Page 1
Spey Catchment Initiative e: [email protected] t:01463 725110 m. 07909 533344
Delagyle Backwater Channel Re-connection
Project Report , June 2018
Summary
An artificially disconnected backwater of the River Spey has been re-connected to the main river by means of
a new culvert to restore increased, continual flow through the channel. The approximately 200m of restored
channel will provide a valuable high water refuge for juvenile fish and additional good quality habitat for
salmonid spawning and endangered fresh water pearl mussel populations.
Background
Restoration of the Delagyle backwater channel was investigated as part of a feasibility study into re-
connection of two backwater channels on the Spey commissioned under the EU LIFE+-funded Pearls in Peril
(PiP) project and undertaken by EnviroCentre Ltd in 2016. Funding granted to the Spey Fishery Board by
Speyburn Distilleries in 2017 for river enhancement along with a top-up contribution from Scottish Natural
Heritage enabled the Spey Catchment Initiative to deliver the project in early 2018.
Page 2
Spey Catchment Initiative e: [email protected] t:01463 725110 m. 07909 533344
Aim and Rationale
The Spey is designated as a Special Area of Conservation (SAC) for freshwater pearl mussel, Atlantic salmon,
otter and sea lamprey. Monitoring of freshwater pearl mussels by Scottish Natural Heritage (SNH) and
salmon by the Spey Fishery Board in recent years suggests that the populations of both have undergone
significant decline.
The project site is an artificially disconnected backwater of the River Spey approximately 3km upstream of
Aberlour at Delagyle (location map appended) and approximately 200m in length. The backwater had been
historically cut-off from the main channel by the installation of upstream bank protection, probably to
improve access for fishing. There was little significant flow in the channel except in spate events when the
banks of the Spey over-topped. At most water levels the channel contained only a small, intermittent flow
with pools of standing water, resulting in the absence of active hydro-morphological processes and good
quality ecological habitat. By re-connecting the backwater to the main river and restoring a continual flow at
a wide range of water levels, the project aimed to restore natural river processes and re-introduce suitable
habitat for fresh water pearl mussels and salmonid fish, especially valuable for spawning and as a high water
refuge for juveniles.
The feasibility study ascertained that during larger flow events the River Spey will overtop the existing banks
and the opening of the backwater channel would have no significant impact on flood levels or extents.
Delagyle Pool is a popular and commercially valuable fishing beat, and the design and implementation of the
re-connection works took into account the need to avoid any interference with access for fishing, protect
and enhance riparian trees and vegetation and maintain the attractive landscape qualities of the area.
Groundworks and re-instatement
Following hydrological and geomorphological survey
and assessment, habitat assessment and an options
appraisal, a 900mm twin pipe culvert was installed
through the retained surrounding bank protection.
This allows flow from the Spey into the backwater
channel at almost all water levels. At high flows the
volume of water entering the backwater is limited
by culvert capacity. As an additional control
measure, provision has been made for removable
sluice boards to be put in place at the culvert inlets
to protect the channel downstream of the culvert
from scouring and ensure the channel functions as a
refuge area for fish.
Some excavation was undertaken to connect the remnant channel with the culvert outlet and to slightly
lower the bed level in the upper reaches of the channel for around 80m downstream to achieve a continual
flow. Some features have been built into the upper end of the channel, such as meanders and larger
boulders, but the majority of the channel downstream has been left unaltered. In time, the channel will
naturally evolve its own course forming pools, riffles, runs and steps, providing a diverse range of hydraulic
and physical habitats.
Construction of culvert
Page 3
Spey Catchment Initiative e: [email protected] t:01463 725110 m. 07909 533344
Turf was re-instated above the culvert site and disturbed ground re-seeded with grass. Around 30 broadleaf
trees of appropriate riparian species were planted close to the banks of the channel where vegetation had
been removed during construction works, to give a boost to natural tree regeneration.
Monitoring
Regular (at least annual) fixed point re-photography will be used to monitor morphological changes in the
channel and surrounding area.
The channel will be electro-fished during the summer of 2018 and annually thereafter to monitor species
and numbers of fish present, and it will also be surveyed for freshwater pearl mussel.
We would like to acknowledge the generous support of Speyburn Distilleries and Scottish Natural Heritage
and the kind permission of Delagyle Fishings, without which this project would not have been possible.
Penny Lawson, June 2018
Completed culverts showing exit and channel
Entrance to culverts from main river, near completion
Page 4
Spey Catchment Initiative e: [email protected] t:01463 725110 m. 07909 533344
Downstream confluence of backwater with main river
before re-connection.
Confluence of re-watered channel with main river one
week after re-connection, showing channel starting to
erode its own course.
Channel post-re-connection, showing in-channel
features.
Backwater channel before re-connection.
Backwater channel before reconnection, middle section
with standing water.
Excavated section of channel downstream of culvert.