Top Banner
GHG Report for CSA Standards GHG CleanProjects ® Registry Multimodal transport on the Magdalena River by Impala Terminals Report Version 3, 23 August 2019 1.1. Relevance ............................................................................................................ 2 1.2. Completeness ...................................................................................................... 2 1.3. Consistency ......................................................................................................... 2 1.4. Accuracy ............................................................................................................. 2 1.5. Transparency ....................................................................................................... 3 1.6. Conservativeness................................................................................................. 3 2. Project Description ...................................................................................................... 3 2.1. Project title .......................................................................................................... 3 2.2. The project’s purpose(s) and objective(s) are: .................................................... 3 2.3. Expected lifetime of the project .......................................................................... 4 2.4. Type of greenhouse gas emission reduction or removal project ......................... 4 2.5. Legal land description of the project or the unique latitude and longitude ........ 4 2.6. Conditions prior to project initiation................................................................... 7 2.7. Description of how the project will achieve GHG emission reductions or removal enhancements .................................................................................................... 8 2.8. Project technologies, products, services and the expected level of activity ....... 8 2.9. Total GHG emission reductions and removal enhancements, stated in tonnes of CO2 e, likely to occur from the GHG project (GHG Assertion) ................................... 13 2.10. Identification of risks ........................................................................................ 14 2.11. Roles and Responsibilities ................................................................................ 14 2.12. Any information relevant for the eligibility of the GHG project under a GHG program and quantification of emission reductions ...................................................... 15 2.13. Summary environmental impact assessment .................................................... 21 2.14. Relevant outcomes from stakeholder consultations and mechanisms for on- going communication.................................................................................................... 22 2.15. Detailed chronological plan .............................................................................. 23 3. Selection and Justification of the Baseline Scenario ................................................. 24 4. Inventory of sources, sinks and Reservoirs (SSRs) for the project and baseline...... 27 5. Quantification and calculation of GHG emissions/removals .................................... 29 6. Monitoring the Data information management system and data controls ................. 34 7. Reporting and verification details.............................................................................. 47
59

GHG Report for CSA Standards GHG CleanProjects Registry · GHG Report Template for CSA Standards GHG CleanProjects® Registry Version 1.0 – September 2009 4 subject of regional

Feb 15, 2021

Download

Documents

dariahiddleston
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • GHG Report for CSA Standards GHG CleanProjects® Registry

    Multimodal transport on the Magdalena River by Impala Terminals

    Report Version 3, 23 August 2019

    1.1. Relevance ............................................................................................................ 2 1.2. Completeness ...................................................................................................... 2 1.3. Consistency ......................................................................................................... 2 1.4. Accuracy ............................................................................................................. 2 1.5. Transparency ....................................................................................................... 3 1.6. Conservativeness................................................................................................. 3

    2. Project Description ...................................................................................................... 3

    2.1. Project title .......................................................................................................... 3 2.2. The project’s purpose(s) and objective(s) are: .................................................... 3 2.3. Expected lifetime of the project .......................................................................... 4 2.4. Type of greenhouse gas emission reduction or removal project......................... 4 2.5. Legal land description of the project or the unique latitude and longitude ........ 4 2.6. Conditions prior to project initiation................................................................... 7 2.7. Description of how the project will achieve GHG emission reductions or removal enhancements .................................................................................................... 8 2.8. Project technologies, products, services and the expected level of activity ....... 8 2.9. Total GHG emission reductions and removal enhancements, stated in tonnes of CO2 e, likely to occur from the GHG project (GHG Assertion) ................................... 13 2.10. Identification of risks ........................................................................................ 14 2.11. Roles and Responsibilities ................................................................................ 14 2.12. Any information relevant for the eligibility of the GHG project under a GHG program and quantification of emission reductions ...................................................... 15 2.13. Summary environmental impact assessment .................................................... 21 2.14. Relevant outcomes from stakeholder consultations and mechanisms for on-going communication.................................................................................................... 22 2.15. Detailed chronological plan .............................................................................. 23

    3. Selection and Justification of the Baseline Scenario ................................................. 24 4. Inventory of sources, sinks and Reservoirs (SSRs) for the project and baseline ...... 27 5. Quantification and calculation of GHG emissions/removals .................................... 29 6. Monitoring the Data information management system and data controls ................. 34 7. Reporting and verification details .............................................................................. 47

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    2

    1.1. Relevance

    The selected methodology was the Clean Development Mechanism AM0090 - Modal

    shift in transportation of cargo from road transportation to water or rail transportation.

    Version 01.1.0, supplemented with the Clean Development Mechanism Tool03 – Tool to

    calculate project or leakage CO2 emissions from fossil fuel combustion. Version 03.0.

    and with the Clean Development Mechanism Tool05 – Baseline, Project and/or leakage

    emissions from electricity consumption and monitoring of electricity generation. Version

    03.0.

    These fit the type of project and are in line with the requirements of Colombian

    regulations. (See 2.12 Any information relevant for the eligibility of the GHG project

    under a GHG program and quantification of emission reductions). As for the

    applicability, see Table 4, Table 5 and Table 6.

    Similarly, some deviations to the methodology and tools were presented, they can be seen

    in more detail in section 7.3 Methodology deviations.

    The sources for this project were selected according to the methodology applied and

    deviations from it, and they are the CO2 emissions avoided by the decrease in fuel use for

    the transportation of liquid cargo from the production fields to the ocean port and vice

    versa. For further details, refer to section 4 Inventory of sources, sinks and Reservoirs

    (SSRs) for the project and baseline.

    1.2. Completeness

    This document quantifies the different sources controlled and affected by project

    activities. All sources of emissions identified by the methodology are considered and no

    further relevant sources were identified. For further details, refer to section 4 Inventory of

    sources, sinks and Reservoirs (SSRs) for the project and baseline.

    1.3. Consistency

    The baseline definition demonstrates consistency with the baseline guidelines for sectoral

    GHG mitigation projects in Resolution 1447 of 2018, Article 35. In addition, the

    calculations are shown to be in line with the CDM methodology for energy efficiency

    projects for cargo transport. It also demonstrated that the service level of the baseline is

    equivalent to the service level of the project scenario.

    1.4. Accuracy

    The measurement methods used to obtain information related to fuel consumption,

    transported cargo and distance traveled are traceable and reliable, reducing the

    propagation of uncertainty in the calculation. Country-specific fuel emission factors were

    applied, which also reduces uncertainty.

    However, some of the variables used are not measured, but are estimated, which

    increases the uncertainty of the data. This is offset by conservative assumptions that

    avoid overestimating reductions.

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    3

    1.5. Transparency

    An example calculation is provided in this report (See numeral 5.5). Further detail of the

    calculations for the years in which the project has been operated is reported in an Excel

    document available to verifiers, with the description of the sources of the emission

    factors, the project operational data and the formulas used. In addition, the assumptions

    applied are described.

    The information contained in this report is of public status.

    1.6. Conservativeness

    In the calculations of the baseline and the project scenario, data, default factors and

    assumptions are applied with a conservative attitude, for example, as to the performance

    of transport vehicles on complementary routes, information was collected from different

    sources in order to capture the variability associated with the different operating

    conditions and a performance assumption was applied so it would not lead to

    overestimating emission reduction.

    2. Project Description

    2.1. Project title

    Multimodal transport on the Magdalena River by Impala Terminals

    2.2. The project’s purpose(s) and objective(s) are:

    Impala Terminals Barrancabermeja S.A. and Impala Terminals Colombia SAS ("Impala

    Terminals") are two companies operating in Colombia, subsidiaries of the multinational

    Trafigura. Impala Terminals' business is the transfer and transport of cargo, mainly from

    the oil industry.

    The purpose of the project developed by Impala Terminals is the implementation of a

    single integral and efficient multimodal system that connects the inland industry with

    ocean ports in a regular and reliable way and that drives the development of riverside

    municipalities. In addition, the project aims to make transport more efficient, which

    allows more cargo to be transported with lower fuel consumption, thus reducing

    greenhouse gas emissions per unit of cargo transported.

    The project involves transporting the liquid cargo by tanker trucks only from the wells to

    the new river port terminal in Barrancabermeja, so that from this point it is transported on

    the barges driven by tugboats along the Magdalena River to the ocean ports. As of

    December 2017, 18 tugs and about 60 barges were in operation for the transport of liquid

    cargo.

    The project's emission reduction accreditation period provides for 10 years of operation

    and a total reduction of 943,375 tCO2 is estimated in that period.

    In addition to the benefits of GHG mitigation, the project has positive effects in a number

    of areas, for example, contributes to the development of local industry, promotes the

    formation of small and medium-sized enterprises, gives training to adults and, on the

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    4

    subject of regional management, professionalizes jobs and has agreements with the

    National Learning Service (SENA).

    Impala seeks to verify the emission reductions of its project Multimodal transport on the

    Magdalena River by Impala Terminals and to use the reductions to become carbon-

    neutral against the national carbon tax. Any GHG emission reduction unit that applies to

    the non-causation of the national carbon tax will not be used in another context as a

    compensation for GHG emissions, which will be evidenced by proof that they are

    previously cancelled within the certification program or source carbon standard.

    2.3. Expected lifetime of the project

    The total emission reduction accreditation period is 10 years, starting on June 19 of 2015

    and ending on June 18 of 2025.

    The total accreditation period of the project is less than the service life (20 years) of the

    river equipment of Impala Terminals. The service life of the river terminal is 30 years,

    evidenced by the port concession for usufruct of a public good.

    2.4. Type of greenhouse gas emission reduction or removal project

    The project pertains to sectoral scope 7 (Transport).

    2.5. Legal land description of the project or the unique latitude and longitude

    2.5.1. Project location

    - Port terminal in Barrancabermeja, ITBSA on maps presented after coordinate tables.

    Latitude Longitude

    7,098653 -73,892951

    - Port Society Puerto Bahia, Cartagena.

    Latitude Longitude

    10,286578 -75,52845

    - River route: Magdalena River route from Barrancabermeja to Calamar and Canal del Dique route from Calamar to Cartagena.

    - Extraction fields.

    Origin Coordinates Origin Coordinates

    Castilla 3.825833, -73.687222 Coyote 6.889451, -73.666725

    Chacharo 4.409121, -72.96609 Cuerva 5.663120, -70.683960

    Cohembi 0.349028, -76.493972 Curucucu 4.371697, -72.663406

    Cpe-6 3.495378, -72.111866 Glauca 6.066469, -74.492128

    Dorotea 5.452906, -71.026691 Iraca 3.595018, -73.663235

    Llanos34 (caribayona) 4.498596, -72.752459 Itbb 7.100000, -73.891151

    Moriche 4.920053, -72.017409 Jacamar 4.371388, -72.66250

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    5

    Origin Coordinates Origin Coordinates

    Vasconia 6.056676, -74.554962 Jacana 4.384020, -72.724213

    Barrancabermeja 7.100000, -73.891151 Juglar 7.697402, -73.705278

    Bullerengue 10.6367397, -74.939920 Llanos 58 3.886894, -72.642027

    Corrales 5.805007, -72.865450 Los ángeles 8.080343, -73.581685

    Platanillo 0.446259,-76.289844 Max 4.494457, -72.550224

    Rubiales 3.786387, -71.453393 Mono araña 8.132602, -73.619489

    Caramelo 8.333228, -73.672156 Paz de ariporo 5.880681, -71.893384

    El difícil 9.916043, -74.11886 Pendare 3.736258, -71.860897

    Fenix 7.508567, -73.380607 Pore 5.728208, -71.991893

    La punta 4.813055, -72.08028 Potrillo 5.57667, -71.75129

    Oso pardo 8.166004, -73.719161 Pozo bolívar 5.771134,-72.852522

    Puerto umbría mirto 0.860203, -76.580530 Puertoasis 0.504902, -76.501082

    Aguas blancas 6.835, -73.771944 Querubin 8.081769,-73.578859

    Aguazul 5.170679, -72.550903 Quillacinga 0.261083, -76.546736

    Akira 4.342604,-72.715315 Rionegro 7.267275, -73.151372

    Atarraya 4.225277, -71.823055 Santana 0.592960, -76.568748

    Begonia 5.78778,-71.38831 Tarotaro 4.446822, -72.610562

    Bonga 9.5047, -75.069862 Tigana 4.491077, -72.714547

    Cabuyaro 4.284443, -72.792399 Tilo 4.484681,-72.625993

    Calona 4.531508, -72.614618 Tua 4.409323, -72.648725

    Carmentea 4.575926,-72.615490 Villa garzón 1.028421, -76.617989

    Carupana 5.575421, -71.749614 Yamu 5.648501,-71.737298

    Chiricoca 4.492222,-72.664722 Zoe 7.8052528,-73.5912025

    Chuira 8.171601, -73.544684 San martin 8.002488, -73.513075

    Colon 7.700889, -73.733602

    Maps of the location of the relevant places of the mitigation project are presented below.

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    6

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    7

    2.5.2. Ownership of the project

    The new river port terminal and river fleet are owned by Impala Terminals. The cargo

    generator is Trafigura, through Trafigura Energy Colombia S.A.S. and C.I. Trafigura

    Petroleum Colombia S.A.S., who buy the liquid cargo products and transport them with

    Impala's services, which in turn outsources the road transport services, so the road fleet of

    tanker trucks is owned by third parties. The cargo generator is one of the project

    participants.

    2.6. Conditions prior to project initiation

    The Colombian oil reserve is mainly made up of heavy crude oil, for which transportation

    to ports on the Atlantic coast is a major challenge, since even the most efficient pipelines

    have capacity restrictions to move such a viscous product. So, usually in the events of

    high-demand in pipelines or contingencies, it is necessary to use tankers to evacuate

    production and maintain the operation of the fields. This transport service has been

    offered by Impala since the start of its operation in 2013. Until the first quarter of 2015,

    heavy crude oil was transported from the extraction wells to the port of Barranquilla by

    road in tankers trucks. On average, the routes were about 1,500 km long and took 5 days

    on the one-way route. Trips were also made from Barranquilla to the wells for the

    transport of naphtha, a product used as a crude oil solvent.

    This transport by tanker trucks was outsourced, i.e. it was carried out by transport

    companies that travel the routes established by Impala. Although at one time Impala also

    had its own fleet, it did not operate as expected, so the operation was maintained with the

    outsourced fleet. The average capacity of these tanker trucks is 210 barrels of crude oil

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    8

    and 240 barrels of naphtha. One of the conditions of the operation is that the vehicles

    could not be of models more than 10 years old.

    As for the river operation, an average of 8 million barrels were transported by the river

    annually between different transport companies prior to the entry of the project, but with

    the start of Impala's operations the sector was boosted and this number was increased to

    15 million barrels, of which Impala is responsible for transporting 44%.

    2.7. Description of how the project will achieve GHG emission reductions or removal enhancements

    The river route is on the order of 700 km length from Barrancabermeja to the port of

    Cartagena and it takes 6 days; the route of the complementary routes, from the wells to

    the port of Barrancabermeja is on the order of 750 km length and takes about 3 days. The

    river route replaces about half the average distance of the land routes. While the time to

    destination is longer, the load capacity is much higher in river transport, so a convoy

    carries between 4 and 6 barges and each barge carries the equivalent of 33 tankers. This

    allows to transport the same amount of cargo with lower fuel consumption.

    In the following figures, the routes prior the project operation vs. the multimodal

    transport route are schematically compared.

    Figure 1 Diagram of the scenario prior to project

    execution. Land routes in purple.

    Figure 2 Diagram of the project scenario. Multimodal

    route. Land routes in green. Note: This image

    corresponds to a report prepared in 2014. In the final

    design, the destination is Cartagena.

    Prior to the multimodal operation, the destination of the land transport by tanker truck

    was a seaport in Barranquilla. In the original design of the project, it had been envisaged

    that the destination of the river transport also would be a seaport in Barranquilla, where

    the mouth of the Magdalena River is located. To this end, the construction of a new

    deepwater port in Barranquilla was contemplated; however, the shallow depth of the

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    9

    access channel became an obstacle to the development of this port. So a capacity-use

    contract was concluded with the Port Society of Puerto Bahia, Cartagena, a new seaport,

    inaugurated in 2015, which is connected to the Magdalena River via the Canal del Dique,

    which has a length of 115 km from Calamar to Puerto Bahia.

    Figure 3 Canal del Dique. Adjusted from Catorce 6 Revista Ambiental.

    2.8. Project technologies, products, services and the expected level of activity

    2.8.1. Technologies implemented by the project

    From March 24, 2015, the multimodal transport project began in its early stages, and

    from February 1, 2018 the official commercial operation of the river port began.

    The features of the river terminal built in Barrancabermeja on the Magdalena River are an

    area of 500,000 m2, storage of 850 kbbl, 1,200 m of dock line and an annual capacity of

    190,000 TEU (Twenty-foot Equivalent Unit, the load capacity of a 20-foot standardized

    container).

    Export, import and re-embarkation operations are carried out at the port through the

    following transport operations: customs transit declarations, cabotage, multimodal

    transport operations and combined transport. It is also suitable for liquid loading and dry

    cargo operations.

    The port concession has effect from 2014 to 2044, granted by the local environmental

    authority, CORMAGDALENA.

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    10

    Figure 4 Port of Impala Terminals Barrancabermeja

    This is the composition of the river fleet and its characteristics:

    Equipment Amount Type

    TRATANK CROATA 27 Barge

    TRATANK ARGENTINA 22 Barge

    MAGBIT 12 Barge

    BIG PUSHER 10 Tugboat

    SMALL PUSHER 6 Tugboat

    GAS 3 Gas tanker

    TRATANK ARGENTINA TRATANK CROATA MAGBIT

    Gen

    eral

    cla

    ssif

    icat

    ion

    Hull Naval Steel Naval Steel Naval Steel

    Length overall (m) 59,48 59,48 59,48

    Beam Max (m) 16 16 16

    Side depth (m) 3,66 3,65 4,6

    Freeboard (m) 0,3 0,3 0,3

    Useful tip (m) 2,71 2,69 3,4

    Empty draft (m) 0,65 0,65 0,9

    Empty Displ. (t) 572 570 624

    Useful Displ. (t) 2503,6 2503 2450

    Total Displ. (t) 3075,6 3073,2 3074

    Ca

    pa

    citi

    es

    Conveyor (t) 2503,6 2503 2450

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    11

    TRATANK ARGENTINA TRATANK CROATA MAGBIT

    Towing (t) N/A 2503 2450

    Cellars 5 4 4

    Void space 10 10 10

    Cottage 2 2 4

    Small Pusher Large Pusher G

    ener

    al c

    lass

    ific

    atio

    n

    Hull Naval Steel Naval Steel

    Length overall (m) 29,5 33,7

    Beam Max (m) 11,2 11,2

    Side depth (m) 2,76 2,76

    Freeboard (m) 0,81 0,3

    Useful tip (m) 0,6 0,83

    Empty draft (m) 1,35 1,63

    Empty Displ. (t) 308,7 438,96

    Useful Displ. (t) 193,87 310,2

    Total Displ. (t) 502,57 749,16

    Cap

    acit

    ies

    Conveyor (t) 0,194 0,31

    Towing (t) 10965 28755

    Exploitation (t) 11158 29065

    Number of propellants 2 3

    Brand Propellants Caterpillar Caterpillar

    Power (HP) 1700 3825

    R.P.M 1800 1800

    Rudder control Hidráulico Hidráulico

    Height (m) 4,65 11,7

    Staterooms 5 7

    Cellars 3 3

    Void space 14 6

    Cottage 4 2

    The crew of the tugboats consists of: Captain, Pilot, Helmsman, Petty Officer, Machinist,

    Machine Assistant, Chef and three Sailors.

    Tugs are fueled with liquid fuel stored on barges called MAGfuel. However, at the start

    of the operation, they were fueled from tanker trucks.

    The volume of cargo transported is variable and is expected to change according to

    Impala's commercial operation and the oil sector activity, for example, the amount of

    cargo carried is expected to rise, mainly because it is likely that crude oil production will

    increase in 2018. Since 2017 Impala transports Fuel Oil to the coast, which also

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    12

    contributes. In addition, since June 2018, the import of crude for refining began in

    Colombia, which would increase the cargo transported on return trips.

    The Port Society of Puerto Bahia is located in Cartagena, of which Trafigura is a

    shareholder. Impala has a buoy inside the port where they have a platform that allows

    mooring of the barges. The process of loading ships is jointly between Trafigura and the

    Port.

    The complementary routes shown schematically in Figure 2 are contracted with third

    parties, using the command model, in which a contract is signed between the transporters

    and Trafigura, but the one who defines the conditions of the operation is Impala. As

    noted, complementary routes go only from the extraction fields and there are no

    complementary routes at the destination.

    For complementary routes, the vehicles used in the operation are two- and three-axle

    tractor-trailers, mostly Kenworth brand. Taking a sample of 1109 vehicles used during

    Impala's operation in July 2018, it is found that the fleet used corresponds to models

    between 2007 and 2017, of which 67% of the fleet used corresponds to models from 2012

    and 2013 years, as shown in the following table:

    Model N° Tanker truck

    2007 47

    2008 89

    2009 28

    2010 30

    2011 99

    2012 542

    2013 201

    2014 34

    2015 35

    2016 2

    2017 2

    TOTAL 1109

    The capacities of these vehicles range from 9,000 to 13,000 gallons, where most of the

    units used are in the range of 11,000 to 12,000 gallons, i.e. between 260 to 285 barrels of

    capacity.

    Capacity (gal) N° Tanker truck

    9000-10000 47

    10000-11000 436

    11000-12000 621

    12000-13000 5

    Total 1109

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    13

    As for the classification according to the number of axles, there is a sample of 684 units

    mobilized in the month of June 2018, of which 56% correspond to 3-axle tractor-trailers

    and 44% of 2 axles, showing that both types of vehicles have an important stake in the

    operation.

    The expected level of activity for the years to come from the project is presented in

    Figure 5.

    Figure 5 Projection of volumes to be transported until 2023. Taken from the file “Proyección Volumenes Proyecto

    Bonos.xlsx”

    2.9. Total GHG emission reductions and removal enhancements, stated in tonnes of CO2 e, likely to occur from the GHG project (GHG Assertion)

    The following table shows the estimated reductions, based on the 2015 to May 2018

    operation and an estimate of each parameter (based on the activity projections to 2023

    and the ratio of the parameter to the cargo of 2017), as shown in the following formula.

    The information was used for 2017 only, because this is the year of commercial operation

    in which the activity was already stabilized and the relationship between each parameter

    and the transported cargo is expected to behave similarly.

    𝑃𝑎𝑟𝑎𝑚𝑒𝑡𝑒𝑟𝑦 =𝑃𝑎𝑟𝑎𝑚𝑒𝑡𝑒𝑟2017

    𝐶𝑎𝑟𝑔𝑜2017∗ 𝐶𝑎𝑟𝑔𝑜𝑦

    Table 1 Project emissions reductions

    Year Estimated net GHG emission reductions or removals (tCO2)

    19/06/2015-31/12/2015 1,351

    2016 19,675

    2017 45,340

    -

    5.00

    10.00

    15.00

    20.00

    25.00

    2019 2020 2021 2022 2023

    MB

    bl

    Transport projection

    Crudo, Fuel oil Nafta, Light Crude

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    14

    2018 46,758

    2019 58,959

    2020 72,190

    2021 113,171

    2022 154,753

    2023 174,802

    2024 174,802

    01/01/2025-18/06/2025 81,574

    Total 943,375

    2.10. Identification of risks

    The main risks of the operation are the conditions of navigability of the river, as there are

    certain restrictions for the operation, such as radius of curvatures, depths and widths of

    the channel that have led to stop the operation, causing routes that in optimal conditions

    take 6 days, take up to 10 days. This risk would be mitigated by the project, which is the

    responsibility of the national government, related to the river navigability that includes,

    among others, the dredging of the river.

    2.11. Roles and Responsibilities

    Organization name Impala Terminals Group (Impala Terminals Colombia SAS y

    Impala Terminals Barrancabermeja S.A.)

    Role in the project Project Manager

    Owner of the river fleet and river port infrastructure

    Contact person Alexander Higuera

    Title Chief Operating Officer

    Address Carrera 55 No. 100 – 51 Piso 8, Barranquilla, Colombia

    Telephone +57 5 3850537

    Email [email protected]

    Organization name Trafigura (Trafigura Energy Colombia S.A.S. y C.I. Trafigura

    Petroleum Colombia S.A.S.)

    Role in the project Cargo owner

    Contact person Susana Dennis

    Title Lawyer

    Address Carrera 11 No. 82 – 01 Piso 7, Bogotá, Colombia

    Telephone +57 1 7420910

    Email [email protected]

    Organization name CAIA Ingeniería SAS

    Role in the project Document preparation, reduction assertion and review of the GHG

    Report.

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    15

    Contact person Alexander Valencia Cruz /Jessica Wade-Murphy de Jiménez

    Title Consultants

    Address Calle 67 7-94 Of. 404, Bogotá, Colombia

    Telephone +57 300 216 2406 / +57 310 782 7017

    Email [email protected] / [email protected]

    2.12. Any information relevant for the eligibility of the GHG project under a GHG program and quantification of emission reductions

    Compliance with the requirements of the GHG CleanProjects Registry

    The project complies with the requirements of the GHG CleanProjects Registry and

    demonstrates compliance with ISO 14064-2, as described in sections 1.1 to 1.6 and

    throughout this report. The validation and verification report that accompanies the current

    report will demonstrate further the conformity of the project with the requirements of the

    GHG CleanProjects registry.

    Context of the mitigation project

    The Nationally Determined Contribution (NDC) of Colombia, presented in 2015,

    envisages a unilateral and unconditional goal of mitigation of 20% of GHG emissions

    from the business-as-usual (BAU) scenario in 2030. The goal was defined against the

    BAU scenario that was projected based on the national GHG Inventory of 2010, applying

    economic and other assumptions. In this way, the year 2010 was defined as the "baseline

    year" of the country, therefore, any activity that was implemented in previous years and

    reduced emissions, is already embodied in the baseline and cannot be considered as

    "mitigation" action for verification. This situation is confirmed in decree 926 of 2017,

    Chapter 2, article 2.2.11.2.1, paragraph 1, "Only reductions of GHG emissions and

    removals generated from 1 January 2010 may be submitted.".

    Measures by sector have been prioritized from the Ministry of Environment and

    Sustainable Development to contribute to the national commitment made in the NDC.

    Among the goals defined for the Ministry of Transport is the "Navigability of the

    Magdalena and the Intermodal Strategic Plan". In this line is the Plan of Action 2018-

    2020, of CORMAGDALENA (Regional Autonomous Corporation of the Great River of

    Magdalena), which contemplates the Strategic Navigation Plan, which aims to recover

    the navigability of the Magdalena River up to 908 km upstream responding to the

    country's need to establish intermodality, as set out in Resolution 0000164 of 5 February

    2015 of the Ministry of Transport. In this sense, this project is aligned with national

    priorities for mitigation in the transport sector.

    Resolution 1447 of 2018 of the Ministry of Environment and Sustainable Development

    (MADS) also defines the additionality criteria for sectoral GHG mitigation projects in

    article 37. Particularly:

    Table 2 Compliance Analysis: Requirements of resolution 1447 of 2018

    Criterion of 2018 resolution 1447 article 37 Project Compliance

    GHG emissions reductions or removals are Section 3 Selection and

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    16

    Criterion of 2018 resolution 1447 article 37 Project Compliance

    considered additional when the head of the

    sectoral mitigation project demonstrates that

    they would not have occurred in the absence of

    the GHG Mitigation initiative and which

    generate a net benefit to the atmosphere with

    respect to their baseline.

    Justification of the Baseline

    Scenario presents the choice and

    justification of baseline, which is

    different from the activity of the

    initiative, and section

    5Quantification and calculation of

    GHG emissions/removals

    evidences the net benefit to the

    atmosphere generated compared to

    the baseline.

    Likewise, GHG removals are considered to be

    additional when they result from the

    implementation of forestry GHG removal

    activities, which are developed in areas other

    than natural forest and that demonstrate the

    positive net change of carbon deposits in the

    area of development of the activity and other

    criteria of additionality defined by the Ministry

    of Environment and Sustainable development.

    Not applicable

    Reductions in emissions or removals of GHG

    resulting from compensation activities of the

    biotic component resulting from the impacts of

    projects, works or activities within the

    framework of environmental licenses,

    concessions, applications for single-use permits

    of forest resources for land use change, and the

    application for definitive extractions of national

    and regional forest reserves, are not considered

    additional.

    Not applicable

    Emissions reductions or GHG removals are not

    considered to be additional when they are the

    product of preservation and restoration activities

    in strategic areas and ecosystems that access

    payments for environmental services of GHG

    reduction and capture according to what is

    established in chapter 8 of title 9 of Part 2 of

    Book 2 of Decree 1076 of 2015.

    Not applicable

    The reductions or removals of GHG generated

    from the date of completion of the legal terms of

    the compensations referred to in this article, or

    the termination of payments for environmental

    services of GHG reduction and capture, shall be

    deemed to be additional.

    Not applicable

    The owners of sectoral GHG mitigation projects

    must apply in all their actions and procedures the

    The GHG CleanProjects Registry

    certification program establishes

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    17

    Criterion of 2018 resolution 1447 article 37 Project Compliance

    additionality criteria set out in this article, in

    complement to the additionality criteria

    established by the GHG certification program or

    carbon standard to which it is subscribed.

    the use of the analysis of

    alternatives and barriers to justify

    the selection of the baseline

    scenario. In section 3 Selection and

    Justification of the Baseline

    Scenario, we present the

    identification and selection of

    baseline, meeting the criteria

    established by the GHG

    certification program.

    Article 221 of Law 1819 of 2016 established the national carbon tax which began validity

    from 1 January 2017. According to its regulation in Sole Statutory Tax Decree 1625 of

    2016, the tax is charged to the purchaser of fuel in proportion to its equivalence in tonnes

    of CO2e generated from combustion. The rate is fixed per tonne of CO2e according to

    the carbon content of the fossil fuel.

    Since the dispatch of Decree 926 of 2017, a non-causation procedure for the national

    carbon tax exists. It is possible to avoid the payment of the tax by means of the

    neutralization of the GHG emissions associated with the use of the fuel, by verified GHG

    emissions reductions. To avoid the payment of the tax, the purchaser of the fuel must

    inter alia show the declaration of verification of the emissions reductions, issued by a

    verification body accredited under the standard ISO 14065, equivalent to the quantity of

    fuel in question.

    The requirements described by the decree for the characteristics of the emission

    reductions that are valid for the non-causation of the tax, include:

    Table 3 Compliance Analysis: Requirements of decree 926 of 2017

    Requirement of decree 926 of 2017 Project Compliance

    The mitigation initiative must be

    developed in the national territory.

    The project takes place in the national

    territory: Route of the Magdalena River,

    between Barrancabermeja, Santander and

    Calamar, and by Canal del Dique between

    Calamar and Cartagena, Bolívar.

    The initiative must be formulated and

    implemented through a certification

    program or carbon standard that has a

    public registration platform.

    The project is formulated through the

    GHG CleanProjects Registry certification

    program, which has a public registry.

    Have been implemented following a

    methodology, either from a certification

    program or carbon standard, or from the

    clean development mechanism.

    The project is implemented from a clean

    development mechanism methodology

    (details below).

    Do not come from activities that are

    developed by the mandate of an

    The project is a voluntary activity.

    https://www.csaregistries.ca/cleanprojects/masterprojects_e.cfm

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    18

    environmental authority.

    Be certified by the certification program

    or carbon standard and duly cancelled

    within it.

    The project will request certification by

    GHG CleanProjects Registry and cancel

    any reduction unit prior to use for non-

    causation of the national carbon tax.

    Impala Terminals is not subject to GHG emissions trading. There are no mandatory limits

    or ceilings on their emissions level, either.

    As for the methodology selected, AM0090 – Modal shift in transportation of cargo from

    road transportation to water or rail transportation. Version 0.1.1.0, the following table

    of applicability is presented:

    Table 4 Applicability Analysis AM0090 – Modal shift in transportation of cargo from road transportation to water or

    rail transportation. Version 0.1.1.0

    Applicability

    This methodology is applicable to project activities

    that result in modal shift in transportation of a

    specific cargo (excluding passengers) from road

    transportation using trucks to water transportation

    using barges or ships or rail transportation.

    Achieved, the project consists

    of the operation of a

    multimodal liquid cargo

    transportation system

    involving a significant section

    of barge transport along the

    Magdalena River and the

    Canal del Dique.

    The methodology is applicable under the following

    conditions:

    a) The owner of the cargo is one of the project participants. If the entity investing in the CDM

    project activity is not the owner of the cargo, it

    should also be a project participant;

    b) The project participants should have made at least one of the below listed new investments:

    o Direct investment in new infrastructure, including facilities (new ports, handling

    areas) and/or equipment (ships, barges, etc.)

    for water transportation;

    o Direct investment in new infrastructure, including facilities (new ports, handling

    areas, railway track) and/or equipment

    (trains, wagons, etc) for rail transportation;

    o Refurbishment/replacement of existing water and rail transportation infrastructure

    or equipment, with transport capacity

    expansion.

    a. Achieved, Trafigura is the cargo generator and

    Impala, who is the project

    owner and the cargo

    transporter, is part of the

    Trafigura group. Both

    Impala and Trafigura

    participate in the project.

    b. Achieved, direct investment was made in

    the construction of the

    new river port and in the

    purchase of barges and

    tugboats.

    The transport infrastructure/equipment in which

    these new investments are made is at least 50%

    Achieved, Impala Terminals

    is a private port for public

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    19

    used by the cargo transported under the project

    activity, i.e. the cargo transported under the project

    activity constitutes at least 50% of the cargo

    transported annually by/with this

    infrastructure/equipment;

    use. However, there is

    currently no significant

    activity of other transport

    companies in the port. While

    the main transport is the

    liquid cargo, a smaller

    volume of dry cargo,

    corresponding to 2.1% of the

    total cargo mobilized by river

    transport between 2016 and

    2017, has also been

    transported.

    With respect to fuels, the following conditions

    apply:

    • In the case of gaseous fossil fuels, the methodology is applicable if it can be

    demonstrated that equal or more gaseous fossil

    fuels are used in the baseline scenario than in

    the project activity. The methodology is not

    applicable in its current form if more gaseous

    fossil fuels are used in the project activity

    compared to the baseline scenario;

    • In the case of biofuels, the methodology is applicable if it can be demonstrated that equal

    or more biofuels are used in the baseline

    scenario than in the project activity. The

    methodology is not applicable in its current

    form if more biofuels are used in the project

    activity compared to the baseline scenario.

    Achieved, more biofuel is

    used in the baseline than in

    the project operation because

    tanker trucks use a

    commercial blended diesel

    with 10% biodiesel, while

    tugs use marine diesel

    without biodiesel content.

    The project transportation mode is defined in the

    CDM-PDD at the validation of the project activity

    and no change of transportation mode is allowed

    thereafter;

    Achieved, the project that is

    presented corresponds only to

    the change from transport by

    tanker trucks to multimodal

    transport by the river

    The cargo is transported from the same origin (point

    A) to the same destination (point B) throughout the

    whole crediting period. These two points and

    transportation routes are defined in the CDM-PDD

    at the validation of the project activity and are fixed

    along the crediting period;

    Achieved, the river transport

    originates in Barrancabermeja

    and its destination is

    Cartagena.

    Under the project activity, the route from origin to

    destination may combine the different

    transportation modes: Trucks, ships, barges and/or

    rail but a part of the route must consist of either

    ships, barges or rail;

    Achieved, the project consists

    of multimodal transport,

    combining transport by tanker

    trucks and barges.

    Both in the baseline and project activity, only one Achieved, the product

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    20

    type of cargo, owned by the project participants, is

    transported and no mix of cargo is permitted (this

    condition does not apply to the return trip cargo).

    The cargo type of the project activity is defined in

    the CDM-PDD at the validation of the project

    activity and is fixed along the crediting period;

    transported corresponds to

    liquid petroleum products

    (e.g. heavy crude, Fuel Oil,

    Nafta).

    The railway infrastructure or waterway has enough

    capacity to accommodate new transportation

    demand under the project activity and will not

    displace other existing transportation demand due to

    limited capacity of infrastructure.

    Achieved, the entry into

    operation of the project does

    not limit the capabilities for

    the operation of other

    transport offers. See section

    2.6.

    Table 5 Applicability analysis: Tool03 – Tool to calculate project or leakage CO2 emissions from fossil fuel

    combustion. Version 03.0.

    Scope and applicability

    This tool provides procedures to calculate project

    and/or leakage CO2 emissions from the combustion

    of fossil fuels. It can be used in cases where CO2

    emissions from fossil fuel combustion are

    calculated based on the quantity of fuel combusted

    and its properties. Methodologies using this tool

    should specify to which combustion process j this

    tool is being applied.

    Achieved; the project

    calculates project emissions

    according to the amount of

    fuel used and its properties.

    Table 6 Applicability análisis: Tool05 – Tool to calculate baseline, project and/or leakage emissions from electricity

    consumption and monitoring of electricity generation. Version 03.0

    Applicability

    If emissions are calculated for electricity

    consumption, the tool is only applicable if one out

    of the following three scenarios applies to the

    sources of electricity consumption:

    - Scenario A: Electricity consumption from the grid. The electricity is purchased from the grid

    only, and either no captive power plant(s) is/are

    installed at the site of electricity consumption

    or, if any captive power plant exists on site, it is

    either not operating or it is not physically able

    to provide electricity to the electricity

    consumer;

    - Scenario B: Electricity consumption from (an) off-grid fossil fuel fired captive power plant(s).

    One or more fossil fuel fired captive power

    plants are installed at the site of the electricity

    Achieved, the project

    contemplates scenario A, as

    the electricity consumed in

    the port corresponds to

    power delivered by the grid.

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    21

    consumer and supply the consumer with

    electricity. The captive power plant(s) is/are not

    connected to the electricity grid; or

    - Scenario C: Electricity consumption from the grid and (a) fossil fuel fired captive power

    plant(s). One or more fossil fuel fired captive

    power plants operate at the site of the electricity

    consumer. The captive power plant(s) can

    provide electricity to the electricity consumer.

    The captive power plant(s) is/are also

    connected to the electricity grid. Hence, the

    electricity consumer can be provided with

    electricity from the captive power plant(s) and

    the grid.

    This tool can be referred to in methodologies to

    provide procedures to monitor amount of electricity

    generated in the project scenario, only if one out of

    the following three project scenarios applies to the

    recipient of the electricity generated:

    - Scenario I: Electricity is supplied to the grid;

    - Scenario II: Electricity is supplied to

    consumers/electricity consuming facilities; or

    - Scenario III: Electricity is supplied to the grid and

    consumers/electricity consuming facilities.

    Not applicable, Tool05 is

    applied to calculate

    emissions corresponding to

    energy consumed from the

    grid.

    This tool is not applicable in cases where captive

    renewable power generation technologies are

    installed to provide electricity in the project

    activity, in the baseline scenario or to sources of

    leakage. The tool only accounts for CO2 emissions.

    Not applicable

    2.13. Summary environmental impact assessment

    The environmental permits in force and relevant to the operation of the river port consist

    of:

    • Environmental License and Environmental Management Plan, approved by Resolution 690 of 2013 of the Regional Autonomous Corporation of Santander

    (CAS).

    This is the summary of the impacts and measures identified in the Environmental

    Management Plan requested by the Colombian environmental authorities.

    Table 7 Summary of the results of the environmental impact assessment and the measures designed for each.

    Impact Measure

    Soil loss and alteration Storage of organic soil removed for use in the formation

    of slopes.

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    22

    Generation of instability and

    erosion.

    Training on appropriate collection and management of

    surface and sub-surface water and confinement of

    materials.

    Generation of sterile material

    and debris, alteration of water

    quality, alteration of air quality

    and noise, visual involvement

    of the landscape.

    Debris will be transported to temporary collection sites,

    well located and protected, for final disposal in a place

    authorized by the environmental authority.

    Alteration of the

    physicochemical

    characteristics of water,

    alteration of aquatic

    ecosystems.

    Treatment plant for the management of domestic

    wastewater from offices.

    Fat trap and API separator for water used for washing

    vehicles and barges and runoff of the liquid terminal.

    Sedimentation tanks for the runoff waters of the coal

    terminal.

    Alteration of air quality,

    alteration of sound pressure

    levels.

    Wind barrier, water spray on the piles and carbon

    conveyor belts.

    Proper maintenance to equipment, ban of whistle and

    sirens, location of the loudest equipment away from

    human settlements.

    Generation of domestic and

    hazardous solid waste,

    pollution of water quality and

    air quality, impact of

    perception and enjoyment of

    the landscape and soil

    pollution.

    Management of domestic solid waste: Separation at the

    source, gathering and collection of waste systems for

    incineration, disposal in landfill or exploitation.

    Hazardous waste will be handled by an authorized

    external manager.

    Special waste will also be taken to landfill or

    incineration.

    Alteration of hydrobiological

    communities and alteration of

    the physicochemical quality of

    water.

    Separation of sediments removed during dredging is

    made. Reduction of movement of cables or anchors to

    avoid resuspension of sediments. Environmental

    education and community information actions.

    Loss of plant coverage and

    terrestrial habitat, alteration of

    terrestrial fauna, alteration of

    hydrobiological communities.

    Specific to the construction process.

    - Delimitation of the work fronts - Environmental awareness workshops - Rescue of plant material and mulch - Management of plant material during intervention - Compensation: Purchase of land for conservation by

    the environmental authority.

    Conservation of endangered

    plant and fauna species.

    Transfer of vulnerable plant species and planting of new

    individuals.

    Continuous study of vulnerable animal populations.

    2.14. Relevant outcomes from stakeholder consultations and mechanisms for on-going communication.

    In the phase before operation, Impala conducted a broad consultation and reporting

    process to stakeholders. From March 2013, the process of socializing the project began

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    23

    with four surrounding communities, the municipal government, the national government

    and the fishing guilds. Then, six-monthly meetings regarding construction progress were

    held. In 2018, the closing meeting of the construction stage was held.

    Consultation with stakeholders in surrounding communities prior to the operation raised

    an interest in employment opportunities. A policy for the recruitment of labour was

    implemented, through which percentages of participation of local labour, both unskilled

    and skilled, were established. The percentages were met and the goals were even

    exceeded.

    In addition, after demonstrations by some members of surrounding communities, in

    October 2014 two commitments were established with the surrounding communities. The

    first was that Impala would continue with voluntary social interventions, and the second

    was that Impala established priority tendering processes for local entrepreneurs and that it

    would ensure the recruitment of local labour by its contractors. To meet these

    commitments, Impala has voluntarily conducted training and empowerment of local

    entrepreneurs to bring them to a better standard of service and also internal management

    with the procurement area to train about benefits of hiring locally.

    In terms of mechanisms for permanent communication with stakeholders, there are four

    mechanisms for permanent communication:

    • Citizen Service Point (PAC) – office in Barrancabermeja.

    • To-use care phone ("01800041769")

    • Email, [email protected]

    • "Request, Complaint, Claim, Suggestion" (PQRS) system, which is administered from the PAC.

    Further ongoing communication actions have been undertaken with communities and

    other stakeholders, such as river and road safety campaigns.

    2.15. Detailed chronological plan

    Table 8 Relevant project activities

    Date Activity Evidence

    November

    2013

    Construction of the terminal begins in

    Barrancabermeja First intervention report.

    2014

    ERM assessment of the GHG

    emission reduction potential of

    Impala Terminals multimodal

    transport in Colombia

    Brochure “Multimodalismo-

    Reduciendo las Emisiones de

    Carbono en Colombia”

    24 March 2015

    Early-stage operation of the terminal

    in Barrancabermeja begins, with river

    transport to Barranquilla

    Letter of notification to

    CORMAGDALENA

    19 June 2015 First river trip with Puerto Bahia

    origin and start of mitigation activity

    Certificate of inspection

    house

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    24

    1 April 2017

    Starts the operation in the commercial

    phase of the terminal in

    Barrancabermeja.

    Logs on TMS1 and TMS2 of

    loading and unloading from

    ITBB.

    June 2017 Fuel Oil transport start Transportation guide

    1 February

    2018

    Starts the full operation of the

    terminal in Barrancabermeja

    Letter of notification to

    CORMAGDALENA

    2018

    Consulting is contracted to formulate

    the project to certify the reduction of

    GHG achieved

    Email from Susana Dennis

    3. Selection and Justification of the Baseline Scenario

    Due to Colombia's national circumstances in relation to its mitigation target and national

    baseline (see section 2.12) the baseline is considered to be the practices prior to the

    project operation.

    However, since the destination of the project operation is the port in Cartagena and not in

    Barranquilla, as was the case in the ground operation in the years prior to the project, the

    baseline was defined based on the information of the trips made by tanker truck to

    Barranquilla (number of trips and volumes transported), but each trip was assigned a

    distance in km according to its respective origin with destination Cartagena.

    In the operation before the project, the transport of liquid petroleum products was done

    by tanker trucks. Crude oil was the liquid petroleum product most transported. Fuel Oil is

    also transported in the project. Even though this service was not previously provided by

    Impala, it is important to highlight the incidence of several factors:

    a) Crude oil production, and consequently its transportation, showed sharp fluctuations in the first years of operation of the project, due to international price variability,

    which prompted Impala to look for other liquid petroleum products for transport.

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    25

    Figure 6 Historic crude oil production in Colombia.1 Thousands of barrels per calendar day (KBDC)

    b) A process was opened to contract the transport of Fuel Oil by Ecopetrol. Even if the multi-modal transport project had not existed, Impala would also have made an offer

    in the process, offering transportation by tanker trucks.

    As a baseline scenario, transport through the pipeline system is ruled out. Before the port

    operation, transport was carried out by tanker trucks, because pipeline use is restricted to

    the transport of products whose API is between 18 and 50 for most of the country

    pipelines2. In addition, according to the magazine Energía 16, in its article of February

    27, 2018, Oil infrastructure and industry in Colombia, business competition for access to

    pipelines is growing, as the current infrastructure is not sufficient to cope with the recent

    increase in production.

    Therefore, the alternative would be the construction of a new pipeline, however, this

    represents a big economic investment and would not solve the technical barriers to the

    transport of products whose API is not between 18 and 50.

    Similarly, multimodal transport with barges along a section of the Magdalena River also

    faces barriers because there was a need to build a new river port and acquire the right

    river fleet to achieve large-scale transport, which represents a large economic investment.

    The operation presents challenges due to the low navigability of the Magdalena River,

    which does not allow the river transport to operate at full capacity. In addition, despite

    the Strategic Navigation Plan, which aims to restore the navigability of the Magdalena

    River, there is uncertainty about the date of implementation of the plan. It was also

    necessary to overcome the perception that Barrancabermeja is not a logistics city, to be

    considered as a river transport port.

    None of the above barriers affect the operation with tanker trucks transportation. The

    analysis of the barriers of alternatives to the mitigation project is presented below.

    1 Adapted from

    http://www.upme.gov.co/generadorconsultas/Consulta_Series.aspx?idModulo=3&tipoSerie=138 2 Pipeline Conveyor Manual. Ecopetrol. (2014) https://www.ecopetrol.com.co/documentos/Manual-

    Transportador-Oleoductos-Ecopetrol.pdf

    750

    800

    850

    900

    950

    1,000

    1,050

    Jan-14 Jun-14 Nov-14 Apr-15 Oct-15 Mar-16 Aug-16 Jan-17 Jul-17

    KB

    DC

    Historic crude production

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    26

    Table 9 Analysis of barriers to project alternatives

    Alternative Economic

    Barrier

    Operational

    Barrier /

    Maintenance

    Sociocultural

    barrier

    Environmental

    Barrier

    Barrier

    Present

    and future

    conditions

    Transport by

    tanker trucks

    (previous

    practice)

    Not

    applicable Not applicable

    Not

    applicable Not applicable

    Not

    applicable

    Pipeline

    transport Exists

    (in case of

    new

    pipeline)

    Exists Not

    applicable Exists

    Not

    applicable

    Multimodal

    transport along

    the Magdalena

    River

    Exists Exists Exists Exists Exists

    The additionality of the project is evident from the table above. Also, following the

    AM0090 and in accordance with the above, the baseline scenario is selected as the M1:

    Road transportation.

    Consistency with Resolution 1447 of 2018, article 35

    Article 35 of the resolution states that the baseline must be established according to the

    reference scenario published by the MADS or approved by the Intersectoral Commission

    of Climate Change. However, no such relevant reference scenario has been established.

    The next option is to define the baseline pursuant to the methods of the national GHG

    inventory in case there is information available at the higher methodological level

    according to IPCC guidelines. For the inventory category regarding this project emission

    sources, 1A3b, the Tier 2 methodologies for CO2 were applied and the source of

    information is the FECOC, a database elaborated by the UPME and MADS. However,

    Tier 3 methods are not applied.

    In this regard, the Project's baseline should be "developed with the information available

    to it ensuring compliance with the principles of the MRV System of mitigation actions,

    so that the project baseline does not lead to an overestimation of the mitigation results

    with respect to national information." In this sense, the baseline is determined according

    to the specific information available taking into account the fuel consumption of the

    vehicles for equivalent transport in the baseline scenario and it is considered that the

    result does not lead to an overestimation of project mitigation results.

    Equivalence in the service level

    From the perspective of the liquid petroleum producer, the level of service for transport is

    equal to or better in multimodal transport with a segment by river, versus tanker trucks

    transport. Some of the advantages and improvements that are obtained in the service

    thanks to multimodal transport are:

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    27

    - Increased efficiency in evacuation by tanker trucks in the oilfields, using fewer vehicles transiting between the production field to the point of unloading and return.

    This helps to have a better availability of vehicles for the evacuation of the product,

    avoiding risks that affect the production of the field.

    - Flexibility for producers when handling production peaks or variations in crude oil chemical conditions, as, given the high storage capacity of the Impala Terminal and

    its technological level, they would not need to look for alternative unloaders,

    incurring additional costs.

    - Decrease in the use of solvent, avoiding the cost of dilution, since the Impala terminal receives more viscous crudes than the pipelines.

    - Temporary storage as an alternative to manage production, according to customer requirements.

    - Cargo consolidation on the barge, allowing partial delivery of higher volume of product. To exemplify this point, the convoy of 6 barges can carry between 42 and 60

    Kbbls (depending on the levels of the river, related to the time of year), equivalent to

    200-286 vehicles.

    4. Inventory of sources, sinks and Reservoirs (SSRs) 3 for the project and baseline

    The scope of the project is the river port terminal in Barrancabermeja, all trips made on

    barges transporting liquid petroleum products and road travel by complementary routes.

    Table 10 Emissions sources within the scope of the project

    Source Gas Included? Justification/Explanation

    Bas

    elin

    e

    Fuel consumption for cargo

    transportation

    CO2 Yes Main emission source

    CH4 No Excluded for simplification. This is

    conservative

    N2O No Excluded for simplification. This is

    conservative

    Pro

    ject

    Fuel and/or electricity

    consumption

    for cargo transportation

    CO2 Yes Main emission source

    CH4 No Excluded for simplification.

    N2O No Excluded for simplification.

    Table 11 Controlled, affected and related emission sources within the Project boundary

    3 Definitions are extracted from the ISO 14064-2 standard:

    Controlled greenhouse gas source, sink or reservoir: GHG source, sink or reservoir whose operation is under the direction and influence of the greenhouse gas project proponent through financial, policy, management or other instruments

    Related greenhouse gas source, sink or reservoir: GHG source, sink or reservoir that has material or energy flows into, out of, or within the project

    Affected greenhouse gas source, sink or reservoir: GHG source, sink or reservoir influenced by a project activity, through changes in market demand or supply for associated products or services, or through physical displacement

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    28

    Source Gas

    How the GHG SSR change from the baseline

    scenario to the project?

    Controlled

    Fuel from the river

    mode of

    transporting cargo CO2

    With the execution of the project, more

    efficient transport is made, resulting in a lower

    fuel consumption to mobilize the same amount

    of cargo between the same origin and

    destination. Emissions are generated due to

    river transport.

    Electricity

    consumed at the

    port CO2

    With the execution of the project, a new

    electricity consumption of the grid is generated

    by the permanent operation of the port facilities

    in Barrancabermeja.

    Fuel consumption

    at ITBB CO2

    With the execution of the project a new fuel

    consumption is generated for the permanent

    operation of the port facilities in

    Barrancabermeja.

    Affected

    Fuel from the

    ground transport

    mode of

    transporting the

    cargo

    CO2

    With the implementation of the project, a modal

    change is made to a more efficient way of

    transport, resulting in lower fuel consumptions

    of the road transportation offered by contracted

    operators.

    Related Not relevant.

    N/A There are no related sources that are relevant to

    the development of the project.

    These are the flowcharts for the baseline scenario and the project scenario.

    Figure 7 Baseline flowchart

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    29

    Figure 8 Project flowchart

    5. Quantification and calculation of GHG emissions/removals

    5.1. Baseline emissions calculation

    Baseline emissions are generated according to equation 2 of the AM0090 methodology.

    𝐵𝐸𝑦 = 𝑇𝑦 ∗ 𝐴𝐷 ∗ 𝐸𝐹𝐵𝐿 ∗ 10−6

    Where:

    𝑇𝑦 = Amount of cargo transported by the project transportation mode in year y (tonne)

    𝐴𝐷 = Distance of the baseline trip route (km) 𝐸𝐹𝐵𝐿 = Baseline emission factor for transportation of cargo (g CO2/ tonne.km)

    To determine the emission factor, it is determined that the type of cargo transported is

    liquid petroleum products and would fall into the category Solid mineral fuels and

    petroleum products in Table 2 of the AM0090, from which the default factor CO2/

    ton.km is taken.

    However, as in Colombia commercial Diesel (B10) corresponds to a mixture of 90%

    Diesel fossil and 10% palm biodiesel by volume, this factor is corrected as follows,

    according to the AM0090 page 7:

    𝐸𝐹𝐵𝐿 = 76𝑔𝐶𝑂2

    𝑡𝑜𝑛. 𝑘𝑚∗

    𝐸𝑛𝑒𝑟𝑔𝑦 𝑐𝑜𝑛𝑡𝑒𝑛𝑡𝑓𝑜𝑠𝑠𝑖𝑙

    𝐸𝑛𝑒𝑟𝑔𝑦 𝑐𝑜𝑛𝑡𝑒𝑛𝑡𝐵10 = 68.99

    𝑔𝐶𝑂2𝑡𝑜𝑛. 𝑘𝑚

    5.2. Project emissions calculation

    Project emissions are calculated according to the AM0090 equation 5.

    𝑃𝐸𝑦 = (𝑃𝐸𝐹𝐶,𝑦 + 𝑃𝐸𝐸𝐶,𝑦) ∗ 𝐹𝑅𝑇,𝑃𝐽,𝑦 + 𝑃𝐸𝐶𝑅,𝑦

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    30

    Where:

    𝑃𝐸𝐹𝐶,𝑦 = Project emissions from fossil fuel combustion in the project activity in year y (tCO2)

    𝑃𝐸𝐸𝐶,𝑦 = Project emissions from electricity consumption in the project activity in year y (tCO2)

    𝐹𝑅𝑇,𝑃𝐽,𝑦 = The factor to account for non-empty return trips in the project scenario in year y (%)

    𝑃𝐸𝐶𝑅,𝑦 = Project emissions from transportation of cargo in complementary routes in trucks in year y (tCO2)

    The factor 𝑃𝐸𝐹𝐶,𝑦 is equivalent to the term 𝑃𝐸𝐹𝐶,𝑗,𝑦 of Tool03 and is quantified according

    to Equation 1 of Tool03:

    𝑃𝐸𝐹𝐶,𝑗,𝑦 = ∑ 𝐹𝐶𝑖,𝑗,𝑦 ∗ 𝐶𝑂𝐸𝐹𝑖,𝑦𝑖

    Where:

    FCi,j,y = Quantity of fuel type i combusted in process j during the year y (Nm3)

    COEFi,y = CO2 emission coefficient of fuel type i in yeary (tCO2 /Nm3)

    The CO2 emission coefficient of the fuel is calculated according to option B based on

    calorific value and an emission factor, according to Tool03 equation 4:

    𝐶𝑂𝐸𝐹𝑖,𝑦 = 𝑁𝐶𝑉𝑖,𝑦 ∗ 𝐸𝐹𝐶𝑂2,𝑖,𝑦

    Where:

    𝑁𝐶𝑉𝑖,𝑦 = Weighted average net calorific value of the fuel type i in year y (GJ/ Nm3)

    𝐸𝐹𝐶𝑂2,𝑖,𝑦 = Weighted average CO2 emission factor of fuel type i in year y (tCO2/GJ)

    This applies to the following processes j: Fuel of the tugs of the river route,

    corresponding to Marine Diesel, and fuel consumption for the operation of ITBB, which

    corresponds to both commercial Diesel, 90% ACPM and 10% palm biodiesel, as well as

    gasoline (E10). Therefore, since this is a mitigation project, adjustments are made to the

    reported emission factors, so that the percentage of biodiesel or ethanol present in the

    mixture has a contribution of zero (0) tCO2/GJ.

    To determine the factor 𝑃𝐸𝐸𝐶,𝑦 is quantified according to equation 1 of Tool05:

    𝑃𝐸𝐸𝐶,𝑦 = ∑ 𝐸𝐶𝑃𝑗,𝑗,𝑦 ∗ 𝐸𝐹𝐸𝐹,𝑗,𝑦 ∗ (1 + 𝑇𝐷𝐿𝑗,𝑦)

    𝑗

    Where:

    𝐸𝐶𝑃𝑗,𝑗,𝑦 = Quantity of electricity consumed by the project electricity consumption source j in year y (MWh/año)

    𝐸𝐹𝐸𝐹,𝑗,𝑦 = Emission factor for electricity generation for source j in year y (tCO2/GJ)

    𝑇𝐷𝐿𝑗,𝑦 = Average technical transmission and distribution losses for providing electricity to source j in year y (%)

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    31

    To determine the term 𝐸𝐹𝐸𝐹,𝑗,𝑦 scenario A, option A1 of the Tool05 is selected. The

    values of the marginal greenhouse gas emission factor for the National Interconnected

    System (SIN) are taken from those reported by the Energy-Mining Planning Unit

    (UPME). For the term 𝑇𝐷𝐿𝑗,𝑦 the value recommended by the Tool05 in Table 3 of 20% is

    used.

    The term 𝐹𝑅𝑇,𝑃𝐽,𝑦 is calculated according to equation 6 of AM0090:

    𝐹𝑅𝑇,𝑃𝐽,𝑦 =𝑇𝑦

    𝑇𝑦 + 𝑇𝑅𝑇,𝑦

    Where:

    𝑇𝑦 = Amount of cargo transported by the project transportation mode in year y (tonne)

    𝑇𝑅𝑇,𝑦 = Amount of cargo transported by the project transportation mode in the return trips in year y (tonne)

    The term 𝑃𝐸𝐶𝑅,𝑦 is calculated according to the Tool03 and is equivalent to the term

    𝑃𝐸𝐹𝐶,𝑗,𝑦 of Tool03. This is quantified according to equation 1 of the tool.

    𝑃𝐸𝐹𝐶,𝑗,𝑦 = 𝐹𝐶𝑖,𝑗,𝑦 ∗ 𝐶𝑂𝐸𝐹𝑖,𝑦

    Where:

    FCi,j,y = Quantity of fuel type i combusted in process j during the year y (Nm3)

    COEFi,y = CO2 emission coefficient of fuel type i in year y (tCO2 /Nm3)

    In this case, process (j) corresponds to the fuel consumption by the trucks on the

    complementary routes. The amount of fuel is reconstructed from (i) the number of trips

    made on each of the complementary routes, recorded by Impala; (ii) the distance of each

    route, as determined by the Impala Land Transport team, and (iii) the average efficiency

    of the vehicles, applying a conservative assumption based on the performance reported

    by three route operators. To obtain the volume of fuel, we multiply the number of trips on

    the route by the kilometers of the route; the results of all routes are summed; and

    multiplied by vehicle efficiency in terms of consumption of gallons per kilometer.

    The CO2 emission coefficient of the fuel is calculated according to option B based on

    calorific value and an emission factor, according to Tool03 equation 4:

    𝐶𝑂𝐸𝐹𝑖,𝑦 = 𝑁𝐶𝑉𝑖,𝑦 ∗ 𝐸𝐹𝐶𝑂2,𝑖,𝑦

    Where:

    𝑁𝐶𝑉𝑖,𝑦 = Weighted average net calorific value of the fuel type i in year y (GJ/ Nm3)

    𝐸𝐹𝐶𝑂2,𝑖,𝑦 = Weighted average CO2 emission factor of fuel type i in year y (tCO2/GJ)

    The specific values for the commercial mixture with which the tanker trucks are fueled

    are adjusted 90% ACPM and 10% palm biodiesel.

    5.3. Leakage

    According to the methodology, these emissions are negligible and are counted as zero.

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    32

    5.4. Net emission reductions calculation

    The project's emission reduction is calculated in accordance with AM0090, equation 1:

    𝐸𝑅𝑦 = 𝐵𝐸𝑦 − 𝑃𝐸𝑦

    Where:

    ERy = Emission reductions in year y, tCO2

    5.5. Example of calculation

    I. Baseline emissions

    Baseline emissions, road transportation

    Description Parameter Units 2016

    Amount of cargo transported by the project in year

    y Ty Ton 578,204.95

    Distance of the baseline trip route AD km 1,557.87

    Baseline emission factor for transportation of cargo EFBL gCO2/Ton.km 68.99

    𝐵𝐸2016 = 578,204.95 Ton ∗ 1,557.87km ∗ 68.99gCO2

    Ton. km∗ 10−6 = 62,143 tCO2

    II. Project emissions

    Fuel consumption by project activity, i.e. river transport on barges and ITBB operation.

    Project emissions, fuel consumption at ITBB

    Description Parameter Units 2016

    Quantity of fuel type i (Commercial gasoline) combusted

    in process j during the year y FCgasoline,ITBB,y m3 3.79

    Quantity of fuel type i (Commercial Diesel) combusted in

    process j during the year y FCdiesel,ITBB,y m3 558.44

    Weighted average net calorific value of the fuel type i

    (Commercial gasoline) in year y NCVgasoline,y GJ/m3 32.0550

    Weighted average net calorific value of the fuel type i

    (Commercial Diesel) in year y NCVdiesel,y GJ/m3 35.9592

    Weighted average CO2 emission factor of fuel type i

    (Commercial gasoline) in year y EFCO2,gasoline,ITBB,y tCO2/GJ 0.0653

    Weighted average CO2 emission factor of fuel type i

    (Commercial Diesel) in year y EFCO2,diesel,ITBB,y tCO2/GJ 0.0680

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    33

    𝑃𝐸𝐹𝐶_𝐼𝑇𝐵𝐵,2016 = 3.79𝑚3 ∗ 32.0550

    𝐺𝐽

    𝑚3∗ 0.0653

    𝑡𝐶𝑂2

    𝐺𝐽+ 558.44𝑚3 ∗ 35.9592

    𝐺𝐽

    𝑚3

    ∗ 0.0680𝑡𝐶𝑂2

    𝐺𝐽= 1,372.69 𝑡𝐶𝑂2

    Project emissions, fuel consumption, river transport

    Description Parameter Units 2016

    Quantity of fuel type i (marine diesel) combusted in

    process j during the year y Fcmarino,river,y m3 12,966

    Weighted average net calorific value of the fuel type i

    (marine diesel) in year y NCVmarino,y GJ/m3 35.91

    Weighted average CO2 emission factor of fuel type i

    (marine diesel) in year y EFCO2,marino,river,y tCO2/GJ 0.0652

    𝑃𝐸𝐹𝐶_𝑟𝑖𝑣𝑒𝑟,2016 = 12,966𝑚3 ∗ 35.91

    𝐺𝐽

    𝑚3∗ 0.0652

    𝑡𝐶𝑂2

    𝐺𝐽= 30,358.96 𝑡𝐶𝑂2

    𝑃𝐸𝐹𝐶 , 2016 = 1,372.69 𝑡𝐶𝑂2 + 30,358.96 𝑡𝐶𝑂2 = 31,731.64 𝑡𝐶𝑂2

    Fuel consumption emissions from tankers that travel through complementary routes.

    Project emissions, fuel consumption complementary routes

    Description Parameter Units 2016

    Quantity of fuel type i (Commercial Diesel)

    combusted by trucks in the year x FCBL,CR,x m3 8,701.8

    Weighted average net calorific value of the fuel

    type i (Commercial Diesel) combusted by trucks in

    the year x

    NCVi,x GJ/m3 35.9592

    Weighted average CO2 emission factor of fuel type

    i (Commercial Diesel) in year y EFCO2,i,CR,x tCO2/GJ 0.0680

    𝑃𝐸𝐶𝑅,2016 = 8,701.8𝑚3 ∗ 35.9592

    𝐺𝐽

    𝑚3∗ 0.0680

    𝑡𝐶𝑂2

    𝐺𝐽= 21,265.93 𝑡𝐶𝑂2

    Emissions from electricity consumption at ITBB.

    Project emissions, electricity consumption at ITBB

    Description Parameter Units 2016

    Quantity of electricity consumed by the project

    electricity consumption source j in year y ECPj,ITBB,y MWh 3,846.26

    Average technical transmission and distribution losses TDLj,y % 20

    Emission factor for electricity generation for source j in

    year y EFEF,j,y

    tCO2/

    MWh 0.401

    𝑃𝐸𝐸𝐶,2016 = 3,846.26 𝑀𝑊ℎ ∗ 0.401𝑡𝐶𝑂2

    𝑀𝑊ℎ ∗ (1 + 20%) = 1,850.82 𝑡𝐶𝑂2

    Factor for accounting for non-empty return trips.

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    34

    Project emissions, return trips factor

    Description Parameter Units 2016

    Amount of cargo transported by the project in year y Ty Ton 578,205.0

    Amount of cargo transported by the project in the return trips in

    year y TRT,y Ton 337,624.5

    The factor to account for non-empty return trips in the project

    scenario in year y FRT,PJ,y % 63%

    𝐹𝑅𝑇,𝑃𝐽,2016 =578,205.0 𝑇𝑜𝑛

    578,205.0 𝑇𝑜𝑛 + 337,624.5 𝑇𝑜𝑛= 63%

    The project's emissions are:

    𝑃𝐸𝑦 = ( 31,731.64 𝑡𝐶𝑂2 + 1,850.82 𝑡𝐶𝑂2 ) ∗ 63% + 21,265.93 𝑡𝐶𝑂2 = 42,468 𝑡𝐶𝑂2

    Emission reductions are:

    ER2016 = 62,143 tCO2 − 42,468 tCO2 = 19,675 tCO2

    6. Monitoring the Data information management system and data controls

    6.1. Data and parameters available in validation

    Data / Parameter: 𝐴𝐷

    Data unit: km

    Description: Distance of the baseline trip route

    Source of data:

    Measurements from Ground Transport, Impala Terminals

    of the land routes that would have been used in the

    absence of the project.

    Value applied: 1,557.87

    Justification of choice of

    data or description of

    measurement methods and

    procedures applied:

    Weighted average of the distances of the baseline routes

    from the year before the start of the project, but with

    Cartagena as the destination. Weighting is done by the

    cargo carried by each route.

    Purpose of Data: Baseline emission calculation

    Comments:

    Data / Parameter: 𝑁𝐶𝑉𝑖,𝑦

    Data unit: GJ/m3

    Description: Weighted average net calorific value of the fuel type i in

    year y

    Source of data: All fuels except for ACPM: Colombian Fuel Emission

    Factors – FECOC 2016 (UPME)

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    35

    ACPM: Colombian Fuel Emission Factors – FECOC 2015

    (UPME)

    Value applied:

    Process j Fuel i 𝑵𝑪𝑽

    ITBB operation Commercial gasoline 32.0550

    ITBB operation Commercial Blended Diesel 35.9592

    Tugboats Diesel Marino 35.91

    Complementary

    routes Commercial Blended Diesel 35.9592

    The same value is taken for all years of the project.

    Justification of choice of

    data or description of

    measurement methods and

    procedures applied:

    Official data of national validity.

    Weighting is made by volumetric biofuel percentages

    (%𝑏𝑐𝑖), this requires considering density (𝜌𝑖) and calorific value per unit of mass (𝐿𝐻𝑉𝑚𝑖).

    𝑁𝐶𝑉𝑖 = 𝜌1 ∗ 𝐿𝐻𝑉𝑚1 ∗ %𝑏𝑐1 + 𝜌2 ∗ 𝐿𝐻𝑉𝑚2 ∗ %𝑏𝑐2 The volumetric percentages are:

    - Commercial gasoline (E10): 90% Gasoline Motor, 10% Ethanol

    - Commercial blended Diesel: 90% ACPM, 10% Palm Biodiesel

    Purpose of Data: Calculation of project emissions

    Comments:

    Data / Parameter: 𝐸𝐹𝐶𝑂2,𝑖,𝑗,𝑦

    Data unit: tCO2/GJ

    Description: weighted average CO2 emission factor of fuel type i in

    year y

    Source of data:

    All fuels except for ACPM: Colombian Fuel Emission

    Factors – FECOC 2016 (UPME)

    ACPM: Colombian Fuel Emission Factors – FECOC 2015

    (UPME)

    Value applied:

    Process j Fuel i 𝑬𝑭𝑪𝑶𝟐

    ITBB operation Commercial gasoline 0.0653

    ITBB operation Commercial Blended Diesel 0.0680

    Tugboats Diesel Marino 0.0652

    Complementary

    routes

    Commercial Blended Diesel 0.0680

    The same value is taken for all years of the project.

    Justification of choice of Official data of national validity.

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    36

    data or description of

    measurement methods and

    procedures applied:

    A volume emission factor is calculated (𝐸𝐹𝑣𝑖) from density (𝜌𝑖), low heating value (𝐿𝐻𝑉𝑖) emission factor per unit of mass (𝐸𝐹𝑚𝑖).

    𝐿𝐻𝑉𝑖 ∗ 𝜌𝑖 ∗ 𝐸𝐹𝑚𝑖 = 𝐸𝐹𝑣𝑖 The corresponding volumetric percentages are applied to

    this factor, considering that the contribution of biofuels is

    zero as it is a mitigation project:

    - Commercial gasoline (E10): 90% Gasoline Motor, 10% Ethanol

    - Commercial blended Diesel: 90% ACPM, 10% Palm Biodiesel

    Subsequently, it is returned to an energy base, as indicated

    by the methodology.

    Purpose of Data: Calculation of project emissions

    Comments:

    Data / Parameter: 𝑇𝐷𝐿𝑗,𝑦

    Data unit: %

    Description: Average technical transmission and distribution losses for

    providing electricity to source j in year y

    Source of data: AM-Tool05- v3.0 – Clean Development Mechanism

    Value applied: 20%

    Justification of choice of

    data or description of

    measurement methods and

    procedures applied:

    Selecting Scenario A, option A1 of the tool. No up-to-date

    country data are available.

    Purpose of Data: Calculation of project emissions

    Comments:

    6.2. Monitored data and parameters

    Data / Parameter: 𝐹𝐶𝑔𝑎𝑠𝑜𝑙𝑖𝑛𝑒,𝐼𝑇𝐵𝐵,𝑦

    Data unit: m3

    Description: Quantity of fuel type i = gasoline, combusted in the

    ITBB operation during the year y

    Source of data Gasoline purchase invoices.

    Values applied:

    Year Fuel i (m3)

    Gasoline (E10)

    19/06/2015-31/12/2015 4.14

    2016 3.79

    2017 5.22

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    37

    2018 5.43

    2019 8.58

    2020 11.13

    2021 15.42

    2022 20.53

    2023 23.22

    2024 23.22

    01/01/2025-18/06/2025 10.83

    Measurement methods and

    procedures:

    Tankers delivering fuel have a meter that records the

    value in gallons. They issue a strip with which the

    purchase order is generated. The fuel seller oversees

    the tanker trucks.

    Evidence is in Navitrans software and invoices, stored

    in the “Accounts payable” area.

    Monitoring frequency: Every time a purchase is made.

    QA/QC procedures:

    In the accounting area, a review of the consistency of

    the value is made, to detect gaps in the fuel

    measurement process.

    Purpose of Data: Calculation of project emissions

    Any comment:

    This data is considered to be of low uncertainty, being

    measured directly by the fuel seller and being part of

    the company's accounting management.

    Data / Parameter: 𝐹𝐶𝑑𝑖𝑒𝑠𝑒𝑙,𝐼𝑇𝐵𝐵,𝑦

    Data unit: m3

    Description: Quantity of fuel type i = diesel, combusted in the ITBB

    operation during the year y

    Source of data: Diesel purchase invoices.

    Values applied:

    Year

    Fuel i (m3)

    ACPM (Commercial

    blended Diesel)

    19/06/2015-31/12/2015 147.92

    2016 558.44

    2017 519.60

    2018 541.03

    2019 854.34

    2020 1107.97

    2021 1534.87

    2022 2044.44

    2023 2311.65

    2024 2311.65

    01/01/2025-18/06/2025 1078.77

    Measurement methods and

    procedures:

    Tankers delivering fuel have a meter that records the

    value in gallons. They issue a strip with which the

  • GHG Report Template for CSA Standards GHG CleanProjects® Registry

    Version 1.0 – September 2009

    38

    purchase order is generated. The fuel seller oversees

    the tanker trucks.

    Monitoring frequency Evidence is shown in Navitrans software and invoices

    stored in the "Accounts Payable" area.

    QA/QC procedures: Every time a purchase is made.

    Purpose of Data

    In the accounting area, a review of the consistency of

    the value is made, to detect gaps in the fuel

    measurement process.

    Any comment: Calculation of project emissions

    Data / Parameter: 𝐹𝐶𝑚𝑎𝑟𝑖𝑛𝑜,𝑟𝑖𝑣𝑒𝑟,𝑦

    Data unit: m3

    Description: Quantity of fuel type i = marine diesel, combusted in

    the river operation during the year y

    Source of data: Fuel purchase invoices by tanker trucks and barges

    (MAGfuel)

    Values applied:

    Year Fuel i (m3)

    Marine Diesel

    19/06/2015-31/12/2015 5,650.51

    2016 12,966.11

    2017 14,489.24

    2018 15,086.85

    2019 23,823.78

    2020 30,896.52

    2021 42,800.71

    2022 57,010.38

    2023 64,461.81

    2024 64,461.81

    01/01/2025-18/06/2025 30,082.18

    Measurement methods and

    procedures:

    When the purchase is made in tankers trucks, the fuel

    seller is in charge of the measureme