University Of Central Florida Big Beam Competition 2012 Design Team 1 Mohamed Alrowaimi Nader Mehdawi Walid Hamad Faculty Advisor Dr. Hae-Bum Yun Sponsoring Producer Finfrock Industries Inc. 1
Oct 26, 2014
University Of Central Florida
Big Beam Competition 2012
Design Team 1
Mohamed AlrowaimiNader MehdawiWalid Hamad
Faculty AdvisorDr. Hae-Bum Yun
Sponsoring Producer
Finfrock Industries Inc.
1
TABLE OF CONTENTS
i Cover Page……………………………………………………………….. 1
ii Table of Contents………………………………………………………… 2
iii Acknowledgements………………………………………………………. 3
1 The Beam Configuration ………………………………………………… 4
2 Cross Section Drawings………………………………………………… 5
3 Design Parameters………………………………………………………. 6
4 Beam Predictions………………………………………………………… 7
4.
1
Crack Prediction……………………………………………………. 7
4.
2
Deflection Prediction……………………………………………….. 8
5 Stress in pre-stressing strands…………………………………………… 8
6 Partial Losses…………………………………………………………….. 8
7 Flexural Design and Analysis ………………………………………….... 9
8 Shear Design and Analysis………………………………………………. 10
9 Anchorage Design………………………………………………………... 11
10 Concrete Mix Design Criteria…………………………………………..... 11
11 Cost Estimation…………………………………………………………... 11
12 Conclusion………………………………………………………………. 13
12 Appendix…………………………………………………………………. 14
2
ACKNOWLEDGEMENTS
The Project Team extends his gratitude to Dr. Hae-Bun Yun for introducing us to this contest, guiding and advising us to have a good design.
Next, we would like to thank Joseph Lord, Executive Director of the Florida Pre-stressed Concrete Association (FPCA) for helping us to participate in the big beam contest for the first time.
Also, we would like to thank Mr. Allen R Finfrock, Vice President of FINFROCK Industries Inc., in Orlando, Fla., for their support and sponsoring our prestressed beam.
Last but not least, we thank the Precast/Prestressed Concrete Institute (PCI) for organizing and sponsoring the 2012 PCI Big Beam Contest.
3
1. The Beam Configuration with the shear and the moment diagram
4
2. Cross Section Drawings
Section
Elevation
5
2' 2' 2'2'2'4'2'
#3 Stirrups ,JYP
9.05"
3"
2.95"
6.00"
9.00"
N.A
10.00"
6.00"
1'-3.00"4.00"
6.55"
4.45"
N.A
#3 Stirrups ,JYP
1/2" Ø, 270K Law lax STRANDS
2"2"2"
10.00"
1'-3.00"
2.95"
3"4.00"
3. Design Parameters
f c, =6000 psi
f ci, =0.8 f c
, =4800 psi
f ci=0.6 f c, =2880 psi
f c=0.45 f c, =2700 psi
f ti=3√ f ci, =207.84 psi at the midspan
f ti=6√ f ci, =415.69 psi at the support
f t=12√ f c, =929.52 psi
f y=60,000 psi
M L=10,000∗6∗12=720,000∈−lb Max unfactored moment at midspan
(4) 1/2 270 ksi low lax tendon∅
f pu=270,000 psi
f pi=0.7 f pu=189,000 psi
Section Properties and Parameters
A=114¿2
I=2143.18¿4
c t=6.55∈¿
cb=8.45∈¿
r2=I / A=18.8¿2
6
St=I /c t=327.1¿3
Sb=I /cb=253.7¿3
W D= 11412∗12
∗150=118.7 plf
M D=W Dl2
8=
118.7(16)2
8∗12=45,600∈−lb
Total Losses of the selected T−Section=12.7 %
γ=1−0.127=0.873
4. Beam Predictions
All the beam predictions were computed either manually or by using a Excel spreadsheet. A few
numbers of rectangular and T beam sections were checked on the cracking load. So, the design
was initially dominated by the restriction of that the beam shall not crack under the total applied
service load of 20 kips. Then the selected T-beam section was designed for the flexural load at
transfer and service. A detailed calculation and checks for the flexural bea
m Design and analysis will be presented in Section 7.
4.1. Crack Prediction
It is important to evaluate the first cracking load. Hence, the moment due to the applied live load
(20 kip) and the self-weight of the T-beam were calculated. Then this moment were compared to
the cracking moment to get the exact cracking applied service load.
The predicted design cracking load = 20 kip
7
M cr
M T
=1.01 the beamwill crack at total applied load of 20 kip
As assumed above, the beam will crack at 20 kips or more. The detailed calculations are shown
in appendix.
4.2 Deflection Prediction
The deflection calculation was done based on uncracked prestressed section since the
assumptions of elastic behavior are more applicable than the cracked section. So, the deflection
was calculated at transfer due to the beam’s self-weight and at service due to the total load,
beam’s self-weight and the live load. Also, the camber due to the prestressing force was
calculated and subtracted from the calculated deflections. A summary of the deflections at
transfer and service is shown in the next table.
Loading Stage Deflection (in)
At transfer (midspan) 0.05
At service (midspan) 0.43
The predicted max. deflection = 0.43 in at the Midspan . The detailed deflection calculation is
presented in the appendix.
5. Stress in Prestressing Strands
The initial prestressing stress: f pi=0.7 f pu=189,000 psi
Hence, the initial prestressing force Pi=115688 lb
The effective prestressing stress: f pe=γ f pi=164,997 psi
Hence, the effective prestressing force Pe=100,978.164 lb
6. Partial Losses
The Partial Losses were calculated for the pretension tendon and the results are shown in the
following table:
Stress Level at various Stages Steel Stress (psi) %
8
After tensioning (0.7 Fpu) 189,000 100Elastic shortening loss -10325 -5.5Creep loss -6757.95 -3.6Shrinkage loss -3690 -1.95Relaxation loss -3126.81 -1.65Final Net Stress (FPe) 165100.24 87.3
The percentage of total losses = 12.7 % for this pre-tensioned beam.
7. Flexural Design and Analysis
The following prestressed beam was designed to carry at least total factored load of 32 kips. In
this design, the service load design method was used.
A several section trails were studied with:
Different shapes and dimensions (rectangular and T-Beam)
Different tendon numbers
Different eccentricities
All these sections were checked to choose the best section in weight, cost and strength.
The following spread sheet table shows the most effective Beam. Also, the stresses for the
selected T-Beam were checked on both transfer and service stage as shown in the following
table.
The design was for number of 4 - ½”∅ 270 ksi , low lax straight tendons ,e = 4 “
9
Spreadsheet Calculation of the most effective beamCalculation Sheet
Trial Section # 5
I-Beam
Section Properties Number of Tendons
N# 4
Area (sq in) 114
I (in^4) 2143.184 Prestressing Force
Ct (in) 6.5526 Losses % 12.70
Cb (in) 8.4474 Pi (psi) 115668
r^2 (sq in) 18.79986 Pe (psi) 100978.164
St (cu in) 327.0739
sb (cu in) 253.7093
Eccentricity Support Midspane (in) 4
Transfer LoadFt 399.948 260.5299
Psi
Loading MomentsFb
-2838.26 -2658.53 Psi
Md (in-lb) 45600
Ml (in-lb)720000
Service LoadFt 349.1546 -1991.6
Psi
Mt (in-lb)765600
Fb
-2477.8 179.3647 Psi
10
6.00"
9.00"
N.A
10.00"
6.00"
1'-3.00"4.00"
6.55"
4.45"
8. Shear Design and Analysis
The shear reinforcement was deigned to carry the shear due to the external load. In this
design, it is found that the shear due to the external load Vu is bigger than half of the shear
capacity Vc.
V u .>V c /2
Hence, the shear reinforcement was taken to be the min as Per ACI, (Min Av/S), which came
to 2 # 3 closed tie stirrups, spaced at 2 in center to center.
9. Anchorage Design
The anchorage was reinforced based on the empirical expression by Mattock.
This was found to be 2 #3 closed tie stirrups.
10.Concrete Mix Design Criteria
In our design we will adopt the concrete mix design done by Finfrock Industries Inc. since they
will produce the concrete at their plant.
Self-compacted concrete
Type 3 cement for high early strength
Water cement ratio is 0.38
According to Finfrock the mix will give concrete comprehensive strength of 6000 psi after two
weeks.
11
11.Cost Estimation
The major challenge in the design is how to design a safe member with the least cost and build
an economically competitive structure of suitable strength performance which would satisfy the
requirements. The need for the most efficient cost design solution has led to the need to carry out
accurate cost estimation and a structural cost optimization.
Self-manufacturing costs are proposed to be defined as a sum of:
- The material costs,
- The power consumption costs
- The labor costs.
In our contest will be responsible of just the material costs. So, we have to break down the
material in the beam. Our beam’s materials are:
Concrete volume (yd³) 0.469135
4 strands 0.5 in dia. Length (ft) 64
#3 stirrups length (ft) 8.7
#3 reinforcement weight (lb/ft) 0.376
Using cost price given in the Big Beam contest specifications, we can give a good predicted as
shown:
Material Unit Cost Amount Cost ($)
Concrete $100/cu yd 0.469135 (cu yd) 46.9135
Pre-stressing Strand
$0.30/ft 64 (ft) 19.2
Steel:A615/A706
$0.45/lb 3.2712 (lb) 1.472
Total Cost 67.59
12
12.Conclusion
During the design of the big beam, our team has tried several sections with different shapes,
dimensions, number of tendons and eccentricities to come with the most effective design. The
beam in this report was designed to carry a total factored live load of 32 kips and must not have a
total peak applied load more than 39 kips.
Also, this beam was designed to have the first crack at load equal or bigger than 20 kips (the total
applied service load).
The selected T-section was found to be the most effective section that meets all the requirements
of the contest:
Self-weight =118.7 plf with total weight of 1899.2 lb
Material cost = $ 67.59
4 - ½”∅ 270 ksi lowlax straight tendons
e = 4 “
13
Appendix
Five Trial Sections:-
Trial #1
Calculation Sheet
Trial Section # 1Rectangular 15*10
Section Properties Number of Tendons
N# 4
Area (sq in) 150
I (in^4) 2812.5 Prestressing ForceCt (in) 7.5 Losses % 12.70Cb (in) 7.5 Pi (psi) 115668r^2 (sq in) 18.75 Pe (psi) 100978.16St (cu in) 375sb (cu in) 375
Eccentricity Support Midspane (in) 4
Transfer LoadFt 462.672 302.672 Ps
i
Loading Moments Fb -2004.912 -1844.912 Psi
Md (in-lb) 60000
14
Ml (in-lb)720000
Service LoadFt 403.91266 -1676.0873 Ps
i
Mt (in-lb)780000 Fb -1750.288 75.088 Ps
i
Trial #2
Calculation Sheet
Trial Section # 2Rectangular 15*6
Section Properties Number of Tendons
N# 4Area (sq in) 90I (in^4) 1687.5 Prestressing ForceCt (in) 7.5 Losses % 12.70Cb (in) 7.5 Pi (psi) 115668r^2 (sq in) 18.75 Pe (psi) 100978.2St (cu in) 225sb (cu in) 225
Eccentricity Support Midspane (in) 4
Transfer LoadFt 771.12 611.12 Ps
i
Loading MomentsFb
-3341.52 -3181.52 Psi
Md (in-lb) 36000
Ml (in-lb)720000
Service LoadFt 673.1878 -2686.81 Ps
i
Mt (in-lb)756000
Fb
-2917.15 18.48 Psi
15
Trial #3
Calculation Sheet
Trial Section # 3I-Beam
Section Properties Number of Tendons
N# 4Area (sq in) 150I (in^4) 5312.5 Prestressing ForceCt (in) 7.5 Losses % 12.70Cb (in) 12.5 Pi (psi) 115668r^2 (sq in) 35.41667 Pe (psi) 100978.2St (cu in) 708.3333sb (cu in) 425
Eccentricity Support Midspane (in) 4
Transfer LoadFt -117.936 -202.642 Ps
i
Loading MomentsFb
-1859.76 -1718.58 Psi
Md (in-lb) 60000
Ml (in-lb)720000
Service LoadFt -102.958 -1204.13 Ps
i
Mt (in-lb)780000
Fb
-1623.57 -24.4659 Psi
16
Trial #4
Calculation Sheet
Trial Section # 4I-Beam
Section Properties Number of Tendons
N# 4Area (sq in) 110I (in^4) 2734.924 Prestressing ForceCt (in) 6.5909 Losses % 12.70Cb (in) 8.4091 Pi (psi) 115668r^2 (sq in) 24.86295 Pe (psi) 100978.16St (cu in) 414.9546sb (cu in) 325.2339
Eccentricity Support Midspane (in) 4
Transfer LoadFt 63.46702 -42.5687 Ps
i
Loading MomentsFb
-2474.11 -2338.82 Psi
Md (in-lb) 44000
Ml (in-lb)720000
Service LoadFt 55.40671 -1785.76 Ps
i
Mt (in-lb)764000
Fb
-2159.9 -125.031 Psi
17
Trial #5
Calculation Sheet
Trial Section # 5I-Beam
Section Properties Number of Tendons
N# 4Area (sq in) 114I (in^4) 2143.184 Prestressing ForceCt (in) 6.5526 Losses % 12.70Cb (in) 8.4474 Pi (psi) 115668r^2 (sq in) 18.79986 Pe (psi) 100978.164St (cu in) 327.0739sb (cu in) 253.7093
Eccentricity Support Midspane (in) 4
Transfer LoadFt 399.948 260.5299 Ps
i
Loading MomentsFb
-2838.26 -2658.53 Psi
Md (in-lb) 45600
Ml (in-lb)720000
Service LoadFt 349.1546 -1991.6 Ps
i
Mt (in-lb)765600
Fb
-2477.8 179.3647 Psi
18
Check for stresses for our selected beam section at 32, and 39 kips
For applied 32 kip load, the stresses are:
For applied 39 kip load, the stresses are:
19
Partial Losses of Pre-stressed Beam
1. Elastic Shortening:
∆FPES = n . FCS
Where,
FCS = −PiAc
¿) + Md e
Ic and n =
E s
Eci
e = 4 in and MD = 45600 in-lb
so,
FCS =-1687.1 psi
Modular Ratio n = E s
Eci =
270000004415000
= 6.12
so,
∆FPES = n . FCS
= 6.12 * 1687.1 = 10325 psi
2. Creep Losses:
∆FPCR = Ct
EPS
Ec FCS
Where;
Ct = t 0.6
10+t 0.6 Cu = 140.6
10+140.6 *2 = 0.655
∆FPCR = 0.655 * 270000004415000 * 1687.1 = 6757.95 psi
3. Shrinkage Losses:
20
Time-dependent method
∆FPSH = ϵSH * ES
Where:
ϵSH = t
35+t (ϵSH)u
= 7
35+7 * 820*10-6
= 1.37*10-4
So,
∆FPSH = 1.37*10-4 * 10-6 = 3690 psi
4. Relaxation:
ACI-ASCE method
∆FPR = {kre - J∆(∆FPES + ∆FPCR + ∆FPSH )}C
= {5000 – 0.04(10325+6757.95+3690)}*0.75
= 3126.81 psi
Total Losses
∆FPT = ∆FPES + ∆FPR+ ∆FPCR + ∆FPSH
∆FPT = 10325+6757.95+3690+3126.81
= 23899.76 psi
Stress Level at various Stages Steel Stress (psi) %
After tendioning (0.7 Fpu) 189,000 100Elastic shortening loss -10325 -5.5Creep loss -6757.95 -3.6Shrinkage loss -3690 -1.95Relaxation loss -3126.81 -1.65Final Net Stress (FPe) 165100.24 87.3
The percentage of total losses = 12.7 % for this pre-tensioned beam based on 14 days.
21
Shear Design Calculation
Calculate Vu due to factored loads Pl= 10 kips Pu=16 kips WD=0.118 kips/ft Wu=0.1425 kips/ft
Calculate Vu at 1/2dpFrom shear force diagram Vu= 17.062 Kips
Nominal shear strength Vc :
Req Vn=Vu∅
=17.0620.75
=22.75 kips
ˇ0.4 fpu<fPe108000 psi<160650 psi
Use ACI alternate method
Vc=(0.6 λ√F c '+700vudpMu )Bwdp ≥2 λ√ F c ' bwdp≤ 5 λ√ f c ' bwdp
Caculate Muat dp/2 :Mu=9.37k . ft¿moment daigramvudpMu
=17.062∗13(9.234∗12 )
=2>1 use1
min vc=2 λ√ f c ' bw dp=2∗1∗√6000∗6∗13=12083.70 Ibmax vc=5 λ√ fc ' bw dp=30209.27 Ib
Vc=(0.6 λ√ f c '+ 700∗vudpMu )bwdp=58225.11 Ib>Vc max
useVcmax=30209.27 Ib
22
vc> vu∅
vc2
=30209.272
=15104.6235 k
minAvs
= Apsfpu80 fytdp √ dp
bw
minAvs
=4∗0.193∗2700080∗6000∗13 √ 13
6=0.00389
use ¿3 Av=2∗0.11=0.22Avs
=0.00389
S=56.65∈¿50∈¿
Defection Calculation
Transfer StageDeflection due to Dead load (Self weight)
∆D= 5 w l4
384 Eci I
Eci=3.94 x 106 psi∆ D=0.21∈↓Camber due prestreesing force:
∆C=Pe . e . l2
8 E I∆C=0.161∈↑At service load of uncracked beam
∆D+L=5 w l4
384 E c I+ P.b
24 E I∆D+L=0.19+0.246 ∆D+L=0.43∈¿ The maximum deflection at the midspan
Crack Calculation
Mcr = fr * Sb + Pe ( e + r2/cb )
Mcr = 7.5 (6000)1/2 *253.709 + 100978.2 (4+18.8/8.45)
Mcr = 775965.97 in-lb
23
Mcr/MT = 775965.97/765600
Mcr/MT = 1.01 O.K.
24