Top Banner

of 33

DUE Mar16 rev2.pptx

Jul 05, 2018

Download

Documents

electroart
Welcome message from author
This document is posted to help you gain knowledge. Please leave a comment to let me know what you think about it! Share it to your friends and learn new things together.
Transcript
  • 8/15/2019 DUE Mar16 rev2.pptx

    1/33

    In association with:

    Speaking of Risks: An Update

    to the NRS097-2 and other Technical Requirements

    (SSEG)

    Background to SSEG

    Specification Development

    Dr Gerhard Botha

    2016/03/31

  • 8/15/2019 DUE Mar16 rev2.pptx

    2/33

    Overview

    • Background to SSEG in South Africa

    • Inverter Specifications

    • Small Generator Specifications

    • Planning Framework

    • Type Testing

    • Policies and Procedures

    • Installation Standards

    • Tariffs

  • 8/15/2019 DUE Mar16 rev2.pptx

    3/33

    Background

    • Small Scale Embedded Generation

    • SA development since 2007

    • Municipalities received many requests for solar PVinstallations

    • Approached Eskom for unified requirements viaNRS

    • First edition published Dec 2010 – Based on IEC61727

    • NERSA “approval” of such installations formunicipalities in Sep 2011 – Municipalities need to keep proper records and

    report to NERSA, what, where, how much etc.;

     – Comply with requirements from NRS 097-2-1;

  • 8/15/2019 DUE Mar16 rev2.pptx

    4/33

    Background

    • Then happened load-shedding… 

    • Co-generation

    • Tariff

    • Requirements –  Eskom response via internal

    standard• “Distribution standard for the interconnection of

    embedded generation” 

    • Minimum technical and statutory requirements forthe connection of embedded generators tomedium-voltage and high-voltage utilitydistribution networks

    • MV and HV

  • 8/15/2019 DUE Mar16 rev2.pptx

    5/33

    NRS 097

    • Grid interconnection of embeddedgeneration

    • Part 1: Distribution standard for the

    interconnection of embedded generation – To be based on Eskom standard

    • Still undeveloped… 

    >100kVA• SA Grid Code for Renewable Power

    Plants (RPP Grid Code)

  • 8/15/2019 DUE Mar16 rev2.pptx

    6/33

  • 8/15/2019 DUE Mar16 rev2.pptx

    7/33

    NRS 097-2

    • Grid interconnection of embedded generation

    • Part 2: Small-scale embedded generation

    • Section 1: Utility interface

     –Technical requirements for a generator toconnect to the utility network

     – Not an inverter specification“Device Independent” 

     – Not a generator specificationInterface Document

     – Describe the requirements at the utility interface

  • 8/15/2019 DUE Mar16 rev2.pptx

    8/33

    NRS 097-2

    • Connected to LV (

  • 8/15/2019 DUE Mar16 rev2.pptx

    9/33

    Section 1 New Additions

    • Controllability requirements

     – Larger than 100kVA

    • Ramp-up after abnormal conditions

    • Communication requirements

     – Need local control

     –

    Number of installations cannot be individuallycontrolled

  • 8/15/2019 DUE Mar16 rev2.pptx

    10/33

    Section 1 New Additions

    • Power factor requirements updated

    • A1 and A2 pf > 0.98

    • A3 pf > 0.95

    • May operate anywhere in the shaded region

  • 8/15/2019 DUE Mar16 rev2.pptx

    11/33

    Section 1 New Additions

    • Safety disconnect requirements

    • Abnormal Voltages

    Voltage range(at point of connection)  Maximum trip timeS 

    V < 50 %  0,2 s 

    50 % ≤ V < 85 %  10 s 

    85 % ≤ V ≤ 110 %  Continuous operation 

    110 % < V < 115 %  40 s 

    115% ≤ V < 120%  2 s 

    120 % ≤ V  0,16 s 

    NOTE If multi-voltage control settings are not possible, the more

    stringent trip time should be implemented, e.g. 2 s between 110%

    and 120% of voltage.

  • 8/15/2019 DUE Mar16 rev2.pptx

    12/33

    Section 1 New Additions

    • Safety disconnect requirements

    • Abnormal Frequency

  • 8/15/2019 DUE Mar16 rev2.pptx

    13/33

    Section 1 New Additions

    • Ride-through requirements (Also RPP Grid

    Code)

     – Category A1 and A2

     – Dip type Y and X1 (NRS 048-2)

    20s

    120%

    110%

    90%Y

    80%

      Z1

    S

    70%

    X160%

    X2

      Z2

    40%

    T

    0%150 600 3000 ms

  • 8/15/2019 DUE Mar16 rev2.pptx

    14/33

    Section 1 New Additions

    • Ride-through requirements (Also RPP Grid

    Code)

     – Category A3

     – Same as category B (and C excluding Area D)

    20s

    110%

    120%

    150 600 3000 ms

    40%

    0%

    60%

    Y

      Z1

    SX1

    X2

      Z2

    T

    70%

    80%

    90%

     Area A

     Area B

     Area C

     Area D

  • 8/15/2019 DUE Mar16 rev2.pptx

    15/33

    Section 1 New Additions

    • Power Quality

    • Limits for flicker and voltage unbalance

    • Pst = 0,35;

    • Plt = 0,30;

    • Maximum unbalance between phases

     – < 4.6 kVA

     – Two- and three-phase connections

  • 8/15/2019 DUE Mar16 rev2.pptx

    16/33

    Section 1 New Additions

    • EMC

    • Smart meter and residential equipment

    interference

    • SANS/IEC 50065-1

    • CISPR 11 Class B

  • 8/15/2019 DUE Mar16 rev2.pptx

    17/33

    Section 1 New Additions

    • Fault Level

    5th percentile of MV

  • 8/15/2019 DUE Mar16 rev2.pptx

    18/33

    NRS 097-2

    • Section 3: Simplified utility connection criteria for low-voltage connected generators

    •  For use by utilities – Customers can establish what would be easy to connect,

    e.g. smaller than 25% of ADMD/Breaker size

     – Maximum size as a function of cable parameters anddistance from transformer

    • Flowchart to consider connection without detailedstudies

    • When SSEG connection request complies with simplifiedchecks, can be connected

    • Principle of fairness

    • Eskom would not allow all these connections at this time – Pilot project (dedicated connections)

  • 8/15/2019 DUE Mar16 rev2.pptx

    19/33

  • 8/15/2019 DUE Mar16 rev2.pptx

    20/33

    NRS 097-2

    • VDE 4105 stipulates 3% max voltage

    rise due to all SSEG connected

     – Implicit in planning flowchart

  • 8/15/2019 DUE Mar16 rev2.pptx

    21/33

    Voltage profiles with no generation

    Low load1% rise

    limit

    Peak load

    15% drop

    limit

    105

    104.5

    109

    108

    90

    90

    95

    100

    105

    110

    0 5

       V  o   l   t  a  g  e   (   %   )

    Distance (km)

  • 8/15/2019 DUE Mar16 rev2.pptx

    22/33

    Voltage profiles with generation

    105

    102

    103.5

    96.5

    105 106.5

    112.5

    114.5

    95

    97.5

    100

    102.5

    105

    107.5

    110

    112.5

    115

       V  o   l   t  a  g  e   (   %

       )

    Distance (km) peak loadlow load

    Network can absorb significantly less power than it can supply

  • 8/15/2019 DUE Mar16 rev2.pptx

    23/33

    NRS 097-2

    • Part 2: Embedded generator requirements – Type Testing

    • How to prove the generator complies with requirements ofpart 1

    • DRAFT

    Review international standards again –  International exposure• No single document that will fulfil the requirements for SSEG

    connection and type testing for LV networks in South Africa• Specific comparison for utility interface:

     – VDE 4105

     – EN 50438

     –IEC 61727, 61000-series, other

     – ER G83/1-1 and G59/2

     – IEEE 1547 / UL 1741

    • Align with international best practices!

  • 8/15/2019 DUE Mar16 rev2.pptx

    24/33

    NRS 097-2

    • Section 4: Procedures for

    implementation and application

    • To be developed… 

  • 8/15/2019 DUE Mar16 rev2.pptx

    25/33

    SA Grid Code

    • RPP Grid Code

    • Category A – A1: 0 -13.8kVA (4.6kVA/phase)

     –

    A2: 13.8-100kVA – A3: 100kVA –  1MVA (including smaller units

    connected to a dedicated MV/LVtransformer)

    • Category B – 1MVA –  20MVA

    • Category C – Larger than 20MVA

  • 8/15/2019 DUE Mar16 rev2.pptx

    26/33

    SANS: Wiring Code

    • SANS 10142-3 WG convened

    • Progress slow

     – Utility viewpoint

     – Installers viewpoint

  • 8/15/2019 DUE Mar16 rev2.pptx

    27/33

    Licensing

    • Feedback received yesterday

  • 8/15/2019 DUE Mar16 rev2.pptx

    28/33

    Safety Concerns

    • Installation deficiencies – Installation of utility-accessible lock-out breaker (where feasible)

     – Such a breaker is not feasible in shared networks

     – DC fed back into network (possible failure modes of the inverter)

     – DC vs. AC breakers and associated derating

    • Anti-islanding – Failure to disconnect when the network is de-energised

     – Test for voltage before work commences will safeguard LV personnel

    • Re-connection while maintenance in progress – Failure of the inverter to detect that the network is not energised

     – Remains a risk (in shared networks) until LV networks can be earthed

     – Earthing at LV requires redesign of LV networks (e.g. providing earthing terminalsetc.)

    • LV Maintenance Process –

    Need to measure after disconnection – Most voltmeters either DC or AC

    • Australia –  rumours of several PV installations that caused fires atresidential homes

    • Emergency Personnel, e.g. firefighting

    2016-04-02 28

  • 8/15/2019 DUE Mar16 rev2.pptx

    29/33

    How to earth a

    generator

  • 8/15/2019 DUE Mar16 rev2.pptx

    30/33

    Few Other Aspects

    • No approved tariffs

     – Cowboy approach –  under the radar

    • Offset of consumption

     – Gives good return on investment

    • Licensing vs. registration

     – Regulatory framework

    • Power Quality – RPP GC

     – Default values for Generators < 5MVA

  • 8/15/2019 DUE Mar16 rev2.pptx

    31/33

    Subtleties

    • Renewable Power Producers

     – Point of Connection

    • Embedded Generators

     – Generator terminals

     – Point of Connection

    • Safety aspects

  • 8/15/2019 DUE Mar16 rev2.pptx

    32/33

    Conclusions

    • South Africa has learnt a lot

    • Alignment with international best

    practices as far as possible

    • BUT: South African Networks and

    Conditions are completely different to

    typical European or American networks

  • 8/15/2019 DUE Mar16 rev2.pptx

    33/33

    Thank you

    [email protected]

    +27 83 407 9651