Farley Junior School Luton New Build and Refurbishment Works
2
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
Page 1: Farley junior school case study

Farley Junior School

Luton

New Build and Refurbishment Works

Page 2: Farley junior school case study

To support the increase in pupil numbers from 282 to 360 4-11 year olds at Farley Primary School,

our Design Team were commissioned to;

Construct three new classrooms, a group room and additional toilets

Extend two existing classrooms to 60m2 and extend the existing staff room

Provide six additional car parking spaces

Extend the existing hard play area

Contract Value: £505,000