _____________________________________________________________________________________________ PART I 1. I have checked the loading of the electrical installation of the above-mentioned building/complex and hereby

confirm that the above-mentioned load requirement can be catered for from the rising/horizontal mains system/main switchboard of the building/complex, and the total approved load to the entire building/complex will not be exceeded.

2. I have no objection for the above-mentioned load to be connected to the rising/horizontal mains system/main

switchboard of the building/complex. 3. The Electrical Installation Licence No. of the building/complex is ___________________________. 4. The electrical installation of the building/complex from which this load is to be connected is Unmetered (i.e. without Master Account) Metered under Master Account No. _________________________________. 5. I will check to ensure that the above-mentioned installation is compatible with the electrical installation of the

building/complex. ________________________________ Date: _______________________ Signature of LEW Licence No.: ______________________________________ Name: __________________________________________ Tel No.: _____________________ Address: _____________________________________________________________________________________ _____________________________________________________________________________________________ PART II I hereby give consent for the above-mentioned customer to tap electricity supply of a capacity indicated above from the rising/horizontal mains system/main switchboard of the building/complex. ________________________________ Date: _______________________ Signature of Authorised Person For and on behalf of Housing & Development Board ________________________________ ____________________________ Name Designation Official Stamp of the Landlord/Developer/Management Corporation

54

Page 56: How to Apply

■ Appendix 5

55

Request to Handover Substation

Date: To: SP PowerGrid Ltd

111 Somerset Road #08-05

Singapore Power Building

Singapore 238164

Attn: Deputy Director

(Customer Projects – East / West / Distribution Projects)

Dear Sir PROJECT: ELECTRICITY SUPPLY TO ________________________________________________________________________ 1. In connection with the electrification scheme (SPSL Appln No: ________________), I wish to advise that the proposed SPPA

substation has been completed in accordance with plans and specifications approved by your Company and the Competent

Authority.

2. I confirm that the structural Professional Engineer in-charge has certified that the substation structure is constructed according

to the approved plan to withstand the load specified by your Company.

3. I also certify that the electrical installation at the substation has been inspected and tested in accordance with the requirements

of your Company as follows:

a Earth value of electrode system is ______________ ohms. b The continuity of each circuit protective conductor is satisfactory. c All metal conduits have been bonded to earth. d Polarity throughout the installation is correct. e All single pole control devices are in live conductors only. f The insulation resistance of the fixed wiring installation is ___________ Megaohm. g All flexible cords, switches, fuses, plugs and socket outlets are in good serviceable condition. h The installation includes ______________ Nos lighting points and _______________ Nos socket outlets. 4. I shall be obliged if you could send your representative for a joint site inspection on _____________________, and thereafter

to takeover the said substation.

Yours faithfully _______________________________ Signature of Licensed Electrical Worker Name: _______________________________________________________________________________________________ Address: _______________________________________________________________________________________________ Tel No: _______________________

NB: This form must be submitted one week prior to the date for joint site inspection, which shall normally take place

from 10 am to 12 noon.

Page 57: How to Apply

■ Appendix 6

56

Page 58: How to Apply

APPLICATION FOR INTERBANK GIRO Please tick: New Application Change of Bank Account Date: Name of SP Services Customer To: Name of Bank: SP Services Account Number (1 account per form) Branch (a) I/We hereby instruct you to process SP Services instructions to debit my/our account. (b) You are entitled to reject SP Services debit instructions if my/our account does not have sufficient funds and charge me/us a fee for this.

You may also at your discretion allow the debit even if this results in an overdraft on the account and impose charges accordingly. (c) This authorisation will remain in force until termination by written notice sent to my/our address last known to you or upon receipt of

my/our revocation through SP Services. My/Our Name(s) As in Bank Account: My/Our Bank Account No: My/Our Contact (Tel/Pager/Handphone) No(s) Bank Account Holder NRIC No/ P/P No: To: SP Services Ltd This application is hereby REJECTED (Please tick) for the following reason(s):

Signature / Thumbprint # differs from Financial institution’s records Wrong account number Signature / Thumbprint# incomplete / unclear# Amendment not countersigned by customer Account operated by signature / thumbprint# Others:______________________________

___________________________________ ___________________________ _____________________________ Name of Approving Officer Authorised Signature Date

# Please delete where inapplicable Co. Registration. : 199504470N

PART 1: FOR APPLICANT’S COMPLETION

My/Our Signature(s)/Thumbprint(s)/Company Stamp (as in bank’s records)

Please remember to sign in this box. Please impress your thumbprint clearly if your bank account is operated by thumbprint.

PART 2: FOR SP SERVICES’S COMPLETION

Bank Branch SP Services’s Account Number Utilities Account Number

Bank Branch Account Number To Be Debited

PART 3: FOR BANK/FINANCIAL INSTITUTION’S COMPLETION

■ Appendix 7

7

5
Page 59: How to Apply

■ Appendix 8 FORM CS/5 APPLICATION FOR INSPECTION OF ELECTRICAL INSTALLATION

For official use

58

To: SP Services Ltd 111Somerset Road #06-05 APPLICATION NO:

Singapore Power Building Singapore 238164

PART I I/We, #Mr/Mrs/Miss/Messrs____________________________________________________________________________________ (# Delete as appropriate). (name of applicant/company)

Utility Account No :

___________________________________________________________________________________________

request you to provide an electrical installation inspection and install kWh meter. (Please tick if meter is required) Details of my/our application are as follows:

(Please fill in the appropriate box below)

An application for electricity supply service has been submitted earlier and approved. SP Services Application Reference No is: _______________________________________ OR

This is a new application with details as given in Part II by my/our Licensed Electrical Worker undertaking the project. (Form CS/3 or CS/3H shall be attached for supply connection from landlord’s or HDB’s electrical installation.) My/Our particulars:

NRIC number/Company ROC number: ________________________________

Name of Authorised Person for Company:_________________________________________________________________ (if applicable)

Forwarding Address: _________________________________________________________________________________

________________________________________________________Postal Code: ______________

Tel:___________________ Fax : ___________________ Mobile phone: ___________________ Pager:_____________

Email: ____________________________ --------------------------------------------------- -------------------------------------------- Signature of Applicant Date

___________________________________________________________________________________________________________

PART II (INSTALLATION DETAILS - To be completed by Licensed Electrical Worker if there is no application submitted earlier) Project Description: ________________________________________________________________________________________

Site Address: ___________________________________________________________________Postal Code: ________________

Type of Application (Please tick the appropriate boxes) New Supply Temporary Supply Upgrading of Supply Downgrading of Supply Extension Rewiring Replacement of switchboard/switchgear Amalgamation Shifting of Meter

Conversion to Master/Sub Metering Scheme

Other Services (Please specify) ………………………………………………………………………………

Page 60: How to Apply

■ Appendix 8

Landlord’s installation HDB’s installation Public Lighting Network Supply SP PowerAssets (Form CS/3 is to be (HDB's endorsement (Form CS/3 PL is to be Connection from: installation/mains submitted) is required) submitted)

Type of Development: Industrial Commercial Residential Others Metering Scheme: *Master / Sub / Normal *(Delete as appropriate) Type of Business (Brief Description): ___________________________________________________________________ Total supply capacity (including existing requirement, if any) 30/40A# 230V 60A/80A/100A# 230V 30A/60A# 400V .............kVA single-phase single-phase three-phase at 400V three-phase (# Delete as appropriate) PART III DETAILS OF PROPOSED INSTALLATION OR EXTENSION. For HDB residential unit, erasure/amendment to any of the “QTY” figure below is NOT acceptable.)

QTY QTY QTY QTY

5A socket outlets 20A SPN ISO Cooker Point Oven Point

13A socket outlets 20A TPN ISO Connection Unit Shaver Unit

15A socket outlets 30/32A SPN ISO Fan Point Urinal Sensor Point

10A SPN/DP ISO 30/32A TPN ISO Hair Dryer Point Washing Machine

10A TPN ISO 60A SPN/DP ISO Hand Dryer Point Water Heater Points

15/16A SPN ISO 60A TPN ISO Lamp points Other Equipment

15/16A TPN ISO Cooker hob point Neon Sign ( A completed Certificate of Compliance is required to be submitted if a new meter is required.)

Name of LEW : _____________________ LEW Licence No. : _____________ __________________________________ Signature of Licensed Electrical Worker Date : ______________________ Forwarding address (as registered with EMA): __________________________________ Fax No.: ____________________

_______________________________________________________________________ Contact No.: ___________________

Postal Code: ________________ __________________________________________________________________________________________________ PART IV Endorsement by HDB (applicable for HDB residentiaI premises) 1 I have checked the loading of the electrical installation of the abovementioned building/complex and hereby confirm that the abovementioned load requirement can be catered for from the rising/horizontal mains system/main switchboard of the building/complex, and the total approved load to the entire building/complex will not be exceeded. 2 I hereby give consent for the abovementioned customer to tap electricity supply of a capacity indicated above from the rising/horizontal mains system/main switchboard of the building/complex. _______________________________________ Name/designation/signature of authorised person Date: ___________________ for and on behalf of Housing & Development Board

59

Page 61: How to Apply

■ Appendix 9

60

Types and Layout of Substation

The type of substation required will depend on the customer's load requirement. SPSL shall endeavour to provide the

requirement of the substation within 10 business days following the receipt of application form.

Typical layout plans and details for substations of the independent building type are given in Appendices 11 to 14.

As a guide, the types of substations applicable for the various load requirements are as follows: -

Load Requirement Primary Distribution

Voltage

Type of rooms

Drawings Applicable/Substation size

6.6kV Appendices 11 Up to 1,000 kVA at 400/230V

22kV Switchroom Transformer

7.6M x 6.2M x 5.6M 4.0M x 4.5M x 3.6M

Up to 2,000 kVA at 400/230V 22kV Appendices 12

Up to 4,250 kW at 22kV 22kV Switchroom 6.9M x 6.2M x 5.6M The functional requirements of the substation structure, however, must be complied with. For example, the minimum

clear height of the cable chamber and switchroom must be 1.5m and 3.1m respectively even if the substation is

integrated into a multi-storey building.

Subject to the layout and access being suitable, the customer may incorporate the substation as part of his main

building. The typical layout plans shown in this handbook depict only the functional requirements.

Page 62: How to Apply

■ Appendix 10

61

Submission of Substation Site and Design Plans Before construction of the substation, the LEW shall submit to SPPG, 2 sets of plans showing the location of the

proposed substation in relation to the rest of the development and detailed layout plans for the substation. One set of

plan will be endorsed and returned to the LEW.

All plans/drawings to be submitted must be on appropriate A1 or A2 size paper and endorsed by the LEW responsible

for the planning, design and supervision of the installation. To facilitate processing, SPSL's Application Reference

Number must be indicated in all submissions which shall be accompanied by a Checklist for Submission of

Substation Plans (Appendix 15).

In the case of re-submission of plans, all amendments (addition/deletion/revision) made must be highlighted in the

new set of drawings and listed out in covering letters.

All plans are to be drawn to scale and dimensions used shall be in metric units.

Substation Site Plans These plans should show the location of the proposed substation(s) in relation to the surrounding area and should

include the following:

(i) The proposed substation(s)

(ii) The customer's switchroom(s)

(iii) The proposed SPPA's incoming cable and customer's service cable routes

(iv) The orientation of other buildings within the development site

(v) The proposed driveway to the substation entrance (to be shaded in red)

(vi) The existing and proposed drains; and

(vii) North-East Gridlines or 2 NE survey coordinates.

Substation Design/Layout Plans It is mandatory that the drawings must include 1 The detailed requirements for the design of the substation are listed in Appendix 16. Unless explicit

waiver is granted, these requirements are to be incorporated in the architectural plans.

2 Plan, Front, Rear and Side Elevations of the substation and at least 2 cross-sections showing the

surrounding roads, cable chamber, switchroom beams and clear height, switchroom floor openings,

transformer plinths and other pertinent details.

3 Details of immediately adjoining upper floor, basement as well as adjacent space all around the

substation shall be depicted, if the substation is part of a larger building

It is the responsibility of the LEW in charge to ensure that all the requirements as endorsed on the drawings are

incorporated in the architectural and structural plans before construction work of the substation begins.

Page 63: How to Apply

■ Appendix 11

6.6kV/LT

6.6KV/LT SUBSTATION

62

Page 64: How to Apply

■ Appendix 11

63

6.6KV/LT SUBSTATION

Page 65: How to Apply

■ Appendix 11

64

6.6KV/LT SUBSTATION

Page 66: How to Apply

■ Appendix 116.6KV/LT SUBSTATION

65

Page 67: How to Apply

■ Appendix 12

22kV/LT

22KV/LT SUBSTATION

66

Page 68: How to Apply

■ Appendix 12

67

22KV/LT SUBSTATION

Page 69: How to Apply

■ Appendix 12

22KV/LT SUBSTATION

68

Page 70: How to Apply

■ Appendix 12

22KV/LT SUBSTATION

69

Page 71: How to Apply

■ Appendix 12

22KV/LT SUBSTATION

70

Page 72: How to Apply
Page 73: How to Apply
Page 74: How to Apply
Page 75: How to Apply
Page 76: How to Apply
Page 77: How to Apply
Page 78: How to Apply
Page 79: How to Apply

■ Appendix 14

78

GATE DETAILS

Page 80: How to Apply

■ Appendix 15

79

SPPG CHECKLIST FOR SUBSTATION BUILDING PLAN SUBMISSION

Proposal: Name of Licensed Electrical Worker: BP No (if any) : Yes Not Applicable 1) Drawings are in A1 or A2 series. 2) Plan, front, rear and side elevations are included. 3) Cross-sections in relation to roads and immediate surroundings are included. 4) Detailed layout scales of 1:50 for all plans and 1:100 for all sections and elevations. 5) Substation requirements stated in Handbook on How to Apply for Electricity Connection including latest updating are complied with. 6) Plans are signed by the Licensed Electrical Worker. 7) Proper vehicular access to the substation from main road is coloured. 8) I have advised the structural PE that substation structure is to be designed to withstand the loading specified in the Handbook and all structural requirements have been reflected in this submission. 9) All trenches/floor openings are not affected by any beam. 10) Required clear height (from underside of any beam) of all equipment rooms and cable chamber are complied with. 11) No column within substation 12) No wet area above substation 13) Location of Customer's Switchroom shown with proposed service cable route shown 14) I undertake to advise the architect and structural PE to ensure that all the requirements, as endorsed, are incorporated into the architectural and structural plans prior to substation construction 15) Previous drawings with SPPG's comments are attached (for resubmission case) 16) All additions/deletions/amendments are coloured 17) Any encumbrances? . Signature & Stamp of Licensed Electrical Worker License No Date Note: Please tick in appropriate box for all items.

This checklist is to be submitted for every submission/re-submission.

Page 81: How to Apply

� Appendix 16 Rev 1

SP POWERGRID LTD (SPPG)

SUBSTATION LAYOUT REQUIREMENTS TO BE INCORPORATED IN THE ARCHITECTURAL PLANS

Item Requirement

Cable Entry Duct • Heavy duty 150mm dia. UPVC pipes in concrete jacket to be provided and terminated 300mm after the roadside drain.

• To be sealed with removable water-tight plugs at both ends of pipes.

• To have piling, if necessary.

Cable Entry Ramp / Ramp • Cross Sectional views to be shown.

• <= 150mm wide removable hot-dipped galvanized mild steel gratings to be provided.

• Walls and floors to be plastered and rendered waterproof.

Cable Trenches • Washed dry sand filling to be carried out after cable installation.

• No beams shall be allowed within / across the trenches.

• Openings to be covered by removable hot-dipped galvanized mild steel gratings.

Switchgear Floor • Gratings of <=300mm width which is able to support at least 100 kg.

• To take a load of 1,600 kg per sq m. Floor beam is to be 200mm away from the HV floor opening. All floor openings to be free of beam.

Switchroom

• Louvred heavy duty aluminium door complying with Appendix 13 drawings. Size 2.9M x 1.8M wide nett for 22KV switchroom. 2.7M x 1.8M wide nett for 6.6KV switchroom.

Hasp and staple (150mm x 65mm X 6mm) complying with Appendix 13B. Door hinges to be of brass or stainless steel.

• Floor to have a 50mm thick cement rendering including a 20mm granolithic smooth finish of cement, granite chips and sand in the ratio of 1:1:1 plus 9kg ironite or equivalent approved hardener to each 45kg of cement. For 22kV substations, final rendering of switchroom floor to be done after installation of switchgear floor frame.

• HT and LT openings to be beam-free. All floor beams supports to be shown.

• Height: No part from floor to ceiling beams to be less than 3.1M. No column allowed within the switchroom.

• Hot-dipped galvanized mild steel/stainless steel railing to be provided for stairs and loading platform. (Removable type in front of door.

• Glass block and ventilation panels to be installed at high level only.

Transformer Room • Noise level of 60 dB emitted from each transformer to be considered in the choice of location

of transformer yard.

• Adequate natural cross air ventilation required. Provisions of PC vent block or Aluminium ventilation panels at high level.

• Each transformer plinth to be able to take a dead load of 6 tonnes.

• Door: 2.7M x 2.7M nett for each transformer. Heavy duty aluminium louvred doors complying with Appendix 13 drawings. Hasp and staple (150mm x 65mm x 6mm) complying with Appendix 13B for doors indicated only. Door hinges to be of brass or stainless steel.

• LV trench of 800mm min. width for every 1.5MVA or 2 x 1MVA transformers. Separate LV trench to be provided for additional transformers.

Wall / Column Finishes • All concrete surfaces shall be properly prepared and 20mm cement plastering work carried out such that there

should be no cracks, blisters and other defects

• The emulsion painting system used for external walls shall be suitable for outdoor application. There shall be a five (5) years warranty of the textured coating on all walls against all defects arising from colour-fastness, faulty workmanship and / or materials, etc.

80

Page 82: How to Apply

� Appendix 16 Rev 1 (Con’t)

Item Requirement

Electrical Installation • Schematic layout to be shown.

• All wiring to be in surface conduits.

• Circuits to be controlled by miniature circuit breakers and ELCB.

• 20A DP isolators for battery charger, RTU & PWS to tap supply by-passing ELCB.

• Substation to be adequately lit. T5 type light fittings are to be installed at 3M (suspension in type) and 2.4M (wall-mounting type) from floor level.

• Wire-mesh casing to be provided for T5 type light fittings installed in cable chamber.

• To label circuits at DB (distribution board) corresponding to the respective switches, sockets and isolators, etc.

Cable Chamber

‘Basement’ (where required)

• Trap door floor openings 760mm x 760mm leading to cable chamber to have: (a) Hinged aluminium chequered covers complete with wall catch. (b) Cat ladders with 6 non-skip steps. Details as shown on drawings.

• Adequate natural ventilation required with new PC vent block panels only. - Height : 2.0m with no part less than 1.5m.

- To paint the front and back of all beam with 50mmH red luminous paint.

- Chamber floor to be ‘suspended’ type capable of supporting 400 kg/m2 (min).

• Floor level : 150mm above the immediate external road/driveway level and above highest recorded flood level Wall and floor to be waterproofed and adequate drainage to be provided, where necessary.

• Heavy Duty aluminium Door : 1-leaf of dimension 1200W x 1500H, with door handle and 5 nos. of shoot bolts on internal side. Door details complying with Appendix 13A rev 2 drawing.

Metering Kisoks • To be provided for SPPG (see Appendices 31 to 33) when customer is taking HV supply.

Woodwork, Metal Work, etc • To be suitably painted and anti-termite treated for all woodwork.

Ceiling • To be smooth finishes and emulsion painted. All beam to be encased in RC concrete.

Roof • To be of flat RC suitably waterproofed and laid to falls of 1:80 minimum.

• Roof eaves with multiple 150mm wide long slot openings to be incorporated for rain water to free-fall direct into apron drain.

Drainage • Proper drainage around the substation to be provided with hinged hot-dipped galvanized m.s. gratings.

Gate / Perimeter

Fencing (where required)

• To be 1.8m high and designed to blend aesthetically with the overall development.

• Hollow section anodized aluminium gates complying with Appendix 14.

• Fence to be embedded into inner end of 600mm wide external concrete apron.

Access Road • To withstand heavy vehicles with laden load of 10 tonnes for all 22kV and 6.6kV substations.

• Width of driveway to be 4000mm (min) and surface to be paved with premix/tarmac, concrete or interlocking paviours only

• No car parking lots are to be drawn in such a way as to obstruct vehicular access to substation.

NOTES

(a) Appointed project LEW is to liaise closely with Architect and Structural Engineer to obtain all their respective requirements for incorporation

into final layout plans submitted for SP PowerGrid’s endorsement.

(b) All dimensions and figures as shown on plans endorsed by SPPG are to be checked by the Architect / structural engineer / appointed project

LEW prior to substation construction.

(c) If the Management Committee (MCST) / building owner / occupier were to subsequently replace the security personnel with other means

e.g. electronic security system etc; SP PowerGrid Ltd shall be consulted on the free unrestricted / unimpeded access arrangement to the

substation.

(d) LEW/M&E consultants are to ensure that the proposed substation is constructed according to plans endorsed by SPPG.

81

Page 83: How to Apply

■ Appendix 17

82

GENERAL REQUIREMENT FOR EHT SUBSTATION (66KV and 230KV ONLY)

1. Where an application for supply of electricity necessitates the provision of a substation, the site shall be provided and substation constructed by the applicant consumer at his own cost. The “Guidelines/Requirements for EHT Substation Buildings” will be made available in SPPG’s service connection proposal to the applicant.

2. The applicant shall grant SPPG, its officers and agents an irrevocable licence at all times to have full and unrestricted

use of the substation and have free access thereto. 3. SPPA may utilize the substation and site in such manner as it deems fit. Subject to the applicant’s requirement being

fully provided for, SPPA shall be at liberty to use the substation for the purpose of supplying other customers or for the improvement of the transmission network (e.g. upgrading, modification to substation structure, alteration and addition works, etc.)

4. The substation site within the substation perimeter fence shall be intended solely for the substation development. 5. The substation structure may be an independent building or form part of a larger building. It shall be located at the 1st

storey level and must be readily accessible from the public road. Proper vehicular access to the substation shall be provided for transportation of substation equipment by normal means, i.e. truck and trailer. The gradient of the access road to the EHT substation site (66kV and above) shall not be more than 1:20.

6. There shall be no danger from flooding and fire hazards. 7. The substation site shall be free from all encumbrances (existing and future proposed services). 8. Suitable and proper cable access shall be provided on at least two sides of the substation site for all cables entering

and leaving the proposed site. If there is any roadside drain fronting/surrounding the substation site, the applicant shall be required to install cable ducts under-crossing the drain. If the depth of the drain is more than 2.0 meters from the proposed substation ground level, the cable ducts shall be installed to over-cross the drains with approval from the relevant authorities.

10. The applicant consumer shall consider the effect of noise disturbance to neighbouring development in its selection of

the substation site. 11. The site of the substation shall be approved by SPPG and the relevant authorities. The applicant shall ensure that all

necessary approval for the substation site be obtained from the relevant authorities. 12. The applicant shall consult SPPG on the substation site before commencement of detail design for the substation

building. The applicant shall submit the necessary architectural and M&E design drawings, incorporating the necessary

requirements in the above-mentioned guidelines/requirements, for SPPG’s review and clearances. The applicant shall also obtain the necessary clearances from the relevant authorities.

Page 84: How to Apply

■ Appendix 18 PROTECTION REQUIREMENTS FOR CUSTOMER’S

22KV MAIN INCOMING SWITCHGEAR

O/C - Overcurr

Plug Sett

E/F - Earth fau

Plug Sett

PW - Pilot wire

A - Ammeter

CB - Circuit br

To circuit

500/5 CLASS 5P20 15VA OR BETTER

500/5 CLASS X

METERING CTs/PTs TO SPPG’S REQUIREMENTS

Notes:

1. Pilot wire protectio

a. Rated knee p

b. Exciting curre

c. Resistance o

2. No other auxiliary

be towards protec

3. Where there is m

mechanically inter

4. All 22kV circuits i

of fault at cable te

INCOMING SUPPLY FROM SPPA SUB-STATION

83

CUSTOMER’S 22kV MAIN INC

ent relay type IDMTL with 3/10 charact

ing =100%, Time Multiplier=0.1.

lt relay type IDMTL with 3/10 characte

ing =20%, Time Multiplier=0.1.

protection relay Solkor ‘R’/ ‘RF’, HOR

eaker

breaker trip circuit

M REVENUE METERS

A E/F

R Y

CABLE TERMINATIONS

n CTs shall comply with the following

oint voltage at maximum secondary tu

nt at the rated knee point voltage not m

f the secondary winding, corrected to 7

device shall be connected to the pilot

ted line.

ore than one incoming service, a bus

locked against parallel operation of the

n the customer installation shall be eq

rminations.

O C

O C

O C

PW

CB

OMING SWITCHB

eristics.

ristics.

4, MHOR.

requirements:

rns not less than 80V

ore than 150mA.

5oC not more than 0

wire protection CTs.

-section breaker sh

incoming services.

uipped with unit-prot

PILOT WIRES TO SPPA’S SWITCHGEAR

B

OARD

.

.15 ohm.

Pilot wire protection CT star-point shall

all be provided and be electrically and

ection for fast fault clearance, inclusive

Page 85: How to Apply

■ Appendix 18 PROTECTION REQUIREMENTS FOR CUSTOMER’S

LT MAIN INCOMING SWITCHGEAR

Y

BXB R

INCOMING SUPPLY

CLASS 5P10 15VAOR BETTER

CU

O/C - Overcurrent relay type IDMTL of approved load with a time laapproved load with a time multsource from SPPA’s 22kV subs

E/F - Earth fault relay operating at pwith time lag of not more than 0

Note: LEW is reminded that unohm. The maximum earth fault

CT - Current transformer Class 5P1CB - Circuit breaker with adequate

series trip (Direct acting trip) dfuses in series.

To circuit breaker trip circuit.

Note: Where there is more than one incoming interlocked against parallel operation of the

O C

0 e

s

O C

w

r

d

i

O C

84

KWH

STOMER’S LT INCOMING SWITCHBOARD

ith 3/10 characteristics or DTL relay. For DTL rg of not more than 0.5 sec. For IDMTL relay, thiplier of 0.1 (or 0.2 for approved load more than tation). imary fault current of 20% of approved load sub.5 second. er CP5, the overall ohmic resistance of earthing

current setting shall be equal to 50V divided by th, 15VA or better. breaking capacity and circuit breaker using shvice that operates with no time delay under sho

ervice, a 4-pole bus-section breaker shall be ncoming services.

REVENUE METER

E/F

METERING CTs

N

C

elay, the setting shall be 100% e plug setting shall be 100% of 1.5kA and up to 2.2kA and with

ject to a maximum of 120 Amp

system should not exceed one e earth resistance value.

unt trip shall be provided with rt-circuit condition, or with HRC

provided and be mechanically

Page 86: How to Apply

■ Appendix 18

85

TYPE 1: CUSTOMER 66KV FEEDER CONNECTION (WITHOUT EMBEDDED GENERATION PLANT)

Type 1a : Supply from SPPA 66kV Source Station

Numerical Relay System (OFC) (see note iii) Feeder Main 1 Current Differential 1 Feeder Main 2 Current Differential 2

Inter-tripping Current Differential 1

Remote End Interlock (on ES & DS) Mechanical Electromechanical Relay System (Metallic pilot wire) (see note iii) Feeder Main 1 Solkor - Rf Feeder Main 2 Translay S Inter-tripping Solkor-Rf Remote End Interlock (on ES & DS) Mechanical Type 1b : Supply from SPPA 66kV Non-Source Station Numerical Relay System (OFC) (see note iii) Feeder Main 1 Current Differential

Inter-tripping Current Differential Remote End Interlock (on ES & DS) Mechanical Electromechanical Relay System (Metallic pilot wire) (see note iii) Feeder Main 1 Solkor - Rf Inter-tripping Solkor-Rf Remote End Interlock (on ES & DS) Mechanical

SPPA 66kV S/S

Feeder Main 1 (plus Main 2 if Source S/S)

87L

Interface points SPPA’s

Scope

Customer’s Scope

Pilot/OFC Marshalling Box

87L

Notes: Customer

66kV S/S i) All electromechanical feeder protection relays are to be

equipped with supervision and guard relays.

ii) Engineering and Protection details including interlocking and intertripping shall be discussed on application.

iii) For reason of obsolescence or availability, the type of

Relays, signalling equipment and protection schemes shall subject to review and confirmation during the consultation period.

iv) Intertrip and interlock schemes, where applicable, shall be implemented via the numerical current differential system or the dedicated signalling equipment if supplied.

v) Customer to supply and install pilot marshalling board of approved design to accommodate the optic fibre cables and other auxiliary cables.

vi) Customer shall be responsible for all termination works at their equipment.

Page 87: How to Apply

■ Appendix 18

86

TYPE 2: CUSTOMER 66KV FEEDER CONNECTION (WITH EMBEDDED GENERATION PLANT)

Feeder Main 1 (plus Main 2 if Source S/S)

Customer 66kV S/S

SPPA 66kV S/S

Customer’s Scope

SPPA’s Scope

Interface points

87L

87L

Pilot/OFC Marshalling Box

Signalling equipment

For inter-tripping and remote electrical interlock

Signalling equipment

Type 2a : Supply from SPPA 66kV Source Station Numerical Relay System (OFC) (see note iii)

Feeder Main 1 Current Differential 1

Feeder Main 2 Current Differential 2

Inter-tripping Signalling equipment Remote End Interlock (on ES, DS & CB)

Mechanical & Electrical (via signalling equipment)

Switching sequencing Signalling equipment

Electromechanical Relay System (Metallic pilot wire) (see note iii) Feeder Main 1 Solkor - Rf

Feeder Main 2 Translay S

Inter-tripping Signalling equipment

Remote End Interlock (on ES, DS & CB)

Mechanical & Electrical (via signalling equipment)

Switching sequencing Signalling equipment Type 2b : Supply from SPPA 66kV Non-Source Station Numerical Relay System (OFC) (see note iii)

Feeder Main 1 Current Differential Inter-tripping Signalling equipment

Remote End Interlock (on ES, DS & CB)

Mechanical & Electrical (via signalling equipment)

Switching sequencing Signalling equipment

Electromechanical Relay System (Metallic pilot wire) (see note iii) Feeder Main 1 Solkor - Rf

Inter-tripping Signalling equipment Remote End Interlock (on ES, DS & CB)

Mechanical & Electrical (via signalling equipment)

Switching sequencing Signalling equipment

Notes: v) Customer shall be responsible for all termination works at their equipment. i) All electromechanical feeder protection relays are to be

equipped with supervision and guard relays.

ii) Engineering and Protection details including interlocking

and intertripping shall be discussed on application.

iii) For reason of obsolescence or availability, the type of

Relays, signalling equipment and protection schemes shall

subject to review and confirmation during the

consultation period.

iv) Customer to supply and install pilot marshalling board of

approved design to accommodate the optic fibre cables

and other auxiliary cables.

Page 88: How to Apply

■ Appendix 18

87

TYPE 3: CUSTOMER 66KV FEEDER TRANSFORMER CONNECTION

Type 3a : Supply from SPPA 66kV Source Station

Numerical Relay System (OFC) (see note iii) Feeder Main 1 Current Differential 1 Feeder Main 2 Current Differential 2 Inter-tripping Current Differential 1 Remote End Interlock (on ES & DS & neutral)

Mechanical

Electromechanical Relay System (Metallic pilot wire) (see note iii) Feeder Main 1 Solkor - Rf Feeder Main 2 Translay S Inter-tripping Signalling equipment Remote End Interlock (on ES & DS & neutral)

Mechanical

Type 3b : Supply from SPPA 66kV Non-Source Station Numerical Relay System (OFC) (see note iii)

Feeder Main 1 Current Differential

Inter-tripping Current Differential

Remote End Interlock (on ES & DS & neutral)

Mechanical

Electromechanical Relay System (Metallic pilot wire) (see note iii) Feeder Main 1 Solkor - Rf Inter-tripping Signalling equipment Remote End Interlock (on ES & DS & neutral)

Mechanical

Include REF, TF Diff, OC/EF & other local protection system

Customer22kV S/S

Customer’s Scope

SPPA’s Scope

87L

Feeder Main 1 (plus Main 2 if Source S/S)

87L

Pilot/OFC Marshalling Box

Interface points

87T

SPPA 66kV S/S

Notes:

i) All electromechanical feeder protection relays are to be

equipped with supervision and guard relays.

ii) Engineering and Protection details including interlocking and intertripping shall be discussed on application.

iii) For reason of obsolescence or availability, the type of

Relays, signalling equipment and protection schemes shall subject to review and confirmation during the consultation period.

iv) Intertrip and interlock schemes, where applicable, shall be implemented via the numerical current differential system or the dedicated signalling equipment if supplied.

vi) Customer shall be responsible for all termination works at their equipment.

v) Customer to supply and install pilot marshalling board of approved design to accommodate the optic fibre cables and other auxiliary cables.

Page 89: How to Apply

■ Appendix 18

88

TYPE 4: CUSTOMER 230KV FEEDER CONNECTION

Supply from SPPA 230kV Source Station Numerical Relay System (OFC) (see note ii)

Feeder Main 1 : Current Differential

Feeder Main 2 : Current Differential with Distance Protection

Teleprotection Signalling equipment

Inter-tripping Signalling equipment

Remote End Interlock (on ES, DS & CB):

Mechanical & Electrical (via signalling equipment)

Switching sequencing: via signalling equipment

Notes:

Customer 230kV S/S

SPPA230kV S/S

Customer’s Scope

SPPA’s Scope

Interface points

87L

87L

Pilot/OFC Marshalling Box

Main 1 and Main 2

Signalling equipment

For teleprotection inter-tripping and remote electrical interlock

Signalling equipment

i) Engineering and Protection details including interlocking

and intertripping shall be discussed on application.

ii) For reason of obsolescence or availability, the type of

relays, signalling equipment and protection schemes shall

subject to review and confirmation during the consultation

period.

iii) Customer to supply and install pilot marshalling board of

approved design to accommodate the optic fibre cables

and other auxiliary cables.

iv) Customer shall be responsible for all termination works

at their equipment.

Page 90: How to Apply

■ Appendix 18

89

TYPE 5: CUSTOMER 230KV FEEDER TRANSFORMER CONNECTION

Supply from SPPA 230kV Source Station

Numerical Relay System (OFC) (see note ii)

Feeder Main 1 Current Differential

Feeder Main 2 Current Differential with Distance Protection

Teleprotection signalling equipment

Inter-tripping signalling equipment

Remote End Interlock (on ES, DS & CB)

Mechanical & Electrical (via signalling equipment)

Switching sequencing signalling equipment

Notes:

i) Engineering and Protection details including interlocking and intertripping shall be discussed on application.

ii) For reason of obsolescence or availability, the type of

relays, signalling equipment and protection schemes

shall subject to review and confirmation during the consultation period.

iii) Customer to supply and install pilot marshalling board of approved design to accommodate the optic fibre cables and other auxiliary cables.

iv) Customer shall be responsible for all termination works at their equipment.

Customer’s Scope

Include T/F Diff, REF, OC/EF & other local protection system

SPPA’s Scope

87L

87L

Customer 230kV S/S

Pilot/OFC Marshalling Box

Interface points

Main 1 and Main 2

87T

Signalling equipment

For teleprotection inter-tripping and remote electrical interlock

Signalling equipment

SPPA 230kV S/S

Page 91: How to Apply

APPLICATION FOR DE-ENERGISATION / RE-ENERGISATION (ADRE)

Licensed Installation No

Service No Voltage

Name of Installation:

Address of Installation:

Requested De-energisation Requested Re-energisation

Date Time *am/pm Date Time *am/pm

Contestable Customer:

*Yes / No

#Name of Customer: #MSS A/C No: #Name of Retailer:

To: *Deputy Director (EHV Network) *Deputy Director (Regional Network – *West / Central / East / North / South) *Deputy Director (Customer Projects – *East / West) *Deputy Director (Distribution Projects)

(1) I, the undersigned LEW for the above installation, wish to apply for a *de-energisation / re energisation at the time stated above. My work, after the de-energisation, will involve the following:

*1 Routine Servicing

2 (Please Specify)

(2) * I / or ________________________________________ (Name / Licence No of appointee approved by Regulation Division of EMA) will attend to the *de-energisation / re-energisation PERSONALLY.

(3) I understand that: - (a) No work is to be carried out on the service cable until both SP PowerGrid officer and

myself have signed the SDRE (“Statement for De-energisation and Re-energisation”) after we have safely isolated the service cable at both ends.

(b) I am required to be on time on the approved date of de-energisation or re-energisation, failing which the SP PowerGrid officer may cancel any appointment made.

Signature: ______________________________ Telephone / HP No.: __________________

Name: _________________________________

Date: _______________ Licence No: _________________ * Grade: Engineer Technician Electrician

Notes: (a) All requested date and time are subject to SP PowerGrid’s approval. (b) For non-contestable customers, this form should reach SP PowerGrid 7 business days before the

requested date. (c) For contestable customers, this form should reach SP PowerGrid 14 business days before the

requested date. (d) For urgent work on Sundays / Public Holidays and after office hours, LEW is required to co-

ordinate with SP PowerGrid personally. (e) * Delete whichever not applicable. (f) # To be filled in for contestable customer.

Section Fax No Tel No EHVN 62909124 62909121 RNW 66609390 66609301 RNC 62799590 62799501 RNE 62409203 62409218 RNN 67653745 63146172 RNS 62909110 62909101 CPE 62409225 62409257 CPW 62799532 62799559 DP 62909140 62909139

■ Appendix 19

90

Page 92: How to Apply

SP POWERGRID LTD A No. 00001 ■ Appendix 20

STATEMENT FOR DE-ENERGISATION AND RE.ENERGISATION (SDRE)

Part I & II concern the de-energisation and re-energisation of the service cable specified below. Each statement is valid only when it is signed by both the LEW of the installation and the SP POWERGRID officer-in-charge of the de-energisation or re-energisation. Name Of Installation: __________________________________________________________________________________ Service Cable No.: *1 / 2 / 3 / 4 Isolated From (Substation Name, OG Box Etc): _____________________________________________________________ This de-energisation is *due to tripping/requested by SP PowerGrid / requested by LEW. * - please delete whichever is not applicable ___________________________________________________________________________________________________ PART I: DE-ENERGISATION STATEMENT (TO BE SIGNED AFTER DE-ENERGISATION) (This statement is required only when work is to be done on the service cable by either the LEW or the SP PowerGrid officer, or both) Date: ________________________________ Time: ____________________________ DECLARATION BY LEW: I, the undersigned LEW, hereby declare that the above service feeder has been turned off and safely isolated from the customer’s intake switchboard. Signature: ___________________ Name: _____________________ Licence No.: __________________________ DECLARATION BY SP POWERGRID OFFICER I, the undersigned SP POWERGRID officer, hereby declare that the above service cable has been de-energised and safely isolated from the SP PowerAssets’ network. Signature: ___________________ Name: _____________________ Section: _____________________________ As agent for and behalf of SP PowerAssets Ltd ___________________________________________________________________________________________________ PART II: RE-ENERGISATION STATEMENT (TO BE SIGNED BEFORE RE-ENERGISATION) DATE: ____________________________________ TIME: _____________________________ DECLARATION BY LEW: I, the undersigned LEW, hereby declare that the consumer's switchgear, to which the above mentioned service feeder is connected, is cleared of all earthing leads, labour and tools, and that the switchgear is fit for re-energisation from SP POWERASSETS’ end with effect from the time specified above. I undertake to ensure that no work by any person will be carried out on the service feeder at the consumer's end until a new shutdown statement is signed by both parties. Signature: ___________________ Name: _______________________ Licence No: ______________________________ ACKNOWLEDGEMENT BY SP POWERGRID OFFICER: Signature: ___________________ Name: _______________________ Section: _________________________________ As agent for and behalf of SP PowerAssets Ltd ___________________________________________________________________________________________________ PART III: DECLARATION BY LEW ON THE TIME OF TURN-OFF AND TURN-ON OF INCOMING SUPPLY AT CUSTOMERS’S INTAKE SWITCHBOARD (for Contestable Customer only) To: SP SERVICES LTD (Fax no: 63092509, Tel no: 63092543) Name of Customer: ___________________________________________ MSS A/C No: _______________________ Address of Installation: ________________________________________________________________________________ DECLARATION BY LEW: I, the undersigned LEW, hereby declare that I had turned-off and turned-on the incoming supply at customer’s intake switchboard at the following date / time: Date of Turn-Off: ___________________________ Time of Turn-Off: __________________________________ Date of Turn-On: ___________________________ Time of Turn-On: __________________________________ Signature: ____________________ Name: _________________________ Licence No. ______________________

91

Page 93: How to Apply

■ Appendix 21

92

CERTIFICATE OF READINESS FOR THE ENERGIZATION OF SERVICE CONNECTION

Name of Customer Installation:

Address:

Customer Installation Licence No/Expiry Date:

Connection Voltage:

Approved Load:

Name of Connection Cable(s):

Owned by Connection Applicant (Yes / No)

MSS Account No:

Name of Retailer:

Certification By LEW I, ______________________(name) the undersigned LEW, hereby certify that the service connection*, the equipment and works at the above installation (Licence No: ______________) is now ready and fit for energisation with effect from the date and time specified below. Date:

Time: I certify that: a. protection details are as follows:

CT Ratio: /1A or 5A* Short-Time Withstand Current Ratings of Main Supply incoming Switchgear kA for 1 sec or 3 sec Main 1 Type: Main 2 Type*: Direct Acting Tripping Setting :___________O/C Type: Setting: E/F Type: Setting:

b. the switching equipment/transformer/service connection* and all associated apparatus related to the service

connection have been tested and checked by me and they have passed the pre-commissioning checks and tests in compliance with the Market Rules, Transmission Code, Handbook on How to Apply for Electricity Connection, Connection Agreement, all other applicable standards, and the associated protection systems have all been proven effective

c. The main protection schemes for the service connection have been commissioned by load simulation method

on date: _______________**. d. *for multi-metered installation with the exception of HDB residential installation, the metering scheme has

been designed as master/sub-metering scheme. * Delete where applicable ** To indicate NA where protection scheme is not applicable

Page 94: How to Apply

■ Appendix 21

93

e. all necessary meters have been installed. f. the safety coordination requirements of the Transmission Code have been fully complied with.

g. all workmen have been withdrawn and warned that it is no longer safe to continue to work on the equipment

without a ‘Permit-to-work (PTW)’, and that all tools, scaffolding, ladders, construction materials including any temporary local earthing connections have been removed from the equipment, and all protective screens or guards, if any, have been securely fixed and the appropriate warning signs displayed and that all keys, if any, necessary for the isolation and operation of the equipment have been handed to me.

h. all circuit earth on equipment to be energized are removed.

i. equipment to be energized in this request (the diagram must clearly indicate the portion of the

equipment to be energized. If space is insufficient, please provide diagram as attachment) is shown below:

Name & Signature of LEW requesting for energisation of supply line

Licence No. Date

Page 95: How to Apply

Appendix 22.1

FORM CS/6 REQUEST FROM CONTESTABLE CUSTOMER FOR INSTALLATION OF ELECTRICITY KWH METER

For Official Use Serial No. : ________________________ CMS Installation no. : _____________________

PART I : Customer Details – To be completed by LEW

To Meter Section, SP PowerGrid Ltd through SP Services Ltd

Name of Customer(Mr/Mdm) /Company(Messrs): __________________________________________

NRIC/Company ROC: ____________ Telephone No. : ____________ Pager/Handphone No. : _________

Existing MSS Account no (if any) : ___________________ Master Account No.(if any) : ______________

Application no.: ____________________ Type Of Business: ___________________________

Site Address as given by IRAS :___________________________________________________________ (You are required to enclose a copy of the IRAS letter.)

Telephone No(s)/point(s) : _______________________________________________________________ (For contestable customer, you are required to install telephone point(s) adjacent to the meter panel and provide the telephone no. before applying for the installation of the meters)

Supply Capacity :___________KVA/KW at ___________ Volts [Form CS/3 or CS/3H(if supply is from landlord) and COC shall be submitted together with this form]

Metering Scheme: ________________ Turn on date : ______________________

Source of supply : SP PowerAssets Landlord

Type of connection : New Connection Upgrading Downgrading

I hereby confirm that the electrical wirings at the meter installation have been checked and certified correct.

Name of LEW : ___________________ LEW License no. : ______________

Telephone no. : _____________ Handphone no. : _____________ Facsimile no. : ____________

Signature : __________________________________ Date : _______________________ *Note: For new supply, customer may apply for contestability status & MSS account no. after meters have been installed. LEW shall apply for license under this MSS account no. to operate electrical installation before proceeding to Installation Section to book for turn on appointment date.

__________________________________________________________________________________________________________________ PART II – To be completed by SP Services Ltd To Meter Section, SP PowerGrid Ltd – Application is in order. Please arrange to install the revenue meters.

Name : _____________________ Signature: _____________________ Date : _______________ __________________________________________________________________________________________ PART III – To be completed by Meter Section SP PowerGrid Ltd To Supply Application, SP Services Ltd – Meters had been installed on _______________. Details in CMS.

Name : _____________________ Signature: ________________________ Date : _____________________ ________________________________________________________________________________________________________________ PART IV (For official use) To Meter Data Management Branch, SP Services Ltd Facsimile no.:6737 2472

Date : _____________________ Data Entered by: ________________________ Signature : _______________ (Full Name) ________________________________________________________________________________________________________________ .PART V (For official use) To Client Relation Branch (MSSL Section), SP Services Ltd

Create MSS Account no. : ______________________ Consumer has been notified MSS account no.

Date : ______________ Account Opened by: ________________________ Signature : _______________ (Full Name)

94

04/07/05

Page 96: How to Apply

Appendix 22.2 Form CS/7 REQUEST FOR INSTALLATION OF ELECTRICITY KWH METER (FOR LOAD EXCEEDING 45KVA)

For Official Use Serial No. :______________________________ CMS Installation No. : ____________________

PART I Customer Details – To be completed by LEW To Meter Section, SP PowerGrid Ltd through SP Services Ltd

Name of Customer(Mr/Mdm) /Company(Messrs): _________________________________________________

NRIC/Company ROC:________________ Name of Contact Person for Company: _______________________

Telephone No. : ____________________ Pager/Handphone No. : ____________________

Site Address for Installation of Meter: ___________________________________________________________

Detail location of supply intake point: ___________________________________________________________

A/c no.: : _________________________ Master A/c no.: ___________________________

Source of supply : SP PowerAssets Landlord HDB Type of connection : New Connection Upgrading Downgrading Others : ____________ Supply Capacity :___________kVA/kW at ___________ Volts Type of Business: ______________________ (Form CS/3 or CS3/H and COC shall be submitted together with this form)

Details of Landlord/MCST

Name of Landlord/MCST: _______________________________ Landlord’s Account no. : ___________________

Forwarding Address : _______________________________________________________Postal Code ________

Name of LEW in charge of landlord’s electrical installation : ____________________________________________

Contact no of Landlord’s LEW : _____________________________

____________________________________________________________________________________________

I hereby confirm that the electrical wirings at the meter installation have been checked and certified correct.

Name of LEW : ___________________ LEW Licence no. : ___________

Forwarding Address (as registered with EMA) : ____________________________________Postal Code_________ Telephone no. : _____________ Handphone no. : ______________ Facsimile no. : ______________ Signature : __________________________________ Date : ____________________ ____________________________________________________________________________________________

PART II - To be completed by SP Services Ltd To Meter Section, SP PowerGrid Ltd -- Application is in order. Please arrange to install the revenue meters. Name : Signature : Date :

PART III -To be completed by Meter Section SP PowerGrid Ltd To Supply Application, SP Services Ltd - Meters had been installed on ____________. Details in CMS. Name : Signature : Date : _____________________________________________________________________________________________________________________________________________________________________________________

PART IV (For official use)

Check and perform Master-sub Tagging

Sent to CRO for account move in on ____________

Move in/ Turn-On Date is on __________________

5

9 01/07/05
Page 97: How to Apply

■ Appendix 23

96

APPLICATION FOR APPOINTMENT FOR ENERGISATION OF SERVICE CONNECTION BY FAX

FACSIMILE TRANSMITTAL SHEET Total No. of Pages (including this page): [ ]

To: Deputy Director, Installation Branch From [Name of LEW]:

Company: SP Services Ltd Company:

Fax No.: 62777044 Fax No.:

Date: Office Telephone No.:

Application No.: Pager/Handphone No.:

MSSL A/C No.: Approved Load: I would like to make an appointment for energisation of service connection to __________________________________________ _______________________________________________________________________________________________________.

(site address) The following documents are faxed together with this application.

Documents Tick if applicable 1) Opening of Account with SP Services Ltd

2) Opening of Account with Electricity Retailer (for contestable consumer)

3) Confirmation of meters already fixed (for contestable consumer)

4) Electrical Installation Licence issued by EMA

5) Certificate of Compliance (original to be submitted to SPPG’s project officer)

6) Letter from IRAS confirming official address

I will submit the Certificate of Readiness on site, failing which service connection shall not be energised and SPPG & SPPA shall

not be liable for any loss arising therefrom.

I understand that the date of appointment is subject to confirmation by SP Services Ltd and the appointment date shall not be earlier than 4 business days from this fax date. The preferred appointment dates are as follows: 1st choice: Date: Time: Morning / Afternoon* 2nd choice: Date: Time: Morning / Afternoon* 3rd choice: Date: Time: Morning / Afternoon*

( *delete whichever not applicable ) Name & Signature of LEW Licence No. ………………………………………………………………………………………………………………………………………………………… FOR OFFICIAL USE The appointment for energisation of service connection is fixed on __________________________ at ____________________. (date) (time)

Please liaise with Meter Section of SPPG for the fixing of revenue meter before the energisation. For clarification, please contact ______________ at Telephone No.: 627770 __________.

Page 98: How to Apply

■ Appendix 24

97

TECHNICAL REQUIREMENTS FOR SERVICE CABLE AND METER COMPARTMENT FOR LANDED HOUSES

1 The service cable termination and meter compartment shall be located at the front-gate pillar/perimeter wall such that it is accessible to SPSL's and SPPG's officer without the need to enter the customer's premises.

2 It shall be constructed of concrete, brick or high impact fibre glass and shall be completely weatherproof. Provision shall be made to prevent any stagnation of water within the compartment.

3 The main dimensions of the compartment are shown in the layout drawing (see Appendix 25). The depth of the compartment shall be between 250 mm and 300 mm.

4 A meter board of 20 mm thick and constructed of teak wood or any hardwood chemically treated against termite attack shall be provided. Plywood board is not acceptable. A minimum space of 450 mm (W) x 800 mm (H) shall be allowed for the termination of the service cable and the installation of service MCBs and meters. Customer's MCBs or connectors shall be mounted on a separate board in a separate compartment.

5 A hinged door with a clear glass viewing window shall be provided. The viewing window with a 200 mm (W) x 300 mm (H) x 6 mm (thickness) glass cover shall be positioned to be directly in front of the meter location. To avoid high humidity and condensation within the compartment, sufficient ventilation shall be provided. The access door shall not have less than 450 mm clear access opening.

6 The door shall be constructed of stainless steel, anodised aluminium or high impact type fibre glass reinforced material. Where a metal door is provided, a means of earthing shall be provided.

7 One 100mm diameter UPVC lead-in pipe shall be provided for SPPA service cable. The pipe shall be laid up to 100 mm from the floor slab of the electric meter compartment and shall undercross any drain in front of the compartment.

8 There shall be adequate standing space in front of the compartment to facilitate meter reading, installation and maintenance work. Where there exists a drain in front of the compartment, a suitable concrete platform or hinged galvanised steel grating shall be provided.

9 The compartment shall be exclusively used for service cable and electricity meter. No water meter, gas meter or other facilities shall be placed within the same compartment.

10 Please obtain clearance from URA's Development Control Division if the meter-box structure exceeds their stipulated dimensions.

Page 99: How to Apply

■ Appendix 24

98

STANDARD METER COMPARTMENTS AT GATE PILLAR

Page 100: How to Apply

■ Appendix 25

99

STANDARD METER BOARD

Page 101: How to Apply

STANDARD SIZE FOR SINGLE-PHASE METER BOARD■ Appendix 26

Fig A

MCB / cut-outMax 100 Amps

Neutral

SinglePhaseMeter

230 mm

280

mm

L

(L =

300

mm

for 3

5 sq

mm

cab

le)

40 m

m

Live

Neu

tral

Neu

tral

Load

PGElectricalServiceBox

Live

Neu

tral

Neu

tral

Load

230 mm

40 m

m

L

(L =

300

mm

for 3

5 sq

mm

cab

le)

280

mm

SinglePhaseMeter

Fig CSinglePhaseMeter

230 mm

L

(L =

300

mm

for 3

5 sq

mm

cab

le)

40 m

m

MCB / cut-outMax 100 Amps Neutral

Fig B

280

mm

Live

Neu

tral

Neu

tral

Load

1. Minimum space for single-phase meter position (enclosed within broken lines):(i) 230mm (W) x 280 mm (H) for 25 sq. mm cable and below.(ii) 230mm (W) x 300 mm (H) for 35 sq. mm cable.

2. A customer’s earthing terminal shall be provided on the meter board for termination of the earthing lead and earth continuity conductor.

3. Not more than one wire should be connected to each terminal of the meter terminal block.4. All wires on the meter board from MCB/Cut-Out to the meter and meter to main switch

should preferably be run on the surface.5. The size of cables to be used for connection to meters should not exceed 35 sq. mm.6. The length of wire “L” protruding from the meter board to the meter terminal shall be at least

200 mm.7. For meters grouped in a centralised meter room etc, an additional minimum spacing of

70mm is necessary between each row of meters for ease of installation/change.8. The meter cables should be colour-coded red for ‘live’ and black for Neutral.9. Some typical layouts are shown in figures A, B and C.

Note : Drawing not to scale. All dimensions in mm.100

Page 102: How to Apply

■ Appendix 27

STANDARD SIZE FOR THREE-PHASE METER BOARD

Overhead Type

MCB / cut-outMax 100 Amps

Neutral

WholeCurrentPolyPhaseMeter

450 mm

450

mm

40 m

m

Mai

nLo

adM

ain

Load

Mai

nLo

adN

eutra

lLo

adL

Type-written on cable sleeve

(L =

300

mm

for 3

5 sq

mm

cab

le)

MCB / cut-outMax 100 Amps

Neutral

WholeCurrentPolyPhaseMeter

450 mm

450

mm

40 m

m

Mai

nLo

adM

ain

Load

Mai

nLo

adN

eutra

lLo

adL

UnderGround Type

Type-written on cable sleeve

(L =

300

mm

for 3

5 sq

mm

cab

le)

1. Minimum space for three-phase meter position 450 mm (W) x 450 mm (H) (enclosed withinbroken lines).

2. A customer’s earthing shall be provided on the meter board for termination of the earthing lead and earth continuity conductor.

3. Not more than one wire should be connected to each terminal of the meter terminal block.

4. All wires from the meter board from MCB/Cut-Out to meter and meter to main switch should preferably be run on the surface.

5. The size of cables to be used for connection to meters should not exceed 35 sq. mm.

6. The length of wire “L” protruding from the meter board to the meter terminal shall be at least 200 mm.

7. The meter cables should be colour-type respective to their phases or be shrouded with coloured sleeving.

Note : Drawing not to scale. All dimensions in mm.

101

Page 103: How to Apply

■ Appendix 28

102

CT METER PANEL FOR LOW TENSION SUPPLY

Page 104: How to Apply

■ Appendix 29

103

METHODS OF SEALING METERING PANELS

Page 105: How to Apply

■ Appendix 30

104

ENCLOSURE FOR LOW TENSION METERING CURRENT TRANSFORMERS

Page 106: How to Apply

■ Appendix 31

105

HT METERING KIOSK REQUIREMENTS

(FOR 1 OR 2 FEEDERS)

Meter Panel

Note: Drawing not to scale. All dimension in mm

Side Elevation of Metering Kiosk for 1 or 2 feeder panel The following are required: a) Metering kiosk : 650mm by 1700mm by minimum height 2400mm of solid brick as shown. b) Floor opening 50mm by 50mm as shown. c) Staircase and 1000mm landing where required. d) Steel or heavy duty aluminium door of 1200mm wide by 2100mm height to be fitted with one of the SPPA approved master series locksets as given in section 6.1.5. e) One 13A switched socket outlet, one 40W lighting points and one fixed telephone c/w telephone socket outlet. f) If landing is above ground level, safety railings must be provided.

Page 107: How to Apply

■ Appendix 32

HT METERING KIOSK REQUIREMENTS (FOR 3 OR 4 FEEDERS)

2100 mm highheavy duty aluminium door

Note : Drawing not be scale. All dimension in mm

STAIRS

1000 mm

100 mm x 60 mm floor openingBASEMENT

40W fluorescent lamp

100 mm thick

610 mmr.c. floor

Side Elevation of Metering Kiosk for 3 or 4 feeder panel

The following are required :

a) Metering kiosk : 810mm by 2650mm by minimum height 2400mm of solid brick as shown

b) Floor opening 100mm by 60mm as shown.

c) Staircase and 1000mm landing where required.

d) Heavy duty aluminium door of 800mm width by 2100mm height to be fitted with oneof the the SPPA approved master series locksets as given in section 6.1.5.

e) One 13A switched socket outlet, two 40W lighting points and one fixed telephone line c/w telephone socket outlet.

f) If landing is above ground level, safety railing must be provided.

106

Page 108: How to Apply

■ Appendix 32

HT METERING KIOSK REQUIREMENTS (FOR 3 OR 4 FEEDERS)

a = b = c =

40 W fluorescent lamp

107

40W fluorescent lamps 13A switched socket outlet 5A switch for fluorescent lamps

Page 109: How to Apply

■ Appendix 33

108

HT METERING PANEL REQUIREMENT

(FOR 1 OR 2 FEEDERS)

Page 110: How to Apply

■ Appendix 34

109

METERING VTS Voltage Ratio, Sequence & Phase Angle Tests Report

Customer : ____ A/C No. : Project Address : A/C No. : PT No. : Voltage Ratio : For Feeder No. : I, , EMA Licensed No. had carried out the above test and results are given below. I hereby certified that the VTs are correctly connected up for tariff metering. Stamp & Signature of LEW Date :

Secondary Phase Angle Primary ( V) Across Sequence Across Volt

Frequency Lead Lag

RY RE

YR

YB YE

RY

BR BE

YB YE

BY

BR BE

YB

RY RE

BR BE

RB

RY RE

BR

YB YE

Page 111: How to Apply

■ Appendix 35

110

BASIS FOR THE SERVICE CONNECTION CHARGE

1 Service Connection Charges for Low Tension (LT) Connection

All LT consumers are required to pay a one-time upfront service connection charge. These charges which vary for different load requirements are categorised depending on the provision of a substation.

For larger consumers with substations, their supply intake point is usually adjacent to the substation, which requires a service cable of approximately 15m in most instances. Therefore, the standard connection charge is computed based on a cost of service cable length of 15m. Consumers shall pay the additional cost for service cable exceeding 15m. In addition, consumers shall also pay for those dedicated assets, such as switchgear and transformers, which are serving them and do not benefit others.

For individual small consumers without substations, the cost of LT service cable for the same capacity may vary widely depending on their locations with respect to the nearest LT mains. These consumers are not the sole beneficiaries of the extension of the LT network. To achieve a greater degree of equity in terms of cost for these general consumers, a standard cost approach is adopted based on similar requirements. The average global cost based on capacity is determined from past statistics. As such, this category of consumers which comprises mainly the individual landed residential owners, applying for the same applied load would pay the same standard connection charge regardless of the location of their premises from the existing LT network.

Standard charges are only applicable to consumers who are connected to the shared network. The rates, which are approved by EMA, are available in the Transmission Services Rate Schedule. Standard charges are not applicable to consumers where the network created is unlikely to be shared by others. Some of these include supply to HDB premises, premises involving installation of bigger capacity cable in order to overcome the excessive voltage drop, temporary work sites, public installations and offshore island premises. These consumers would have to pay for the full connection network cost, based on user-pay principle, as they are the main beneficiaries.

2 Service Connection Charges for HT and EHT Connection

Customers receiving HT and EHT connection shall pay the cost of the service connections to their intake equipment including cables, associated equipment and facilities to effect the connection of customer’s equipment to SPPA’s substation/network. The service connection shall cater for single contingency.

Customers requesting for additional level of contingency above single contingency are required to pay for the full cost of such provision.

3 Dedicated Network/Substation

The customer shall pay the full cost for all associated equipment and facilities under a dedicated network/substation scheme which the network capacity is intended to serve to its development exclusively.

Substation comprises land, building, electrical equipment and associated cables. Substations which serve a development or premises have to be provided and paid for by the developer or customer. As the capacity of electrical equipment is lumpy, the substations may have excess capacity. The developer or customer will carry the cost of this excess capacity which cannot be avoided. As these substations are required to serve the development or customer loads, they are dedicated substations.

To reduce cost, a developer or customer can choose to let SPPA bear the cost of the electrical equipment and associated cables. In return, SPPA must therefore be allowed to sell off the excess capacity. Even after the excess capacity is sold off, SPPA remains committed to return the capacity to the customer if his demand grows later. At present, most substations provided by developer or customer are non-dedicated substations.

Page 112: How to Apply

■ Appendix 36

111

STANDARD SERVICE CONNECTION CABLES The type of service connection cables for terminating into a customer’s intake point for the applied load connected at the LT and 22kV level and the typical connection schemes are illustrated as follows: Voltage Level Applied Load (kVA) Size of Cables Type of cables

Up to 15 35mm2 2Core Cu/XLPE/SWA/PVC 16 – 45 35mm2 4Core Cu/XLPE/SWA/PVC 46 – 75 35mm2 4Core Cu/XLPE/SWA/PVC 76 – 140 120mm2 4Core Al/XLPE/SWA/PVC 141 – 180 185mm2 4Core Al/XLPE/SWA/PVC 181 – 230 300mm2 4Core Al/XLPE/SWA/PVC 231 – 280 300mm2 4Core Cu/XLPE/SWA/PVC 281 – 460 2x300mm2 4Core Al/XLPE/SWA/PVC 461 – 560 2x300mm2 4Core Cu/XLPE/SWA/PVC 561 – 1000 7x500mm2 1Core Cu/XLPE/PVC 1001 – 1500* 7x1000mm2 1Core Cu/XLPE/PVC 1001 – 2000^ 2 sets of 7x500mm2 1Core Cu/XLPE/PVC

LT

2001 – 3000^ 3 sets of 7x500mm2 1Core Cu/XLPE/PVC Up to 12750kW^ 2x300mm2 3Core Cu/XLPE/DSTA/PVC 12751 – 25500kW^ 4x300mm2 3Core Cu/XLPE/DSTA/PVC 25501 – 38250kW^ 6x300mm2 3Core Cu/XLPE/DSTA/PVC

22kV+

Pilot cables 1.5 mm2 5 pair Cu/PE/DSTA/PVC For installations where the customers supply, install and maintain the service cables, to ensure that these cables comply with SPPA's specifications, the customers shall seek approval from Distribution Engineering Section prior to procurement. * applies to upgrading of applied load. + The 22kV scheme is designed to cater for the outage of a single service connection circuit. The customer is

required to reduce or maintain his load to within the rated capacity of the remaining service connection circuit(s) in the event of a busbar failure or outage for maintenance.

^ There must be an electrical and mechanical interlocking bus coupler between each set of cables terminating into the customer’s switchboard as shown below, and to ensure that there is no possibility of paralleling SPPA source:

Bus Coupler

HT Customer’s SwitchBoard

12751- 25500kW

7x500mm2 1Core 7x500mm2 1Core

LT Customer’s SwitchBoard 1001- 2000kVA

Bus Coupler

LT Customer’s SwitchBoard 2001- 3000kVA

7x500mm2 1Core 7x500mm2 1Core 7x500mm2 1Core

Bus CouplerBus Coupler

300mm2 3Core 300mm2 3Core HT Customer’s SwitchBoard

Up to 12750kW

Bus Coupler

300mm2 3Core 300mm2 3Core 300mm2 3Core

Normally Open

HT Customer’s SwitchBoard 25501- 38250kW (subject to SPPG approval)

300mm2 3Core 300mm2 3Core 300mm2 3Core 300mm2 3Core 300mm2 3Core 300mm2 3Core

Bus Coupler

Normally Open

Normally Open

Normally Open Normally Open

Normally Open

300mm2 3Core

Page 113: How to Apply

▅ Appendix 37

CERTIFICATE OF COMPLIANCE

Particulars of Electrical Installation

Name of Consumer: ________________________________________________

Address of Installation: ______________________________________________

_________________________________________________________________

Electrical Installation Licence No. _________ MSS Account No. _____________

Approved load & Supply Voltage: _______________ kW ____________ Volts

Generator(s) Installed: Operated in parallel with SP PowerAssets’ network.

No. of generator: ________ Rating: _________ kVA

Standby generator.

No. of generator: ________ Rating: _________ kVA

Not applicable

Electrical Installation Design Certification

I certify that the design of the above-mentioned electrical installation complies with the requirements of the Electricity (Electrical Installations) Regulations 2002 and the relevant Singapore Standard Code of Practice. With the certification of compliance by the LEW responsible for the installation work as shown below, I hereby request for the energisation of the supply line to the said electrical installation on _________________ (date). __________ _________ Name & Signature of LEW responsible Licence No. Date for design of electrical installation* Electrical Installation Inspection Certification I have supervised the work of the above-mentioned electrical installation and hereby certify that the electrical installation complies with the requirements of the Electricity (Electrical Installations) Regulations 2002 and the relevant Singapore Standard Code of Practice. I further certify that the technical requirements as stipulated by the person responsible for turning on the switchgear which controls the supply of electricity to the said electrical installation have been complied with.

__________ _________ Name & Signature of LEW responsible Licence No. Date for electrical installation work* * The same LEW may perform both design and installation work for the electrical installation. Copy to: Market Support Services Licensee

REF: E(EI)Reg5(2)

112

Page 114: How to Apply

■ Appendix 38

113

STATEMENT OF TURN-ON OF ELECTRICITY ELECTRICITY SUPPLY TO _____________________________________________________________ (Name of Applicant) AT__________________________________________________________________________________ (Address of Installation) ELECTRICAL INSTALLATION LICENCE NO : ______________________________________________ APPLICATION NUMBER : ______________________________________________________________ I agree that the above-mentioned electrical installation is suitable for connection to the electrical system. I certify that the supply line to the installation has been energised on

_______________________at ______________________. (date) (time)

____________________________________ _____________ ____________ Name & Signature of SP PowerGrid officer NRIC No. Date SP PowerGrid Ltd As agent for and on behalf of SP PowerAssets Ltd I acknowledge that the supply line has been energised on the date and time as indicated above. _______________________________________ ________________ ____________ Name & Signature of LEW requesting for Licence No. Date energisation of supply line

I acknowledge that the supply line has been energised on the date and time as indicated above and confirm that I will be responsible for the operation of this electrical installation hereafter. _______________________________________ ________________ ____________ Name & Signature of LEW responsible for the Licence No. Date operation of the electrical installation*

I acknowledge that the supply line has been energised on the date and time as indicated above. ______________________________________ ________________ _____________ Name & Signature of Applicant NRIC / Passport No. Date or his representative *Not Applicable for an electrical installation that is exempted from licensing Original Copy - SP PowerGrid Ltd Pink Copy - LEW (Requesting) Yellow Copy - LEW (Operation) Green Copy - Applicant Blue Copy - MSSL White (last) Copy - File REF: E(EI) REG 5(4)

Page 115: How to Apply

■ Appendix 39

114

REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITY The customer applying for distributed generation facility is required to obtain SPPA’s approval and shall comply with

the technical, safety & operational and commercial & legal requirements as follows:

A) Technical Requirements

1 real and reactive power/voltage output and voltage and frequency response times must be within agreed limits

2 not contribute to the voltage unbalance, voltage fluctuation and harmonic content specified for the transmission network

3 ensure that there is no interference to SPPA’s Equipment or any other directly or indirectly connected consumers 4 ensure adequate partitioning of the exempt generation facility equipment from SPPA’s equipment 5 where required by SPPA, install harmonic filtering circuit at the incoming switchboard of the service connection in

compliance with the harmonics standard 6 LEW is required to submit fault level reports to SPPG’s Distribution Planning Section. The distributed generation

system shall limit their fault level contribution to the grid to a level acceptable to SPPG.

B) Safety & Operational Requirements

1 provide an interlocking and inter-tripping facility for the service connection that meets SPPA’s requirement

2 fit exempt generation facility with reverse power relays to prevent export of power to the transmission system. However, this requirement will not apply in the event that EMA / EMC had given approval for the export of power to the transmission system

3 not operate the exempt generation facility in islanding mode i.e., the embedded generator must isolate itself from

the distribution network when there is a fault/tripping on the latter or the customer’s installation (non-islanding protection)

4 provide a synchronizing facility at the incoming switchboard of its service connection and ensure that any output is always synchronized with the distribution network

C) Commercial & Legal Requirement The customer with an exempt generation facility shall 1 pay standby use of system charges or any other charges approved by the EMA 2 indemnify SPPA

i) for all losses and liabilities arising from any loss of synchronisation caused by any tripping or re-closing of any breakers in the transmission system and the exempt generation facility connected in parallel to the transmission system ; and

ii) against losses to third parties caused by impedance, disruption degradation interference or failure of transmission services to third parties caused by the system or works carried out on the transmission system

3 certify to SPPG that the exempt generation facility meet all conditions of the relevant legislation, regulation

(including installation, fire and safety, noise and environment); 4 conduct regular site tests and to notify the SPPG of the results 5 allow SPPG to conduct inspection of, disconnect and enforce conditions in respect of the service connection if the

exempt generation facility fails to meet any of the above requirements 6 resolve, at its own expense all third party complaints concerning the exempt generation facility (e.g.complaints

due to noise, or aesthetic reasons); and

7 use the service connection to operate in parallel with its exempt generation facility at its own risk

Page 116: How to Apply

■ Appendix 39.1

TERMS AND CONDITIONS FOR CAPPED CAPACITY SCHEME (CCS)

1 The Consumer shall at its own expense, install and maintain, in accordance with such

requirements that Transmission Licensee may from time to time stipulate:

1.1 at the Consumer’s incoming switchboard (or at such other point that Transmission Licensee may specify), a Load Limiting Device (“LLD”), which will automatically disconnect the Service Connection from the Transmission System in the event (“Event”) that the Consumer’s intake from the Transmission System exceeds one hundred twenty percent (120%) of the Contracted Capacity (“CC”) continuously for more than ten (10) seconds.

1.2 at the HT metering kiosk (or at such other point that Transmission Licensee

may specify), a Load Monitoring Device (“LMD”) including all control cables for the LMD as well as metering accessories and telephone line(s) for Transmission Licensee to monitor the Consumer’s intake from the Transmission System.

2 Upon installation, all title, rights and interest in the LMD shall vest immediately in

Transmission Licensee. However, the Consumer shall ensure that: 2.1 The LMD shall at all times be set and adjusted to the satisfaction of

Transmission Licensee; 2.2 No modification, reset or adjustment to the LMD is carried out without first

obtaining Transmission Licensee’s approval; 2.3 The testing, commissioning and subsequent annual testing of the LMD as well

as any modification, reset or adjustment to the LMD approved by the Transmission Licensee is to be carried out by a Licensed Electrical Worker and in the presence of a representative from Transmission Licensee;

2.4 The LMD is re-tested and re-commissioned as and when required at the

discretion of Transmission Licensee; 2.5 All test results are submitted to Transmission Licensee at such address as

notified by Transmission Licensee within two (2) weeks of the testing; 2.6 The telephone line(s) set up for Transmission Licensee’s remote data

downloading from LMD shall be operational at all times; 2.7 Transmission Licensee officers are granted unrestricted access to substation

premises for on-site inspection and retrieval of data from the LMD; and 2.8 The LMD is covered under a valid maintenance contract providing for relevant

technical support and replacement parts to keep the LMD in good operational condition at all times.

3 The Transmission Licensee shall witness the testing of LMD at its own expense. All

other expenses in connection with the testing of the LMD shall be borne by the Consumer.

i

Page 117: How to Apply

4 The conversion to CCS shall be effective upon the following (the “CCS Effective Date”):

4.1 the Consumer’s compliance with Item 1 above; and 4.2 the successful commissioning of the LLD and LMD.

5 In the event that the LLD fails to cap the power demand (kW) drawn from the network

in the circumstances as described in Item 1.1, the Uncontracted Standby Capacity Charge (“USCC”) shall apply and be payable.

6 USCC is a monthly charge payable in any month for the Uncontracted Standby

Capacity utilised. The Uncontracted Standby Capacity is the peak power demand in kW drawn from the network exceeding 120% of CC, recorded from the time the power drawn exceeds 120% of CC to the time the power drawn falls below 120% of CC. This peak power demand is recorded by the LMD at single second intervals.

7 The rate of USCC shall be the prevailing rate stated in the Transmission Service Rate

Schedule. SPPA reserves the right to review the USCC rate applicable to the Consumer from time to time, such review to be subject to EMA’s approval. The current rate for USCC is 5 times CC Charge for demand drawn exceeding 120% of CC.

8 For each Event, as defined in Item 1.1 above, the Consumer is required to submit, within two weeks of the occurrence of the Event, a report to the Transmission Licensee on the causes of the occurrence. The report shall also include the Consumer’s follow-up actions to prevent similar Events from occurring.

9 The Consumer shall ensure that multiple sources of Transmission System are not

connected in parallel at any time, and that any switching between circuits is undertaken on “black changeover” or “break before make” basis.

10 Transmission Licensee reserves the right to withdraw the CCS from the Consumer if

the Consumer fails to comply with the terms and conditions applicable to the scheme, and to offer only the Summation Scheme (as outlined in Clause 12.14(a) of the CCA) to such Consumer.

11 In the event of a change in scheme for whatever reason, the Service Connection may

be disconnected temporarily to facilitate the installation of energy meters and other equipment for the purposes of the implementation of the Summation Scheme.

ii

Page 118: How to Apply

■ Appendix 39.2

TERMS AND CONDITIONS FOR EXTENDED CAPPED CAPACITY SCHEME (ECCS)

1 The Consumer shall at its own expense, install and maintain, in accordance with such

requirements that Transmission Licensee may from time to time stipulate:

1.1 at the Consumer’s incoming switchboard (or at such other point that Transmission Licensee may specify), a Load Limiting Device (“LLD”), which will automatically disconnect the Service Connection from the Transmission System on the happening of any one of the following events (“Event”):

(a) when the Consumer’s intake from the Transmission System exceeds

one hundred twenty percent (120%) of the Contracted Capacity (“CC”) continuously for more than one hundred (100) seconds; or

(b) when the Consumer’s intake exceeds two hundred percent (200%) of

the CC continuously for more than ten (10) seconds. 1.2 at the HT metering kiosk (or at such other point that Transmission Licensee

may specify), a Load Monitoring Device (“LMD”) including all control cables for the LMD as well as metering accessories and telephone line(s) for Transmission Licensee to monitor the Consumer’s intake from the Transmission System.

2 Upon installation, all title, rights and interest in the LMD shall vest immediately in

Transmission Licensee. However, the Consumer shall ensure that: 2.1 The LMD shall at all times be set and adjusted to the satisfaction of

Transmission Licensee; 2.2 No modification, reset or adjustment to the LMD is carried out without first

obtaining Transmission Licensee’s approval; 2.3 The testing, commissioning and subsequent annual testing of the LMD as well

as any modification, reset or adjustment to the LMD approved by the Transmission Licensee is to be carried out by a Licensed Electrical Worker and in the presence of a representative from Transmission Licensee;

2.4 The LMD is re-tested and re-commissioned as and when required at the

discretion of Transmission Licensee; 2.5 All test results are submitted to Transmission Licensee at such address as

notified by Transmission Licensee within two (2) weeks of the testing; 2.6 The telephone line(s) set up for Transmission Licensee’s remote data

downloading from LMD shall be operational at all times; 2.7 Transmission Licensee officers are granted unrestricted access to substation

premises for on-site inspection and retrieval of data from the LMD; and 2.8 The LMD is covered under a valid maintenance contract providing for relevant

technical support and replacement parts to keep the LMD in good operational condition at all times.

3 The Transmission Licensee shall witness the testing of LMD at its own expense. All

iii

Page 119: How to Apply

other expenses in connection with the testing of the LMD shall be borne by the Consumer.

4 The conversion to ECCS shall be effective upon the following (the “ECCS Effective

Date”):

4.1 the Consumer’s compliance with Item 1 above; and 4.2 the successful commissioning of the LLD and LMD.

5 In the event that the LLD fails to cap the power demand (kW) drawn from the network

in the circumstances as described in Item 1.1, the Uncontracted Standby Capacity Charge (“USCC”) shall apply and be payable. The USCC is a monthly charge payable in any month for the Uncontracted Standby Capacity utilised.

6 For the purposes of this ECCS, the term “Uncontracted Standby Capacity” shall mean

the capacity by which the demand in kW drawn from the network: 6.1 exceeds 120% up to a level of 200% of the CC at the metered intake supply

point for a duration of more than 100 seconds continuously; or 6.2 exceeds 200% of the CC at the metered intake supply point for a duration of

more than 10 seconds continuously,

in both cases, arising from a failure by the Consumer to cap the demand in kW drawn from the Transmission System. The definition of “Uncontracted Standby Capacity” as stated in the CCA is hereby superceded.

7 The rate of USCC shall be the prevailing rate stated in the Transmission Service Rate

Schedule. SPPA reserves the right to review the USCC rate applicable to the Consumer from time to time, such review to be subject to EMA’s approval. The current rate for USCC is:

7.1 5 times CC Charge for demand drawn exceeding 120% up to 200% of CC; and 7.2 12 times CC Charge for demand exceeding 200% of CC.

8 For each Event, as defined in Item 1.1 above, the Consumer is required to submit,

within two weeks of the occurrence of the Event, a report to the Transmission Licensee on the causes of the occurrence. The report shall also include the Consumer’s follow-up actions to prevent similar Events from occurring.

9 The Consumer shall ensure that multiple sources of Transmission System are not

connected in parallel at any time, and that any switching between circuits is undertaken on “black changeover” or “break before make” basis.

10 Transmission Licensee reserves the right to withdraw the ECCS from the Consumer if

the Consumer fails to comply with the terms and conditions applicable to the scheme, and to offer only the Summation Scheme (as outlined in Clause 12.14(a) of the CCA) to such Consumer.

11 The Consumer acknowledges and accepts that in the event of a change in scheme for

whatever reason, the Service Connection may be disconnected temporarily to facilitate the installation of energy meters and other equipment for the purposes of the implementation of the Summation Scheme.

iv

Page 120: How to Apply

■ Appendix 40

115

LIST OF STANDARDS IEC Standards

IEC 60044-1 (1996-12) Ed. 1.0 Instrument transformers - Part 1 : Current transformers IEC 60044-1-am1 (2000-07) Ed. 1.0 Amendment 1 IEC 60044-2 (2000-11) Consol. Ed. 1.1 (incl. am1) Instrument transformers - Part 2 : Inductive

voltage transformers IEC 60044-6 (1992-03) Ed. 1.0 Instrument transformers - Part 6 : Requirements for protective

current transformers for transient performance IEC 60060-1 (1989-11) Ed. 2.0 High-voltage test techniques - Part 1 : General definitions and

test requirements IEC 60060-2 (1994-11) Ed. 2.0 High-voltage test techniques - Part 2 : Measuring systems IEC 60060-2-am1 (1996-03) Ed. 2.0 Amendment No.2 to IEC 60-2 IEC 60076-1 (2000-04) Consol. Ed. 2.1 (incl. am1) Power transformers - Part 1 : General IEC 60076-2 (1993-04) Ed. 2.0 Power transformers - Part 2 : Temperature rise IEC 60076-3 (2000-03) Ed. 2.0 Power transformers - Part 3 : Insulation levels, dielectric tests

and external clearances in air IEC 60076-5 (2000-07) Ed. 2.0 Power transformers - Part 5 : Ability to withstand short circuit IEC 60076-8 (1997-11) Ed. 1.0 Power transformers - Part 8 : Application guide IEC 60076-10 (2001-05) Ed. 1.0 Power transformers - Part 10 : Determination of sound levels IEC 60099-4 (2001-12) Consol. Ed. 1.2 (incl. am1 + am2) Surge arresters - Part 4 : Metal-oxide

surge arresters without gaps for a.c. systems IEC 60137 (1995-12) Ed. 4.0 Insulating bushings for alternating voltages above 1000V IEC 60141-1 (1993-09) Ed. 3.0 Tests on oil-filled and gas-pressure cables and their accessories

– Part 1 : Oil-filled, paper or polypropylene paper laminate insulated, metal-sheathed cables and accessories for alternating voltages up to and including 500kV

IEC 60141-1-am1 (1995-02) Ed. 3.0 Amendment No.1 IEC 60141-1-am2 (1998-08) Ed. 3.0 Amendment No.2 IEC 60228 (1978-01) Ed. 2.0 Conductors of insulated cables IEC 60228-am1 (1993-01) Ed. 2.0 Amendment No.1 IEC 60230 (1966-01) Ed. 1.0 Impulse tests on cables and their accessories IEC 60255-3 (1989-06) Ed. 2.0 Electrical relays – Part 3: Single input energizing quantity

measuring relays with dependent or independent time IEC 60255-5 (2000-12) Ed. 2.0 Electrical relays – Part 5: Insulation coordination for measuring

relays and protection equipment – Requirements and tests IEC 60255-6 (1988-12) Ed. 2.0 Electrical relays – Part 6: Measuring relays and protection

equipment IEC 60255-8 (1990-10) Ed. 2.0 Electrical relays – Part 8: Thermal electrical relays IEC 60255-12 (1980-01) Ed. 1.0 Electrical relays – Part 12: Directional relays and power relays

with two input energizing quantities IEC 60255-13 (1980-01) Ed. 1.0 Electrical relays – Part 13: Biased (percentage) differential

relays IEC 60255-14 (1981-01) Ed. 1.0 Electrical relays – Part 14: Endurance tests for electrical relay

contacts – Preferred values for contact loads IEC 60255-16 (1982-01) Ed. 1.0 Electrical relays – Part 16: Impedance measuring relays IEC 60255-19 (1983-01) Ed. 1.0 Electrical relays – Part 19: Sectional specification:

Electromechanical all-or-nothing relays of assessed quality IEC 60255-23 (1994-10) Ed. 1.0 Electrical relays – Part 23: Contact performance IEC 60255-24 (2001-05) Ed. 1.0 Electrical relays – Part 24: Common format for transient data

exchange (COMTRADE) for power systems IEC 60273 (1990-03) Ed. 3.0 Characteristics of indoor and outdoor post insulators for

systems with nominal voltages greater than 1000V

Page 121: How to Apply

■ Appendix 40

116

LIST OF STANDARDS

IEC Standards continued IEC 60186 Voltage Transformers IEC 60287-1-1 (2001-11) Consol. Ed. 1.2 (incl. am1 + am2) Electric cables - Calculation of the

current rating – Part 1-1: Current rating equations (100% load factor) and calculation of losses – General

IEC 60287-1-2 (1993-12) Ed. 1.0 Electric cables - Calculation of the current rating – Part 1: Current rating equations (100% load factor) and calculations of losses – Section 2: Sheath eddy current loss factors for two circuits in flat formation

IEC 60287-2-1 (2001-11) Consol. Ed. 1.0 (incl. am1) Electric cables - Calculation of the current rating – Part 2-1: Thermal resistance – Calculation of the thermal resistance

IEC 60287-2-2 (1995-05) Ed. 1.0 Electric cables - Calculation of the current rating – Part 2: Thermal resistance – Section 2: A method for calculating reduction factors for groups of cables in free air, protected from solar radiation

IEC 60287-3-1 (1999-05) Consol. Ed. 1.1 (incl. am1) Electric cables - Calculation of the current rating – Part 3-1: Sections on operating conditions – Reference operating conditions and selection of cable type

IEC 60287-3-2 (1995-07) Ed. 1.0 Electric cables - Calculation of the current rating – Part 3: Sections on operating conditions – Section 2: Economic optimization of power cable size

IEC 60287-3-2-am1 (1996-10) Ed. 1.0 Amendment No.1 to IEC 287-3-2 IEC 60289 (1988-05) Ed. 2.0 Reactors IEC 60298 (1990-12) Ed. 3.0 A.C. metal-enclosed switchgear and controlgear for rated

voltages above 1kV and up to and including 52kV IEC 60332-1 (1993-04) Ed. 3.0 Tests on electric cables under fire conditions - Part 1 : Test on a

single vertical insulated wire or cable IEC 60354 (1991-10) Ed. 2.0 Loading guide for oil-immersed power transformers IEC 60376 (1971-01) Ed. 1.0 Specification and acceptance of new sulphur hexafluoride IEC 60502-1 (1998-11) Consol. Ed. 1.1 (incl. am1) Power cables with extruded insulation and

their accessories for rated voltages from 1kV(Um = 1,2kV) up to 30kV (Um = 36kV) - Part 1 : Cables for rated voltages of 1kV (Um = 1,2kV) and 3kV (Um = 3,6kV)

IEC 60517 (1990-10) Ed. 3.0 Gas-insulated metal-enclosed switchgear for rated voltages of 72.5kV and above

IEC 60517-am1 (1994-11) Ed. 3.0 Amendment No.1 IEC 60521 (1988-03) Ed. 2.0 Class 0.5, 1 and 2 alternating-current watthour meters IEC 60529 (2001-02) Consol. Ed. 2.1 (incl. am1) Degrees of protection provided by

enclosures (IP Code) IEC 60651 (2001-10) Consol. Ed. 1.2 (incl. am1 + am2) Sound level meters IEC 60660 (1999-10) Ed. 2.0 Insulators – Tests on indoor post insulators of organic material

for systems with nominal voltages greater than 1000V up to but not including 300kV

IEC 60687 (1992-06) Ed. 2.0 Alternating current static watt-hour meters for active energy (classes 0,2 S and 0,5 S)

IEC 60694 (2001-05) Consol. Ed. 2.1 (incl. am1) Common specifications for high-voltage switchgear and controlgear standards

IEC 60722 (1982-01) Ed. 1.0 Guide to the lightning impulse and switching impulse testing of power transformers and reactors

IEC 60811-1-1 (2001-07) Consol. Ed. 2.1 (incl. am1) Common test methods for insulating and sheathing materials of electric cables and optical cables - Part 1-1 : Methods for general application – Measurement of thickness and overall dimensions - Tests for determining the mechanical properties

IEC 60840 (1999-02) Ed. 2.0 Power cables with extruded insulation and their accessories for rated voltages above 30kV (Um = 36kV) up to 150kV (Um = 170kV) - Test methods and requirements

Page 122: How to Apply

■ Appendix 40

117

LIST OF STANDARDS IEC Standards

IEC 60859 (1999-07) Ed. 2.0 Cable connections for gas-insulated metal-enclosed switchgear for rated voltages of 72.5kV and above - Fluid-filled and extruded insulation cables - Fluid-filled and dry type cable-terminations

IEC 60885-1 (1987-03) Ed. 1.0 Electrical test methods for electric cables. Part 1: Electrical tests for cables, cords and wires for voltages up to and including 450-750V

IEC 60885-2 (1987-03) Ed. 1.0 Electrical test methods for electric cables. Part 2: Partial discharge tests

IEC 60885-3 (1988-07) Ed. 1.0 Electrical test methods for electric cables. Part 3: Tests methods for partial discharge measurements on lengths of extruded power cables

IEC 60947-1 (2001-12) Consol. Ed. 3.2 (incl. am1 + am2) Low-voltage switchgear and controlgear - Part 1 : General rules

IEC 60947-7-1 (1999-08) Consol. Ed. 1.1 (incl. am1) Low-voltage switchgear and controlgear – Part 7 : Ancillary equipment - Section 1 : Terminal blocks for copper conductors

IEC 61000-4-2 (2001-04) Consol. Ed. 1.2 (incl. am1 + am2) Electromagnetic compatibility (EMC) -Part 4-2 : Testing and measurement techniques – Electrostatic discharge immunity test

IEC 61036 (2000-09) Consol. Ed. 2.1 (incl. am1) Alternating current static watt-hour meters for active energy (classes 1 and 2)

IEC 62098 (2000-11) Ed. 1.0 Evaluation methods for microprocessor based instruments IEC 62271-100 (2001-05) Ed. 1.0 High-voltage switchgear and controlgear - Part 100 : High-

voltage alternating-current circuit-breakers IEC 62271-102 (2001-12) Ed. 1.0 High-voltage switchgear and controlgear - Part 102 : High-

voltage alternating-current disconnectors and earthing switches IEC 60068 (1988-06) Environmental testing. Part 1: General and guidance IEC 60068-1-am1 (1992-04) Amendment No. 1 IEC 60068-2-3 (1969-01) Environmental testing - Part 2: Tests. Tests Ca: Damp heat, steady

state. IEC 60068-2-11 (1981-01) Environmental testing - Part 2: Tests. Tests Ka: Salt Mist. IEC 60068-2-11 (1999-12) Corrigendum 1. IEC 60068-2-30 (1980-01) Environmental testing - Part 2: Tests. Tests Db and guidance: Damp

heat, cyclic (12 + 12-hour cycle) IEC 60068-2-30-am1 (1985-08) Amendment No. 1 IEC 60068-2-67 (1995-12) Environmental testing – Part 2: Tests – Test Cy: Damp heat, steady

state, accelerated test primarily intended for components. IEC 60068-3-4 (2001-08) Environmental testing – Part 3-4: Supporting documentation and

guidance – Damp heat tests IEC 60068-4 (1987-09) Environmental testing. Part 4: Information for specification writers –

Test Summaries IEC 60068-4-am1 (1992-02) Amendment No. 1 IEC 60068-4-am2 (1994-03) Amendment No. 2 IEC 61000-1-1 (1992-05) Electromagnetic compatibility (EMC) – Part 1: General – Section 1:

Application and interpretation of fundamental definitions and terms. IEC 61000-1-2 (2001-06) Electromagnetic compatibility (EMC) – Part 1-2: General – Methodology

for the achievement of the functional safety of electrical and electronic equipment with regard to electromagnetic phenomena.

IEC 62067 (2001-10) Power cables with extruded insulation and their accessories for rated voltages above 150kV (Um = 170kV) up to 500kV (Um = 550kV) – Test methods and requirements

Page 123: How to Apply

■ Appendix 40

118

LIST OF STANDARDS

British Standards BS EN 60051-1 (1999) [IEC 60051-1(1997)]

Direct acting indicating analogue electrical measuring instruments and their accessories. Definitions and general requirements common for all parts.

BS 89-2 (1990) [IEC 60051-2 (1984)]

Direct acting indicating analogue electrical measuring instruments and their accessories. Specification for special requirements for ammeters and voltmeters

BS 89-3 (1990) [IEC 60051-3 (1984)]

Direct acting indicating analogue electrical measuring instruments and their accessories. Specification for special requirements for wattmeters and varmeters.

BS 89-4 (1990) [IEC 60051-4 (1984)]

Direct acting indicating analogue electrical measuring instruments and their accessories. Specification for special requirements for frequency meters.

BS 89-5 (1990) [IEC 60051-5 (1985)]

Direct acting indicating analogue electrical measuring instruments and their accessories. Specification for special requirements for phase meters, power factor meters and synchroscopes.

BS 89-9 (1990) [IEC 60051-9 (1988)]

Direct acting indicating analogue electrical measuring instruments and their accessories. Recommended test methods.

BS 148 (1998) Specification for unused and reclaimed mineral insulating oils for transformers and switchgear.

BS 159 (1992) Specification for high-voltage busbars and busbar connections. BS EN 60076-1 (1997)

Power transformers. General

BS 171-5 (1978) [IEC 60076-5 (1976)]

Power transformers. Specification for ability to withstand short circuit.

BS EN 60060-2 (1995)

High-voltage testing techniques. Measuring systems

BS 3938 (1973) Specification for current transformers BS 3941 (1975) Specification for voltage transformers BS EN 60214 (1998) On-load tap changers BS 5207(1975) Specification for sulphur hexafluoride for electrical equipment BS 5209 (1975) Code of practice for the testing of sulphur hexafluoride taken from electrical

equipment BS 5311(1996) High-voltage alternating-current circuit-breakers BS EN 60947-4-1 (1992) Specification for low-voltage switchgear and controlgear. Contactors and motor-

starters. Electromechanical contactors and motor-starters BS 5685-1(1979) Electricity meters. Specification for class 0.5, 1 and 2 single-phase and

polyphase, single rate and multi-rate watt-hour meters. BS 5685-2 (1986) Electricity meters. Specification for single-phase coin operated prepayment flat

rate and two-part tariff watt-hour meters of class 2 and fixed charge collectors of class 2.

BS 5685-3 (1986) Electricity meters. Specification for meters having class 1 electro-mechanical maximum demand indicators.

BS 5685-4 (1986) Electricity meters. Specification for class 3 var-hour meters. BS 5685-5 (1987) Electricity meters. Specification for input and output switching or logic

arrangements for multi-rate registers for electricity meters. BS 5685-8 (1991) Electricity meters. Specification for impulse operated multiple registers for use

with induction electricity meters. BS 5730 (2001) Monitoring and maintenance guide for mineral insulating oils in electrical

equipment. BS 5992-1(1980) [IEC 60255-0-20 (1974)]

Electrical relays. Specification for contact performance of electrical relays

BS 6231(1998) Specification for PVC-insulated cables for switchgear and controlgear wiring. BS EN 60044-2 (1999) [IEC 60044-2 (1997)]

Instrument transformers. Inductive voltage transformers

Page 124: How to Apply

■ Appendix 40

119

LIST OF STANDARDS Singapore Standards

SS 318 (1987) Current transformers for measurement and protection SS 404 (1997) Power transformers Part 1: General SS 404 (1997) Power transformers Part 2: Temperature rise SS 404 (2001) Power transformers Part 3: Insulation levels and dielectric tests and external

clearances in air SS 404 (2001) Power transformers Part 5: Ability to withstand short circuit SS 404 (2000) Power transformers Part 8: Application guide SS 443 (1998) Part 1: Power cables with extruded insulation and their accessories for rated

voltages from 1kV (Um = 1.2kV) up to 30kV (Um = 36kV) – Cables for rated voltages of 1kV (Um = 1.2kV) and 3kV (Um = 3.6kV)

SS ISO 9000 (2000) Quality management systems – Fundamentals and vocabulary SS ISO 9001 (2000) Quality management systems – Requirements SS ISO 9004 (2000) Quality management systems – Guidelines for performance improvements CP 5 (1998) Code of practice for electrical installations CP 10 (1993) Code of practice for the installation and servicing of electrical fire alarm systemsCP 16 (1991) Code of practice for earthing CP 19 (2000) Code of practice for the installation and maintenance of emergency lighting and

power supply systems in buildings CP 31 (1996) Code of practice for installation, operation, maintenance, performance and

constructional requirements of mains failure standby generating systems CP 33 (1996) Code of practice for lightning protection

Other Standards

IEEE C37.09 ANSI C37.09 (1999)

Test procedure for A.C high-voltage circuit breakers rated on a symmetrical current basis

IEEE 32 (1972)

Neutral grounding devices, req term and test procedures

ISO 7-2 (2000) Pipe threads where pressure-tight joints are made on the threads – Part 2: Verification by means of limit gauges

AEIC CS2 (1997) Impregnated paper and laminated paper polypropylyne insulated cable high-pressure-pipe type

AEIC CS4 (1993) Impregnated-paper-insulated-low and medium pressure self-contained liquid filled cable

ASTM B187 (2000) Standard specification for copper bar, bus-bar, rod and shapes ASTM B3 (2001) Standard specification for soft or annealed copper wire

Page 125: How to Apply

■ Appendix 41 FORM CS/12 To: SP Services Ltd Fax No: 6823 8289 APPLICATION FOR ELECTRICAL INSTALLATION INSPECTION (UP TO 45KVA)

I/We hereby request an appointment to inspect the electrical installation at the premises with SP Services Account No :

(Please tick or fill in the appropriate boxes)

An application for electricity supply service has been submitted earlier and approved. SP Services Application Reference No is:

OR

This is a new application. Form CS/5, together with Certificate of Compliance (COC), is enclosed. (Please note that CS/3 form is required for supply connection from Landlord’s Electrical Installation).

Type of Single- Three No new meter Meter Required: phase phase required Removal of old meter(s) : Yes No *Preferred Dates : 1 ___________ Morning Afternoon (in order of preference) 2 ___________ Morning Afternoon 3 ___________ Morning Afternoon Remarks: ___________________________________________________________________ (*Your preferred dates shall be from the third working day onwards. If you do not give us your preferred date(s), we shall provide you with the earliest available appointment date & time. ) Signature : Licensed Electrical Worker : Telephone/ Handphone No : FAX NO : Pager No : _________________________________________________________________________________

Please note the following:

1. For applications received before 3pm, it will be processed on the same day. For applications received after 3pm, it will be processed on the following business day.

2. The granting of an appointment on the preferred date is at SP Services discretion and

subject to availability.

3. It is important that you provide us with your contact number and fax number.

4. All applications are to be accompanied by Certificate of Compliance (COC). 09/06/2005

120

Page 126: How to Apply

■ Appendix 42

APPLICATION FOR CONTESTABILITY STATUS

Existing ElectricityAccount No :(if applicable)Name of Consumer

(company):(“the Consumer”)

Official PremisesAddress wheresupply is required:

(“the Premises”)

Mailing Address:(if different fromthe Premises) Fax No:

Contact Person: Contact Tel: E-mail:

1.

2.

3.

4.

5.

6.

SIGNATURE:

DESIGNATION:NAME:

COMPANY STAMP:

DATE:

I wish to apply to be a contestable consumer with respect to the premises stated above (“the Premises”)

In accordance with the Electricity (Contestable Consumers) Regulations 2003 or such further amendments thereto, Iconfirm that “the Premises” is a non-residential premises.

The phone number of the phone line connected to my meters for the purpose of remote meter reading is _____________.

I agree that my application for contestability is subject to my compliance with paragraph 3 above and that SP Servicesshall not be liable for any inconvenience, loss, expense and damage that may be incurred or suffered as a result of adelay or postponement of my compliance or non-compliance of paragraph 3 provided always that such delay,postponement or non-compliance is not caused by SP Services or is within its reasonable control.

If my application as a contestable consumer is approved, I agree to open an account with you for Market SupportServices and to pay a Security Deposit for an amount declared and in the form approved by you within the time periodstipulated by you.

I agree to be bound by the Conditions of Service (a copy which will be given to me), which shall take effect when I openan account with you for Market Support Services after being classified as a contestable consumer.

* Requested Date of contestability:

* Note : (a) You shall be classified as a contestable consumer from such date as may be notified by SP Services Ltd and approved by the Authority.(b) This form should reach SP Services Ltd at least 12 business days before the Requested Date of contestability

CompanyRegistration No:

SP Services Ltd111 Somerset Road #06-05 Singapore Power Building Singapore 238164Tel : 1800- 2338000 Website: www.mssl.com.sg Email: [email protected] Fax: 6820 6800 Updated 15 April 2005

121

Page 127: How to Apply

■ Appendix 43

APPLICATION TO OPEN A MARKET SUPPORT SERVICES ACCOUNT

(For Official Use)MSSL A/C No.

Name of Consumer(company):

(“the Consumer”)

CompanyRegistration No:

Official PremisesAddress wheresupply is required :

(“the Premises”)

Fax No:

Contact Person: Contact Tel: E-mail:

Tick where appropriate

I confirm that I am a contestable consumer and have been notified by Energy Market Authority/SP Services through theContestability Notice dated ______________. (Please attach the Contestability Notice).

I confirm that I intend to move-in/take-over a contestable premises currently taking high tension supply.

Contract Capacity : _________________

Contract Expiry date : _________________

I agree that my move-in/take-over of the premises is subject to the corresponding move-out of the existing consumer ofthe premises and I agree that SP Services shall not be liable for any inconvenience, loss, expense and damage that maybe incurred or suffered as a result of a delay, postponement or cancellation of such move-out by the existing consumer,provided always that such delay, postponement or cancellation is not caused by SP Services or is within its reasonablecontrol.

I agree to pay a Security Deposit for an amount declared and in the form approved by you within the time period stipulated byyou or before the supply at the premises has been turned on, whichever is earlier.

I wish to apply to open an account for Market Support Services (“MSS”) for the above premises (“the Premises”).

I agree to be bound by the Conditions of Service (a copy of which has been given to me) which shall take effect when thisapplication is approved.

I will make arrangement to turn on the supply of electricity to the electrical installation of my premises on ________ (date),and I will send a confirmation to notify you of any changes.

I agree that I will be billed from 00:00hrs on the date of move in/take over and up to 23:59hrs on the date I move out of thePremises.

SIGNATURE:

1.

2.

3.

5.

4.

6.

DESIGNATION:

COMPANY STAMP:

DATE:

Mailing Address:(if different fromthe Premises)

Please specify Retailer Name : Billing Option: * Split / Consolidated (delete appropriately)

* Requested Date of Account Activation:(must be at least 12 business days from date of application)

NAME:

I intend to purchase my electricity supply from :

An Electricity Retailer

Indirectly from the wholesale electricity market through SP Services Ltd

Directly from the wholesale electricity market

SP Services Ltd111 Somerset Road #06-05 Singapore Power Building Singapore 238164Tel : 1800- 2338000 Website: www.mssl.com.sg Email: [email protected] Fax: 6820 6800 Updated 15 April 2005

122

Page 128: How to Apply

■ Appendix 44 COMPLETION CERTIFICATE FOR MODIFICATION

OF SMALL ELECTRICAL INSTALLATION To: SP Services Ltd 111 Somerset Rd #06-05 Singapore Power Building Singapore 238164 MODIFICATION TO ELECTRICAL INSTALLATION AT ____________________________ __________________________________________________________________________________________ (Address of installation) MSSL Account No. : ____________________________________________________________ in the name of : ______________________________________________________________ I, ______________________________ certify that the modification to the above-mentioned electrical installation has been inspected and tested by me in accordance with Singapore Standard CP5: Code of Practice for Electrical Installations, and that to the best of my knowledge and belief the modification summarized below complies with the said Singapore Standard CP5 and the relevant Regulations. Description Quantity Lighting points 13 Amp socket outlets 15 Amp socket outlets Heater Isolator Others (please specify) The said modification has been connected to the supply of electricity on ____________. The existing supply line is adequate for the after diversity maximum demand of the above-mentioned electrical installation.

2. I append below the result of my inspection and test: Incoming supply : SP PowerAssets Network / Third party electrical installation

MCB / Cutout size : Amp Revenue meter no : RCCB rating : Amp/30mA sensitivity Phase to Phase insulation : Mohm Phase to Earth insulation : Mohm Neutral to Earth insulation : Mohm RCCB test satisfactory : Yes/No Polarity check satisfactory : Yes/No Earth fault loop impedance : ohm Date of inspection/test : _________________ ________________________________________ ____________ ____________ Name & signature of Licensed Electrical Worker Licence No. Date cc Consumer

REF: E(EI)Reg7(1)

201003

123

Page 129: How to Apply

■ Appendix 45 FORM E CERTIFICATE OF FITNESS OF RESIDENTIAL UNIT

Application No. ____________________ To: Deputy Director, Installation Branch SP Services Ltd 111 Somerset Road #06-01 Singapore Power Building

Singapore 238164 PROJECT: AT APARTMENT BLOCK No. STREET NAME: DATE OF TEST: POSTAL DISTRICT:

Type/Total No. of Units / ( units) / ( units)

MCB Rating

MCB Type (Before & after Revenue Meter)

Service Cable Size

RCCB Rating / Sensitivity

Cooker / Oven Point

Water Heater Point

15A Socket Outlet

13A Socket Outlet

Fan Point

Lamp Point

20A isolator SPN

20A isolator TPN

30A isolator SPN

30A isolator TPN

Others

Unit Nos.

I hereby declare that I have supervised the installation, inspected and tested the electrical installation of the residential units(s) in accordance with the relevant Regulations and Code of Practice. ________________________________________ Signature/Name/Licence No. of LEW responsible for electrical installation work*

I hereby certify that the electrical installation of theresidential unit(s) has been designed in accordance with the relevant Regulations and Code of Practice. _____________________________________________ Signature/Name/Licence No. of LEW responsible for design of electrical installation*

Oth

ers

Det

ails

of E

lect

rical

Inst

alla

tion

*The same LEW may perform both design and installation work for the electrical installation.

124